JPH11270151A - Concrete structure - Google Patents

Concrete structure

Info

Publication number
JPH11270151A
JPH11270151A JP7228698A JP7228698A JPH11270151A JP H11270151 A JPH11270151 A JP H11270151A JP 7228698 A JP7228698 A JP 7228698A JP 7228698 A JP7228698 A JP 7228698A JP H11270151 A JPH11270151 A JP H11270151A
Authority
JP
Japan
Prior art keywords
steel pipe
concrete member
pipe
concrete
pieces
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7228698A
Other languages
Japanese (ja)
Inventor
Yoshinaga Oyama
能永 大山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP7228698A priority Critical patent/JPH11270151A/en
Publication of JPH11270151A publication Critical patent/JPH11270151A/en
Pending legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with a drilling work at a demolition work and eliminate generation of noise, vibration, and coarse particulates, by burrying a pipe divided into a plurality of pieces on the diametral section in the concrete member of a temporary structure so as to expose one end on the surface. SOLUTION: A steel pipe 1 buried in a concrete member 10 is formed into a hollow pipe of which the diametral section is divided into three pieces or four pieces, and it is temporarily fixed by a tape or the like. The form of the steel pipe 1 is made into a cylinder, a square, a hexagon, or the like, and the material is thermoplastic material, a thin piece of metal, or the like. The steel pipe 1 is arranged together with reinforcement so as to expose the one end on the surface, and the number of pipes is set to be the number matching to a demolition work. The piston of a hydraulic lock jack or the wedge is inserted in a drilled hole formed by the steel pipe 1, and the steel pipe 1 is burstedly opened to crush the concrete member. When a static crushing agent is used, the static crushing agent having moisture absorbing expansion characteristic is charged, and the concrete member is crushed by the expansion pressure. Hereby, demolition considering peripheral environment can be carried out.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、コンクリート構
造物に関するものであり、特に解体作業を容易にするた
めに予めコンクリート破砕用の鋼管を埋設したコンクリ
ート構造物に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete structure, and more particularly to a concrete structure in which a steel pipe for crushing concrete is buried in advance to facilitate dismantling work.

【0002】[0002]

【従来の技術】万博、オリンピック、各種イベント施設
等の仮設構造物は、数ヶ月或いは数年で解体されるた
め、解体に要する作業を少なくし、人件費等のコストを
節約することが望まれる。また解体する仮設構造物が都
市部に隣接している場合は、解体に伴う騒音、振動等が
問題になるので、周辺環境にも配慮した解体工法が望ま
れる。
2. Description of the Related Art Temporary structures such as the Expo, the Olympics, and various event facilities are dismantled in several months or years, so it is desirable to reduce the work required for dismantling and to save costs such as labor costs. . Also, when the temporary structure to be demolished is adjacent to an urban area, noise and vibrations associated with the demolishing become a problem. Therefore, a dismantling method considering the surrounding environment is desired.

【0003】解体工法のうち騒音、振動がほとんどない
ものとしてロックジャッキ式破壊工法、静的破砕剤を用
いた工法等が挙げられる。ロックジャッキ式破壊工法
は、コンクリート構造物に穿設した削孔に油圧ロックジ
ャッキのピストンまたはウェッジ(くさび)を挿入し、
油圧によりピストンまたはウェッジを押し込んでコンク
リートを破砕する工法である。また静的破砕剤を用いた
工法は、吸湿膨張特性を有する物質の水和膨張等に起因
する膨張圧力を利用して破砕を行うものである。
[0003] Among the dismantling methods, there are lock-jack type destruction methods, methods using a static crushing agent, and the like that have almost no noise and vibration. The lock jack type destruction method inserts the piston or wedge of a hydraulic lock jack into a drilled hole in a concrete structure,
This method crushes concrete by pushing a piston or wedge with hydraulic pressure. In the method using a static crushing agent, crushing is performed by using an expansion pressure caused by hydration expansion of a substance having a hygroscopic expansion characteristic.

【0004】これらの工法は、大きな騒音、振動を伴わ
ないので、都市部に隣接した地域で使用することができ
る。
[0004] Since these construction methods do not involve large noise and vibration, they can be used in an area adjacent to an urban area.

【0005】[0005]

【発明が解決しようとする課題】しかしながらロックジ
ャッキ式破壊工法、静的破砕剤による工法は、いずれも
始めに削孔する必要があり、この削孔作業にはレッグハ
ンマーを用いるので、削孔の際に騒音と粉塵が発生する
ことになる。ロックジャッキ式破壊工法においては1回
の破壊量が少ないために、コンクリートの破砕塊をダン
プトラック等による搬出に適した大きさまで破砕するに
は、かなりの回数の削孔が必要となる。同様に静的破砕
剤を用いた場合でも、コンクリート構造物を破砕するた
めには相当な箇所を削孔し、これらの削孔に静的破砕剤
を充填する必要がある。従って、ロックジャッキ式破壊
工法、静的破砕剤による工法では、事前の削孔作業で騒
音、粉塵発生等の問題が生じることになる。
However, both the rock jack type destruction method and the method using a static crushing agent require drilling first, and a leg hammer is used in this drilling operation. In this case, noise and dust will be generated. In the rock-jack type destruction method, since the amount of destruction at one time is small, a considerable number of holes are required to crush the crushed mass of concrete to a size suitable for carrying out by a dump truck or the like. Similarly, even in the case of using a static crushing agent, it is necessary to drill a considerable portion and fill the hole with a static crushing agent in order to crush concrete structures. Therefore, in the rock jack type destruction method and the method using a static crushing agent, problems such as noise and dust generation occur in advance drilling work.

【0006】上記の問題点を踏まえて、本発明において
は、削孔作業を要しないコンクリート構造物を提供する
ことを目的とする。
[0006] In view of the above problems, an object of the present invention is to provide a concrete structure that does not require drilling work.

【0007】[0007]

【課題を解決するための手段】すなわち本発明は、径の
断面を複数割りにした管を一端が表面に露出するように
埋設したコンクリート構造物である。ロックジャッキ式
破砕工法及び静的破砕剤による工法を用いてこのような
コンクリート構造物を破砕する場合、削孔作業を必要と
せずに破砕作業を行うことができるので、騒音、振動、
粉塵の発生がなく、特に都市部に隣接した地域での適用
に有益である。
That is, the present invention is a concrete structure in which a pipe having a plurality of diameter sections is embedded so that one end is exposed on the surface. When crushing such a concrete structure using a rock jack crushing method and a method using a static crushing agent, the crushing work can be performed without the need for drilling work, so that noise, vibration,
There is no generation of dust, which is particularly useful for applications in areas adjacent to urban areas.

【0008】[0008]

【発明の実施の形態】以下、添付図面に沿って本発明を
詳述する。図1(a)は、本発明による仮設構造物のコ
ンクリート部材を示す斜視図である。図1(b)は、コ
ンクリート部材に埋設された管を拡大して示す斜視図で
ある。本発明による仮設構造物では、解体作業の効率化
を考慮してコンクリート部材10内に予め径の断面を複
数割りにした管1を埋設しておく。これは、解体に際し
て油圧ロックジャッキまたは静的破砕剤を挿入するため
の削孔を予め設けておくためである。尚、本実施例にお
いては、管1は鋼管として説明するが、管1の材料は適
用する解体工法に応じて適宜選択することができる。例
えば、静的破砕剤を使用する場合には熱可塑性材料が、
油圧ロックジャッキを使用する場合には、ジャッキのウ
ェッジによる応力で容易に破壊できる脆弱な材質、金属
の薄片等が有益である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below in detail with reference to the accompanying drawings. FIG. 1A is a perspective view showing a concrete member of a temporary structure according to the present invention. FIG. 1B is an enlarged perspective view showing a pipe buried in a concrete member. In the temporary structure according to the present invention, the pipe 1 whose diameter is divided into a plurality of sections in advance is embedded in the concrete member 10 in consideration of the efficiency of dismantling work. This is because a hole for inserting a hydraulic lock jack or a static crushing agent is provided in advance at the time of dismantling. In this embodiment, the pipe 1 is described as a steel pipe, but the material of the pipe 1 can be appropriately selected according to the dismantling method to be applied. For example, when using a static crushing agent, a thermoplastic material is used.
When a hydraulic lock jack is used, a fragile material, metal flake, or the like that can be easily broken by the stress caused by the wedge of the jack is useful.

【0009】図1(b)に示すように、コンクリート部
材10内に埋設される鋼管1は、径の断面を3ツ割りま
たは4ツ割りにした中空の管を用いる。鋼管1の形状
は、図示したような円筒状の管に限らず、四角形、六角
形等でも良い。しかしながらいずれの場合にも、削孔を
形成し、管内に挿入する油圧ロックジャッキのウエッジ
または静的破砕剤により及ぼされる応力に起因して崩壊
し、その応力を効率的にコンクリート部材10に波及さ
せる形状でなければならない。また、径の断面の複数割
りとしては、取扱いの容易等の観点から3ツ割りまたは
4ツ割り程度が適当であり、3ツ割りまたは4ツ割りに
した鋼管は、各部がバラバラにならないようにテープ等
で仮止めをする。
As shown in FIG. 1 (b), as a steel pipe 1 to be buried in a concrete member 10, a hollow pipe whose diameter section is divided into three or four is used. The shape of the steel pipe 1 is not limited to a cylindrical pipe as illustrated, but may be a square, a hexagon, or the like. In either case, however, a hole is formed and collapses due to the stress exerted by the wedge or static crusher of the hydraulic lock jack inserted into the pipe, effectively spreading the stress to the concrete member 10. Must be shaped. In addition, as a plurality of sections of the diameter cross section, about 3 or 4 sections are appropriate from the viewpoint of easy handling and the like, and the steel pipe divided into 3 or 4 sections is designed so that each part does not fall apart. Temporarily fix with tape.

【0010】鋼管10は鉄筋と共に配筋する。埋設する
鋼管10の本数は、どのような方法によって解体を行う
かを考慮して、その解体工法に必要とされる削孔の数に
見合う本数とする。従って、本発明のコンクリート構造
物は、施工以前に解体方法を考慮しておく必要がある。
[0010] The steel pipe 10 is arranged together with the rebar. The number of the steel pipes 10 to be buried is set to a number corresponding to the number of drill holes required for the demolition method in consideration of a method of demolition. Therefore, it is necessary to consider the dismantling method of the concrete structure of the present invention before construction.

【0011】また鋼管10の端部にはキャップを被せて
おくことが好ましい。これは、コンクリートを打込む際
に管内にコンクリートが流れ込むのを防ぐとともに、コ
ンクリート構造物の表面に多数の孔が開いて見栄えが悪
くなるのを防ぐためである。鋼管10の端部に被せたキ
ャップは、仮止め用のテープと共に鋼管の強度を増し、
打設するコンクリートの重量によって鋼管1が潰れるの
を防ぐ役割も果たす。
It is preferable that the end of the steel pipe 10 be covered with a cap. This is to prevent the concrete from flowing into the pipe when the concrete is poured, and to prevent the appearance of the concrete structure from being deteriorated due to a large number of holes being opened. The cap placed on the end of the steel pipe 10 increases the strength of the steel pipe together with the tape for temporary fixing,
It also serves to prevent the steel pipe 1 from being crushed by the weight of the concrete to be cast.

【0012】以下、本発明による仮設構造物の解体方法
について説明する。都市部に隣接した地域に建設された
仮設構造物は、解体の際に騒音、振動等が問題となる。
従って、騒音、振動等を伴う解体工法を適用することが
できない場合には、ロックジャッキ式破壊工法及び静的
破砕剤による解体工法によって仮設構造物のコンクリー
ト部材を破砕する。コンクリート部材に埋設した鋼管1
の端部にキャップを被せてある場合は、始めにこれらを
全て取り外しておく。次に、コンクリート部材内に埋設
した鋼管1によって形成された削孔に、油圧ロックジャ
ッキのピストンまたはウェッジを挿入し、油圧ポンプを
駆動してピストンまたはウェッジを押出す。鋼管1は予
め3ツ割りまたは4ツ割りにしたものを仮止めしてある
だけなので、管内に挿入されたピストンまたはウェッジ
によって及ぼされる応力に起因して裂開する。油圧ロッ
クジャッキによる応力は、鋼管1の裂開によってコンク
リート部材に波及し、これを破砕する。静的破砕剤を用
いてコンクリート部材を破砕する場合には、鋼管1によ
って形成された削孔に吸湿膨張特性を有する静的破砕剤
を充填する。充填した静的破砕剤が化学変化を起こす
と、水和膨張による膨張圧によってコンクリート部材を
破砕する。
A method for dismantling a temporary structure according to the present invention will be described below. Temporary structures constructed in areas adjacent to urban areas are subject to noise, vibration, etc. when dismantling.
Therefore, when the demolition method involving noise, vibration, and the like cannot be applied, the concrete member of the temporary structure is crushed by the rock jack type destruction method and the demolition method using a static crushing agent. Steel pipe 1 embedded in concrete member
If there are caps on the ends, remove them all first. Next, the piston or wedge of the hydraulic lock jack is inserted into the hole formed by the steel pipe 1 embedded in the concrete member, and the hydraulic pump is driven to extrude the piston or wedge. Since the steel pipe 1 is only temporarily fixed to a preliminarily divided one of three or four, the steel pipe 1 ruptures due to stress exerted by a piston or wedge inserted into the pipe. The stress caused by the hydraulic lock jack spreads to the concrete member due to the rupture of the steel pipe 1 and breaks it. When crushing a concrete member using a static crushing agent, a static crushing agent having a hygroscopic expansion property is filled into a hole formed by the steel pipe 1. When the charged static crushing agent undergoes a chemical change, the concrete member is crushed by the expansion pressure due to hydration expansion.

【0013】本発明によるコンクリート構造物において
は、鋼管1の中空部分を利用して破砕作業を行うことが
できるので、解体に際して改めて削孔を行う必要がな
い。騒音、振動等が特に問題となる場所での解体には、
ロックジャッキ式破壊工法または静的破砕剤による解体
工法を用いれば、鋼管1の中空部分を利用することがで
きるので、削孔のための振動、粉塵等が一切なく、周辺
環境に配慮した解体が可能となる。また削孔作業が必要
ないので、解体作業に係るコストを節約することができ
る。解体する仮設構造物が万博やオリンピック施設等比
較的広大な敷地に建設されたもので、解体の際の周辺環
境に対する騒音、振動、粉塵等がさほど問題とならない
場合には、ロックジャッキ式破砕工法、静的破砕剤によ
る解体工法に限らず様々な解体工法を適用することが可
能である。例えば、コンクリート部材に埋設された鋼管
1の中空部分を利用して火薬類を装填し、発破によって
コンクリート構造物を破砕することなどが可能である。
従って、削孔が必要な解体工法を適用する場合には、削
孔作業を省略できるので、コストの大幅な節約が可能で
ある。
In the concrete structure according to the present invention, since the crushing operation can be performed using the hollow portion of the steel pipe 1, there is no need to perform a new drilling at the time of dismantling. For dismantling where noise, vibration, etc. are particularly problematic,
If a rock jack type destruction method or a dismantling method using a static crushing agent is used, the hollow portion of the steel pipe 1 can be used, so there is no vibration, dust, etc. for drilling, and dismantling in consideration of the surrounding environment is possible. It becomes possible. Further, since the drilling operation is not required, the cost for the demolition operation can be saved. If the temporary structure to be dismantled was constructed on a relatively large site, such as the Expo or Olympic facilities, and the noise, vibration, dust, etc. to the surrounding environment during dismantling do not pose a significant problem, the rock jack crushing method It is possible to apply not only the dismantling method using a static crushing agent but also various dismantling methods. For example, it is possible to load explosives using the hollow portion of the steel pipe 1 buried in the concrete member and crush the concrete structure by blasting.
Therefore, when a dismantling method requiring drilling is applied, drilling work can be omitted, so that significant cost savings can be achieved.

【0014】[0014]

【発明の効果】本発明による仮設構造物は、径の断面を
複数割りにした管を一端が表面に露出するように埋設し
たコンクリート構造物であるので、削孔を必要とせずに
解体を行うことができる。従って、削孔作業に係るコス
トを節約することが可能であるとともに、適用する解体
工法によっては無騒音、無振動での解体が可能である。
The temporary structure according to the present invention is a concrete structure in which a pipe having a cross section of a plurality of diameters is buried so that one end is exposed on the surface, so that the temporary structure can be dismantled without requiring drilling. be able to. Therefore, it is possible to save the cost related to the drilling work, and it is possible to disassemble without noise and vibration depending on the dismantling method applied.

【図面の簡単な説明】[Brief description of the drawings]

【図1】(a)は、本発明による仮設構造物のコンクリ
ート部材を示す斜視図である。(b)は、コンクリート
部材に埋設された管を拡大して示す斜視図である。
FIG. 1A is a perspective view showing a concrete member of a temporary structure according to the present invention. (B) is a perspective view which expands and shows the pipe | tube embedded in the concrete member.

【符号の説明】[Explanation of symbols]

1 ......管(鋼管) 10......コンクリート部材 1. . . . . . Pipe (steel pipe) 10. . . . . . Concrete material

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 径の断面を複数割りにした管を一端が表
面に露出するように埋設したコンクリート構造物。
1. A concrete structure in which a pipe having a cross section of a plurality of diameters is buried such that one end is exposed on the surface.
JP7228698A 1998-03-20 1998-03-20 Concrete structure Pending JPH11270151A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7228698A JPH11270151A (en) 1998-03-20 1998-03-20 Concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7228698A JPH11270151A (en) 1998-03-20 1998-03-20 Concrete structure

Publications (1)

Publication Number Publication Date
JPH11270151A true JPH11270151A (en) 1999-10-05

Family

ID=13484898

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7228698A Pending JPH11270151A (en) 1998-03-20 1998-03-20 Concrete structure

Country Status (1)

Country Link
JP (1) JPH11270151A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014167228A (en) * 2013-02-28 2014-09-11 Kajima Corp Underground wall and construction method of underground wall
CN105715299A (en) * 2016-03-31 2016-06-29 枣庄矿业(集团)有限责任公司矿山救护大队 Device capable of being rapidly sealed and unsealed

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014167228A (en) * 2013-02-28 2014-09-11 Kajima Corp Underground wall and construction method of underground wall
CN105715299A (en) * 2016-03-31 2016-06-29 枣庄矿业(集团)有限责任公司矿山救护大队 Device capable of being rapidly sealed and unsealed

Similar Documents

Publication Publication Date Title
KR20070083474A (en) Shearing force reinforcing structure and shearing force reinforcing member
KR100415809B1 (en) precast pile for braced wall and the method using the same
KR100806867B1 (en) Steel pipe roof assembly and the construction method for Tunnel using thereof
KR100779988B1 (en) Method for constructing micropile
JPH11270151A (en) Concrete structure
KR100505301B1 (en) The structure for underground tunnel formation
JP3860301B2 (en) Bridge girder temporary construction method and pedestal that can be used for it
JP4867488B2 (en) Construction method of underground space, underground space constructed by this method, and underground structure constructed by this method
KR100753140B1 (en) Steel pipe roof assembly and the construction method for tunnel using thereof
JPH11310928A (en) Vibration isolation reinforcing method for existing structure
CN1973097B (en) Composite anchor bolt and construction method for the anchor bolt
JP2006057290A (en) Shear reinforcement structure
KR200317830Y1 (en) The structure for underground tunnel formation
JP2006057290A5 (en)
JPH09170338A (en) Base isolation method for existing building
KR100327547B1 (en) Composite retaining wall construction method
JPH06346679A (en) Method for crushing bedrock or concrete
JPH04350290A (en) Tunnel construction method, pillar part reinforcing method, and spread diameter pipe for reinforcing pillar part
JPH09170340A (en) Base isolation method of existing building and base isolation device therefor
JPH09235889A (en) Base isolation construction method of existing building
JPH09100536A (en) Foundation structure for building structure
JP3353166B2 (en) Method of rebuilding building structure and basic structure used for it
KR20240001887A (en) Microfile with circular triangle member and its construction method
JPH09100538A (en) Foundation structure for building
KR200245407Y1 (en) Soil-Nail able to Withdraw Itself by Blasting