JPH10311033A - Collared steel pipe pile and penetration method therefor - Google Patents

Collared steel pipe pile and penetration method therefor

Info

Publication number
JPH10311033A
JPH10311033A JP12065197A JP12065197A JPH10311033A JP H10311033 A JPH10311033 A JP H10311033A JP 12065197 A JP12065197 A JP 12065197A JP 12065197 A JP12065197 A JP 12065197A JP H10311033 A JPH10311033 A JP H10311033A
Authority
JP
Japan
Prior art keywords
steel pipe
pipe pile
flange
collar
flanged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12065197A
Other languages
Japanese (ja)
Inventor
Tadaya Onda
忠彌 恩田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP12065197A priority Critical patent/JPH10311033A/en
Publication of JPH10311033A publication Critical patent/JPH10311033A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve work environment by applying the constitution that a collar having a joint means is preliminarily secured to the end of a steel pipe pile, and collared steel pipe piles so formed are carried to a work space under a building and driven into a subsoil in such a state as being jointed each other with the collars. SOLUTION: A collar 2 made of metal such as a steel plate is welded to one end of a steel pipe pile 10, and a jointing flange 3 is welded to the other end thereof. The collar 2 is a circular or square flat plate body and the center thereof is formed to have a through-hole for inserting a steel pipe. Also, through- holes 2b as jointing means for the collar 2 are formed at equal intervals around the center through-hole. A collared steel pipe pile 1 with the collar 2 secured to the end of the steel pipe pile 10 at a factory of the like is carried to a construction site, and further carried into work space under a building foundation. Then, the collar 2 and the collar 2 of the next-stage collared steel pipe pile 1 are connected with bolts and nuts. A reaction force is taken from the lower surface of the building foundation, and the collared steel pipe pile 1 is pushed into a subsoil by use of a jack. According to this construction, no welding work is required and work environment in narrow space is improved.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、建物の基礎を支持
するため地盤に打ち込まれる鋼管杭とその貫入方法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steel pipe pile driven into the ground to support the foundation of a building and a method of penetrating the steel pipe pile.

【0002】[0002]

【従来の技術】従来、建物の地盤沈下による傾きを修正
したり、傾くおそれのある建物の基礎を支持したりする
鋼管杭においては、建物の基礎の下に作業空間を確保し
て、該基礎に反力をとって鋼管杭を地盤に打ち込み、建
物を支持させることが知られている。
2. Description of the Related Art Conventionally, in a steel pipe pile for correcting a tilt due to land subsidence of a building or for supporting a foundation of a building which may be tilted, a work space is secured under the foundation of the building to secure the working space. It is known that a steel pipe pile is driven into the ground by taking a reaction force to support the building.

【0003】そして、鋼管杭を連結して地盤12に打ち
込むには、図8乃至図9に示すように、作業空間内で鋼
管杭10,10の上下端面同士を溶接手段aで連結し
て、鋼管杭を伸張させている。また、鋼管杭の支持力を
増大させるために、鋼管杭10の途中に鍔11を溶接手
段で取り付けている。この場合、地盤12に鍔付鋼管杭
を連結しながら基礎に反力をとってジャッキなどで押し
込み、鍔11と鍔11との間で地盤と鋼管杭との空隙に
は、砂利や砂若しくは充填用の薬剤などを充填するもの
である。
In order to connect the steel pipe piles and drive them into the ground 12, as shown in FIGS. 8 and 9, the upper and lower end surfaces of the steel pipe piles 10 are connected to each other by a welding means a in a work space. The steel pipe pile is being extended. Further, in order to increase the supporting force of the steel pipe pile, a flange 11 is attached in the middle of the steel pipe pile 10 by welding means. In this case, while connecting the flanged steel pipe pile to the ground 12, a reaction force is applied to the foundation and pushed in by a jack or the like, and the gap between the ground and the steel pipe pile between the flanges 11 is filled with gravel, sand, or filling. It is filled with chemicals for use.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、前記鋼
管同士の溶接作業や、鋼管杭の途中に鍔を溶接して固着
する溶接作業も、建物の基礎下の狭い作業空間内で行う
ものであり、その溶接作業に伴う強い光や煙などの発生
により作業環境が悪化すると言う問題点がある。このよ
うに、従来の建物を支持する鋼管杭は、その作業性と作
業環境において解決すべき課題を有している。
However, the welding work of the steel pipes and the welding work of welding and fixing a flange in the middle of a steel pipe pile are also performed in a narrow working space under the foundation of the building. There is a problem that the working environment deteriorates due to the generation of strong light or smoke accompanying the welding operation. As described above, the conventional steel pipe pile supporting a building has problems to be solved in its workability and work environment.

【0005】[0005]

【課題を解決するための手段】本発明に係る鍔付鋼管杭
の貫入方法の上記課題を解決するための要旨は、鋼管杭
の端部に連結手段を有した鍔を予め固着し、該鍔付鋼管
杭を建物下の作業空間に搬入し、前記鍔で鋼管杭同士を
連結しながら地盤に打ち込むことである。
The gist of the present invention for solving the above-mentioned problem of the method for penetrating a flanged steel pipe pile according to the present invention is that a flange having connection means is previously fixed to an end of the steel pipe pile, The steel pipe piles are carried into the work space under the building, and are driven into the ground while connecting the steel pipe piles with each other by the flange.

【0006】前記地盤に打ち込む先端の鋼管杭は、両端
部に鍔を固着した鍔付鋼管杭をその中央部で切断し、そ
の鍔のない切断部分を地盤に向けてセットした先導管で
あることである。
[0006] The steel pipe pile at the tip to be driven into the ground is a front pipe in which a flanged steel pipe pile having flanges fixed to both ends is cut at the center, and a cut portion without the flange is set toward the ground. It is.

【0007】本発明に係る鍔付鋼管杭の貫入方法の要旨
は、鋼管杭の端部に連結手段を有した鍔を固着してなる
ことであり、更に、前記鍔を鋼管杭の端面から突出させ
るか若しくは後退させるかして該鋼管杭の端部に固着さ
れて、該鋼管杭の端部に連結用のガイド部が形成されて
いることである。
The gist of the method for penetrating a flanged steel pipe pile according to the present invention is that a flange having connection means is fixed to an end of the steel pipe pile, and the flange is projected from an end face of the steel pipe pile. That is, it is fixed to the end of the steel pipe pile by being moved or retracted, and a guide portion for connection is formed at the end of the steel pipe pile.

【0008】本発明に係る鍔付鋼管杭の貫入方法および
その鋼管杭によれば、鋼管杭に予め鋼管連結用の鍔が固
着されているので、建物の基礎下の狭い作業空間におい
て溶接作業をする必要が無いので、作業者の作業環境の
改善となり、また、鋼管杭のガイド部によりボルトなど
で容易に鋼管杭を首尾連接することができ作業工数が低
減されて工期短縮に貢献するものとなる。
According to the method for penetrating a flanged steel pipe pile according to the present invention and the steel pipe pile, a flange for connecting steel pipes is fixed to the steel pipe pile in advance, so that welding work can be performed in a narrow work space under the foundation of a building. Since it is not necessary to improve the working environment for the workers, the steel pipe pile guides can easily connect the steel pipe piles with bolts, etc. Become.

【0009】[0009]

【発明の実施の形態】次に、本発明に係る鍔付鋼管杭の
貫入方法とその鍔付鋼管杭について図面を参照して説明
する。なお、発明に理解容易のため従来例に対応する部
分には従来例と同一の符号を付けて説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, a method for penetrating a flanged steel pipe pile according to the present invention and the flanged steel pipe pile will be described with reference to the drawings. Note that, for easy understanding of the present invention, portions corresponding to the conventional example are denoted by the same reference numerals as the conventional example.

【0010】本発明の第1実施例において、鍔付鋼管杭
1は、図1に示すように、鋼管杭10の端部に、例え
ば、一端部に鉄板等の金属製の鍔2を溶接手段で固着
し、他端部に連結用フランジ3を溶接手段で固着してな
るものである。この溶接作業は工場などで予め固着して
おくものである。
In the first embodiment of the present invention, as shown in FIG. 1, a flanged steel pipe pile 1 is formed by welding a metal flange 2 such as an iron plate to one end of a steel pipe pile 10, for example. And the connecting flange 3 is fixed to the other end by welding means. This welding work is performed in advance at a factory or the like.

【0011】前記鍔2には、図2(イ)、(ロ)に示す
ように、円形状または角形状の平板体であって、その中
央部に鋼管挿通用の貫通孔2aが設けられ、該貫通孔2
aの周囲に鍔2用の連結手段たる貫通孔2bが、少なく
とも3個で、この実施例では4個にして周方向に等間隔
で設けられている。
As shown in FIGS. 2A and 2B, the flange 2 is a circular or square plate having a through hole 2a for inserting a steel pipe at the center thereof. The through hole 2
At least three through holes 2b, which are connecting means for the collar 2, are provided around the periphery of a in FIG.

【0012】また、この鍔2の大きさは、前記通常の連
結用フランジ3の面積よりも大きく、鋼管杭10の断面
積の約2〜3倍の面積にされている。
The size of the flange 2 is larger than the area of the normal connecting flange 3 and is set to be approximately two to three times the cross-sectional area of the steel pipe pile 10.

【0013】また、鋼管杭10の両端部に、前記鍔2を
溶接手段にて固着してもよいものである。
Further, the flange 2 may be fixed to both ends of the steel pipe pile 10 by welding means.

【0014】そして、工場などで鋼管杭10の端部に予
め鍔2が固着された鍔付鋼管杭1を、現場に搬入し、建
物の基礎の下に形成した作業用空間内に搬入する。
Then, the flanged steel pipe pile 1 in which the flange 2 is fixed in advance to the end of the steel pipe pile 10 at a factory or the like is carried into the site, and is carried into the working space formed under the foundation of the building.

【0015】地盤12に打ち込んでいる先行した鍔付鋼
管杭1に、図3に示すように、その鍔2と次段の鍔付鋼
管杭1の鍔2とを合わせ、鍔2,2の貫通孔2b,2b
を合わせてそこにボルトを通しナットで締結し、鍔付鋼
管杭1,1を首尾連接する。
As shown in FIG. 3, the flange 2 and the flange 2 of the next-stage flanged steel pipe pile 1 are fitted to the preceding flanged steel pipe pile 1 that has been driven into the ground 12, and the flanges 2 and 2 are penetrated. Holes 2b, 2b
And a bolt is passed therethrough and fastened with a nut to connect the flanged steel pipe piles 1 and 1 successfully.

【0016】そして、建物の基礎の下面に反力をとり、
ジャッキなどで前記鍔付鋼管杭1を地盤12に押し込ん
でいくものである。
Then, a reaction force is applied to the lower surface of the foundation of the building,
The flanged steel pipe pile 1 is pushed into the ground 12 with a jack or the like.

【0017】次に、本発明の第2実施例として、図4乃
至図5に示すように、鋼管杭10の端部に鍔2を溶接し
て固着する際、前記鍔2を鋼管杭10の端面から突出さ
せるか若しくは後退させるかして該鋼管杭10の端部に
固着し、該鋼管杭10の端部に連結用のガイド部4を形
成して、鋼管杭1a,1bとするものである。
Next, as a second embodiment of the present invention, as shown in FIGS. 4 and 5, when the flange 2 is fixed to the end of the steel pipe pile 10 by welding, the flange 2 is attached to the steel pipe pile 10. The steel pipe pile 10 is fixed to the end of the steel pipe pile 10 by projecting or retracting from the end face, and a connecting guide portion 4 is formed at the end of the steel pipe pile 10 to obtain the steel pipe piles 1a and 1b. is there.

【0018】図4(イ)に示すように、鍔2を鋼管杭1
0の端面からαだけ後退させて、突出したガイド部4を
形成し、これに嵌合させるものとして、図4(ロ)に示
すように、鍔2を鋼管杭10の端面から略前記α分に等
しいβ分突出させてガイド部4を形成するものである。
As shown in FIG. 4A, the flange 2 is connected to the steel pipe pile 1.
As shown in FIG. 4B, the flange 2 is retracted from the end face of the steel pipe pile 10 by approximately α from the end face of the steel pipe pile 10 so as to be retracted by α from the end face of the steel pipe pile 10 to form a protruding guide section 4 and to be fitted into the guide section 4. The guide portion 4 is formed so as to protrude by β equal to.

【0019】そして、前記鋼管杭1a,1bを連結する
には、図5に示すように、突出したガイド部4に嵌合さ
せるようにして鋼管杭1bを嵌装させ、位置合わせした
鍔2,2の貫通孔2b,2bにボルトを挿通させナット
で締結するものである。
In order to connect the steel pipe piles 1a and 1b, as shown in FIG. 5, the steel pipe piles 1b are fitted so as to be fitted to the protruding guide portions 4, and the aligned flanges 2 are arranged. The bolts are inserted through the through holes 2b, 2b, and fastened with nuts.

【0020】このように、鋼管杭10の端部に鍔2を固
着する際に、ガイド部4を設けることで、鋼管杭1a,
1bの連結が容易となるものである。
As described above, when the flange 2 is fixed to the end of the steel pipe pile 10, the provision of the guide part 4 enables the steel pipe pile 1 a,
1b can be easily connected.

【0021】本発明の第3実施例として、地盤12に打
ち込む鍔付鋼管杭1のうち、先端のものは、図6乃至図
7に示すように、鋼管杭10の少なくとも一端部に鍔2
を固着した鍔付鋼管杭1cを、その中央部で切断し、そ
の鍔2のない切断部分1dを地盤12に向けてセットす
る先導管にするものである。
As a third embodiment of the present invention, the tip of a flanged steel pipe pile 1 driven into the ground 12 has a flange 2 at least at one end of the steel pipe pile 10 as shown in FIGS.
The flanged steel pipe pile 1c to which is fixed is cut at the center thereof, and the cut portion 1d without the flange 2 is used as a leading conduit for setting the ground portion 12 toward the ground 12.

【0022】この先導管を杭の先端とすることで、前記
切断部分1dがジャッキで圧入される際に、地盤12に
食い込んで横方向に位置ズレせずに確実に貫入させるこ
とが出来るものである。
By using the leading end of the pile as the tip of the pile, when the cut portion 1d is press-fitted with a jack, the cut portion 1d can penetrate into the ground 12 without being displaced in the lateral direction and can be reliably penetrated. .

【0023】以上のように、本発明の第1実施例乃至第
3実施例において、鍔付鋼管杭1,1a,1b,1cを
建物の基礎の下面に反力をとってジャッキ等で地盤12
に押し込むことで、首尾連接した鋼管杭の鍔2,2間で
鋼管杭10と地盤12との間の空隙ができるので、ここ
に砂利や砂若しくは充填用の薬剤,資材を充填して支持
力を強化し、鍔付鋼管杭を地盤12に貫入させて、建物
の基礎を支持して沈下を防止するものである。
As described above, in the first to third embodiments of the present invention, the flanged steel pipe piles 1, 1a, 1b, and 1c are placed on the ground 12 by jacks or the like by applying a reaction force to the lower surface of the foundation of the building.
To form a gap between the steel pipe pile 10 and the ground 12 between the flanges 2 and 2 of the steel pipe piles that have been successfully connected, so that gravel, sand, or a filling agent or material is filled into the gap to support the steel pipe pile. And a flanged steel pipe pile penetrates the ground 12 to support the foundation of the building and prevent settlement.

【0024】[0024]

【発明の効果】以上説明したように、本発明に係る鍔付
鋼管杭の貫入方法は、鋼管杭の端部に連結手段を有した
鍔を予め固着し、該鍔付鋼管杭を建物下の作業空間に搬
入し、前記鍔で鋼管杭同士を連結しながら地盤に打ち込
む方法なので、前記作業空間内ではボルト等による鍔の
連結作業を施工することで鋼管杭の連結が出来、溶接作
業が不要となって狭い作業空間での作業環境が改善さ
れ、作業能率も向上して工期短縮となるという優れた効
果を奏するものである。
As described above, according to the method for penetrating a flanged steel pipe pile according to the present invention, a flange having a connecting means is fixed to an end of the steel pipe pile in advance, and the flanged steel pipe pile is placed under a building. It is carried into the work space and driven into the ground while connecting the steel pipe piles with each other with the flange, so in the work space, the connection of the steel pipe piles can be performed by connecting the flanges with bolts etc., and welding work is unnecessary As a result, the working environment in a narrow working space is improved, the working efficiency is improved, and the construction period is shortened.

【0025】また、前記地盤に打ち込む先端の鋼管杭
は、両端部に鍔を固着した鍔付鋼管杭をその中央部で切
断し、その鍔のない切断部分を地盤に向けてセットした
先導管とすることで、位置ズレなく所定の位置に鍔付鋼
管杭を貫入させることが出来るという優れた効果を奏す
るものである。
Further, the steel pipe pile at the tip to be driven into the ground is formed by cutting a flanged steel pipe pile having flanges fixed to both ends at the center thereof, and setting a cut portion without the flange toward the ground. By doing so, there is an excellent effect that the flanged steel pipe pile can be penetrated into a predetermined position without displacement.

【0026】更に、前記鋼管杭の端部に鍔を固着する際
には、該鍔を鋼管杭の端面から突出させるか若しくは後
退させるかして、該鋼管杭の端部に連結用のガイド部を
設けて鍔付鋼管杭を形成し、当該ガイド部を利用して鋼
管杭を連結するようにすることで、狭い作業空間でも容
易に鋼管杭を正確に連結させることが容易に出来るとい
う優れた効果を奏するものである。
Further, when the flange is fixed to the end of the steel pipe pile, the flange is projected or retracted from the end face of the steel pipe pile, and a guide portion for connection is provided at the end of the steel pipe pile. By forming a flanged steel pipe pile and providing a connection between the steel pipe piles using the guide portion, it is possible to easily and accurately connect the steel pipe piles even in a narrow work space. It is effective.

【0027】本発明に係る鍔付鋼管杭は、鋼管杭の端部
に連結手段を有した鍔を固着してなるので、予め工場で
制作することで、溶接も確実に出来て、現場での作業が
無くなって、作業環境の改善と作業能率の向上となると
いう優れた効果を奏するものである。
In the flanged steel pipe pile according to the present invention, a flange having a connecting means is fixed to the end of the steel pipe pile. There is an excellent effect that the work is eliminated and the working environment is improved and the working efficiency is improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1実施例に係る鍔付鋼管杭の一部を
破断して示す正面図である。
FIG. 1 is a partially cutaway front view showing a flanged steel pipe pile according to a first embodiment of the present invention.

【図2】同本発明に係る鍔付鋼管杭の鍔の斜視図
(イ)、(ロ)である。
FIG. 2 is perspective views (a) and (b) of a flange of the flanged steel pipe pile according to the present invention.

【図3】同本発明に係る鍔付鋼管杭を連結した様子を示
す説明図である。
FIG. 3 is an explanatory view showing a state where flanged steel pipe piles according to the present invention are connected.

【図4】同本発明に係る第2実施例の鍔付鋼管杭の一部
正面図(イ)、(ロ)である。
FIG. 4 is a partial front view (a) and (b) of a flanged steel pipe pile according to a second embodiment of the present invention.

【図5】同本発明に係る第2実施例の鍔付鋼管杭の使用
状態を示す説明図である。
FIG. 5 is an explanatory view showing a use state of a flanged steel pipe pile according to a second embodiment of the present invention.

【図6】同本発明の第3実施例に係る鍔付鋼管杭を形成
する方法を示す説明図である。
FIG. 6 is an explanatory view showing a method for forming a flanged steel pipe pile according to a third embodiment of the present invention.

【図7】同本発明の第3実施例に係る鍔付鋼管杭の使用
状態を示す説明図である。
FIG. 7 is an explanatory view showing a use state of a flanged steel pipe pile according to a third embodiment of the present invention.

【図8】従来例に係る鋼管杭の連結方法と鍔の固着方法
を示す説明図(イ)、(ロ)である。
FIGS. 8A and 8B are explanatory views (a) and (b) showing a method of connecting a steel pipe pile and a method of fixing a flange according to a conventional example.

【図9】同従来例に係る鋼管杭の使用状態を示す説明図
(イ)、(ロ)である。
FIG. 9 is an explanatory view (a) and (b) showing a use state of the steel pipe pile according to the conventional example.

【符号の説明】[Explanation of symbols]

1,1a,1b,1c 鍔付鋼管杭 、2 鍔、2b
連結手段の貫通孔、3 フランジ、4 ガイド部、 1
0 鋼管、11 鍔、12 地盤。
1, 1a, 1b, 1c flanged steel pipe pile, 2 flange, 2b
Through-hole of connecting means, 3 flanges, 4 guides, 1
0 steel pipe, 11 tsuba, 12 ground.

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】鋼管杭の端部に連結手段を有した鍔を予め
固着し、該鍔付鋼管杭を建物下の作業空間に搬入し、前
記鍔で鋼管杭同士を連結しながら地盤に打ち込むこと、 を特徴とする鍔付鋼管杭の貫入方法。
1. A flange having a connecting means is fixed to an end of a steel pipe pile in advance, and the flanged steel pipe pile is carried into a work space under a building, and is driven into the ground while connecting the steel pipe piles with the flange. A method of penetrating a flanged steel pipe pile, characterized in that:
【請求項2】地盤に打ち込む先端の鋼管杭は、両端部に
鍔を固着した鍔付鋼管杭をその中央部で切断し、その鍔
のない切断部分を地盤に向けてセットした先導管である
こと、 を特徴とする請求項1に記載の鍔付鋼管杭の貫入方法。
2. A steel pipe pile at the tip to be driven into the ground is a front pipe in which a flanged steel pipe pile having flanges fixed to both ends is cut at a central portion thereof, and a cut portion without the flange is set toward the ground. The method for penetrating a flanged steel pipe pile according to claim 1, characterized in that:
【請求項3】鋼管杭の端部に鍔を固着する際には、該鍔
を鋼管杭の端面から突出させるか若しくは後退させるか
して、該鋼管杭の端部に連結用のガイド部を設けて鍔付
鋼管杭を形成し、当該ガイド部を利用して鋼管杭を連結
すること、 を特徴とする請求項1に記載の鍔付鋼管杭の貫入方法。
When the flange is fixed to the end of the steel pipe pile, the flange is projected or retracted from the end face of the steel pipe pile, and a connecting guide portion is provided at the end of the steel pipe pile. The method of penetrating a flanged steel pipe pile according to claim 1, wherein the flanged steel pipe pile is formed to connect the steel pipe piles using the guide portion.
【請求項4】鋼管杭の端部に連結手段を有した鍔を固着
してなること、 を特徴とする鍔付鋼管杭。
4. A flanged steel pipe pile, characterized in that a flange having connection means is fixed to an end of the steel pipe pile.
【請求項5】鍔を鋼管杭の端面から突出させるか若しく
は後退させるかして該鋼管杭の端部に固着されて、該鋼
管杭の端部に連結用のガイド部が形成されていること、 を特徴とする請求項4に記載の鍔付鋼管杭。
5. The steel pipe pile is fixed to an end of the steel pipe pile by projecting or retracting a flange from an end face of the steel pipe pile, and a guide portion for connection is formed at the end of the steel pipe pile. The flanged steel pipe pile according to claim 4, characterized in that:
JP12065197A 1997-05-12 1997-05-12 Collared steel pipe pile and penetration method therefor Pending JPH10311033A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12065197A JPH10311033A (en) 1997-05-12 1997-05-12 Collared steel pipe pile and penetration method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12065197A JPH10311033A (en) 1997-05-12 1997-05-12 Collared steel pipe pile and penetration method therefor

Publications (1)

Publication Number Publication Date
JPH10311033A true JPH10311033A (en) 1998-11-24

Family

ID=14791514

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12065197A Pending JPH10311033A (en) 1997-05-12 1997-05-12 Collared steel pipe pile and penetration method therefor

Country Status (1)

Country Link
JP (1) JPH10311033A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102513630A (en) * 2011-12-20 2012-06-27 北京航科发动机控制系统科技有限公司 Positioning and laminating method for steel plates of cleaning start valve
JP2017186752A (en) * 2016-04-01 2017-10-12 あおみ建設株式会社 Method for establishing compaction ground improvement pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102513630A (en) * 2011-12-20 2012-06-27 北京航科发动机控制系统科技有限公司 Positioning and laminating method for steel plates of cleaning start valve
JP2017186752A (en) * 2016-04-01 2017-10-12 あおみ建設株式会社 Method for establishing compaction ground improvement pile

Similar Documents

Publication Publication Date Title
EP2141286B1 (en) Spiral steel pipe pile
KR20170005991A (en) soil retaining wall using PHC pile and its construction method
JP3095376B2 (en) Construction method of building foundation
JPH10311033A (en) Collared steel pipe pile and penetration method therefor
JP4556737B2 (en) Steel pipe joint structure used in pipe roof construction method and pipe roof construction method
JP2007051485A (en) Structure and method for joining foundation of structure and sheet pile together
JPH11193685A (en) Segment piece
KR20160120160A (en) Precast pile with wale supporting member
JP2003003781A (en) Reinforcing ring and mounting structure of joint plate
JP2009162029A (en) Retaining wall
JP2000008398A (en) Correcting method and correcting device for building having uneven settlement
JP2821477B2 (en) Equipment for preventing misalignment of buried piles
JPS61250222A (en) Method and apparatus for connection of pile
JP3116098B2 (en) Construction method for underground structures
JP3236541B2 (en) Joint method between knotted pile and steel pipe pile
JP3135495B2 (en) Construction method of avalanche and rock fall protection fence and avalanche and rock fall protection fence
JP3629474B2 (en) Steel pipe sheet pile method
JP4473400B2 (en) Foundation of construction and construction method
JP2566162B2 (en) Method for cutting and expanding between parallel tunnels and supporting device used therefor
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JP4552122B2 (en) Joining structure and joining method of structural column and steel beam
JPH1129953A (en) Penetration method of steel pipe pile, correction method of settlement of building, and joint of steel pipe pile used therefor
JP6545557B2 (en) segment
KR200192128Y1 (en) Pile joint tool
JP2893422B2 (en) Construction method of underground structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040512

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060428

A131 Notification of reasons for refusal

Effective date: 20060515

Free format text: JAPANESE INTERMEDIATE CODE: A131

A02 Decision of refusal

Effective date: 20060919

Free format text: JAPANESE INTERMEDIATE CODE: A02