JP7444763B2 - Tunnel lining structure and tunnel construction method - Google Patents

Tunnel lining structure and tunnel construction method Download PDF

Info

Publication number
JP7444763B2
JP7444763B2 JP2020199293A JP2020199293A JP7444763B2 JP 7444763 B2 JP7444763 B2 JP 7444763B2 JP 2020199293 A JP2020199293 A JP 2020199293A JP 2020199293 A JP2020199293 A JP 2020199293A JP 7444763 B2 JP7444763 B2 JP 7444763B2
Authority
JP
Japan
Prior art keywords
lining
precast
tunnel
shoring
filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020199293A
Other languages
Japanese (ja)
Other versions
JP2022087385A (en
Inventor
雄貴 植野
勇 大塚
賢 板垣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2020199293A priority Critical patent/JP7444763B2/en
Publication of JP2022087385A publication Critical patent/JP2022087385A/en
Application granted granted Critical
Publication of JP7444763B2 publication Critical patent/JP7444763B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

本発明は、トンネル覆工構造およびトンネル施工方法に関する。 The present invention relates to a tunnel lining structure and a tunnel construction method.

NATM等の山岳トンネルの施工では、掘削により露出した地山面を、吹付コンクリート、鋼製支保工およびロックボルト等を組み合わせた支保工により閉塞した後、支保工の内空側に所定厚さの覆工コンクリートを打設するのが一般的である。覆工コンクリートは、トンネル坑内にスライドセントル(型枠)を組み立てる作業と、スライドセントルと支保工との間にコンクリートを打設する作業とを繰り返すことにより、トンネル延長に沿って連続的に施工する。
前記従来のトンネル施工方法では、大規模なスライドセントルの移動、組立、解体を繰り返す必要があるため、作業に手間がかかる。また、所定厚さのコンクリートをすべて現場で打設するため、コンクリートの打ち込みおよび養生に時間がかかる。
スライドセントルに代えてプレキャスト部材を捨て型枠として使用すれば、型枠(スライドセントル)の移動、解体を省略することができ、施工性の向上を図ることができる。また、現場打ちコンクリートの打設量を削減することによる工期短縮化も図ることができる。ここで、特許文献1には、トンネルの既設覆工の内面に沿ってプレキャストパネルを設置し、プレキャストパネルと既設覆工との隙間に充填材を充填する施工方法が開示されている。
プレキャストパネルの背面に充填される充填材は、プレキャストパネルの脚部から上昇し、プレキャストパネルの天端において閉合される。そのため、充填材の注入時のプレキャストパネルには、充填材による側圧が作用することより天端付近に過大な曲げモーメントが作用する。
In the construction of mountain tunnels such as NATM, the ground surface exposed by excavation is closed off with a shoring system that combines shotcrete, steel shoring, rock bolts, etc., and then a predetermined thickness is installed on the inner side of the shoring. It is common to pour concrete lining. Lining concrete is constructed continuously along the length of the tunnel by repeating the work of assembling the slide center (formwork) inside the tunnel and pouring concrete between the slide center and the shoring. .
In the conventional tunnel construction method, it is necessary to repeatedly move, assemble, and dismantle a large-scale slide center, which takes time and effort. Furthermore, since all concrete of a predetermined thickness is poured on site, it takes time to pour and cure the concrete.
If a precast member is used as a waste formwork instead of a slide center, the movement and disassembly of the formwork (slide center) can be omitted, and workability can be improved. Furthermore, the construction period can be shortened by reducing the amount of cast-in-place concrete. Here, Patent Document 1 discloses a construction method in which a precast panel is installed along the inner surface of an existing lining of a tunnel, and a gap between the precast panel and the existing lining is filled with a filler material.
The filler material filling the back side of the precast panel rises from the legs of the precast panel and is closed at the top of the precast panel. Therefore, when the filler is injected into the precast panel, an excessive bending moment acts on the precast panel near the top due to the lateral pressure caused by the filler.

特開2003-227296号公報JP2003-227296A

本発明は、プレキャスト部材を用いることにより施工時の手間を削減するとともに、プレキャスト部材に発生する断面力の緩和を図ることが可能なトンネル覆工構造およびトンネル施工方法を提案することを課題とする。 An object of the present invention is to propose a tunnel lining structure and a tunnel construction method that can reduce the labor during construction by using precast members and alleviate the cross-sectional force generated in the precast members. .

前記課題を解決するための本発明のトンネル覆工構造は、トンネル内面に沿って設けられたアーチ状のプレキャスト覆工と、前記プレキャスト覆工と前記トンネル内面との間に充填された充填材と、充填材注入時の圧力による前記プレキャスト覆工の変形を抑制する形状保持材とを備えている。前記形状保持材は、前記プレキャスト覆工の天端部において、前記プレキャスト覆工と前記トンネル内面との間に介設されたコンクリート製の柱状部材、または、内部に流体もしくはセメント系固化材が充填された袋体である。また、前記形状保持材の一端は鋼製支保工の内面に当接し、前記形状保持材の他端は前記プレキャスト覆工の外面に当接している。
また、本発明のトンネル施工方法は、地山を掘削する掘削工程と、地山の掘削により露出した地山面を支保工により閉塞する支保工程と、前記支保工の内面に沿ってアーチ状のプレキャスト覆工を設置する覆工部材設置工程と、前記プレキャスト覆工と前記地山面との隙間に充填材を充填する充填工程とを備えており、前記支保工程では鋼製支保工を建て込むとともに吹付コンクリートを吹き付け、前記覆工部材設置工程では充填材注入時の圧力による前記プレキャスト覆工の変形を抑制するコンクリート製の柱状部材からなる形状保持材を、一端を前記鋼製支保工の内面に当接させるとともに他端を前記プレキャスト覆工の外面に当接させた状態で配設する。
かかるトンネル覆工構造およびトンネル施工方法によれば、プレキャスト覆工を用いているため、スライドセントルなどの型枠を使用する場合に比べて、型枠の組立、脱型、移動等に要する手間を削減し、施工性の向上を図ることができる。また、所定の品質が確保されたプレキャスト覆工と充填材(例えば現場打ちコンクリート)との複合構造にすることで、覆工の薄肉化を図ることができる。さらに、形状保持材を配設しているため、充填材による側圧が作用した場合でも、プレキャスト覆工の天端付近における上方向への変位が抑制され、その結果、プレキャスト覆工に発生する曲げモーメントを緩和できる。
The tunnel lining structure of the present invention for solving the above problem includes: an arch-shaped precast lining provided along the inner surface of the tunnel; and a filler filled between the precast lining and the inner surface of the tunnel. and a shape-retaining material that suppresses deformation of the precast lining due to pressure when injecting the filler . The shape-retaining material is a columnar member made of concrete interposed between the precast lining and the inner surface of the tunnel at the top end of the precast lining, or the inside thereof is filled with a fluid or a cement-based solidifying material. It is a bag made of plastic. Further, one end of the shape-retaining material is in contact with the inner surface of the steel shoring, and the other end of the shape-retaining material is in contact with the outer surface of the precast lining.
Further, the tunnel construction method of the present invention includes an excavation step of excavating the ground, a shoring step of closing the surface of the ground exposed by the excavation of the ground with a shoring, and an arch-shaped construction along the inner surface of the shoring. The method includes a lining member installation step for installing a precast lining, and a filling step for filling a gap between the precast lining and the ground surface with a filler material, and in the supporting step, steel shoring is erected. At the same time, shotcrete is sprayed, and in the lining member installation process, a shape-retaining material consisting of a columnar member made of concrete that suppresses deformation of the precast lining due to the pressure during injection of filler is attached to one end of the inner surface of the steel shoring. and the other end is placed in contact with the outer surface of the precast lining.
According to this tunnel lining structure and tunnel construction method, since a precast lining is used, the labor required for assembling, demolding, and moving the formwork is reduced compared to when using formwork such as a slide center. It is possible to reduce the amount of waste and improve workability. Further, by using a composite structure of a precast lining with a predetermined quality and a filler (for example, cast-in-place concrete), the lining can be made thinner. Furthermore, since the shape-retaining material is provided, even when lateral pressure from the filler is applied, upward displacement near the top of the precast lining is suppressed, and as a result, bending that occurs in the precast lining is suppressed. The moment can be alleviated.

なお、前記プレキャスト覆工は、複数のプレキャストパネル同士を組み合わせることにより形成するのが望ましい。施工スペースが限られたトンネル坑内において、取り扱いやすい形状および重量のプレキャストパネルを使用すれば、プレキャスト覆工の設置時の効率化を図ることができる。
また、形状保持材は、例えば、前記プレキャスト覆工の天端部において前記プレキャスト覆工と前記トンネル内面との間に介設された間詰部材を使用することができる。このような間詰部材には、コンクリート製のスペーサ、高さ調整可能なスペーサ、または、内部に流体もしくはセメント系固化材が充填された袋体を使用することができる。
また、より確実な充填性を確保する観点から、前記充填材には高流動コンクリートを使用するのが望ましい。
Note that the precast lining is preferably formed by combining a plurality of precast panels. In tunnels where construction space is limited, using precast panels with an easy-to-handle shape and weight can improve the efficiency of precast lining installation.
Further, as the shape-retaining material, for example, a filler member interposed between the precast lining and the inner surface of the tunnel at the top end of the precast lining can be used. As such a filling member, a concrete spacer, a height-adjustable spacer, or a bag filled with a fluid or a cement-based solidifying material can be used.
Furthermore, from the viewpoint of ensuring more reliable filling properties, it is desirable to use high fluidity concrete as the filling material.

本発明のトンネル覆工構造およびトンネル施工方法によれば、プレキャスト部材を用いることにより施工時の手間を削減するとともに、プレキャスト部材に発生する断面力の緩和を図ることが可能となる。 According to the tunnel lining structure and tunnel construction method of the present invention, by using a precast member, it is possible to reduce the labor during construction and to alleviate the cross-sectional force generated in the precast member.

第一実施形態のトンネル覆工構造の横断図である。It is a cross-sectional view of the tunnel lining structure of the first embodiment. 第一実施形態のトンネル覆工構造の縦断図である。It is a longitudinal sectional view of the tunnel lining structure of the first embodiment. 第一実施形態のトンネル施工方法のフローチャートである。It is a flowchart of the tunnel construction method of a first embodiment. 覆工部材設置工程の概要を示す斜視図である。It is a perspective view showing an outline of a lining member installation process. トンネル覆工構造の解析結果を示す図であって、(a)は実施例の変位図、(b)は比較例の変位図である。It is a figure which shows the analysis result of a tunnel lining structure, Comprising: (a) is a displacement diagram of an Example, (b) is a displacement diagram of a comparative example. トンネル覆工構造の解析結果を示す図であって、(a)は実施例の曲げモーメント図、(b)は比較例の曲げモーメント図である。It is a figure which shows the analysis result of a tunnel lining structure, Comprising: (a) is a bending moment diagram of an Example, (b) is a bending moment diagram of a comparative example. 第二実施形態のトンネル覆工構造の横断図である。It is a cross-sectional view of a tunnel lining structure of a second embodiment. 第二実施形態のトンネル覆工構造の一部を示す部分拡大図である。It is a partially enlarged view showing a part of the tunnel lining structure of the second embodiment. (a)および(b)は他の形態に係る形状保持材を示す横断図である。(a) and (b) are cross-sectional views showing shape-retaining materials according to other embodiments.

本実施形態では、NATM等の山岳工法によりトンネルTを施工する場合について説明する。山岳工法では、地山Gを掘削してトンネルTの切羽K(トンネルTの先端部)を前進させる作業と、トンネルTの掘削により露出した地山Gを支保工2により閉塞する作業とを繰り返すことにより、所定延長のトンネルTを形成する。また、地山Gの掘削に起因するトンネルTの周辺地山の変形が収束したら、支保工2の内側(内空側)に覆工3を形成することで、トンネル覆工構造1を構築する。図1に本実施形態のトンネル覆工構造1の横断図、図2にトンネル覆工構造1の縦断図を示す。図1に示すように、本実施形態のトンネル覆工構造1は、断面アーチ状を呈していて、支保工2と覆工3とを備えている。
支保工2は、トンネルTの掘削により露出した地山Gを早期に閉塞するものであって、図1および図2に示すように、地山Gに対して吹付けられた吹付コンクリート21と、トンネル軸方向に対して所定の間隔により建て込まれた鋼製支保工22と、地山Gに打設されたロックボルト23により構成されている。なお、支保工2の支保構造は、地山等級に応じて設定するものとし、良好な地山Gの場合には鋼製支保工22やロックボルト23を省略してもよい。また、軟弱な地盤の場合は、ロックボルト23に代えて、あるいはロックボルト23と併用して、先受工法(例えば、フォアポーリングやパイプルーフ等)や地盤改良工法等の補助工法を採用する場合もある。
In this embodiment, a case will be described in which the tunnel T is constructed using a mountain construction method such as NATM. In the mountain construction method, the work of excavating the ground G and advancing the face K of the tunnel T (the tip of the tunnel T), and the work of closing the ground G exposed by the excavation of the tunnel T with the support 2 are repeated. By doing so, a tunnel T of a predetermined length is formed. Furthermore, once the deformation of the surrounding ground of the tunnel T due to the excavation of the ground G has subsided, the tunnel lining structure 1 is constructed by forming the lining 3 inside the shoring 2 (on the inner side). . FIG. 1 shows a cross-sectional view of the tunnel lining structure 1 of this embodiment, and FIG. 2 shows a longitudinal cross-sectional view of the tunnel lining structure 1. As shown in FIG. 1, the tunnel lining structure 1 of this embodiment has an arched cross section and includes shoring 2 and a lining 3.
The shoring 2 is for quickly blocking the ground G exposed by the excavation of the tunnel T, and as shown in FIGS. 1 and 2, shotcrete 21 sprayed onto the ground G, It consists of steel supports 22 built at predetermined intervals in the axial direction of the tunnel, and rock bolts 23 driven into the ground G. The support structure of the support 2 shall be set according to the grade of the ground, and in the case of good ground G, the steel support 22 and the rock bolts 23 may be omitted. In addition, in the case of soft ground, auxiliary construction methods such as advance construction methods (for example, forepoling, pipe roofing, etc.) or ground improvement methods may be used instead of or in combination with rock bolts 23. There is also.

本実施形態の覆工3は、支保工2の内面に沿って形成されており、図1および図2に示すように、プレキャスト覆工4と、間詰部材5(形状保持材)と、充填材(裏込め材)6とを備えている。
プレキャスト覆工4は、アーチ状を呈していて、支保工2(トンネルT)の内面に沿って隙間をあけて設けられている。
プレキャスト覆工4は、複数のプレキャストパネル41同士を組み合わせることにより、アーチ状に形成されている。プレキャストパネル41は、トンネル断面形状に応じて断面弧状を呈した鉄筋コンクリート製のパネル(セグメント)である。プレキャストパネル41の端面には、ジョイントが設けられており、プレキャストパネル41の端面同士を突き合せる際にジョイントを係合することにより、プレキャストパネル41同士を連結する。本実施形態では、プレキャストパネル41のトンネル周方向のジョイントとしてくさび継手を採用する。プレキャスト覆工4は、プレキャストパネル41の継手部が回転バネとして機能することで、断面力を緩和する。また、本実施形態では、プレキャストパネル41のトンネル軸方向のジョイントとしてピン挿入継手を採用する。ピン挿入継手は、一方のプレキャストパネル41に埋め込んだ金具に、他方のプレキャストパネル41に突設された金具を差し込むことで嵌合する。
The lining 3 of this embodiment is formed along the inner surface of the shoring 2, and as shown in FIGS. material (backfilling material) 6.
The precast lining 4 has an arch shape and is provided with gaps along the inner surface of the shoring 2 (tunnel T).
The precast lining 4 is formed into an arch shape by combining a plurality of precast panels 41. The precast panel 41 is a panel (segment) made of reinforced concrete and has an arcuate cross-section depending on the cross-sectional shape of the tunnel. Joints are provided on the end faces of the precast panels 41, and the precast panels 41 are connected to each other by engaging the joints when the end faces of the precast panels 41 are butted together. In this embodiment, a wedge joint is employed as a joint of the precast panel 41 in the tunnel circumferential direction. In the precast lining 4, the joint portion of the precast panel 41 functions as a rotating spring, thereby alleviating the cross-sectional force. Further, in this embodiment, a pin insertion joint is employed as a joint of the precast panel 41 in the tunnel axis direction. The pin insertion joint is fitted by inserting a metal fitting protruding from the other precast panel 41 into a metal fitting embedded in one precast panel 41 .

間詰部材5は、充填材注入時の圧力によるプレキャスト覆工4の変形を抑制するための形状保持材であって、プレキャスト覆工4の天端部において、プレキャスト覆工4と支保工2(トンネル内面)との間に介設されている。間詰部材5は、図2に示すように、トンネル軸方向に所定の間隔をあけて、複数設けられている。本実施形態の間詰部材5は、コンクリート製のスペーサである。間詰部材5は、プレキャスト覆工4の天端部におけるプレキャスト覆工4と支保工2との隙間と同等の高さを有している。間詰部材5の形状は限定されるものではなく、例えば、四角柱状や円柱状とする。 The filling member 5 is a shape-retaining material for suppressing the deformation of the precast lining 4 due to the pressure when injecting the filler, and is a material that maintains the shape of the precast lining 4 and the shoring 2 ( (inner surface of the tunnel). As shown in FIG. 2, a plurality of filler members 5 are provided at predetermined intervals in the tunnel axis direction. The filling member 5 of this embodiment is a spacer made of concrete. The filler member 5 has a height equivalent to the gap between the precast lining 4 and the shoring 2 at the top end of the precast lining 4. The shape of the filler member 5 is not limited, and may be, for example, a square prism or a cylinder.

充填材6は、プレキャスト覆工4と支保工2(トンネルT)の内面との隙間に充填された固化材(本実施形態では高流動コンクリート)である。充填材6は、プレキャスト覆工4を形成した後、プレキャスト覆工4と支保工2との隙間にポンプ圧送により充填され、所定期間の養生を経て、覆工コンクリートとして必要な強度を発現する。なお、プレキャスト覆工4と支保工2との隙間には、必要に応じて鉄筋を配筋してもよい。 The filler 6 is a solidifying material (high fluidity concrete in this embodiment) filled in the gap between the precast lining 4 and the inner surface of the shoring 2 (tunnel T). After forming the precast lining 4, the filler 6 is pumped into the gap between the precast lining 4 and the shoring 2, and is cured for a predetermined period of time to develop the strength required for the concrete lining. Note that reinforcing bars may be arranged in the gap between the precast lining 4 and the shoring 2 as necessary.

以下、トンネル施工方法について説明する。図3に、本実施形態のトンネル施工方法のフローチャートを示す。本実施形態のトンネル施工方法は、掘削工程S1と、支保工程S2と、覆工部材設置工程S3と、充填工程S4とを備えている。
掘削工程S1では、地山Gを掘削して切羽Kを前進させる。地山Gの掘削方法は限定されるものではなく、機械掘削でもよいし、発破掘削でもよい。
The tunnel construction method will be explained below. FIG. 3 shows a flowchart of the tunnel construction method of this embodiment. The tunnel construction method of this embodiment includes an excavation step S1, a shoring step S2, a lining member installation step S3, and a filling step S4.
In the excavation process S1, the ground G is excavated and the face K is advanced. The method of excavating the ground G is not limited, and may be mechanical excavation or blast excavation.

支保工程S2では、地山Gの掘削により露出した地山面を支保工2により閉塞する。支保工程S2では、掘削により露出した地山Gに沿って鋼製支保工22を建て込むとともに、吹付コンクリート21を吹き付ける。吹付コンクリート21を吹き付けたら、ロックボルト23の打設を行う。なお、吹付コンクリート21は、鋼製支保工22の建て込みの前後に一次吹付けと二次吹付けとの2回に分けて吹付けてもよい。吹付コンクリート21の吹付け厚さや、吹付コンクリート21の配合等は、地山状況に応じて適宜変更することが可能である。同様に鋼製支保工22およびロックボルト23の仕様も地山状況(地山等級)に応じて決定する。 In the shoring step S2, the surface of the ground exposed by excavating the ground G is closed with the shoring 2. In the shoring process S2, steel shoring 22 is erected along the ground G exposed by the excavation, and shotcrete 21 is sprayed. After spraying the shotcrete 21, rock bolts 23 are placed. Note that the shotcrete 21 may be sprayed in two parts: primary spraying and secondary spraying, before and after the steel shoring 22 is erected. The spraying thickness of the shotcrete 21, the composition of the shotcrete 21, etc. can be changed as appropriate depending on the ground conditions. Similarly, the specifications of the steel shoring 22 and the rock bolts 23 are determined depending on the ground condition (ground grade).

覆工部材設置工程S3では、支保工2の内面に沿ってアーチ状のプレキャスト覆工4を設置する。プレキャスト覆工4は、複数のプレキャストパネル41を組み合わせることにより形成する。図4は、プレキャスト覆工4の設置状況を示す図である。プレキャスト覆工4を組み立てる際には、図4に示すようにトンネル内空側から、支持マシンMによりプレキャストパネル41を支持する。本実施形態では、支持マシンMとして、上下動可能なアームを有したいわゆるフォークリフトを使用する。支持マシンMは、プレキャストパネル41を支持するための支持架台M1を保持しており、支持架台M1により支持したプレキャストパネル41(プレキャスト覆工4)を所定の位置に配設する。
覆工部材設置工程S3では、プレキャスト覆工4の天端部において、プレキャスト覆工4と支保工2との間に間詰部材5を介設する。間詰部材5は、プレキャスト覆工4の天端部を構成するプレキャストパネル41に予め取り付けておくことで、所定の位置に配置してもよいし、プレキャスト覆工4を組み立てながら、プレキャスト覆工4と支保工2との隙間に介設させてもよい。
In the lining member installation step S3, an arch-shaped precast lining 4 is installed along the inner surface of the shoring 2. Precast lining 4 is formed by combining a plurality of precast panels 41. FIG. 4 is a diagram showing how the precast lining 4 is installed. When assembling the precast lining 4, the precast panel 41 is supported by the support machine M from the hollow side of the tunnel, as shown in FIG. In this embodiment, a so-called forklift truck having an arm that can move up and down is used as the support machine M. The support machine M holds a support frame M1 for supporting the precast panel 41, and arranges the precast panel 41 (precast lining 4) supported by the support frame M1 at a predetermined position.
In the lining member installation step S3, a filler member 5 is interposed between the precast lining 4 and the shoring 2 at the top end of the precast lining 4. The filler member 5 may be installed at a predetermined position by attaching it to the precast panel 41 constituting the top end of the precast lining 4 in advance, or it may be installed in the precast lining while assembling the precast lining 4. 4 and the shoring 2 may be interposed.

充填工程S4では、プレキャスト覆工4と支保工2との隙間に充填材6を充填する。充填材6は、高流動コンクリートをポンプ圧送することにより、プレキャスト覆工4と支保工2との隙間に注入する。また、充填材6を注入する際には、プレキャスト覆工4と支保工2の隙間の端面(プレキャスト覆工4の先端側)を妻板により塞いだ状態で行う。このとき、アーチ状に組み立てられたプレキャスト覆工4は自立している。 In the filling step S4, the gap between the precast lining 4 and the shoring 2 is filled with the filler 6. The filler 6 is injected into the gap between the precast lining 4 and the shoring 2 by pumping high fluidity concrete. In addition, when injecting the filler 6, the end face of the gap between the precast lining 4 and the shoring 2 (the tip side of the precast lining 4) is filled with the end plate. At this time, the precast lining 4 assembled in an arch shape is self-supporting.

本実施形態のトンネル覆工構造1およびトンネル施工方法によれば、プレキャスト覆工4を用いているため、スライドセントルなどの型枠を使用する場合に比べて、型枠の組立、脱型、移動等に要する手間を削減し、施工性の向上を図ることができる。
プレキャスト覆工4と充填材6との複合構造により、既往の覆工と同等以上の構造性能を確保できる。
また、プレキャスト製品であれば、場所打ちには適さないような高強度コンクリートを使用でき、さらには水中養生や蒸気養生を行うこともできるので、プレキャスト覆工4の品質を高め易い。そして、このような高品質のプレキャスト覆工4と充填材6(例えば現場打ちコンクリート)との複合構造にすることで、覆工の薄肉化を図ることができる。
さらに、プレキャスト覆工4の天端部に間詰部材5を配設しているため、充填材6による側圧が作用した場合でも、プレキャスト覆工4の天端付近における上方向への変位が抑制され、その結果、プレキャスト覆工4に発生する曲げモーメントを緩和できる。
また、複数のプレキャストパネル41同士を組み合わせてプレキャスト覆工4を形成するすることで、施工スペースが限られたトンネル坑内において、プレキャスト覆工4の設置時の効率化を図ることができる。
また、充填材6に高流動コンクリートを使用しているため、充填性に優れている。
According to the tunnel lining structure 1 and tunnel construction method of this embodiment, since the precast lining 4 is used, the assembly, demolding, and movement of the formwork are easier than when using formwork such as a slide center. It is possible to reduce the labor required for etc. and improve workability.
The composite structure of the precast lining 4 and the filler 6 can ensure structural performance equivalent to or better than existing linings.
Furthermore, if it is a precast product, high-strength concrete that is not suitable for cast-in-place can be used, and furthermore, it can be cured in water or in steam, so it is easy to improve the quality of the precast lining 4. By forming a composite structure of such high-quality precast lining 4 and filler 6 (for example, cast-in-place concrete), the lining can be made thinner.
Furthermore, since the filler member 5 is provided at the top end of the precast lining 4, even when lateral pressure from the filler 6 is applied, upward displacement near the top end of the precast lining 4 is suppressed. As a result, the bending moment generated in the precast lining 4 can be alleviated.
Further, by forming the precast lining 4 by combining a plurality of precast panels 41, it is possible to improve the efficiency of installing the precast lining 4 in a tunnel where construction space is limited.
Furthermore, since high fluidity concrete is used for the filler 6, it has excellent filling properties.

以下、本実施形態のトンネル覆工構造1について実施した解析結果を示す。本解析では、本実施形態のトンネル覆工構造1(実施例)を施工する際の荷重(充填材6(高流動コンクリート)の注入に伴うコンクリート圧)により発生するプレキャスト覆工4の断面力(変位および曲げモーメント)を算出した。また、比較例として、間詰部材5を設置しなかった場合に発生するプレキャスト覆工4の断面力も算出した。図5(a)に解析により算出された実施例の変位量を示し、(b)に比較例の変位量を示す。また、図6(a)に実施例の曲げモーメント図を示し、(b)に比較例の曲げモーメント図を示す。 Below, the results of an analysis performed on the tunnel lining structure 1 of this embodiment will be shown. In this analysis, the cross-sectional force ( displacement and bending moment) were calculated. Furthermore, as a comparative example, the cross-sectional force of the precast lining 4 that would occur when the filler member 5 was not installed was also calculated. FIG. 5(a) shows the displacement amount of the example calculated by analysis, and FIG. 5(b) shows the displacement amount of the comparative example. Further, FIG. 6(a) shows a bending moment diagram of the example, and FIG. 6(b) shows a bending moment diagram of a comparative example.

図5(b)に示すように、比較例では、コンクリート注入時の側圧により、プレキャスト覆工4の脚部において15.0mm、天端部において11.6mmの大きな変位が生じる結果となった。一方、実施例では、図5(a)に示すように、プレキャスト覆工4の脚部では3.7mm、肩部では2.8mm、天端部では0mmと、変位量を大幅に削減することができた。
また、図6(b)に示すように、比較例では、脚部において63.9kNm、天端部において-33.2kNmの曲げモーメントが生じたのに対し、実施例では、図6(a)に示すように、脚部で39.8kNm、肩部で-20.0kNmであった。このように、曲げモーメントについても、脚部及びトンネル上半部において大幅に低減できる。
As shown in FIG. 5(b), in the comparative example, the lateral pressure during concrete pouring resulted in large displacements of 15.0 mm at the legs and 11.6 mm at the top of the precast lining 4. On the other hand, in the example, as shown in Fig. 5(a), the amount of displacement can be significantly reduced to 3.7 mm at the legs, 2.8 mm at the shoulders, and 0 mm at the top of the precast lining 4. was completed.
In addition, as shown in FIG. 6(b), in the comparative example, a bending moment of 63.9 kNm was generated at the leg portion and -33.2 kNm at the top portion, whereas in the example, as shown in FIG. As shown in Figure 2, it was 39.8 kNm at the legs and -20.0 kNm at the shoulders. In this way, the bending moment can also be significantly reduced in the legs and the upper half of the tunnel.

<第二実施形態>
第二実施形態では、第一実施形態と同様に、支保工2の内側(内空側)に覆工3を形成して、トンネル覆工構造1を構築することで、トンネルTを施工する場合について説明する。図7に第二実施形態のトンネル覆工構造1を示す。図7に示すように、第二実施形態のトンネル覆工構造1は、形状保持材としてプレキャストパネル41に取り付けれたスペーサ51を使用する点で、間詰部材5をプレキャスト覆工4と支保工2との間に介設する引用文献1のトンネル覆工構造1と異なっている。支保工2の詳細は、第一実施形態の支保工2と同様なため、詳細な説明は省略する。
<Second embodiment>
In the second embodiment, similarly to the first embodiment, when constructing the tunnel T by forming the lining 3 inside the shoring 2 (inner space side) and constructing the tunnel lining structure 1. I will explain about it. FIG. 7 shows a tunnel lining structure 1 of the second embodiment. As shown in FIG. 7, the tunnel lining structure 1 of the second embodiment uses a spacer 51 attached to a precast panel 41 as a shape-retaining material, and the filling member 5 is used as a precast lining 4 and a shoring 2. This is different from the tunnel lining structure 1 of Cited Document 1, which is interposed between the two. The details of the shoring 2 are the same as the shoring 2 of the first embodiment, so a detailed explanation will be omitted.

第二実施形態の本実施形態の覆工3は、支保工2の内面に沿って形成されており、プレキャスト覆工4と、スペーサ51(形状保持材)と、充填材(裏込め材)6とを備えている。なお、充填材6の詳細は、第一実施形態の充填材6と同様なため、詳細な説明は省略する。
プレキャスト覆工4は、アーチ状を呈していて、支保工2(トンネルT)の内面に沿って隙間をあけて設けられている。
プレキャスト覆工4は、複数のプレキャストパネル41同士を組み合わせることにより、アーチ状に形成されている。図8(a)に示すように、プレキャストパネル41には、内面にネジ加工(雌ネジ)が施されたボルト孔42が形成されている。ボルト孔42は、プレキャストパネル41を貫通している。ボルト孔42の内空側端部には、ボルト孔42の内径よりも大きな内径の凹部43が形成されている。図8(b)に示すように、凹部43には、プレキャスト覆工4の内空側から蓋材44の取り付けが可能である。本実施形態では、各プレキャストパネル41にボルト孔42が1か所ずつ形成されているが、プレキャストパネル41に形成されるボルト孔の数および配置は限定されるものではない。この他のプレキャストパネル41(プレキャスト覆工4)の詳細は、第一実施形態で示した内容と同様なため、詳細な説明は省略する。
The lining 3 of this embodiment of the second embodiment is formed along the inner surface of the shoring 2, and includes a precast lining 4, a spacer 51 (shape retaining material), and a filler (backfilling material) 6. It is equipped with Note that the details of the filler 6 are the same as the filler 6 of the first embodiment, so a detailed explanation will be omitted.
The precast lining 4 has an arch shape and is provided with gaps along the inner surface of the shoring 2 (tunnel T).
The precast lining 4 is formed into an arch shape by combining a plurality of precast panels 41. As shown in FIG. 8(a), the precast panel 41 has bolt holes 42 threaded (female threads) formed on the inner surface. Bolt holes 42 pass through precast panel 41. A recess 43 having an inner diameter larger than the inner diameter of the bolt hole 42 is formed at the inner end of the bolt hole 42 . As shown in FIG. 8(b), a lid member 44 can be attached to the recess 43 from the inner cavity side of the precast lining 4. In this embodiment, one bolt hole 42 is formed in each precast panel 41, but the number and arrangement of bolt holes formed in the precast panel 41 are not limited. The other details of the precast panel 41 (precast lining 4) are the same as those shown in the first embodiment, so a detailed explanation will be omitted.

スペーサ51は、充填材注入時の圧力によるプレキャスト覆工4の変形を抑制するための形状保持材であって、図8(a)に示すように、プレキャストパネル41に形成されたボルト孔42に基端部が螺着されている。スペーサ51の先端には、スペーサ51の断面よりも大きな形状の板材52が固定されている。また、スペーサ51の基端面には、締付治具を係合するための多角形断面の係合孔53が開口している。スペーサ51は、係合孔53に締付治具54を挿入した状態で、締付治具を回転させることにより、プレキャストパネル41からの突出長を変化させて、板材52を支保工2に当接させる。
本実施形態では、トンネル周方向に複数のスペーサ51が設けられているが、スペーサ51の数および配置は限定されるものではなく、例えば、プレキャスト覆工4の頂部のみや、肩部のみに配設されていてもよい。また、スペーサ51は、必ずしも支保工2に当接させる必要はない。また、板材52は、省略してもよい。
The spacer 51 is a shape-retaining material for suppressing the deformation of the precast lining 4 due to the pressure when injecting the filler, and as shown in FIG. The proximal end is screwed on. A plate member 52 having a larger cross section than the spacer 51 is fixed to the tip of the spacer 51 . Further, an engagement hole 53 having a polygonal cross section for engaging a tightening jig is opened in the base end surface of the spacer 51. The spacer 51 is inserted into the engagement hole 53 with the tightening jig 54 inserted, and by rotating the tightening jig, the protrusion length from the precast panel 41 is changed, and the plate material 52 is attached to the shoring 2. Let them come into contact with you.
In this embodiment, a plurality of spacers 51 are provided in the circumferential direction of the tunnel, but the number and arrangement of spacers 51 are not limited. may be set. Moreover, the spacer 51 does not necessarily need to be brought into contact with the shoring 2. Further, the plate material 52 may be omitted.

以下、第二実施形態のトンネル施工方法について説明する。本実施形態のトンネル施工方法は、第一実施形態と同様に、掘削工程S1と、支保工程S2と、覆工部材設置工程S3と、充填工程S4とを備えている。掘削工程S1、支保工程S2および充填工程S4の詳細は、第一実施形態と同様なため、詳細な説明は省略する。
覆工部材設置工程S3では、支保工2の内面に沿ってアーチ状のプレキャスト覆工4を設置する。プレキャスト覆工4は、複数のプレキャストパネル41を組み合わせることにより形成する。覆工部材設置工程S3では、プレキャスト覆工4の形成に伴い、スペーサ51の調整を行う。プレキャストパネル41のボルト孔42には、予めスペーサ51が取り付けられている。プレキャストパネル41を所定の位置に配設したら、内空側から締付治具54を介してスペーサ51の突出長を調節して、板材52を支保工2に当接させる。プレキャスト覆工4は、周方向に複数配設されたスペーサ51を支保工2に当接させることにより、充填材注入時の圧力に対して抵抗可能な反力を支保工2から確保した状態で組み立てられる。スペーサ51の調節が完了したら締付治具54を取り外して、凹部43に蓋材44を取り付ける。蓋材44は、ボルト孔42に螺合可能なネジ部45と、凹部43と同等の形状の蓋部46とを有していて、ネジ部45をボルト孔42に螺着することで、蓋部46によりボルト孔42(凹部43)を遮蔽する。このとき、必要に応じて蓋材44と凹部43との間に止水材を介設する。
この他の覆工部材設置工程S3の詳細は、第一実施形態で示した内容と同様なため、詳細な説明は省略する。
The tunnel construction method of the second embodiment will be described below. Similar to the first embodiment, the tunnel construction method of this embodiment includes an excavation step S1, a shoring step S2, a lining member installation step S3, and a filling step S4. The details of the excavation process S1, the shoring process S2, and the filling process S4 are the same as those in the first embodiment, so detailed explanations will be omitted.
In the lining member installation step S3, an arch-shaped precast lining 4 is installed along the inner surface of the shoring 2. Precast lining 4 is formed by combining a plurality of precast panels 41. In the lining member installation step S3, the spacers 51 are adjusted as the precast lining 4 is formed. A spacer 51 is attached to the bolt hole 42 of the precast panel 41 in advance. After the precast panel 41 is placed in a predetermined position, the protruding length of the spacer 51 is adjusted from the inner space via the tightening jig 54 to bring the plate material 52 into contact with the shoring 2. The precast lining 4 has a plurality of spacers 51 arranged in the circumferential direction brought into contact with the shoring 2, thereby ensuring a reaction force from the shoring 2 that can resist the pressure at the time of filling material injection. Can be assembled. When the adjustment of the spacer 51 is completed, the tightening jig 54 is removed and the cover member 44 is attached to the recess 43. The lid member 44 has a threaded portion 45 that can be screwed into the bolt hole 42 and a lid portion 46 that has the same shape as the recess 43. By screwing the threaded portion 45 into the bolt hole 42, the lid can be closed. The bolt hole 42 (recess 43) is covered by the portion 46. At this time, a water stop material is interposed between the lid member 44 and the recess 43 if necessary.
The other details of the lining member installation step S3 are the same as those shown in the first embodiment, so detailed explanation will be omitted.

第二実施形態のトンネル覆工構造1およびトンネル施工方法によれば、プレキャストパネル41からスペーサ51が突設されているため、充填材6による側圧が作用した場合でも、プレキャスト覆工4の変位が抑制され、その結果、プレキャスト覆工4に発生する曲げモーメントを緩和できる。
ボルト孔42は、蓋材44により遮蔽するため、地下水の浸透が抑制されている。
この他の第二実施形態のトンネル覆工構造1の作用効果は第一実施形態のトンネル覆工構造1と同様なため、詳細な説明は省略する。
According to the tunnel lining structure 1 and tunnel construction method of the second embodiment, since the spacer 51 is provided protruding from the precast panel 41, the displacement of the precast lining 4 is prevented even when lateral pressure from the filler 6 is applied. As a result, the bending moment generated in the precast lining 4 can be alleviated.
Since the bolt holes 42 are covered by the cover material 44, penetration of underground water is suppressed.
The effects of the other tunnel lining structure 1 of the second embodiment are similar to those of the tunnel lining structure 1 of the first embodiment, so detailed explanations will be omitted.

以上、本発明の実施形態について説明したが、本発明は、前述の実施形態に限られず、前記の各構成要素については本発明の趣旨を逸脱しない範囲で適宜変更が可能である。
第一実施形態では、間詰部材5としてコンクリート部材を使用する場合について説明したが、間詰部材5を構成する部材は限定されるものではなく、例えば、高さ調整可能なスペーサであってもよい。間詰部材5が高さ調整可能であれば、施工誤差などによるプレキャスト覆工4と支保工2との隙間の大きさの変化に追従することができる。また、間詰部材5は、内部に充填材6が充填された袋体であってもよい。かかる間詰部材5によれば、プレキャスト覆工4と支保工2との隙間の大きさの変化に追従できるとともに、間詰部材5の設置が容易である。すなわち、先端に袋体が設けられた注入管を隙間に挿入し、所定の位置に袋体を設置した後、袋体内にセメント系固化材(充填材6と同じ材料でもよい)を充填することで、間詰部材5を形成できる。袋体に水等の流体の充填するようにすれば、プレキャスト覆工4の背面の所定の高さまで充填材6が注入された段階で、袋体内から流体を排出し、袋体を撤去することもできる。
Although the embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments, and each of the above-mentioned components can be modified as appropriate without departing from the spirit of the present invention.
In the first embodiment, a case where a concrete member is used as the filler member 5 has been described, but the members constituting the filler member 5 are not limited, and for example, a height-adjustable spacer may be used. good. If the height of the filler member 5 is adjustable, it can follow changes in the size of the gap between the precast lining 4 and the shoring 2 due to construction errors or the like. Further, the filler member 5 may be a bag body filled with the filler material 6 inside. According to the filler member 5, it is possible to follow changes in the size of the gap between the precast lining 4 and the shoring 2, and the filler member 5 can be easily installed. That is, after inserting an injection tube with a bag at its tip into the gap and setting the bag at a predetermined position, the bag is filled with a cement-based solidifying material (the same material as the filler 6 may be used). Thus, the filling member 5 can be formed. If the bag body is filled with a fluid such as water, the fluid can be discharged from the bag body and the bag body can be removed when the filler 6 has been injected to a predetermined height on the back side of the precast lining 4. You can also do it.

第二実施形態では、スペーサ51の基端面に形成された多角形断面の係合孔53に締付治具54を係合させて、スペーサ51の突出長を調整するものとしたが、係合孔53は、内面にネジ加工が施された雌ネジであってもよい。この場合には係合孔53に頭部を有した雄ボルトをプレキャストパネル41の内空側からねじ込んでおき、雄ボルトを回転させることで、スペーサ51の突出長を調整する。そして、充填材6の硬化後に、雄ボルトを係合孔53から抜き出すことで、トンネル内空側の突出部分を無くす。こうすることで、専用の締付治具を要することなく汎用性の高い雄ボルトによりスペーサ51を設置することができる。 In the second embodiment, the protrusion length of the spacer 51 is adjusted by engaging the tightening jig 54 with the engagement hole 53 having a polygonal cross section formed in the base end surface of the spacer 51. The hole 53 may be a female screw threaded on the inner surface. In this case, a male bolt having a head is screwed into the engagement hole 53 from the inner space side of the precast panel 41, and the protruding length of the spacer 51 is adjusted by rotating the male bolt. After the filler 6 hardens, the male bolt is pulled out from the engagement hole 53, thereby eliminating the protruding portion on the tunnel inner space side. By doing so, the spacer 51 can be installed using a highly versatile male bolt without requiring a dedicated tightening jig.

形状保持材は、前記各実施形態で示したもの(間詰部材5やスペーサ51)に限定されるものではなく、例えば、図9(a)に示すように、プレキャスト覆工4の内面頂部に吊り下げられた錘55であってもよい。また、錘55は、図9(b)に示すようにワイヤー56等を介して、ブレキャスト覆工4の頂部に下向きの力を作用するように設けられた錘55であってもよい。このように、プレキャスト覆工4の頂部に錘55を設置すれば、充填材注入時の側圧によりプレキャスト覆工4の頂部に生じる鉛直変位を抑制できる。 The shape-retaining material is not limited to those shown in the above embodiments (the filling member 5 and the spacer 51), and for example, as shown in FIG. 9(a), the shape-retaining material is It may also be a suspended weight 55. Moreover, the weight 55 may be a weight 55 provided so as to apply a downward force to the top of the breakcast lining 4 via a wire 56 or the like, as shown in FIG. 9(b). In this way, by installing the weight 55 at the top of the precast lining 4, it is possible to suppress the vertical displacement that occurs at the top of the precast lining 4 due to the lateral pressure when the filler is injected.

前記実施形態では、トンネル坑内でプレキャストパネル41を組み立ててプレキャスト覆工4を形成するものとしたが、坑外で組み立てたプレキャスト覆工4をトンネル坑内に搬入してもよい。
覆工部材設置工程S3におけるプレキャスト覆工4を支持方法は、フォークリフトによるものに限定されるものではなく、例えば、その他の支持マシンMを使用してもよいし、架台等を設置してもよい。
充填材6の注入は、プレキャスト覆工4に形成された注入孔から行ってもよいし、プレキャスト覆工4の端面に設けられた妻板に形成された注入口等から注入してもよい。
プレキャストパネル41同士の継手構造は限定されるものではない。
In the embodiment described above, the precast panels 41 are assembled inside the tunnel to form the precast lining 4, but the precast lining 4 assembled outside the tunnel may be carried into the tunnel.
The method of supporting the precast lining 4 in the lining member installation step S3 is not limited to using a forklift; for example, other supporting machines M may be used, or a frame or the like may be installed. .
The filler 6 may be injected through an injection hole formed in the precast lining 4, or may be injected through an injection hole formed in an end plate provided on the end surface of the precast lining 4.
The joint structure between precast panels 41 is not limited.

1 トンネル覆工構造
2 支保工
3 覆工
4 プレキャスト覆工
41 プレキャストパネル
5 間詰部材
6 充填材
G 地山
T トンネル
1 Tunnel lining structure 2 Shoring 3 Lining 4 Precast lining 41 Precast panel 5 Filling member 6 Filling material G Earth T Tunnel

Claims (4)

トンネル内面に沿って設けられたアーチ状のプレキャスト覆工と、
前記プレキャスト覆工と前記トンネル内面との間に充填された充填材と、
充填材注入時の圧力による前記プレキャスト覆工の変形を抑制する形状保持材と、を備えるトンネル覆工構造であって、
前記形状保持材が、前記プレキャスト覆工の天端部において、前記プレキャスト覆工と前記トンネル内面との間に介設されたコンクリート製の柱状部材、または、内部に流体もしくはセメント系固化材が充填された袋体であり、
前記形状保持材の一端は鋼製支保工の内面に当接し、前記形状保持材の他端は前記プレキャスト覆工の外面に当接していることを特徴とする、トンネル覆工構造。
An arch-shaped precast lining installed along the inner surface of the tunnel,
a filler filled between the precast lining and the tunnel inner surface;
A tunnel lining structure comprising: a shape retaining material that suppresses deformation of the precast lining due to pressure during injection of filler,
The shape retaining material is a concrete columnar member interposed between the precast lining and the inner surface of the tunnel at the top end of the precast lining, or the inside thereof is filled with a fluid or a cement solidification material. It is a bag body that has been
A tunnel lining structure, wherein one end of the shape-retaining material is in contact with an inner surface of a steel shoring, and the other end of the shape-retaining material is in contact with an outer surface of the precast lining.
前記プレキャスト覆工が、複数のプレキャストパネル同士を組み合わせることにより形成されていることを特徴とする、請求項1に記載のトンネル覆工構造。 The tunnel lining structure according to claim 1, wherein the precast lining is formed by combining a plurality of precast panels. 前記充填材が高流動コンクリートであることを特徴とする、請求項1または請求項2に記載のトンネル覆工構造。 The tunnel lining structure according to claim 1 or 2 , wherein the filler is high fluidity concrete. 地山を掘削する掘削工程と、
地山の掘削により露出した地山面を支保工により閉塞する支保工程と、
前記支保工の内面に沿ってアーチ状のプレキャスト覆工を設置する覆工部材設置工程と、
前記プレキャスト覆工と前記地山面との隙間に充填材を充填する充填工程と、を備えるトンネル施工方法であって、
前記支保工程では、鋼製支保工を建て込むとともに吹付コンクリートを吹き付け、
前記覆工部材設置工程では、充填材注入時の圧力による前記プレキャスト覆工の変形を抑制するコンクリート製の柱状部材からなる形状保持材を、一端を前記鋼製支保工の内面に当接させるとともに他端を前記プレキャスト覆工の外面に当接させた状態で配設することを特徴とする、トンネル施工方法。
An excavation process to excavate the ground;
A shoring process in which the ground surface exposed by excavation of the ground is closed with shoring;
a lining member installation step of installing an arch-shaped precast lining along the inner surface of the shoring;
A tunnel construction method comprising a filling step of filling a gap between the precast lining and the ground surface with a filler,
In the shoring process, steel shoring is erected and shotcrete is sprayed,
In the lining member installation step, one end of a shape-retaining material made of a concrete columnar member that suppresses deformation of the precast lining due to pressure during injection of filler material is brought into contact with the inner surface of the steel shoring. A tunnel construction method, characterized in that the other end of the precast lining is placed in contact with the outer surface of the precast lining.
JP2020199293A 2020-12-01 2020-12-01 Tunnel lining structure and tunnel construction method Active JP7444763B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020199293A JP7444763B2 (en) 2020-12-01 2020-12-01 Tunnel lining structure and tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020199293A JP7444763B2 (en) 2020-12-01 2020-12-01 Tunnel lining structure and tunnel construction method

Publications (2)

Publication Number Publication Date
JP2022087385A JP2022087385A (en) 2022-06-13
JP7444763B2 true JP7444763B2 (en) 2024-03-06

Family

ID=81975668

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020199293A Active JP7444763B2 (en) 2020-12-01 2020-12-01 Tunnel lining structure and tunnel construction method

Country Status (1)

Country Link
JP (1) JP7444763B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116517588B (en) * 2023-04-25 2023-10-13 广东水电二局股份有限公司 Construction method for preventing tunnel lining vault from falling out and falling out preventing device thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001090487A (en) 1999-09-20 2001-04-03 Ohbayashi Corp Tunnel lining work
JP2003227296A (en) 2002-02-05 2003-08-15 Nippon Concrete Ind Co Ltd Tunnel repairing construction method and tunnel repairing plate
JP2004324139A (en) 2003-04-23 2004-11-18 Ando Corp Construction method of tunnel timbering
JP2007321450A (en) 2006-06-01 2007-12-13 Public Works Research Institute Installation structure of lining pc slab and its pc slab
JP2015214853A (en) 2014-05-12 2015-12-03 大成建設株式会社 Tunnel lining method
JP2016142088A (en) 2015-02-04 2016-08-08 大成建設株式会社 Tunnel lining concrete mold support structure
JP2017031035A (en) 2015-08-06 2017-02-09 鹿島建設株式会社 High fluidity concrete and installation method of coated concrete using the same
JP2022021003A (en) 2020-07-21 2022-02-02 清水建設株式会社 PCa BOARD SUPPORT DEVICE AND TUNNEL LINING CONSTRUCTION METHOD

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001090487A (en) 1999-09-20 2001-04-03 Ohbayashi Corp Tunnel lining work
JP2003227296A (en) 2002-02-05 2003-08-15 Nippon Concrete Ind Co Ltd Tunnel repairing construction method and tunnel repairing plate
JP2004324139A (en) 2003-04-23 2004-11-18 Ando Corp Construction method of tunnel timbering
JP2007321450A (en) 2006-06-01 2007-12-13 Public Works Research Institute Installation structure of lining pc slab and its pc slab
JP2015214853A (en) 2014-05-12 2015-12-03 大成建設株式会社 Tunnel lining method
JP2016142088A (en) 2015-02-04 2016-08-08 大成建設株式会社 Tunnel lining concrete mold support structure
JP2017031035A (en) 2015-08-06 2017-02-09 鹿島建設株式会社 High fluidity concrete and installation method of coated concrete using the same
JP2022021003A (en) 2020-07-21 2022-02-02 清水建設株式会社 PCa BOARD SUPPORT DEVICE AND TUNNEL LINING CONSTRUCTION METHOD

Also Published As

Publication number Publication date
JP2022087385A (en) 2022-06-13

Similar Documents

Publication Publication Date Title
EP3382143B1 (en) Tunnel construction method using pre-support and post-support and apparatus suitable for same
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
JP6636773B2 (en) Construction structure and construction method of tunnel lining body
JP5308116B2 (en) How to build a tunnel
CN110656954B (en) Tunnel collapse processing method for convergent collapsed cavity
CN205742213U (en) Foundation pit supporting construction
JP5055249B2 (en) Multiple tunnel construction method and multiple tunnel structure
CN108868834B (en) Temporary support device for tunnel arch wall primary support intrusion limit arch changing construction
JP7178243B2 (en) Tunnel lining construction method
CN109057801B (en) Construction method for excavating and supporting double-side-wall pilot tunnel composite step type large-section tunnel
CN109488342A (en) A kind of hoop shell perfusion type flexibility for roadway support, which allows, pressure lining cutting and applies method
JP7444763B2 (en) Tunnel lining structure and tunnel construction method
KR100546998B1 (en) Construction method of temporary apparatus of thnnel for direct digging
CN108547635B (en) Surrounding rock reinforcing method for tunnel with pipe lining and spray anchor support alternately
JPH07197792A (en) Tunnel lining structure, lining device and construction method
CN212716667U (en) Steel pipe concrete and sprayed concrete rigid combined structure tunnel supporting system
JP2016044494A (en) Construction method of foundation
KR100941437B1 (en) 2 arch tunnel construction method for upper girder void proofing and efficient construction
CN109723465B (en) Tube sheet centralizing method for TBM tunnel boring machine
JP7146607B2 (en) Joint structure between pile and superstructure, construction method for joint structure, and structure
CN114086982A (en) High ground stress fragmentation surrounding rock deformation construction control method
CN102937024A (en) Digging and building method for water-proof gate chamber
LU502525B1 (en) A Method for Centralizing TBM Segments
CN110318419A (en) The construction method of the lining door opening supporting of underpass type piping lane one
CN214301821U (en) High pile cap pouring structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230124

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230928

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231010

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231212

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240118

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240213

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240222

R150 Certificate of patent or registration of utility model

Ref document number: 7444763

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150