JPH108445A - Laying method for piping - Google Patents
Laying method for pipingInfo
- Publication number
- JPH108445A JPH108445A JP8164678A JP16467896A JPH108445A JP H108445 A JPH108445 A JP H108445A JP 8164678 A JP8164678 A JP 8164678A JP 16467896 A JP16467896 A JP 16467896A JP H108445 A JPH108445 A JP H108445A
- Authority
- JP
- Japan
- Prior art keywords
- trench
- sheet pile
- steel sheet
- steel
- timbering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Sewage (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は地中に管路を布設す
る管路の布設工事方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pipe laying method for laying a pipe in the ground.
【0002】[0002]
【従来の技術】地中に管路を布設する一般的な開削工法
では、管布設経路に沿ってトレンチ(埋設用溝)を掘削
し、トレンチ両側の地山が崩れないように、矢板をトレ
ンチ側壁際に立設し、矢板の表面に矢板を押える腹起し
(横梁)を配置し、両側壁の腹起しを突っ張る多数の切
梁を用いて山留めを施し、その後、トレンチ内に順次配
管し、管体同士を端面溶接して布設し、これらが完了す
ると、前記トレンチを埋め戻しつつ、山留めに用いた矢
板・腹起し・切梁などを撤去するといった手順を踏んで
行われていた。2. Description of the Related Art In a general open-cutting method for laying a pipeline in the ground, a trench (buried groove) is excavated along a pipe laying route, and a sheet pile is trenched so that the ground on both sides of the trench does not collapse. Standing on the side of the side wall, ridges (cross beams) for holding the sheet pile are placed on the surface of the sheet pile, and a number of cut beams that stretch the ridges on both side walls are used to secure the mountain, and then piped sequentially in the trench Then, the pipes were welded end-to-end and laid, and when these were completed, steps were taken such as removing the sheet piles, bulges, cutting beams, etc. used for the mountain retaining while backfilling the trench. .
【0003】[0003]
【発明が解決しようとする課題】ところが、山留めのた
めの矢板、腹起し、切梁の設置には時間を要することは
もとより、トレンチ内へ管を吊り降ろす時にはトレンチ
を横断するように取付けられた切梁が邪魔になり、この
切梁を一旦取り外さざるをえないといった手戻り作業が
生じたり、あるいは管を斜め方向から切梁の下をくぐら
せながらセットするといった煩雑な作業が伴う。このよ
うな工法は従来より改善の余地があると指摘されてき
た。However, not only does it take time to install a sheet pile, a bulge, and a girder for mountain retaining, but also when the pipe is suspended in the trench, it is mounted so as to cross the trench. The cut beam becomes an obstacle, and a reworking operation in which the cut beam must be once removed occurs, or a complicated operation such as setting a pipe while passing under the cut beam from an oblique direction is involved. It has been pointed out that such a construction method has room for improvement.
【0004】なお、切梁として水圧ジャッキを使用した
ものが、特公昭63−10250号公報に開示されてい
るが、この場合もやはり上記と同様の問題がある。本発
明は、上記事情に鑑み、短い工期で安価、安全に地中に
管路を布設することができる管路の布設方法を提供する
ことを目的とする。[0004] An apparatus using a hydraulic jack as a cutting beam is disclosed in Japanese Patent Publication No. 63-10250, but this case also has the same problem as described above. The present invention has been made in view of the above circumstances, and has as its object to provide a method of laying a pipeline that can lay the pipeline safely and inexpensively in a short period of time.
【0005】[0005]
【課題を解決するための手段】本発明は、トレンチを掘
削し、順次鋼矢板をトレンチの両壁に爪部を連結しなが
ら打設し、鋼製U字形支保工を前記鋼矢板内面に配設し
て鋼矢板を固定し、鋼管をトレンチ内に配管し、U字形
支保工を鋼管長手方向に倒して支保工及び鋼矢板を回収
し、埋戻しを行うことを特徴とする管路の布設方法であ
る。本発明は、掘削したトレンチの両側に矢板壁材を吊
り降ろし、矢板同士をトレンチに沿って爪部を連結しな
がら打設する。トレンチ延長方向に適当なピッチで鋼製
U字形支保工をそのU字形の開口部が上になるようにト
レンチ内に設置する。この状態のまま、鋼管をトレンチ
内に吊り降ろして、芯出し、溶接など一連の接合作業を
施す。しかる後、埋戻しに合わせて、順次U字形支保工
の回収、矢板の回収を手際よく行う。以上の工程を繰り
返しつつ、管路布設を能率よく行うことができる。According to the present invention, a trench is excavated, steel sheet piles are sequentially driven into the two walls of the trench while connecting claws, and a steel U-shaped support is arranged on the inner surface of the steel sheet pile. Laying pipes, fixing steel sheet piles, piping steel pipes in trenches, tilting U-shaped supports in the longitudinal direction of steel pipes, collecting supports and recovering sheet piles, and performing backfilling. Is the way. In the present invention, a sheet pile wall material is hung down on both sides of the excavated trench, and the sheet piles are driven together while connecting the claw portions along the trench. A steel U-shaped support is installed in the trench at an appropriate pitch in the trench extension direction such that the U-shaped opening is on the top. In this state, the steel pipe is suspended in the trench, and a series of joining operations such as centering and welding are performed. After that, the U-shaped support and the sheet pile are sequentially and efficiently collected in line with the backfill. By repeating the above steps, the pipe laying can be performed efficiently.
【0006】[0006]
【発明の実施の形態】以下、図面を参照して本発明の実
施の形態を説明する。図2に示すように、鋼製U字形支
保工3として、H形鋼−150×150を使用して、ト
レンチの幅及び深さとほぼ等しいU字形に曲げ形成し、
U字形31の立上り部の両横面に押え板32を取付け
た。押え板32は、U字形支保工3をトレンチ内の両側
壁の矢板表面に圧着するために、押え板と矢板の間に楔
33等を打ち込んで固定するためのものである。例え
ば、図2に示すように、長さ350〜450mm程度×
幅100〜150mm程度の短冊形の押え板32をU字
形の立ち上がり部の外面に横向きに貼着するとよい。Embodiments of the present invention will be described below with reference to the drawings. As shown in FIG. 2, as a steel U-shaped support 3, an H-shaped steel 150 × 150 is used and bent into a U-shape substantially equal to the width and depth of the trench,
A holding plate 32 was attached to both lateral surfaces of the rising portion of the U-shaped 31. The holding plate 32 is used for driving and fixing a wedge 33 or the like between the holding plate and the sheet pile in order to press the U-shaped support 3 against the sheet pile surface on both side walls in the trench. For example, as shown in FIG.
It is preferable to attach a strip-shaped pressing plate 32 having a width of about 100 to 150 mm laterally to the outer surface of the U-shaped rising portion.
【0007】図1は、実施例の斜視図である。幅2m程
度、深さ3m程度のトレンチ1内に、その両壁に鋼矢板
2、2が配設されており、この鋼矢板2、2を鋼製U字
形支保工3が押えている。鋼矢板2は隣接鋼矢板同士が
爪部を連結して配置されている。この例では矢板には軽
量鋼矢板2を当矢板として用い、U字形支保工3は1.
5Mピッチで設置した。そのトレンチ1内に、直径50
0mm程度の管4が配設されている様子が示されてい
る。FIG. 1 is a perspective view of an embodiment. In a trench 1 having a width of about 2 m and a depth of about 3 m, steel sheet piles 2, 2 are arranged on both walls thereof, and a steel U-shaped support 3 holds the steel sheet piles 2, 2. The steel sheet piles 2 are arranged such that adjacent steel sheet piles connect the claw portions. In this example, a lightweight steel sheet pile 2 is used as a sheet pile for the sheet pile, and the U-shaped support 3 is made of 1.
It was installed at a 5M pitch. In the trench 1, a diameter of 50
A state in which a pipe 4 of about 0 mm is provided is shown.
【0008】本発明方法の作業手順は、次のとおりであ
る。 (a)図3に示すように、トレンチ1を重機(例えばバ
ックホウ11)にて掘削する。図3(a)は側面図であ
って図3(b)のA矢視図、図3(b)は断面図であっ
て、図3(a)のB矢視図である。 (b)図4に示すように、順次、軽量鋼矢板2を土留壁
としてトレンチ1の両側壁に打込む。図4(a)は側面
図で図4(b)のC矢視を示している。図4(b)は断
面図である。 (c)引き続き、鋼製U字形支保工3を軽量鋼矢板2の
内側に所定ピッチで配設し、押え板32と矢板壁との間
隙に適宜、木製楔33(図1参照)を打込む。図5
(a)はこの工程を示す側面図で図5(b)のD矢視図
である。図5(b)は断面図である。 (d)トラッククレーン12などにより鋼管4をトレン
チ内に吊り降ろし、芯出し、肌合わせなどを行った後、
溶接・塗覆装などを施す(図6)。 (e)図7に示すように、U字形支保工3ならびに土留
め用の軽量矢板2の撤去作業を行い、埋戻土5により埋
戻しを行い、管布設が完了する。U字形支保工3を撤去
する段取りは以下の通りとなる。すなわち、楔33を外
し、U字形支保工3を管長方向に倒す。次いで、鋼管4
の下をくぐらせながら、土留壁と管体の空隙部より重機
にて吊上げ、地表面まで持ち運ぶ。The working procedure of the method of the present invention is as follows. (A) As shown in FIG. 3, the trench 1 is excavated by a heavy equipment (for example, the backhoe 11). 3A is a side view, and is a view as viewed from an arrow A in FIG. 3B, and FIG. 3B is a sectional view as viewed from an arrow B in FIG. 3A. (B) As shown in FIG. 4, the lightweight steel sheet pile 2 is sequentially driven into both side walls of the trench 1 as a retaining wall. FIG. 4A is a side view showing a view taken in the direction of arrow C in FIG. 4B. FIG. 4B is a sectional view. (C) Subsequently, the steel U-shaped support 3 is disposed inside the lightweight steel sheet pile 2 at a predetermined pitch, and a wooden wedge 33 (see FIG. 1) is appropriately driven into the gap between the holding plate 32 and the sheet pile wall. . FIG.
(A) is a side view showing this step, and is a view as seen from an arrow D in FIG. 5 (b). FIG. 5B is a sectional view. (D) After the steel pipe 4 is suspended in the trench by the truck crane 12 and the like, and the centering and the skin matching are performed,
Welding and painting are applied (Fig. 6). (E) As shown in FIG. 7, the work of removing the U-shaped support 3 and the lightweight sheet pile 2 for retaining the soil is performed, the backfill is performed with the backfill soil 5, and the pipe installation is completed. The setup for removing the U-shaped support 3 is as follows. That is, the wedge 33 is removed, and the U-shaped support 3 is lowered in the pipe length direction. Next, steel pipe 4
While passing under the ground, lift it with heavy equipment from the gap between the retaining wall and the pipe, and carry it to the ground surface.
【0009】[0009]
【発明の効果】以上の説明の通り、本発明によれば、切
梁や腹起しが不要となる。したがって、鋼管をトレンチ
内に吊り降ろす時にも、トレンチを横断する切梁が存在
しないため、なんら支障なく吊り降ろすことができる。
矢板壁同士又は矢板とU字形支保工とは単純な接触状態
を保持して組立てられているだけであるから、組立、解
体が容易である。さらに、高能率作業が可能となるた
め、工期短縮、コストダウンを期待することができると
いう効果を奏する。As described above, according to the present invention, there is no need for a cutting beam or a belly. Therefore, even when the steel pipe is hung in the trench, it can be hung without any trouble because there is no cut beam crossing the trench.
Since the sheet pile walls or the sheet pile and the U-shaped support are merely assembled while maintaining a simple contact state, assembly and disassembly are easy. Furthermore, since high-efficiency work becomes possible, it is possible to expect an effect of shortening the construction period and reducing costs.
【図1】実施例の斜視図である。FIG. 1 is a perspective view of an embodiment.
【図2】U字形支保工の斜視図である。FIG. 2 is a perspective view of a U-shaped support.
【図3】実施例の工程図で、(a)は側面図、(b)は
横断面図である。FIGS. 3A and 3B are process diagrams of the embodiment, in which FIG. 3A is a side view and FIG.
【図4】実施例の工程図で、(a)は側面図、(b)は
横断面図である。4A and 4B are process diagrams of the embodiment, in which FIG. 4A is a side view, and FIG.
【図5】実施例の工程図で、(a)は側面図、(b)は
横断面図である。FIGS. 5A and 5B are process diagrams of the embodiment, in which FIG. 5A is a side view and FIG.
【図6】実施例の工程図で、(a)は側面図、(b)は
横断面図である。6 (a) is a side view, and FIG. 6 (b) is a cross-sectional view.
【図7】実施例の工程図で、(a)は側面図、(b)は
横断面図である。FIGS. 7A and 7B are process diagrams of the embodiment, in which FIG. 7A is a side view and FIG.
1 トレンチ 2 鋼矢板 3 U字形支保工 4 鋼管 5 埋戻土 11 バックホウ 12 トラッククレーン 31 U字形鋼 32 押え板 33 楔 Reference Signs List 1 trench 2 steel sheet pile 3 U-shaped support 4 steel pipe 5 backfill soil 11 backhoe 12 truck crane 31 U-shaped steel 32 holding plate 33 wedge
フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 F16L 1/024 Continued on the front page (51) Int.Cl. 6 Identification code Agency reference number FI Technical display F16L 1/024
Claims (1)
チの両壁に打込み、鋼製U字形支保工を前記鋼矢板内面
に配設して鋼矢板を固定し、鋼管をトレンチ内に配管
し、U字形支保工を鋼管長手方向に倒して支保工及び鋼
矢板を回収し、埋戻しを行うことを特徴とする管路の布
設方法。1. A trench is excavated, steel sheet piles are sequentially driven into both walls of the trench, and a steel U-shaped support is disposed on an inner surface of the steel sheet pile to fix the steel sheet pile, and a steel pipe is piped into the trench. A method of laying a pipeline, comprising: tilting a U-shaped support in the longitudinal direction of a steel pipe, collecting the support and steel sheet pile, and performing backfilling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8164678A JPH108445A (en) | 1996-06-25 | 1996-06-25 | Laying method for piping |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8164678A JPH108445A (en) | 1996-06-25 | 1996-06-25 | Laying method for piping |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH108445A true JPH108445A (en) | 1998-01-13 |
Family
ID=15797773
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8164678A Withdrawn JPH108445A (en) | 1996-06-25 | 1996-06-25 | Laying method for piping |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH108445A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101962113A (en) * | 2010-09-03 | 2011-02-02 | 东方电气集团东方电机有限公司 | Overlapping light heavy-duty material rack |
KR101039115B1 (en) | 2011-03-08 | 2011-06-03 | 주식회사 삼안 | Reinforcement apparatus of water pipe in weaknessground |
CN105926655A (en) * | 2016-05-03 | 2016-09-07 | 东通岩土科技(杭州)有限公司 | Water stop building envelope construction method without removing pipeline |
CN106978843A (en) * | 2017-04-25 | 2017-07-25 | 杭州之江市政建设有限公司 | Municipal drainage pipeline construction technology |
CN107587524A (en) * | 2017-08-18 | 2018-01-16 | 新地能源工程技术有限公司 | A kind of drainpipe construction method for passing through sea wall |
CN107893402A (en) * | 2017-11-15 | 2018-04-10 | 黄河勘测规划设计有限公司 | The method of reservoir reconstruction of diversion tunnel emptying tunnel |
CN108301485A (en) * | 2018-02-07 | 2018-07-20 | 长沙理工大学 | A kind of sewer and preparation method thereof |
JP2019097690A (en) * | 2017-11-29 | 2019-06-24 | 花王株式会社 | Absorbent article |
CN110512642A (en) * | 2019-08-30 | 2019-11-29 | 中国二十二冶集团有限公司 | Soft clay area drainage pipeline concrete pack punching block board construction method |
CN111155623A (en) * | 2019-12-10 | 2020-05-15 | 宣城市政建设集团有限公司 | Construction and installation method for outdoor square stainless steel and plastic finished product combined drainage ditch |
CN112728229A (en) * | 2020-10-27 | 2021-04-30 | 中投(天津)智能管道股份有限公司 | Production method of 3PE steel outer protective type early warning direct-buried heat insulation pipe |
CN112832354A (en) * | 2021-03-03 | 2021-05-25 | 陈雪琼 | A fixed protector for water conservancy pipeline |
CN115978296A (en) * | 2022-12-08 | 2023-04-18 | 宁波市政工程建设集团股份有限公司 | Anti-deformation construction method for electric melting connection of large-diameter flexible pipeline |
-
1996
- 1996-06-25 JP JP8164678A patent/JPH108445A/en not_active Withdrawn
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101962113A (en) * | 2010-09-03 | 2011-02-02 | 东方电气集团东方电机有限公司 | Overlapping light heavy-duty material rack |
KR101039115B1 (en) | 2011-03-08 | 2011-06-03 | 주식회사 삼안 | Reinforcement apparatus of water pipe in weaknessground |
CN105926655A (en) * | 2016-05-03 | 2016-09-07 | 东通岩土科技(杭州)有限公司 | Water stop building envelope construction method without removing pipeline |
CN105926655B (en) * | 2016-05-03 | 2018-01-23 | 东通岩土科技(杭州)有限公司 | The sealing construction method of enclosure structure that a kind of pipeline is not removed |
CN106978843A (en) * | 2017-04-25 | 2017-07-25 | 杭州之江市政建设有限公司 | Municipal drainage pipeline construction technology |
CN106978843B (en) * | 2017-04-25 | 2019-11-15 | 杭州之江市政建设有限公司 | Municipal drainage pipeline construction technology |
CN107587524A (en) * | 2017-08-18 | 2018-01-16 | 新地能源工程技术有限公司 | A kind of drainpipe construction method for passing through sea wall |
CN107893402A (en) * | 2017-11-15 | 2018-04-10 | 黄河勘测规划设计有限公司 | The method of reservoir reconstruction of diversion tunnel emptying tunnel |
JP2019097690A (en) * | 2017-11-29 | 2019-06-24 | 花王株式会社 | Absorbent article |
CN108301485A (en) * | 2018-02-07 | 2018-07-20 | 长沙理工大学 | A kind of sewer and preparation method thereof |
CN110512642A (en) * | 2019-08-30 | 2019-11-29 | 中国二十二冶集团有限公司 | Soft clay area drainage pipeline concrete pack punching block board construction method |
CN111155623A (en) * | 2019-12-10 | 2020-05-15 | 宣城市政建设集团有限公司 | Construction and installation method for outdoor square stainless steel and plastic finished product combined drainage ditch |
CN112728229A (en) * | 2020-10-27 | 2021-04-30 | 中投(天津)智能管道股份有限公司 | Production method of 3PE steel outer protective type early warning direct-buried heat insulation pipe |
CN112832354A (en) * | 2021-03-03 | 2021-05-25 | 陈雪琼 | A fixed protector for water conservancy pipeline |
CN115978296A (en) * | 2022-12-08 | 2023-04-18 | 宁波市政工程建设集团股份有限公司 | Anti-deformation construction method for electric melting connection of large-diameter flexible pipeline |
CN115978296B (en) * | 2022-12-08 | 2024-06-14 | 宁波市政工程建设集团股份有限公司 | Anti-deformation construction method for electric smelting connection of large-caliber flexible pipeline |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH108445A (en) | Laying method for piping | |
JP4625796B2 (en) | Multiple arc tunnel connection structure and construction method | |
KR100815568B1 (en) | The tunel execution method and the using fabric | |
KR101069702B1 (en) | Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel | |
JP2017137688A (en) | Earth retaining method and supporting system | |
JP2021181751A (en) | Reaction force structure and method for launching concrete box or open shield machine | |
JP4668829B2 (en) | Tunnel excavation method, tunnel branching / merging widening part using the same, and tunnel branching / merging widening part constructed thereby | |
JPS5873623A (en) | Sheathing work for excavated trench and sheeting therefor | |
JP6542825B2 (en) | Construction method of underground structure | |
JP2011063957A (en) | Method for removing upper portion of pile | |
JP3093937B2 (en) | Pipe laying method | |
JP2001207452A (en) | Method for burying pipe | |
JP3116098B2 (en) | Construction method for underground structures | |
JP6441842B2 (en) | Box roof cylinder | |
JP5037997B2 (en) | Leading beam construction method and leading beam connection structure | |
KR102079634B1 (en) | Construction method for under-ground structure construction using steel pipe with bracket | |
JP2004076490A (en) | Earth retaining member of trench and earth retaining method | |
JP2823975B2 (en) | Vertical hole drilling method | |
JP2017128944A (en) | Construction method of underground structure | |
JP3725005B2 (en) | Flat panel and its construction method | |
JP2001131977A (en) | Soldier pile and lagging method | |
JP2000257068A (en) | Earth retaining method for pipe burying ditch and earth retaining wall support device | |
KR0181964B1 (en) | Underground construction | |
KR101479266B1 (en) | Construction method for non open cut tunnel by using of roll type roof plate | |
JP2592901B2 (en) | How to put a long pipe into the groove in sheet pile construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20030902 |