CN102966119A - Geogrid reinforced wall and construction method thereof - Google Patents

Geogrid reinforced wall and construction method thereof Download PDF

Info

Publication number
CN102966119A
CN102966119A CN201210515042XA CN201210515042A CN102966119A CN 102966119 A CN102966119 A CN 102966119A CN 201210515042X A CN201210515042X A CN 201210515042XA CN 201210515042 A CN201210515042 A CN 201210515042A CN 102966119 A CN102966119 A CN 102966119A
Authority
CN
China
Prior art keywords
grid
geogrids
geo
concrete
anchor pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210515042XA
Other languages
Chinese (zh)
Other versions
CN102966119B (en
Inventor
夏飞
戴征杰
褚景英
赵燕
陈丽丽
王旭龙
杨广庆
朱冀军
陈泽明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO BOSTD GEOSYNTHETICS Ltd
Original Assignee
QINGDAO BOSTD GEOSYNTHETICS Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO BOSTD GEOSYNTHETICS Ltd filed Critical QINGDAO BOSTD GEOSYNTHETICS Ltd
Priority to CN201210515042.XA priority Critical patent/CN102966119B/en
Publication of CN102966119A publication Critical patent/CN102966119A/en
Application granted granted Critical
Publication of CN102966119B publication Critical patent/CN102966119B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The invention provides a geogrid reinforced wall and a construction method thereof. The geogrid reinforced wall comprises a surface layer system and a geogrid reinforced soil body and is characterized in that the other side surface of the geogrid reinforced soil body, which is opposite to the surface layer system, is leaned on a hard slope surface; the hard slope surface is provided with an anchor rod drilled hole; an anchor rod is inserted and fixed in the anchor rod drilled hole; and the geogrid is connected together with the anchor rod by a connecting component. The construction method comprises the following steps: (1) digging of foundation earthwork; (2) construction of a strip foundation; (3) construction of an anchor rod anchoring structure; (4) construction of the connecting component between the geogrid and the anchor rod; and (5) construction of a geogrid reinforcing structure. The invention solves the problem of limitation on space of a reinforcing field; the geogrid reinforced wall adopting a flexible retaining structure can be constructed in regions which are narrow in field, are limited in space and contain rocks and native-state hard soil; the geogrid reinforced wall and the construction method thereof have high construction efficiency and are low in cost; and the wall has a firm and stable structure.

Description

Fill Reinforced With Geogrids body of wall and job practices thereof
Technical field
The invention belongs to the geotechnics field, relate in particular to a kind of Fill Reinforced With Geogrids body of wall and job practices thereof.
Background technology
In the engineering constructions such as present highway, railway, mine, foundation ditch, municipal administration, owing to different geological conditionss adopts different retaining structures.The retaining structure that is used for the excavation side slope in the engineering can be divided into rigidity retaining structure and flexible shoring structure two large classes.
The rigidity retaining structure refers to as main, be aided with other necessary integrated treatment schemes take masonry structure (Gravity Retaining Wall, antislide pile and slabstone facing wall etc.).For the rigidity retaining structure, short retaining structure such as mortar flag stone, Gravity Retaining Wall is bulky, bricklaying is more (highly being generally less than 8m); The steel concrete cantilevered, hold up arm-type barricade (highly being generally less than 10m), such retaining structure engineering time is longer, and cost is relatively high, and anti-seismic performance is relatively poor.
The flexible shoring structure refers to take Fill Reinforced With Geogrids as main, is aided with the processing scheme that other necessary integrated treatment measure combines.The flexible shoring structure belongs to light supporting structure, has good anti-seismic performance, and is lower to the ground requirement for bearing capacity, and the processing of ground is easier.When soft foundation was built, the foundation deformation that causes because banketing was little to the flexible structure stability influence.The stability of flexible shoring structure is born by the Fill Reinforced With Geogrids material that level is laid, so need enough spaces, place to lay reinforcement muscle material.In the rock of difficulty excavation, original state pan soil situation, the use of Fill Reinforced With Geogrids flexible shoring structure is restricted.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of Fill Reinforced With Geogrids body of wall and job practices thereof, can solve the problem of reinforcement place limited space, make that the Fill Reinforced With Geogrids body of wall that adopts the flexible shoring structure is narrow in the place, the zone of limited space and rock, original state pan soil also can construct, efficiency of construction is high, cost is low, and wall body structure is firm, stable.
In order to solve the problems of the technologies described above, the present invention adopts following technical scheme: a kind of Fill Reinforced With Geogrids body of wall, comprise surface layer system and geogrids reinforced earth body, the geogrids reinforced earth body is to replace pressing by the geogrids layer of level laying and backfill packing layer to form, it is characterized in that the described geogrids reinforced earth body another side relative with the surface layer system leans against on the hard slope face, have armature boring on the hard slope face, insert anchor pole and fixing in the armature boring, described geo-grid and described anchor pole link together by connecting elements; Described armature boring aperture is 50-100mm, and described adjacent anchor pole spacing is 60-250cm.
To improvement of the technical scheme: described hard slope face is that rock slope or hard soil are domatic, described connecting elements comprises steel mesh reinforcement, skeleton reinforcing steel bar, described skeleton reinforcing steel bar is latticed and is arranged on the hard slope face, described anchor pole exposes an end weldable steel backing plate, billet on skeleton reinforcing steel bar crossover sites and the corresponding anchor pole connects, described steel mesh reinforcement is arranged on the hard slope face by geogrids reinforced earth body one side, and is connected with geo-grid.
To further improvement in the technical proposal: described geogrids layer adopts the unidirectional geo-grid of high density polyethylene (HDPE), and the backfill packing layer is gravelly soil, gravelly soil and fine grained soils water permeability filler.
To further improvement in the technical proposal: described surface layer system by concrete bear down on one, railing, rubble drainage blanket, concrete modular, mortar mask, gutter, strip foundation form.
To further improvement in the technical proposal: described anchor pole is φ 20-35mm indented bars, and described steel mesh reinforcement is made of the indented bars of φ 10-16mm, and described skeleton reinforcing steel bar is made of the indented bars of φ 16-25mm.
The job practices of a kind of Fill Reinforced With Geogrids body of wall of the present invention, comprise the construction of geogrids reinforced earth body and surface layer system, the geogrids reinforced earth body is to replace pressing by the geogrids layer of level laying and backfill packing layer to form, it is characterized in that the job practices of described Fill Reinforced With Geogrids body of wall comprises the steps: (1) basic earthwork excavation; (2) strip foundation construction; (3) anchor rod anchored structure construction; (4) construction of the connecting elements between geo-grid and anchor pole; (5) Fill Reinforced With Geogrids structure construction;
The concrete steps of described anchor rod anchored structure construction are: open armature boring at the hard slope face near the geogrids reinforced earth body, described armature boring aperture is 50-100mm, described adjacent anchor pole spacing is 60-250cm, inserts anchor pole and fixing with the cement mortar cast in the armature boring; Described geo-grid and described anchor pole link together by connecting elements;
To further improvement in the technical proposal: the concrete steps of the connecting elements construction between described geo-grid and anchor pole are: described hard slope face is that rock slope or hard soil are domatic, connecting elements between described geo-grid and anchor pole comprises steel mesh reinforcement, skeleton reinforcing steel bar, apply anticorrisive agent or lacquer at steel mesh reinforcement and skeleton reinforcing steel bar, expose an end weldable steel backing plate at anchor pole, lay at the hard slope face and to be latticed skeleton reinforcing steel bar, the skeleton reinforcing steel bar crossover sites connects with billet on the corresponding anchor pole; Lay described steel mesh reinforcement at the hard slope face that lays skeleton reinforcing steel bar, steel mesh reinforcement is used for connecting geo-grid; Described anchor pole is φ 20-35mm indented bars, and described steel mesh reinforcement is made of the indented bars of φ 10-16mm, and described skeleton reinforcing steel bar is made of the indented bars of φ 16-25mm.
To further improvement in the technical proposal: the concrete steps of described basic earthwork excavation are: measure unwrapping wire, excavate with smooth by the setting-out position, the excavation bedding is filled out the degree of depth to changing, and through the leveling compacting, makes base bearing capacity reach designing requirement;
The concrete steps of described strip foundation construction are: described strip foundation adopts concrete cast-in-situ, and preformed groove position, to guarantee building by laying bricks or stones smoothly of concrete modular, concrete continuous footing and preformed groove the construction line-putting position are accurate, and it is corresponding with the barricade settlement joint that concrete continuous footing arranges settlement joint;
To further improvement in the technical proposal: described surface layer system by concrete bear down on one, railing, rubble drainage blanket, concrete modular, mortar mask, gutter, concrete continuous footing form; The concrete steps of described Fill Reinforced With Geogrids structure construction are: described geo-grid is unidirectional geo-grid, hanging wire is with the mortar laminated concrete modular of building by laying bricks or stones on concrete continuous footing, then begins the connection of unidirectional grid and the roller compaction construction of backfill gravel drainage blanket and filler within the walls; Every laying one deck unidirectional grid, end connecting reinforcement net or a skeleton reinforcing steel bar of exposing at unidirectional grid; The Specific construction process is as follows:
(1) press the unidirectional geo-grid of design length cutting, must satisfy the requirement of geo-grid design length during cutting, the cutting position is the middle position of geo-grid longitudinal rib;
(2) prefabricated concrete modular is built in layering by laying bricks or stones;
(3) lay the unidirectional geo-grid of first floor;
(4) with pitman unidirectional geo-grid and concrete modular being reserved grid is connected or lays with connector hook grid;
(5) with the stretch-draw beam unidirectional geo-grid is strained, free end is passed skeleton or steel mesh reinforcement bending, fix with pitman, then decontrol the stretch-draw beam;
(6) with loader sandy gravel and filler vertically are poured on the basis of completing unidirectional geo-grid, with excavator or the smooth sandy gravel of bulldozer, shake rolling machine with the sandy gravel compacting with halo, form the backfill packing layer, in the inboard near concrete modular the rubble drainage blanket is set successively, gutter is arranged in rubble drainage blanket and the concrete modular;
(7) repeat above operation to the barricade concrete position of bearing down on one, bearing down on one at concrete arranges railing; Faulting of slab ends end face in the setting of surface layer system arranges the mortar mask;
(8) top layer concrete modular is connected with unidirectional geo-grid, and unidirectional geo-grid laying length is consistent with lower floor.
The present invention compared with prior art has the following advantages and good effect:
The invention provides compound retaining structure and job practices that a kind of Fill Reinforced With Geogrids structure is combined with anchor rod anchored structure, anchor structure is comprised of rock and the anchor pole that is anchored in the rock; Connecting elements between geo-grid and anchor pole partly is comprised of steel mesh reinforcement, skeleton reinforcing steel bar, cast-in-situ concrete etc.
Connecting elements is the transfer device of power among the present invention, will pass to geo-grid by the anchored force of anchor rod anchored structure generation, the tension pull out force that balance reduces because the geo-grid laying length is not enough, thus guarantee the stability of whole retaining structure; As a kind of novel composite support gear form of structure, geo-grid is compared with traditional soil-baffling structure form with the compound retaining structure that anchor pole is combined with to be had: also can construct in the zone of, limited space narrow in the place and rock, original state pan soil, save cost, shorten the engineering time, save the reinforcement place, reduce fill out excavation, wall body structure firmly, the advantage such as stable.
Description of drawings
Fig. 1 be Fill Reinforced With Geogrids body of wall of the present invention structural representation;
Fig. 2 is the partial enlarged drawing shown in the A among Fig. 1;
Fig. 3 is that anchor pole is connected the layout schematic diagram among Fig. 1 with steel mesh reinforcement;
Fig. 4 is the partial enlarged drawing shown in Fig. 3 B;
Fig. 5 is that the I-I of Fig. 4 is to sectional view;
Fig. 6 is the flow chart of a kind of Fill Reinforced With Geogrids wall construction of the present invention method.
Among the figure: 1, concrete bears down on one; 2, railing; 3, rubble drainage blanket; 4, concrete modular; 5, mortar mask; 6, gutter; 7, above-ground route; 8, concrete continuous footing; 9, anchor pole; 10, hard slope face (rock or hard soil); 11, backfill packing layer; 12, geo-grid; 13, steel mesh reinforcement; 14, skeleton reinforcing steel bar; 15, billet; 16, cement mortar; 17, armature boring; 18, cast-in-situ concrete.
The specific embodiment
The present invention will be described in detail below in conjunction with accompanying drawing;
Referring to Fig. 1-Fig. 5, the embodiment of a kind of Fill Reinforced With Geogrids body of wall of the present invention comprises surface layer system and geogrids reinforced earth body, and the geogrids reinforced earth body is to replace pressing by 12 layers of the geo-grid of level laying and backfill packing layer 11 to form.The another side that described geogrids reinforced earth body is relative with the surface layer system leans against on the hard slope face 10, have the substantially vertical armature boring 17 in some and the surface of hard slope face 10 on the hard slope face 10, the aperture of described armature boring 17 is 50-100mm, and the spacing of described adjacent anchor pole 9 is 60-250cm.At the interior insertion anchor poles 9 of armature boring 17 and fixing by cement mortar 16, described geo-grid 12 and described anchor pole 9 link together by connecting elements.
Above-mentioned hard slope face 10 is that rock slope or hard soil are domatic, described connecting elements comprises steel mesh reinforcement 13, skeleton reinforcing steel bar 14, described skeleton reinforcing steel bar 14 is latticed and is arranged on the hard slope face 10, described anchor pole 9 exposes an end weldable steel backing plate 15, billet 15 on skeleton reinforcing steel bar 14 crossover sites and the corresponding anchor pole 9 connects, described steel mesh reinforcement 13 is arranged on the hard slope face 10 by geogrids reinforced earth body one side, and is connected with geo-grid 12.Grid in the described skeleton reinforcing steel bar 14 is greater than the grid in the steel mesh reinforcement 13.
Above-mentioned anchor pole 9 is φ 20-35mm indented bars, generally selects the anchor pole 9 of φ 25 and 32 two kinds of specifications of φ.Described steel mesh reinforcement 13 is made of the indented bars of φ 10-16mm, generally selects the indented bars of φ 12 to consist of steel mesh reinforcement 13.Described skeleton reinforcing steel bar 14 is made of the indented bars of φ 16-25mm, generally selects the indented bars of φ 20 to consist of steel mesh reinforcement 14.
The unidirectional geo-grid of above-mentioned geo-grid 12 layers of employing high density polyethylene (HDPE), backfill packing layer 11 is gravelly soil, gravelly soil and fine grained soils water permeability filler.
Above-mentioned surface layer system by concrete bear down on one 1, railing 2, rubble drainage blanket 3, concrete modular 4, mortar mask 5, gutter 6, concrete continuous footing 8 form.Concrete structure is: concrete continuous footing 8 is laid on below the above-ground route 7, and concrete modular 4 is built in layering by laying bricks or stones on concrete continuous footing 8, and concrete modular 4 lateral surfaces tilt to hard slope face 10.Inboard near concrete modular 4 successively arranges rubble drainage blanket 3, and described gutter 6 is arranged in rubble drainage blanket 3 and the concrete modular 4.Faulting of slab ends end face in the setting of surface layer system arranges mortar mask 5.At the superiors' concrete modular 4 concrete is set and bears down on one 1, concrete bears down on one and railing 2 is set on 1.
The present invention is before the Fill Reinforced With Geogrids wall construction, according to layout plan, site topography figure, fill out the related datas such as excavation, Soil Parameters.After stability calculation, determine following content: the gradient of Fill Reinforced With Geogrids structure, height and form of fracture (whether establishing faulting of slab ends); The model of reinforcement material, length, vertical spacing, return packet length and consumption; Concrete modular, strip foundation and the shape of bearing down on one, size, concrete model and consumption; The arrangement form of anchor pole, skeleton reinforcing steel bar and steel mesh reinforcement, reinforcing bar model and consumption.
Referring to Fig. 1-Fig. 6, the embodiment of a kind of Fill Reinforced With Geogrids wall construction of the present invention method, comprise the construction of geogrids reinforced earth body and surface layer system, the geogrids reinforced earth body is to replace pressing by 12 layers of the geo-grid of level laying and backfill packing layer 11 to form; The surface layer system by concrete bear down on one 1, railing 2, rubble drainage blanket 3, concrete modular 4, mortar mask 5, gutter 6, concrete continuous footing 8 form.
The step that Fill Reinforced With Geogrids wall construction method comprises is as follows:
The first step, the basic earthwork excavation; Second step, the strip foundation construction; The 3rd step, the construction of anchor pole 9 anchor structures; The 4th step, the connecting elements construction that geo-grid 12 and anchor pole are 9; The 5th step, the Fill Reinforced With Geogrids structure construction.
Each step concrete grammar is as follows:
1, the concrete grammar of basic earthwork excavation is: measure unwrapping wire, excavate with smooth by the setting-out position, the excavation bedding is filled out the degree of depth to changing, and through the leveling compacting, makes base bearing capacity reach designing requirement.
2, the concrete grammar of strip foundation construction is: referring to Fig. 1, concrete continuous footing 8 adopts concrete cast-in-situ, and preformed groove position, to guarantee building by laying bricks or stones smoothly of concrete modular 4, concrete continuous footing 8 and preformed groove the construction line-putting position are accurate, and it is corresponding with the barricade settlement joint that concrete continuous footing 8 arranges settlement joint; Concrete continuous footing 8 is laid on below the above-ground route 7.
3, the concrete grammar of anchor rod anchored structure construction is: open armature boring 17 at the hard slope face 10 near the geogrids reinforced earth body, described armature boring aperture is 50-100mm, described adjacent anchor pole 9 spacings are 60-250cm, and armature boring 17 interior insertion anchor poles 9 are also fixing with cement mortar 16 cast; Described geo-grid 12 and described anchor pole 9 link together by connecting elements, such as Fig. 2, shown in Figure 5.
4, the concrete grammar of the connecting elements of 9 of geo-grid 12 and anchor poles construction is: described hard slope face 10 is domatic for rock slope or hard soil, the connecting elements that described geo-grid 12 and anchor pole are 9 comprises steel mesh reinforcement 13, skeleton reinforcing steel bar 14, apply anticorrisive agent or lacquer at steel mesh reinforcement 13 and skeleton reinforcing steel bar 14, expose an end weldable steel backing plate 15 at anchor pole 9, lay at hard slope face 10 and to be latticed skeleton reinforcing steel bar 14, skeleton reinforcing steel bar 14 crossover sites connect with billet 15 on the corresponding anchor pole 9; Lay described steel mesh reinforcement 13 at the hard slope face that lays skeleton reinforcing steel bar 14, steel mesh reinforcement 13 is used for connecting geo-grid 12, on hard slope face 10 surfaces one deck cast-in-situ concrete 18 is arranged; Described anchor pole is φ 20-35mm indented bars, generally selects the anchor pole 9 of φ 25 and 32 two kinds of specifications of φ; Described steel mesh reinforcement 13 is made of the indented bars of φ 10-16mm, generally selects the indented bars of φ 12 to consist of steel mesh reinforcement 13; Described skeleton reinforcing steel bar 14 is made of the indented bars of φ 16-25mm, generally selects the indented bars of φ 20 to consist of steel mesh reinforcement 14.Such as Fig. 3, shown in Figure 5.
5, the concrete grammar of Fill Reinforced With Geogrids structure construction is: referring to Fig. 1, Fig. 2, described geo-grid 12 is the unidirectional geo-grid of high density polyethylene (HDPE), hanging wire is with the mortar laminated concrete modular 4 of building by laying bricks or stones on concrete continuous footing 8, then begins the connection of geo-grid 12 and the roller compaction construction of backfill rubble drainage blanket 3 and backfill packing layer 11 within the walls; Every laying one deck geo-grid 12, end connecting reinforcement net 13 or a skeleton reinforcing steel bar 14 of exposing in geo-grid 12; The Specific construction process is as follows:
(1) press design length cutting geo-grid 12, must satisfy geo-grid 12 design length requirements during cutting, the cutting position is the middle position of geo-grid 12 longitudinal ribs;
(2) prefabricated concrete modular 4 is built in layering by laying bricks or stones;
(3) lay first floor geo-grid 12(and see Fig. 1);
(4) with pitman geo-grid 12 and concrete modular being reserved grid is connected or lays (see figure 1) with connector hook grid;
(5) with the stretch-draw beam geo-grid 12 is strained, free end is passed skeleton or steel mesh reinforcement bending, fix with pitman, then decontrol stretch-draw beam (see figure 2);
(6) with loader sandy gravel and filler vertically are poured on the basis of completing geo-grid 12, with excavator or the smooth sandy gravel of bulldozer, with the sandy gravel compacting, form backfill packing layer 11 with halo vibrations rolling machine; In the inboard near concrete modular 4 rubble drainage blanket 3 is set successively, gutter 6 is arranged on (see figure 1) in rubble drainage blanket 3 and the concrete modular 4;
(7) repeat above operation to barricade concrete 1 position of bearing down on one, bearing down on one at concrete 1 arranges railing 2(and sees Fig. 1); Present embodiment is about 47 layers of backfill packing layer 11 and 47 layers of geo-grid 12; Faulting of slab ends end face in the setting of surface layer system arranges mortar mask 5.
(8) top layer concrete modular 4 is connected the consistent (see figure 1) with lower floor of geo-grid 12 laying lengths with geo-grid 12.
Above disclosed is a kind of preferred embodiment of the present invention only, certainly can not limit with this interest field of the present invention, and the equivalent variations of therefore doing according to claim of the present invention still belongs to the scope that the present invention is contained.

Claims (10)

1. Fill Reinforced With Geogrids body of wall, comprise surface layer system and geogrids reinforced earth body, the geogrids reinforced earth body is to replace pressing by the geogrids layer of level laying and backfill packing layer to form, it is characterized in that the described geogrids reinforced earth body another side relative with the surface layer system leans against on the hard slope face, have armature boring on the hard slope face, insert anchor pole and fixing in the armature boring, described geo-grid and described anchor pole link together by connecting elements; Described armature boring aperture is 50-100mm, and described adjacent anchor pole spacing is 60-250cm.
2. Fill Reinforced With Geogrids body of wall according to claim 1, it is characterized in that described hard slope face is that rock slope or hard soil are domatic, described connecting elements comprises steel mesh reinforcement, skeleton reinforcing steel bar, described skeleton reinforcing steel bar is latticed and is arranged on the hard slope face, described anchor pole exposes an end weldable steel backing plate, billet on skeleton reinforcing steel bar crossover sites and the corresponding anchor pole connects, and described steel mesh reinforcement is arranged on the hard slope face by geogrids reinforced earth body one side, and is connected with geo-grid.
3. Fill Reinforced With Geogrids body of wall according to claim 2 is characterized in that described geogrids layer adopts the unidirectional geo-grid of high density polyethylene (HDPE), and the backfill packing layer is gravelly soil, gravelly soil and fine grained soils water permeability filler.
4. each described Fill Reinforced With Geogrids body of wall according to claim 1-3, it is characterized in that described surface layer system by concrete bear down on one, railing, rubble drainage blanket, concrete modular, mortar mask, gutter, strip foundation form.
5. each described Fill Reinforced With Geogrids body of wall is characterized in that described anchor pole is φ 20-35mm indented bars according to claim 1-3, and described steel mesh reinforcement is made of the indented bars of φ 10-16mm, and described skeleton reinforcing steel bar is made of the indented bars of φ 16-25mm.
6. Fill Reinforced With Geogrids body of wall according to claim 4 is characterized in that described anchor pole is φ 20-35mm indented bars, and described steel mesh reinforcement is made of the indented bars of φ 10-16mm, and described skeleton reinforcing steel bar is made of the indented bars of φ 16-25mm.
7. the job practices of a Fill Reinforced With Geogrids body of wall, comprise the construction of geogrids reinforced earth body and surface layer system, the geogrids reinforced earth body is to replace pressing by the geogrids layer of level laying and backfill packing layer to form, it is characterized in that the job practices of described Fill Reinforced With Geogrids body of wall comprises the steps: (1) basic earthwork excavation; (2) strip foundation construction; (3) anchor rod anchored structure construction; (4) construction of the connecting elements between geo-grid and anchor pole; (5) Fill Reinforced With Geogrids structure construction;
The concrete steps of described anchor rod anchored structure construction are: open armature boring at the hard slope face near the geogrids reinforced earth body, described armature boring aperture is 50-100mm, described adjacent anchor pole spacing is 60-250cm, inserts anchor pole and fixing with the cement mortar cast in the armature boring; Described geo-grid and described anchor pole link together by connecting elements.
8. the job practices of Fill Reinforced With Geogrids body of wall according to claim 7, it is characterized in that, the concrete steps of the connecting elements construction between described geo-grid and anchor pole are: described hard slope face is that rock slope or hard soil are domatic, connecting elements between described geo-grid and anchor pole comprises steel mesh reinforcement, skeleton reinforcing steel bar, apply anticorrisive agent or lacquer at steel mesh reinforcement and skeleton reinforcing steel bar, expose an end weldable steel backing plate at anchor pole, lay at the hard slope face and to be latticed skeleton reinforcing steel bar, the skeleton reinforcing steel bar crossover sites connects with billet on the corresponding anchor pole; Lay described steel mesh reinforcement at the hard slope face that lays skeleton reinforcing steel bar, steel mesh reinforcement is used for connecting geo-grid; Described anchor pole is φ 20-35mm indented bars, and described steel mesh reinforcement is made of the indented bars of φ 10-16mm, and described skeleton reinforcing steel bar is made of the indented bars of φ 16-25mm.
9. according to claim 7 or the job practices of 8 described Fill Reinforced With Geogrids bodies of wall, it is characterized in that, the concrete steps of described basic earthwork excavation are: measure unwrapping wire, excavate with smooth by the setting-out position, the excavation bedding is filled out the degree of depth to changing, and through the leveling compacting, make base bearing capacity reach designing requirement;
The concrete steps of described strip foundation construction are: described strip foundation adopts concrete cast-in-situ, and preformed groove position, to guarantee building by laying bricks or stones smoothly of concrete modular, concrete continuous footing and preformed groove the construction line-putting position are accurate, and it is corresponding with the barricade settlement joint that concrete continuous footing arranges settlement joint.
10. the job practices of Fill Reinforced With Geogrids body of wall according to claim 9 is characterized in that, described surface layer system by concrete bear down on one, railing, rubble drainage blanket, concrete modular, mortar mask, gutter, concrete continuous footing form; The concrete steps of described Fill Reinforced With Geogrids structure construction are: described geo-grid is unidirectional geo-grid, hanging wire is with the mortar laminated concrete modular of building by laying bricks or stones on concrete continuous footing, then begins the connection of unidirectional grid and the roller compaction construction of backfill gravel drainage blanket and filler within the walls; Every laying one deck unidirectional grid, end connecting reinforcement net or a skeleton reinforcing steel bar of exposing at unidirectional grid; The Specific construction process is as follows:
(1) press the unidirectional geo-grid of design length cutting, must satisfy the requirement of geo-grid design length during cutting, the cutting position is the middle position of geo-grid longitudinal rib;
(2) prefabricated concrete modular is built in layering by laying bricks or stones;
(3) lay the unidirectional geo-grid of first floor;
(4) with pitman unidirectional geo-grid and concrete modular being reserved grid is connected or lays with connector hook grid;
(5) with the stretch-draw beam unidirectional geo-grid is strained, free end is passed skeleton or steel mesh reinforcement bending, fix with pitman, then decontrol the stretch-draw beam;
(6) with loader sandy gravel and filler vertically are poured on the basis of completing unidirectional geo-grid, with excavator or the smooth sandy gravel of bulldozer, shake rolling machine with the sandy gravel compacting with halo, form the backfill packing layer, in the inboard near concrete modular the rubble drainage blanket is set successively, gutter is arranged in rubble drainage blanket and the concrete modular;
(7) repeat above operation to the barricade concrete position of bearing down on one, bearing down on one at concrete arranges railing; Faulting of slab ends end face in the setting of surface layer system arranges the mortar mask;
(8) top layer concrete modular is connected with unidirectional geo-grid, and unidirectional geo-grid laying length is consistent with lower floor.
CN201210515042.XA 2012-12-05 2012-12-05 Geogrid reinforced wall and construction method thereof Active CN102966119B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210515042.XA CN102966119B (en) 2012-12-05 2012-12-05 Geogrid reinforced wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210515042.XA CN102966119B (en) 2012-12-05 2012-12-05 Geogrid reinforced wall and construction method thereof

Publications (2)

Publication Number Publication Date
CN102966119A true CN102966119A (en) 2013-03-13
CN102966119B CN102966119B (en) 2015-07-01

Family

ID=47796532

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210515042.XA Active CN102966119B (en) 2012-12-05 2012-12-05 Geogrid reinforced wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN102966119B (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103452130A (en) * 2013-08-20 2013-12-18 中铁第四勘察设计院集团有限公司 Prestressing force reinforcing mesh ribbing earth pillar plate type retaining wall
CN104099919A (en) * 2013-04-07 2014-10-15 唐善祥 Reinforced earth connection device
CN104674842A (en) * 2015-02-13 2015-06-03 福建省建专岩土工程有限公司 Solidified soil retaining wall and construction method thereof
CN104790428A (en) * 2015-04-08 2015-07-22 贵州建工集团第一建筑工程有限责任公司 Ultrahigh integrated plastic-steel grid reinforced soil abutment retaining wall structure and construction method thereof
CN105256824A (en) * 2015-11-13 2016-01-20 山东大学 Waste tire gabion units, gabion anchor plate earth-retaining wall and construction method
CN107761663A (en) * 2017-11-08 2018-03-06 江苏科技大学 A kind of sheep pile wharf structure and its construction method
CN108104153A (en) * 2017-11-16 2018-06-01 贵阳开磷化肥有限公司 A kind of support construction and its construction method for conveyer
CN108330908A (en) * 2017-01-18 2018-07-27 吴金栋 A kind of stacked shore protection bank protection building method and implementing process
CN108978704A (en) * 2018-08-14 2018-12-11 中国十七冶集团有限公司 A kind of reinforced soil retaining wall and its construction method
CN109750637A (en) * 2019-03-12 2019-05-14 中国电建集团中南勘测设计研究院有限公司 A kind of RCC dam structure
CN109989313A (en) * 2019-05-06 2019-07-09 浙江交工集团股份有限公司 A kind of lightweight combined member and construction method suitable for facing the broadening of precipice road
CN109989312A (en) * 2019-05-06 2019-07-09 浙江交工集团股份有限公司 A kind of widen structure and its construction method suitable for Lin Ya highway
CN114045866A (en) * 2021-11-24 2022-02-15 中铁二院工程集团有限责任公司 Reinforced cantilever type retaining wall based on coordinated deformation and design and construction method thereof
CN114277777A (en) * 2021-11-24 2022-04-05 中铁二院工程集团有限责任公司 Reinforcement type sheet pile wall based on coordinated deformation and design and construction method thereof
CN114703875A (en) * 2022-04-20 2022-07-05 长沙理工大学 High-steep artificial slope wave-shaped reinforced retaining structure and construction method thereof
CN114809037A (en) * 2022-05-12 2022-07-29 江苏镇江路桥工程有限公司 Ramp way back-pressure embankment deformation control structure and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2729153Y (en) * 2004-10-01 2005-09-28 国家电力公司华东勘测设计研究院 Built-in structural beam
CN202140098U (en) * 2011-07-22 2012-02-08 中铁十一局集团有限公司 Large soft rock deformation tunnel supporting structure based on controllable deformation release
KR101126666B1 (en) * 2008-12-11 2012-03-29 주식회사 알지엘텍 Vertical drain induction type retaining wall reinforced by nailing
CN202416329U (en) * 2011-12-21 2012-09-05 中铁第四勘察设计院集团有限公司 Retaining structure of combined reinforced soil pile wall
CN203174626U (en) * 2012-12-05 2013-09-04 青岛旭域土工材料股份有限公司 Geogrid reinforced wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2729153Y (en) * 2004-10-01 2005-09-28 国家电力公司华东勘测设计研究院 Built-in structural beam
KR101126666B1 (en) * 2008-12-11 2012-03-29 주식회사 알지엘텍 Vertical drain induction type retaining wall reinforced by nailing
CN202140098U (en) * 2011-07-22 2012-02-08 中铁十一局集团有限公司 Large soft rock deformation tunnel supporting structure based on controllable deformation release
CN202416329U (en) * 2011-12-21 2012-09-05 中铁第四勘察设计院集团有限公司 Retaining structure of combined reinforced soil pile wall
CN203174626U (en) * 2012-12-05 2013-09-04 青岛旭域土工材料股份有限公司 Geogrid reinforced wall

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104099919A (en) * 2013-04-07 2014-10-15 唐善祥 Reinforced earth connection device
CN103452130A (en) * 2013-08-20 2013-12-18 中铁第四勘察设计院集团有限公司 Prestressing force reinforcing mesh ribbing earth pillar plate type retaining wall
CN103452130B (en) * 2013-08-20 2016-08-31 中铁第四勘察设计院集团有限公司 The deformed bar net board-like barricade of reinforcement earth pillar
CN104674842A (en) * 2015-02-13 2015-06-03 福建省建专岩土工程有限公司 Solidified soil retaining wall and construction method thereof
CN104790428A (en) * 2015-04-08 2015-07-22 贵州建工集团第一建筑工程有限责任公司 Ultrahigh integrated plastic-steel grid reinforced soil abutment retaining wall structure and construction method thereof
CN105256824A (en) * 2015-11-13 2016-01-20 山东大学 Waste tire gabion units, gabion anchor plate earth-retaining wall and construction method
CN105256824B (en) * 2015-11-13 2018-01-02 山东大学 A kind of junked tire lattice guest unit qualifying guest anchored plate retaining wall and construction method
CN108330908A (en) * 2017-01-18 2018-07-27 吴金栋 A kind of stacked shore protection bank protection building method and implementing process
CN107761663A (en) * 2017-11-08 2018-03-06 江苏科技大学 A kind of sheep pile wharf structure and its construction method
CN108104153A (en) * 2017-11-16 2018-06-01 贵阳开磷化肥有限公司 A kind of support construction and its construction method for conveyer
CN108978704A (en) * 2018-08-14 2018-12-11 中国十七冶集团有限公司 A kind of reinforced soil retaining wall and its construction method
CN109750637A (en) * 2019-03-12 2019-05-14 中国电建集团中南勘测设计研究院有限公司 A kind of RCC dam structure
CN109989313A (en) * 2019-05-06 2019-07-09 浙江交工集团股份有限公司 A kind of lightweight combined member and construction method suitable for facing the broadening of precipice road
CN109989312A (en) * 2019-05-06 2019-07-09 浙江交工集团股份有限公司 A kind of widen structure and its construction method suitable for Lin Ya highway
CN114045866A (en) * 2021-11-24 2022-02-15 中铁二院工程集团有限责任公司 Reinforced cantilever type retaining wall based on coordinated deformation and design and construction method thereof
CN114277777A (en) * 2021-11-24 2022-04-05 中铁二院工程集团有限责任公司 Reinforcement type sheet pile wall based on coordinated deformation and design and construction method thereof
CN114703875A (en) * 2022-04-20 2022-07-05 长沙理工大学 High-steep artificial slope wave-shaped reinforced retaining structure and construction method thereof
CN114703875B (en) * 2022-04-20 2024-02-23 长沙理工大学 High-steep artificial side slope wavy reinforced soil retaining structure and construction method thereof
CN114809037A (en) * 2022-05-12 2022-07-29 江苏镇江路桥工程有限公司 Ramp way back-pressure embankment deformation control structure and construction method
CN114809037B (en) * 2022-05-12 2024-04-26 江苏镇江路桥工程有限公司 Slope protection counter-pressure embankment deformation control structure and construction method

Also Published As

Publication number Publication date
CN102966119B (en) 2015-07-01

Similar Documents

Publication Publication Date Title
CN102966119B (en) Geogrid reinforced wall and construction method thereof
CN103669399B (en) Concrete slab reinforced soil retaining wall and construction method thereof
CN103958780B (en) The method for forming cementing retaining wall
CN105155558A (en) Combined retaining structure and construction method thereof
CN109371989B (en) A kind of combined type retaining structure and its construction method suitable for stability of slope supporting
CN106988178A (en) A kind of subgrade in soft soil zone widened structure and its construction method
CN108560349A (en) The high embankment retaining structure in soft clay area
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN112575670A (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN110485230B (en) Treatment structure and construction method of high-water-level soft soil bridge head roadbed
CN213143117U (en) Assembled keyway basis retaining wall structure
KR100603888B1 (en) Construction method of reinforced earth abutment in post tensioning system
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN203174626U (en) Geogrid reinforced wall
CN209722993U (en) A kind of embankment side slope framework parts La Tuoding anchor slab supporting construction a little
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
CN111705576A (en) Steep slope high-filling roadbed structure adopting high-density EPS filler
CN217324788U (en) Abrupt slope roadbed structure convenient to prefabrication installation
CN114232666B (en) Multi-span prestressed elastic foundation beam structure for spanning complex karst cave group and construction method
CN215165799U (en) Reinforced retaining wall
CN112627002B (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN213173779U (en) Cutting slope protection structure
CN204940310U (en) A kind of combination retaining structure
CN210507517U (en) Combined member suitable for retaining wall heightening

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Xia Fei

Inventor after: Zheng Hong

Inventor after: Chu Jingying

Inventor after: Zhao Yan

Inventor after: Chen Zeming

Inventor after: Dai Zhengjie

Inventor after: Yang Guangqing

Inventor after: Zhou Shiguang

Inventor after: Han Jianwen

Inventor after: Yang Baohe

Inventor after: Chen Lili

Inventor after: Wang Xulong

Inventor after: Zhu Jijun

Inventor before: Xia Fei

Inventor before: Dai Zhengjie

Inventor before: Chu Jingying

Inventor before: Zhao Yan

Inventor before: Chen Lili

Inventor before: Wang Xulong

Inventor before: Yang Guangqing

Inventor before: Zhu Jijun

Inventor before: Chen Zeming

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: XIA FEI DAI ZHENGJIE CHU JINGYING ZHAO YAN CHEN LILI WANG XULONG YANG GUANGQING ZHU JIJUN CHEN ZEMING TO: XIA FEI DAI ZHENGJIE YANG GUANGQING ZHOU SHIGUANG HAN JIANWEN YANG BAOHE CHEN LILI WANG XULONG ZHU JIJUN ZHENG HONG CHU JINGYING ZHAO YAN CHEN ZEMING

C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Geogrid reinforced wall and construction method thereof

Effective date of registration: 20170627

Granted publication date: 20150701

Pledgee: Qingdao high technology financing Company limited by guarantee

Pledgor: Qingdao BOSTD Geosynthetics Ltd.

Registration number: 2017370010027

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20190422

Granted publication date: 20150701

Pledgee: Qingdao high technology financing Company limited by guarantee

Pledgor: Qingdao BOSTD Geosynthetics Ltd.

Registration number: 2017370010027

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Geogrid reinforced wall and construction method thereof

Effective date of registration: 20190516

Granted publication date: 20150701

Pledgee: Qingdao high technology financing Company limited by guarantee

Pledgor: Qingdao BOSTD Geosynthetics Ltd.

Registration number: 2019990000434

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20200509

Granted publication date: 20150701

Pledgee: Qingdao high technology financing Company limited by guarantee

Pledgor: BOSTD GEOSYNTHETICS QINGDAO Ltd.

Registration number: 2019990000434

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Geogrid reinforced wall and construction method thereof

Effective date of registration: 20200509

Granted publication date: 20150701

Pledgee: Qingdao high technology financing Company limited by guarantee

Pledgor: BOSTD GEOSYNTHETICS QINGDAO Ltd.

Registration number: Y2020990000446

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20210421

Granted publication date: 20150701

Pledgee: Qingdao high technology financing Company limited by guarantee

Pledgor: BOSTD GEOSYNTHETICS QINGDAO Ltd.

Registration number: Y2020990000446

PC01 Cancellation of the registration of the contract for pledge of patent right