JPS5912839B2 - Tunnel filler lining construction method - Google Patents

Tunnel filler lining construction method

Info

Publication number
JPS5912839B2
JPS5912839B2 JP50016041A JP1604175A JPS5912839B2 JP S5912839 B2 JPS5912839 B2 JP S5912839B2 JP 50016041 A JP50016041 A JP 50016041A JP 1604175 A JP1604175 A JP 1604175A JP S5912839 B2 JPS5912839 B2 JP S5912839B2
Authority
JP
Japan
Prior art keywords
segment
lining
tunnel
segments
filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP50016041A
Other languages
Japanese (ja)
Other versions
JPS5190725A (en
Inventor
稔 山本
富男 木川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KUBOTA TETSUKO KK
Original Assignee
KUBOTA TETSUKO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUBOTA TETSUKO KK filed Critical KUBOTA TETSUKO KK
Priority to JP50016041A priority Critical patent/JPS5912839B2/en
Publication of JPS5190725A publication Critical patent/JPS5190725A/ja
Publication of JPS5912839B2 publication Critical patent/JPS5912839B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明はトンネルの充填材覆工施工方法に関するもので
ある。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for lining a tunnel with a filler material.

トンネルの施工にあたっては、RTM(RockTun
heling Machine)工法、発破工法、シー
ルド工法など各種トンネル工法によって所定の断面形状
のトンネル坑を掘削し、支保工として鋼アーチ支保工や
セグメントを用いて地山を支保し、この支保工の内側か
らコンクリート等の充填材で覆工することにより永久覆
工が形成される。
When constructing tunnels, RTM (RockTun
A tunnel shaft with a predetermined cross-sectional shape is excavated using various tunneling methods such as (heiling machine) method, blasting method, shield method, etc., and the ground is supported using steel arch supports or segments as support, and from the inside of this support. A permanent lining is formed by lining with a filler material such as concrete.

尚、前記支保工としてセグメントを用いた場合には、こ
のセグメント覆工それ自体を永久覆工とされる場合が多
いが、この場合セグメント覆工と地山との間に充填材に
よる裏込め覆工が行なわれる。
In addition, when segments are used as the shoring, the segment lining itself is often considered to be a permanent lining, but in this case, backfilling with filler is used between the segment lining and the ground. construction will be carried out.

さらに、支保材としてセグメントを用いると共にセグメ
ント覆工と地山との間に確保されたほぼ均等な間隙に充
填材を充填し、硬化結合したこの充填材覆工を支保工あ
るいはそのまへ永久覆工とする工法も提案されている。
Furthermore, while using segments as supporting materials, filling material is filled into the almost uniform gaps between the segment lining and the ground, and this hardened and bonded filler lining can be used as shoring or as a permanent covering. Construction methods have also been proposed.

本発明はかかるトンネルの充填材覆工の施工時に、地山
がらの湧水を速やかにトンネル外に排出することのでき
る充填材覆工施工方法を提案するものである。
The present invention proposes a filling material lining construction method that can quickly drain spring water from the ground to the outside of the tunnel when constructing such a tunnel filling material lining.

以下、本発明の一実施例として、セグメントを支保材と
して用いたRTM工法において充填材覆工を支保工ある
いはそのま〜永久覆工とするトンネル構築の場合を例に
とり、その詳細を図面に基づいて説明する。
Hereinafter, as an example of the present invention, we will take as an example the case of tunnel construction in which the filler lining is used as shoring or permanent to permanent lining in the RTM construction method using segments as supporting materials, and the details will be explained based on the drawings. I will explain.

まずPTMにより地山4にトンネル坑1を掘進し、該P
TMによって切羽が前進すれば、その後方のトンネル下
部位置にインバートセグメント5を敷く。
First, tunnel pit 1 is excavated into the ground 4 using PTM, and the PTM
When the face moves forward due to TM, the invert segment 5 is laid at the lower part of the tunnel behind it.

該インバートセグメント5はコンクリート製であり、後
述する鉄板6と、支保工および型枠として組立てるセグ
メント7の支台となると共に、該インバートセグメント
5の上にレール(図示せず)を敷く場合の枕木の代用と
なる。
The invert segment 5 is made of concrete and serves as a support for a steel plate 6 to be described later and a segment 7 to be assembled as shoring and formwork, and also as a sleeper when a rail (not shown) is laid on the invert segment 5. It is a substitute for

こうして、インバートセグメント5の敷設が終れば、そ
のレベルを調整してインバートセグメント5の下部にコ
ンクリートを裏込し、インバートセグメント5の位置を
固定する。
When the invert segment 5 has been laid in this way, its level is adjusted and the lower part of the invert segment 5 is filled with concrete, thereby fixing the position of the invert segment 5.

尚、インバートセグメント50レベル調整にはクサビを
使用するのが適当である。
Note that it is appropriate to use a wedge to adjust the level of the invert segment 50.

次に、インバートセグメント5の上部側に、その両側位
置からセグメント7を順次ボルト継手8を用いてアーチ
状に組上げ、頂点近傍で閉合してセグメント覆工9を構
成する3この場合、セグメント7を組上げてゆく時、該
セグメント7の外側位置に薄い鉄板(トタン板等)6を
置き、後述する支持具10によって該鉄板6を地山4に
接当する状態に、且つ該鉄板6とセグメント7との間に
一定の空隙11が形成されるよう抑圧保持せしめ、セグ
メント7取外立てに伴い、同様にして鉄板6をセグメン
ト7の外部にアーチ状に組立てる。
Next, the segments 7 are sequentially assembled into an arch shape on the upper side of the invert segment 5 from both sides using bolt joints 8, and closed near the apex to form the segment lining 9. In this case, the segments 7 are When assembling, a thin iron plate (such as a galvanized iron plate) 6 is placed outside the segment 7, and the iron plate 6 is brought into contact with the ground 4 by a support 10, which will be described later, and the iron plate 6 and the segment 7 are When the segment 7 is removed, the iron plate 6 is similarly assembled in an arch shape outside the segment 7.

こうして、一回の覆工コンクリートを打設するに適当な
長さ、例えば20m程度の長さまでトンネル長手方向に
順次セグメント7および鉄板6の組立てを行なう。
In this way, the segments 7 and the steel plates 6 are sequentially assembled in the longitudinal direction of the tunnel to a length suitable for one time of pouring concrete lining, for example, about 20 m.

尚、インバートセグメント5とこれに連結されるセグメ
ント7の間に、打設した覆工コンクリートが流出しない
ように、第4図の如くシール材12を介してセグメント
Tをインバートセグメント5にねじ止めしておくのが良
い。
In addition, in order to prevent the cast lining concrete from flowing out between the invert segment 5 and the segment 7 connected thereto, the segment T is screwed to the invert segment 5 through a sealing material 12 as shown in Fig. 4. It's good to keep it.

かくして適当な長さに形成されたセグメント覆工9の先
端側面に、地山4表面とセグメント覆工周縁にわたる幅
を有する溝用セグメント13を、第6図に示す様にイン
バートセグメント5両側上面から組み上げて溝部セグメ
ント覆工14を構成する。
A groove segment 13 having a width that spans the surface of the ground 4 and the periphery of the segment lining is placed on the side surface of the tip of the segment lining 9 formed to an appropriate length from the upper surface of both sides of the invert segment 5 as shown in FIG. The groove segment lining 14 is constructed by assembling the groove segment lining 14.

この溝部セグメント覆工14は、前記溝3を形成する型
枠として機能すると共に空隙11に打設した充填材がト
ンネル前方に流出するのを防ぐ堰板としても機能する。
The groove segment lining 14 functions as a formwork for forming the groove 3, and also functions as a weir plate to prevent the filler cast in the gap 11 from flowing out to the front of the tunnel.

従ってこの溝用セグメント13とセグメント7との間に
もシール材を介在せしめることが望ましい。
Therefore, it is desirable to interpose a sealing material between the groove segment 13 and the segment 7 as well.

そして溝部セグメント覆工14の組立てが終れば引続き
前記と同様にセグメント覆工9を構築し、こうして切羽
が前進して切羽の作業との競合がなくなれば、できるだ
け早急に空隙11に硬化性充填材であるコンクリートを
流し込むか、又は非硬化性充填材である砂利、砕石又は
ズリを注入した後結合剤としてセメントミルクなどを注
入して裏込めを行なう。
Once the groove segment lining 14 has been assembled, the segment lining 9 is constructed in the same manner as described above, and once the face advances and there is no competition with the work on the face, fill the void 11 with hardening filler as soon as possible. After pouring concrete, or injecting non-hardening filler such as gravel, crushed stone, or waste, backfilling is performed by injecting cement milk or the like as a binder.

この際、地山4側に湧水があると、水が前記充填材側に
流入してその硬化作用を妨げたり、充填材を一部流し去
るように働いたりするが、トンネル1内表面に鉄板6を
配設しているので、地山4側から流出する水は空隙11
内に進入することなく、鉄板6外面に沿って流れ落ちる
At this time, if there is spring water on the side of the ground 4, the water flows into the filling material side and prevents its hardening action or works to wash away part of the filling material. Since the iron plate 6 is installed, water flowing out from the ground 4 side flows through the void 11.
It flows down along the outer surface of the iron plate 6 without entering the inside.

一方、インバートセグメント5には、上面中央部にトン
ネル坑1長手方向に沿う排水溝15が形成されていると
共に、下面に、前記排水溝15の底面に達する上下方向
に沿う取水孔16が穿設されてい−るので、前記流下し
た水は取水孔16から排水溝15へと移行し、これによ
って速やかにトンネル外に排出される。
On the other hand, in the invert segment 5, a drainage groove 15 is formed in the center of the upper surface along the longitudinal direction of the tunnel shaft 1, and a water intake hole 16 is bored in the lower surface along the vertical direction reaching the bottom surface of the drainage groove 15. Therefore, the flowing water moves from the water intake hole 16 to the drain groove 15, and is thereby quickly discharged outside the tunnel.

この様にして地山4側からの水の影響を除外した状態で
、裏込めした充填材が硬化結合して充填材覆工2となる
In this way, with the influence of water from the ground 4 side excluded, the backfilled filler is hardened and bonded to form the filler lining 2.

この充填材覆工2が支保工あるいは永久覆工としての所
定の強度が得られると、第2図及び第3図に示す様に支
持具10を埋込みにしたま〜セグメント7および溝用セ
グメント13を取外し、該充填材覆工2で地山4の荷重
を支保する。
When this filler lining 2 has a predetermined strength as a shoring or a permanent lining, the supports 10 are embedded in the segments 7 and groove segments 13 as shown in FIGS. 2 and 3. The filler lining 2 supports the load of the earth 4.

尚、充填材覆工2は鉄板6によって地山4に対して区画
されているので、充填材覆工2と地山4との密着を良く
する意味で鉄板6と地山4との間にセメントミルクの注
入を行なっても良い。
In addition, since the filler lining 2 is separated from the ground 4 by the iron plate 6, there is a gap between the iron plate 6 and the ground 4 in order to improve the adhesion between the filler lining 2 and the ground 4. Cement milk may also be injected.

前記セグメント7取外し後、前記充填材覆工2をそのま
へ永久覆工とすることもできるが、地山4の荷重が大き
い場合にはその内側に永久覆工としてのコンクリート巻
立てを行なえば良く、このコンクリート巻立ては、例え
ばトンネル全長にわたって充填材覆工2を形成した後に
行なっても良く、セグメント7を撤去しながら遂次行な
っても良い。
After removing the segments 7, the filler lining 2 can be used as a permanent lining, but if the load of the ground 4 is large, concrete can be placed inside it as a permanent lining. This concrete laying may be carried out, for example, after the filler lining 2 has been formed over the entire length of the tunnel, or it may be carried out sequentially while the segments 7 are being removed.

他方、取外されたセグメント7及び溝用セグメント13
は、RTM後端部でのセグメント覆工9及び溝部セグメ
ント覆工14の組立てに順次循環使用される。
On the other hand, the removed segment 7 and the groove segment 13
are sequentially used in circulation to assemble the segment lining 9 and the groove segment lining 14 at the rear end of the RTM.

すなわち、本実施例においては、セグメント7及び溝用
セグメント13は充填材覆工2の覆工型枠として使用さ
れるのである。
That is, in this embodiment, the segments 7 and the groove segments 13 are used as a lining formwork for the filler lining 2.

この様にして形成された充填材覆工2には、適当長さ毎
に地山4表面に達する周方向溝3が設けられることにな
るため、前記鉄板6が長期間経過して腐食し、充填材覆
工2の外周面が滑らかでなくなってこの外周面に沿って
湧水が流下しにくくなった場合でも、その水はトンネル
長手方向に流れて前記溝3を通って充填材覆工2内に導
かれるためトンネル外に排出することができる。
Since the filler lining 2 formed in this way is provided with circumferential grooves 3 reaching the surface of the ground 4 at appropriate lengths, the iron plate 6 may corrode over a long period of time. Even if the outer peripheral surface of the filler lining 2 is no longer smooth and it becomes difficult for spring water to flow down along this outer peripheral surface, the water will flow in the longitudinal direction of the tunnel and pass through the grooves 3 to the filler lining 2. Since it is guided inside, it can be discharged outside the tunnel.

なお本実施例のように溝3を形成した場合、この溝3部
分において、第1図の如く互に隣接する充填材覆工2,
2を溝3をまたがる結合部材17で強固に結合しておく
のが望ましく、さらに充填材覆工2及び結合部材17の
内側に内装コンクリート2aを巻き立てると良い。
Note that when the groove 3 is formed as in this embodiment, in the groove 3 portion, the filler lining 2, which is adjacent to each other as shown in FIG.
2 are preferably firmly connected by a connecting member 17 that spans the groove 3, and it is also preferable to roll interior concrete 2a inside the filler lining 2 and the connecting member 17.

また、この内装コンクリ−)2aあるいは前記の様にコ
ンクリート巻立てによる永久覆工を行なう際には、この
コンクリート1に、溝3に対応する取水孔を設けてトン
ネル覆工内に導く様にしておけば良い。
In addition, when performing this interior concrete 2a or a permanent lining by concrete lining as described above, water intake holes corresponding to the grooves 3 are provided in the concrete 1 to guide it into the tunnel lining. Just leave it there.

次に、セグメント7および支持具10の具体実施例につ
いて説明すると、セグメント7は第7図に示す様に、セ
グメント同士を締結組立するための締結孔18の他に、
前記支持具10を挿通させて取付けるため、セグメント
7の外面側に凹入した適数の凹陥部19と、その中央位
置に穿設した挿通孔20とを有しており、且つ適宜裏込
め注入孔21が穿設されている。
Next, a specific example of the segment 7 and the support 10 will be described. As shown in FIG. 7, the segment 7 has a fastening hole 18 for fastening and assembling the segments, and
In order to insert and attach the support 10, the segment 7 has an appropriate number of recesses 19 recessed on the outer surface side and an insertion hole 20 bored in the center thereof, and back-filling is performed as appropriate. A hole 21 is bored.

また、支持具10は、第3図に示す様に前記凹陥部19
に嵌入するナツト部材22と、該ナツト部材22に螺合
された押付けねじ軸23と、該押付けねじ軸23の先端
に装着したスチールパイプ(内部にコンクリートが詰め
られている)24および接当部材25とから成る。
Further, the support 10 has the recessed portion 19 as shown in FIG.
A nut member 22 that is fitted into the nut member 22, a pressing screw shaft 23 that is screwed into the nut member 22, a steel pipe (with concrete filled inside) 24 attached to the tip of the pressing screw shaft 23, and a contact member. It consists of 25.

そして、セグメント7の外面側から押付けねじ軸23の
一部を挿通孔20に挿入せしめた状態で、ナツト部材2
2を凹陥部19に嵌入させ、しかるのちナツト部材22
とセグメント7とを該セグメント7の内側からボルト2
6等で締結する。
Then, with a part of the pressing screw shaft 23 inserted into the insertion hole 20 from the outer surface side of the segment 7, the nut member 2 is inserted.
2 into the recessed part 19, and then the nut member 22
and segment 7 from the inside of segment 7.
Concluded with 6th prize.

そして、接当部材20によって鉄板6を地山4側に押し
て空隙11を保つのである。
Then, the abutment member 20 pushes the iron plate 6 toward the ground 4 to maintain the gap 11.

尚、充填材覆工2を行なったあと、ボルト26を取外す
ことにより支持具10を埋込んだまNセグメント7を取
除くことができる。
Incidentally, after performing the filler lining 2, by removing the bolts 26, the N segment 7 can be removed with the support 10 still embedded.

また、溝用セグメント13としては、第8図乃至第10
図に示すものが適当である。
In addition, as the groove segment 13, FIGS.
The one shown in the figure is appropriate.

すなわち、該溝用セグメント13は、溝部セグメント覆
工14の頂点を形成する第8図の様なセグメンN3aと
、溝部セグメント覆工14の両側部を形成する第9図の
様なセグメンN3bと、インバートセグメント5に連結
される第10図の様なセグメント13cとから成り、こ
のうちセグメント13aは両側部に積上げてきたセグメ
ン)13b同士を連結するために両側に雄部27を形成
され、またセグメン)13bは一方に開口された雌部2
8を、他方に雄部29を形成され、またセグメント13
cには一方にセグメン)13bとの嵌合用雌部30を、
他方にはインバートセグメント5と連結するための締結
孔31が穿設されている。
That is, the groove segment 13 includes a segment N3a as shown in FIG. 8 that forms the apex of the groove segment lining 14, and a segment N3b as shown in FIG. 9 that forms both sides of the groove segment lining 14. The segment 13a is connected to the invert segment 5 as shown in FIG. ) 13b is the female part 2 which is open on one side.
8, a male portion 29 is formed on the other side, and a segment 13 is formed on the other side.
c has a female part 30 for fitting with the segment) 13b on one side,
A fastening hole 31 for connecting with the invert segment 5 is bored on the other side.

そしてインバートセグメント50両側にセグメン)13
cを固定したのち、セグメン)13bを雄雌嵌合によっ
て組立て、しかる後セグメント13aによって両側のセ
グメンN3bの連結を行ない溝部セグメント覆工14を
形成するのである。
and invert segment 50 segments on both sides) 13
After fixing N3b, the segments 13b are assembled by male and female fitting, and then the segments N3b on both sides are connected by the segments 13a to form the groove segment lining 14.

以上説明したように本発明によれば、トンネル内表面に
鉄板を配設しているので、地山側から流出する水は鉄板
外面に沿って流れ落ち、またインバートセグメントには
排水溝及び取水孔が穿設されており、従って前記流下し
た水は取水孔から排水溝へと移行し、これによってトン
ネル外に速やかに排出されるので、セグメントを用いた
充填材覆工の施工に際して、地山側に湧水があっても、
水が充填材側に流入してその硬化作用を妨げたり、充填
材を一部流し去るように働いたりすることがなく、また
充填材やセグメントへの湧水圧の作用を減することがで
きる。
As explained above, according to the present invention, since the iron plate is disposed on the inner surface of the tunnel, water flowing out from the ground side flows down along the outer surface of the iron plate, and the invert segment is provided with drainage channels and water intake holes. Therefore, the flowing water moves from the water intake hole to the drainage ditch, where it is quickly discharged outside the tunnel. Therefore, when constructing the filler lining using segments, it is possible to prevent water from springing up on the ground side. Even if there is,
Water does not flow into the filling material side and interfere with its hardening action or act to partially wash away the filling material, and the action of spring water pressure on the filling material and segments can be reduced.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の一実施態様を示し、第1図は概略構成を
示す全体縦断面図、第2図はインバートセグメント周り
の構成図、第3図は充填材覆工およびセグメント覆工を
説明する構成図、第4図はインバートセグメントとセグ
メントとの連結部を示す斜視図、第5図は充填材覆工部
分のセグメント覆工の配置状態を示す横断面図、第6図
は溝部セグメント覆工の配置状態を示す横断面図、第7
図a 、bはセグメントの表裏の斜視図、第8図乃至第
10図は溝用セグメントの各種構成を示す斜視図である
。 1・・・・・・トンネル坑、2・・・・・・充填材覆工
、4・・・・・・地山、5・・・・・・インバートセグ
メント、6・・・・・・鉄板、7・・・・・・セグメン
ト、9・・・・・・セグメント覆工、10・・・・・・
支持具、11・・・・・・空隙、13.13a=13b
s13c・・・・・・溝用セグメント、14・・・・・
・溝部セグメント覆工、15・・・・・・排水溝、16
・・・・・・取水孔。
The drawings show one embodiment of the present invention; FIG. 1 is an overall vertical cross-sectional view showing a schematic configuration, FIG. 2 is a configuration diagram around an invert segment, and FIG. 3 explains a filler lining and a segment lining. 4 is a perspective view showing the connection between the invert segments and the segments, FIG. 5 is a cross-sectional view showing the arrangement of the segment lining in the filler lining part, and FIG. 6 is the groove segment lining. 7th cross-sectional view showing the arrangement of
Figures a and b are front and back perspective views of the segment, and Figures 8 to 10 are perspective views showing various configurations of the groove segment. 1...Tunnel pit, 2...Filling material lining, 4...Ground, 5...Invert segment, 6...Iron plate , 7... Segment, 9... Segment lining, 10...
Support, 11...Gap, 13.13a=13b
s13c...Groove segment, 14...
・Gutter segment lining, 15...Drainage ditch, 16
・・・・・・Water intake hole.

Claims (1)

【特許請求の範囲】[Claims] 1 トンネル坑の内周面下部位置に、上面にトンネル坑
長手方向に沿う排水溝が全長にわたって形成されかつ下
面には前記排水溝の底面に達する上下方向に沿う取水孔
が穿設されたインバートセグメントを、トンネル坑長手
方向に連続的に敷設し、これら各インバートセグメント
の上部側に、その両側位置から順次セグメントを接続し
てアーチ状に組上げながら地山に鉄板を接当させてこの
鉄板を前記セグメントに取付けた支持具により抑圧支持
し、セグメント及び鉄板の組立後、前記セグメントと鉄
板との間隙に充填材を充填することを特徴とするトンネ
ルの充填材覆工施工方法。
1. An invert segment in which a drainage groove extending in the longitudinal direction of the tunnel shaft is formed along the entire length of the upper surface at a lower position on the inner peripheral surface of the tunnel shaft, and a water intake hole extending in the vertical direction reaching the bottom surface of the drainage trench is bored in the lower surface. are laid continuously in the longitudinal direction of the tunnel, and the segments are sequentially connected from both sides of each invert segment to form an arch, and a steel plate is brought into contact with the ground. 1. A method for lining a tunnel with a filler material, which comprises suppressing and supporting the segment with a support attached to the segment, and after assembling the segment and the steel plate, filling the gap between the segment and the steel plate with a filler material.
JP50016041A 1975-02-06 1975-02-06 Tunnel filler lining construction method Expired JPS5912839B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP50016041A JPS5912839B2 (en) 1975-02-06 1975-02-06 Tunnel filler lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP50016041A JPS5912839B2 (en) 1975-02-06 1975-02-06 Tunnel filler lining construction method

Publications (2)

Publication Number Publication Date
JPS5190725A JPS5190725A (en) 1976-08-09
JPS5912839B2 true JPS5912839B2 (en) 1984-03-26

Family

ID=11905479

Family Applications (1)

Application Number Title Priority Date Filing Date
JP50016041A Expired JPS5912839B2 (en) 1975-02-06 1975-02-06 Tunnel filler lining construction method

Country Status (1)

Country Link
JP (1) JPS5912839B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49112435A (en) * 1973-02-26 1974-10-26

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49112435A (en) * 1973-02-26 1974-10-26

Also Published As

Publication number Publication date
JPS5190725A (en) 1976-08-09

Similar Documents

Publication Publication Date Title
CA1217349A (en) Engineering of reinforced concrete structures, such as tunnels, underpasses and the like, and precast concrete elements used in said engineering processes
KR100701633B1 (en) Load dispersing plate for supporting central part of a twin tunnel and a construction method of a twin tunnel using the load dispersing plate
JP4881555B2 (en) Construction method of underground structure
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
CN113529752A (en) Construction method for ecologically treating tunnel entrance and exit structure by using foam concrete
JP3125288B2 (en) Construction method of tunnel invert and precast plate for tunnel invert
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
JPS5912839B2 (en) Tunnel filler lining construction method
KR102243586B1 (en) Two-side semicircle arch type leading pipe and structure of non-excavation type tunnel using thereof and method of constructing thereof
JPH0510596U (en) Concrete box for underground structure
CN109763518A (en) A kind of construction method of basement post-pouring zone
JP2693028B2 (en) Construction method of human hole in middle of pipeline
CN216275754U (en) Foam concrete ecological treatment tunnel inlet and outlet structure
KR102243585B1 (en) Structure of constructing non-excavation type tunnel using steel pipe loof and leading pipe
JP4079749B2 (en) Rehabilitation method for existing manhole
JPH0477764B2 (en)
JP3332507B2 (en) How to build underground structures
JPS5818519B2 (en) Jiyu Tenzai Sekidomekousou
JP4319122B2 (en) Branch and junction structure of branching tunnel and its construction method
JPS6124623Y2 (en)
JP2023165499A (en) Method for placing lining concrete for tunnel
JPS6124627Y2 (en)
JP3178357B2 (en) Construction method of large section tunnel
JP3352951B2 (en) Installation method of invert and underground drainage in mountain tunnel
JPH0574676B2 (en)