KR20060134651A - Landscape facilities and constuction method thereof - Google Patents

Landscape facilities and constuction method thereof Download PDF

Info

Publication number
KR20060134651A
KR20060134651A KR1020050054526A KR20050054526A KR20060134651A KR 20060134651 A KR20060134651 A KR 20060134651A KR 1020050054526 A KR1020050054526 A KR 1020050054526A KR 20050054526 A KR20050054526 A KR 20050054526A KR 20060134651 A KR20060134651 A KR 20060134651A
Authority
KR
South Korea
Prior art keywords
stone
support
stone material
landscaping
landscaping facility
Prior art date
Application number
KR1020050054526A
Other languages
Korean (ko)
Inventor
문창석
정해용
Original Assignee
문창석
정해용
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 문창석, 정해용 filed Critical 문창석
Priority to KR1020050054526A priority Critical patent/KR20060134651A/en
Publication of KR20060134651A publication Critical patent/KR20060134651A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Revetment (AREA)

Abstract

Landscape facilities and a construction method for the same are provided to reduce time and cost for the construction, and maintain a secure state of a retaining wall. Landscape facilities set up on a front side of a slope, comprises a stone material(100), a linking wire(200), and a supporting body(300). One end of the linking wire is connected to the stone material. The supporting body is installed at a predetermined distance from a rear side of the stone material. The other end of the linking wire is connected to the stone material. The supporting body is supported by weight of filler soil charging a gap between the stone material and the slope, to form stepped layers by a plurality of the stone materials. A construction method for the landscape facilities comprises a first step for setting up a plurality of the stone materials, a second step for casting filler concrete to fix the stone material, a third step for connecting neighboring stone materials, a fourth step for installing the supporting body, a fifth step for fixing the supporting body and the stone material to each other, and a six step for filling and tamping the filler soil.

Description

조경시설물과 그 시공방법{LANDSCAPE FACILITIES AND CONSTUCTION METHOD THEREOF}Landscaping facilities and construction methods {LANDSCAPE FACILITIES AND CONSTUCTION METHOD THEREOF}

도 1은 본 발명에 따른 조경시설물을 도시한 측면도.1 is a side view showing a landscaping facility according to the present invention.

도 2a는 본 발명에 따라 조경시설물에 설치된 지지체를 도시한 사시도.Figure 2a is a perspective view showing a support installed in the landscaping facility according to the present invention.

도 2b는 본 발명에 따라 조경시설물에 설치된 지지체를 도시한 평면도.Figure 2b is a plan view showing a support installed in a landscape facility in accordance with the present invention.

도 3a는 본 발명의 다른 실시예에 따른 조경시설물에 설치된 지지체를 도시한 사시도.Figure 3a is a perspective view showing a support installed in a landscaping facility according to another embodiment of the present invention.

도 3b는 본 발명의 다른 실시예에 따른 조경시설물에 설치된 지지체를 도시한 측면도.Figure 3b is a side view showing the support installed in the landscaping facility according to another embodiment of the present invention.

도 4a는 본 발명의 다른 실시예에 따른 조경시설물에 설치된 지지체를 도시한 사시도.Figure 4a is a perspective view showing a support installed in a landscaping facility according to another embodiment of the present invention.

도 4b는 본 발명의 다른 실시예에 따른 조경시설물을 도시한 측면도.Figure 4b is a side view showing a landscape facility according to another embodiment of the present invention.

도 4c는 본 발명의 또 다른 실시예에 따른 조경시설물을 도시한 측면도.Figure 4c is a side view showing a landscape facility according to another embodiment of the present invention.

도 5a는 본 발명의 다른 실시예에 따른 조경시설물을 설치된 지지체를 도시한 사시도.Figure 5a is a perspective view showing a support installed landscaping facility according to another embodiment of the present invention.

도 5b는 본 발명의 다른 실시예에 따른 조경시설물에 설치된 지지체를 도시한 측면도.Figure 5b is a side view showing the support installed in the landscaping facility according to another embodiment of the present invention.

<도면의 주요 부분에 대한 부호설명><Code Description of Main Parts of Drawing>

100...석재물 200...연결와이어100 ... Stone 200 ... Connection Wire

300...지지체 310...연결공300 ... support 310 ... connector

320...수직플레이트 330...수평플레이트320 ... Horizontal Plate 330 ... Horizontal Plate

340...수직바 350...지지플레이트 340 Vertical Bar 350 Support Plate

본 발명은 조경시설물과 그 시공방법에 관한 것으로서, 석재물과, 상기 석재물에 일단이 연결되는 연결와이어와, 상기 연결와이어의 타단이 고정되는 지지체를 포함하고, 상기 석재물이 연결와이어와 채움토의 자중에 의해 지지되도록 하는 조경시설물과 그 시공방법에 관한 것이다.The present invention relates to a landscaping facility and its construction method, comprising a stone, a connection wire connected to one end of the stone material, and a support on which the other end of the connection wire is fixed, wherein the stone is filled with the connection wire. It relates to a landscaping facility and its construction method to be supported by the discussion weight.

일반적으로 옹벽구조물은 주택부지 및 노변 등에 형성된 경사지, 절토지 및 암반 등의 전면에 이들이 토압 또는 우수 등에 의해 붕괴되는 것을 방지할 수 있도록 형성되는 벽체를 말하는데, 이러한 옹벽구조물은 벽돌 또는 콘크리트 등으로 구축되고, 규모 및 시공의 편리성 등을 고려하여 콘크리트 옹벽구조물이 널리 사용되고 있다.In general, the retaining wall structure refers to a wall that is formed on the front of slopes, cuts, and rocks formed on a housing site and a roadside to prevent them from being collapsed by earth pressure or rainwater. Such a retaining wall structure is constructed of brick or concrete. In addition, concrete retaining wall structures are widely used in consideration of scale and convenience of construction.

그러나, 종래의 콘크리트 옹벽구조물은 그 특성상 설치되는 대상의 경사지 및 암반 등의 형태에 대응한 유연성 및 가변성이 부족하고, 콘크리트 특유의 색상과 획일적인 형태로 인해 위화감을 주는 동시에 주변의 자연경관을 저해시키는 문제가 있었다.However, the conventional concrete retaining wall structure lacks flexibility and variability corresponding to the shape of the slope and rock of the object to be installed due to its characteristics, and gives a sense of discomfort and hinders the surrounding natural landscape due to the unique color and uniform shape of the concrete. There was a problem to let.

이러한 문제점을 해결하기 위해 자연석을 이용한 옹벽 구조물이 소개된바 있다. 즉, 절개면이 형성된 옹벽구조물의 설치 위치를 선정할 때 작업의 안전성을 고려하여 절개면과 옹벽의 설치간격을 넓게 선정하여 절개면의 바닥면에 돌, 자갈 등의 잡석으로 바닥을 다지고, 그 위에 콘크리트를 부어 기초층을 형성하고, 이 기초층 위에 자연석을 올려 콘크리트에 의해 고정되게 한 후, 그 자연석의 이면에 홈을 형성하여 이 홈에 와이어의 일단을 박아 고정하고, 와이어의 타단은 절개면에 고정하여 자연석이 옹벽형태를 유지하는 구성으로 이루어진다. In order to solve this problem, a retaining wall structure using natural stone has been introduced. In other words, when selecting the installation position of the retaining wall structure having the cut surface, in consideration of the safety of the work, the installation interval between the cut surface and the retaining wall is widely selected, and the bottom surface of the cut surface is ground with rubble such as stones and gravel. Pour concrete on top to form a foundation layer, put natural stone on the foundation layer to be fixed by concrete, and then form a groove on the back of the natural stone to fix one end of the wire in this groove, and the other end of the wire is cut It is fixed to the surface and consists of a natural stone to retain the retaining wall shape.

그러나, 이러한 옹벽구조물은 자연석에 설치되는 와이어가 절개면에 견고하게 고정되지 못하여 적층되는 지반의 절개면에 빗물이 스며들거나 지진과 같은 자연재해에 의해 충격이 전달될 경우에는 옹벽 구조물 자체가 안전하지 않게 되는 문제가 있었다. However, such retaining wall structures are not secure when the wires installed in the natural stone are not firmly fixed to the incision surface and the impact is transmitted by natural disasters such as earthquakes or rainwater infiltrating the incision surface of the ground. There was a problem of not going.

본 발명의 목적은 이를 개선하기 위한 것으로서, 옹벽구조물로 자연석과 같은 석재물을 이용하여 조경함으로써 별도의 미관공사가 필요없고, 자연친화적인 환경을 조성할 수 있도록 하는데 있다.An object of the present invention is to improve this, it is possible to create a nature-friendly environment without the need for aesthetics by landscaping using a stone, such as natural stone as a retaining wall structure.

또한, 본 발명은 석재물을 고정하는 연결와이어가 절개면에 고정시 빗물이나 지진과 같은 자연상태에 따라 발생될 수 있는 옹벽의 불안전한 요소를 미연에 방지할 수 있도록 하는 조경시설물과 그 시공방법을 제공하는데 있다.In addition, the present invention is a landscaping facility and its construction method to prevent the unstable elements of the retaining wall that can be generated according to natural conditions such as rainwater or earthquake when the connection wire for fixing the stone is fixed to the incision surface To provide.

상기 목적을 달성하기 위해 본 발명은, 경사면의 전방에 설치되는 조경시설물에 있어서, 석재물과, 상기 석재물에 일단이 연결되는 연결와이어와, 상기 석재물의 후방으로 일정거리 이격되어 설치되고, 상기 연결와이어의 타단이 고정되는 지지체를 포함하고, 상기 지지체는 상기 석재물과 경사면 사이에 채워지는 채움토의 자중에 의해 지지되어 서로 다른 다수개의 석재물이 계단형의 층을 이루도록 설치된다.In order to achieve the above object, the present invention, in a landscaping facility installed in front of the inclined surface, the stone, the connection wire is connected to one end of the stone, and the stone is installed at a predetermined distance apart from the rear, The support wire is fixed to the other end of the connection wire, the support is supported by the weight of the filling soil filled between the stone material and the inclined surface is installed so that a plurality of different stone material to form a stepped layer.

또한, 본 발명은 절토지, 성토지, 또는 암반이 형성된 경사면의 전방에 일정 거리 이격하여 다수개의 석재물을 설치하는 제1단계와, 상기 석재물이 고정되도록 채움 콘크리트를 타설하는 제2단계와, 인접한 석재물을 상호 연결하는 제3단계와, 상기 석재물의 후미와 연결되는 연결와이어를 고정하도록 지지체를 상기 경사면과 석재물 사이에 설치하는 제4단계와, 상기 지지체와 석재물을 상호 연결와이어로 고정하는 제5단계와, 상기 석재물의 후방으로 채움토로 다짐하는 제6단계를 포함하고, 상기 하부 석재물에 상부 석재물이 계단형의 층으로 이루어지도록 상기 제1,3,5,6 단계를 순차적으로 반복 시공한다. 이때, 상기 하부 석재물에 상부 석재물이 계단형의 층으로 이루어지도록 상기 제1,3,5,6 단계를 순차적으로 반복 시공한다. In addition, the present invention is a first step of installing a plurality of stone spaced apart a certain distance in front of the inclined surface cut land, land, or rock formation, and the second step of placing the filling concrete to fix the stone and A third step of interconnecting adjacent stone materials, a fourth step of installing a support between the inclined surface and the stone to fix the connection wire connected to the rear end of the stone, and the support and the stone interconnection wires And a fifth step of fixing to the back of the stone, and a sixth step of compacting with the filling soil to the rear of the stone, wherein the first stone is formed of a stepped layer on the lower stone. Repeat the construction sequentially. At this time, the first, third, fifth, and sixth steps are sequentially repeated so that the upper stone material is made of a stepped layer on the lower stone material.

이하, 본 발명을 상세히 설명하기로 한다.Hereinafter, the present invention will be described in detail.

도 1은 석재물을 이용한 조경시설물의 측면을 도시한 도면이다.1 is a view showing the side of the landscape facility using a stone.

도 1에서 도시된 바와 같이, 본 발명은 다수의 석재물(100)이 계단형의 층으로 이루어지도록 상기 석재물(100)을 연결와이어(200)를 통해 고정하는 지지체(300)가 상기 경사면(700)의 전방에 설치되는 구성으로 이루어진다.As shown in FIG. 1, the present invention provides a support 300 for fixing the stone material 100 through the connection wire 200 such that a plurality of stone materials 100 are formed in a stepped layer. It consists of a configuration that is installed in front of 700).

예컨대, 상기 석재물(100)은 견고한 옹벽의 기능을 수행할 수 있도록 이웃하는 서로 다른 석재물(100)과 셈앙카에 의해 상호 연결되고, 상기 석재물(100)의 후면으로 연결와이어(200)의 일단이 고정된다. 이때, 상기 셈앙카는 시멘트계 혼합물과 특수 첨가물을 주성분으로 한 삽입식 고착제에 의해 상기 석재물(100)에 고정된다.For example, the stone material 100 is connected to each other by the adjacent stone material 100 and Semiangka so as to perform the function of a solid retaining wall, the wire 200 to the rear of the stone material 100 One end of is fixed. At this time, the Semka is fixed to the stone material 100 by an insert fixing agent, which is mainly composed of a cement-based mixture and a special additive.

상기 석재물(100)에 그 일단이 고정되는 연결와이어(200)는 앙카와 턴버클을 통해 상기 석재물에 연결되고, 타단으로 상기 지지체(300)에 고정되도록 설치된다.The connection wire 200, one end of which is fixed to the stone material 100, is connected to the stone material through an anchor and a turnbuckle, and the other end is installed to be fixed to the support 300.

상기 지지체(300)는 상기 석재물(100)의 후방으로 일정거리 이격되어 수직으로 연장 형성되고, 상기 연결와이어(200)의 타단이 상기 지지체에 고정된다.The support 300 is formed to extend vertically spaced apart to the rear of the stone material 100, the other end of the connection wire 200 is fixed to the support.

여기서, 상기 석재물(100)과 지지체(300)는 콘크리트(500)가 타설되는 바닥면에 설치되고, 상기 석재물(100)은 상기 지지체(300)와의 사이에 채워지는 채움토(600)의 자중에 의해 지지되고 서로 다른 다수개의 석재물(100)이 계단형의 층을 이루며 설치된다.Here, the stone material 100 and the support 300 is installed on the bottom surface where the concrete 500 is poured, the stone material 100 of the filling soil 600 is filled with the support 300 A plurality of stone materials 100 supported by their own weight and different from each other are installed in a stepped layer.

계속하여, 첨부된 도면에 의거하여 본 발명의 실시예를 상세히 설명하면 다음과 같다.Subsequently, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

<실시예 1><Example 1>

도 2a는 조경시설물에 설치된 지지체의 사시도를 나타낸 도면이고, 도 2b는 조경시설물에 설치된 지지체의 평면도를 나타낸 도면이다.Figure 2a is a view showing a perspective view of the support installed in the landscaping facility, Figure 2b is a view showing a plan view of the support installed in the landscaping facility.

도 2a 또는 도 2b에서 도시된 바와 같이, 본 발명에 따른 상기 지지체(300)는 지면으로부터 수직으로 연장 형성되는 수직바(340)와, 상기 지지체(300)의 방사방향으로 연장 형성되는 지지플레이트(350)로 구성된다. 이때, 상기 지지플레이트(350)는 사각형상의 판형으로 상기 수직바(340)가 그 중심을 관통하고, 상기 수직바(340)의 길이방향을 따라 소정 간격 이격 되도록 상기 수직바(340)에 다수개가 설치된다. 또한, 상기 수직바(340)에는 서로 다른 크기를 갖는 지지플레이트(350)가 적층형성되되, 하부에 설치된 지지플레이트(350)가 넓은 면적을 갖도록 설치되는 것이 좋다.As shown in FIG. 2A or 2B, the support 300 according to the present invention includes a vertical bar 340 extending vertically from the ground, and a support plate extending radially from the support 300. 350). In this case, the support plate 350 has a rectangular plate shape and a plurality of vertical bars 340 penetrate the center thereof, and a plurality of the support plates 350 are spaced apart at predetermined intervals along the longitudinal direction of the vertical bars 340. Is installed. In addition, the vertical bar 340 is laminated to the support plate 350 having a different size, it is preferable that the support plate 350 installed in the lower portion is installed to have a large area.

이때, 상기 수직바(340)는 수직방향으로 연장형성되는 원기둥 형상의 파이프 형상으로 이루어지고, 상기 수직바(340)에는 상기 연결와이어(200)의 타단이 상기 지지체에 고리형상으로 고정된다.In this case, the vertical bar 340 is formed in a cylindrical pipe shape extending in the vertical direction, the other end of the connection wire 200 is fixed to the support in a ring shape on the vertical bar 340.

<실시예 2><Example 2>

도 3a는 조경시설물에 설치된 지지체의 사시도를 나타낸 도면이고, 도 3b는 조경시설물에 설치된 지지체의 측면도를 나타낸 도면이다.Figure 3a is a view showing a perspective view of the support installed in the landscaping facility, Figure 3b is a view showing a side view of the support installed in the landscaping facility.

도 3a에서 도시된 바와 같이, 본 발명에 따른 상기 지지체(300)는 수직플레이트(320)와, 상기 수직플레이트의 저단부가 수직 고정되는 수평플레이트(330)로 이루어진다. 이때, 상기 수직플레이트(320)는 전면의 중심부를 관통하는 연결공 (310)이 형성되고, 상기 연결공(310)은 일단이 상기 석재물(100)에 고정되는 연결와이어(200)의 타단과 연결된다. As shown in FIG. 3A, the support 300 according to the present invention includes a vertical plate 320 and a horizontal plate 330 at which a lower end of the vertical plate is vertically fixed. At this time, the vertical plate 320 is formed with a connection hole 310 penetrating through the central portion of the front surface, the connection hole 310 and the other end of the connection wire 200, one end is fixed to the stone material 100 and Connected.

도 3b에서 도시된 바와 같이, 상기 지지체(300)는 상기 석재물(100)이 적층되는 층에 대응되도록 상기 지지체(300)와 서로 다른 지지체를 사이에 두고 적층 설치되되, 상기 연결와이어(200)를 구속하는 다수개의 지지체(300)가 종방향으로 채움토의 자중에 의해 고정되고, 적층되는 위치에는 다른 층에 연결된 연결와이어(200)를 구속하도록 다른 크기의 다수개의 지지체(300)가 채움토의 자중에 의해 고정 설치된다.As shown in FIG. 3B, the support 300 is installed to be stacked with the support 300 and different supports interposed therebetween so as to correspond to the layer on which the stone material 100 is stacked, and the connection wire 200. A plurality of supports 300 for restraining the fixed soil in the longitudinal direction is fixed by the weight of the filling soil, a plurality of supports 300 of different sizes so as to restrain the connection wire 200 connected to another layer in the stacked position It is fixedly installed by.

<실시예 3><Example 3>

도 4a는 다른 실시예에 따른 지지체의 정면을 나타낸 도면이고, 도 4b는 상기 지지체가 조경시설물에 설치된 지지체의 측면도를 나타낸 도면이고, 도 4c는 지지체가 조경시설물에 설치되는 다른 실시예에 따라 지지체가 조경시설물에 설치되는 측면도를 나타낸 도면이다.Figure 4a is a view showing the front of the support according to another embodiment, Figure 4b is a view showing a side view of the support installed in the landscaping facility, Figure 4c is a support according to another embodiment in which the support is installed in the landscaping facility Is a view showing a side view installed in the landscape facilities.

본 실시예는 전술된 실시예 1 또는 실시예 2에도 적용이 가능함은 물론이다.This embodiment is also applicable to the above-described embodiment 1 or 2 of course.

도 4a 또는 도 4b에서 도시된 바와 같이, 본 발명에 따른 상기 지지체(300)의 측부방향으로 굴곡면이 형성되어 높이방향으로 연장형성되고, 상기 지지체(300)가 설치되는 각도에 무관하게 전면에 설치된 석재물(100)과 연결와이어(200)를 통해 고정될 수 있도록 상기 굴곡면에는 다수의 연결공(310)이 서로 다른 각도로 바라보도록 형성된다. 또한, 상기 지지체(300)의 저단부는 타설된 채움 콘트리트를 관통하여 소정깊이 저부로 연장되도록 설치된다.As shown in Figure 4a or 4b, the curved surface is formed in the side direction of the support 300 according to the present invention is formed extending in the height direction, regardless of the angle at which the support 300 is installed on the front A plurality of connection holes 310 are formed on the curved surface so as to be fixed through the installed stone 100 and the connection wire 200 to look at different angles. In addition, the bottom end of the support 300 is installed so as to extend through the pour filling concrete to a predetermined depth bottom.

이때, 도 4c에서 도시된 바와 같이, 상기 지지체(300)는 상기 경사면과 대응되는 기울기로 상기 경사면과 하부 석재물 사이에 설치될 수 있다.At this time, as shown in Figure 4c, the support 300 may be installed between the inclined surface and the lower stone in a slope corresponding to the inclined surface.

<실시예 4><Example 4>

도 5a는 또 다른 실시예에 따른 지지체의 정면을 나타낸 도면이고, 도 5b는 상기 지지체가 조경시설물에 설치된 지지체의 측면도를 나타낸 도면이다.Figure 5a is a view showing the front of the support according to another embodiment, Figure 5b is a view showing a side view of the support is installed in the landscaping facility.

본 실시예는 전술된 실시예 1 또는 실시예 2에도 적용이 가능함은 물론이다.This embodiment is also applicable to the above-described embodiment 1 or 2 of course.

도 5a에서 도시된 바와 같이, 본 발명에 따른 상기 지지체(300)의 상하방향으로 굴곡면이 형성되고, 연결공(310)이 그 중앙부에 형성되되, 도 5b에서 도시된 바와 같이, 상기 석재물(100)이 적층되는 층에 대응되도록 상기 연결와이어(200)를 구속하는 다수개의 지지체(300)가 종방향으로 채움토의 자중에 의해 고정된다.As shown in Figure 5a, the curved surface is formed in the vertical direction of the support 300 according to the present invention, the connection hole 310 is formed in the central portion, as shown in Figure 5b, the stone A plurality of supports 300 constraining the connecting wire 200 is fixed by the weight of the filling soil in the longitudinal direction so as to correspond to the layer on which the 100 is stacked.

이와 같은 구성으로 이루어진 본 발명의 시공방법을 설명하면 다음과 같다.Referring to the construction method of the present invention made of such a configuration as follows.

먼저, 조경시설물을 설치하고자 하는 장소를 선정하여 절개공사를 하여 바닥면에 대하여 일정경사를 갖는 경사면을 형성한 후, 그 경사면에 경사면 고정장치를 통하여 절개면을 고정시킨다.First, to select a place to install the landscaping facilities to make an incision to form an inclined surface having a predetermined slope with respect to the floor surface, and then to fix the incision surface through the inclined surface fixing device on the inclined surface.

계속하여, 절개공사를 통해 절토지 또는 암반이 형성된 경사면의 전방으로 일정 거리 이격하여 기초가 되는 다수개의 하부 석재물을 설치하고, 하부 석재물이 고정되도록 채움 콘크리트를 타설한다.Subsequently, a plurality of lower stones, which are the foundations, are installed at a predetermined distance from the front of the inclined surface of the cut ground or rock through the incision, and the filling concrete is poured to fix the lower stones.

여기서, 인접한 하부 석재물을 셈앙카를 통해 상호 연결하고, 상기 하부 석재물의 후미에 앙카와 턴버클을 설치하여 연결와이어의 일단을 고정하고, 지지체를 상기 경사면과 하부 석재물 사이에 설치한 후, 상기 연결와이어의 타단을 상기 지 지체에 고정한다. 상기 지지체를 상기 경사면과 대응되는 기울기로 상기 경사면과 하부 석재물 사이에 설치할 수 있다. 계속하여, 상기 석재물을 상호 연결하는 셈앙카와 석재물을 연결와이어로 긴장되게 고정하는 지지체에 의해 고정된 상기 석재물의 후방으로 뒷채움 다짐하고, 배수층을 설치한다.Here, the adjacent lower stones are interconnected through the semi-anchor, and an anchor and a turnbuckle are installed at the rear of the lower stone to fix one end of the connecting wire, and the support is installed between the inclined surface and the lower stone, and then the connection Secure the other end of the wire to the support. The support may be installed between the inclined surface and the lower stone at an inclination corresponding to the inclined surface. Subsequently, the back-filled compaction is fixed to the rear of the stone, which is fixed by a semi-anka that interconnects the stone and the support that securely fixes the stone with a connection wire, and installs a drainage layer.

상기와 같은 시공방법에 의해 한 층의 석재물이 고정되면, 설치하고자 하는 조경시설물이 계단형의 층을 이루도록 설치된 상기 석재물의 상부로 상부 석재물을 설치한다.When a layer of stone is fixed by the construction method as described above, the upper stone material is installed on top of the stone installed so that the landscaping facility to be installed forms a stepped layer.

상부 석재물을 고정하는 방법은 상기에서 설명한 방법과 같이, 다수개의 상부 석재물을 설치하고, 인접한 상부 석재물을 상호 연결한 후, 상기 지지체와 하부 석재물을 상호 연결와이어로 고정하고, 상기 석재물의 후방으로 뒷채움 다짐하는 과정을 반복하여 원하는 높이의 석재물을 적층하여 시공한다. The method of fixing the upper stone is, as described above, install a plurality of upper stones, interconnecting adjacent upper stones, and then fixing the support and the lower stone with the interconnection wire, the stone Repeat the process of backfilling to the rear of the water to lay and install the stone of the desired height.

이때, 상기 지지체가 수직플레이트와 상기 수직플레이트의 저단부가 수직 고정되는 수평플레이트로 이루어진 경우에는, 다수개의 상부 석재물을 설치하고, 인접한 상부 석재물을 상호 연결한 후, 상기 지지체를 상기 경사면과 상부 석재물 사이에 설치한 후, 상기 지지체와 하부 석재물을 상호 연결와이어로 고정하고, 상기 석재물의 후방으로 뒷채움 다짐하는 과정을 반복하여 원하는 높이의 석재물을 적층하여 시공한다. In this case, when the support is made of a vertical plate and a horizontal plate in which the lower end of the vertical plate is vertically fixed, a plurality of upper stone materials are installed, and adjacent upper stone materials are interconnected, and then the support is formed on the inclined surface and the upper portion. After installing between the stones, the support and the lower stone is fixed with the interconnection wire, the process of compacting the back filling to the rear of the stone is repeated by stacking the stone of the desired height.

이상에서 설명한 바와 같이, 본 발명은 자연석이나 발파석과 같은 석재물에 앵커와 와이어를 통해 연결하여 석재물을 고정 시키고, 안전하고 견고한 옹벽의 기능을 수행함과 동시에 내구성 및 조경효과를 더하여 현장에 맞는 자연친화적인 경 관을 창출할 수 있다.As described above, the present invention is connected to the stone, such as natural stone or blasting stone through anchors and wires to fix the stone, while performing the function of a safe and solid retaining wall and at the same time to add durability and landscaping effect to the natural A friendly landscape can be created.

본 발명은 특정한 실시예에 관련하여 도시하고 설명 하였지만, 이하의 특허청구범위에 의해 제공되는 본 발명의 정신이나 분야를 벗어나지 않는 한도 내에서 본 발명이 다양하게 개량 및 변화 될 수 있다는 것을 당업계에서 통상의 지식을 가진자는 용이하게 알 수 있음을 밝혀 두고자 한다.While the invention has been shown and described with respect to specific embodiments thereof, it will be appreciated that the invention can be variously modified and modified without departing from the spirit or scope of the invention as provided by the following claims. It will be clear to those skilled in the art that they can easily know.

이상에서 살펴본 바와 같이 본 발명에 의하면, 경사진 절개면에 설치되는 옹벽구조물로 자연석과 같은 석재물을 이용함으로써 별도의 미관을 위한 조경공사를 할 필요가 없고, 조경시설물을 완성하는데 소요되는 공사기간이 단축되고, 공사비용이 절감되는 등의 경제적인 효과가 있다.As described above, according to the present invention, there is no need for landscaping work for aesthetics by using stone materials such as natural stones as the retaining wall structure installed on the inclined incision surface, and the construction period required to complete the landscaping facility. This shortens the cost and reduces the cost of construction.

또한, 본 발명은 기존의 삭막한 콘크리트에 의해 옹벽구조물을 시공하던 것을 자연석과 같은 석재물을 이용함으로써 자연 친화적인 경관과 환경을 조성할 수 있다.In addition, the present invention can construct a nature-friendly landscape and environment by using a stone material such as natural stone that the construction of the retaining wall structure by the existing rough concrete.

또한, 본 발명은 석재물을 고정하는 연결와이어가 별도의 지지체에 의해 고정됨으로써 상기 연결와이어가 절개면에 고정시 발생될 수 있는 옹벽의 불안전한 요소를 미연에 방지하여 옹벽상태를 안전하게 유지할 수 있는 이점이 있다.In addition, the present invention can be secured by a separate support for fixing the stone by a separate support to prevent the unsafe element of the retaining wall that may be generated when the connection wire is fixed to the incision surface in order to maintain the retaining wall state safely There is an advantage.

또한, 본 발명은 지지체에 형성된 연결공의 높이와 각도에 따라 연결와이어를 통한 석재물과의 연결이 용이하게 이루어짐으로써 상기 석재물를 다단으로 설치하여도 축조후 안정성이 유지되고, 시공이 용이하게 이루어지는 장점이 있다. In addition, the present invention is easy to connect with the stone material through the connection wire according to the height and angle of the connection hole formed in the support even if the stone is installed in multiple stages stability is maintained after the construction, the construction is made easy There is an advantage.

Claims (9)

경사면의 전방에 설치되는 조경시설물에 있어서,In the landscaping facilities installed in front of the slope, 석재물(100)과,Stone material (100), 상기 석재물(100)에 일단이 연결되는 연결와이어(200)와,A connection wire 200 having one end connected to the stone material 100; 상기 석재물(100)의 후방으로 일정거리 이격되어 설치되고, 상기 연결와이어(200)의 타단이 고정되는 지지체(300)를 포함하고, It is installed to be spaced apart a certain distance to the rear of the stone material 100, and includes a support 300 to which the other end of the connection wire 200 is fixed, 상기 지지체(300)는 상기 석재물(100)과 경사면 사이에 채워지는 채움토의 자중에 의해 지지되어 서로 다른 다수개의 석재물(100)이 계단형의 층을 이루도록 설치되는 것을 특징으로 하는 조경시설물.The support 300 is a landscaping facility, characterized in that supported by the self-weight of the filling soil filled between the stone material 100 and the inclined surface is installed so that a plurality of different stone material (100) forms a stepped layer. 제 1항에 있어서,The method of claim 1, 상기 지지체(300)는 The support 300 is 수직으로 연장 형성되는 수직바(340)와,A vertical bar 340 extending vertically; 상기 지지체(300)의 방사방향으로 연장 형성되는 지지플레이트(350)를 포함하고,It includes a support plate 350 extending in the radial direction of the support 300, 상기 지지플레이트(350)는 상기 수직바(340)의 높이방향을 따라 소정 간격 이격되어 설치되는 것을 특징으로 하는 조경시설물.The support plate 350 is a landscaping facility, characterized in that spaced apart a predetermined interval along the height direction of the vertical bar (340). 제 2항에 있어서,The method of claim 2, 상기 수직바(340)는 원기둥 형상으로 형성되는 것을 특징으로 하는 조경시설물.The vertical bar 340 is a landscaping facility, characterized in that formed in a cylindrical shape. 제 2항에 있어서,The method of claim 2, 상기 수직바(340)에는 서로 다른 크기를 갖는 지지플레이트(350)가 적층형성되되, 하부에 설치된 지지플레이트(350)가 더 넓은 면적을 갖는 것을 특징으로 하는 조경시설물.The vertical bar 340, the support plate 350 having a different size is formed laminated, the landscaping facility, characterized in that the support plate 350 installed on the lower has a larger area. 제 1항에 있어서,The method of claim 1, 상기 지지체(300)는,The support 300, 수직플레이트(320)와,Vertical plate 320, 상기 수직플레이트(320)의 저단부에 수직 연결되는 수평플레이트(330)를 포함하여 상기 석재물(100)과 대응되도록 채움토에 의해 적층 설치되는 것을 특징으로 하는 조경시설물.Landscaping facility, characterized in that the stack is installed by the filling soil so as to correspond to the stone material 100, including a horizontal plate 330 vertically connected to the bottom end of the vertical plate (320). 제 1항 내지 제 5항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 5, 상기 지지체(300)의 전면은 굴곡면으로 형성되고, 상기 굴곡면에는 상기 연결와이어(200)의 타단이 고정되는 연결공(310)이 형성되는 것을 특징으로 하는 조경시설물.The front surface of the support 300 is formed with a curved surface, landscaping facility characterized in that the curved surface is formed with a connection hole 310 is fixed to the other end of the connection wire (200). 제 1항 내지 제 5항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 5, 상기 석재물(100)은 이웃하는 서로 다른 석재물(100)과 상호 연결되는 것을 특징으로 하는 조경시설물.The stone material 100 is a landscaping facility, characterized in that it is interconnected with the neighboring different stone material (100). 절토지, 성토지, 또는 암반이 형성된 경사면의 전방에 일정 거리 이격하여 다수개의 석재물을 설치하는 제1단계; A first step of installing a plurality of stone materials at a predetermined distance from the front of the inclined surface where the cut land, the fill land, or the rock is formed; 상기 석재물이 고정되도록 채움 콘크리트를 타설하는 제2단계;A second step of pouring concrete filling the stone to be fixed; 인접한 석재물을 상호 연결하는 제3단계;A third step of interconnecting adjacent stone materials; 상기 석재물의 후미와 연결되는 연결와이어를 고정하도록 상기 제 1항 내지 제 4항 중 어느 한 항에 따른 지지체를 상기 경사면과 석재물 사이에 설치하는 제4단계; A fourth step of installing the support according to any one of claims 1 to 4 between the inclined surface and the stone to fix the connection wire connected to the tail of the stone; 상기 지지체와 석재물을 상호 연결와이어로 고정하는 제5단계;A fifth step of fixing the support and the stone with interconnection wires; 상기 석재물의 후방으로 채움토로 다짐하는 제6단계를 포함하고,And a sixth step of compacting the filling soil to the rear of the stone, 상기 하부 석재물에 상부 석재물이 계단형의 층으로 이루어지도록 상기 제1,3,5,6 단계를 순차적으로 반복 시공하는 것을 특징으로 하는 조경시설물 시공방법.Landscaping facility construction method characterized in that for repeating the first, third, fifth, sixth step in order to make the upper stone material in the lower stone material in a stepped layer. 절토지, 성토지, 또는 암반이 형성된 경사면의 전방에 일정 거리 이격하여 다수개의 석재물을 설치하는 제1단계; A first step of installing a plurality of stone materials at a predetermined distance from the front of the inclined surface where the cut land, the fill land, or the rock is formed; 상기 석재물이 고정되도록 채움 콘크리트를 타설하는 제2단계;A second step of pouring concrete filling the stone to be fixed; 인접한 석재물을 상호 연결하는 제3단계;A third step of interconnecting adjacent stone materials; 상기 석재물의 후미와 연결되는 연결와이어를 고정하도록 상기 제 5항에 따른 지지체를 상기 경사면과 석재물 사이에 설치하는 제4단계; A fourth step of installing the support according to claim 5 between the inclined surface and the stone to fix the connection wire connected to the rear of the stone; 상기 지지체와 석재물을 상호 연결와이어로 고정하는 제5단계;A fifth step of fixing the support and the stone with interconnection wires; 상기 석재물의 후방으로 채움토로 다짐하는 제6단계를 포함하고,And a sixth step of compacting the filling soil to the rear of the stone, 상기 하부 석재물에 상부 석재물이 계단형의 층으로 이루어지도록 상기 제1,3,4,5,6 단계를 순차적으로 반복 시공하는 것을 특징으로 하는 조경시설물 시공방법.Landscaping facility construction method characterized in that for repeating the first, third, fourth, fifth, sixth step in order to make the upper stone material in the lower stone material in a stepped layer.
KR1020050054526A 2005-06-23 2005-06-23 Landscape facilities and constuction method thereof KR20060134651A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050054526A KR20060134651A (en) 2005-06-23 2005-06-23 Landscape facilities and constuction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050054526A KR20060134651A (en) 2005-06-23 2005-06-23 Landscape facilities and constuction method thereof

Publications (1)

Publication Number Publication Date
KR20060134651A true KR20060134651A (en) 2006-12-28

Family

ID=37812991

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050054526A KR20060134651A (en) 2005-06-23 2005-06-23 Landscape facilities and constuction method thereof

Country Status (1)

Country Link
KR (1) KR20060134651A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100933660B1 (en) * 2009-08-04 2009-12-23 동양이앤씨 주식회사 Structure for supporting stone wall for reinforcement and construction method thereof
KR101020217B1 (en) * 2008-06-12 2011-03-08 최종선 rock construction structure of using anchor and method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101020217B1 (en) * 2008-06-12 2011-03-08 최종선 rock construction structure of using anchor and method thereof
KR100933660B1 (en) * 2009-08-04 2009-12-23 동양이앤씨 주식회사 Structure for supporting stone wall for reinforcement and construction method thereof

Similar Documents

Publication Publication Date Title
US6089792A (en) Reinforced retaining wall
KR20060103309A (en) Gradual bottom-up slice and gradual infilling method for removing underground retaining wall
CN102966119A (en) Geogrid reinforced wall and construction method thereof
EA037484B1 (en) Retaining wall method of precast block to prevent landslide
US5154542A (en) Earth-retaining module, system and method
KR20090007144A (en) Retaining wall using stone for landscape
JP5937488B2 (en) Temporary support method for foundation
JP4979789B2 (en) Construction method of stair-permeable permeable retaining fence
JP2005009210A (en) Reinforced structure of masonry wall and its reinforcing method
JP6240625B2 (en) Retaining wall, creation site and creation method of creation site
JP7115817B2 (en) Reinforced soil wall using large sandbags and retaining method using large sandbags
KR20060134651A (en) Landscape facilities and constuction method thereof
US9243380B2 (en) Reinforced arch with floating footer and method of constructing same
KR102263958B1 (en) the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
CA2818730C (en) Reinforced arch with floating footer and method of constructing same
CN203174626U (en) Geogrid reinforced wall
KR102259659B1 (en) Ornamental stone retaining wall structure and construction method using L type anker and strip bar
KR20090073330A (en) Revetment structure using natural stones
KR20030086233A (en) execution method of landscape architecture for cutting ground using blasting stone and structure of landscape architecture for the same
KR20190004497A (en) A Eco-friendly retain wall structure
KR200413303Y1 (en) Stone stacked wall structure using steel beam
Dellaria et al. Combining multiple techniques to complete an urban deep excavation
JP2020159006A (en) Retaining wall and its construction method
KR101058628B1 (en) Retaining wall construction structure using landscape stones
KR102249603B1 (en) Retaining wall construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application