JPS6215300Y2 - - Google Patents

Info

Publication number
JPS6215300Y2
JPS6215300Y2 JP14728782U JP14728782U JPS6215300Y2 JP S6215300 Y2 JPS6215300 Y2 JP S6215300Y2 JP 14728782 U JP14728782 U JP 14728782U JP 14728782 U JP14728782 U JP 14728782U JP S6215300 Y2 JPS6215300 Y2 JP S6215300Y2
Authority
JP
Japan
Prior art keywords
waterway
hull
caisson
hull caisson
view
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14728782U
Other languages
Japanese (ja)
Other versions
JPS5951820U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP14728782U priority Critical patent/JPS5951820U/en
Publication of JPS5951820U publication Critical patent/JPS5951820U/en
Application granted granted Critical
Publication of JPS6215300Y2 publication Critical patent/JPS6215300Y2/ja
Granted legal-status Critical Current

Links

Description

【考案の詳細な説明】 本考案は、海底へ船体ケーソンを沈設すること
により構築される護岸構造に関する。
[Detailed Description of the Invention] The present invention relates to a seawall structure constructed by sinking a hull caisson into the seabed.

一般に、船体ケーソン工法では、中古船の船首
側および船尾側のブロツクを切断撤去して、その
整備を完了した後、この船体を現地へ曳航して、
その沈設を行ない、さらにその内部へ土砂等を投
入する中詰作業を行なつて、これを堤体として再
利用することが行なわれる。
Generally, in the hull caisson construction method, the bow and stern blocks of a used ship are cut and removed, and after the maintenance is completed, the hull is towed to the site.
This is done by sinking the dam, then filling it with earth and sand, and then reusing it as an embankment body.

ところで、従来の船体ケーソン沈設による護岸
工事と水路工事との関係は、第1図および第2図
にて示すようになつている。
Incidentally, the relationship between conventional bank protection work by sinking hull caissons and waterway work is shown in FIGS. 1 and 2.

すなわち、第1図に示すごとく、護岸工事で
は、海底に造成されたマウンド1上に船体ケーソ
ン2が沈座せしめられ、その上部に上部コンクリ
ート3が打設されるほか、底側部に洗掘防止用の
根固めブロツク4が設置されて、船体内には波圧
安定用として砂または砕石等の中詰材5が投入さ
れる。
In other words, as shown in Figure 1, in the revetment work, the hull caisson 2 is sunk on a mound 1 built on the seabed, an upper concrete 3 is placed on top of the mound 1, and the bottom side is scoured. A foot protection block 4 for prevention is installed, and a filling material 5 such as sand or crushed stone is put into the hull to stabilize wave pressure.

そして、第2図に示すように、船体ケーソン沈
設完了後、その埋立側には埋立土6による造成工
事が施される。
As shown in FIG. 2, after the hull caisson is completely sunk, construction work is performed on the reclaimed side using reclaimed soil 6.

その後、水路7を設けるため、水路布設範囲の
埋立土が掘削され、水路7の施工が行なわれてか
ら、掘削土の埋戻しが行なわれる。
Thereafter, in order to provide the waterway 7, the reclaimed soil in the waterway installation range is excavated, and after the waterway 7 is constructed, the excavated soil is backfilled.

上述のごとく、護岸構造に水路を併設する場
合、従来は一度埋立した土を水路施工のため掘削
し、水路施工完了後に再度掘削土を埋戻すとい
う、作業の重複を必要とする不具合がある。
As mentioned above, when installing a waterway alongside a revetment structure, conventionally there is a problem in that it requires duplication of work, such as excavating the reclaimed soil to construct the waterway, and then backfilling with excavated soil again after the construction of the waterway is completed.

本考案は、このような問題点の解決をはかろう
とするもので、護岸工事と水路工事とを作業の重
複を要することなく能率よく施工できるようにし
た、水路付き護岸構造を提供することを目的とす
る。
The present invention is an attempt to solve these problems, and aims to provide a bank revetment structure with a waterway that allows bank protection work and waterway work to be carried out efficiently without duplication of work. purpose.

このため本考案の水路付き護岸構造は、海底へ
沈設された船体ケーソンから成る護岸構造におい
て、上記船体ケーソンに水路が内蔵されているこ
とを特徴としている。
For this reason, the revetment structure with a channel of the present invention is a revetment structure consisting of a hull caisson sunk into the seabed, and is characterized in that the hull caisson has a built-in channel.

以下、図面により本考案の実施例について説明
すると、第3〜5図は本考案の第1実施例として
の水路付き護岸構造を示すもので、第3図はその
横断面図、第4図はその縦断面図、第5図は第4
図のV部の拡大図であり、第6〜8図はいずれも
第5図に対応させて船体ケーソンの隔壁と水路と
の関係の変形例を示す部分図である。
Hereinafter, embodiments of the present invention will be explained with reference to drawings. Figures 3 to 5 show a revetment structure with a water channel as the first embodiment of the present invention, Figure 3 is a cross-sectional view thereof, and Figure 4 is a cross-sectional view of the structure. Its vertical cross-sectional view, Figure 5, is the 4th
It is an enlarged view of section V in the figure, and FIGS. 6 to 8 are all partial views showing a modified example of the relationship between the bulkhead of the hull caisson and the waterway, corresponding to FIG.

第3〜5図に示すように、海底に造成されたマ
ウンド1上に船体ケーソン2が沈座せしめられ、
その底側部に洗掘防止用の根固めブロツク4が設
置されるほか、船体ケーソン2の内部には砂また
は砕石等の中詰材5が投入される。
As shown in Figures 3 to 5, the hull caisson 2 is sunk on a mound 1 built on the seabed,
A foot protection block 4 for preventing scouring is installed on the bottom side of the caisson, and filling material 5 such as sand or crushed stone is placed inside the hull caisson 2.

こ中詰材5の投入の際、船体ケーソン2の内部
にコンクリート製水路7が基礎部9を介して設け
られるが、船体ケーソン2の両サイドタンクへの
中詰材5の投入は、水路7の施工に先立つて行な
われる。
When filling the filling material 5, a concrete waterway 7 is provided inside the hull caisson 2 via the foundation 9. This will be done prior to construction.

そして、中詰材5を船体ケーソン2内に充填す
る作業が完了したのち、船体ケーソン2の上部に
上部コンクリート3が打設される。
Then, after the work of filling the inside of the hull caisson 2 with the filling material 5 is completed, the upper concrete 3 is placed in the upper part of the hull caisson 2.

コンクリート製水路7およびその基礎部9は、
第15図に示すように、予じめ工場で船体ケーソ
ン2内に組込んでおいてもよく、このようにプレ
ハブ化したものを現地へ曳航することにより、現
地での工数および工期の低減に寄与することがで
きる。
The concrete waterway 7 and its foundation 9 are
As shown in Figure 15, it may be assembled in advance into the hull caisson 2 at the factory, and by towing this prefabricated product to the site, it is possible to reduce the number of man-hours and construction period on site. can contribute.

なお、第5図に示すように、船体ケーソンの隔
壁10には複数の連結棒11が取付けられてお
り、これらの連結棒11を埋設させるようにコン
クリート製水路7が打設される。
As shown in FIG. 5, a plurality of connecting rods 11 are attached to the bulkhead 10 of the hull caisson, and a concrete waterway 7 is cast so as to bury these connecting rods 11.

この水路7と隔壁10との関係は、上述のごと
く連結棒11を介して一体に固着されたものとす
るほか、第6図に示すごとく連結材12を介して
水路7と隔壁10とを結合してもよい。
Regarding the relationship between the water channel 7 and the partition wall 10, in addition to being fixed together via the connecting rod 11 as described above, the water channel 7 and the partition wall 10 are connected via a connecting member 12 as shown in FIG. You may.

また、第7図に示すように、水路7と隔壁10
との間にゴム製シール材15を挿入してもよく、
さらに第8図に示すように、水路7と隔壁10と
の間に隙間を形成して、両者を互いに拘束されな
い状態にしてもよい。
Moreover, as shown in FIG. 7, the water channel 7 and the partition wall 10
A rubber sealing material 15 may be inserted between the
Furthermore, as shown in FIG. 8, a gap may be formed between the water channel 7 and the partition wall 10 so that they are not restrained from each other.

上述のごとく水路7を内蔵する船体ケーソン2
が設置されてから、その埋立側には埋立土(第2
図の符号6参照)による造成工事が行なわれる。
Hull caisson 2 with built-in waterway 7 as described above
After the first stage was installed, the reclaimed soil (the second
Reclamation work (see reference numeral 6 in the figure) will be carried out.

第9〜11図は本考案の第2実施例としての水
路付き護岸構造を示すもので、第9図はその横断
面図、第10図はその縦断面図、第11図は第1
0図のXI部の拡大図であり、第12〜14図はい
ずれも第11図に対応させて船体ケーソンの隔壁
と水路との関係の変形例を示す部分図である。
9 to 11 show a revetment structure with a water channel as a second embodiment of the present invention, in which FIG. 9 is a cross-sectional view thereof, FIG. 10 is a vertical cross-sectional view thereof, and FIG.
12 is an enlarged view of the XI section of FIG. 0, and FIGS. 12 to 14 are partial views showing a modified example of the relationship between the bulkhead of the hull caisson and the waterway, corresponding to FIG. 11.

この第2実施例の場合も、前述の第1実施例の
場合と同様に、海底に造成されたマウンド1上に
船体ケーソン2が沈座せしめられ、その底側部に
洗掘防止用の根固めブロツク4が設置されるほ
か、船体ケーソン2の内部には砂または砕石等の
中詰材5が投入される。
In the case of this second embodiment, as in the case of the first embodiment described above, the hull caisson 2 is sunk on a mound 1 built on the seabed, and there are roots on the bottom side of the mound 1 to prevent scour. In addition to installing a compaction block 4, a filling material 5 such as sand or crushed stone is placed inside the hull caisson 2.

また、中詰材5の投入の際に船体ケーソン2の
内部に水路8が基礎部9を介して設けられるが、
この水路8は鋼管製になつている。
Furthermore, when inserting the filling material 5, a waterway 8 is provided inside the hull caisson 2 via the foundation 9.
This waterway 8 is made of steel pipe.

なお、この場合も、水路8およびその基礎部9
を予じめ工場で船体ケーソン2に組込んでおくこ
とができる。
In addition, in this case as well, the waterway 8 and its foundation 9
can be assembled into the hull caisson 2 in advance at the factory.

この鋼管製の水路8は、第11図に示すごとく
その端部を船体ケーソンの隔壁10の開口部周縁
に連結板13を介して固着されるほか、第12図
に示すごとく連続した鋼管製水路8の外周を、隔
壁10の開口部周縁に連結板13で固着してもよ
い。
This steel pipe waterway 8 has its end fixed to the opening periphery of the bulkhead 10 of the hull caisson via a connecting plate 13 as shown in FIG. 11, and also has a continuous steel pipe waterway as shown in FIG. The outer periphery of 8 may be fixed to the periphery of the opening of the partition wall 10 with a connecting plate 13.

また、第13図に示すように、鋼管製水路8の
端部にシール押え金具14を取付けて、この金具
14と隔壁10の開口部周縁との間にゴム製シー
ル材15を挿入してもよく、あるいは第14図に
示すように、連続した鋼管製水路8の外周と隔壁
10の開口部周縁との間の隙間を設けて、両者が
互いに拘束されない状態にしてもよい。
Alternatively, as shown in FIG. 13, a seal holding fitting 14 may be attached to the end of the steel pipe waterway 8, and a rubber sealing material 15 may be inserted between this fitting 14 and the periphery of the opening of the partition wall 10. Alternatively, as shown in FIG. 14, a gap may be provided between the outer periphery of the continuous steel pipe waterway 8 and the periphery of the opening of the partition wall 10 so that the two are not restrained from each other.

中詰材5を船体ケーソン2内に充填する作業が
完了したのち、船体ケーソン2の上部に上部コン
クリート3が打設され、また船体ケーソン2の埋
立側には前述の第1実施例の場合と同様に埋立土
による造成工事が行なわれる。
After the filling material 5 has been filled into the hull caisson 2, upper concrete 3 is placed on the upper part of the hull caisson 2, and on the reclaimed side of the hull caisson 2, as in the case of the first embodiment, Similarly, construction work using reclaimed soil will be carried out.

第5,6図および第11,12図に示すよう
に、船体ケーソンの隔壁10に対し水路7,8を
力学的に結合した場合に比べて、第7,8図およ
び第13,14図に示すごとく船体ケーソンの隔
壁10に対し水路7,8を力学的に分離した場合
は、地盤の沈下等で船体ケーソンに強制変形を生
じても、船体ケーソンの応力が水路7,8に伝達
されない利点がある。
As shown in Figs. 5 and 6 and Figs. 11 and 12, compared to the case where the water channels 7 and 8 are mechanically connected to the bulkhead 10 of the hull caisson, Figs. If the waterways 7 and 8 are mechanically separated from the bulkhead 10 of the hull caisson as shown, even if the hull caisson is forcibly deformed due to ground subsidence, the stress in the hull caisson will not be transmitted to the waterways 7 and 8. There is.

いずれにしても本考案の水路付き護岸構造によ
れば、水路を護岸構造の内陸側の埋立地に別個に
施工するようにした従来の場合と比べて、水路
7,8が船体ケーソン2内に設けられるので、水
路設置のための埋立土の掘削および埋戻しのごと
き重複工事が不要となり、工期の短縮とコストの
低減に寄与することができる。
In any case, according to the revetment structure with waterways of the present invention, the waterways 7 and 8 are located inside the hull caisson 2, compared to the conventional case where the waterways were constructed separately on the reclaimed land on the inland side of the revetment structure. This eliminates the need for redundant construction work such as excavation and backfilling of reclaimed soil for waterway installation, contributing to shortening the construction period and reducing costs.

また本考案の水路付き護岸構造では、船体ケー
ソンによる護岸構造に水路が組込まれるため、そ
の内陸側の埋立地に水路を必要とせず、埋立地の
スペースの利用度が広くなる利点があり、さらに
船体ケーソンに予じめ工場で水路等を組込んでお
くことも可能となつて、工事の能率を一層向上さ
せうる利点がある。
In addition, in the revetment structure with a waterway of the present invention, since the waterway is incorporated into the revetment structure using the ship's caisson, there is no need for a waterway in the reclaimed land on the inland side, which has the advantage of widening the utilization of space in the reclaimed land. It is also possible to incorporate waterways etc. into the hull caisson in advance at the factory, which has the advantage of further improving construction efficiency.

【図面の簡単な説明】[Brief explanation of the drawing]

第1,2図は従来の護岸構造を示すもので、第
1図はその横断面図、第2図はその埋立地への水
路施工状態を示す横断面図であり、第3〜5図は
本考案の第1実施例としての水路付き護岸構造を
示すもので、第3図はその横断面図、第4図はそ
の縦断面図、第5図は第4図のV部の拡大図であ
り、第6〜8図はいずれも第5図に対応させて船
体ケーソンの隔壁と水路との関係の変形例を示す
部分図であり、第9〜11図は本考案の第2実施
例としての水路付き護岸構造を示すもので、第9
図はその横断面図、第10図はその縦断面図、第
11図は第10図のXI部の拡大図であり、第12
〜14図はいずれも第11図に対応させて船体ケ
ーソンの隔壁と水路との関係の変形例を示す部分
図であり、第15図は上記船体ケーソンへの水路
のプレハブ化を示す横断面図である。 1……マウンド、2……船体ケーソン、3……
上部コンクリート、4……根固めブロツク、5…
…中詰材、6……埋立土、7……コンクリート製
水路、8……鋼管製水路、9……基礎部、10…
…隔壁、11……連結棒、12……連結材、13
……連結板、14……シール押え金具、15……
ゴム製シール材。
Figures 1 and 2 show a conventional bank protection structure. Figure 1 is a cross-sectional view of the structure, Figure 2 is a cross-sectional view of the construction of a waterway to the reclaimed land, and Figures 3 to 5 are Fig. 3 is a cross-sectional view thereof, Fig. 4 is a longitudinal sectional view thereof, and Fig. 5 is an enlarged view of section V in Fig. 4. 6 to 8 are partial views showing modified examples of the relationship between the bulkhead of the hull caisson and the waterway, corresponding to FIG. 5, and FIGS. It shows a seawall structure with a waterway, and it is the 9th
The figure is a cross-sectional view, FIG. 10 is a vertical cross-sectional view, FIG. 11 is an enlarged view of section XI in FIG.
14 are partial views showing modified examples of the relationship between the bulkhead of the hull caisson and the waterway, corresponding to FIG. 11, and FIG. 15 is a cross-sectional view showing the prefabricated waterway to the hull caisson. It is. 1...mound, 2...hull caisson, 3...
Upper concrete, 4... Root hardening block, 5...
...Filling material, 6...Reclaimed soil, 7...Concrete waterway, 8...Steel pipe waterway, 9...Foundation, 10...
...Partition wall, 11...Connection rod, 12...Connection material, 13
...Connecting plate, 14...Seal holding fitting, 15...
Rubber sealing material.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 海底へ沈設された船体ケーソンから成る護岸構
造において、上記船体ケーソンに水路が内蔵され
ていることを特徴とする、水路付き護岸構造。
A revetment structure with a water channel, which is comprised of a hull caisson sunk into the seabed, characterized in that the hull caisson has a built-in water channel.
JP14728782U 1982-09-29 1982-09-29 Bank structure with waterway Granted JPS5951820U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14728782U JPS5951820U (en) 1982-09-29 1982-09-29 Bank structure with waterway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14728782U JPS5951820U (en) 1982-09-29 1982-09-29 Bank structure with waterway

Publications (2)

Publication Number Publication Date
JPS5951820U JPS5951820U (en) 1984-04-05
JPS6215300Y2 true JPS6215300Y2 (en) 1987-04-18

Family

ID=30327581

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14728782U Granted JPS5951820U (en) 1982-09-29 1982-09-29 Bank structure with waterway

Country Status (1)

Country Link
JP (1) JPS5951820U (en)

Also Published As

Publication number Publication date
JPS5951820U (en) 1984-04-05

Similar Documents

Publication Publication Date Title
CN101225664A (en) Caisson dock structure and construction method therefor
CN214784073U (en) Cofferdam retaining and protecting structure for coastal soft soil hydraulic reclamation land reclamation
CN111335263B (en) Method for building artificial island
JPS6215300Y2 (en)
JPH06146305A (en) Underwater foundation and installation method thereof
CN111305050B (en) Protection process for existing piers on two sides in tunnel construction
CN211498907U (en) Waterproof curtain at end of underwater channel foundation pit along two sides of water
CN211200274U (en) Assembled channel shore protection structure
JPS605072Y2 (en) Sheet pile type wall structure
JP3999628B2 (en) Construction method of caisson dyke
JP2784314B2 (en) How to set up an open caisson
CN218374182U (en) Drainage pipeline system is got to bank
CN113605904B (en) Construction method of ultra-shallow earthing large-diameter shield under-crossing river back pressure protection structure
JP3809631B2 (en) Submarine tunnel connection method
CN219327071U (en) Combined hydraulic structure
JPH07216903A (en) Bulkhead caisson and construction method of bulkhead
CN217758882U (en) Double-deck steel cofferdam open caisson structure
CN203247606U (en) Construction structure for sewage pipe and utility tunnel of deep sludge foundation to penetrate through center trench
JPH10298971A (en) Side flow preventing method for ground
JPH0615773B2 (en) Steel pipe extension caisson foundation sealing method
JP4139193B2 (en) Connection method for submerged boxes and underwater tunnels
CN115492193A (en) Coastal water taking and draining pipeline system and construction method thereof
JPS6357566B2 (en)
JP2581602B2 (en) Waste treatment method
JPS6331633B2 (en)