JPS5818519B2 - Jiyu Tenzai Sekidomekousou - Google Patents

Jiyu Tenzai Sekidomekousou

Info

Publication number
JPS5818519B2
JPS5818519B2 JP50016042A JP1604275A JPS5818519B2 JP S5818519 B2 JPS5818519 B2 JP S5818519B2 JP 50016042 A JP50016042 A JP 50016042A JP 1604275 A JP1604275 A JP 1604275A JP S5818519 B2 JPS5818519 B2 JP S5818519B2
Authority
JP
Japan
Prior art keywords
segment
lining
filler
segments
weir plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP50016042A
Other languages
Japanese (ja)
Other versions
JPS5190726A (en
Inventor
山本稔
木川富男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KUBOTA TETSUKO KK
Original Assignee
KUBOTA TETSUKO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUBOTA TETSUKO KK filed Critical KUBOTA TETSUKO KK
Priority to JP50016042A priority Critical patent/JPS5818519B2/en
Publication of JPS5190726A publication Critical patent/JPS5190726A/ja
Publication of JPS5818519B2 publication Critical patent/JPS5818519B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明はRTM(Rock Tunne l ing
Machine 、’工法、発破工法、シールド工法等
によって掘削したトンネルを支保するための充填材覆工
を施工する際の充填材堰止構造に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention utilizes RTM (Rock Tunneling).
The present invention relates to a filler dam structure for constructing a filler lining to support a tunnel excavated by a machine, blasting method, shield method, or the like.

従来、トンネルの施工にあたっては支保工として木製支
保工、鋼アーチ支保工またはセグメントなどを用い、地
山を支持していた。
Traditionally, when constructing tunnels, wooden supports, steel arch supports, or segments were used to support the ground.

そして、木製支保工や鋼アーチ支保工にあっては支保工
を仮設とし、その内側からコンクリート覆工を巻立てる
ことにより支保工ごと永久覆工としていた。
In the case of wooden shoring and steel arch shoring, the shoring was made temporary and a concrete lining was rolled up from the inside to make the shoring a permanent lining.

またセグメントにあっては、前記木製支保工や鋼アーチ
支保工と同様に仮設とし、その内側からコンクリート覆
工を巻立てて永久覆工とする考え方と、セグメント覆工
それ自体を永久覆工とする考え方とが併存していた。
Regarding segments, there are two methods: temporary lining, similar to the wooden shoring and steel arch shoring mentioned above, and concrete lining from the inside to create a permanent lining, and segment lining itself as a permanent lining. There was a coexistence with the idea of

ところで、支保工を用いる場合には、支保工は地山に対
して矢板およびクサビを介して接するにすぎないから、
施工に当って注意しないと支保工と地山との接触が十分
に保たれず、支保工に曲げが発生して支保工の耐荷能力
を低下させる惧れがある。
By the way, when using shoring, the shoring only touches the ground through the sheet piles and wedges, so
If care is not taken during construction, there is a risk that sufficient contact between the shoring and the ground will not be maintained, causing bending of the shoring and reducing the load-bearing capacity of the shoring.

すなわち、支保工に軸力状態を生じさせるようにするた
め、地山との接触をできるだけ完全にする必要があり、
支保工使用時には十分な注意を払わねばならないのであ
る。
In other words, in order to create an axial force state in the shoring, it is necessary to make contact with the ground as complete as possible.
Great care must be taken when using shoring.

これに対して、セグメントを用いる場合は、セグメント
覆工と地山の間に裏込め注入を行なうことによってセグ
メントと地山との接触を完全にすることができ、従って
セグメントによればその耐荷能力を十分に発揮できる。
On the other hand, when using segments, the contact between the segments and the ground can be completed by performing backfill injection between the segment lining and the ground, and therefore, according to the segment, its load-bearing capacity is Can fully demonstrate.

しかし、セグメントそれ自体を支保材として、また永久
覆工として使用すると工費が嵩み、力学的に合理性はあ
っても経済的に問題が残ることになる。
However, if the segments themselves are used as shoring materials or permanent linings, the construction cost will increase, and even though it is mechanically reasonable, there will still be economic problems.

本発明者は、かかる問題の解消を図るべく工夫したトン
ネル覆工の構築方法を先に提案したが、本発明はそこで
採用する充填材堰止構造として効果的なものを提案する
ものである。
The present inventor has previously proposed a method for constructing a tunnel lining devised to solve this problem, and the present invention proposes an effective filler dam structure to be employed therein.

すなわち、トンネル施工に当って支保材としてセグメン
トを用い、セグメントをトンネル掘削断面と同心状に組
立て、組立て後セグメントの外径方向に出退可能な支持
具を地山に圧着または貫入させることにより、該支持具
を介してセグメント覆工で地山を一時的に支保すると共
に、地山とセグメントの間にほぼ均等な間隙を確保し、
かつこのセグメント覆工は、堰板を付設したセグメント
を覆工の長手方向適当間隔おきに用いて行う。
That is, when constructing a tunnel, segments are used as supporting materials, the segments are assembled concentrically with the tunnel excavation cross section, and after assembly, a support that can move in and out of the segment in the outer diameter direction is crimped or penetrated into the ground. Temporarily support the ground with the segment lining through the support, and ensure approximately equal gaps between the ground and the segments,
This segment lining is performed using segments provided with weir plates at appropriate intervals in the longitudinal direction of the lining.

次に切羽の地山の条件および切羽の作業状況に応じて適
宜に前記堰板間の前記間隙に充填材を充填し、セグメン
トと地山との密着を図る。
Next, the gap between the weir plates is filled with a filler material as appropriate depending on the conditions of the ground at the face and the work status of the face to ensure close contact between the segments and the ground.

この充填材の充填後は、充填材を通じて地山荷重をセグ
メント覆工の全面で均等に支持できるから、セグメント
はその耐荷能力を十分に発揮できる。
After filling with this filler, the earth load can be evenly supported over the entire surface of the segment lining through the filler, so the segments can fully demonstrate their load-bearing capacity.

そして充填材が硬化性のものであれば、充填材の硬化後
はその強度によって地山を支保することができ、また非
硬化性のものであれば結合剤を注入することによって充
填材を結合し、その強度によって地山を支持することが
できる。
If the filler is hardening, it can support the ground with its strength after hardening, and if it is non-hardening, it can be bonded by injecting a binder. However, it can support the ground due to its strength.

この様にして充填材が硬化結合すれば、セグメントは単
に型枠の役目をもつにすぎないからこれを適宜撤去して
切羽側でのセグメント覆工に再使用することができる。
When the filler is hardened and bonded in this manner, the segments serve only as formwork, and can be appropriately removed and reused for segment lining on the face side.

そして以下同様に堰板間の区間毎に順次充填材を充填し
て行き、硬化結合した充填材からなを支楳工を構築でき
る。
Then, in the same manner, the filler is sequentially filled in each section between the weir plates, and a shoring structure can be constructed from the hardened and bonded filler.

一方、硬化結合した充填材はそれ自体覆工の役目を果す
ことかでさるが、セグメントの撤去と並行してその内側
にコンクリート覆工を巻立てれは、覆工の機能をさらに
強化できる。
On the other hand, although the hardened and bonded filler itself serves as a lining, if a concrete lining is placed inside the segment at the same time as the segment is removed, the lining's function can be further strengthened.

またこの場合硬化結合した充填材の内面は平滑であるた
め防水処理を完全に行なえ、巻立てるコンクリート覆工
に防水工を兼ねさせる目的にもよく合致する効果がある
Further, in this case, since the inner surface of the hardened and bonded filler is smooth, it can be completely waterproofed, and this effect is well suited to the purpose of making the concrete lining to be rolled also serve as a waterproofing material.

そして、本発明では、前記充填材の堰失め部分において
、セグメント−側面の外方に堰板を着脱自在に取付け、
該堰板の内周端面とセグメント7内側との間には適当な
間隙を有せしめ、かつセグメントの堰板取付側一側面と
これに隣接するセグメント側面との間に、前記堰板の内
周端面に接当するコーキング溝形成用突部を有するスペ
ーサを介装することにより、セグメントを撤去した時堰
板で区画された充填材覆工の継目部分にコーキング溝が
形成される。
In the present invention, a weir plate is removably attached to the outside of the segment-side surface at the weir loss portion of the filler,
An appropriate gap is provided between the inner circumferential end surface of the weir plate and the inside of the segment 7, and an appropriate gap is provided between the inner peripheral end surface of the weir plate and the inside of the segment 7, and the inner circumference of the weir plate is provided between one side of the weir plate attachment side of the segment and the adjacent segment side. By interposing a spacer having a protrusion for forming a caulking groove in contact with the end face, a caulking groove is formed at the joint portion of the filler lining divided by the weir plate when the segment is removed.

従って、この溝内にコーキング材を充填すれば、一区画
毎に充填材を充填する方法を採用しながら、その継目部
分からの漏水を無くすることができる。
Therefore, by filling this groove with caulking material, it is possible to eliminate water leakage from the joint portion while employing a method of filling the filler into each section.

次に、本発明の一実施態様としてRTM工法に適用した
場合を図面に基づいて説明する。
Next, a case where the present invention is applied to the RTM construction method as an embodiment of the present invention will be explained based on the drawings.

第1図において、地山1にRTM2によりトンネル坑3
を掘進しながらこのRTM2後部で順次セグメント4を
組立ててセグメント覆工5を行う。
In Figure 1, a tunnel shaft 3 is installed in the ground 1 by RTM2.
While excavating, segments 4 are sequentially assembled at the rear of this RTM 2, and segment lining 5 is performed.

このときセグメント覆工5は、第2図aに示す様にトン
ネル坑2に対みて偏心し易く、地山1とセグメント覆工
5との間隙δが下部で小さく上部で大きくなるため、後
の支保工としての充填材硬化層の厚さが不均一になって
強度的に弱くなるため、第2図すに示す様にトンネル坑
3′とセグメント覆工5の中心を一致させる必要がある
At this time, the segment lining 5 tends to be eccentric with respect to the tunnel shaft 2, as shown in Fig. 2a, and the gap δ between the ground 1 and the segment lining 5 is small at the bottom and becomes large at the top. Since the thickness of the hardened filler layer serving as the support becomes uneven and the strength becomes weak, it is necessary to align the centers of the tunnel shaft 3' and the segment lining 5 as shown in FIG.

そこで第3図に示す様に、セグメント4の外側に数本の
牟持具6を突出させ該支持具6のフ狛ツキングにより地
山1を支持してセグメント覆工5をトンネル坑3と同心
状に保持させる。
Therefore, as shown in FIG. 3, several holders 6 are protruded from the outside of the segments 4, and the ground 1 is supported by the locking of the holders 6, so that the segment lining 5 is concentric with the tunnel shaft 3. keep it in shape.

こうしてセグメント覆工5の長さが、1回の充填材打設
に適当な長さ、例えは20m程度の長さになれば、堰板
8を付設したセグメント7を組立てて堰止め用セグメン
ト覆工9を行なう。
In this way, when the length of the segment lining 5 becomes suitable for one time of pouring the filling material, for example, about 20 m, the segments 7 with the dam plate 8 attached are assembled and the segment lining for dam stop is assembled. Perform step 9.

この堰板8は間隙δ内に充填した充填材がトンネル坑3
の前方に流出するのを防ぐためのものであり、これによ
ってRTM2後部でのセグメント覆工5構築と切離して
所要の時期に一区画毎に充填材の充填を行なえる。
This weir plate 8 has a filling material filled in the gap δ in the tunnel shaft 3.
This is to prevent the filling material from flowing out to the front of the RTM 2. This allows the segment lining 5 to be separated from the construction of the segment lining 5 at the rear of the RTM 2, and the filling material can be filled section by section at the required time.

そして堰止め用セグメント覆工9が終れば引続き前記と
同様にセグメント覆工5を構築する。
After the dam-stopping segment lining 9 is completed, the segment lining 5 is constructed in the same manner as described above.

かくしてRTM2が前進し、その切羽作業との競合がな
くなれは、できるだけ早急に堰板8,8間の間隙δに硬
化性充填材であるコンクリートを流し込むか、又は非硬
化性充填材である砂利、砕石又はズリを注入した後結合
剤としてセメントミルクなどを注入して裏込めを行なう
In this way, when the RTM 2 moves forward and there is no competition with its face work, it is necessary to pour concrete as a hardening filler into the gap δ between the weir plates 8 and 8 as soon as possible, or pour gravel as a non-hardenable filler. After injecting crushed stone or debris, backfilling is performed by injecting cement milk as a binder.

この裏込めした充填材が硬化して充填材覆工10となり
、支保工としての所定の強度が得られると、第4図に示
す様に支持具6を埋込みにしたま5セグメント4を取外
し、この充填材覆工10で地山1の荷重を支保する。
When this backfilled filler hardens and becomes the filler lining 10, and a predetermined strength for shoring is obtained, the five segments 4 are removed while the supports 6 are embedded, as shown in FIG. This filler lining 10 supports the load of the earth 1.

他方、取外されたセグメント4及び8は第1図に示す様
にRTM2後部でのセグメント覆工5,9の組立てに順
次循環使用される。
On the other hand, the removed segments 4 and 8 are sequentially used in circulation to assemble segment linings 5 and 9 at the rear of the RTM 2, as shown in FIG.

次に本発明の要部である前記堰止め用セグメント覆工9
部分について第5図乃至第7図により詳細に説明する。
Next, the segment lining for damming 9 which is the main part of the present invention
The parts will be explained in detail with reference to FIGS. 5 to 7.

第5図において前記堰板8は、セグメントTの堰止め側
−側面7a外方に位置する様に、L字状支持部材゛11
の立上り腕11aに固着されており、この支持部材の横
腕11bが、プラスチック等からなるコーン状カラー1
2を介在させた状態で、セグメント7内側から貫通させ
たボルト13によりセグメント側面面に着脱自在に取付
けられている。
In FIG. 5, the dam plate 8 is provided with an L-shaped support member 11 so as to be located outside the dam-blocking side-side surface 7a of the segment T.
The side arm 11b of this support member is fixed to the upright arm 11a of the
2 is interposed therebetween, and is detachably attached to the side surface of the segment by a bolt 13 passed through from the inside of the segment 7.

そして堰板8の内周端面8aとセグメント側面周面との
間に適当な間隙を有せ、しめ、かつ堰板内周端面8aと
外周端面8bにはシール用ゴムライング14を貼着して
シールを施せる様にしである。
Then, a suitable gap is provided between the inner circumferential end surface 8a of the weir plate 8 and the segment side surface circumferential surface, and a sealing rubber lining 14 is pasted on the weir plate inner circumferential end surface 8a and outer circumferential end surface 8b for sealing. It is designed so that it can be applied.

また、セグメント7の堰板取付側一側面7aとこれに隣
接するセグメント4の側面4aとの間には、前記堰板内
周端面に接当する台形状のコーキング溝形成用突部16
を有するスペーサ15を介装せしめてあり、このスペー
サ15を介在せしめた状態でセグメント4と7とがボル
トで締結しである。
Further, between one side surface 7a of the segment 7 on the weir plate mounting side and the side surface 4a of the adjacent segment 4, there is a trapezoidal caulking groove forming protrusion 16 that comes into contact with the inner circumferential end surface of the weir plate.
A spacer 15 is interposed therebetween, and the segments 4 and 7 are fastened together with bolts with this spacer 15 interposed.

なお、第5図すに示す様に堰板8の周方向の継目部分に
ゴムパツキン17を介装して充填材の漏れを完全に無く
するのが望ましい。
In addition, as shown in FIG. 5, it is desirable to insert a rubber gasket 17 at the circumferential joint portion of the weir plate 8 to completely eliminate leakage of the filler material.

第5図に示す状態は、一区画の充填材覆工10が終了し
たところであり、その前方ではセグメント覆工5及び堰
止め用セグメント覆エフが構築されている。
In the state shown in FIG. 5, one section of the filler lining 10 has been completed, and in front of it, the segment lining 5 and the segment lining F for damming have been constructed.

そしてこの充填材覆工10が硬化結合すると、第6図に
示す様にその区画部分のセグメント4が取除かれ、堰止
め用セグメント7はボルト13を外すことにより堰板8
、支持部材11及びコーン状カラー12を充填材覆工1
0に埋め殺したま\そのセグメントのみが取除かれる4
この時、コーン状カラー12が介在されているため、L
字状支持部材11の横腕11bが充填材覆工10の内周
面に露出せず、またこのカラー12の介在により支持部
材11の立上り腕11a下端を堰板8の内周端面8aと
同−又はそれ以上のレベルにすることができ、従ってコ
ーキング溝形成用突部16側面に立上り腕11a下端が
位置する様なこともなくなって充填材がこの部分にも完
全に充填され、欠損のないコーキング溝が得られる。
When the filler lining 10 is hardened and bonded, the segment 4 of the partitioned portion is removed as shown in FIG.
, the support member 11 and the cone-shaped collar 12 are lined with a filler material 1
0\only that segment will be removed 4
At this time, since the cone-shaped collar 12 is interposed, L
The horizontal arm 11b of the character-shaped support member 11 is not exposed to the inner circumferential surface of the filler lining 10, and the lower end of the rising arm 11a of the support member 11 is aligned with the inner circumferential end surface 8a of the weir plate 8 due to the interposition of this collar 12. - or higher level, therefore, the lower end of the rising arm 11a is no longer located on the side surface of the caulking groove forming protrusion 16, and the filler is completely filled in this area, and there is no damage. A caulking groove is obtained.

次に、セグメント4の後端面4aに、スペーサ15を介
在させた状態でブラケット18をボルト止めし、このブ
ラケット18を前記充填材覆工10に埋込まれた状態の
支持部材11にボルト19で固定することにより次の区
画のセグメント覆工5を充填材覆工10で補強し、かく
してこの堰板8とその前方の堰板8間の間隙に充填材を
充填する。
Next, a bracket 18 is bolted to the rear end surface 4a of the segment 4 with a spacer 15 interposed therebetween, and this bracket 18 is bolted to the support member 11 embedded in the filler lining 10 using bolts 19. By fixing, the segment lining 5 of the next section is reinforced with the filler lining 10, thus filling the gap between this weir plate 8 and the weir plate 8 in front of it with the filler.

そしてその充填材が硬化結合後、第7図に示す様にこの
区画のセグメント4及びスペーサ15を取除けば、充填
材覆工10,10の継目部分にコーキング溝20が形成
される。
After the filler is hardened and bonded, the segment 4 and spacer 15 in this section are removed as shown in FIG. 7, and a caulking groove 20 is formed at the joint between the filler linings 10, 10.

このコーキング溝20内にコーキング材を充填すれば、
−区画毎に充填材覆工10を構築しながらその継目部分
を完全にシールすることができ、継目部分からの浅水を
無くすることができる。
If this caulking groove 20 is filled with caulking material,
- While constructing the filler lining 10 for each section, the joints can be completely sealed, and shallow water from the joints can be eliminated.

尚、この様にして構築された充填材覆工101ま、地山
1の荷重が小さい場合にはそのま5永久覆工することも
できるが、その内側から永久覆工としてのコンクリート
巻立てを行なうこともあり、その場合には例えばトンネ
ル全長にわたって充填材覆工10を形成した後行なって
も良く、セグメント4を撤去しながら逐次に行なっても
良い。
In addition, if the load of the filler lining 101 constructed in this way or the ground 1 is small, it is possible to use a permanent lining as it is, but it is also possible to line it with concrete as a permanent lining from the inside. In that case, for example, it may be carried out after forming the filler lining 10 over the entire length of the tunnel, or it may be carried out sequentially while removing the segments 4.

次に、前記セグメント4及び支持具6の具体構成例を説
明し″ておくと、セグメント4は第8図に示す様に、セ
グメント同士を締結組立するための締結孔21の他に、
前記支持具6を挿通させて取付けるため、セグメン、ト
4の外面に凹設した適数の凹陥部22とその中央位置に
穿設した挿通孔23とを有しており、かつ適宜裏込注入
孔24が穿設されてい乞。
Next, a specific example of the structure of the segments 4 and the support 6 will be explained. As shown in FIG. 8, the segments 4 have fastening holes 21 for fastening and assembling the segments,
In order to insert and attach the support 6, the segment 4 has an appropriate number of recesses 22 recessed on the outer surface thereof, and an insertion hole 23 formed at the center thereof, and backfilling is performed as appropriate. Hole 24 must be drilled.

また、前記支持具6は、第3図に示す様に、前記凹陥部
22に嵌入するナツト部材25と、該ナツト部材25に
螺合された押付ねじ軸26と、この押付ねじ軸26の先
端に装着した接当部材27とから成る。
Further, as shown in FIG. 3, the support 6 includes a nut member 25 that fits into the recessed portion 22, a pressing screw shaft 26 screwed into the nut member 25, and a tip of the pressing screw shaft 26. The contact member 27 is attached to the contact member 27.

そしてセグメント4の外面側から支持具6を挿通し、前
記ナツト部材25を凹陥部22に嵌入させた状態で、こ
のナツト部材25とセグメン1〜4とをセグメント4の
内側からボルト28等で締結する。
Then, the support 6 is inserted from the outside of the segment 4, and with the nut member 25 fitted into the recess 22, the nut member 25 and the segments 1 to 4 are fastened from the inside of the segment 4 with bolts 28 or the like. do.

このセグメント4を組立ててセグメント覆工5を行なっ
た後、前記押付ねじ軸26を回転することによりその先
端の接当部材27を外径方向に突出させて地山表面に押
圧又は貫入させ、前記の様にセグメント覆工5をトンネ
ル坑3と同心状に保持するのである。
After the segments 4 are assembled and the segment lining 5 is performed, the pressing screw shaft 26 is rotated so that the abutment member 27 at the tip thereof protrudes in the outer radial direction to press or penetrate into the ground surface. The segment lining 5 is held concentrically with the tunnel shaft 3 as shown in FIG.

また、充填材硬化後は、前記ボルト28を外すことによ
り支持具6を埋込んだまXセグメント4を取除くことが
できる。
Further, after the filler hardens, the X segment 4 can be removed with the support 6 still embedded by removing the bolt 28.

尚、以上の実施例ではRTM工法についてのみ説明した
が、トンネル坑3の掘進を発破工法で行なっても本発明
を適用し得、シールド工法に適用し得ることも明らかで
ある。
Although only the RTM construction method has been described in the above embodiments, it is clear that the present invention can be applied even if the tunnel shaft 3 is excavated by the blasting method, and can also be applied to the shield construction method.

本発明は、以上の実施例に示した様に実施し得るもので
あって、堰板によって充堰材がトンネル坑の前方に流出
するのを防止できるため、1回の充填材打設に適当な長
さの区画毎に充填材を間隙に充填することができると共
に、切羽後部でのセグメント覆工構築と切離して所要の
時期に任意に充填材覆工を構築できるため、必要時に効
率の良い覆工が可能でありミ特に本発明堰止構造を用い
れば、上記の様に−(イ)画毎に充填材覆工を行ないな
がら、充填材覆工の継目部分にコーキング溝が形成され
るため、ごの構内にコーキング材を充填することにより
その継目部分からの漏水を無くすることができる。
The present invention can be carried out as shown in the above embodiments, and since the weir plate can prevent the filling material from flowing out to the front of the tunnel shaft, it is suitable for one-time filling material casting. It is possible to fill the gap with filler material for each section of length, and it is also possible to separate the segment lining construction at the rear of the face and construct the filler lining at the required time, making it efficient when necessary. Particularly, if the dam structure of the present invention is used, caulking grooves can be formed at the joints of the filler lining while lining with the filler for each stroke as described above. Therefore, by filling the inside of the roof with caulking material, water leakage from the joints can be eliminated.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の一実施態様を示し、第1図はRTM工法
に適用した場合の縦断側面図、第2図a、bはセグメン
ト覆工とトンネル坑との関係を示す横断面図、第3図は
セグメント覆工時の部分拡大横断面図、第4図は充填材
覆工後の部分拡大横断面図、第5図31第6図a及び第
7図は堰止部分における施工順序を示す縦断側面図、第
5図すは第5図aのA−A矢視図、第6図すは第6図a
のB−B矢視図、第8図a、bはセグメントの表裏の斜
視図である。 1・・・・・・地山、2・・・・・・RTM、 3・
・・・・・トンネル坑、4・・・・・・セグメント、5
・・・・・・セグメント覆工、6・・・・・・支持具、
I・・・・・・堰止め用セグメント、8・・・・・・堰
板、8a・・・・・・堰板内周端面、9・・・・・・堰
止め用セグメント覆工、10・・・・・・充填材覆工、
11・・・・・・L字状支持部材、11a・・・・・・
立上り腕、Ilb・・・・・・横腕、12・・・・・・
コーン状カラー、15・・・・・・スペーサ、16・・
・・・・コーキング溝形成用突部、20・・・・・・コ
ーキング溝、δ・・・・・・間隙。
The drawings show one embodiment of the present invention, and FIG. 1 is a longitudinal cross-sectional side view when applied to the RTM construction method, FIGS. 2 a and b are cross-sectional views showing the relationship between the segment lining and the tunnel shaft, and FIG. The figure shows a partially enlarged cross-sectional view during segment lining, Fig. 4 shows a partially enlarged cross-sectional view after filling material lining, Fig. 5, 31, Fig. 6 a and Fig. 7 show the construction order in the dam section. Longitudinal side view, Figure 5 is a view from the A-A arrow in Figure 5a, Figure 6 is Figure 6a
FIGS. 8a and 8b are perspective views of the front and back sides of the segment. 1... Earth, 2... RTM, 3.
...Tunnel pit, 4...Segment, 5
...Segment lining, 6...Support,
I... Segment for weir stop, 8... Weir plate, 8a... Inner peripheral end surface of weir plate, 9... Segment lining for weir stop, 10 ...filler lining,
11... L-shaped support member, 11a...
Standing arm, Ilb... Lateral arm, 12...
Cone-shaped collar, 15...Spacer, 16...
... Protrusion for forming caulking groove, 20 ... Caulking groove, δ ... Gap.

Claims (1)

【特許請求の範囲】[Claims] 1 セグメント−側面の外方に堰板を着脱自在に取付け
、該堰板の内周端面と前記セグメント外周面との間には
適当な間隙を有せしめ、前記セグメントの堰板取付側一
側面とこれに隣接するセグメント側面との間に、前記堰
板の内周端面に接当するコーキング溝形成用突部を有す
るスペーサを介装した事を特徴とする充填材堰止構造。
1. A weir plate is removably attached to the outside of the segment-side surface, with an appropriate gap between the inner circumferential end surface of the weir plate and the outer circumferential surface of the segment, and one side of the segment on the weir plate installation side and A filler damming structure characterized in that a spacer having a protrusion for forming a caulking groove that comes into contact with the inner peripheral end surface of the dam plate is interposed between the adjacent segment side surface.
JP50016042A 1975-02-06 1975-02-06 Jiyu Tenzai Sekidomekousou Expired JPS5818519B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP50016042A JPS5818519B2 (en) 1975-02-06 1975-02-06 Jiyu Tenzai Sekidomekousou

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP50016042A JPS5818519B2 (en) 1975-02-06 1975-02-06 Jiyu Tenzai Sekidomekousou

Publications (2)

Publication Number Publication Date
JPS5190726A JPS5190726A (en) 1976-08-09
JPS5818519B2 true JPS5818519B2 (en) 1983-04-13

Family

ID=11905505

Family Applications (1)

Application Number Title Priority Date Filing Date
JP50016042A Expired JPS5818519B2 (en) 1975-02-06 1975-02-06 Jiyu Tenzai Sekidomekousou

Country Status (1)

Country Link
JP (1) JPS5818519B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0694795B2 (en) * 1988-04-15 1994-11-24 三井建設株式会社 Wife stopper for building tunnel lining
JP6245604B2 (en) * 2013-12-04 2017-12-13 株式会社ケー・エフ・シー Drainage sheet and tunnel drainage structure

Also Published As

Publication number Publication date
JPS5190726A (en) 1976-08-09

Similar Documents

Publication Publication Date Title
JP6636773B2 (en) Construction structure and construction method of tunnel lining body
JP3367013B2 (en) Existing tunnel lining structure
JP3321697B2 (en) Tunnel lining method using composite panels
JP2874561B2 (en) Fore piling method with stiffening of the leading leg using a shaft
JP4730610B2 (en) Tunnel excavation method and tunnel liner
JP3890528B2 (en) Tunnel construction method
JPS5818519B2 (en) Jiyu Tenzai Sekidomekousou
JPH07197792A (en) Tunnel lining structure, lining device and construction method
KR20030065963A (en) A method of constrution method for tunnel of structure pipe
KR20010026028A (en) Shaft construction system using precasted segment block
JPH07103785B2 (en) Segment that does not require joint bolts
JPH0788759B2 (en) Tunnel lining method
JPH0637836B2 (en) Tunnel lining method
CN109098718A (en) Assembled roadway construction method
JPS62121299A (en) Method for covering casting of tunnel and shield excavator used therein
JPH1018786A (en) Method of lining tunnel
JPH0197724A (en) Repairing of lining of horseshoe-shaped existing tunnel
JPH06180097A (en) Repairing method of horseshoe type tunnel lining
JP2001090487A (en) Tunnel lining work
JPH0772476B2 (en) How to build a tunnel lining
JPS6332095A (en) Segment coating construction method and concrete segment also used as mold frame
JPH0610597A (en) Tunnel lining method and tunnel lining body
GB2186010A (en) Improvements in or relating to methods of erecting tunnel linings
JPS5912839B2 (en) Tunnel filler lining construction method
JPS62220697A (en) Method and structure for connecting inner mold frame and outer mold frame in non-segment shield construction method