JP3090091B2 - Termination method of shield tunnel - Google Patents
Termination method of shield tunnelInfo
- Publication number
- JP3090091B2 JP3090091B2 JP09171980A JP17198097A JP3090091B2 JP 3090091 B2 JP3090091 B2 JP 3090091B2 JP 09171980 A JP09171980 A JP 09171980A JP 17198097 A JP17198097 A JP 17198097A JP 3090091 B2 JP3090091 B2 JP 3090091B2
- Authority
- JP
- Japan
- Prior art keywords
- shield
- bulkhead
- shield machine
- shield tunnel
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【0001】[0001]
【発明の属する技術分野】この発明は、終端部が海辺な
どの海中に開口する放水路などとして掘進されるシール
ドトンネルの終端部施工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a terminal portion of a shield tunnel excavated as a water discharge channel whose terminal portion opens into the sea such as a seaside.
【0002】[0002]
【従来の技術】近年、例えば発電所の放水路などとして
利用されるシールドトンネルもシールドマシンによって
掘進される。また、放水路の終端部を海辺などの海中に
開口するように掘進するには、前面に隔壁を設けて、切
り羽の土砂がトンネル側に流入しないように構成された
密閉式のシールドマシンが使用され、さらに放水路の終
端部を覆工するには、例えば図8に図示するようにシー
ルドトンネル20を掘進し終え、シールドマシン21の先端
部が防波堤22の壁面から突出したら、最初にシールドト
ンネル20の中を海水で満水させる。次に、シールドマシ
ン21のカッターデスク23など、スキンプレート24を除く
シールドマシン21の主要装置を全て撤去し、その後スキ
ンプレート24の内側に水中コンクリート25を打設する。2. Description of the Related Art In recent years, shield tunnels used as, for example, water outlets of power plants are excavated by shield machines. In order to excavate the tail end of the tailrace so that it opens into the sea such as the seaside, a sealed shield machine configured with a partition wall on the front so that the earth and sand of the cutting face does not flow into the tunnel side is provided. In order to further lining the tail end of the water discharge channel, for example, as shown in FIG. 8 , the excavation of the shield tunnel 20 is completed, and when the tip of the shield machine 21 protrudes from the wall surface of the breakwater 22, the shield is firstly provided. The inside of the tunnel 20 is filled with seawater. Next, all the main devices of the shield machine 21 except the skin plate 24 such as the cutter desk 23 of the shield machine 21 are removed, and then the underwater concrete 25 is poured inside the skin plate 24.
【0003】[0003]
【発明が解決しようとする課題】しかし、カッターデス
ク23などのシールドマシン21の主要装置の撤去、水中コ
ンクリート25の打設など、全ての作業が水中での作業と
なり、水中作業は天候に大きく左右されやすいだけでな
く、作業効率が悪く、しかも大変危険を伴うなどの課題
があった。However, all work such as removal of the main equipment of the shield machine 21 such as the cutter desk 23 and placing of the underwater concrete 25 is underwater work, and underwater work largely depends on the weather. In addition to this, there is a problem that the work efficiency is low and the operation is very dangerous.
【0004】この発明は、以上の課題を解決するために
なされたもので、特に施工の効率性性および安全性の向
上を可能にしたシールドトンネルの終端部施工法を提供
することを目的とする。SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object of the present invention is to provide a method of constructing a terminal portion of a shield tunnel which can improve the efficiency and safety of construction. .
【0005】[0005]
【課題を解決するための手段】前記課題を解決するため
に、この発明に係るシールドトンネルの終端部施工法
は、シールドトンネルを掘進し終えてシールドマシンが
水中に突出したら、シールドマシンの先端部にバルクヘ
ッドを取り付けてシールドマシンの先端部を密閉状態に
塞ぎ、次に前記シールドマシンのスキンプレートを除く
主要装置を撤去し、次に前記スキンプレートの内側にコ
ンクリートを打設して前記シールドトンネルの終端部の
内周を覆工し、次に前記バルクヘッドを撤去する。In order to solve the above-mentioned problems, a method of constructing a terminal portion of a shield tunnel according to the present invention comprises the steps of: excavating the shield tunnel and projecting the shield machine into water; Attach the bulkhead to the shield machine and close the tip of the shield machine in a sealed state, then remove the main equipment except the skin plate of the shield machine, and then cast concrete inside the skin plate to make the shield tunnel Lining the inner periphery of the terminal end of the above, and then removing the bulkhead.
【0006】その際、シールドマシンの先端部にバルク
ヘッドを取り付けてシールドマシンの先端部を密閉状態
に塞いだ後、シールドマシンの主要装置を撤去する前
に、シールドマシンの先端部分に位置する隔壁とバルク
ヘッドとからなるチャンバー内を排水し、またシールド
トンネルの終端部の内周を覆工した後、バルクヘッドを
撤去する前に、前記シールドトンネル内を湛水する。At this time, after the bulkhead is attached to the tip of the shield machine to close the tip of the shield machine in a sealed state, before removing the main equipment of the shield machine, the partition located at the tip of the shield machine is removed. After draining the inside of the chamber composed of the bulkhead and the inside of the end of the shield tunnel, the inside of the shield tunnel is flooded before the bulkhead is removed.
【0007】[0007]
発明の実施の形態1.図1〜図7は、この発明の実施の
一形態を示し、図において、符号1は陸地に構築された
立て坑2から海に向かって掘進し、かつ海辺に構築され
た防波堤3を貫通し、終端が海中に開口するシールドト
ンネル、4はこのシールドトンネル1の内周を覆工する
セグメント、そして、符号5はこのシールドトンネル1
を掘進するシールドマシンである。Embodiment 1 of the Invention 1 to 7 show an embodiment of the present invention. In the drawings, reference numeral 1 denotes a dug from a shaft 2 constructed on land to the sea, and penetrates a breakwater 3 constructed on the seaside. , A shield tunnel whose end opens into the sea, 4 is a segment lining the inner periphery of the shield tunnel 1, and 5 is a shield tunnel 1
It is a shield machine that excavates.
【0008】また、符号6はシールドトンネル1を掘進
し終えて防波堤3を貫通し、かつ防波堤3から海中に一
部が突出したシールドマシン5の先端部に取り付け、シ
ールドマシン5のカッターデスク8等の部品を全て撤去
し、さらにシールドトンネル1の終端部を施工する間
中、シールドマシン5の先端部を海水がシールドトンネ
ル1内に流入しないように塞ぐバルクヘッドである。Reference numeral 6 designates a cutter desk 8 of the shield machine 5 which is attached to the tip of a shield machine 5 which has finished excavating the shield tunnel 1 and penetrates the breakwater 3 and partially projects from the breakwater 3 into the sea. This is a bulkhead that removes all of the components and closes the tip of the shield machine 5 so that seawater does not flow into the shield tunnel 1 during the construction of the terminal end of the shield tunnel 1.
【0009】防波堤3は、例えば海辺に鋼管矢板を多数
打ち込んで地中連続壁を構築し、この地中連続壁の中に
コンクリートを打設する等して構築されている。また、
セグメント4にはコンクリートセグメント等が使用され
ている。The breakwater 3 is constructed by, for example, driving a large number of steel sheet piles into the seashore to form an underground continuous wall, and then casting concrete into the underground continuous wall. Also,
A concrete segment or the like is used for the segment 4.
【0010】シールドマシン5は前面に隔壁10を設け
て、切り羽の土砂がトンネル内に流入しないように構成
された密閉式シールドマシンであり、シールドマシン5
の主要装置を内蔵し、かつ掘進直後のシールドトンネル
1の内周を保持するスキンプレート7、地盤を掘削する
カッターディスク8、このカッターディスク8を回転す
る動力を伝えるカッターシャフト9、土砂の流入を阻止
する隔壁10などを備えて構成されている。The shield machine 5 is a hermetic shield machine provided with a partition wall 10 on the front surface so as to prevent the earth and sand of the cutting face from flowing into the tunnel.
A skin plate 7 for holding the inner periphery of the shield tunnel 1 immediately after excavation, a cutter disk 8 for excavating the ground, a cutter shaft 9 for transmitting power for rotating the cutter disk 8, and an inflow of earth and sand. It is provided with a partition 10 and the like for blocking.
【0011】バルクヘッド6は鋼板などからシールドマ
シン5の外径と略同径のキャップ状に形成されたバルク
ヘッド本体11とこのバルクヘッド本体11の外側に添えつ
けられたトラス構造の補強ばり12とから構成されてい
る。補強ばり12は、例えばバルクヘッド本体11の中央部
から周辺方向に放射状に、又は一方向に平行に架け渡さ
れている。The bulkhead 6 is made of a steel plate or the like and has a bulkhead body 11 formed in the shape of a cap having substantially the same diameter as the outer diameter of the shield machine 5 and a reinforcing truss beam 12 attached to the outside of the bulkhead body 11. It is composed of The reinforcing beam 12 is, for example, bridged radially from the center of the bulkhead main body 11 to the peripheral direction or parallel to one direction.
【0012】バルクヘッド6とシールドマシン5との当
接部には、合成ゴムなどからなるガスケット13がシール
ドマシン5とバルクヘッド6の周方向に連続して介在さ
れ、当接部からシールドトンネル1内に海水が流入しな
いようになっている。A gasket 13 made of synthetic rubber or the like is interposed continuously between the bulkhead 6 and the shield machine 5 in the circumferential direction of the shield machine 5 and the bulkhead 6. Seawater is prevented from flowing into the interior.
【0013】さらに、当接部の外側にバルクヘッド6を
シールドマシン5の先端部から外れないように固定する
外れ止め14がシールドマシン5とバルクヘッド6の周方
向に連続して、又は所定間隔おきに取り付けられてい
る。Further, outside the abutting portion, a stopper 14 for fixing the bulkhead 6 so as not to come off from the tip of the shield machine 5 is continuous with the shield machine 5 and the bulkhead 6 in the circumferential direction or at a predetermined interval. Every other is attached.
【0014】このようにしてシールドマシン5の先端部
をバルクヘッド6で密閉状態に塞いだ後、スキンプレー
ト7のみを残し、カッターディスク8、カッターシャフ
ト9、隔壁10などを全て撤去し、さらにその後にスキン
プレート7の内側にコンクリート15を打設してシールド
トンネル1の終端部が構築されている。After the distal end of the shield machine 5 is closed by the bulkhead 6 in this manner, the cutter disk 8, the cutter shaft 9, the partition 10 and the like are all removed, leaving only the skin plate 7, and further thereafter. Concrete 15 is cast inside the skin plate 7 to construct the terminal end of the shield tunnel 1.
【0015】次に、施工方法を順をおって説明する。Next, the construction method will be described step by step.
【0016】 シールドマシン5がシールドトンネル
1を掘進し終えて防波堤3を貫通し、かつ防波堤3の壁
面から海中に一部が突出したら、カッターディスク8を
スキンプレート7の内側まで縮径する(図3参照)。When the shield machine 5 has finished excavating the shield tunnel 1 and has penetrated the breakwater 3 and partially protrudes from the wall surface of the breakwater 3 into the sea, the cutter disc 8 is reduced in diameter to the inside of the skin plate 7 (FIG. 3).
【0017】 次に、シールドマシン5の先端部にバ
ルクヘッド6を添えつけてシールドマシン5の先端部を
密閉状態に塞ぐ(図3参照)。バルクヘッド6は工場や
現地で組み立て、クレーン船16で吊って海中に沈設し、
かつシールドマシン5の先端部に設置する(図2参
照)。その際、バルクヘッド6の周囲をシールドマシン
5のスキンプレート7の周囲にガスケット13を介して密
着させ、またシールドマシン5とバルクヘッド6との当
接部の外側に外れ止め14を取りつけてバルクヘッド6を
スキンプレート7の先端部に外れないように固定する
(図3参照)。Next, the tip of the shield machine 5 is attached to the bulkhead 6 to seal the tip of the shield machine 5 in a sealed state (see FIG. 3). The bulkhead 6 is assembled at a factory or on site, suspended by a crane ship 16 and submerged in the sea,
And it is installed at the tip of the shield machine 5 (see FIG. 2). At this time, the periphery of the bulkhead 6 is brought into close contact with the periphery of the skin plate 7 of the shield machine 5 via a gasket 13, and a stopper 14 is attached to the outside of the contact portion between the shield machine 5 and the bulkhead 6 to bulk The head 6 is fixed to the tip of the skin plate 7 so as not to come off (see FIG. 3).
【0018】 次に、隔壁10とバルクヘッド6とから
なるチャンバーa内の水を排水ポンプ(図省略)によっ
て強制排水する。チャンバーa内の水を排水すると、バ
ルクヘッド6の周囲がスキンプレート7の周囲に水圧に
よって強く押しつけられて、ガスケット13がつぶされる
ため、バルクヘッド6とスキンプレート7間の当接部の
止水性が完全なものになる。Next, water in a chamber a including the partition wall 10 and the bulkhead 6 is forcibly drained by a drain pump (not shown). When the water in the chamber a is drained, the periphery of the bulkhead 6 is strongly pressed against the periphery of the skin plate 7 by water pressure, and the gasket 13 is crushed. Will be complete.
【0019】 次に、カッターディスク8、カッター
シャフト9、隔壁10などのシールドマシン5の主要装置
を、スキンプレート7のみを残して全て撤去する(図4
参照)。そして、スキンプレート7の内側にコンクリー
ト15を所定の厚さに打設してシールドトンネル1の終端
部を覆工する(図5参照)。Next, all the main devices of the shield machine 5, such as the cutter disk 8, the cutter shaft 9, and the partition 10, are removed except for the skin plate 7 (FIG. 4).
reference). Then, concrete 15 is poured into the skin plate 7 to a predetermined thickness to cover the terminal end of the shield tunnel 1 (see FIG. 5).
【0020】 次に、シールドトンネル1に給水し
て、シールドトンネル1内を湛水することにより、シー
ルドトンネル1の中と外を同水圧にする。Next, by supplying water to the shield tunnel 1 and flooding the inside of the shield tunnel 1, the inside and outside of the shield tunnel 1 are made to have the same water pressure.
【0021】 そして、シールドトンネル1の中と外
が同水圧になったら、外れ止め14を取り外し、バルクヘ
ッド6をクレーン船16で吊って撤去する(図6,7参
照)。When the inside and outside of the shield tunnel 1 have the same water pressure, the stopper 14 is removed, and the bulkhead 6 is suspended by the crane ship 16 and removed (see FIGS. 6 and 7).
【0022】[0022]
【0023】[0023]
【0024】[0024]
【0025】[0025]
【0026】[0026]
【0027】[0027]
【0028】[0028]
【0029】[0029]
【0030】[0030]
【0031】[0031]
【0032】[0032]
【0033】[0033]
【0034】[0034]
【0035】[0035]
【0036】[0036]
【0037】[0037]
【発明の効果】この発明に係るシールドトンネルの終端
部施工法は、以上説明した構成からなり、シールドトン
ネルを掘進し終えてシールドマシンが水中に突出した
ら、前記シールドマシンの先端部にバルクヘッドを取り
付けて前記シールドマシンの先端部を密閉し、次に前記
シールドマシンのスキンプレートを除く主要装置を撤去
し、次に前記スキンプレートの内側にコンクリートを打
設して前記シールドトンネルの終端部の内周を覆工し、
次に前記バルクヘッドを撤去するので、カッターデスク
等のシールドマシンの主要装置の撤去、覆工用コンクリ
ートの打設など、全ての作業をドライ施工で行うことが
できるので、施工性がきわめて高く、安全性もきわめて
高い等の効果がある。According to the present invention, the method for constructing the end portion of the shield tunnel has the above-described structure. When the shield machine has protruded into the water after excavating the shield tunnel, a bulkhead is attached to the tip of the shield machine. Attach and seal the tip of the shield machine, then remove the main equipment except the skin plate of the shield machine, and then cast concrete inside the skin plate to set the inside of the shield tunnel end Lining the circumference,
Next, since the bulkhead is removed, the removal of the main equipment of the shield machine such as the cutter desk, the placement of concrete for lining, etc., all the work can be performed by dry construction, so the workability is extremely high, There are also effects such as extremely high safety.
【0038】また、シールドマシンの先端部にバルクヘ
ッドを取り付けて前記シールドマシンの先端部を密閉し
た後、シールドマシンの主要装置を撤去する前に、チャ
ンバー内を排水するので、バルクヘッドの周囲がスキン
プレートの周囲に水圧によって強く押しつけられてガス
ケットがつぶされるため、バルクヘッドとスキンプレー
ト間の当接部の止水を確実に行うことができる。After the bulkhead is attached to the tip of the shield machine to seal the tip of the shield machine, and before the main equipment of the shield machine is removed, the inside of the chamber is drained. Since the gasket is crushed by being strongly pressed by the water pressure around the skin plate, it is possible to reliably stop the water at the contact portion between the bulkhead and the skin plate.
【0039】さらに、バルクヘッドを撤去するに先立っ
て、シールドトンネル内を湛水してシールドトンネルの
中と外を同水圧にするので、バルクヘッドを簡単に撤去
できる。Further, prior to removing the bulkhead, the inside of the shield tunnel is flooded to make the inside and outside of the shield tunnel have the same water pressure, so that the bulkhead can be easily removed.
【0040】[0040]
【0041】[0041]
【図1】立て坑から海に向かって掘進されるシールドト
ンネルの縦断面図である。FIG. 1 is a longitudinal sectional view of a shield tunnel excavated from a shaft into the sea.
【図2】海中に開口するシールドトンネル終端部の施工
状況を示す縦断面図である。FIG. 2 is a longitudinal sectional view showing a construction state of a shield tunnel terminal end opening into the sea.
【図3】海中に開口するシールドトンネル終端部の施工
状況を示す縦断面図である。FIG. 3 is a longitudinal sectional view showing a construction state of a shield tunnel terminal end opening into the sea.
【図4】海中に開口するシールドトンネル終端部の施工
状況を示す縦断面図である。FIG. 4 is a vertical cross-sectional view showing a construction state of a shield tunnel terminal end opening into the sea.
【図5】海中に開口するシールドトンネル終端部の施工
状況を示す縦断面図である。FIG. 5 is a longitudinal sectional view showing a construction state of a shield tunnel terminal end opening into the sea.
【図6】海中に開口するシールドトンネル終端部の施工
状況を示す縦断面図である。FIG. 6 is a longitudinal sectional view showing a construction state of a shield tunnel terminal end opening into the sea.
【図7】海中に開口するシールドトンネル終端部の施工
後の状態を示す縦断面図である。FIG. 7 is a longitudinal sectional view showing a state after construction of a shield tunnel terminal end opening into the sea.
【図8】立て坑から海に向かって掘進し、終端部が海中
に開口するシールドトンネルの縦断面図である。FIG. 8 is a longitudinal sectional view of a shield tunnel excavating from a shaft into the sea and having a terminal end opening into the sea.
1…シールドトンネル、2…立て坑、3…防波堤、4…
セグメント、5…シールドマシン、6…バルクヘッド、
7…スキンプレート、8…カッターディスク、9…カッ
ターシャフト、10…隔壁、11…バルクヘッド本体、12…
補強ばり、13…ガスケット、14…外れ止め、15…コンク
リート、16…クレーン船。1 ... shield tunnel, 2 ... shaft, 3 ... breakwater, 4 ...
Segment, 5 ... shield machine, 6 ... bulk head,
7 ... skin plate, 8 ... cutter disk, 9 ... cutter shaft, 10 ... partition wall, 11 ... bulkhead body, 12 ...
Reinforced beams, 13 ... gaskets, 14 ... clamps, 15 ... concrete, 16 ... cranes.
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E21D 9/06 301 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 7 , DB name) E21D 9/06 301
Claims (3)
が水中に開口するシールドトンネルの終端部施工法にお
いて、シールドトンネルを掘進し終えて前記シールドマ
シンが水中に突出したら、前記シールドマシンにおける
スキンプレートの先端部にバルクヘッドを取り付けて前
記シールドマシンの先端部を密閉し、次に前記シールド
マシンのスキンプレートを除く主要装置を撤去し、次に
前記スキンプレートの内側にコンクリートを打設して前
記シールドトンネルの終端部の内周を覆工し、次に前記
バルクヘッドを撤去することを特徴とするシールドトン
ネルの終端部施工法。1. A and excavation by the shield machine, the terminal end construction methods of the shield tunnel end portion is opened in the water, when the shield machine finished excavating shield tunnel projects into the water, in the shield machine
Attach the bulkhead to the tip of the skin plate to seal the tip of the shield machine, then remove the main equipment except the skin plate of the shield machine, and then cast concrete inside the skin plate Lining the inner periphery of the end of the shield tunnel, and then removing the bulkhead.
ートの先端部に前記バルクヘッドを取り付けてシールド
マシンの先端部を密閉した後に、シールドマシンの先端
部に位置する隔壁とバルクヘッドとからなるチャンバー
内を排水するすることを特徴とする請求項第1項記載の
シールドトンネルの終端部施工法。2. The method of claim 1] Sukinpure in the shield machine
After sealing the front end portion of the sheet Rudomashin attach the bulkhead to the tip portion of the over preparative, claims, characterized in that the draining chamber comprising a partition wall and bulkhead located at the top portion of the sheet Rudomashin 2. The method for constructing a terminal portion of a shield tunnel according to claim 1.
ルドトンネル内を湛水することを特徴とする請求項第1
項または第2項記載のシールドトンネルの終端部施工
法。3. The method according to claim 1, wherein the shield tunnel is flooded before the bulkhead is removed.
Item 3. The method for constructing an end portion of a shield tunnel according to item 2 or 2.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09171980A JP3090091B2 (en) | 1997-01-17 | 1997-06-27 | Termination method of shield tunnel |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9-6194 | 1997-01-17 | ||
JP619497 | 1997-01-17 | ||
JP09171980A JP3090091B2 (en) | 1997-01-17 | 1997-06-27 | Termination method of shield tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10259691A JPH10259691A (en) | 1998-09-29 |
JP3090091B2 true JP3090091B2 (en) | 2000-09-18 |
Family
ID=26340275
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP09171980A Expired - Fee Related JP3090091B2 (en) | 1997-01-17 | 1997-06-27 | Termination method of shield tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3090091B2 (en) |
-
1997
- 1997-06-27 JP JP09171980A patent/JP3090091B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH10259691A (en) | 1998-09-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2004270252A (en) | Shaft arrival method of shield machine and pressure-resistant sealing device for use in it | |
JP3090091B2 (en) | Termination method of shield tunnel | |
JP2779680B2 (en) | Construction method of underwater tunnel and underwater excavator | |
JP2891889B2 (en) | Underwater tunnel penetration method | |
JP2779681B2 (en) | Underwater excavator | |
JP3902828B2 (en) | Connection method between underwater structure and shield tunnel | |
JP2779679B2 (en) | Construction method of underwater tunnel and underwater excavator | |
JP4139193B2 (en) | Connection method for submerged boxes and underwater tunnels | |
JP3840405B2 (en) | Submerged box and method of starting / arriving of deformed shield machine using submerged box | |
JP4277181B2 (en) | Tunnel construction method with manhole | |
JPH0437916B2 (en) | ||
JPH10292773A (en) | Method for connecting construction of underwater structure and shield tunnel | |
JP2963632B2 (en) | Underwater shield excavation method | |
JP2891888B2 (en) | Underwater tunnel penetration method | |
JP3177908B2 (en) | Starting method of shield excavator | |
JPS6215300Y2 (en) | ||
JPS60181497A (en) | Drilling method and apparatus for covering pipeline wall by water impermeable film | |
JP2963630B2 (en) | Underwater shield excavation method | |
JP2976830B2 (en) | Joining method of shield excavator and reaching shaft | |
JPS5991228A (en) | Pit excavation work using caisson | |
JPH09273382A (en) | Jacking machine for underwater tunnel | |
JPH1025989A (en) | Water-stop method of arrival opening | |
JP2003041575A (en) | Water flow-through hole forming device and water flow- through hole forming method used for forming water flow-through hole for maintaining underground water flow in impervious wall | |
JP2851520B2 (en) | Shaft | |
JP2826759B2 (en) | Construction method of intake / discharge port in water |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20000620 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |