JP2566162B2 - Method for cutting and expanding between parallel tunnels and supporting device used therefor - Google Patents

Method for cutting and expanding between parallel tunnels and supporting device used therefor

Info

Publication number
JP2566162B2
JP2566162B2 JP1043795A JP4379589A JP2566162B2 JP 2566162 B2 JP2566162 B2 JP 2566162B2 JP 1043795 A JP1043795 A JP 1043795A JP 4379589 A JP4379589 A JP 4379589A JP 2566162 B2 JP2566162 B2 JP 2566162B2
Authority
JP
Japan
Prior art keywords
steel material
horizontal
horizontal supporting
supporting steel
parallel tunnels
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP1043795A
Other languages
Japanese (ja)
Other versions
JPH02221588A (en
Inventor
誠 前田
博一 田口
満壽男 阿曽
卓明 金尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP1043795A priority Critical patent/JP2566162B2/en
Publication of JPH02221588A publication Critical patent/JPH02221588A/en
Application granted granted Critical
Publication of JP2566162B2 publication Critical patent/JP2566162B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、並列トンネル間の切拡げ工法及びこれに
用いる支保装置に関するものである。
TECHNICAL FIELD The present invention relates to a method for expanding and cutting between parallel tunnels and a supporting device used for the method.

「従来の技術、発明が解決せんとする問題点」 従来、トンネル間を切拡げてプラットホーム等を構築
する工法として、上部からの開削による方式またはトン
ネル内からのルーフ方式又はカンザシ桁方式等が用いら
れている。
“Problems to be solved by conventional techniques and inventions” Conventionally, as a method of constructing a platform or the like by expanding the space between tunnels, a method by excavation from the top, a roof method from inside the tunnel, or a girder girder method is used. Has been.

しかしながら、開削方式においてはトンネル上部の構
造物、トンネル深さの関係などから立坑等の小規模なも
のに採用されるケースがあるが、一般的には非常に少な
い。
However, in the case of the excavation method, there are cases in which it is used in small-scale structures such as vertical shafts due to the structure of the tunnel upper part, the tunnel depth, etc.

次に、ルーフ方式はシールドによる場合やパイプによ
るものが多いが、掘削量が多くなる欠点がある。
Secondly, the roof method is often based on a shield or a pipe, but it has a drawback of increasing the amount of excavation.

そこで、掘削量を少なくする方法としてカンザシ桁に
よる方式があるが、この場合左右のトンネル上に誤差等
を生ずると施工が困難な上に、トンネル上部での作業空
間の狭いところでの作業となるため、短い桁材を継ぎな
がら挿入する形になり、工期、工費の面で不利となる場
合が少なくない。
Therefore, there is a method of using a girder girder as a method to reduce the amount of excavation, but in this case it will be difficult to construct if errors occur on the left and right tunnels, and it will be a work in a narrow work space above the tunnel. , It is often the case that the short girder material is inserted while being spliced, which is disadvantageous in terms of construction period and construction cost.

また、これらの工法の共通の問題として、並列トンネ
ルの施工においては、各トンネル間に水平及び鉛直方向
の施工誤差が数cmから数十cmになることが不可欠である
ことから、トンネル間に水平支保部材等を設置する時に
は、その都度並列トンネル間の距離を測定し、大型支保
部材になると継手を設けた上に部材端部の切断又は溶接
を繰返しながら設置することになるが、完全な状態で設
置することが困難で、施工も煩雑であるなどの問題があ
った。
In addition, as a common problem with these construction methods, it is essential that the horizontal and vertical construction errors be between several cm and several tens of cm between the tunnels when constructing parallel tunnels. When installing support members, etc., measure the distance between parallel tunnels each time, and if it becomes a large support member, it will be installed by repeatedly cutting or welding the end of the member after installing a joint, but in a perfect condition There was a problem that it was difficult to install in, and the construction was complicated.

「問題点を解決するための手段」 この発明は前記従来の課題を解決するために、並列ト
ンネル間の上部を掘削してその切羽天端に左右一対の水
平支持鋼材を一方の先端部に継手鋼材の一端をボルトに
より締結すると共に、他端を前記他方の水平支持鋼材の
先端部に軸方向にスライド可能にボルトにより仮締め
し、前記継手鋼材の後端部とその後方における前記他方
の水平支持鋼材に設けた反力受間に設置したジャッキに
より、他方の水平支持鋼材をスライドさせ、前記左右の
水平支持鋼材の後端部を左右の並列トンネル外周面に密
着して支持させた状態において、前記継手鋼材と前記他
方の水平支持鋼材をボルトにより締結し、前記水平支持
鋼材の下方を保持部材により支持し、順次掘削しながら
同様に前記水平支持鋼材を並列トンネル間に設置するこ
とにより、並列トンネル間の施工誤差に応じて左右一対
の水平支持鋼材を継手鋼材を介してジャッキによりスラ
イド調節し、狭い作業空間においても極めて簡単かつ確
実に並列トンネル間に水平支持鋼材の端部を密着して設
置することを可能とすると共に、トンネルの掘削量も少
ない合理的な切拡げ工法及びこれに用いる支保装置を提
案するものである。
[Means for Solving the Problems] In order to solve the above-mentioned conventional problems, the present invention excavates an upper portion between parallel tunnels, and joins a pair of left and right horizontal supporting steel members to the top end of the face with one tip end portion. One end of the steel material is fastened with a bolt, and the other end is temporarily tightened with a bolt so as to be slidable in the axial direction on the tip end portion of the other horizontal supporting steel material, and the rear end portion of the joint steel material and the other horizontal portion behind the joint steel material. In a state where the other horizontal supporting steel material is slid by the jack installed between the reaction force receiving members provided on the supporting steel material, and the rear ends of the left and right horizontal supporting steel materials are closely adhered to and supported by the outer peripheral surfaces of the left and right parallel tunnels. , The joint steel material and the other horizontal support steel material are fastened by bolts, the lower part of the horizontal support steel material is supported by a holding member, and the horizontal support steel material is similarly installed between parallel tunnels while sequentially excavating. By installing, the pair of left and right horizontal supporting steels can be slide-adjusted by jacks through the joint steels according to the construction error between the parallel tunnels, and even in a narrow working space, the horizontal supporting steels can be very easily and reliably installed between the parallel tunnels. The present invention proposes a rational cutting and expanding method and a supporting device used for the method, in which the ends can be installed closely and the amount of tunnel excavation is small.

「実施例」 以下この発明を図面に示すプラットホームを構築する
実施例について説明すると、左右の並列トンネル1,1′
の隣接する内側壁部に、これと一体に切拡げ目的の構築
物のサイド部2として柱・梁及び床からなるサイドホー
ムを構築すると共に、並列トンネル1,1′の防護仮設物
3を設置する。
[Embodiment] An embodiment for constructing a platform shown in the drawings for the present invention will be described below. The left and right parallel tunnels 1, 1 '
A side home consisting of columns, beams, and floors will be constructed as the side part 2 of the structure intended to be cut and expanded integrally with the adjacent inner wall part of, and the protective temporary structure 3 of the parallel tunnels 1, 1'will be installed. .

この状態で、並列トンネル1,1′間の上部片側を所要
長掘削し、その切羽上部にH型鋼等の型鋼からなる水平
支持鋼材4を建込み、その後端を一側の並列トンネル1
の外壁に設けた係合凹部に支持すると共に、その先端部
を仮支柱5に支持し、水平支持鋼材4と地山間に木矢板
等の土留板6及び桁材7を挿入設置し、地山を安定させ
る。
In this state, one side of the upper part of the parallel tunnel 1,1 'is excavated for a required length, and a horizontal supporting steel material 4 made of a shape steel such as H-shaped steel is erected on the upper face of the face, and the rear end of the horizontal tunnel 1 is formed on one side.
While supporting it in the engaging recess provided on the outer wall of, and supporting the tip end thereof on the temporary support column 5, the earth retaining plate 6 such as wood sheet pile and the girder material 7 are inserted and installed between the horizontal supporting steel material 4 and the ground. Stabilize.

次いで、他側上部を掘削して上記同様に水平支持鋼材
4′を建込み、仮支柱5に支持した上でこれと先の水平
支持鋼材4とを継手鋼材8を介して連結する。
Next, the upper portion on the other side is excavated, the horizontal supporting steel material 4'is built in the same manner as above, and after being supported by the temporary support column 5, this and the previous horizontal supporting steel material 4 are connected via the joint steel material 8.

水平支持鋼材4は、そのウェブ先端部に所要数のボル
ト穴9が設けられ、また水平支持鋼材4′にはそのウェ
ブ先端部に軸方向に沿って上下複数列のボルト挿通用長
孔10が設けられ、この長孔10は並列トンネル1,1′間の
予測される施工誤差範囲の長さに形成されている。
The horizontal support steel material 4 is provided with a required number of bolt holes 9 at its web front end, and the horizontal support steel material 4'is provided with a plurality of upper and lower rows of bolt holes 10 along the axial direction at the web front end thereof. The long hole 10 is provided so as to have a length within a predicted construction error range between the parallel tunnels 1 and 1 '.

また、水平支持鋼材4′の長孔10よりも後方には反力
受11が設けられている。
A reaction force receiver 11 is provided behind the elongated hole 10 of the horizontal supporting steel material 4 '.

継手鋼材8は水平支持鋼材4,4′のウェブ両側に添接
可能な溝型鋼等からなり、その前後端部にはボルト穴9
及び長孔10のピッチに合せたボルト穴12,12′が設けら
れており、その一端には反力受11′が設けられている。
The joint steel material 8 is made of grooved steel or the like that can be affixed to both sides of the web of the horizontal supporting steel materials 4 and 4 ', and bolt holes 9 are provided at the front and rear ends thereof.
And bolt holes 12 and 12 'that match the pitch of the elongated holes 10, and a reaction force receiver 11' is provided at one end thereof.

左右の水平支持鋼材4,4′の連結に際しては、相対向
するそれらの先端部間の両側に継手鋼材8を添接し、そ
の上に座金プレート13を添接した上で、ボルト穴12と水
平支持鋼材4のボルト穴9に高張力ボルト14を挿通して
両者を締結固定すると共に、継手鋼材8の他側のボルト
穴12′と水平支持鋼材4′の長鋼10に高張力ボルト14を
挿通して両者をスライド可能に仮締めする。
When connecting the left and right horizontal supporting steel members 4 and 4 ', joint steel members 8 are abutted on both sides between the tip portions facing each other, and a washer plate 13 is abutted on the joint steel members 8, and then the bolt holes 12 and The high tensile bolts 14 are inserted into the bolt holes 9 of the supporting steel material 4 to fasten and fix them, and the high tensile bolts 14 are attached to the bolt holes 12 'on the other side of the joint steel material 8 and the long steel 10 of the horizontal supporting steel material 4'. Insert them and temporarily tighten both so that they can slide.

そして、継手鋼材8と水平支持鋼材4′の反力受11,1
1′間にジャッキ15をセットし、これを作動して水平支
持鋼材4′を後方にスライドさせ、その後端を他側の並
列トンネル1′の外壁に設けた係合凹部に密着させて支
持し、この状態で仮締めした高張力ボルト14を本締めし
て継手鋼材8と水平支持鋼材4′を締結固定し、これと
地山間に木矢板等の土留板6及び桁材7を挿入設置す
る。
Then, the reaction force of the joint steel material 8 and the horizontal supporting steel material 4'is received 11,1.
Set the jack 15 between the 1'and operate it to slide the horizontal supporting steel material 4'backward so that the rear end is closely contacted with the engaging recess provided on the outer wall of the parallel tunnel 1'on the other side to support it. In this state, the temporarily tightened high-tensile bolt 14 is fully tightened to fasten and fix the joint steel material 8 and the horizontal support steel material 4 ', and the earth retaining plate 6 such as a wood sheet pile and the girder material 7 are inserted and installed between this and the ground. .

このようにして、並列トンネル1,1′間に施工誤差を
生じていても、この誤差に順応して水平支持鋼材4′を
スライドして他側の並列トンネル1′の外壁に設けた係
合凹部に密着させることができ、これによって左右の水
平支持鋼材4,4′を継手鋼材8により連結一体化した長
さ調節自在の切梁により順次掘削地山を確実に支持する
ことができる。
In this way, even if there is a construction error between the parallel tunnels 1 and 1 ', the horizontal support steel material 4'slides in conformity with the error and the engagement provided on the outer wall of the parallel tunnel 1'on the other side. It is possible to make close contact with the recessed portion, whereby the left and right horizontal supporting steel members 4 and 4'are connected and integrated by the joint steel member 8 so that the excavated ground can be sequentially supported by the adjustable length beam.

なお、水平支持鋼材4,4′に急激に設計以上の荷重が
作用した場合に、継手鋼材8に対して水平支持鋼材4′
が滑動する恐れもあることから、水平支持鋼材4,4′の
先端間にT型鋼等を切断したストッパー16を嵌装する。
When a load more than designed is applied to the horizontal supporting steel members 4 and 4 ', the horizontal supporting steel members 4'to the joint steel member 8'
Since there is a risk of slipping, a stopper 16 formed by cutting a T-shaped steel or the like is fitted between the tips of the horizontal supporting steel members 4 and 4 '.

次に、この切梁の下方の上半部の地盤を掘削し、支保
部材としての仮柱17により、あるいは並列トンネル1,
1′のセグメントの一部を撤去した上でサイド部2の梁
に支持した支保部材としての支杖18により切梁を支持す
る。
Next, excavate the ground in the upper half below the beam, and use the temporary pillars 17 as supporting members or the parallel tunnels 1,
After removing a part of the 1'segment, the beam is supported by a supporting member 18 as a supporting member supported by the beam of the side portion 2.

その後、上半部の掘削空間部の両側に露出する並列ト
ンネル1,1′のセグメントを撤去して、トンネル内部と
連通させ、掘削空間部の上部に天井スラブ用型枠19を設
置し、その内部に現場打ちコンクリートを打設して天井
スラブ20をサイド部2の梁と一体に構築する。
After that, the segments of the parallel tunnels 1 and 1'exposed on both sides of the upper half of the excavation space are removed and communicated with the inside of the tunnel, and the ceiling slab formwork 19 is installed on the upper part of the excavation space. The ceiling slab 20 is constructed integrally with the beam of the side part 2 by pouring cast-in-place concrete inside.

型枠19及び仮柱17を撤去した後、下半部の地盤を掘削
し、この掘削空間部の両側に露出するセグメントを撤去
し、左右のサイド部2,2の床部間に下部切梁21を設置し
た後、この床部間に現場打ちコンクリートを打設して一
体の床22を構築する。
After removing the formwork 19 and the temporary columns 17, the bottom half of the ground is excavated, the segments exposed on both sides of this excavation space are removed, and the lower cut beam between the floors of the left and right side parts 2, 2 is removed. After the 21 is installed, cast-in-place concrete is poured between the floors to construct an integrated floor 22.

最後に、防護仮設物3を撤去して施工を完了する。 Finally, the protective temporary structure 3 is removed and the construction is completed.

「発明の効果」 以上の通りこの発明によれば、並列トンネル間の上部
を掘削してその切羽天端に左右一対の水平支持鋼材を一
方の先端部に継手鋼材の一部をボルトにより締結すると
共に、他端を前記他方の水平支持鋼材の先端部に軸方向
にスライド可能にボルトにより仮締めし、前記継手鋼材
の後端部とその後方における前記他方の水平支持鋼材に
設けた反力受間に設置したジャッキにより、他方の水平
支持鋼材をスライドさせ、前記左右の水平支持鋼材の後
端部を左右の並列トンネル外周面に密着して支持させた
状態において、前記継手鋼材と前記他方の水平支持鋼材
をボルトにより締結し、前記水平支持鋼材の下方を支保
部材により支持し、順次掘削しながら同様に前記水平支
持鋼材を並列トンネル間に設置するので、並列トンネル
間の施工誤差に応じて左右一対の水平支持鋼材を継手鋼
材を介してジャッキにより簡単にスライド調節すること
ができ、狭い作業空間においても切断及び溶接などの作
業を要することもなく極めて簡単な作業で確実に並列ト
ンネル間に水平支持鋼材の端部を密着して設置すること
が可能となると共に、並列トンネル間の掘削量も少なく
工期、工費を削減することが可能となる。
[Advantages of the Invention] As described above, according to the present invention, the upper portion between the parallel tunnels is excavated, and a pair of left and right horizontal supporting steel members are fastened to the top end of the face and one end portion of the joint steel member is fastened with bolts. At the same time, the other end is temporarily fastened to the tip end of the other horizontal supporting steel member by a bolt so as to be slidable in the axial direction, and the reaction force receiving member provided on the rear end part of the joint steel member and the other horizontal supporting steel member behind the joint steel member is received. With the jack installed in between, the other horizontal supporting steel material is slid, and the rear end portions of the left and right horizontal supporting steel materials are adhered to and supported by the outer peripheral surfaces of the left and right parallel tunnels. The horizontal supporting steel materials are fastened with bolts, the lower side of the horizontal supporting steel materials is supported by a supporting member, and the horizontal supporting steel materials are similarly installed between the parallel tunnels while excavating sequentially, so Depending on the construction error, a pair of left and right horizontal supporting steel materials can be easily slide-adjusted by jacking through the joint steel material, and even in a narrow work space, cutting and welding operations are not required and reliable with extremely simple work. In addition, it is possible to install the end portions of the horizontal supporting steel material in close contact with each other between the parallel tunnels, and it is possible to reduce the amount of excavation between the parallel tunnels and reduce the construction period and cost.

【図面の簡単な説明】[Brief description of drawings]

第1図はこの発明工法の一連の工程を示す縦断正面図、
第2図はこの発明に用いる切梁の連結状態を示す側面
図、第3図は第2図のA−A断面図、第4図は第2図の
B−B断面図、第5図はこの発明に用いる水平支持鋼材
の先端部の側面図、第6図は同継手鋼材の側面図、第7
図は同座金プレートの側面図、第8図(a)〜(j)は
この発明における切拡げ工程を示す縦断正面図である。 1,1′……並列トンネル、2……サイド部、3……防護
用仮設物、4,4′……水平支持鋼材、8……継手鋼材、
9……ボルト穴、 10……ボルト挿通用長孔、12……ボルト穴 13……座金プレート、14……高張力ボルト 15……ジャッキ、16……ストッパー、 17……仮柱(保持部材)、18……方杖(保持部材)。
FIG. 1 is a vertical sectional front view showing a series of steps of the invention method,
FIG. 2 is a side view showing the connection state of the beams used in the present invention, FIG. 3 is a sectional view taken along the line AA of FIG. 2, FIG. 4 is a sectional view taken along the line BB of FIG. 2, and FIG. A side view of the tip portion of the horizontal supporting steel material used in the present invention, FIG. 6 is a side view of the joint steel material, and FIG.
FIG. 8 is a side view of the washer plate, and FIGS. 8 (a) to 8 (j) are vertical sectional front views showing a cutting and expanding process in the present invention. 1,1 '... Parallel tunnel, 2 ... Side part, 3 ... Temporary structure for protection, 4,4' ... Horizontal support steel, 8 ... Joint steel,
9 …… Bolt hole, 10 …… Bolt insertion long hole, 12 …… Bolt hole 13 …… Washer plate, 14 …… High tension bolt 15 …… Jack, 16 …… Stopper, 17 …… Temporary column (holding member ), 18 ... Stand (holding member).

フロントページの続き (56)参考文献 特開 昭49−103446(JP,A) 特開 昭53−83324(JP,A) 特開 昭53−95230(JP,A)Continuation of the front page (56) References JP-A-49-103446 (JP, A) JP-A-53-83324 (JP, A) JP-A-53-95230 (JP, A)

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】並列トンネル間の上部を掘削してその切羽
天端に左右一対の水平支持鋼材を一方の先端部に継手鋼
材の一端をボルトにより締結すると共に、他端を前記他
方の水平支持鋼材の先端部に軸方向にスライド可能にボ
ルトにより仮締めし、前記継手鋼材の後端部とその後方
における前記他方の水平支持鋼材に設けた反力受間に設
置したジャッキにより、他方の水平支持鋼材をスライド
させ、前記左右の水平支持鋼材の後端部を左右の並列ト
ンネル外周面に密着して支持させた状態において、前記
継手鋼材と前記他方の水平支持鋼材をボルトにより締結
し、前記水平支持鋼材の下方を支保部材により支持し、
順次掘削しながら同様に前記水平支持鋼材を並列トンネ
ル間に設置することを特徴とする並列トンネル間の切拡
げ工法。
1. An excavation of an upper part between parallel tunnels, and a pair of left and right horizontal supporting steel materials are fastened to the top end of the face, one end of a joint steel material is fastened to one end portion by a bolt, and the other end is horizontally supported to the other. The bolt is temporarily fastened to the tip of the steel material so as to be slidable in the axial direction by a bolt, and a jack installed between the rear end portion of the joint steel material and the reaction force receiver provided on the other horizontal supporting steel material behind the joint steel material causes the other horizontal In a state where the supporting steel materials are slid and the rear end portions of the left and right horizontal supporting steel materials are closely adhered to and supported by the outer peripheral surfaces of the left and right parallel tunnels, the joint steel material and the other horizontal supporting steel material are fastened with bolts, Support the lower part of the horizontal support steel with a support member,
A method for cutting and expanding between parallel tunnels, characterized in that the horizontal supporting steel materials are similarly installed between parallel tunnels while sequentially excavating.
【請求項2】先端部の側面にボルト穴を設けた水平支持
鋼材と、先端部の側面に軸方向に沿ってボルト挿通用長
孔を設け、かつ先端部後方にジャッキ反力受を設けた水
平支持鋼材と、前記各水平支持鋼材の先端部間に当てが
ってボルトにより締結可能な継手鋼材と、前記各水平支
持鋼材の先端間に嵌合可能なストッパーと、前記水平支
持鋼材を下方から支持可能な支保部材とからなることを
特徴とする並列トンネル間の切拡げ工法に用いる支保装
置。
2. A horizontal supporting steel material having a bolt hole on the side surface of the tip portion, a long hole for inserting a bolt along the axial direction on the side surface of the tip portion, and a jack reaction force receiving member provided on the rear side of the tip portion. Horizontal support steel, a joint steel that can be fastened between the tip ends of the horizontal support steels by bolts, a stopper that can be fitted between the tips of the horizontal support steels, and the horizontal support steels downward A support device for use in a method of cutting and expanding between parallel tunnels, the support device comprising:
JP1043795A 1989-02-23 1989-02-23 Method for cutting and expanding between parallel tunnels and supporting device used therefor Expired - Fee Related JP2566162B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1043795A JP2566162B2 (en) 1989-02-23 1989-02-23 Method for cutting and expanding between parallel tunnels and supporting device used therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1043795A JP2566162B2 (en) 1989-02-23 1989-02-23 Method for cutting and expanding between parallel tunnels and supporting device used therefor

Publications (2)

Publication Number Publication Date
JPH02221588A JPH02221588A (en) 1990-09-04
JP2566162B2 true JP2566162B2 (en) 1996-12-25

Family

ID=12673681

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1043795A Expired - Fee Related JP2566162B2 (en) 1989-02-23 1989-02-23 Method for cutting and expanding between parallel tunnels and supporting device used therefor

Country Status (1)

Country Link
JP (1) JP2566162B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2746807B2 (en) * 1993-02-12 1998-05-06 戸田建設株式会社 segment
JP4534069B2 (en) * 2005-07-08 2010-09-01 大成建設株式会社 Parallel tunnel joining method
CN106703814B (en) * 2015-07-30 2019-07-12 宏润建设集团股份有限公司 Tunneling subway station hole pile construction method

Also Published As

Publication number Publication date
JPH02221588A (en) 1990-09-04

Similar Documents

Publication Publication Date Title
JP3211673B2 (en) Simple temporary bridge temporary pier construction method
JP3680294B2 (en) Mountain retaining method using braided piles consisting of diagonal piles
JP2016528406A (en) Beam connection structure of temporary retaining works for earth retaining
JPH1150457A (en) Earth retaining construction used for earth anchor
JP2566162B2 (en) Method for cutting and expanding between parallel tunnels and supporting device used therefor
JP3850785B2 (en) Caisson laying method using main foundation pile
KR200387344Y1 (en) Establishment structure of strut for retaining walls
JPH11310928A (en) Vibration isolation reinforcing method for existing structure
JPH05179647A (en) Supporting structure for earth retaining wall
KR940011420B1 (en) Tunnel timbering method
JP2979117B2 (en) Building foundation method
JPS62202121A (en) Jack-up method for shore strut
JP3116098B2 (en) Construction method for underground structures
JP2816827B2 (en) Loading fulcrum method on pile side body of precast concrete pile
JP2757209B2 (en) Cut-and-joint underground construction method using synthetic steel beams
JP2523234B2 (en) Anchor retaining wall
JPS6012494B2 (en) Stray beam jack-up method
JP2894217B2 (en) Building structural frame
JPH0813494A (en) Fixing method of earth retaining wall and timbering
JP4889993B2 (en) Construction method of widening shaft
JPH0443549Y2 (en)
JPH08302689A (en) Construction method for skeleton of underground exterior wall
KR20060089271A (en) Establishment structure of strut for retaining walls
JP2005201009A (en) Earth retaining wall structure
JP2618796B2 (en) How to build a wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081003

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees