JP2001090487A - Tunnel lining work - Google Patents

Tunnel lining work

Info

Publication number
JP2001090487A
JP2001090487A JP26482699A JP26482699A JP2001090487A JP 2001090487 A JP2001090487 A JP 2001090487A JP 26482699 A JP26482699 A JP 26482699A JP 26482699 A JP26482699 A JP 26482699A JP 2001090487 A JP2001090487 A JP 2001090487A
Authority
JP
Japan
Prior art keywords
formwork
panel
concrete
lining
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26482699A
Other languages
Japanese (ja)
Other versions
JP3633397B2 (en
Inventor
Tomoya Yasuo
知也 安尾
Masataka Tayu
正孝 田湯
Akira Niimura
亮 新村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP26482699A priority Critical patent/JP3633397B2/en
Publication of JP2001090487A publication Critical patent/JP2001090487A/en
Application granted granted Critical
Publication of JP3633397B2 publication Critical patent/JP3633397B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a lining work capable of shortening the term of work. SOLUTION: In a lining work method, formworks 12 are installed along the inner periphery of an excavation surface 10 at predetermined intervals, and a lining concrete layer 14 is formed by placing concrete between the excavation surface 10 and the formwork 12. The formwork 12 has a precast concrete flat panel 16 which is used also as a formwork panel and a coupling reinforcing member 18 accompanied along the inner surface of this flat panel 16. When installing the formwork 12 along the inner periphery of the excavated surface 10, the lower end side of a pair of formworks 121 located at both the ends in the peripheral direction is placed on the side wall concrete portion 22 and another formwork 122 is placed and connected adjacently at its upper side. When installing the formwork 122, its lower end side is coupled to the upper end side of the formwork 121 being adjacent in the peripheral direction, and the upper end portion is supported by an anchor 24. The one end side of the anchor 24 is anchored to the natural ground 26.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、トンネル覆工工
法に関し、特に、型枠兼用のパネルを用いるトンネル覆
工工法に関するものである。
The present invention relates to a tunnel lining method, and more particularly to a tunnel lining method using a panel that also serves as a formwork.

【0002】[0002]

【従来の技術】山岳トンネルを構築する際には、掘削さ
れた断面に覆工コンクリート層を形成することが行われ
ていて、このような覆工コンクリート層は、一般的に、
吹付けにより一次覆工を行った後に、二次覆工が行われ
る。
2. Description of the Related Art When constructing a mountain tunnel, a lining concrete layer is formed on an excavated cross section.
After performing the primary lining by spraying, the secondary lining is performed.

【0003】二次覆工では、掘削面の内面側に、型枠板
を設置して、掘削面と型枠板との間にコンクリートを打
設する型枠を用いる工法が知られている。
[0003] In the secondary lining, a method is known in which a form plate is installed on the inner side of an excavation surface, and concrete is poured between the excavation surface and the form plate.

【0004】型枠を用いる二次覆工工法では、セントル
と呼ばれる幅が約10m程度の移動式の型枠を用いる方
式が知られている。この種の覆工工法に用いられるセン
トルは、トンネル全断面の大きさをカバーできる型枠板
を、移動式の支持架台に組付け支持させた構造になって
いて、これを坑外で組み立てた状態で、坑内に引き込
み、掘削面と型枠板との間にコンクリートを打設して、
覆工コンクリート層を形成した後に、順次トンネル軸方
向に沿って移動させて施工を行う。
As a secondary lining method using a mold, a method using a movable mold having a width of about 10 m, called a centur, is known. The centre used in this type of lining method has a structure in which a form plate that can cover the entire cross-sectional size of the tunnel is assembled and supported on a movable support base, and this is assembled outside the mine In the state, pulled into the mine, cast concrete between the excavated surface and the formwork,
After forming the lining concrete layer, construction is performed by sequentially moving it along the tunnel axis direction.

【0005】しかしながら、このようなセントル方式の
覆工工法には、以下に説明する技術的な課題があった。
[0005] However, such a centre lining method has the following technical problems.

【0006】[0006]

【発明が解決しようとする課題】すなわち、トンネルを
構築する際には、内部の一部分を拡幅する場合がある
が、このような場合に前記セントル方式の覆工工法を採
用すると、拡幅部の断面が、他の部分の断面に比べて大
きいので、予め坑外でセントルを組立てると、坑内に引
き込むことができないので、拡幅部の施工現場でセント
ルを組むことになる。
That is, when constructing a tunnel, a part of the inside may be widened. In such a case, if the lining method of the centre method is adopted, the cross section of the widened portion is increased. However, since the cross section of the other portion is larger than the cross section of the other portion, if the centre is assembled in advance outside the mine, it cannot be drawn into the mine, so that the centre is assembled at the construction site of the widening portion.

【0007】ところが、坑内でセントルを組む作業は、
クレーンの吊り代ろを確保することができないので、人
力に頼らざるを得ず、この作業が煩雑で危険を伴なうこ
ともあって、工期が長期化する大きな要因となってい
た。
[0007] However, the work of assembling the center in the mine is
Since it was not possible to secure a margin for hanging the crane, it had to rely on human power, and this work was complicated and sometimes dangerous, which was a major factor in prolonging the construction period.

【0008】本発明は、このような従来の問題点に鑑み
てなされたものであって、坑内でセントルを組んで施工
する場合よりも、大幅に工期を短縮することができるト
ンネル覆工工法を提供することにある。
The present invention has been made in view of such a conventional problem, and a tunnel lining method capable of greatly shortening a construction period as compared with a case of constructing a pit in a mine. To provide.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するため
に、本発明は、掘削面の内周に沿って所定の間隔を隔て
て型枠を設置し、前記掘削面と型枠との間にコンクリー
トを打設して覆工コンクリート層を形成するトンネル覆
工工法において、前記型枠は、前記覆工コンクリート層
の表面に残置される型枠板兼用のパネルと、このパネル
の内面または外面に添設された連結用補強材とを備え、
前記型枠を前記掘削面に沿って設置する際に、その連結
用補強材の下端側を、周方向に隣接設置する他の型枠の
連結用補強材と相互に結合させるとともに、各型枠の上
端側を、地山または地山に設置された支保工に一端側を
連結したアンカーにより支持するようにした。このよう
に構成したトンネル覆工工法によれば、掘削面の内周に
沿って所定の間隔を隔てて設置される型枠は、覆工コン
クリート層の表面に残置される型枠板兼用のパネルと、
このパネルの内面または外面に添設された連結用補強材
とを備え、型枠を掘削面に沿って設置する際に、その連
結用補強材の下端側を、周方向に隣接設置する他の型枠
の連結用補強材と相互に結合させるとともに、各型枠の
上端側を、地山または地山に設置された支保工に一端側
を連結したアンカーにより支持するので、型枠を支持す
る坑内支保工が不要になり、他の作業との干渉を避ける
ことができる。また、パネルには、坑外で連結用補強材
を取付けることができるとともに、連結用補強材を添設
することにより大型化が可能になり、大型のパネルを使
用することで、型枠の設置作業を迅速に行える。さら
に、本発明では、前記パネルは、予め製作されるプレキ
ャストコンクリート版で構成することができる。この構
成によれば、プレキャストコンクリート版製のパネル
は、型枠板を兼用し、覆工コンクリート層の表面に残置
されるので、コンクリート打設後の養生を必要とせず、
これにより工期を短縮できる。また、覆工コンクリート
層の表面は、高品質に工場生産することができるプレキ
ャストコンクリート版製のパネルで覆われるため、美観
に優れ、耐久性も優れたものとなる。また、本発明で
は、前記パネルは、平板状に形成することができる。こ
の構成によれば、パネルを容易に製作することができ
る。
In order to achieve the above object, according to the present invention, a formwork is provided at predetermined intervals along an inner periphery of an excavation surface, and a space between the excavation surface and the formwork is provided. In a tunnel lining method of forming a lining concrete layer by casting concrete on the surface, the formwork includes a panel also serving as a formwork plate left on the surface of the lining concrete layer, and an inner surface or an outer surface of the panel. With a connecting reinforcing material attached to the
When the formwork is installed along the excavation surface, the lower end side of the connection reinforcing material is mutually connected to the connection reinforcing material of another formwork installed adjacently in the circumferential direction, and Is supported by an anchor having one end connected to a ground or a shoring installed at the ground. According to the tunnel lining method configured as described above, the formwork that is installed at a predetermined interval along the inner periphery of the excavation surface is a panel that also serves as a formwork plate that is left on the surface of the lining concrete layer. When,
A connection reinforcing member attached to the inner surface or the outer surface of the panel, and when the formwork is installed along the excavation surface, the lower end side of the connecting reinforcing material is installed adjacently in the circumferential direction. Since it is mutually connected with the reinforcing material for connection of the formwork, and the upper end side of each formwork is supported by an anchor having one end connected to the ground or a shoring installed on the ground, the formwork is supported. No underground support is required, and interference with other operations can be avoided. In addition, the panel can be fitted with connecting reinforcements outside the mine, and by adding the connecting reinforcements, it is possible to increase the size. By using large panels, the formwork can be installed. Work can be done quickly. Further, in the present invention, the panel may be constituted by a precast concrete slab. According to this configuration, since the panel made of the precast concrete plate also serves as the formwork plate and is left on the surface of the lining concrete layer, it does not require curing after casting the concrete,
This can shorten the construction period. Further, since the surface of the lining concrete layer is covered with a panel made of a precast concrete plate that can be factory-produced with high quality, the appearance is excellent and the durability is excellent. In the present invention, the panel may be formed in a flat plate shape. According to this configuration, the panel can be easily manufactured.

【0010】[0010]

【発明の実施の形態】以下、本発明の好適な実施の形態
について、添付図面に基づいて詳細に説明する。図1か
ら図3は、本発明にかかるトンネル覆工工法の第1実施
例を示している。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. 1 to 3 show a first embodiment of a tunnel lining method according to the present invention.

【0011】同図に示したトンネル覆工工法では、図1
に施工状態の全体正面図を示すように、掘削面10の内
周面に沿って所定の間隔を隔てて型枠12を設置し、掘
削面10と型枠12との間にコンクリートを打設して覆
工コンクリート層14を形成することを基本構成として
いる。
In the tunnel lining method shown in FIG.
As shown in the overall front view of the construction state, the formwork 12 is installed at predetermined intervals along the inner peripheral surface of the excavation surface 10, and concrete is poured between the excavation surface 10 and the formwork 12. The lining concrete layer 14 is formed as a basic configuration.

【0012】掘削面10の内周側には、その湾曲に沿う
ようにしてアーチ状の鋼製支保工11が設けられ、この
支保工11を埋設するようにして、一次覆工コンクリー
ト層13が吹付け形成されている。
An arch-shaped steel support 11 is provided on the inner peripheral side of the excavation surface 10 so as to follow the curvature thereof, and a primary lining concrete layer 13 is provided so as to bury the support 11. Spraying is formed.

【0013】本実施例のトンネル覆工工法では、型枠1
2は、同一構造の複数枚から構成され、各型枠12は、
覆工コンクリート層14の表面側に残置される型枠板兼
用のプレキャストコンクリート版製の平板パネル16
と、この平板パネル16の内面(覆工コンクリートを打
設する側)に添設された連結用補強材18とを備えてい
る。
In the tunnel lining method of this embodiment, the form 1
2 is composed of a plurality of sheets having the same structure,
A flat panel 16 made of a precast concrete slab which also serves as a form plate, which is left on the surface side of the lining concrete layer 14
And a connection reinforcing member 18 attached to the inner surface of the flat panel 16 (the side where the lining concrete is cast).

【0014】プレキャストコンクリート版製の平板パネ
ル16は、予め、坑外の製造プラントで工場生産される
ものであって、製作された平板パネル16には、連結用
補強材18が坑外で添設固定される。
The flat panel 16 made of a precast concrete slab is manufactured in advance in a production plant outside the mine, and a reinforcing member 18 for connection is attached to the manufactured flat panel 16 outside the mine. Fixed.

【0015】連結用補強材18は、H型鋼からなる縦お
よび横補強材18a,18bを有していて、この縦およ
び横補強材18a,18bが平板パネル16の裏面側に
所定の間隔を隔てて格子状に配置されている。
The connecting reinforcing member 18 has vertical and horizontal reinforcing members 18a and 18b made of H-shaped steel. The vertical and horizontal reinforcing members 18a and 18b are spaced apart from the flat panel 16 by a predetermined distance. Are arranged in a lattice.

【0016】平板パネル16の裏面側に連結用補強材1
8を添設固定すると、平板パネル16の面積を大きくす
ることが可能になり、大面積の大型化された平板パネル
16を使用すると、掘削面10を覆うパネル16の数が
低減され、その分だけ設置および組立て作業が容易かつ
迅速に行える。
On the back side of the flat panel 16, a reinforcing member 1 for connection is provided.
8, the area of the flat panel 16 can be increased. When the large flat panel 16 having a large area is used, the number of the panels 16 that cover the excavation surface 10 is reduced. Only installation and assembly work can be performed easily and quickly.

【0017】掘削面10の内周に沿って型枠12を設置
する際には、図1に示すように、周方向の両端に位置す
る一対の型枠121の下端側が、まず、トンネルのイン
バート部20上に、予め立ち上げ形成される側壁コンク
リート部22に載置される。
[0017] When installing the formwork 12 along the inner periphery of the excavating surface 10, as shown in FIG. 1, a pair of the form 12 1 of the lower end side which is positioned in the circumferential direction of the both ends, first, the tunnel On the invert section 20, it is mounted on a side wall concrete section 22 which is formed upright in advance.

【0018】この端部側の型枠121の設置が終了する
と、その上部側に別の型枠122が隣接するようにして
連結設置される。型枠122を設置する際には、その下
端側を周方向に隣接する型枠121の上端側と結合させ
るとともに、上端側をアンカー24により支持する。
[0018] When this form 12 1 of the installation of the end portion is completed, the upper portion another formwork side 12 2 is connected to and installed so as to be adjacent. When installing the formwork 12 2, together with is combined with the mold frame 12 1 of the upper side adjacent the lower end side in the circumferential direction, for supporting the upper side by the anchor 24.

【0019】アンカー24は、型枠12を設置する前に
既に設置されていて、一端側が地山26中に定着されて
いる。型枠122の設置終了すると、その上部側に同じ
方法により順次他の型枠123以降が、トンネルの中心
側を向かうようにして連結設置される。
The anchor 24 is already installed before the formwork 12 is installed, and one end of the anchor 24 is fixed in the ground 26. When the form 12 2 of installation ends, the upper side sequentially another mold 12 3 and later by the same method, are connected to and installed in the toward the center side of the tunnel.

【0020】そして、トンネル断面の中心軸上に一端が
位置する型枠126を設置する際には、天井部に鋼製枠
27を設置して、その上部側が鋼製枠27に係止され
る。鋼製枠27は、型枠126の設置後に、トンネル軸
上の天井部に設置されるものであって、コンクリート注
入口28が設けられている。このコンクリート注入口2
8は、型枠126内にコンクリートを打設する際に用い
られる。
[0020] Then, when installing the formwork 12 6 located at one end on the center axis of the tunnel cross section, by installing a steel frame 27 in the ceiling portion, the upper side is locked in a steel frame 27 You. Steel frame 27, after installation of the formwork 12 6, there is installed on a ceiling portion of the tunnel axis, the concrete inlet 28 is provided. This concrete inlet 2
8 is used when concrete is in the mold 12 6.

【0021】周方向に隣接設置される型枠121と同1
2のより具体的な連結設置状態の詳細を図2,3に示し
ている。既設の型枠121に別の型枠122を連結設置す
る際には、まず、型枠122の縦補強材18aの下端側
を、既設型枠121の縦補強材18aの上端側と、連結
プレート30を両者間にボルトナットで固定して連結す
る。
Same as the formwork 12 1 installed adjacently in the circumferential direction
2 2 more specific coupling installation state details are shown in FIGS. When connected to and installed another form 12 2 to form 12 1 of the existing, first, the mold 12 the lower end of the second vertical reinforcing member 18a, the upper end of the vertical stiffener 18a of the existing mold 12 1 Then, the connection plate 30 is fixed and connected between the two by bolts and nuts.

【0022】このとき、型枠121と同122の平板パネ
ル16間に、打設するコンクリートの漏れ防止用のシー
ルガスケット32を介装する。一方、型枠122の上部
側は、一端が地山26に定着されたアンカー24の頭部
側を、結合ブラケット34を介して、上部側の横補強材
18bと結合することにより支持する。アンカー24
は、長ナットなどを用いることで、その長さが調整され
る。
[0022] At this time, between the mold 12 1 and the 12 second flat panel 16, is interposed a seal gasket 32 for preventing leakage of the concrete for pouring. On the other hand, the upper side of the mold 12 2, one end of the head side of the anchor 24 that is fixed to the natural ground 26 via a coupling bracket 34, is supported by coupling with the upper side of the transverse stiffener 18b. Anchor 24
Is adjusted by using a long nut or the like.

【0023】以上のようにして型枠12の設置が終了す
ると、トンネル軸方向の妻側に漏れ止め対策を施した後
に、型枠122の平板パネル16の上端側から、例え
ば、高流動コンクリートを型枠122と掘削面10との
間に打設して、表面側にプレキャストコンクリート版製
の平板パネル16を残置させた覆工コンクリート層14
を形成する。
[0023] When the installation of the form 12 in the manner described above is terminated, after performing leakproof measures gable of the tunnel axis, from the upper end side of the mold 12 and second flat panel 16, for example, a high fluidity concrete the by Da設between the mold 12 2 and excavating surface 10, lining concrete layer precast concrete panel made of flat panel 16 was left on the surface side 14
To form

【0024】そして、同様な作業を順次トンネル中心軸
側まで行うことにより、プレキャストコンクリート版製
の平板パネル16の長さに対応した覆工コンクリート層
14が形成され、1サイクルの作業を終了する。
By repeating the same operation up to the tunnel center axis side, the lining concrete layer 14 corresponding to the length of the flat panel 16 made of a precast concrete plate is formed, and one cycle of operation is completed.

【0025】さて、以上のように構成したトンネル覆工
工法によれば、型枠12を掘削面10に沿って設置する
際に、その連結用補強材18の下端側を、周方向に隣接
設置する他の型枠12の連結用補強材18と相互に結合
させるとともに、各型枠12の上端側を、地山に一端側
を定着したアンカー24により支持するので、型枠12
を支持する坑内支保工が不要になり、他の作業との干渉
を避けることができる。
According to the tunnel lining method configured as described above, when the formwork 12 is installed along the excavation surface 10, the lower end side of the connection reinforcing member 18 is installed adjacently in the circumferential direction. And the upper end of each mold 12 is supported by an anchor 24 fixed at one end to the ground.
This eliminates the need for an underground shoring for supporting the work, thereby avoiding interference with other work.

【0026】また、平板パネル16は、坑外で連結用補
強材18を取付けることができるとともに、連結用補強
材18を添設することにより大型化が可能になり、大型
のパネルを使用することで、型枠12の設置作業を迅速
に行える。
Further, the flat panel 16 can be provided with the connecting reinforcement 18 outside the mine, and can be increased in size by adding the connecting reinforcement 18, so that a large panel can be used. Thus, the work of installing the formwork 12 can be performed quickly.

【0027】さらに、プレキャストコンクリート版製の
平板パネル16は、型枠板を兼用し、覆工コンクリート
層14の表面に残置されるので、コンクリート打設後の
養生を必要とせず、これにより工期を短縮できる。
Further, the flat panel 16 made of a precast concrete plate also serves as a form plate and is left on the surface of the lining concrete layer 14, so that curing after concrete casting is not required. Can be shortened.

【0028】このため、本実施例の覆工工法をトンネル
の拡幅部に適用すると、セントル方式よりも大幅に工期
を低減させることができるとともに、拡幅部以外の一般
部分に適用しても、その効果を有効に発揮させることが
できる。
For this reason, when the lining method of this embodiment is applied to the widened portion of the tunnel, the construction period can be greatly reduced as compared with the centrifugal method, and even if the lining method is applied to a general portion other than the widened portion. The effect can be exhibited effectively.

【0029】また、覆工コンクリート層14の表面は、
高品質に工場生産することができるプレキャストコンク
リート版製の平板パネル16で覆われるため、美観に優
れ、耐久性も優れたものとなる。
The surface of the lining concrete layer 14 is
Since it is covered with the flat panel 16 made of a precast concrete slab which can be factory-produced with high quality, the appearance is excellent and the durability is also excellent.

【0030】さらに、本実施例の場合には、プレキャス
トコンクリート版製の平板パネル16の背面側には、格
子状に配置された連結用補強材18が突設されて、凹凸
状になっているので、コンクリートを打設すると、コン
クリートと平板パネル16との間の接合面積が大きくな
り、両者間の付着強度を増加させる。
Further, in the case of the present embodiment, on the rear side of the flat panel panel 16 made of a precast concrete plate, connecting reinforcing members 18 arranged in a lattice shape are protruded to be uneven. Therefore, when the concrete is cast, the joint area between the concrete and the flat panel 16 increases, and the bonding strength between the two increases.

【0031】図4は、本発明にかかるトンネル覆工工法
の第2実施例を示しており、上記第1実施例と同一若し
くは相当する部分には、同一符号を付してその説明を省
略するとともに、異化にその特徴点についてのみ説明す
る。
FIG. 4 shows a second embodiment of the tunnel lining method according to the present invention, in which the same or corresponding parts as those in the first embodiment are denoted by the same reference numerals and description thereof is omitted. At the same time, only the features of catabolic will be described.

【0032】同図に示した実施例では、各型枠12は、
上記実施例と同様に、型枠板兼用のプレキャストコンク
リート版製の平板パネル16と、連結用補強材18とを
備えているが、本実施例の場合には、連結用補強材18
は、平板パネル16の外面(覆工コンクリートを打設す
る側と反対側の面)に添設されている。
In the embodiment shown in FIG.
As in the above-described embodiment, a flat panel 16 made of a precast concrete plate that also serves as a form plate and a reinforcing member 18 for connection are provided. In the present embodiment, the reinforcing member 18 for connecting is used.
Is attached to the outer surface of the flat panel 16 (the surface opposite to the side where the lining concrete is cast).

【0033】また、平板パネル16の内面側には、打設
されるコンクリートとの間の付着力を補強する複数のジ
ベル36が突設されている。本実施例の場合にも、既設
の型枠121に別の型枠122を連結設置する際には、ま
ず、型枠122の縦補強材18aの下端側を、既設型枠
121の縦補強材18aの上端側と連結し、型枠122
上部側は、アンカー24により支持する。
A plurality of dowels 36 are provided on the inner surface of the flat panel 16 to reinforce the adhesive force between the flat panel 16 and the concrete to be cast. In the case of the present embodiment also, when connected to and installed another form 12 2 to form 12 1 of the existing, first, the lower end of the mold 12 and second longitudinally reinforcements 18a, existing mold 12 1 the connecting the upper side of the vertical stiffener 18a, the upper side of the mold 12 2, supported by an anchor 24.

【0034】このとき、本実施例の場合には、平板パネ
ル16の外面側に連結用補強材18が添設されているの
で、別の部材を介在させることなく、型枠122の縦補
強材18aの下端側を、既設型枠121の縦補強材18
aの上端側に、ボルトナットを用いて直接連結すること
ができる。
[0034] At this time, in the case of the embodiment, since the connecting reinforcement 18 on the outer surface side of the flat panel 16 is additionally provided, without interposing another member, longitudinal reinforcement of the form 12 2 the lower end of the timber 18a, the vertical reinforcement 18 of the existing mold 12 1
It can be directly connected to the upper end side of a using a bolt and nut.

【0035】また、本実施例の場合には、アンカー24
の一端は、地山26に接触するように設置された支保工
11に先付けプレート38を介して定着され、他端側
は、平板パネル16および縦補強材18aを貫通して、
その外方まで延設され、横補強材18bにナットを装着
することにより定着されている。
In this embodiment, the anchor 24
Is fixed to the shoring 11 installed so as to be in contact with the ground 26 via a leading plate 38, and the other end penetrates the flat panel 16 and the vertical reinforcing member 18 a,
It extends to the outside and is fixed by attaching a nut to the lateral reinforcing member 18b.

【0036】この実施例においても、型枠12の設置が
終了すると、掘削面10と型枠12との間にコンクリー
トが打設され、上記実施例と同様に覆工コンクリート層
14が形成される。
Also in this embodiment, when the installation of the formwork 12 is completed, concrete is poured between the excavated surface 10 and the formwork 12, and the lining concrete layer 14 is formed in the same manner as in the above embodiment. .

【0037】このような型枠12を用いる第2実施例に
おいても第1実施例と同等の作用効果が得られるととも
に、特に、第2実施例の場合には、補強材18同志を直
接連結することができ、また、例えば、連結用補強材1
8を平板パネル16から離脱可能に構成しておくと、打
設したコンクリートが硬化した後に、これを取り外して
転用することも可能なので、第1実施例の場合よりも、
構造が簡単で経済的な面でも有利になる。
In the second embodiment using such a formwork 12, the same operation and effect as those of the first embodiment can be obtained. In particular, in the case of the second embodiment, the reinforcing members 18 are directly connected. And, for example, the connecting reinforcement 1
When the concrete 8 is configured to be detachable from the flat panel 16, it is possible to remove and convert the cast concrete after it has hardened, so that the concrete can be removed more than in the first embodiment.
The structure is simple, which is advantageous in terms of economy.

【0038】なお、上記実施例では、パネル16をプレ
キャストコンクリート版で構成し、かつ、その形状を平
板としているが、本発明の実施は、これに限られること
はなく、例えば、鋼鈑パネルであっても良いし、また、
例えば、トンネルの掘削面に沿った湾曲形状のパネルを
用いることもできる。
In the above embodiment, the panel 16 is made of a precast concrete slab, and its shape is a flat plate. However, the present invention is not limited to this. It may be,
For example, a curved panel along the excavation surface of the tunnel can be used.

【0039】[0039]

【発明の効果】以上、詳細に説明したように、本発明に
かかるトンネル覆工工法によれば、坑内でセントルを組
んで施工する場合よりも、大幅に工期を短縮することが
できる。
As described above in detail, according to the tunnel lining method of the present invention, the construction period can be significantly shortened as compared with the case of constructing the pit in a pit.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかるトンネル覆工工法の一実施例を
示す施工状態の正面図である。
FIG. 1 is a front view of a construction state showing one embodiment of a tunnel lining method according to the present invention.

【図2】図1の要部拡大図である。FIG. 2 is an enlarged view of a main part of FIG.

【図3】図2の上面図である。FIG. 3 is a top view of FIG. 2;

【図4】本発明にかかるトンネル覆工工法の他の実施例
を示す要部説明図である。
FIG. 4 is an explanatory view of a principal part showing another embodiment of the tunnel lining method according to the present invention.

【符号の説明】[Explanation of symbols]

10 掘削面 11 支保工 12 型枠 14 覆工コンクリート層 16 プレキャストコンクリート平板パネル 18 連結用補強材 24 アンカー DESCRIPTION OF SYMBOLS 10 Excavation surface 11 Shoring 12 Formwork 14 Lining concrete layer 16 Precast concrete flat panel panel 18 Connection reinforcement 24 Anchor

フロントページの続き (72)発明者 新村 亮 東京都港区港南2丁目15番2号 株式会社 大林組本社内 Fターム(参考) 2D055 CA03 DA01 Continued on the front page (72) Inventor Ryo Shinmura 2-15-2 Konan, Minato-ku, Tokyo Obayashi Corporation F-term (reference) 2D055 CA03 DA01

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 掘削面の内周に沿って所定の間隔を隔て
て型枠を設置し、前記掘削面と型枠との間にコンクリー
トを打設して覆工コンクリート層を形成するトンネル覆
工工法において、 前記型枠は、前記覆工コンクリート層の表面に残置され
る型枠板兼用のパネルと、このパネルの内面または外面
に添設された連結用補強材とを備え、 前記型枠を前記掘削面に沿って設置する際に、その連結
用補強材の下端側を、周方向に隣接設置する他の型枠の
連結用補強材と相互に結合させるとともに、各型枠の上
端側を、地山または地山に設置された支保工に一端側を
連結したアンカーにより支持することを特徴とするトン
ネル覆工工法。
1. A tunnel cover that forms a lining concrete layer by placing a formwork at a predetermined interval along an inner periphery of an excavation surface and casting concrete between the excavation surface and the formwork. In the method of construction, the formwork includes a panel that also serves as a formwork plate that is left on the surface of the lining concrete layer, and a connecting reinforcing material attached to an inner surface or an outer surface of the panel. When installing along the excavation surface, the lower end side of the connection reinforcing material is mutually connected with the connection reinforcing material of another formwork installed adjacently in the circumferential direction, and the upper end side of each formwork. A tunnel lining method characterized by supporting the ground by means of an anchor having one end connected to a ground or a shoring installed at the ground.
【請求項2】 前記パネルは、予め製作されるプレキャ
ストコンクリート版からなることを特徴とする請求項1
記載のトンネル覆工工法。
2. The panel as claimed in claim 1, wherein the panel is made of a precast concrete slab.
The tunnel lining method described.
【請求項3】 前記パネルは、平板状に形成されること
を特徴とする請求項1または2記載のトンネル覆工工
法。
3. The tunnel lining method according to claim 1, wherein the panel is formed in a flat plate shape.
JP26482699A 1999-09-20 1999-09-20 Tunnel lining method Expired - Fee Related JP3633397B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26482699A JP3633397B2 (en) 1999-09-20 1999-09-20 Tunnel lining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26482699A JP3633397B2 (en) 1999-09-20 1999-09-20 Tunnel lining method

Publications (2)

Publication Number Publication Date
JP2001090487A true JP2001090487A (en) 2001-04-03
JP3633397B2 JP3633397B2 (en) 2005-03-30

Family

ID=17408754

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26482699A Expired - Fee Related JP3633397B2 (en) 1999-09-20 1999-09-20 Tunnel lining method

Country Status (1)

Country Link
JP (1) JP3633397B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102337903A (en) * 2011-08-25 2012-02-01 安徽理工大学 Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway
JP2020105806A (en) * 2018-12-27 2020-07-09 日鉄建材株式会社 Construction metho of underground structure, and underground structure
JP2021092029A (en) * 2019-12-06 2021-06-17 株式会社奥村組 Existing tunnel reinforcement structure
JP2022087385A (en) * 2020-12-01 2022-06-13 大成建設株式会社 Tunnel lining structure and tunnel construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102337903A (en) * 2011-08-25 2012-02-01 安徽理工大学 Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway
CN102337903B (en) * 2011-08-25 2013-10-23 安徽理工大学 Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway
JP2020105806A (en) * 2018-12-27 2020-07-09 日鉄建材株式会社 Construction metho of underground structure, and underground structure
JP7288301B2 (en) 2018-12-27 2023-06-07 日鉄建材株式会社 Underground structure construction method and underground structure
JP2021092029A (en) * 2019-12-06 2021-06-17 株式会社奥村組 Existing tunnel reinforcement structure
JP7409849B2 (en) 2019-12-06 2024-01-09 株式会社奥村組 Reinforcement structure of existing tunnel
JP2022087385A (en) * 2020-12-01 2022-06-13 大成建設株式会社 Tunnel lining structure and tunnel construction method
JP7444763B2 (en) 2020-12-01 2024-03-06 大成建設株式会社 Tunnel lining structure and tunnel construction method

Also Published As

Publication number Publication date
JP3633397B2 (en) 2005-03-30

Similar Documents

Publication Publication Date Title
CN109252875B (en) Existing tunnel lining reinforcing structure and reinforcing method
CN106930777B (en) The construction method that Bored Section of Metro main track assembled two serves as a contrast
JP3321697B2 (en) Tunnel lining method using composite panels
JPH1122390A (en) Form device for tunnel lining and lining method using the same
KR100313720B1 (en) Composite Underground Structure Construction Method
CN111287764A (en) Tunnel secondary lining structure and construction method thereof
KR20060096706A (en) Deck suspension top-down method of sub-structure
CN209195425U (en) Existing tunnel lining reinforcement structure
JP2001090487A (en) Tunnel lining work
JP2004169474A (en) Connecting structure for tunnel cutting and enlarging section
JPH09268583A (en) Structural steel embedded half precast concrete member and construction method of underground structure using the same member
KR200390421Y1 (en) Top-down substructure by deck suspension
CN212452765U (en) Two-in-one underground pipe gallery structure
CN205382595U (en) Integral shear force wall of steel pipe concrete edge constraint coincide
JP5022150B2 (en) Tunnel merge structure and method for constructing tunnel merge structure
CN113958088A (en) Assembled elevator shaft
JP2002364008A (en) Synthesized arch tunnel with large cross section and its work method
KR200219236Y1 (en) A mold assembly for reinforced concrete girders execution
JP3578414B2 (en) Construction method of reinforced concrete retaining wall
KR200163856Y1 (en) Prefabricate arch construction
CN219412672U (en) Prefabricated flue box culvert, integral assembly type flue structure and shield tunnel
JPH08253947A (en) Installation method for form-support in reverse placing method of concrete
JP2733722B2 (en) Construction method of deep foundation pile type retaining wall
CN220469099U (en) Multilayer crossed reinforced concrete V-shaped cylindrical structure
CN221546015U (en) Column wall integrated precast concrete wallboard

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041129

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20041207

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041220

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080107

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090107

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100107

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100107

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110107

Year of fee payment: 6

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110107

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120107

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130107

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130107

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140107

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees