JPH10292406A - Connecting method for underwater structure and shield tunnel - Google Patents
Connecting method for underwater structure and shield tunnelInfo
- Publication number
- JPH10292406A JPH10292406A JP9094027A JP9402797A JPH10292406A JP H10292406 A JPH10292406 A JP H10292406A JP 9094027 A JP9094027 A JP 9094027A JP 9402797 A JP9402797 A JP 9402797A JP H10292406 A JPH10292406 A JP H10292406A
- Authority
- JP
- Japan
- Prior art keywords
- shield tunnel
- underwater structure
- water
- lower pipe
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、例えば火力発電所
の取水ポンプ場や排水ポンプ場などに適用するのに好適
な水中構造物とシールドトンネルとの連結工法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of connecting an underwater structure and a shield tunnel suitable for application to, for example, an intake pump station or a drain pump station of a thermal power plant.
【0002】[0002]
【従来の技術】例えば海岸沿いに建設される火力発電所
においては、取水ポンプ又は排水ポンプから海底に向け
て通水用のシールドトンネルを掘削し、このシールドト
ンネルの先端にフィルタ施設を連結して、海中のゴミな
どがポンプに入らないようにしているのが普通である。2. Description of the Related Art For example, in a thermal power plant constructed along the coast, a shield tunnel for water flow is excavated from an intake pump or a drain pump toward the sea floor, and a filter facility is connected to a tip of the shield tunnel. It is common practice to prevent underwater debris from entering the pump.
【0003】従来、通水用のシールドトンネルとフィル
タ施設とを連結する場合、まず海中の所定の位置にフィ
ルタ施設を建設する。次に、取水ポンプ又は排水ポンプ
からフィルタ施設に達するまでシールドトンネルを掘削
する。そして、フィルタ施設の内側から外壁に貫通孔を
あけて、シールドトンネルと連結するのが一般的であっ
た。Conventionally, when connecting a shield tunnel for water flow and a filter facility, the filter facility is first constructed at a predetermined position in the sea. Next, a shield tunnel is excavated from the intake pump or the drain pump until the filter facility is reached. Then, it is common to form a through hole in the outer wall from the inside of the filter facility and connect it to the shield tunnel.
【0004】[0004]
【発明が解決しようとする課題】しかし、従来のフィル
タ施設とシールドトンネルとの連結工法では、フィルタ
施設の内側で外壁の孔あけ作業をするために、フィルタ
施設の上端を海面上まで延ばすことによりフィルタ施設
の内側に海水が侵入するのを防止するようにしていたの
で、フィルタ施設として本来必要な部分の上に、海面上
まで延びる部分を余計に設けることになり、コストアッ
プになるという問題があった。However, in the conventional connection method between a filter facility and a shield tunnel, the upper end of the filter facility is extended to the surface of the sea in order to drill holes in an outer wall inside the filter facility. Since seawater was prevented from entering the inside of the filter facility, an additional part extending to the sea surface was additionally provided on the part originally required for the filter facility, resulting in a problem of increased cost. there were.
【0005】また、フィルタ施設の内側から外壁に貫通
孔をあけるとき、フィルタ施設とシールドトンネルとの
結合部分から浸水したり土砂が流入したりするのを防ぐ
ため、フィルタ施設周辺の地盤の改良或いは凍結などの
補助工法が必要であり、これも工期及び工費の増大を招
く原因になっていた。In addition, when a through hole is formed in the outer wall from the inside of the filter facility, the ground around the filter facility is improved or prevented in order to prevent inundation or inflow of sediment from the joint between the filter facility and the shield tunnel. Auxiliary construction methods such as freezing were required, which also caused an increase in construction period and construction cost.
【0006】更に、フィルタ施設の施工は洋上で行われ
るので、締め切り工法、築島によるケーソン工法、鋼殻
を用いた設置ケーソン工法などが用いられていたが、何
れの工法も大規模な仮設工事が必要になり、工期及び工
費の面で不利になるという問題があった。Further, since the construction of the filter facility is performed offshore, a deadline method, a caisson method using Tsukishima, an installation caisson method using a steel shell, and the like have been used. However, there is a problem that it is necessary and disadvantageous in terms of construction period and construction cost.
【0007】このような問題は、フィルタ施設とシール
ドトンネルとを連結する場合に限らず、各種の水中構造
物とシールドトンネルとを連結する場合に同様に発生す
る。本発明の目的は、このような問題点を解決すること
にあり、水中構造物のコストダウンが可能で、しかも工
期及び工費を低減することが可能な水中構造物とシール
ドトンネルとの連結工法を提供することにある。[0007] Such a problem occurs not only when the filter facility and the shield tunnel are connected but also when various underwater structures and the shield tunnel are connected. SUMMARY OF THE INVENTION An object of the present invention is to solve such a problem, and to provide a method of connecting an underwater structure and a shield tunnel capable of reducing the cost of the underwater structure and reducing the construction period and cost. To provide.
【0008】[0008]
【課題を解決するための手段】本発明は水中構造物とシ
ールドトンネルとの連結工法であり、前述の技術的課題
を解決するために以下のように構成されている。すなわ
ち、本発明は、水底の地中に設けられたシールドトンネ
ル上の土砂を除去し、前記シールドトンネルの所定の位
置に型枠を設置し、前記シールドトンネルに連結すべき
水中構造物に浸水防止手段を施して、前記水中構造物を
前記型枠内の前記シールドトンネルに取り付け、前記型
枠内に止水性を有するコンクリートを打設して前記シー
ルドトンネルと前記水中構造物とを結合し、前記水中構
造物と前記シールドトンネルとの間の隔壁に、前記シー
ルドトンネルの内側から貫通孔をあけることにより、前
記水中構造物と前記シールドトンネルとを連結すること
を特徴とする。SUMMARY OF THE INVENTION The present invention relates to a method for connecting an underwater structure and a shield tunnel, and is configured as follows to solve the above-mentioned technical problem. That is, the present invention removes earth and sand on a shield tunnel provided in the ground at the bottom of the water, installs a formwork at a predetermined position of the shield tunnel, and prevents inundation in an underwater structure to be connected to the shield tunnel. Applying means, attaching the underwater structure to the shield tunnel in the formwork, casting concrete having water stoppage in the formwork to join the shield tunnel and the underwater structure, The underwater structure and the shield tunnel are connected by forming a through hole in the partition wall between the underwater structure and the shield tunnel from inside the shield tunnel.
【0009】本発明の水中構造物とシールドトンネルと
の連結工法は、浸水防止手段によって内部空間が保持さ
れた水中構造物とシールドトンネルとを止水性を有する
コンクリートで結合した後、シールドトンネルと水中構
造物との間の隔壁にシールドトンネルの内側から貫通孔
をあけるので、孔あけ作業をしている最中にシールドト
ンネル内に浸水したり土砂が流入したりするのを防止で
きる。In the method for connecting an underwater structure and a shield tunnel according to the present invention, the underwater structure whose internal space is maintained and the shield tunnel are connected to each other by a waterproof concrete, and then the shield tunnel and the underwater structure are connected. Since a through hole is formed in the partition between the structure and the inside of the shield tunnel from inside the shield tunnel, it is possible to prevent flooding and inflow of earth and sand into the shield tunnel during drilling work.
【0010】前記シールドトンネルは火力発電所の取水
ポンプ又は排水ポンプに接続された通水用シールドトン
ネルとし、前記水中構造物は前記通水用シールドトンネ
ルの先端に設けられたフィルタ施設とすることができ
る。The shield tunnel may be a shield tunnel for water passage connected to an intake pump or a drain pump of a thermal power plant, and the underwater structure may be a filter facility provided at a tip of the shield tunnel for water passage. it can.
【0011】[0011]
【発明の実施の形態】以下、本発明に係る水中構造物と
シールドトンネルとの連結工法の実施の形態について、
図面を参照して詳細に説明する。BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, an embodiment of a method for connecting an underwater structure and a shield tunnel according to the present invention will be described.
This will be described in detail with reference to the drawings.
【0012】図1〜図14は、本発明に係る水中構造物
とシールドトンネルとの連結工法を、例えば海岸沿いに
ある火力発電所の取水ポンプ場に適用した場合の作業手
順を説明する図である。この連結工法では、まず、図1
に示すように海底11の地中に火力発電所の取水ポンプ
(図示せず)から延びる通水用のシールドトンネル12
を形成する。FIG. 1 to FIG. 14 are diagrams for explaining a work procedure when the method of connecting an underwater structure and a shield tunnel according to the present invention is applied to, for example, an intake pump station of a thermal power plant along a coast. is there. In this connection method, first,
As shown in the figure, a shield tunnel 12 for flowing water extending from an intake pump (not shown) of a thermal power plant underground on the seabed 11.
To form
【0013】次に、シールドトンネル12上の所定の範
囲の土砂13、すなわち、後述のフィルタ施設14(図
10)を設置しようとする場所を含めた適宜な範囲Wの
土砂13を、例えばグラブ浚渫船15などを使用して浚
渫することにより除去する。Next, a predetermined range of earth and sand 13 on the shield tunnel 12, that is, an appropriate range W including a place where a filter facility 14 (FIG. 10) to be described later is to be installed is put into, for example, a grab dredger. Remove by dredging using 15 or the like.
【0014】次に、図2に示すようにシールドトンネル
12のセグメント表面を仕上げて平滑にした後、シール
ドトンネル12の所定の位置にフィルタ施設14を取り
付けるためのブラケット17を固定する。次に、シール
ドトンネル12の両側の地表面にコンクリートで台座1
8を設置する。なお、図中の符号19はコンクリートミ
キサー船、20は潜水士船である。Next, as shown in FIG. 2, after the segment surface of the shield tunnel 12 is finished and smoothed, a bracket 17 for attaching the filter facility 14 to a predetermined position of the shield tunnel 12 is fixed. Next, the pedestal 1 is made of concrete on the ground surface on both sides of the shield tunnel 12.
8 is installed. In addition, the code | symbol 19 in a figure is a concrete mixer ship, 20 is a diver's ship.
【0015】次に、図3に示すようにシールドトンネル
12とブラケット17上に、フィルタ施設14の下部配
管21と、下部配管21の側面に設けた取付具22とを
それぞれ載置する。このとき、下部配管21は、下端面
を開放すると共に上端面をバルクヘッド23で封止す
る。なお、図3中の24は吊り具、25は起重機船であ
る。また、下部配管21とシールドトンネル12のセグ
メント12aとの間には、図4に示すようにパッキン2
1aが配置されている。これによって、下部配管21の
内部に浸水するのを防止できる。Next, as shown in FIG. 3, the lower pipe 21 of the filter facility 14 and the fixture 22 provided on the side of the lower pipe 21 are placed on the shield tunnel 12 and the bracket 17 respectively. At this time, the lower pipe 21 has a lower end face opened and an upper end face sealed with the bulkhead 23. In addition, 24 in FIG. 3 is a hanging tool, 25 is a hoist ship. As shown in FIG. 4, a packing 2 is provided between the lower pipe 21 and the segment 12a of the shield tunnel 12.
1a is arranged. This can prevent the inside of the lower pipe 21 from being flooded.
【0016】次に、図5に示すように潜水士船20の真
空発生手段(図示せず)を用いて下部配管21内の空気
を抜いて減圧する。そうすると、海水の圧力が下部配管
21の外表面にかかり、この水圧によって下部配管21
がシールドトンネル12に押し付けられて密着される。
この状態で取付具22をブラケット17にボルトで固定
する。続いて、下部配管21内に圧力空気を送り、下部
配管21とシールドトンネル12との密着部の止水性能
確認試験を行う。Next, as shown in FIG. 5, the air in the lower pipe 21 is evacuated using the vacuum generating means (not shown) of the diver's ship 20, and the pressure is reduced. Then, seawater pressure is applied to the outer surface of the lower pipe 21, and this water pressure causes the lower pipe 21.
Is pressed against and adhered to the shield tunnel 12.
In this state, the fixture 22 is fixed to the bracket 17 with bolts. Subsequently, pressurized air is sent into the lower pipe 21 to perform a test for confirming the water stopping performance of the contact portion between the lower pipe 21 and the shield tunnel 12.
【0017】続いて、図6に示すように台座18上に型
枠、本実施の形態ではRC型枠26を載置して固定す
る。このRC型枠26は内筒と、この内筒より高さの低
い外筒とが同心状に配置されており、内筒によって下部
配管21の周囲が囲まれる。RC型枠26は台座18よ
り上側に配置されるので、台座18の側方には隙間があ
いている。なお、図中の符号27は吊り具である。Subsequently, as shown in FIG. 6, a formwork, in this embodiment, an RC formwork 26, is placed and fixed on the pedestal 18. In the RC frame 26, an inner cylinder and an outer cylinder having a height lower than the inner cylinder are concentrically arranged, and the inner pipe surrounds the lower pipe 21. Since the RC form 26 is disposed above the pedestal 18, there is a gap on the side of the pedestal 18. Reference numeral 27 in the figure is a hanging tool.
【0018】次に、図7に示すようにRC型枠26内の
下部配管21上に、フィルタ施設14の上部配管28を
配置する。上部配管28の上端面は蓋29で密閉されて
いる。また、下部配管21のバルクヘッド23は取り外
される。なお、図中の符号30は、上部配管28を運搬
する台船である。次に、図8に示すようにRC型枠26
内に所定量の水中コンクリートを打設し、この水中コン
クリートを台座18の周囲に広げて、RC型枠26の下
側にベース31を形成する。Next, as shown in FIG. 7, the upper pipe 28 of the filter facility 14 is arranged on the lower pipe 21 in the RC form 26. The upper end surface of the upper pipe 28 is closed with a lid 29. In addition, the bulkhead 23 of the lower pipe 21 is removed. Reference numeral 30 in the figure denotes a barge that transports the upper pipe 28. Next, as shown in FIG.
A predetermined amount of underwater concrete is poured into the inside, and the underwater concrete is spread around the pedestal 18 to form a base 31 below the RC formwork 26.
【0019】ベース31が硬化したあと、図9に示すよ
うにRC型枠26の内筒及び外筒の内側に水中コンクリ
ート32を打設して充満させる。この水中コンクリート
32は、構造部材としての特性と止水性とを有してい
る。そして、RC型枠26の内筒に打設された水中コン
クリート32によって、シールドトンネル12、下部配
管21及び上部配管28が結合される。After the base 31 has hardened, underwater concrete 32 is poured and filled inside the inner and outer cylinders of the RC formwork 26 as shown in FIG. The underwater concrete 32 has characteristics as a structural member and water-stopping property. Then, the shield tunnel 12, the lower pipe 21, and the upper pipe 28 are connected by the underwater concrete 32 cast in the inner cylinder of the RC formwork 26.
【0020】次に、図10に示すようにRC型枠26の
外側の水中コンクリート32上に、所定の高さのサイド
ポール33を複数本立設する。そして、このサイドポー
ル33上にフィルタ施設14のフィルタ部34を取り付
けて上部配管28に連結する。このとき、フィルタ部3
4の取水口(図示せず)を浸水防止手段であるバルクヘ
ッド35で閉塞すると共に、上部配管28の蓋29を取
り外す。図中の符号36は吊り具である。Next, as shown in FIG. 10, a plurality of side poles 33 having a predetermined height are erected on the underwater concrete 32 outside the RC formwork 26. Then, the filter section 34 of the filter facility 14 is mounted on the side pole 33 and connected to the upper pipe 28. At this time, the filter unit 3
The intake port (not shown) of No. 4 is closed by a bulkhead 35 which is a flood prevention means, and the lid 29 of the upper pipe 28 is removed. Reference numeral 36 in the figure is a hanging tool.
【0021】次に、図11に示すようにRC型枠26の
周囲に土砂37を元通りに埋め戻す。これによって、シ
ールドトンネル12、下部配管21及び上部配管28の
殆どが土砂37内に埋設されると共に、フィルタ部34
が土砂37上に突出する。これによって、フィルタ部3
4を介して海水を取水することが可能になる。図中の符
号38は土砂運搬船である。Next, as shown in FIG. 11, earth and sand 37 are buried back around the RC formwork 26. Thereby, most of the shield tunnel 12, the lower pipe 21, and the upper pipe 28 are buried in the earth and sand 37, and the filter section 34 is formed.
Project above the earth and sand 37. Thereby, the filter unit 3
4, it becomes possible to take in seawater. Reference numeral 38 in the figure denotes a sediment transport ship.
【0022】続いて、図12に示すようにシールドトン
ネル12の上部側の外壁に、比較的短い排水配管40及
び空気配管41を差し込んで下部配管21内に貫通させ
る。これによって、下部配管21及び上部配管28内に
貯まっていた海水が、排水配管40を通してシールドト
ンネル12内に流出する。次に、このシールドトンネル
12内に流れ込んだ海水を排水した後、シールドトンネ
ル12内に圧力空気を供給して漏水試験を行う。Subsequently, as shown in FIG. 12, a relatively short drain pipe 40 and air pipe 41 are inserted into the outer wall on the upper side of the shield tunnel 12 and penetrate into the lower pipe 21. Thus, the seawater stored in the lower pipe 21 and the upper pipe 28 flows out into the shield tunnel 12 through the drain pipe 40. Next, after the seawater flowing into the shield tunnel 12 is drained, pressurized air is supplied into the shield tunnel 12 to perform a water leakage test.
【0023】次に、図13に示すようにシールドトンネ
ル12の内側からシールドトンネル12とフィルタ施設
14との間の隔壁、本実施の形態ではシールドトンネル
12の外壁の上側に、下部配管21の内側に貫通する貫
通孔38をあける。これによって、シールドトンネル1
2とフィルタ施設14とが連結される。Next, as shown in FIG. 13, a partition wall between the shield tunnel 12 and the filter facility 14 from the inside of the shield tunnel 12, in this embodiment, above the outer wall of the shield tunnel 12, and inside the lower pipe 21. Then, a through hole 38 penetrating through is formed. Thereby, shield tunnel 1
2 and the filter facility 14 are connected.
【0024】この後、フィルタ施設14のバルクヘッド
35を取り外してフィルタ部34の取水口を開けること
により、取水ポンプで海水をフィルタ部34を介して取
水することが可能になる。このフィルタ部34によっ
て、取水時に海水中のゴミなどが取水ポンプに吸い込ま
れるのを防止できる。なお、取り外したバルクヘッド3
5は、取水ポンプなどのメンテナンスをするために、シ
ールドトンネル12、フィルタ施設14の下部配管21
及び上部配管28内の海水を排水するときに使用され
る。Thereafter, by removing the bulkhead 35 of the filter facility 14 and opening the water intake of the filter part 34, it becomes possible to take in seawater through the filter part 34 with the water intake pump. The filter unit 34 can prevent dust and the like in seawater from being sucked into the water intake pump at the time of water intake. The removed bulkhead 3
5 is a lower pipe 21 of a shield tunnel 12 and a filter facility 14 for maintenance of an intake pump and the like.
And when the seawater in the upper pipe 28 is drained.
【0025】上述のように、この水中構造物とシールド
トンネルとの連結工法は、バルクヘッド35によって内
部空間が保持されたフィルタ施設14とシールドトンネ
ル12とを、止水性を有する水中コンクリート32で結
合するので、シールドトンネル12とフィルタ施設14
との間の隔壁、すなわち、シールドトンネル12の外壁
に、シールドトンネル12の内側から貫通孔38をあけ
るときに、シールドトンネル12とフィルタ施設14と
の結合部分から浸水したり土砂が流入したりするのを防
止できる。As described above, in this method of connecting the underwater structure and the shield tunnel, the filter facility 14 whose internal space is held by the bulkhead 35 and the shield tunnel 12 are connected with the underwater concrete 32 having water blocking properties. The shield tunnel 12 and the filter facility 14
When a through-hole 38 is made from the inside of the shield tunnel 12 to the partition wall between the shield tunnel 12 and the outer wall of the shield tunnel 12, water or earth and sand flows in from the joint between the shield tunnel 12 and the filter facility 14. Can be prevented.
【0026】したがって、従来のようにフィルタ施設1
4を海面上に突出させて内部空間を保持する必要がない
から、フィルタ施設14は本来の機能を達成するために
必要な部分だけで構成することができ、それ以外に余計
な部分を設ける必要がなくなるためコスト低減が可能に
なる。また、フィルタ施設14を施工するために、従来
のように地盤の改良や凍結などの補助工法を行う必要が
ないので、工期及び工費を低減できる。Therefore, as in the prior art, the filter facility 1
Since there is no need to protrude above the sea surface to maintain the internal space, the filter facility 14 can be composed of only the parts necessary to achieve the original function, and it is necessary to provide extra parts other than that. Is eliminated, thereby enabling cost reduction. In addition, since the construction of the filter facility 14 does not require an auxiliary construction method such as ground improvement or freezing as in the related art, the construction period and construction cost can be reduced.
【0027】更に、フィルタ施設14の施工は、シール
ドトンネル12の上に下部配管21、上部配管28及び
フィルタ部34を順次載置して固定するだけであるか
ら、従来のように締め切り工法、築島によるケーソン工
法又は鋼殻を用いた設置ケーソン工法などによって施工
する場合に比べて仮設工事を小規模にすることができ
る。したがって、フィルタ施設14の工期及び工費を低
減することができる。Further, the construction of the filter facility 14 simply involves placing and fixing the lower pipe 21, the upper pipe 28 and the filter section 34 on the shield tunnel 12 in this order. The temporary construction can be made smaller than when the construction is performed by the caisson method or the caisson method using a steel shell. Therefore, the construction period and construction cost of the filter facility 14 can be reduced.
【0028】なお、上述の実施の形態では図4に示した
ように、シールドトンネル12のセグメント12aと下
部配管21との間にパッキン21aを配置して漏水防止
を行った場合について説明したが、図14に示すように
パッキン21aに代えてセグメント12aと下部配管2
1との間に全周に亘ってゴムチューブ45を配置し、こ
のゴムチューブ45にシールドトンネル12の内部から
注水して膨張させることにより、シールドトンネル12
と下部配管21との間を密閉することが可能である。In the above embodiment, as shown in FIG. 4, the case where the packing 21a is disposed between the segment 12a of the shield tunnel 12 and the lower pipe 21 to prevent water leakage has been described. As shown in FIG. 14, instead of the packing 21a, the segment 12a and the lower pipe 2
A rubber tube 45 is disposed around the entire circumference of the shield tunnel 12, and water is injected into the rubber tube 45 from inside the shield tunnel 12 to expand the rubber tube 45.
And the lower pipe 21 can be sealed.
【0029】このようにゴムチューブ45を使用する場
合の施工手順は、次に説明するようにパッキン21aを
使用した場合とは異なっている。すなわち、この場合
は、まず下部配管21をシールドトンネル12に取り付
ける前にゴムチューブ45を取り付ける。このときに
は、ゴムチューブ45に注入口46を設けておき、この
注入口46を下部配管21の注入口取付部(図示せず)
に固定する。The construction procedure when the rubber tube 45 is used is different from that when the packing 21a is used as described below. That is, in this case, first, before attaching the lower pipe 21 to the shield tunnel 12, the rubber tube 45 is attached. At this time, an injection port 46 is provided in the rubber tube 45, and the injection port 46 is connected to an injection port mounting portion (not shown) of the lower pipe 21.
Fixed to
【0030】また、ゴムチューブ45への注水作業をシ
ールドトンネル12の内側から行うようにするため、ゴ
ムチューブ45の注入口46に繋がるパイプ(或いは銅
チューブ)47を一旦下部配管21の外側に出し、適宜
な位置で再度下部配管21内に戻す。下部配管21内に
おいては、適宜な長さの銅チューブ48をパイプ47に
接続する。また、銅チューブ48の途中にはバルブ49
を接続する。In order to perform the work of injecting water into the rubber tube 45 from the inside of the shield tunnel 12, a pipe (or copper tube) 47 connected to the injection port 46 of the rubber tube 45 is once taken out of the lower pipe 21. Then, it is returned to the lower pipe 21 again at an appropriate position. In the lower pipe 21, a copper tube 48 of an appropriate length is connected to the pipe 47. In the middle of the copper tube 48, a valve 49 is provided.
Connect.
【0031】次に、ゴムチューブ45を取り付けた下部
配管21をシールドトンネル12の所定の位置に載置
し、下部配管21の取付具22をシールドトンネル12
のブラケット17にボルト及びナットで固定する。Next, the lower pipe 21 to which the rubber tube 45 is attached is placed at a predetermined position in the shield tunnel 12, and the fixture 22 of the lower pipe 21 is attached to the shield tunnel 12.
To the bracket 17 with bolts and nuts.
【0032】次に、下部配管21に取り付けられている
銅チューブ48の先端を、セグメント12aの注入孔5
0に例えばワンタッチ継手51などによって接続する。
また、下部配管21の下端縁には予め伸び縮み自在なス
カート部材52を取り付けておき、下部配管21をセグ
メント12aに取り付けた後、このスカート部材52を
伸ばしてセグメント12aにボルトで固定する。これら
の接続作業は、潜水士によって行う。なお、これらの作
業の邪魔にならないように取付具22の取付位置が設定
される。Next, the tip of the copper tube 48 attached to the lower pipe 21 is connected to the injection hole 5 of the segment 12a.
0, for example, by a one-touch joint 51 or the like.
Further, a skirt member 52 which can be stretched and contracted is attached to the lower end edge of the lower pipe 21 in advance, and after attaching the lower pipe 21 to the segment 12a, the skirt member 52 is extended and fixed to the segment 12a with bolts. These connections are performed by divers. The attachment position of the attachment 22 is set so as not to hinder these operations.
【0033】このようにして下部配管21を取り付けた
後、上述のパッキン21aを用いた場合と同様に、RC
型枠26の取付(図6)、下部配管21上へのフィルタ
施設14の上部配管28の取付(図7)を行う。After the lower pipe 21 is attached in this manner, the RC pipe is mounted in the same manner as in the case where the packing 21a is used.
Attach the mold 26 (FIG. 6) and attach the upper pipe 28 of the filter facility 14 to the lower pipe 21 (FIG. 7).
【0034】この後、上述のパッキン21aを使用した
場合と同様に、ベース31の形成(図8)、RC型枠2
6の内筒及び外筒の内側への水中コンクリート32の打
設(図9)、サイドポール33の立設及びフィルタ部3
4の取付(図10)、土砂37の埋め戻し(図11)を
行う。Thereafter, as in the case where the packing 21a is used, the formation of the base 31 (FIG. 8) and the RC form 2
6, placing the underwater concrete 32 inside the inner cylinder and the outer cylinder (FIG. 9), erecting the side pole 33, and setting the filter portion 3
4 (FIG. 10) and backfilling of the soil 37 (FIG. 11).
【0035】次に、図14に示すようにシールドトンネ
ル12の内側から銅チューブ48、バルブ49及びパイ
プ47を介してゴムチューブ45に所定の圧力で注水す
る。そうすると、ゴムチューブ45が水圧によって膨張
し、シールドトンネル12のセグメント12aと下部配
管21との間の隙間が密封される。Next, as shown in FIG. 14, water is injected from the inside of the shield tunnel 12 into the rubber tube 45 through the copper tube 48, the valve 49 and the pipe 47 at a predetermined pressure. Then, the rubber tube 45 expands due to the water pressure, and the gap between the segment 12a of the shield tunnel 12 and the lower pipe 21 is sealed.
【0036】次に、下部配管21、上部配管28及びシ
ールドトンネル12の排水を行い、この後漏水試験(図
12)を行う。このとき、漏水があった場合は、ゴムチ
ューブ45内に更に高圧水を注水して漏水試験を行う。
そして、漏水がないことを確認したら、シールドトンネ
ル12のセグメント12aを解体して貫通孔38(図1
3)を形成する。この場合には、ゴムチューブ45(図
14)内の水が逆流しないように、銅チューブ48のバ
ルブ49を閉じておく。貫通孔38の形成後、ゴムチュ
ーブ45内にモルタルを注入して水と置き換える。ま
た、セグメント12aとゴムチューブ45及び下部配管
21で囲まれた空間に、セグメント12aの注入孔53
からモルタルを注入する。Next, the lower pipe 21, the upper pipe 28, and the shield tunnel 12 are drained, and then a water leakage test (FIG. 12) is performed. At this time, if there is water leakage, high-pressure water is further injected into the rubber tube 45 to perform a water leakage test.
When it is confirmed that there is no water leakage, the segment 12a of the shield tunnel 12 is dismantled and the through hole 38 (FIG.
Form 3). In this case, the valve 49 of the copper tube 48 is closed so that the water in the rubber tube 45 (FIG. 14) does not flow backward. After the formation of the through holes 38, mortar is injected into the rubber tube 45 and replaced with water. In addition, in the space surrounded by the segment 12a, the rubber tube 45, and the lower pipe 21, the injection hole 53 of the segment 12a is provided.
Inject mortar from.
【0037】このように、ゴムチューブ45を用いた場
合は、シールドトンネル12と下部配管21との位置関
係が多少ずれていても、このずれをゴムチューブ45の
膨張によって吸収することができるので、下部配管21
の取付作業が容易になると共に漏水を確実に防止するこ
とができる。As described above, when the rubber tube 45 is used, even if the positional relationship between the shield tunnel 12 and the lower pipe 21 is slightly shifted, the shift can be absorbed by the expansion of the rubber tube 45. Lower piping 21
Can be easily attached and water leakage can be reliably prevented.
【0038】また、上述の実施の形態ではシールドトン
ネル12とフィルタ施設14とを結合するため、RC型
枠26を使用した場合について説明したが、これに代え
て鋼製の型枠を使用することができる。更に、上述の実
施の形態では、本発明を取水ポンプ場に適用した場合に
ついて説明したが、本発明はこれに限らず、排水ポンプ
場など各種のポンプ場に適用することができる。In the above-described embodiment, the case where the RC formwork 26 is used to connect the shield tunnel 12 and the filter facility 14 has been described. However, a steel formwork may be used instead. Can be. Furthermore, in the above-described embodiment, the case where the present invention is applied to a water pumping station is described. However, the present invention is not limited to this, and can be applied to various pumping stations such as a drainage pumping station.
【0039】[0039]
【発明の効果】以上説明したように、本発明の水中構造
物とシールドトンネルの連結工法によれば、浸水防止手
段によって内部空間が保持された水中構造物とシールド
トンネルとを止水性を有するコンクリートで結合するの
で、シールドトンネルと水中構造物との間の隔壁にシー
ルドトンネルの内側から貫通孔をあけるときに、シール
ドトンネルと水中構造物との結合部分から浸水したり土
砂が流入したりするのを防止できる。As described above, according to the method for connecting an underwater structure and a shield tunnel according to the present invention, the underwater structure whose internal space is maintained by the inundation prevention means and the shield tunnel are made of concrete having waterproofness. When a through hole is opened from the inside of the shield tunnel to the partition wall between the shield tunnel and the underwater structure, flooding and sediment may flow in from the junction between the shield tunnel and the underwater structure. Can be prevented.
【0040】したがって、従来のように水中構造物を海
面上に突出させて内部空間を保持する必要がないから、
水中構造物は本来の機能を達成するために必要な部分だ
けで構成することができ、それ以外に余計な部分を設け
る必要がないためコスト低減が可能になる。また、水中
構造物を施工するために従来のように地盤の改良や凍結
などの補助工法を行う必要がないので、工期及び工費を
低減できる。Therefore, unlike the conventional case, it is not necessary to protrude the underwater structure above the sea surface to maintain the internal space.
The underwater structure can be composed of only the parts necessary to achieve the original function, and there is no need to provide any extra parts, so that the cost can be reduced. Further, since it is not necessary to perform an auxiliary construction method such as ground improvement or freezing as in the related art in order to construct an underwater structure, the construction period and construction cost can be reduced.
【0041】更に、水中構造部は、シールドトンネルの
所定の位置に固定するだけであるから、従来のように締
め切り工法、築島によるケーソン工法又は鋼殻を用いた
設置ケーソン工法などによって施工する場合に比べて仮
設工事を小規模にすることができる。したがって、水中
構造物の工期及び工費を低減することができる。Furthermore, since the underwater structure is merely fixed at a predetermined position in the shield tunnel, it is necessary to construct the underwater structure by a conventional method such as a deadline method, a caisson method using Tsukishima or an installation caisson method using a steel shell. In comparison, temporary construction can be made smaller. Therefore, the construction period and construction cost of the underwater structure can be reduced.
【図1】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(1/12)を説明する断面図で
ある。FIG. 1 is a cross-sectional view for explaining a work procedure (1/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図2】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(2/12)を説明する断面図で
ある。FIG. 2 is a cross-sectional view illustrating a work procedure (2/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図3】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(3/12)を説明する断面図で
ある。FIG. 3 is a cross-sectional view illustrating a work procedure (3/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図4】シールドトンネルと下部配管との間のパッキン
を示す断面図である。FIG. 4 is a cross-sectional view showing packing between a shield tunnel and a lower pipe.
【図5】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(4/12)を説明する断面図で
ある。FIG. 5 is a cross-sectional view for explaining a work procedure (4/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図6】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(5/12)を説明する断面図で
ある。FIG. 6 is a cross-sectional view illustrating a work procedure (5/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図7】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(6/12)を説明する断面図で
ある。FIG. 7 is a cross-sectional view illustrating a work procedure (6/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図8】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(7/12)を説明する断面図で
ある。FIG. 8 is a cross-sectional view illustrating a work procedure (7/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図9】本発明に係る水中構造物とシールドトンネルと
の連結工法の作業手順(8/12)を説明する断面図で
ある。FIG. 9 is a cross-sectional view for explaining the work procedure (8/12) of the method of connecting the underwater structure and the shield tunnel according to the present invention.
【図10】本発明に係る水中構造物とシールドトンネル
との連結工法の作業手順(9/12)を説明する断面図
である。FIG. 10 is a cross-sectional view for explaining the work procedure (9/12) of the method of connecting the underwater structure and the shield tunnel according to the present invention.
【図11】本発明に係る水中構造物とシールドトンネル
との連結工法の作業手順(10/12)を説明する断面
図である。FIG. 11 is a cross-sectional view illustrating a work procedure (October 12) of the method of connecting the underwater structure and the shield tunnel according to the present invention.
【図12】本発明に係る水中構造物とシールドトンネル
との連結工法の作業手順(11/12)を説明する断面
図である。FIG. 12 is a cross-sectional view for explaining an operation procedure (11/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図13】本発明に係る水中構造物とシールドトンネル
との連結工法の作業手順(12/12)を説明する断面
図である。FIG. 13 is a cross-sectional view illustrating a work procedure (12/12) of a method of connecting an underwater structure and a shield tunnel according to the present invention.
【図14】シールドトンネルと下部配管との間のゴムチ
ューブを示す図である。FIG. 14 is a diagram showing a rubber tube between a shield tunnel and a lower pipe.
11 海底 12 通水用のシールドトンネル 13 土砂 14 フィルタ施設(水中構造物) 26 RC型枠 32 水中コンクリート 38 貫通孔 11 Sea floor 12 Shield tunnel for water flow 13 Sediment 14 Filter facility (underwater structure) 26 RC formwork 32 Underwater concrete 38 Through hole
フロントページの続き (72)発明者 佐野 憲一 富山県富山市牛島町15番1号北陸電力株式 会社内 (72)発明者 大村 秀雄 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 稲津 俊昭 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 藤山 浩司 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 三輪 俊彦 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 戸畑 研二 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内Continuing on the front page (72) Kenichi Sano 15-1, Ushijima-cho, Toyama City, Toyama Prefecture Hokuriku Electric Power Company (72) Inventor Hideo Omura 2-10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Corporation (72) Inventor Toshiaki Inazu 2-10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industries Co., Ltd. (72) Inventor Toshihiko Miwa 2-10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industries Co., Ltd. (72) Inventor Kenji Tobata 2- 10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. Inside
Claims (2)
ル上の土砂を除去し、 前記シールドトンネルの所定の位置に型枠を設置し、 前記シールドトンネルに連結すべき水中構造物に浸水防
止手段を施して、前記水中構造物を前記型枠内の前記シ
ールドトンネルに取り付け、 前記型枠内に止水性を有するコンクリートを打設して前
記シールドトンネルと前記水中構造物とを結合し、 前記水中構造物と前記シールドトンネルとの間の隔壁
に、前記シールドトンネルの内側から貫通孔をあけるこ
とにより、前記水中構造物と前記シールドトンネルとを
連結することを特徴とする水中構造物とシールドトンネ
ルとの連結工法。1. A method for removing sediment on a shield tunnel provided in the ground at the bottom of a water floor, installing a formwork at a predetermined position in the shield tunnel, and preventing inundation in an underwater structure to be connected to the shield tunnel. And attaching the underwater structure to the shield tunnel in the formwork, casting concrete having water stoppage in the formwork to join the shield tunnel and the underwater structure, An underwater structure and a shield tunnel, wherein the underwater structure and the shield tunnel are connected by opening a through hole from the inside of the shield tunnel to a partition wall between the structure and the shield tunnel. Connection method.
水ポンプ又は排水ポンプに接続された通水用シールドト
ンネルであり、前記水中構造物は前記通水用シールドト
ンネルの先端に設けられたフィルタ施設であることを特
徴とする請求項1に記載の水中構造物とシールドトンネ
ルとの連結工法。2. The shield tunnel is a shield tunnel for water flow connected to an intake pump or a drain pump of a thermal power plant, and the underwater structure is a filter facility provided at a tip of the shield tunnel for water power. The method according to claim 1, wherein the underwater structure is connected to a shield tunnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09402797A JP3902828B2 (en) | 1997-04-11 | 1997-04-11 | Connection method between underwater structure and shield tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09402797A JP3902828B2 (en) | 1997-04-11 | 1997-04-11 | Connection method between underwater structure and shield tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10292406A true JPH10292406A (en) | 1998-11-04 |
JP3902828B2 JP3902828B2 (en) | 2007-04-11 |
Family
ID=14099091
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP09402797A Expired - Fee Related JP3902828B2 (en) | 1997-04-11 | 1997-04-11 | Connection method between underwater structure and shield tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3902828B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102677623A (en) * | 2012-05-25 | 2012-09-19 | 黄河勘测规划设计有限公司 | Intake tower arranging method for reservoir |
JP2013506098A (en) * | 2009-09-23 | 2013-02-21 | レイモンド フレイジャー,スコット | System for storing compressed fluid energy in water and method of deploying the system |
CN105317028A (en) * | 2015-04-14 | 2016-02-10 | 贵州省水利水电勘测设计研究院 | Surge chamber structure applicable to long-distance pressure diversion tunnel and construction method |
-
1997
- 1997-04-11 JP JP09402797A patent/JP3902828B2/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013506098A (en) * | 2009-09-23 | 2013-02-21 | レイモンド フレイジャー,スコット | System for storing compressed fluid energy in water and method of deploying the system |
US9022692B2 (en) | 2009-09-23 | 2015-05-05 | Bright Energy Storage Technologies, Llp | System for underwater compressed fluid energy storage and method of deploying same |
CN102677623A (en) * | 2012-05-25 | 2012-09-19 | 黄河勘测规划设计有限公司 | Intake tower arranging method for reservoir |
CN105317028A (en) * | 2015-04-14 | 2016-02-10 | 贵州省水利水电勘测设计研究院 | Surge chamber structure applicable to long-distance pressure diversion tunnel and construction method |
CN105317028B (en) * | 2015-04-14 | 2018-08-17 | 贵州省水利水电勘测设计研究院 | A kind of surge-chamber structure and construction method for being suitable for having pressure diversion tunnel over long distances |
Also Published As
Publication number | Publication date |
---|---|
JP3902828B2 (en) | 2007-04-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109853604A (en) | A kind of static pressure waterpower suction open caisson construction method | |
JPWO2003008715A1 (en) | Construction method of manhole structure, waterproof joint for manhole structure and manhole structure | |
JPH10292406A (en) | Connecting method for underwater structure and shield tunnel | |
JPH08109651A (en) | Cut-off method of deep well in building work | |
JP2000265474A (en) | Temporary cofferdam constructing method for construction | |
JP2002220991A (en) | Partition wall installed in main-tunnel shield tunnel and construction method therefor | |
KR100880367B1 (en) | Process for constructing diffuser in the water | |
KR20050017815A (en) | Construction and design method about center wall of two arch tunnel excavation method | |
JP3893052B2 (en) | Joint structure of manhole for propulsion pipe and its construction method | |
JP6214808B1 (en) | Submarine pipeline landing method | |
JP4626052B2 (en) | Construction method for underwater structures | |
JPH10292773A (en) | Method for connecting construction of underwater structure and shield tunnel | |
JPH0813495A (en) | Earth retaining wall and method thereof | |
JP3090091B2 (en) | Termination method of shield tunnel | |
JP3799106B2 (en) | Final joint construction method for submerged boxes | |
JP3131119B2 (en) | How to stop water at a pipe propulsion wellhead | |
JP2003336484A (en) | Pipe laying method for subaqueous ground and excavating tip device used for pipe laying method | |
JP3840405B2 (en) | Submerged box and method of starting / arriving of deformed shield machine using submerged box | |
JP3540400B2 (en) | Piping method of fluid pipe | |
JPH0381421A (en) | Shaft construction method | |
JP4807930B2 (en) | Water intake construction method | |
JP3069822B2 (en) | Installation method of intake water discharge pipe | |
JP2000291376A (en) | Departing method of shielding machine at bottom of water and structure of departing part | |
JPH10102521A (en) | Final joint device for submerged caisson and its execution method | |
JP2000240078A (en) | Submerged caisson connecting method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040401 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060515 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060523 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061219 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070105 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110112 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110112 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120112 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120112 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130112 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130112 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140112 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313532 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |