JPS58150631A - Construction work of underground structure - Google Patents

Construction work of underground structure

Info

Publication number
JPS58150631A
JPS58150631A JP57033042A JP3304282A JPS58150631A JP S58150631 A JPS58150631 A JP S58150631A JP 57033042 A JP57033042 A JP 57033042A JP 3304282 A JP3304282 A JP 3304282A JP S58150631 A JPS58150631 A JP S58150631A
Authority
JP
Japan
Prior art keywords
foundation
joint
load
wall
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57033042A
Other languages
Japanese (ja)
Inventor
Seitaro Ebi
成太郎 海老
Hideo Iijima
飯島 英雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP57033042A priority Critical patent/JPS58150631A/en
Publication of JPS58150631A publication Critical patent/JPS58150631A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To raise the accuracy and efficiency of construction work by a method in which a structure oonsisting of pillars, wale and beams is formed in a wall- shaped trench excavated underground so that it can share the pressure of surround ground and water pressure and also the numbers of temporary materials are reduced. CONSTITUTION:In a wall-shaped trench 1 excavated underground and subjected to a mud-water treatment in advance, pillars 2 are fixed at given intervals by a temporary fitting tool 24, a proper number of beams 4 are laid, a strength wall 3 is inserted and joined through a T-shaped guide rail and coupler 12 and a T-shaped tool 13, the ground inside the structure is excavated to a given flooring face 8, a foundation slab (not illustrated) is set and joined with a foundation beam 4', and a floor slab (not illustrated) is laid and connected with the beam 4. Thus, the structure can be constructed with a high accuracy and also can withstand surround soil pressure and water pressure, and the numbers of temporary structures can be reduced.

Description

【発明の詳細な説明】 この発明は、プレキャストコンクリート部材を用いて柱
材、梁材、耐力壁材及び床材等を形成して地下構造物の
構築工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing an underground structure by forming pillar materials, beam materials, load-bearing wall materials, floor materials, etc. using precast concrete members.

従来の地下構造物の構築工法は、構築中に周囲の地盤の
土圧、水圧を負担させる山止め支保工や掘削土砂の搬出
のための乗入れ構台等の多くの仮設構造物を構築する必
要があり、またケーソン工法では、掘削作業が地盤の状
態に影響され、施工能率上問題があり、多(の工費と工
期を必要とした。更にプレキャストコンクリート部材を
接合する場合、掘削空間において作業員が接合部付近で
接合作業を行なったり、接合作業は泥水中で行なうため
泥水が接合部に付着したり、打設するコンクリートやモ
ルタルに混入する問題があった。
Conventional construction methods for underground structures require the construction of many temporary structures, such as pile shoring to bear the earth pressure and water pressure of the surrounding ground, and a platform for transporting excavated soil. In addition, with the caisson construction method, the excavation work was affected by the ground condition, which caused problems in terms of construction efficiency and required a large amount of construction cost and construction time.Furthermore, when joining precast concrete members, workers were required to work in the excavation space. Since the joining work is performed near the joint or in muddy water, there are problems with muddy water adhering to the joint or getting mixed into the concrete or mortar being poured.

この発明は、上述の問題点を解決し、本体構造物の架構
精度と施工性との向上を図った地下構造物の構築工法を
提供するものである。
The present invention solves the above-mentioned problems and provides a method for constructing an underground structure that improves the structural precision and workability of the main structure.

次に、この発明の実施例を図面に基づいて説明する。第
1図及び第2図は、この発明の構築工法を示したもので
ある。図において、あらかじめ掘削し、泥水処理された
壁状溝1内に所定間隔を設けて柱材2を仮固定治具24
によって固定し、柱材2間に適宜数の梁材4を架は渡し
、接合し、更に構築物外周部に耐力壁材3を挿入し、耐
力壁材3間及び耐力壁材3と梁材4を接合し、連続壁を
有した架構体を構築した後、壁状溝1内に泥水固化処理
を施して所定強度を有する泥水固化体5にょる止水壁を
形成させ、周囲の地盤6からの土庄及び水圧に耐え得る
架構体内の土砂7を所定の床付は面8まで掘削する。次
に、床付は面8上に基礎スラブ材9を設置し、基礎梁材
47と接合し床材]0を梁材4に架構し接合する。
Next, embodiments of the present invention will be described based on the drawings. FIGS. 1 and 2 show the construction method of this invention. In the figure, a temporary fixing jig 24 is used to fix the pillars 2 at predetermined intervals in the wall groove 1 that has been excavated in advance and treated with muddy water.
The appropriate number of beams 4 are passed between the pillars 2 and joined, and the load-bearing wall materials 3 are inserted into the outer periphery of the structure, and the load-bearing wall materials 3 and the load-bearing wall materials 3 and the beam materials 4 are After joining and constructing a frame structure having continuous walls, a muddy water solidification treatment is performed in the wall-shaped groove 1 to form a water-stop wall made of the muddy water solidified body 5 having a predetermined strength, and from the surrounding ground 6. The earth and sand 7 inside the frame structure, which can withstand the soil and water pressure, is excavated to a predetermined floor surface 8. Next, a foundation slab material 9 is installed on the surface 8 and joined to the foundation beam material 47, and the floor material]0 is framed and joined to the beam material 4.

この発明において、梁材4の架橋時には柱材2をガイド
レールとし、耐力壁材3の架構時には主として梁材4を
ガイドレールとすることにより構築される。第3図は、
柱材2と梁材4と耐力壁材3との継手部の水平断面図で
あり、図中の右半分は組立中を示し、左半分は組立後の
充填材を充填した状態を示したものである。図において
、柱材2と梁材4と耐力壁材3のそれぞれの接合面の所
定位置に適宜数のT型ガイドレール兼用継手材12を固
着し、対応した位置に同数のT型溝13を設けて係合せ
しめるとともに、T型ガイドレール兼用継手材12には
アンカー筋14と連結せしめ、またT型溝13には圧送
ホース15に連結し、かつ各部材の接合部の目地部11
の全周部には弾性ガスケット16により密閉せしめてお
き、梁材4及び耐力壁材3を所定深さまで降下させた後
、圧送ボース15より洗浄水を圧送して各接合部を洗浄
して圧送ホース15より充填材を充填すればよい。
In this invention, the pillars 2 are used as guide rails when the beams 4 are bridged, and the beams 4 are mainly used as the guide rails when the load-bearing wall materials 3 are constructed. Figure 3 shows
This is a horizontal cross-sectional view of the joint between the column material 2, the beam material 4, and the load-bearing wall material 3. The right half of the figure shows the state during assembly, and the left half shows the state filled with filler after assembly. It is. In the figure, an appropriate number of T-shaped guide rail joints 12 are fixed at predetermined positions on the joint surfaces of the pillars 2, beams 4, and load-bearing wall materials 3, and the same number of T-shaped grooves 13 are installed at corresponding positions. At the same time, the T-shaped guide rail joint material 12 is connected to the anchor bar 14, the T-shaped groove 13 is connected to the pressure feed hose 15, and the joint part 11 of the joint part of each member is connected to the T-shaped groove 13.
After the beam material 4 and the load-bearing wall material 3 are lowered to a predetermined depth, cleaning water is pumped through the pressure feed boss 15 to clean each joint and then the material is pressure-fed. Filling material may be filled from the hose 15.

なお、第1図及び第2図は、地業をべた基礎とした場合
の工法を示したが、杭基礎とした場合は、構造設計上柱
下部や梁下部に杭を設けることが好ましいが、接合作業
が困難である。第4図及び第5図は、基礎杭と基礎スラ
ブ材の接合方法を示したものである。図において、柱材
2と基礎梁材4+が交差する附近、または基礎梁材4の
側面附近に基礎杭17が位置するように設け、基礎杭1
7に接合するように基礎孔18の周辺に補強鋼管23を
固着した基礎スラブ材9′を使用し、基礎杭17と基礎
スラブ材9+を接合する。この際、基礎杭17の杭頭部
20及び基礎スラブ材9+にそれぞれ杭筋21とベース
筋22を配置して、接合部に充填材を充填することによ
り地盤6と確実に定着することができる。
In addition, although Figures 1 and 2 show the construction method when using earthworks as a solid foundation, if a pile foundation is used, it is preferable to install piles at the bottom of the columns or beams in terms of structural design. Difficult to join. Figures 4 and 5 show a method of joining foundation piles and foundation slab materials. In the figure, the foundation pile 17 is located near the intersection of the pillar material 2 and the foundation beam material 4+, or near the side of the foundation beam material 4, and the foundation pile 1
7, the foundation pile 17 and the foundation slab material 9+ are joined using a foundation slab material 9' with a reinforcing steel pipe 23 fixed around the foundation hole 18. At this time, by arranging pile reinforcements 21 and base reinforcements 22 on the pile head 20 of the foundation pile 17 and the foundation slab material 9+, respectively, and filling the joint with filler material, it is possible to securely anchor the foundation pile 17 to the ground 6. .

上述の通り、この発明は従来工法と比較して、次の効果
が得られる。
As mentioned above, the present invention provides the following effects compared to conventional construction methods.

(1)壁状溝を掘削して、あらかじめ基礎スラブ材と床
材を除く本体構造物を架構するので、山止め支保工や乗
入れ構第台の仮設構造物、プレキャストコンクリート部
材を組立てる仮設材等は大1】に削減でき、工費や工期
の低減がはかられる。
(1) Since a wall-like trench is excavated and the main structure excluding the foundation slab material and flooring material is erected in advance, temporary structures such as heap shoring, temporary structures for the platform for entry, and temporary materials for assembling precast concrete members, etc. can be reduced to 1], reducing construction costs and construction period.

(2)壁状溝内に柱材、耐力壁材、梁材を構築して架構
体を形成し、周囲の地盤の土工及び水圧を架構体に負担
せしめた後、内部土砂を掘削するため、工事の安全性が
はかられる。
(2) After constructing columns, load-bearing walls, and beams in the wall-shaped trench to form a frame structure and burdening the frame structure with the earthworks and water pressure of the surrounding ground, excavate the internal earth and sand. Construction safety can be measured.

(3)柱材及び梁材の接合部には、それぞれT型状のガ
イドレール兼用継手部材とT型溝を設けて係合せしめる
ことにより、柱材と梁材との接合部に生ずる諸応力を伝
達させることができ、土中内での部材接合が遠隔操作に
よって行なって高精度で構築することが可能である。
(3) By providing a T-shaped joint member that also serves as a guide rail and a T-shaped groove at the joints of the columns and beams, and engaging them, various stresses occur at the joints of the columns and beams. can be transmitted, and members can be joined in the soil by remote control, making it possible to build with high precision.

(4)柱材と梁材の接合時に各接合面に洗浄水を圧送、
洗浄した後、充填材を圧送することにより、スライムや
泥水の混入を極力少なくすることが可能となり、断面積
や鉄筋量を増す必要もなく経済的な構造設計が行なえる
(4) When joining pillars and beams, cleansing water is pumped to each joint surface,
By pumping the filler after cleaning, it is possible to minimize the amount of slime and muddy water mixed in, and an economical structural design can be achieved without the need to increase the cross-sectional area or amount of reinforcing bars.

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図は、この発明の構築工法の斜挽断面図
であり、第3図は、柱材と梁材と耐力壁材の継手部の水
平断面図であり、図の右半分は組立中を示し、左半分は
組立後を示しているものであり、第4図は、杭基礎工法
の斜視断面図であり、第5図は、第4図の接合部の拡大
図である。 1: 壁状溝 2: 柱材 3: 耐力壁材 4.4:  梁材及び基礎梁材 5: 泥水固化体 6: 地盤 7: 掘削土砂 8: 床付は面 919:  基礎スラブ材及び基礎杭接合用基礎スラブ
材 IO=  床材 11:  目地部 12: T型状ガイドレール兼用継手材13: T型溝 14:  アンカー筋 15:  圧送ホース 16:  弾性ガスケット 17:  基礎杭 18:  基礎孔 20:  杭頭部 21:  杭筋 22:  ベース筋 23:  補強鋼管 24:  仮固定治具 第  1  図 第2図 l7 第4図 第5図
Figures 1 and 2 are oblique cross-sectional views of the construction method of the present invention, and Figure 3 is a horizontal cross-sectional view of the joints of columns, beams, and load-bearing wall materials, and the right half of the figure. Figure 4 is a perspective sectional view of the pile foundation construction method, and Figure 5 is an enlarged view of the joint in Figure 4. . 1: Wall groove 2: Column material 3: Bearing wall material 4.4: Beam material and foundation beam material 5: Solidified mud 6: Ground 7: Excavation earth and sand 8: Flooring is surface 919: Foundation slab material and foundation pile Connection foundation slab material IO = Floor material 11: Joint portion 12: T-shaped guide rail joint material 13: T-shaped groove 14: Anchor bar 15: Pressure feed hose 16: Elastic gasket 17: Foundation pile 18: Foundation hole 20: Pile head 21: Pile reinforcement 22: Base reinforcement 23: Reinforcement steel pipe 24: Temporary fixing jig No. 1 Fig. 2 Fig. 7 Fig. 4 Fig. 5

Claims (1)

【特許請求の範囲】[Claims] (1)地中に掘削した壁状溝内に所定間隔を設けて柱材
を固定し、柱材間に適宜数の耐力壁材及び基礎梁材を含
む梁材を架は渡しして連続する壁状溝内に柱材、耐力壁
材及び梁材を構築することによって架構体を形成し、柱
材と耐力壁材、または柱材と梁材とにより囲まれた多角
柱状の内部土砂を所定の床付は面まで掘削し、多角柱状
の空間に基礎スラブ材及び床材を基礎梁材あるいは梁材
に架は渡しして構築することを特徴とする地下構造物の
構築工法 (2、特許請求の範囲第1項記載の梁材と柱材の接合面
、梁材と耐力壁材の接合面のそれぞれ柱材及び梁材の接
合面の所定位置に適宜数のT型状のガイドレール兼用継
手材を軸方向に設け、梁材及び耐力壁材の接合面に対応
して同数のT型溝を設けてT型状ガイドレール兼用継手
材に係合せしめ、梁材及び耐力壁材を所定位置に吊下し
た後、洗浄と充填材の充填によって結合する継手構造と
することを特徴とする地下構造物の構築工法(3)特許
請求の範囲第1項及び第2項記載の柱材と基礎梁材との
交差部位、又は基礎梁材の側面部位に所定数の杭筋を設
けた基礎杭の杭頭部を挿入可能とし、周辺に補強鋼管を
固着した基礎孔が設けられた基礎スラブ材を設置した後
、基礎孔内にベース筋を配置し充填材を充填することを
特徴とする地下構造物の構築工法
(1) Pillars are fixed at predetermined intervals in a wall groove excavated underground, and a suitable number of load-bearing wall materials and beam materials, including foundation beam materials, are passed between the pillars to form a continuous frame. A frame structure is formed by constructing columns, load-bearing walls, and beams in a wall groove, and a polygonal column-shaped interior surrounded by the columns and load-bearing walls or columns and beams is predetermined. An underground structure construction method (2, patented An appropriate number of T-shaped guide rails are also used at predetermined positions of the joint surfaces of the beam and the column and the joint of the beam and the load-bearing wall, respectively, as described in claim 1. The joint material is provided in the axial direction, and the same number of T-shaped grooves are provided corresponding to the joint surfaces of the beam material and the load-bearing wall material, and the T-shaped guide rail double-use joint material is engaged with the joint material, and the beam material and the load-bearing wall material are fixed to the specified position. A construction method for an underground structure characterized by forming a joint structure in which the joint structure is joined by washing and filling with a filler material after hanging in a position (3) The pillar material according to claims 1 and 2 and A foundation slab with a foundation hole around which a reinforcing steel pipe is fixed, into which the pile head of a foundation pile with a predetermined number of pile reinforcements can be inserted at the intersection with the foundation beam material or at the side surface of the foundation beam material. A construction method for underground structures characterized by placing base reinforcement inside the foundation hole and filling it with filler after installing the material.
JP57033042A 1982-03-04 1982-03-04 Construction work of underground structure Pending JPS58150631A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57033042A JPS58150631A (en) 1982-03-04 1982-03-04 Construction work of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57033042A JPS58150631A (en) 1982-03-04 1982-03-04 Construction work of underground structure

Publications (1)

Publication Number Publication Date
JPS58150631A true JPS58150631A (en) 1983-09-07

Family

ID=12375727

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57033042A Pending JPS58150631A (en) 1982-03-04 1982-03-04 Construction work of underground structure

Country Status (1)

Country Link
JP (1) JPS58150631A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104929152A (en) * 2015-04-03 2015-09-23 刘卡丁 Building method for underground engineering inverted construction overlapping structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104929152A (en) * 2015-04-03 2015-09-23 刘卡丁 Building method for underground engineering inverted construction overlapping structure

Similar Documents

Publication Publication Date Title
JP6636773B2 (en) Construction structure and construction method of tunnel lining body
JP4881555B2 (en) Construction method of underground structure
JP2000352296A (en) Method o constructing passage just under underground structure
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JPS6137692Y2 (en)
JPS58150631A (en) Construction work of underground structure
JPH01315520A (en) Underground outer wall constructing method for superstructure
JPS63280153A (en) Underground inverted lining method
JP2571426B2 (en) Construction method of retaining wall
JPH0781274B2 (en) How to build a beam on an underground wall
TW418274B (en) A pre-cast and site-cast combined construction method of retaining and waterproof diaphragm wall
JP3646698B2 (en) Construction method for underground structures
JP2603307B2 (en) Retaining method for the upper part of the continuous underground wall
JPH04360908A (en) Construction of underground continuous wall and formwork therefor
JP2506978Y2 (en) Synthetic retaining wall
JP2572680B2 (en) Underground structure by reverse strike method
JPS6245369B2 (en)
JPS58199925A (en) Construction of underground wall and underground foundation pile with brace
KR960009270B1 (en) Culvert structure and the method for making culvert
KR200405652Y1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it
JPS62111028A (en) Construction of underground structure
JPH06108459A (en) Construction of underground continuous wall
JPH0376922A (en) Construction of continuous underground wall and steel panel therefor