CN106978843A - Municipal drainage pipeline construction technology - Google Patents

Municipal drainage pipeline construction technology Download PDF

Info

Publication number
CN106978843A
CN106978843A CN201710276350.4A CN201710276350A CN106978843A CN 106978843 A CN106978843 A CN 106978843A CN 201710276350 A CN201710276350 A CN 201710276350A CN 106978843 A CN106978843 A CN 106978843A
Authority
CN
China
Prior art keywords
pipeline
meters
inspection shaft
pipe
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710276350.4A
Other languages
Chinese (zh)
Other versions
CN106978843B (en
Inventor
陈少军
马爱国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Zhijiang Municipal Construction Co Ltd
Original Assignee
Hangzhou Zhijiang Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Zhijiang Municipal Construction Co Ltd filed Critical Hangzhou Zhijiang Municipal Construction Co Ltd
Priority to CN201710276350.4A priority Critical patent/CN106978843B/en
Publication of CN106978843A publication Critical patent/CN106978843A/en
Application granted granted Critical
Publication of CN106978843B publication Critical patent/CN106978843B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes

Abstract

The invention discloses a kind of municipal drainage pipeline construction technology, its drip irrigation device is:Including surveying setting-out, beat steel sheet pile and precipitation, channel excavation, pipeline foundation, pipeline laying, inspection shaft and build by laying bricks or stones, closed-water test, trench backfill and extract steel sheet pile;With improving its construction quality, reduction difficulty of construction, shortening the construction period, the effect of surrounding pipeline safety is improved.

Description

Municipal drainage pipeline construction technology
Technical field
The present invention relates to urban architecture engineering construction field, more specifically, it relates to which a kind of municipal drainage pipeline is constructed Technique.
Background technology
Geology is more complicated in urban road widening and improving project, and the construction period should be considered during construction, is considered again Close traffic problem, if routinely construction method is constructed(Fluting slope, fluting supporting)It cannot be guaranteed that the peace of Adjacent Buildings Entirely, while construction cost is improved, it is impossible to ensure the duration;Also in conventional construction method, need to take one using slot grooving Fixed groove timbering measure, once construction environment changes, execution conditions are complicated, and the construction period is longer, and surrounding pipeline can not Ensure safety, so as to reduce construction quality reduction.
The content of the invention
In view of the deficienciess of the prior art, it is an object of the invention to provide a kind of municipal drainage pipeline construction technology, With the effect for improving its construction quality.
To achieve the above object, the invention provides following technical scheme:
A kind of municipal drainage pipeline construction technology, comprises the following steps:
S1, surveying setting-out:The measure of ditch groove center, excavating sideline positioning and center absolute altitude is carried out, and encrypts the wire of construction Point and bench mark;
S2, beat steel sheet pile and precipitation:Interim horizontal supporting system is added to go along with sb. to guard him using steel sheet pile buried excavation section, heavy excavation is applied Work, and artificial rainmaking is used to the foundation ditch of buried depth≤3.5 meter;
S3, channel excavation:Channel excavation depth is less than 2 meters and excavated using slope;Cutting depth uses steel sheep pile support more than 2 meters Go along with sb. to guard him, support level distance is 2.5 meters, and be excavated to 1.2 meters and be supported using waling plate and steel pipe;
S4, pipeline foundation:The absolute altitude of elevation model is checked before foundation construction, the bottom on basis is dug according to design requirement Remove, trim slots bottom, remove mud and hack, pipe substrate absolute altitude is backfilled to gravel sand, compaction in layers passes through armored concrete bottom Plate makes reinforced concrete pipeline foundation, and after after the hardening of reinforced concrete pipeline surface of base, pipe centerline is ejected in its end face;
S5, pipeline laying:Reinforced concrete pipeline foundation is poured, and intensity starts row and set comb up to after more than 70%;
S6, inspection shaft are built by laying bricks or stones:Caliber, direction and the absolute altitude that inspection shaft reserves sewer pipe all should meet design requirement, reserve sewer pipe Top should connect flat with interior wall, and the junction of inspection shaft and sewer pipe uses 1:2 cement mortar smear triangle seam at 45 °;
S7, closed-water test:The examination that first added water on request when closing water is closed 20 minutes, after carrying out formally closing water after stable level, closes Shui Shui Head should be 2 meters above of top in inspection section upstream line, calculate the average value of water level decreasing in 30 minutes;
S8, trench backfill:The uniform backfill simultaneously of drainage pipeline both sides, the both sides discrepancy in elevation must not exceed 30 centimetres, more than tube top 50 lis Earth backing layering leveling in the range of rice, and the compactness of groove earth backing is successively checked;
S9, extraction steel sheet pile:Banket reach closely knit requirement after steel sheet pile is removed, steel sheet pile interval is pulled out, and in time Sand is filled, keeps soil layer closely knit, and the sheet pile of extraction is cleared up, maintained, and is distinguished by its length and bending, the degree damaged Stack, one simultaneously neat.
It is arranged such, each orientation of construction can be accurately determined to, overall related data reduces construction by bench mark Error;By beating steel sheet pile and precipitation, the stability during the Construction of sewer that it entirely constructs is improved, is passed through simultaneously Artificial rainmaking, which can reach, to be easy to carry out the reparation that relaxes to dry soil layer;Drainage pipeline can be improved by channel excavation and carry out draining And to the stability of groove construction, the soil layer that being supported using waling plate and steel pipe can reduce on groove is collapsed;Pipeline Foundation construction is places the substrate of drainpipe band, while excavating to the bottom on basis, trim slots bottom, removes mud and broken Soil, pipe substrate absolute altitude is backfilled to gravel sand, and compaction in layers reaches and is easy to constructing operation;When be poured and intensity up to 70% with After upper, implement pipeline laying, built by laying bricks or stones while carrying out inspection shaft, improve the connective stability between pipeline and inspection shaft, on the one hand The stable connection performance between pipeline can be improved, and then reaches the sealing property between raising pipeline, and between inspection shaft Sealing property;The drainage performance and water resistance of inspection shaft and pipeline can be improved by closed-water test, be easy to repair again with Improve, the construction monitoring of pipeline, reparation well etc. when improving construction improves the security performance and construction matter of Construction of sewer Amount;The overall construction stability of drainage pipeline is improved after backfill, by one layer of one earth backing, compacting degree during backfill is improved, makes to apply Entirety after work is wound up;Banket reach closely knit requirement after steel sheet pile is removed, steel sheet pile interval is pulled out, and in time Sand is filled, keeps soil layer closely knit;Construction is added drainage pipeline and is repaired after well, place is replied original appearance, keep postorder place Use, with improve its construction quality, reduction difficulty of construction, shorten the construction period, improve surrounding pipeline safety effect.
Further set:The surveying setting-out includes:(1)Verification bench mark simultaneously sets up interim at one along one every 60 meters Bench mark;(2)Measurement pipe road ground elevation, pipe centerline, box cut sideline and construct object location;(3)According to each pipeline Unit tell somebody what one's real intentions are and project management department scene investigates the conditions on the spot, contact and coordinate with each pipeline unit, discharge pipe canal digging model Enclose interior buried pipeline;(4)After excavation is tested pits, its excavation slope value and sliding-resistant system are determined.
It is arranged such, accurately each orientation of construction can be determined by bench mark, reduce construction error, by existing Field prospecting understood Optimizing construction orientation to former water pipe layout, improved the effect of the precision constructed and safe construction.
Further set:The channel excavation includes:(1)Cut the earth using excavator, trough rim, mound are banked up in the part earthwork It is more than 2 meters from groove back gauge, mound is highly less than 1.5 meters, unnecessary earthwork outward transport;(2)Shoveling should work in coordination with support, dig Pick machine is supported in time after cutting the earth;(3)When digging depth is to 1.2m, fastener baffle plate is cut the earth with fagging alternately, after deburring immediately Fagging, each fagging is highly generally 0.6~0.8 meter;(4)When digging depth is to 2 meters, answers and supportted at first 0.6~0.8 meter away from ground Head falls to support, and the level interval of steel sheep pile support is 2 meters, and PH pipe diameters are not more than 3 meters, and the vertical interval of support is not more than 2 meters; (5)Offer gutter in the bottom land both sides of groove, set sump one in 30m or so and set pump drainage, sump diameter or Width is in 0.6~0.8m, and depth uses bamboo and wood or brick Simple reinforced in 0.7~1m, crater wall, and spreads in shaft bottom rubble filter Water layer.
It is arranged such, the earthwork is stacked in and is more than 2 meters from groove back gauge, on the one hand can reduce mound and groove is squeezed Pressure, makes groove cave in or be influenceed on the size of excavation, is on the other hand easy to being constructed near groove;Baffle plate is thrown by city The slurry trench stability performance of groove can be stablized, be easy to lasting construction, the construction safety performance of groove is improved, while gutter is conducive to Carry out draining to groove, rubble drainage layer can also improve the stability of groove with and play a part of certain drainage, reduce Bottom rainwater dilutes to the soil of groove, improves the compacting degree of groove bottom.
Further set:The pipeline laying includes:(1)Bottom absolute altitude is defined in pipe during comb, at well location during comb, The internal diameter size of inspection shaft should be controlled;(2)Pipeline fracture, groove, cleaning conduit section and surface are carried out by program;(3)Inspection Pipe socket and rubber ring quality are looked into, the working face of material is cleared up;(4)In the groove that rubber ring is arranged on to bellmouth, bellmouth should For the direction that meets water;(5)With tape measure bellmouth depth, and scored marks in tubing socket end, label size should be the depth of bellmouth The 0.8-0.85% of degree;(6)Lubricant is dipped in covering with paint or varnish, is uniformly brushed on the inside of rubber ring and on the outside of tubing socket;(7)Keep Connecting tube straightened condition, is directed at bellmouth by pipeline socket, is manually once inserted into mark;Finally bell and spigot is inserted with clearance gauge Gap, peripherally checks rubber ring installation site;(8)The position that pipeline is connected with inspection shaft uses short tube, inspection shaft brick Wall short tube exposed parts are preferably less than 600 millimeters, and pipe muscle should be full positioned at brick wall part mortar, are seeped water to prevent seam crossing.
Be arranged such, make pipeline cleaner, improve pipeline between welded seal performance, and be easy to adjacent channel it Between operating characteristics, while using rubber ring can improve pipeline sealing welding act on, on the one hand can improve the company between pipeline Stability is connect, and then reaches the sealing property between raising pipeline, and the sealing property between inspection shaft.
Further set:The inspection shaft, which is built by laying bricks or stones, to be comprised the following steps:(1)Inspection shaft size is set according to the logical figure of row and drawing Size is counted, and is carried out on the concrete bed course poured;(2)Inspection shaft basis should simultaneously be poured with pipeline foundation;(3)Check well stream Groove uses brick masonry, and the height of chute should be 1/2nd of caliber, and two shoulders are overboard to centre, and use 1:2 cement mortar are smeared Face, inspection shaft, which is built to desired height, lays prefabricated reinforced concrete cover plate, and cover plate adjusts brick wall height according to road horizontal slope Lay, should be first in brick wall top surface seat 1 when cover plate is laid:2 cement mortar, and thickness is 5 millimeters, cover plate then is laid into place, lid Plate surrounding uses 1:2 cement mortar depressed places jail, smears triangle seam at 45 °, and seam height is 50 millimeters, and laying should be first in lid before cast iron cover base The reserved groove inner seat 1 of plate:2 cement mortar, thickness is 1 millimeter, and cage, cage surrounding pea gravel concreten are laid after correction absolute altitude Depressed place jail.
It is arranged such, inspection shaft chute uses brick masonry, improves the compactedness of inspection shaft, be easy to the later stage to pass through inspection shaft pair The inspection and reparation of pipeline, the effect with the construction quality for improving inspection shaft.
Further set:The closed-water test comprises the following steps:(1)Close before water, mortar joint and concrete should reach Some strength, pipeline should first pour water 24 hours, be thoroughly impregnated pipeline;(2)The examination that first adds water is closed 20 minutes, treats that water level decreasing is stable Afterwards, carry out formally closing water, calculate 30 minutes water level decreasing average value.
It is arranged such, the drainage performance and water resistance of inspection shaft and pipeline can be improved by closed-water test, is easy to again Secondary maintenance is with improving, pipeline when improving construction, the construction monitoring for repairing well etc., improve Construction of sewer security performance and Construction quality.
Further set:The trench backfill comprises the following steps:(1)Tear plate earth backing open:Pipeline acceptance of concealed work is qualified Afterwards, bottom land debris is cleaned out before earth backing immediately, earth backing;(2)During earth backing in groove must not ponding, tear open plate earth backing should by under And on order, successively carry out, tear plate open every time and typically must not exceed 45 centimetres;(3)Tear same day earth backing after plate open;(4)Pipeline both sides Simultaneously uniform it should backfill, the both sides discrepancy in elevation must not exceed 30 centimetres, the earth backing layering leveling more than tube top in 50 cm ranges, and it is right The compactness of groove earth backing is successively checked;(5)The equipment such as fagging, the dagger pulled down should in time be cleared up, maintained and neat heap Put.
It is arranged such, improves the cleannes of groove, while improving the overall construction stability of drainage pipeline after backfill, passes through One layer of one earth backing, improves compacting degree during backfill;Simultaneously backfill after Density Detection is carried out to it, can implementing monitoring construction construction Quality, is easy to further optimization and improves, and is cleared up after finally having constructed, improves the cleannes and construction environment after construction.
By using above-mentioned technical proposal, the present invention is compared compared with the prior art:By between drainage pipeline, inspection shaft Connection sealing, and to construction period carry out examinations, with improve its construction quality, reduction difficulty of construction, shorten apply The work duration, improve the effect of surrounding pipeline safety.
Embodiment
Municipal drainage pipeline construction technology is described further below.
A kind of municipal drainage pipeline construction technology, includes surveying setting-out, beats steel sheet pile and precipitation, channel excavation, pipeline Basis, pipeline laying, inspection shaft are built by laying bricks or stones, closed-water test, trench backfill and extract steel sheet pile, and its Specific construction step is as follows.
First, surveying setting-out includes following steps
The measure of ditch groove center, excavating sideline positioning and center absolute altitude is carried out, and encrypts the traverse point and bench mark of construction, is made Each operation position and elevation are measured in construction at any time.
(1)Verification bench mark simultaneously sets up temporary bench mark at one along every 60 meters;
(2)Measurement pipe road ground elevation, pipe centerline, box cut sideline and construct object location;
(3)According to each pipeline unit tell somebody what one's real intentions are and project management department scene investigates the conditions on the spot, contact and assist with each pipeline unit Adjust, the buried pipeline in the range of discharge pipe canal digging;
(4)After excavation is tested pits, its excavation slope value and sliding-resistant system are determined.
2nd, steel sheet pile and precipitation are beaten
Interim horizontal supporting system is added to go along with sb. to guard him using steel sheet pile buried excavation section, heavy excavation construction, and to buried depth≤3.5 meter Foundation ditch use artificial rainmaking.
3rd, channel excavation includes following steps
This engineering is using the method construction being manually combined with machinery;Channel excavation depth is excavated when being less than 2 meters using slope, is opened Dig depth to go along with sb. to guard him using steel sheep pile support more than 2 meters, support level distance is 2.5 meters;With digging with support, first layer soil is excavated to 1.2 meters this be supported using waling plate and 209 steel pipes;To ensure that groove is stable, cutting depth is designed altogether in the range of 5 meters Two roads support and enclose purlin plate, dig to 0.5 meter of trench bottom place, for last one of the temporary support of setting, after the completion for the treatment of basis, before comb Remove.
(1)Using machinery(Excavator)Cut the earth, the part earthwork(Backfill part)Trough rim is banked up, mound is from groove back gauge not 2 meters must be less than, mound highly cannot be greater than 1.5 meters;Unnecessary earthmoving machinery outward transport;
(2)Shoveling should be worked in coordination with support, and excavator is supported in time after cutting the earth, and is prevented cell wall unstability and is caused groove to cave in;
(3)Excavator is cut the earth and takes retrusive shoveling method, is forbidden excavator to enter and is not set in the region of support;
(4),, should if meeting soft soil or Changes in weather when digging depth is to 1.2 meters, it is necessary to fastener baffle plate in the construction of fagging method Fagging in advance, cuts the earth with fagging alternately later, fagging immediately after deburring, highly generally 0.6~0.8 meter of each fagging, If soil property is soft or rainy answer and adds support at timely fagging;Wale piece encloses purlin, length 4m using steel;Perpendicular strake uses channel-section steel, Length is not less than gash depth, and dagger sleeve level interval is not more than 2.5 meters(PH pipes are not more than 3 meters), vertical interval is not more than 1.5 meters, first gear iron dagger should be 0.6~0.8 meter apart from ground;
(5)When digging depth is to 2 meters, fastener road support at first 0.6~0.8 meter away from ground is answered;The level interval of steel sheep pile support For 2 meters;PH pipes are not more than 3 meters, and the vertical interval of support is not more than 2 meters;
(6)Draining trench is dug out in bottom land both sides, sump one is set at 30 meters or so and pump drainage is set.Sump diameter or width Spend at 0.6~0.8 meter, depth is at 0.7~1 meter, and crater wall uses bamboo and wood or brick Simple reinforced, and rubble is spread in shaft bottom and filter Water layer;
(7)The strict elevation control of machinery shoveling, prevents basal surface of backbreaking or disturb, and is used instead when digging to more than bottom land absolute altitude 20 centimetres Excavated by manual work is removed, and is repaiied when digging, and carry out foundation construction as early as possible;
(8)Excavating the debris such as loose ground, mud, boulder in groove in groove must be removed, and holding is not soaked.
4th, channel excavation
The absolute altitude of elevation model must be checked before foundation construction, basic bottom is removed by excavated by manual work, trim slots bottom, remove mud and Hack, if any backbreaking, is tamped with gravel sand or old material;, should when section of tubing basis is seated on fill stratum according to design requirement Fill stratum is cut out, pipe substrate absolute altitude, compaction in layers are backfilled to gravel sand.
Treat channel excavation finish and without ponding in the case of, start from pipeline foundation, reinforced concrete pipeline foundation is used C25, thick 200 millimeters of reinforced concrete floors, pipeline rest the head on positioning using prefabricated pipe, and bottom plate divides into the plain concrete bed courses of 100mm thickness C10; When precast concrete pipe pillow is laid on the basis of, it should place steady, it is uniform in point, it should keep 200~300 millis from tube coupling end Rice;Then by there is surveyor to release the basic sideline of concrete as the control line of supporting module, nine clamping plates of template, concrete Commercial Concrete pump Mould is sent into, poker vibrator vibration compacting is used.After after concrete Surface hardened layer, pipe centerline is ejected above.
5th, pipeline laying
Preparation of construction:A, design working drawing and other files are complete, and have been confided a technological secret;B, pipeline and auxiliary construction seat Mark and ttom of pipe absolute altitude have determined that at the scene;C, the product for entering job site have the quality certification of quality inspection department of factory, and had Visible marking, being had using preceding discovery should reject before defect, deformation etc..
Concrete basis is poured, and intensity is up to that can start comb after more than 70%, and step is as follows:
(1)Bottom absolute altitude is defined in pipe during comb, at well location during comb, should control the internal diameter size of inspection shaft;
(2)Pipeline fracture, groove, cleaning conduit section and surface are carried out by program;
(3)Pipe socket and rubber ring quality are checked, the working face of material is cleared up;
(4)In the groove that rubber ring is arranged on to bellmouth, bellmouth should be the direction that meets water;
(5)With tape measure bellmouth depth, and scored marks in tubing socket end, label size should be the depth of bellmouth 0.8-0.85%;
(6)Lubricant is dipped in covering with paint or varnish, is uniformly brushed on the inside of rubber ring and on the outside of tubing socket;
(7)Connecting tube straightened condition is kept, pipeline socket is directed at bellmouth, mark is manually once inserted into.Finally with plug Chi inserts bell and spigot gap, peripherally checks rubber ring installation site;
(8)The position that pipeline is connected with inspection shaft uses short tube, and inspection shaft brick wall short tube exposed parts are preferably less than 600 millimeters, pipe Muscle should be full positioned at brick wall part mortar, is seeped water to prevent seam crossing.
6th, inspection shaft, which is built by laying bricks or stones, includes following steps
(1)Inspection shaft size is carried out according to the logical figure of row and layout design size on the concrete bed course poured, when soil property is poor Using reinforced concrete bottom plate;
(2)Inspection shaft basis should simultaneously be poured with pipeline foundation;
(3)Inspection shaft chute uses brick masonry, and the height of chute should be 1/2nd of caliber, and two shoulders are overboard to centre, and adopt With 1:2 cement sand plasters, inspection shaft, which is built to desired height, lays prefabricated reinforced concrete cover plate, and cover plate is horizontal according to road Slope adjustment brick wall is highly laid, should be first in brick wall top surface seat 1 when cover plate is laid:2 cement mortar, and thickness is 5 millimeters, then will lid Plate lays in place, and cover plate surrounding uses 1:2 cement mortar depressed places jail, smears triangle seam at 45 °, and seam height is 50 millimeters, lays cast iron Should be first in the reserved groove inner seat 1 of cover plate before cage:2 cement mortar, thickness is 1 millimeter, and cage, cage four are laid after correction absolute altitude Week is firm with pea gravel concreten depressed place.
(4)Caliber, direction and the absolute altitude that inspection shaft reserves sewer pipe all should meet design requirement, and the top for reserving sewer pipe should be with Interior wall connects flat, and the junction of inspection shaft and sewer pipe uses 1:2 cement mortar smear triangle seam at 45 °;
(5)Quality requirement:A, inspection shaft inwall must be mutually perpendicular to, and mortar joint mortar is filled with enough, and is firmly bonded, paint it is smooth, it is not permeable not Leakage, does not flake, not crack;Without rubbish in b, well.The debris such as remaining mortar;C, the interim measure done during construction must not be remained; D, cage must be complete, do not rupture, not unfilled corner.
7th, closed-water test
Sewage conduct must be section by section(Pipeline between two inspection shafts is a section)Water inspection is closed, storm sewer is regional extremely in flour sand Few every four to save to take out and close a section, the backfill of groove both sides could be carried out after the assay was approved by closing water;Diameter is equal to or less than 800 millimeters Pipeline water is closed using pound cylinder, the pipeline that diameter is equal to or more than 1000 millimeters closes water using inspection shaft;Should be on request when closing water The examination that first adds water is closed 20 minutes, after just carrying out formally closing water after stable level, calculates the average value of water level decreasing in 30 minutes;Close water Head should be in inspection section upstream line more than top 2 meters;Specifically include following steps:
(1)Close before water, mortar joint and concrete should reach some strength, and pipeline should first pour water 24 hours, pipeline is fully soaked Thoroughly;
(2)The examination that first adds water is closed 20 minutes, after water level decreasing is stable, carries out formally closing water, is calculated 30 minutes water level decreasings and is averaged Value.
8th, trench backfill comprises the following steps
(1)Tear plate earth backing open:Tearing plate earth backing open should be carried out after pipeline acceptance of concealed work is qualified, all to have possessed earth backing condition, all should Earth backing immediately.Bottom land odds and ends (straw bag, template and support equipment etc.) must be cleaned out before earth backing;
(2)During earth backing in groove must not ponding, tearing plate earth backing open should successively be carried out by order from bottom to top, torn open plate every time general 45cm is must not exceed, soil property is poor or support is walked about if meeting, and must not exceed 30cm;
(3)Tear necessary same day earth backing after plate open, during earth backing, mud, humus, frozen soil, organic substance must not be backfilled, and be more than The lump debris such as 10cm building stones, big clod should be broken into pieces;
(4)Pipeline both sides simultaneously uniform should be backfilled, and the both sides discrepancy in elevation must not exceed 30cm, during earth backing, soil must not be directly discharged at into pipe On pipeline joint, the earth backing in the range of tube top above 50cm must be layered leveling.The compactness of groove earth backing is successively checked;
(5)The equipment such as fagging, the dagger pulled down should in time be cleared up, maintained and neatly stack, and accomplish that the complete field of work is clear.
9th, steel sheet pile is extracted
Banket reach closely knit requirement after steel sheet pile is removed, steel sheet pile interval is pulled out, and fills sand in time, keeps soil layer close It is real, and the sheet pile of extraction is cleared up, maintained, and stacked respectively by its length and bending, the degree damaged, one and together.
Described above is only the preferred embodiment of the present invention, and protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (7)

1. a kind of municipal drainage pipeline construction technology, it is characterised in that comprise the following steps:
S1, surveying setting-out:The measure of ditch groove center, excavating sideline positioning and center absolute altitude is carried out, and encrypts the wire of construction Point and bench mark;
S2, beat steel sheet pile and precipitation:Interim horizontal supporting system is added to go along with sb. to guard him using steel sheet pile buried excavation section, heavy excavation is applied Work, and artificial rainmaking is used to the foundation ditch of buried depth≤3.5 meter;
S3, channel excavation:Channel excavation depth is less than 2 meters and excavated using slope;Cutting depth uses steel sheep pile support more than 2 meters Go along with sb. to guard him, support level distance is 2.5 meters, and be excavated to 1.2 meters and be supported using waling plate and steel pipe;
S4, pipeline foundation:The absolute altitude of elevation model is checked before foundation construction, the bottom on basis is dug according to design requirement Remove, trim slots bottom, remove mud and hack, pipe substrate absolute altitude is backfilled to gravel sand, compaction in layers passes through armored concrete bottom Plate makes reinforced concrete pipeline foundation, and after after the hardening of reinforced concrete pipeline surface of base, pipe centerline is ejected in its end face;
S5, pipeline laying:Reinforced concrete pipeline foundation is poured, and intensity starts row and set comb up to after more than 70%;
S6, inspection shaft are built by laying bricks or stones:Caliber, direction and the absolute altitude that inspection shaft reserves sewer pipe all should meet design requirement, reserve sewer pipe Top should connect flat with interior wall, and the junction of inspection shaft and sewer pipe uses 1:2 cement mortar smear triangle seam at 45 °;
S7, closed-water test:The examination that first added water on request when closing water is closed 20 minutes, after carrying out formally closing water after stable level, closes Shui Shui Head should be 2 meters above of top in inspection section upstream line, calculate the average value of water level decreasing in 30 minutes;
S8, trench backfill:The uniform backfill simultaneously of drainage pipeline both sides, the both sides discrepancy in elevation must not exceed 30 centimetres, more than tube top 50 lis Earth backing layering leveling in the range of rice, and the compactness of groove earth backing is successively checked;
S9, extraction steel sheet pile:Banket reach closely knit requirement after steel sheet pile is removed, steel sheet pile interval is pulled out, and in time Sand is filled, keeps soil layer closely knit, and the sheet pile of extraction is cleared up, maintained, and is distinguished by its length and bending, the degree damaged Stack, one simultaneously neat.
2. municipal drainage pipeline construction technology according to claim 1, it is characterised in that the surveying setting-out includes:
(1)Verification bench mark simultaneously sets up temporary bench mark at one along one every 60 meters;
(2)Measurement pipe road ground elevation, pipe centerline, box cut sideline and construct object location;
(3)According to each pipeline unit tell somebody what one's real intentions are and project management department scene investigates the conditions on the spot, contact and assist with each pipeline unit Adjust, the buried pipeline in the range of discharge pipe canal digging;
(4)After excavation is tested pits, its excavation slope value and sliding-resistant system are determined.
3. municipal drainage pipeline construction technology according to claim 1, it is characterised in that the channel excavation includes:
(1)Cut the earth using excavator, trough rim is banked up in the part earthwork, mound is more than 2 meters from groove back gauge, and mound is highly less than 1.5 meters, unnecessary earthwork outward transport;
(2)Shoveling should be worked in coordination with support, and excavator is supported in time after cutting the earth;
(3)When digging depth is to 1.2m, fastener baffle plate is cut the earth with fagging alternately, fagging immediately after deburring, each fagging is high Generally 0.6~0.8 meter of degree;
(4)When digging depth is to 2 meters, fastener at first 0.6~0.8 meter away from ground is answered to fall to support, the level interval of steel sheep pile support For 2 meters, PH pipe diameters are not more than 3 meters, and the vertical interval of support is not more than 2 meters;
(5)Gutter is offered in the bottom land both sides of groove, sump one is set in 30m or so and sets pump drainage, sump is straight Footpath or width use bamboo and wood or brick Simple reinforced in 0.6~0.8m, depth in 0.7~1m, crater wall, and spread in shaft bottom broken Stone drainage layer.
4. municipal drainage pipeline construction technology according to claim 1, it is characterised in that the pipeline laying includes:
(1)Bottom absolute altitude is defined in pipe during comb, at well location during comb, should control the internal diameter size of inspection shaft;
(2)Pipeline fracture, groove, cleaning conduit section and surface are carried out by program;
(3)Pipe socket and rubber ring quality are checked, the working face of material is cleared up;
(4)In the groove that rubber ring is arranged on to bellmouth, bellmouth should be the direction that meets water;
(5)With tape measure bellmouth depth, and scored marks in tubing socket end, label size should be the depth of bellmouth 0.8-0.85%;
(6)Lubricant is dipped in covering with paint or varnish, is uniformly brushed on the inside of rubber ring and on the outside of tubing socket;
(7)Connecting tube straightened condition is kept, pipeline socket is directed at bellmouth, mark is manually once inserted into;Finally with plug Chi inserts bell and spigot gap, peripherally checks rubber ring installation site;
(8)The position that pipeline is connected with inspection shaft uses short tube, and inspection shaft brick wall short tube exposed parts are preferably less than 600 millimeters, pipe Muscle should be full positioned at brick wall part mortar, is seeped water to prevent seam crossing.
5. municipal drainage pipeline construction technology according to claim 1, it is characterised in that the inspection shaft build by laying bricks or stones including with Lower step:
(1)Inspection shaft size is carried out according to the logical figure of row and layout design size on the concrete bed course poured;
(2)Inspection shaft basis should simultaneously be poured with pipeline foundation;
(3)Inspection shaft chute uses brick masonry, and the height of chute should be 1/2nd of caliber, and two shoulders are overboard to centre, and adopt With 1:2 cement sand plasters, inspection shaft, which is built to desired height, lays prefabricated reinforced concrete cover plate, and cover plate is horizontal according to road Slope adjustment brick wall is highly laid, should be first in brick wall top surface seat 1 when cover plate is laid:2 cement mortar, and thickness is 5 millimeters, then will lid Plate lays in place, and cover plate surrounding uses 1:2 cement mortar depressed places jail, smears triangle seam at 45 °, and seam height is 50 millimeters, lays cast iron Should be first in the reserved groove inner seat 1 of cover plate before cage:2 cement mortar, thickness is 1 millimeter, and cage, cage four are laid after correction absolute altitude Week is firm with pea gravel concreten depressed place.
6. municipal drainage pipeline construction technology according to claim 1, it is characterised in that the closed-water test includes following Step:
(1)Close before water, mortar joint and concrete should reach some strength, and pipeline should first pour water 24 hours, pipeline is fully soaked Thoroughly;
(2)The examination that first adds water is closed 20 minutes, after water level decreasing is stable, carries out formally closing water, is calculated 30 minutes water level decreasings and is averaged Value.
7. municipal drainage pipeline construction technology according to claim 1, it is characterised in that the trench backfill includes following Step:
(1)Tear plate earth backing open, after pipeline acceptance of concealed work is qualified, earth backing immediately is cleaned out bottom land odds and ends before earth backing;
(2)During earth backing in groove must not ponding, tearing plate earth backing open should successively be carried out by order from bottom to top, torn open plate every time general It must not exceed 45 centimetres;
(3)Tear same day earth backing after plate open;
(4)Pipeline both sides simultaneously uniform should be backfilled, and the both sides discrepancy in elevation must not exceed 30 centimetres, more than tube top answering in 50 cm ranges Soil layering leveling, and the compactness of groove earth backing is successively checked;
(5)The equipment such as fagging, the dagger pulled down should in time be cleared up, maintained and neatly stack.
CN201710276350.4A 2017-04-25 2017-04-25 Municipal drainage pipeline construction technology Active CN106978843B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710276350.4A CN106978843B (en) 2017-04-25 2017-04-25 Municipal drainage pipeline construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710276350.4A CN106978843B (en) 2017-04-25 2017-04-25 Municipal drainage pipeline construction technology

Publications (2)

Publication Number Publication Date
CN106978843A true CN106978843A (en) 2017-07-25
CN106978843B CN106978843B (en) 2019-11-15

Family

ID=59344167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710276350.4A Active CN106978843B (en) 2017-04-25 2017-04-25 Municipal drainage pipeline construction technology

Country Status (1)

Country Link
CN (1) CN106978843B (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587557A (en) * 2017-09-27 2018-01-16 广东景源建设工程有限公司 Outdoor water engineering construction method
CN107630500A (en) * 2017-09-27 2018-01-26 广东景源建设工程有限公司 A kind of water supply and drainage construction method
CN107724499A (en) * 2017-09-27 2018-02-23 广东景源建设工程有限公司 The construction method and pedestal of sewage conduct
CN108222220A (en) * 2018-01-31 2018-06-29 杭州市市政工程集团有限公司 The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation
CN108505607A (en) * 2018-04-25 2018-09-07 安徽鸿佑建设工程有限公司 A kind of municipal works subsoil drain construction technology process and its method
CN108978838A (en) * 2018-08-10 2018-12-11 湖南省建筑设计院有限公司 Concrete expires packet drainage pipeline tubine construction method
CN109577458A (en) * 2018-12-27 2019-04-05 中国电建集团成都勘测设计研究院有限公司 The method for embedding of pipeline aerial crossing sandy soils stream section
CN110056722A (en) * 2019-04-26 2019-07-26 四川航天建筑工程有限公司 A kind of drainage pipeline and its construction method
CN110273424A (en) * 2018-03-13 2019-09-24 中冶建筑研究总院(上海)有限公司 A kind of construction method of yard piping
CN110333018A (en) * 2019-06-14 2019-10-15 浙江华东工程安全技术有限公司 45 ° of rectangular rosettes and inspection shaft concrete cushion principal stress test method
CN110468938A (en) * 2019-07-02 2019-11-19 北京质诚捷讯水利工程有限公司 A kind of municipal drain pipeline construction method
CN110593375A (en) * 2019-08-29 2019-12-20 上海景铭建设发展有限公司 Pipe burying construction method for pipeline by adopting digging groove
CN111021509A (en) * 2019-12-18 2020-04-17 诚通凯胜生态建设有限公司 Municipal drainage pipeline construction method
CN111021508A (en) * 2019-12-16 2020-04-17 南通永泰建设工程有限公司 Underground drainage pipeline construction process
CN111042049A (en) * 2019-12-30 2020-04-21 中建港航局集团有限公司 Rainwater pipe construction process
CN111677095A (en) * 2020-06-19 2020-09-18 中建富林集团有限公司 Construction method of drainage pipeline
CN112227499A (en) * 2020-10-24 2021-01-15 安徽宸昊工程设计有限公司 Municipal drainage pipeline construction technology
CN112283445A (en) * 2020-10-26 2021-01-29 张学昌 Quick connecting pipe hoop for pipeline construction and construction method thereof
CN113339588A (en) * 2021-04-13 2021-09-03 张家港市永茂建筑工程有限公司 Pipeline frame and construction method for newly-built access well of drainage pipeline using pipeline frame
CN113374055A (en) * 2021-06-18 2021-09-10 中铁四局集团有限公司 Construction method of buried reinforced HDPE (high-density polyethylene) spiral corrugated pipe
CN113445606A (en) * 2021-07-07 2021-09-28 中建八局第四建设有限公司 Old community sewer pipeline paving and modifying method
CN113585426A (en) * 2021-08-25 2021-11-02 北方国际合作股份有限公司 Construction process of outdoor drainage pipeline
CN113622235A (en) * 2021-08-05 2021-11-09 广州市艺杰园林建设工程有限公司 Green construction method for water accumulation preventing ecological garden road
CN113668613A (en) * 2021-08-27 2021-11-19 中国江苏国际经济技术合作集团有限公司 Application of GRP sewage well in ultra-deep sewage pipeline system

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335445B (en) * 2020-03-18 2021-11-02 中国十七冶集团有限公司 Construction method of concrete catch basin by using steel pipe as inner mold

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH108445A (en) * 1996-06-25 1998-01-13 Kawasaki Steel Corp Laying method for piping
KR20060092193A (en) * 2006-08-02 2006-08-22 (주)동양엠티 Method for constructing propulsion base for the construction method for propulsion steelpipe
CN106320368A (en) * 2016-08-21 2017-01-11 中铁四局集团有限公司 Construction method applicable to open-excavation pipeline at compound stratum
CN106402492A (en) * 2016-10-26 2017-02-15 朱育盼 Method and device for pipeline laying

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH108445A (en) * 1996-06-25 1998-01-13 Kawasaki Steel Corp Laying method for piping
KR20060092193A (en) * 2006-08-02 2006-08-22 (주)동양엠티 Method for constructing propulsion base for the construction method for propulsion steelpipe
CN106320368A (en) * 2016-08-21 2017-01-11 中铁四局集团有限公司 Construction method applicable to open-excavation pipeline at compound stratum
CN106402492A (en) * 2016-10-26 2017-02-15 朱育盼 Method and device for pipeline laying

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
园林工程监理一本通编委会: "《园林工程监理一本通》", 31 August 2007, 地震出版社 *
李华驹: "市政排水管道深基坑开挖支护施工技术浅析", 《低碳世界》 *

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107630500A (en) * 2017-09-27 2018-01-26 广东景源建设工程有限公司 A kind of water supply and drainage construction method
CN107724499A (en) * 2017-09-27 2018-02-23 广东景源建设工程有限公司 The construction method and pedestal of sewage conduct
CN107587557A (en) * 2017-09-27 2018-01-16 广东景源建设工程有限公司 Outdoor water engineering construction method
CN108222220A (en) * 2018-01-31 2018-06-29 杭州市市政工程集团有限公司 The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation
CN108222220B (en) * 2018-01-31 2024-04-02 杭州市市政工程集团有限公司 Construction method for connecting new sewage pipe and old sewage pipe in displacement transformation of sewage pipe
CN110273424A (en) * 2018-03-13 2019-09-24 中冶建筑研究总院(上海)有限公司 A kind of construction method of yard piping
CN108505607A (en) * 2018-04-25 2018-09-07 安徽鸿佑建设工程有限公司 A kind of municipal works subsoil drain construction technology process and its method
CN108978838A (en) * 2018-08-10 2018-12-11 湖南省建筑设计院有限公司 Concrete expires packet drainage pipeline tubine construction method
CN109577458A (en) * 2018-12-27 2019-04-05 中国电建集团成都勘测设计研究院有限公司 The method for embedding of pipeline aerial crossing sandy soils stream section
CN110056722A (en) * 2019-04-26 2019-07-26 四川航天建筑工程有限公司 A kind of drainage pipeline and its construction method
CN110333018A (en) * 2019-06-14 2019-10-15 浙江华东工程安全技术有限公司 45 ° of rectangular rosettes and inspection shaft concrete cushion principal stress test method
CN110468938A (en) * 2019-07-02 2019-11-19 北京质诚捷讯水利工程有限公司 A kind of municipal drain pipeline construction method
CN110593375A (en) * 2019-08-29 2019-12-20 上海景铭建设发展有限公司 Pipe burying construction method for pipeline by adopting digging groove
CN111021508A (en) * 2019-12-16 2020-04-17 南通永泰建设工程有限公司 Underground drainage pipeline construction process
CN111021509A (en) * 2019-12-18 2020-04-17 诚通凯胜生态建设有限公司 Municipal drainage pipeline construction method
CN111042049A (en) * 2019-12-30 2020-04-21 中建港航局集团有限公司 Rainwater pipe construction process
CN111677095A (en) * 2020-06-19 2020-09-18 中建富林集团有限公司 Construction method of drainage pipeline
CN112227499A (en) * 2020-10-24 2021-01-15 安徽宸昊工程设计有限公司 Municipal drainage pipeline construction technology
CN112283445A (en) * 2020-10-26 2021-01-29 张学昌 Quick connecting pipe hoop for pipeline construction and construction method thereof
CN113339588A (en) * 2021-04-13 2021-09-03 张家港市永茂建筑工程有限公司 Pipeline frame and construction method for newly-built access well of drainage pipeline using pipeline frame
CN113374055A (en) * 2021-06-18 2021-09-10 中铁四局集团有限公司 Construction method of buried reinforced HDPE (high-density polyethylene) spiral corrugated pipe
CN113445606A (en) * 2021-07-07 2021-09-28 中建八局第四建设有限公司 Old community sewer pipeline paving and modifying method
CN113622235A (en) * 2021-08-05 2021-11-09 广州市艺杰园林建设工程有限公司 Green construction method for water accumulation preventing ecological garden road
CN113585426A (en) * 2021-08-25 2021-11-02 北方国际合作股份有限公司 Construction process of outdoor drainage pipeline
CN113668613A (en) * 2021-08-27 2021-11-19 中国江苏国际经济技术合作集团有限公司 Application of GRP sewage well in ultra-deep sewage pipeline system

Also Published As

Publication number Publication date
CN106978843B (en) 2019-11-15

Similar Documents

Publication Publication Date Title
CN106978843B (en) Municipal drainage pipeline construction technology
CN110306616B (en) Construction method of sewage pipeline
CN103758084B (en) A kind of ecological riverway interlocking type building block and construct the construction that protects bank
CN107587557A (en) Outdoor water engineering construction method
CN103669291B (en) The construction method of articulated revetment brick bank protection
CN108166397A (en) Railway frame bridge construction method
CN110344423A (en) A kind of drop shaft sinking forms the construction method of water level for local deep foundation pit under high water level
CN107151950A (en) The construction method of desert area railway underground water route moat
CN107859041B (en) The construction method of collapsible loess zanjon high roadbed structure
CN111677095A (en) Construction method of drainage pipeline
CN109914161B (en) Construction method of high-speed railway filling roadbed in soft soil area
CN106761776A (en) Existing pipeline construction method is worn under super shallow-buried tunnel shield
CN109252549A (en) A kind of bentonite waterproof blanket and its construction method for man-made lake wetland
CN110397079A (en) Marine facies rich water karst strata open-cut station construction technology
CN101424063A (en) Interim and permanent roads single time construction method
CN109706952A (en) Large-scale well-sinking construction method
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN111778941A (en) High-standard farmland channel construction method and structure
CN108411933A (en) Soft soil foundation concrete reinforced pipe construction method and its foundation structure
CN110761316B (en) Prefabricated foundation ring beam prefabricating method and storage tank construction method applying prefabricated foundation ring beam prefabricating method
CN205399440U (en) Inflation dirt road moat structure
CN107152012A (en) Sluice construction technique
CN106638675A (en) Reverse structural steel and bamboo splint soil retaining construction method
CN109610429A (en) Sedimentation treatment method under a kind of Collapsible Loess District prevention gas collection station ground and terrace
CN106638684B (en) A kind of piping lane backfill soil processing method of Collapsible Loess District

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant