JPH11236712A - Foot protection of slope, foot protection pressure receiving plate and device - Google Patents

Foot protection of slope, foot protection pressure receiving plate and device

Info

Publication number
JPH11236712A
JPH11236712A JP28754298A JP28754298A JPH11236712A JP H11236712 A JPH11236712 A JP H11236712A JP 28754298 A JP28754298 A JP 28754298A JP 28754298 A JP28754298 A JP 28754298A JP H11236712 A JPH11236712 A JP H11236712A
Authority
JP
Japan
Prior art keywords
pressure receiving
anchor
receiving plate
plate
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP28754298A
Other languages
Japanese (ja)
Other versions
JP3247348B2 (en
Inventor
Koji Kurihara
光二 栗原
Tetsuo Suzuki
哲夫 鈴木
Tetsuo Toshino
哲男 戸篠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji PS Corp
Original Assignee
Fuji PS Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji PS Corp filed Critical Fuji PS Corp
Priority to JP28754298A priority Critical patent/JP3247348B2/en
Publication of JPH11236712A publication Critical patent/JPH11236712A/en
Application granted granted Critical
Publication of JP3247348B2 publication Critical patent/JP3247348B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve workability by embedding a pressure receiving leg on a stepped horizontal surface, and applying initial tension by fixing an anchoring member to the ground to the pressure receiving plate. SOLUTION: A horizontal surface 1 for sodding and a vertical cut slope 1' are formed in a stepped state on a slope E with a prescribed level difference. And then the reverses of concrete square pressure receiving plates 2 having reinforcing PC steel 13 and having a height nearly equal to the level difference, are arranged to come into contact with the plane 1', the concrete square pressure receiving plates 2 are erected on the plane 1 side by side, legs 7 are embedded in holes 5 on the plane 1, and the slope before cut is covered by embankment (e). And then after anchor holes reaching the ground through through holes 9 for anchoring the plates 2 are made, inclined downward almost horizontally, and anchoring members 10 are inserted from the holes 9 and a grouting material is injected and solidified, prestressed concrete is introduced into the anchoring members 10 and anchored in the holes 9. Thus the introduction of the prestressed concrete helps increase the strength of the pressure receiving plates and thereby reduce the weight, facilitating transport and installation, and controlling a stratiform landslide.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は斜面ののり留め工
法と、これに用いるコンクリート製ののり留め受圧板及
びのり留め受圧装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for fastening a slope and a pressure receiving plate and a pressure receiving device made of concrete for use in the method.

【0002】[0002]

【従来の技術】特公平7−42708号公報により、の
り面を削って形成した植栽用の水平面上に載る底壁と、
底壁から起立し、上記水平面の切り土斜面の前に沿って
立つ一体の垂直壁とからなるコンクリート製のL形の自
立形のり留めブロックが公知である。こののり留めブロ
ックを植栽用の水平面上に左右一列に立て並べ、各ブロ
ックの垂直壁にあるアンカー固定孔と、背後の土中に打
込んで固定したアンカー材とを連結することによりのり
留め擁壁を構築することができる。
2. Description of the Related Art According to Japanese Patent Publication No. 7-42708, a bottom wall placed on a horizontal surface for planting formed by cutting a slope is provided.
2. Description of the Related Art Concrete L-shaped self-supporting gluing blocks are known which consist of an integral vertical wall rising from a bottom wall and standing in front of the horizontal cut slope. Glue the blocks by arranging them in a row on the horizontal plane for planting, and connecting the anchor fixing holes in the vertical walls of each block with the anchor material that has been driven into the soil behind and fixed. Retaining walls can be built.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記のり留め
ブロックの底壁は植栽用の水平面上に載っているため、
水平面の全体を植栽面にすることができず、植栽面の奥
行は水平面の奥行より狭くなる。又自立させるための底
壁部分が重量増となり作業性等が悪い。更に、のり留め
ブロックの底壁が載る水平面上にはコンクリートを打設
して、載台を設ける必要があり、手数がかかる。更に、
各ブロックの垂直壁と連結するアンカー材を背後の土中
に打込む際は、下段の水平面上に架台を置き、この架台
の上にアンカー打込機を設置し、未だブロックを立て並
べていない上段用のアンカー孔を背後の土中に打込む。
従って、下段の水平面上で架台と、アンカー打込機を左
右に移動させながら上段に立て並べるブロックの垂直壁
にあるアンカー固定孔に正確に一致するようにアンカー
を一定の間隔で打込まねばならず、精度を要し、時間と
手数が必要になると共に、上段の水平面にブロックを立
て並べる際は、ブロックの垂直壁にあるアンカー固定孔
に既に背後の土中に打込んだアンカーの端部が突入する
ようにブロックを立て並べねばならないので施工能率が
悪い。
However, since the bottom wall of the above-mentioned gluing block rests on a horizontal plane for planting,
The entire horizontal surface cannot be a planting surface, and the depth of the planting surface is smaller than the depth of the horizontal surface. Further, the weight of the bottom wall for self-supporting is increased, resulting in poor workability. Furthermore, it is necessary to cast concrete on the horizontal surface on which the bottom wall of the gluing block rests and provide a mounting table, which is troublesome. Furthermore,
When driving the anchor material to be connected to the vertical wall of each block into the soil behind, place a gantry on the lower horizontal plane, install an anchor driving machine on this gantry, and Drill anchor holes into the soil behind.
Therefore, the anchor and the anchor must be driven at regular intervals so as to exactly match the anchor fixing holes in the vertical wall of the block that is erected on the upper stage while moving the base and the anchor driving machine left and right on the horizontal plane of the lower stage. It requires precision, time and effort, and when arranging the blocks vertically on the upper horizontal surface, the end of the anchor that has already been driven into the soil behind the anchor hole in the vertical wall of the block The construction efficiency is poor because the blocks must be erected and lined up so as to enter.

【0004】その上、水平面の背後は切土斜面になって
いるので、立て並べたブロックの垂直壁との間には楔形
の空間が生じる。このため、アンカーにプレストレスを
かけるには上記楔形の空間を土砂で埋めて締め固めた
り、ブロック背面のすき間にブロック高の下方半分位に
コンクリートを打設して、コンクリートの強度がでてブ
ロックが転倒するのを防ぐと共に、アンカーと、垂直壁
にあるアンカー固定孔との間に楔を打込んでブロックの
ずれ動きを防止してからでなければプレストレスをかけ
ることができず、非常に時間と手数がかかる。
In addition, since a cut slope is formed behind the horizontal plane, a wedge-shaped space is formed between the block and the vertical wall. For this reason, to apply prestress to the anchor, fill the wedge-shaped space with earth and sand and compact it, or place concrete in the lower half of the block height in the gap on the back of the block to increase the strength of the concrete and Prevent the falling of the block and prevent the block from shifting by inserting a wedge between the anchor and the anchor fixing hole in the vertical wall. It takes time and trouble.

【0005】[0005]

【課題を解決するための手段】本発明の請求項1、請求
項2、請求項3、請求項4ののり留め工法は、上述した
問題点を解消するために開発されたものであって、請求
項1ののり留め工法は、のり面を所要段差で削って植栽
用の水平面と、この水平面の背後に連なった切土面とを
有する段を階段状に形成し、その各水平面の切土面の前
に沿って左右に所要間隔で穴を削孔し、その各穴に広幅
で、高さが上記段差と同程度の四角な大形版体の受圧板
から垂下する脚を挿入して複数の受圧板を切土面に概ね
接触させながら水平面上に左右一列に隣接させて立て並
べ、上記各受圧板に予め開設されたアンカー用貫通孔か
ら切土面を経てアンカー材を斜め下向きに挿入し、アン
カー材の先端部を地山に固定し、このアンカー材にプレ
ストレスをかけてアンカー材の他端部を各受圧板のアン
カー用貫通孔に定着することを各段ごとに行うことを特
徴とする。請求項2ののり留め工法は、のり面を所要段
差で削って植栽用の水平面と、この水平面の背後に連な
った安定な傾斜切土面とを有する段を階段状に形成し、
その各水平面の傾斜切土面の前に沿って左右に所要間隔
で穴を削孔し、その各穴に広幅で、高さが上記段差と同
程度の四角な大形版体の受圧板から垂下する脚を挿入し
て複数の受圧板を水平面上に左右一列に隣接させて垂直
に立て並べ、上記受圧板と傾斜切土面との間に生じてい
る空隙に圧縮強度の大きな裏込め材を充填、転圧して裏
込め強化層を形成し、上記各受圧板に予め開設されたア
ンカー用貫通孔から上記裏込め強化層及び傾斜切土面を
経てアンカー材を斜め下向きに挿入し、アンカー材の先
端部を地山に固定し、このアンカー材にプレストレスを
かけてアンカー材の他端部を各受圧板のアンカー用貫通
孔に定着することを各段ごとに行うことを特徴とする。
請求項3ののり留め工法は、のり面を所要段差で削って
植栽用の水平面と、この水平面の背後に連なった切土面
とを有する段を階段状に形成し、その各水平面の切土面
の前に沿って左右に所要間隔で穴を削孔し、その各穴に
細幅で、高さが上記段差と同程度の短冊形受圧板から垂
下する脚を挿入して複数の短冊形受圧板を切土面に概ね
接触させながら水平面上に左右に一定の隣接間隔を保っ
て立て並べ、上記短冊形受圧板の各隣接間隔に横長受圧
板を左右の短冊形受圧板に係合させて短冊形受圧板の高
さまで積み立て、上記短冊形受圧板に予め開設されたア
ンカー用貫通孔から切土面を経てアンカーを斜め下向き
に挿入し、アンカーの先端部を地山に固定し、このアン
カー材にプレストレスをかけてアンカー材の他端部を各
短冊形受圧板のアンカー用貫通孔に定着することを、各
段ごとに行うことを特徴とする。請求項4ののり留め工
法は、のり面を所要段差で削って植栽用の水平面と、こ
の水平面の背後に連なった安定な傾斜切土面とを有する
段を階段状に形成し、その各水平面の傾斜切土面の前に
沿って左右に所要間隔で穴を削孔し、その各穴に細幅
で、高さが上記段差と同程度の短冊形受圧板から垂下す
る脚を挿入して複数の短冊形受圧板を水平面上に左右に
一定の隣接間隔を保って垂直に立て並べ、上記短冊形受
圧板の各隣接間隔に横長受圧板を左右の短冊形受圧板に
係合させながら短冊形受圧板の高さまで垂直に積み立
て、上記短冊形受圧板、横長受圧板と傾斜切土面との間
に生じている空隙に圧縮強度の大きな裏込め材を充填、
転圧して裏込め強化層を形成し、上記短冊形受圧板に予
め開設されたアンカー用貫通孔から上記裏込め強化層及
び傾斜切土面を経てアンカー材を斜め下向きに挿入し、
アンカーの先端部を地山に固定し、このアンカー材にプ
レストレスをかけてアンカー材の他端部を各短冊形受圧
板のアンカー用貫通孔に定着することを、各段ごとに行
うことを特徴とする。
The gluing method according to claims 1, 2, 3, and 4 of the present invention has been developed to solve the above-mentioned problems. In the gluing method of the first aspect, a slope having a horizontal surface for planting and a cutting surface connected behind the horizontal surface is formed in a step shape by shaving the slope at a required step, and the cutting of each horizontal surface is performed. Drill holes at the required intervals left and right along the front of the soil surface.In each hole, insert a leg that is wide and has a height that is approximately the same as the above-mentioned step, and that hangs down from a large-sized pressure plate. A plurality of pressure receiving plates are placed side by side in a row on the horizontal surface while making general contact with the cut surface, and the anchor material is directed obliquely downward through the cut surface from the through holes for anchors previously established in each of the pressure receiving plates. And anchor the tip of the anchor material to the ground, prestress this anchor material And performing for each stage to fix the other end portion of the anchor member to anchor through hole of the pressure receiving plate. In the gluing method according to claim 2, the slope is shaved at a required step to form a step having a horizontal surface for planting and a stable inclined cutting surface connected to the rear of the horizontal surface in a stepped manner,
Holes are drilled at required intervals to the left and right along the front of the inclined cutting surface of each horizontal plane, and each of the holes is wide and the height is about the same as the above-mentioned step. A plurality of pressure receiving plates are inserted vertically into the horizontal plane adjacent to each other in a row on the horizontal plane, and the backing material with high compressive strength is inserted into the gap between the pressure receiving plate and the inclined cut surface. Filling and rolling to form a backfill reinforcement layer, and insert the anchor material obliquely downward through the backfill reinforcement layer and the inclined cut surface from the through hole for anchor previously established in each of the pressure receiving plates. It is characterized in that the front end of the material is fixed to the ground, prestress is applied to the anchor material, and the other end of the anchor material is fixed to the through hole for anchor of each pressure receiving plate for each step. .
According to a third aspect of the present invention, the step of forming a step having a horizontal surface for planting and a cutting surface connected to the rear of the horizontal surface is formed in a step-like manner by shaving the slope at a required step, and cutting each horizontal surface. Holes are drilled at required intervals to the left and right along the front of the soil surface, and a plurality of strips are inserted into each of the holes by inserting legs that are narrow and have a height that is approximately the same as the step above, and that hang from a strip-shaped pressure receiving plate. The pressure receiving plates are placed vertically on the horizontal surface while maintaining a constant adjacent spacing while making general contact with the cut surface, and the horizontal pressure receiving plates are engaged with the left and right rectangular pressure receiving plates at each adjacent spacing of the rectangular pressure receiving plates. To the height of the strip-shaped pressure receiving plate, insert the anchor obliquely downward through the cut surface from the through hole for the anchor previously established in the strip-shaped pressure receiving plate, and fix the tip of the anchor to the ground, A prestress is applied to this anchor material, and the other end of the anchor material is connected to each of the rectangular pressure receiving plates. That colonize the car through hole, and performing in each stage. In the gluing method according to claim 4, the slope is shaved at a required step to form a step having a horizontal surface for planting and a stable inclined cut surface connected behind the horizontal surface in a step-like manner. Holes are drilled at required intervals to the left and right along the front of the inclined cutting surface on the horizontal plane, and each hole is inserted with a leg that is hanging from a strip-shaped pressure plate with a narrow width and the same height as the above-mentioned step. A plurality of strip-shaped pressure receiving plates are vertically erected on the horizontal plane with a constant adjacent space on the left and right while engaging the horizontally long pressure-receiving plate with the left and right strip-shaped pressure receiving plates at each adjacent interval of the strip-shaped pressure receiving plates. Vertically stacked up to the height of the strip-shaped pressure receiving plate, filling the gap between the strip-shaped pressure-receiving plate, the horizontally long pressure-receiving plate and the inclined cut surface with a backfill material having a large compressive strength,
Rolling to form a backfill reinforcement layer, insert the anchor material obliquely downward through the backfill reinforcement layer and the inclined cut surface from the through hole for anchor previously established in the rectangular pressure receiving plate,
Fixing the tip of the anchor to the ground, prestressing the anchor and fixing the other end of the anchor to the through hole for anchor of each strip-shaped pressure receiving plate is performed for each step. Features.

【0006】請求項5ののり留め受圧板は、請求項1、
請求項2ののり留め工法に使用するためのもので、のり
面を所要段差で削って植栽用の水平面と、水平面の背後
に連なった切土面とを形成した階段状の各段の、上記切
土面に概ね接触して前記水平面上に左右一列に隣接して
立て並べるコンクリート製ののり留め受圧板であって、
広幅で、高さが上記段差と同程度の四角な大形版体と、
この大形版体の下端面から一体に垂下し、水平面の地中
に埋設される脚とからなり、上記大形版体には切土面に
概ね接触させて水平面上に立てた時、切土面を経て斜め
下向きにアンカー材を挿入でき、且つアンカー材の端部
を定着することができるアンカー用貫通孔を設けたこと
を特徴とする。又、請求項6ののり留め受圧装置は請求
項3,請求項4ののり留め工法に使用するもので、のり
面を所要段差で削って植栽用の水平面と、水平面の背後
に連なった切土面とを形成した階段状の各段の、上記切
土面の前で前記水平面上に左右一列に立て並べるコンク
リート製ののり留め受圧板装置であって、細幅で、高さ
が上記段差と同程度の短冊版体と、この版体の下端面か
ら一体に垂下し、水平面の地中に埋設される脚を備え、
前記短冊版体を切土面に概ね接触させて水平面上に左右
に特定の間隔を保って立て並べる短冊形受圧板と、上記
短冊形受圧板の隣接間隔に、該受圧板の高さまで積み立
てられる横長受圧板とからなり、前記短冊形受圧板の短
冊版体には切土面を経て斜め下向きにアンカー材を挿入
でき、且つアンカー材の端部を定着することができるア
ンカー用貫通孔を設けると共に、短冊版体の左右の側部
と、これに対向する横長受圧板の左右の側部には凹凸の
係合部を設けたことを特徴とする。
According to a fifth aspect of the present invention, there is provided a pressure receiving plate
It is for use in the gluing method according to claim 2, wherein the slope is shaved at a required step to form a horizontal plane for planting, and a step-shaped step formed with a cut surface connected to the rear of the horizontal plane, A concrete glue-receiving pressure plate that is substantially in contact with the cut surface and is arranged side by side on the horizontal surface in a row on the left and right sides,
A wide, square, large plate that is about the same height as the step above,
It consists of legs that hang down from the lower end surface of this large plate and are buried in the ground in a horizontal plane. An anchor through-hole through which an anchor material can be inserted obliquely downward through the soil surface and an end of the anchor material can be fixed is provided. The gluing pressure receiving device according to claim 6 is used for the gluing method according to claim 3 or claim 4, wherein a cutting surface is cut at a required step to form a horizontal plane for planting and a cutting plane connected behind the horizontal plane. A concrete glue-receiving pressure plate device which is arranged in a row on the horizontal surface in front of the cut surface of each of the steps in the form of a step having a soil surface, the narrow width and the height having the height difference. With a strip plate of the same size as the above, and legs that hang down integrally from the lower end surface of this plate and are buried in the ground on a horizontal plane,
A strip-shaped pressure receiving plate that is arranged so that the strip plate body is substantially in contact with a cut surface and is arranged on a horizontal plane at a specific interval on the left and right sides, and at an interval adjacent to the strip-shaped pressure receiving plate, is stacked up to the height of the pressure receiving plate. It is composed of a horizontally long pressure receiving plate, and the strip plate of the strip-shaped pressure receiving plate is provided with an anchor through hole through which an anchor material can be inserted obliquely downward through a cut surface and an end of the anchor material can be fixed. In addition, the left and right side portions of the strip plate and the left and right side portions of the horizontally long pressure receiving plate opposed thereto are provided with uneven engagement portions.

【0007】[0007]

【発明の実施の形態】図1に請求項1ののり留め工法を
適用した斜面の一部の仕上がり外観を示す。1はのり面
に作った階段状水平面で、各水平面1の背後の鉛直状の
切土面に接して大形版体の受圧板2が立て並べられてい
る。各受圧板2は、斜め下方へ設置したPC鋼材である
アンカーにより、それぞれ地山につなぎ止められてお
り、3がアンカー定着部の蓋である。各水平面には樹木
Pを植える。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows a partially finished appearance of a slope to which the gluing method of claim 1 is applied. Reference numeral 1 denotes a step-like horizontal plane formed on a slope, and large-sized pressure receiving plates 2 are vertically arranged in contact with a vertical cut surface behind each horizontal plane 1. Each pressure receiving plate 2 is connected to the ground by an anchor made of PC steel installed diagonally downward, and 3 is a lid of an anchor fixing portion. Trees P are planted on each horizontal plane.

【0008】図2は請求項1ののり留め工法の各工程の
説明図である。図2(A)はのり斜面Eに最初の棚状水
平面1と、その背後に連なる鉛直状の切土面1′を作
り、その水平面1の、切土面1′の前に所要間隔でアー
スオーガー6により垂直な穴5を順次削孔しているとこ
ろを示す。アースオーガー(削孔機)6の図示しない本
体は小型軽量で、狭い水平面1に載せても使い得る。
FIG. 2 is an explanatory view of each step of the gluing method according to claim 1. FIG. 2 (A) shows a first shelf-shaped horizontal surface 1 and a vertical cutting surface 1 'connected behind the first cutting surface 1' on the slope G, and grounding the horizontal surface 1 at a required interval before the cutting surface 1 '. The vertical holes 5 are sequentially drilled by the auger 6. The body (not shown) of the earth auger (drilling machine) 6 is small and lightweight, and can be used even if it is mounted on the narrow horizontal surface 1.

【0009】図2(B)は、(A)で造った水平面1に
受圧板2を鉛直状の切土面1′に接触させながら一列に
立て並べているところを示す。受圧板2から垂下する脚
7を穴5に落とし嵌めつつ次々と立て並べるので、穴5
の相互間隔は隣接する二つの受圧板の脚7、7の間隔に
一致させる。脚7は支柱の働きをする強固なもので、図
では一本であるが、複数本にしてもよい。受圧板2の形
状、寸法は後述するが、図を略した小型クレーンのワイ
ヤロープ8で吊上げ吊下ろし出来る大きさにする。9は
受圧板に設けたアンカー用貫通孔を示す。
FIG. 2B shows a state in which the pressure receiving plates 2 are arranged in a line on the horizontal surface 1 made in FIG. 2A while making contact with the vertical cut surface 1 ′. The legs 7 hanging from the pressure receiving plate 2 are lined up one after another while being fitted into the holes 5.
Of the two pressure receiving plates are matched with each other. The leg 7 is a strong one that functions as a support, and is one in the figure, but may be plural. Although the shape and dimensions of the pressure receiving plate 2 will be described later, the pressure receiving plate 2 is made large enough to be lifted and hung by the wire rope 8 of a small crane (not shown). Reference numeral 9 denotes a through hole for an anchor provided in the pressure receiving plate.

【0010】図2(C)は受圧板2に予め明けてあるア
ンカー用貫通孔9から穿孔機11を土中へ差込み、切土
面1′から地山に達するアンカー穴を水平に近い下向き
傾斜角(10°付近)で次々と削孔し、そのアンカー穴
にそれぞれPC鋼材のアンカー材10を挿入している状
態を示す。アンカー材の挿入後、アンカー穴にグラウト
(モルタル)を注入し、その固化後、アンカー材を緊張
させてプレストレスをかけ、受圧板2のアンカー用貫通
孔9に定着する。これで受圧板2は緊張したアンカー材
10により、地山につなぎ留められる。なおこの地山と
受圧板とを結ぶアンカーとその工法は周知ゆえ、詳細は
略す。
FIG. 2 (C) shows that the drilling machine 11 is inserted into the soil through the anchor through hole 9 previously drilled in the pressure receiving plate 2, and the anchor hole reaching the ground from the cut surface 1 'is inclined downward almost horizontally. This shows a state in which holes are drilled one after another at a corner (around 10 °), and anchor members 10 of PC steel are inserted into the respective anchor holes. After the insertion of the anchor material, grout (mortar) is injected into the anchor hole, and after solidification, the anchor material is tensioned to apply prestress, and is fixed to the anchor through hole 9 of the pressure receiving plate 2. Thus, the pressure receiving plate 2 is fixed to the ground by the tensioned anchor member 10. Since the anchor connecting the ground and the pressure receiving plate and the method of construction are well known, the details are omitted.

【0011】図2(D)は、各受圧板2のアンカー用貫
通孔9にアンカー材10の外端を定着し、その定着部を
蓋3で覆った状態を示す。各受圧板2の背面上端と地山
斜面との間隙は盛土eで平らにふさぐ(図3B参照)。
これでこの段は完成し、次の段に移るのである。斜面が
自然斜面なら下から上へ一段ずつ、水平面1を作るごと
に図2(A)〜(D)の工程を繰返す。なお斜面が切土
のり面になっている場合は上から下へ一段ずつ仕上げる
と、作業手順も安全上も良い。段差は受圧板2の高さに
合わせるが、状況に応じて変えてよい。
FIG. 2D shows a state where the outer end of the anchor member 10 is fixed to the anchor through hole 9 of each pressure receiving plate 2 and the fixing portion is covered with the lid 3. The gap between the upper end of the rear surface of each pressure receiving plate 2 and the slope of the ground is flatly covered with the embankment e (see FIG. 3B).
This completes this stage and moves on to the next stage. If the slope is a natural slope, the steps of FIGS. 2 (A) to 2 (D) are repeated every time the horizontal plane 1 is created, one step from the bottom to the top. If the slope is a cut slope, the work procedure and safety can be improved by finishing one step from top to bottom. The step is adjusted to the height of the pressure receiving plate 2, but may be changed according to the situation.

【0012】地山の土質が粘性土等のように安定してい
る場合は図2(A),(B)に示したように棚状水平面
1の背後に鉛直状の切土面1′を形成し、受圧板2を切
土面1′に接触させながら水平面1に一列に立て並べる
ことができるが、土質によっては工事中の崩落を防ぐた
め安定した斜面となるように傾斜して切土し、受圧板2
から垂下する脚7を傾斜切土面1”の前に沿って水平面
1に掘った穴5に落とし嵌めて受圧板を水平面1上に隣
接して立てたとき、受圧板2の背面と傾斜切土面1”の
間には、受圧板のアンカー貫通孔9よりも下方に達する
空隙が生じる場合がある(図12参照)。そのときには
受圧板2を立て並べたあと、その空隙に単なる土砂では
なく道路路盤として使用されるクッラシャラン(切込み
砕石)等の圧縮強度の大きな裏込め材を受圧板の高さの
約2/3程度まで充填、転圧して裏込め強化層Cを形成
することによりに裏込め強化層で空隙を埋め、受圧板の
アンカー用貫通孔9から穿孔機11を裏込め強化層Cを
経て土中へ差込み、傾斜切土面1”から地山に達するア
ンカー穴を水平に近い下向き傾斜角(10°付近)で次
々と削孔し、そのアンカー穴にそれぞれアンカー材10
を挿入し、アンカー材の挿入後、アンカー穴にグラウト
(モルタル)を注入し、その固化後、アンカー材を緊張
させてプレストレスをかけ、受圧板2のアンカー用貫通
孔9に定着する。これにより、強度が発現するまで長時
間待たねばならないコンクリートを空隙に充填する場合
にくらべて工期は短縮し、経済的に施工できる。尚、裏
込め強化層Cの上には盛土eをし、受圧板の上端と地山
斜面との間を塞ぐ。
When the soil of the ground is stable such as clayey soil, a vertical cut surface 1 'is provided behind the shelf-like horizontal surface 1 as shown in FIGS. 2 (A) and 2 (B). It can be formed and lined up in a row on the horizontal surface 1 while the pressure receiving plate 2 is in contact with the cutting surface 1 '. However, depending on the soil quality, the cutting is performed by inclining so as to form a stable slope to prevent collapse during construction. And pressure receiving plate 2
When the pressure receiving plate is placed adjacent to the horizontal surface 1 by dropping and fitting the leg 7 hanging from the hole 5 into the hole 5 dug in the horizontal surface 1 in front of the inclined cutting surface 1 ″, the rear surface of the pressure receiving plate 2 is inclined and cut. There may be a gap between the soil surface 1 "and the space below the anchor through hole 9 of the pressure receiving plate (see FIG. 12). At that time, after the pressure receiving plate 2 is vertically arranged, a backing material having a high compressive strength such as crusher sharan (cut crushed stone) used as a road base instead of mere earth and sand is provided in the gap about 2/3 of the height of the pressure receiving plate. Filling and rolling to form the backfill reinforcing layer C, thereby filling the voids with the backfill reinforcing layer, and inserting the drilling machine 11 from the anchor through hole 9 of the pressure receiving plate into the soil via the backfill reinforcing layer C. The anchor holes reaching the ground from the sloping cut surface 1 "are drilled one after another at a downward inclination angle (nearly 10 °) which is almost horizontal, and the anchor material 10 is formed in each of the anchor holes.
After the anchor material is inserted, grout (mortar) is injected into the anchor hole. After solidification, the anchor material is tensioned to apply prestress, and is fixed in the anchor through hole 9 of the pressure receiving plate 2. Thereby, the construction period can be shortened and the construction can be carried out economically as compared with the case where the voids are filled with concrete which has to wait for a long time until the strength is developed. An embankment e is placed on the backfill reinforcement layer C to close the gap between the upper end of the pressure receiving plate and the ground slope.

【0013】図3は請求項5の受圧板で、図1の受圧板
2がこれである。図3(B)に示すように、のり斜面E
を所要段差で削って植栽用水平面1と、水平面1の背後
に連なった鉛直状の切土面1′とを階段状に形成してお
り、切土面1′の高さは階段段差より低いが、脚7を垂
直の孔5に落し嵌めて立ったときの受圧板2のアンカー
用貫通孔9よりも高くなるようにしている。その切土面
1′に背面を接触させて、段差とほぼ等しい高さを有す
るコンクリート製ののり留め受圧板2を水平面1上に、
左右へ一列に隣接して立て並べる。図2に示したよう
に、各受圧板2は切土面1′の前の水平面1上に予め設
けられた穴5に脚7を落し嵌めて並べられる。
FIG. 3 shows a pressure receiving plate according to a fifth aspect, and the pressure receiving plate 2 shown in FIG. As shown in FIG.
A horizontal plane 1 for planting and a vertical cutting surface 1 'connected to the rear of the horizontal plane 1 are formed in steps so that the height of the cutting plane 1' is higher than the height of the steps. Although it is low, it is configured to be higher than the anchor through hole 9 of the pressure receiving plate 2 when the leg 7 is dropped into the vertical hole 5 and stands. The back surface is brought into contact with the cut surface 1 ′, and a concrete gluing pressure receiving plate 2 having a height substantially equal to the step is placed on the horizontal surface 1,
Stand side by side in a row to the left and right. As shown in FIG. 2, each pressure receiving plate 2 is arranged by dropping a leg 7 into a hole 5 previously provided on a horizontal surface 1 in front of a cutting surface 1 '.

【0014】図3、4は請求項5のコンクリート製のの
り留め受圧板2を立て並べた使用状態を示す。寸法を例
示すると、四角形版体は高さ、横幅ともに2mの正方形
で、厚さは最も厚い下端中央で300mm、最も薄い上
端両端部が100mmであり、脚7は直径300mm、
長さ600mmの円柱で、アンカー用貫通孔9は直径9
6mmである。なお図3(B)の鎖線Eは切土前の斜面
であり、eは盛土を示す。受圧板2は脚7を地山にさし
込み、背後の鉛直状の切土面1′に接触させてあるか
ら、アンカー材を緊張させて受圧板本体に接続定着して
も安定である。
FIGS. 3 and 4 show a state in which the concrete pressure receiving plate 2 of claim 5 is arranged upright. To illustrate the dimensions, the square plate is a square having a height and a width of 2 m both in width and a thickness of 300 mm at the center of the thickest lower end, and 100 mm at both ends of the thinnest upper end.
It is a cylinder of 600 mm in length, and the through hole 9 for anchor has a diameter of 9
6 mm. The chain line E in FIG. 3B is the slope before cutting, and e indicates embankment. Since the pressure receiving plate 2 has the legs 7 inserted into the ground and is in contact with the vertical cut surface 1 'behind, the anchoring material is stable even if the anchor material is tensioned and connected and fixed to the pressure receiving plate main body.

【0015】図3(A)の一枚の受圧板2には破線で、
縦横に入れた補強用PC鋼材13を示している。各受圧
板2は図5に示すように四角形版体と、脚7に編組鉄筋
14を入れ、特に脚7との接続を強固にしているが、こ
れにPC鋼材13によるプレストレスを加えた事によ
り、アンカー材10の一点けん引による曲げに耐える十
分な強度を備える。尚、脚7を2本ずつにして受圧板の
方向及び鉛直姿勢保持作用を強めてもよい。
A broken line is shown on one pressure receiving plate 2 in FIG.
The reinforcing PC steel material 13 vertically and horizontally is shown. As shown in FIG. 5, each pressure receiving plate 2 has a square plate and braided reinforcing bars 14 inserted into the legs 7, and particularly, the connection with the legs 7 is strengthened. Accordingly, the anchor member 10 has sufficient strength to withstand bending due to one-point towing. Note that the legs 7 may be provided two by two to enhance the action of maintaining the direction of the pressure receiving plate and the vertical posture.

【0016】図3、4(A)では、隣接した受圧板2、
2の四角形版体相互の接触面は平らな側面2a、2a同
志になっているが、例えば図4(B)に示すように側面
の一方に縦の凸部2bとして突条、他方に上記突条を受
入れる縦の凹部2cとして凹溝を設けたり、図4
(C)、(C′)に示すように、両側面ともに凹溝2c
付きとし、向き合った凹溝2c、2cの間に筒状布袋2
eを挿入してこれにモルタルを充填する等、夫々図示の
ように係合させることにより、一列に立て並べた複数の
受圧板が連携して強力に受圧作用を行うので好ましい。
なお、のり斜面に沿う鉛直状の切土面1′が湾曲してい
る場合、図4(C′)のように受圧板2の側面の前後縁
部2f、2gの肉を落して、湾曲接続可能にしておくこ
とは、図4(A)(B)(C)いずれにも必要である。
3 and 4 (A), adjacent pressure receiving plates 2,
The contact surfaces of the two rectangular plates 2 are flat side surfaces 2a and 2a. For example, as shown in FIG. 4B, one of the side surfaces has a ridge as a vertical projection 2b, and the other side has the ridge. As shown in FIG.
As shown in (C) and (C '), the groove 2c is formed on both sides.
And a tubular cloth bag 2 between the opposed concave grooves 2c, 2c.
It is preferable that a plurality of pressure receiving plates arranged in a row perform a powerful pressure receiving action in cooperation with each other as shown in the drawing, for example, by inserting e and filling it with mortar.
When the vertical cut surface 1 'along the glue slope is curved, the meat of the front and rear edges 2f and 2g of the side surface of the pressure receiving plate 2 is dropped as shown in FIG. Making it possible is necessary for each of FIGS. 4A, 4B, and 4C.

【0017】図3、4の実施例の受圧板2の四角形版体
は、上端面の左右および前面下端部の左右に、それぞれ
インサートアンカー15を設けてある。これは図6に示
すように、例えば立て並べた下段の各受圧板2を正しい
姿勢で固定後、上段の受圧板2を立て並べる際に役立
つ。すなわち図6のように、下段の受圧板2の上端面の
インサートアンカー15と、上段の受圧板2の前面の下
端部又は上端面のインサートアンカー15とをターンバ
ックル15cを介してボルト15a、座板15bなどで
つなぎ止め、ターンバックル15cの回し加減で、上段
の受圧板を下段の受圧板と同じ正しい姿勢に調整し保持
することが出来る。
The rectangular plate of the pressure receiving plate 2 of the embodiment shown in FIGS. 3 and 4 has insert anchors 15 on the left and right sides of the upper end face and on the left and right sides of the lower end of the front face, respectively. For example, as shown in FIG. 6, this is useful when the upper pressure receiving plates 2 are arranged vertically after the lower pressure receiving plates 2 arranged vertically are fixed in a correct posture. That is, as shown in FIG. 6, the insert anchor 15 on the upper end surface of the lower pressure receiving plate 2 and the lower end or upper end insert anchor 15 on the front surface of the upper pressure receiving plate 2 are connected to the bolt 15 a and the seat The upper pressure receiving plate can be adjusted and held in the same correct posture as the lower pressure receiving plate by fastening with the plate 15b or the like and turning the turn buckle 15c.

【0018】図7は請求項3の工法の仕上がり外観、図
8はその各工程を示す。図8(A)の工程は図2(A)
と全く同じである。中継用の短冊形受圧板2′は、横幅
の狭い矩形板状で、左右の側縁に土留め板になる横長受
圧板4の片縁を落し嵌められる縦溝16を備え、下端に
脚7を有する。この短冊形受圧板2′を所要間隔で立て
並べるため、水平面1の、鉛直状の切土面1′の前に明
ける穴5の隣接間隔は横長受圧板4の横幅に応じて正確
に定める。脚7を図8(B)のようにそれぞれ穴に落し
嵌めれば、短冊形受圧板2′は切土面1′に接触して安
定に立つ。尚、短冊形受圧板2′の隣接間隔は横長受圧
板4の横幅よりも少し小にする。又、切土面1′の高さ
は段差よりも低いが、短冊形受圧板を立てたとき、短冊
形受圧板のアンカー用貫通孔9の位置よりも高くしてあ
る。
FIG. 7 shows a finished appearance of the method of the third aspect, and FIG. 8 shows each step. The process of FIG. 8A is the same as that of FIG.
Is exactly the same as The strip-shaped pressure receiving plate 2 'for relaying is a rectangular plate having a narrow width, and has a vertical groove 16 on one side of the left and right side edges, into which one edge of the horizontally long pressure receiving plate 4 serving as a retaining plate is fitted. Having. In order to arrange the strip-shaped pressure receiving plates 2 ′ at required intervals, the interval between the holes 5 formed in front of the vertical cutting surface 1 ′ on the horizontal surface 1 is accurately determined according to the width of the horizontally long pressure receiving plate 4. When the legs 7 are respectively dropped into the holes as shown in FIG. 8B, the strip-shaped pressure receiving plate 2 'comes into contact with the cut surface 1' and stands stably. It should be noted that the interval between the strip-shaped pressure receiving plates 2 ′ is slightly smaller than the horizontal width of the horizontally long pressure receiving plate 4. Although the height of the cut surface 1 'is lower than the step, when the rectangular pressure receiving plate is erected, it is higher than the position of the anchor through hole 9 of the rectangular pressure receiving plate.

【0019】図8(C)は立ち並んだ短冊形受圧板2′
…の隣接するもの同志の間に単純な矩形コンクリート板
である横長受圧板4を各短冊形受圧板の側縁にある縦溝
に、この例では二枚ずつ上下に重ねて落し嵌める。その
後、図2(C)の説明と同様に、短冊形受圧板2′のア
ンカー用貫通孔9に穿孔機11をさし込んで、切土面
1′から地山に達するアンカー穴を作り、この穴にPC
鋼材のアンカー材10の挿入と、グラウトの注入を行
い、グラウトが固まったらアンカー材の緊張と、アンカ
ー用貫通孔9への定着を行い、定着部を蓋3で塞ぐ(図
9参照)。短冊形受圧板2′、横長受圧板4の背面と、
鉛直状切土面の上ののり斜面との間隙に必要な盛り土e
を行う。こうして1つの段が完成したら、上述の図8
(A)〜(C)の工程を繰り返して次の段を作る。この
場合、斜面が自然斜面なら下から上へ1段宛作り、斜面
が切土のり面の場合は、上から下へ1段宛作ると作業手
順も、安全上も良い。
FIG. 8 (C) shows a strip-shaped pressure receiving plate 2 'arranged side by side.
In this example, two horizontally long pressure receiving plates 4 each of which is a simple rectangular concrete plate are dropped and fitted in a vertical groove on a side edge of each strip-shaped pressure receiving plate. Thereafter, as in the description of FIG. 2C, the drilling machine 11 is inserted into the anchor through hole 9 of the strip-shaped pressure receiving plate 2 'to form an anchor hole reaching the ground from the cut surface 1'. PC in this hole
The steel anchor material 10 is inserted and grout is injected. When the grout hardens, the anchor material is tensioned and fixed in the anchor through-hole 9, and the fixing portion is closed with the lid 3 (see FIG. 9). A rear face of the strip-shaped pressure receiving plate 2 ′ and the horizontally long pressure receiving plate 4;
Embankment e required for clearance between the vertical slope and the slope
I do. When one stage is completed in this way, FIG.
The next step is made by repeating the steps (A) to (C). In this case, if the slope is a natural slope, one step is created from the bottom to the top, and if the slope is a cut slope, one step is created from the top to the bottom, so that the work procedure and safety are good.

【0020】段落0012で述べたように、地山の土質
が粘性土等のように安定している場合は図8に示したよ
うに棚状水平面1の背後に鉛直状の切土面1′を形成
し、短冊形受圧板2′及び横長受圧板4を切土面1′に
接触させながら水平面1に一列に立て並べることができ
るが、土質によっては工事中の崩落を防ぐため安定した
斜面となるように傾斜して切土し、短冊形受圧板2′か
ら垂下する脚7を傾斜切土面1”の前に沿って水平面に
掘った穴5に落とし嵌めて水平面1上に左右に一定の隣
接間隔を保って立てたり、立ち並んだ短冊形受圧板の隣
接間隔に横長受圧板4を上下に重ねて立てたとき、短冊
形受圧板2′や、横長受圧板4の背面と傾斜切土面1”
の間には、短冊形受圧板のアンカー貫通孔9よりも下方
に達する空隙が生じる場合がある(図13参照)。その
ときには短冊形受圧板2を立て並べ、短冊形受圧板の隣
接間隔に横長受圧板4を上下に重ねて立てたあと、その
空隙に単なる土砂ではなく道路路盤として使用されるク
ッラシャラン(切込み砕石)等の圧縮強度の大きな裏込
め材を短冊形受圧板の高さの約2/3程度まで充填、転
圧して裏込め強化層Cを形成することによりに裏込め強
化層で空隙を埋め、短冊形受圧板のアンカー用貫通孔9
から穿孔機11を裏込め強化層Cを経て土中へ差込み、
傾斜切土面1”から地山に達するアンカー穴を水平に近
い下向き傾斜角(10°付近)で次々と削孔し、そのア
ンカー穴にそれぞれアンカー材10を挿入し、アンカー
材の挿入後、アンカー穴にグラウト(モルタル)を注入
し、その固化後、アンカー材を緊張させてプレストレス
をかけ、短冊形受圧板2′のアンカー用貫通孔9に定着
する。これにより、強度が発現するまで長時間待たねば
ならないコンクリートを空隙に充填する場合にくらべて
工期は短縮し、経済的に施工できる。尚、裏込め強化層
Cの上には盛土eをし、受圧板の上端と地山斜面との間
を塞ぐ。
As described in the paragraph 0012, when the soil quality of the ground is stable such as clayey soil, a vertical cut surface 1 'behind the shelf-like horizontal surface 1 as shown in FIG. And the strip-shaped pressure receiving plate 2 'and the horizontally long pressure receiving plate 4 can be arranged in a line on the horizontal surface 1 while making contact with the cut surface 1'. However, depending on the soil quality, a stable slope is required to prevent collapse during construction. Then, the leg 7 hanging from the strip-shaped pressure receiving plate 2 'is dropped and fitted into a hole 5 dug in a horizontal plane along the front of the inclined cut surface 1 ", and the cut 7 is left and right. When the vertical pressure receiving plate 4 is erected at a certain interval, or when the horizontal pressure receiving plate 4 is vertically stacked at the adjacent distance between the strip-shaped pressure receiving plates, the rear surface of the rectangular pressure receiving plate 2 ′ or the back of the horizontal pressure receiving plate 4 is inclined. Soil 1 "
In some cases, a gap may be formed below the anchor through hole 9 of the strip-shaped pressure receiving plate (see FIG. 13). At this time, the strip-shaped pressure receiving plates 2 are arranged side by side, and the horizontally long pressure-receiving plates 4 are vertically stacked at intervals adjacent to the strip-shaped pressure receiving plates. Filling the backing material with high compressive strength to about 2/3 of the height of the strip-shaped pressure receiving plate and rolling it to form the backfill reinforcing layer C, thereby filling the voids with the backfill reinforcing layer, Through hole 9 for anchor of pressure receiving plate
From the drilling machine 11 through the backfill reinforcement layer C and into the soil,
Anchor holes reaching the ground from the sloping cut surface 1 "are drilled one after another at a nearly horizontal downward inclination angle (around 10 °), and anchor materials 10 are inserted into the anchor holes respectively. After grout (mortar) is injected into the anchor hole and solidified, the anchor material is tensioned to apply a prestress and is fixed in the anchor through hole 9 of the strip-shaped pressure receiving plate 2 '. The construction period is shorter and more economical than when filling the voids with concrete that has to wait for a long time.The embankment e is placed on the backfill reinforcement layer C, and the upper end of the pressure receiving plate and the ground slope Close between.

【0021】図9、10は図8(C)のコンクリート製
の短冊形受圧板2′と横長受圧板4の構成を示す。寸法
を例示すると、短冊形受圧板2′は高さが段差と同程度
の2mであり、横幅は700mm、厚み300mmの長
方形の版体の下に、直径300mm、長さ600mmの
脚7が付き、両側縁に幅、深さとも100mmの縦溝1
6があって、厚さ80mm、横幅2m、高さ1mの横長
受圧板4の一端を受入れるようになっている。縦溝16
の位置は短冊形受圧板2′の厚みの半ばより後側へ25
mmだけ寄っていて、土圧を受止める前側溝壁を厚くし
ている。横長受圧板にも編組鉄筋や、プレストレスを与
えたPC鋼材を内蔵させて補強してもよい。又、短冊形
受圧板2′にも、図3、5の四角形受圧板2と同様、編
組鉄筋14とプレストレスを与えたPC鋼材13とを内
蔵させれば、軽量でアンカーによる集中荷重に耐える曲
げ強度を得られると共に、脚7との取付強度を高めるこ
とができる。なお、縦溝16の溝は少し外開きとして、
短冊形受圧板2′と横長受圧板4との向きが違っても屈
折接続できるようにしておくと、切土面1′が湾曲して
いても対応できる(図10B参照)。
FIGS. 9 and 10 show the configuration of the strip-shaped pressure receiving plate 2 'and the horizontally long pressure receiving plate 4 made of concrete shown in FIG. To illustrate the dimensions, the strip-shaped pressure receiving plate 2 ′ has a height of about 2 m, which is almost the same as the step, and a leg 7 having a diameter of 300 mm and a length of 600 mm is provided below a rectangular plate having a width of 700 mm and a thickness of 300 mm. A vertical groove 1 with 100 mm width and depth on both sides
6 for receiving one end of a horizontally long pressure receiving plate 4 having a thickness of 80 mm, a width of 2 m and a height of 1 m. Flute 16
Is located at a position 25 rearward from the middle of the thickness of the strip-shaped pressure receiving plate 2 '.
mm, and the front groove wall for receiving earth pressure is thickened. The horizontally long pressure receiving plate may be reinforced by incorporating a braided reinforcing bar or a prestressed PC steel material. Also, if the braided reinforcing bar 14 and the prestressed PC steel material 13 are incorporated in the strip-shaped pressure receiving plate 2 ', similarly to the rectangular pressure receiving plate 2 in FIGS. The bending strength can be obtained, and the mounting strength with the leg 7 can be increased. In addition, the groove of the vertical groove 16 is slightly opened outward,
If the strip-shaped pressure receiving plate 2 'and the horizontally long pressure receiving plate 4 have different directions, refraction connection is possible, so that the cut surface 1' can be curved (see FIG. 10B).

【0022】短冊形受圧板2′にも、図9(A)、図1
1のように上端面の左右および前面下端部の左右に、そ
れぞれインサートアンカー15を設け、下段の短冊形受
圧板2′の上端面のインサートアンカーと、上段のもの
の前面下端部又は上端面のインサートアンカーとを、図
6に示したと同様にターンバックル15cを介してボル
ト、座板などでつなぎ止め、ターンバックル15cを回
して上段の支柱を下段の支柱と同じ正しい姿勢に調整、
保持できるようにすることが好ましい。
FIG. 9A and FIG.
1, insert anchors 15 are provided on the left and right sides of the upper end face and on the left and right sides of the lower end of the front face, respectively. The insert anchors on the upper end face of the lower rectangular pressure receiving plate 2 'and the inserts on the lower front face or the upper end face of the upper one are provided. The anchor is connected with a bolt, a seat plate or the like via a turnbuckle 15c in the same manner as shown in FIG. 6, and the turnbuckle 15c is turned to adjust the upper support to the same correct posture as the lower support,
Preferably, it can be retained.

【0023】以上、この発明ののり留め工法と、その受
圧板、受圧装置の実施形態について説明したが、この発
明はその要旨を変えることなく、実施条件に応じて変
化、応用し得ることは言うまでもなく、四角形のり留め
受圧板や短冊形受圧板の脚は一本に限らず、複数本にし
てもよい。斜面に順次所要段差で棚状水平面を作るとい
っても、一段だけの場合も当然あり得る。受圧板2、
2′の高さは水平面の段差に正確に一致させる必要はな
く、少し高くてもよく、又、それらが立つ姿勢は要すれ
ば鉛直より多少傾斜させてもよい。
The embodiments of the gluing method and the pressure receiving plate and the pressure receiving device according to the present invention have been described above, but it goes without saying that the present invention can be changed and applied according to the working conditions without changing the gist. In addition, the number of legs of the square-shaped pressure receiving plate or the rectangular pressure receiving plate is not limited to one but may be plural. Even if it is necessary to form a shelf-like horizontal surface with a required step on the slope, it is naturally possible that there is only one step. Pressure plate 2,
The height of 2 'does not need to be exactly equal to the level difference in the horizontal plane, but may be slightly higher, and the posture in which they stand may be slightly inclined from the vertical if necessary.

【0024】[0024]

【発明の効果】従来、のり面の地崩れ防止のため斜面沿
いに組んだコンクリートフレームを、PC鋼材のアンカ
ー材により地山につなぎ留める工法が開発されて、大き
な成果を挙げて来た。その後、斜面緑化のため斜面に沿
いつつコンクリートフレームを階段状に鉛直に立て、そ
れらの間に植樹する緑化擁壁が開発された。しかし、こ
の発明は緑化擁壁の鉛直に立つコンクリートフレームを
単なる土留め材でなく、地すべり防止用受圧板とする工
法に発展させた。すなわち、水平面の背後の切土面に接
して立つ受圧板から強力な支柱となる脚を地山にさし込
むことにより、アンカー材に層状地すべりを抑えるに足
るプレストレスを与えて定着しても、受圧板が安定的に
これを受止めるようにした。そしてアンカー材の斜下向
き傾斜を水平に近づけることにより、受圧板と脚とが層
状地すべりに正対して抑止する効果を挙げ得る。尚、脚
埋め込みによる自立方式及び補強用PC鋼材の使用(プ
レストレスの導入)により、受圧板の強度を高め重量も
軽減できるので、現場での運搬、設置等の作業性が向上
し経済的になった。
Conventionally, a construction method has been developed in which a concrete frame assembled along a slope to prevent a landslide on a slope is connected to the ground with a PC steel anchor material, and great results have been obtained. Later, a greening retaining wall was developed, in which the concrete frame was erected vertically along the slope to make the slope greener, and trees were planted between them. However, the present invention has developed a method of using a concrete frame that stands vertically on a greening retaining wall as a pressure receiving plate for preventing landslides, not as a simple earth retaining material. In other words, by inserting the legs serving as strong supports from the pressure receiving plate standing in contact with the cut surface behind the horizontal plane into the ground, the anchor material is given a prestress sufficient to suppress the layered landslide and settles. The pressure receiving plate stably receives the pressure. Then, by making the slope of the anchor member downwardly inclined closer to the horizontal, an effect of suppressing the pressure receiving plate and the leg from directly facing the layered landslide can be obtained. In addition, the strength of the pressure receiving plate can be increased and the weight can be reduced by the self-standing system with embedded legs and the use of PC steel for reinforcement (introduction of pre-stress), so that the workability of transportation and installation at the site is improved and economic became.

【図面の簡単な説明】[Brief description of the drawings]

【図1】請求項1の発明による外観の説明図である。FIG. 1 is an explanatory view of an external appearance according to the invention of claim 1;

【図2】請求項1の工程説明図で、(A)は棚状水平面
を作り、垂直穴を掘下げている状態、(B)は四角形受
圧板を立て並べている状態、(C)は穿孔機でアンカー
穴を明け、アンカーを定着している状態、(D)はブロ
ック背面に盛り土して一段完成した状態を示す。
2 (A) is a process explanatory view of claim 1, wherein (A) is a state in which a vertical shelf is formed and a vertical hole is dug, (B) is a state in which square pressure receiving plates are vertically arranged, and (C) is a drilling machine. Shows a state in which the anchor hole is drilled and the anchor is fixed, and (D) shows a state in which the block is buried on the back surface and completed one step.

【図3】(A)は図1の請求項1によるのり留め状態の
正面図、(B)は(A)の断面図である。
3A is a front view of the glued state according to claim 1 of FIG. 1, and FIG. 3B is a cross-sectional view of FIG.

【図4】(A)は図3(A)の平面図、(B)は受圧板
2の第2例の平面図、(C)は受圧板2の第3例の平面
図、(C′)は(C)の要部の拡大平面図である。
4A is a plan view of FIG. 3A, FIG. 4B is a plan view of a second example of the pressure receiving plate 2, FIG. 4C is a plan view of a third example of the pressure receiving plate 2, and FIG. () Is an enlarged plan view of a main part of (C).

【図5】(A)は受圧板2の内部の編組鉄筋の立面図、
(B)は(A)の平面図である。
5A is an elevation view of a braided reinforcing bar inside the pressure receiving plate 2, FIG.
(B) is a plan view of (A).

【図6】図1の上下段の四角形受圧板の組立状況説明図
である。
FIG. 6 is an explanatory diagram of an assembling situation of upper and lower quadrangular pressure receiving plates of FIG. 1;

【図7】請求項3の発明による外観の説明図である。FIG. 7 is an explanatory view of an appearance according to the invention of claim 3;

【図8】請求項3の工程説明図で、(A)は棚状水平面
を作り、垂直穴を掘下げている状態、(B)は短冊形受
圧板を立て並べている状態、(C)は短冊形受圧板相互
間に横長受圧板を渡し嵌めている状態を示す。
8 (A) is a state in which a vertical shelf is dug down, (B) is a state in which strip-shaped pressure receiving plates are erected, and (C) is a strip. FIG. 4 shows a state in which a horizontally long pressure receiving plate is inserted between the pressure receiving plates.

【図9】(A)は請求項3によるのり留め状態の正面
図、(B)は(A)の断面図である。
9A is a front view of a glued state according to claim 3, and FIG. 9B is a cross-sectional view of FIG. 9A.

【図10】(A)は図9(A)の平面図、(B)は図1
0(A)の部分拡大図である。
10A is a plan view of FIG. 9A, and FIG.
It is the elements on larger scale of 0 (A).

【図11】図7の上下段の短冊形受圧板の組立状況説明
図である。
11 is an explanatory view of the assembling situation of the upper and lower strip-shaped pressure receiving plates of FIG. 7;

【図12】請求項2によるのり留め状態の断面図であ
る。
FIG. 12 is a sectional view of a glued state according to claim 2;

【図13】請求項4によるのり留め状態の断面図であ
る。
FIG. 13 is a sectional view of a glued state according to claim 4;

【符号の説明】[Explanation of symbols]

1 水平面 1′1″ 切土面 2 四角形受圧板 2′ 短冊形受圧板 4 横長受圧板 7 脚 10 アンカー材 DESCRIPTION OF SYMBOLS 1 Horizontal surface 1'1 "Cut surface 2 Square pressure receiving plate 2 'Rectangular pressure receiving plate 4 Horizontal long pressure receiving plate 7 Leg 10 Anchor material

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 のり面を所要段差で削って植栽用の水平
面と、この水平面の背後に連なった切土面とを有する段
を階段状に形成し、その各水平面の切土面の前に沿って
左右に所要間隔で穴を削孔し、その各穴に広幅で、高さ
が上記段差と同程度の四角な大形版体の受圧板から垂下
する脚を挿入して複数の受圧板を切土面に概ね接触させ
ながら水平面上に左右一列に隣接させて立て並べ、上記
各受圧板に予め開設されたアンカー用貫通孔から切土面
を経てアンカー材を斜め下向きに挿入し、アンカー材の
先端部を地山に固定し、このアンカー材にプレストレス
をかけてアンカー材の他端部を各受圧板のアンカー用貫
通孔に定着することを各段ごとに行うことを特徴とする
のり留め工法。
1. A step having a horizontal surface for planting and a cutting surface connected behind the horizontal surface is formed in a stair-like shape by shaving a slope with a required step, and the cutting surface of each horizontal surface is formed in front of the cutting surface. Holes are drilled at required intervals to the left and right along the width of each hole. Standing vertically in a horizontal line on a horizontal surface while making the plate almost in contact with the cut surface, insert the anchor material obliquely downward through the cut surface from the through hole for anchor previously established in each of the pressure receiving plates, Fixing the tip of the anchor material to the ground, prestressing this anchor material and fixing the other end of the anchor material to the through hole for anchor of each pressure receiving plate is performed for each step. Gluing method.
【請求項2】 のり面を所要段差で削って植栽用の水平
面と、この水平面の背後に連なった安定な傾斜切土面と
を有する段を階段状に形成し、その各水平面の傾斜切土
面の前に沿って左右に所要間隔で穴を削孔し、その各穴
に広幅で、高さが上記段差と同程度の四角な大形版体の
受圧板から垂下する脚を挿入して複数の受圧板を水平面
上に左右一列に隣接させて垂直に立て並べ、上記受圧板
と傾斜切土面との間に生じている空隙に圧縮強度の大き
な裏込め材を充填、転圧して裏込め強化層を形成し、上
記各受圧板に予め開設されたアンカー用貫通孔から上記
裏込め強化層及び傾斜切土面を経てアンカー材を斜め下
向きに挿入し、アンカー材の先端部を地山に固定し、こ
のアンカー材にプレストレスをかけてアンカー材の他端
部を各受圧板のアンカー用貫通孔に定着することを各段
ごとに行うことを特徴とするのり留め工法。
2. A step having a horizontal surface for planting and a stable inclined cutting surface connected to the rear of the horizontal surface is formed in a step-like manner by shaving the slope with a required step, and the inclined cutting of each horizontal surface is performed. Drill holes at the required intervals left and right along the front of the soil surface.In each hole, insert a leg that is wide and has a height that is approximately the same as the above-mentioned step, and that hangs down from a large-sized pressure plate. A plurality of pressure receiving plates are vertically arranged vertically adjacent to each other on a horizontal plane in a horizontal plane, and a gap between the pressure receiving plate and the inclined cut surface is filled with a backing material having a large compressive strength and rolled. A backfill reinforcement layer is formed, and the anchor material is inserted obliquely downward from the anchor through-hole previously formed in each of the pressure receiving plates, through the backfill reinforcement layer and the inclined cut surface, and the tip of the anchor material is grounded. Fix the anchor to the mountain, prestress this anchor and apply the other end of the anchor to the A gluing method, wherein fixing to a through hole for a car is performed for each step.
【請求項3】 のり面を所要段差で削って植栽用の水平
面と、この水平面の背後に連なった切土面とを有する段
を階段状に形成し、その各水平面の切土面の前に沿って
左右に所要間隔で穴を削孔し、その各穴に細幅で、高さ
が上記段差と同程度の短冊形受圧板から垂下する脚を挿
入して複数の短冊形受圧板を切土面に概ね接触させなが
ら水平面上に左右に一定の隣接間隔を保って立て並べ、
上記短冊形受圧板の各隣接間隔に横長受圧板を左右の短
冊形受圧板に係合させて短冊形受圧板の高さまでに積み
立て、上記短冊形受圧板に予め開設されたアンカー用貫
通孔から切土面を経てアンカー材を斜め下向きに挿入
し、アンカーの先端部を地山に固定し、このアンカー材
にプレストレスをかけてアンカー材の他端部を各短冊形
受圧板のアンカー用貫通孔に定着することを、各段ごと
に行うことを特徴とするのり留め工法。
3. A step having a horizontal surface for planting and a cutting surface continuous behind the horizontal surface is formed in a step-like manner by shaving the slope with a required step, and the cutting surface in front of the cutting surface of each horizontal surface is formed. Holes are drilled at required intervals to the left and right along the length of each hole, and a plurality of strip-shaped pressure receiving plates are inserted into each of the holes by inserting legs that are narrow and have a height that is approximately the same as the height of the step. Standing vertically on the horizontal surface with a certain adjacent interval on the horizontal plane while making almost contact with the cut surface,
At each adjacent interval of the rectangular pressure receiving plate, a horizontally long pressure receiving plate is engaged with the left and right rectangular pressure receiving plates and stacked up to the height of the rectangular pressure receiving plate, and from the anchor through hole previously established in the rectangular pressure receiving plate. Insert the anchor material obliquely downward through the cut surface, fix the tip of the anchor to the ground, apply prestress to this anchor material, and pass the other end of the anchor material through each strip-shaped pressure plate for anchoring A gluing method, wherein fixing to holes is performed for each step.
【請求項4】 のり面を所要段差で削って植栽用の水平
面と、この水平面の背後に連なった安定な傾斜切土面と
を有する段を階段状に形成し、その各水平面の傾斜切土
面の前に沿って左右に所要間隔で穴を削孔し、その各穴
に細幅で、高さが上記段差と同程度の短冊形受圧板から
垂下する脚を挿入して複数の短冊形受圧板を水平面上に
左右に一定の隣接間隔を保って垂直に立て並べ、上記短
冊形受圧板の各隣接間隔に横長受圧板を左右の短冊形受
圧板に係合させながら短冊形受圧板の高さまで垂直に積
み立て、上記短冊形受圧板、横長受圧板と傾斜切土面と
の間に生じている空隙に圧縮強度の大きな裏込め材を充
填、転圧して裏込め強化層を形成し、上記短冊形受圧板
に予め開設されたアンカー用貫通孔から上記裏込め強化
層及び傾斜切土面を経てアンカー材を斜め下向きに挿入
し、アンカーの先端部を地山に固定し、このアンカー材
にプレストレスをかけてアンカー材の他端部を各短冊形
受圧板のアンカー用貫通孔に定着することを、各段ごと
に行うことを特徴とするのり留め工法。
4. A step having a horizontal surface for planting and a stable inclined cutting surface connected to the rear of the horizontal surface by shaving the slope with a required step to form a step-like step, and the inclined cutting of each horizontal surface Holes are drilled at required intervals to the left and right along the front of the soil surface, and a plurality of strips are inserted into each of the holes by inserting legs that are narrow and have a height that is approximately the same as the step above, and that hang from a strip-shaped pressure receiving plate. The pressure-receiving plates are vertically arranged on the horizontal surface with a certain interval between them on the left and right sides, and the rectangular pressure-receiving plates are engaged with the horizontal pressure-receiving plates at the adjacent intervals of the rectangular pressure-receiving plates while engaging with the left and right rectangular pressure-receiving plates. Vertically up to the height of the above, filling the gap between the above-mentioned strip-shaped pressure receiving plate, the horizontally long pressure receiving plate and the inclined cut surface with a backing material with high compressive strength, and rolling it to form a backfill reinforcing layer , The backfill reinforcement layer and the inclined cut surface from the through hole for anchor previously established in the rectangular pressure receiving plate. After that, insert the anchor material obliquely downward, fix the tip of the anchor to the ground, apply prestress to this anchor material, and fix the other end of the anchor material to the anchor through hole of each strip-shaped pressure receiving plate. A gluing method characterized in that this is performed for each stage.
【請求項5】 のり面を所要段差で削って植栽用の水平
面と、水平面の背後に連なった切土面とを形成した階段
状の各段の、上記切土面に概ね接触して前記水平面上に
左右一列に隣接して立て並べるコンクリート製ののり留
め受圧板であって、広幅で、高さが上記段差と同程度の
四角な大形版体と、この大形版体の下端面から一体に垂
下し、水平面の地中に埋設される脚とからなり、上記大
形版体には切土面に概ね接触させて水平面上に立てた
時、切土面を経て斜め下向きにアンカー材を挿入でき、
且つアンカー材の端部を定着することができるアンカー
用貫通孔を設けたことを特徴とするのり留め受圧板。
5. The method according to claim 5, wherein said slope is cut at a required step to form a horizontal surface for planting and a cut surface connected to the horizontal surface to form a cut surface. A large-sized rectangular plate having a wide width and the same height as the above-mentioned step, and a lower end surface of the large-sized plate, which is a concrete glue-receiving pressure plate which is arranged vertically adjacent to a horizontal line on a horizontal plane. From the ground, and the large plate is placed on the horizontal surface almost in contact with the cut surface, and anchored diagonally downward through the cut surface Material can be inserted,
A glue receiving pressure plate provided with a through hole for an anchor capable of fixing an end of an anchor material.
【請求項6】 のり面を所要段差で削って植栽用の水平
面と、水平面の背後に連なった切土面とを形成した階段
状の各段の、上記切土面の前で前記水平面上に左右一列
に立て並べるコンクリート製ののり留め受圧板装置であ
って、細幅で、高さが上記段差と同程度の短冊版体と、
この版体の下端面から一体に垂下し、水平面の地中に埋
設される脚を備え、前記短冊版体を切土面に概ね接触さ
せて水平面上に左右に特定の間隔を保って立て並べる短
冊形受圧板と、上記短冊形受圧板の隣接間隔に、該受圧
板の高さまで積み立てられる横長受圧板とからなり、前
記短冊形受圧板の短冊版体には切土面を経て斜め下向き
にアンカー材を挿入でき、且つアンカー材の端部を定着
することができるアンカー用貫通孔を設けると共に、短
冊版体の左右の側部と、これに対向する横長受圧板の左
右の側部には凹凸の係合部を設けたことを特徴とするの
り留め受圧装置。
6. A stepped step formed by shaving a slope with a required step to form a horizontal plane for planting and a cut plane connected to the rear of the horizontal plane. A pressure plate device made of concrete which is arranged vertically in a row on the left and right sides, and has a narrow width and a height of about the same height as the step, and
It is provided with legs which are integrally hung from the lower end surface of the plate body and are buried in the ground in a horizontal plane, and the strip plate bodies are substantially in contact with a cut surface, and are vertically arranged on the horizontal plane with a specific space left and right. A strip-shaped pressure receiving plate and a horizontally long pressure-receiving plate that is stacked up to the height of the pressure-receiving plate at adjacent intervals of the strip-shaped pressure-receiving plate, and the strip plate of the strip-shaped pressure-receiving plate faces obliquely downward through a cut surface. Anchor material can be inserted and an anchor through hole can be provided to fix the end of the anchor material.In addition, the left and right sides of the strip plate and the left and right sides of the horizontally long pressure receiving plate opposed thereto are provided. A gluing pressure receiving device comprising an uneven engagement portion.
JP28754298A 1997-12-17 1998-10-09 Gluing method Expired - Lifetime JP3247348B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28754298A JP3247348B2 (en) 1997-12-17 1998-10-09 Gluing method

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP9-347743 1997-12-17
JP34774397 1997-12-17
JP28754298A JP3247348B2 (en) 1997-12-17 1998-10-09 Gluing method

Publications (2)

Publication Number Publication Date
JPH11236712A true JPH11236712A (en) 1999-08-31
JP3247348B2 JP3247348B2 (en) 2002-01-15

Family

ID=26556767

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28754298A Expired - Lifetime JP3247348B2 (en) 1997-12-17 1998-10-09 Gluing method

Country Status (1)

Country Link
JP (1) JP3247348B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108914954A (en) * 2018-08-22 2018-11-30 中国电建集团成都勘测设计研究院有限公司 Slope support method of the pre support in conjunction with permanent support

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108914954A (en) * 2018-08-22 2018-11-30 中国电建集团成都勘测设计研究院有限公司 Slope support method of the pre support in conjunction with permanent support
CN108914954B (en) * 2018-08-22 2020-04-14 中国电建集团成都勘测设计研究院有限公司 Slope supporting method combining pre-supporting and permanent supporting

Also Published As

Publication number Publication date
JP3247348B2 (en) 2002-01-15

Similar Documents

Publication Publication Date Title
US20060193699A1 (en) Construction work and method of production
JP2007530833A (en) Reinforced soil retaining wall system and construction method
KR20090007144A (en) Retaining wall using stone for landscape
JP2009221777A (en) Banking structure and its construction method
KR20030097085A (en) A Precast Concrete Block for Retaining-Wall and Construction Method of Retaining-Wall for using Top-down Method
US5356242A (en) System and method for adjustably connecting wall facing panels to the soldier beams of a tie-back or anchored wall
JP2020070705A (en) Method for constructing lightweight fill retaining wall structure
JP2004100157A (en) Retaining wall structure and its construction method
JP3465026B2 (en) Forming method of pressure plate type foundation
KR101007566B1 (en) Structure of reinforcing cut-slope using nailing and anchoring device and the method of constructing the same
JP3247348B2 (en) Gluing method
JPS6245801A (en) Construction of structure by foamed resin block
JP2000144769A (en) Method of landslide protection work for preparing housing lot
JP2641182B2 (en) Slope stabilization method and slope expansion method
KR100660989B1 (en) Revetment structure
JPH0480432A (en) Water permeable temporary sheathing material and concrete wall construction method
JP2523234B2 (en) Anchor retaining wall
KR102272494B1 (en) Slope reinforcement structure using support and tension and Its Construction method
JP2002070024A (en) Earth retaining frame and earth retaining method of slope or the like
JP2843532B2 (en) Reticulated formwork with finishing plate
JPH0841880A (en) Method of planting face of slope of banking
KR20060134651A (en) Landscape facilities and constuction method thereof
JP2004197408A (en) Sheathing structure
JP2601140B2 (en) Independent mountain retaining wall method
JPS6315385Y2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081102

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091102

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101102

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111102

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 11

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 11

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 11

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 11

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131102

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term