JPH0995949A - Back filling construction method for buried pipe - Google Patents

Back filling construction method for buried pipe

Info

Publication number
JPH0995949A
JPH0995949A JP7253553A JP25355395A JPH0995949A JP H0995949 A JPH0995949 A JP H0995949A JP 7253553 A JP7253553 A JP 7253553A JP 25355395 A JP25355395 A JP 25355395A JP H0995949 A JPH0995949 A JP H0995949A
Authority
JP
Japan
Prior art keywords
layer
earth
sand
backfilling
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7253553A
Other languages
Japanese (ja)
Inventor
Hiroshi Abe
大志 安部
Takashi Nakajima
中島  隆
Hideaki Hoshi
秀明 星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP7253553A priority Critical patent/JPH0995949A/en
Publication of JPH0995949A publication Critical patent/JPH0995949A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a back filling construction method which uses inexpensive fluidized earth being generally combined, and can deposit an upper layer part such as a road bed within specified time after depositing a fluidized earth layer. SOLUTION: In a back filling construction method for back filling various buried pipes which are buried or constructed under the surface of the ground, after depositing the fluidized earth layer 1 composed of fliuidzied earth from the lower end of the buried pipe 3 to height more than 1/5 of the diameter of the buried pipe 3, an earth and sand layer 2 composed of the earth and sand is provided on the fluidized earth layer 1 so that an earth and sand layer 22 composed of only the earth and sand having a fixed layer thickness necessary for compaction may be formed on a mixed layer 21 composed by mixing the earth and sand and the fluidized earth. After compacting of the earth and sand layer 2, an upper layer part such as a road bed is executed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えばガス管や通
信ケーブルなどの地下埋設管の埋戻し工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for backfilling underground buried pipes such as gas pipes and communication cables.

【0002】[0002]

【従来の技術】従来より、地下埋設物を埋戻すときに用
いる埋戻し材としては、多くの場合、別の場所から採取
した良質の山砂などが利用されている。これは地下埋設
物の敷設時に発生する掘削土が埋戻し材に適している場
合が少ないためである。
2. Description of the Related Art Conventionally, as a backfill material used when backfilling an underground buried object, in many cases, good quality sand or the like collected from another place is used. This is because excavated soil generated during the laying of underground buried objects is rarely suitable for backfill materials.

【0003】また、近年、天然資源である良質山砂の枯
渇化、その採取による環境破壊、その運搬による交通公
害および掘削土の処分問題などの観点から、埋戻し材と
して不適な掘削土や建設汚泥およびその他の不良土砂を
有効活用する動きが活発化している。
In recent years, from the viewpoints of depletion of high-quality mountain sand, which is a natural resource, environmental damage due to its extraction, traffic pollution due to its transportation, and disposal problems of excavated soil, excavated soil and construction unsuitable as backfill materials. There is a growing movement to effectively utilize sludge and other bad soil.

【0004】良質の山砂などの埋戻し材を直接用いる従
来の埋戻し工法では、埋戻し後の陥没を防ぐために、埋
戻し材を埋設物周辺部などの狭隘部分にも隙間なく充填
し、ランマによる締め固めを十分に行う必要がある。し
かし、この従来法には、埋戻し材の充填やランマによる
締め固めはすべて人力作業であり、また、騒音や振動を
引き起こすというような問題がある。
In the conventional backfilling method in which a backfill material such as high quality sand is directly used, in order to prevent depression after backfilling, the backfill material is filled in a narrow area such as a peripheral portion of the buried object without any gap. Sufficient compaction with a rammer is required. However, in this conventional method, filling of the backfill material and compaction by a rammer are all manual work, and there is a problem that noise and vibration are caused.

【0005】最近、上記良質の山砂などの特別な埋戻し
材を用いる代わりに、埋設物の敷設時に発生する掘削土
や安価な土砂を利用して、しかも上記のような従来法の
問題点を解決できる流動化埋戻し工法が開発され、一部
実用化されている。この工法は、掘削土や安価な土砂に
水と固化材を混合し、埋戻し材に流動性を持たせ、埋設
物周辺部などの狭隘部分にも隙間なく充填させるととも
に、固化材の作用により地山と同等以上の強度を発現し
ようというものである。
Recently, instead of using a special backfill material such as the above-mentioned high quality mountain sand, excavated soil or cheap earth and sand generated when laying an embedded object is used, and the problems of the conventional method as described above. A fluidized backfilling method that can solve the problem has been developed and is partly in practical use. This method mixes water and solidifying material with excavated soil or cheap earth and sand, makes the backfill material fluid, and fills narrow spaces such as the periphery of buried objects without any gaps. It is intended to develop strength equal to or higher than that of the natural ground.

【0006】例えば、特開昭63ー233115号公
報、特開平1ー312118号公報、特開平4ー351
388号公報には、土砂に水と固化材を混合し、流動性
を持たせた流動化土として埋設管などの埋戻しに用いる
工法が開示されている。
[0006] For example, Japanese Patent Laid-Open Nos. 63-233115, 1-312118, and 4-351.
No. 388 discloses a method in which water and a solidifying material are mixed with earth and sand, and the resulting soil is used for backfilling a buried pipe or the like as fluidized soil having fluidity.

【0007】また、特開平3ー287909号公報に
は、掘削土に予め固化材を配合混合し、この処理土を埋
戻し現場へ運搬し、埋戻しつつ処理土に注水するととも
に振動を与えて流動化して、埋戻し箇所の完全な充填を
行う工法が開示されている。
Further, in Japanese Patent Laid-Open No. 3-287909, the excavated soil is mixed with a solidifying material in advance, and the treated soil is transported to the backfill site, and water is poured into the treated soil while backfilling and vibration is applied. A method of fluidizing and completely filling the backfilled portion is disclosed.

【0008】一方、こうしたガス埋設配管工事などがそ
の大部分を占める都市街路の道路占有工事においては、
即日交通開放の条件下で施工することが余儀なくされて
おり、したがって短時間の埋戻し作業が必須となってい
る。特に、上記のような流動化埋戻し工法で行う場合
は、流動化土層打設後2時間以内に路床などの上層部の
施工が可能であることが要求されている。
On the other hand, in the road occupancy work on the city streets, where the gas burial piping work and the like occupy the majority,
Since it is unavoidable to construct it under the condition that the traffic can be opened on the same day, short-time backfilling work is essential. In particular, when the fluidized backfilling method as described above is used, it is required that the upper layer portion such as the roadbed can be constructed within 2 hours after the fluidized soil layer is cast.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、上記の
特許公報に開示された流動化埋戻し工法では、流動化土
が路床などの上層部を施工可能な強度になるまで固化す
るのを待たなければならないが、通常その待ち時間は4
〜5時間と長いので、市街地における即日復旧工事には
対応できない。
However, in the fluidization backfilling method disclosed in the above-mentioned patent publication, it is necessary to wait until the fluidized soil solidifies until the fluidized soil has a strength capable of constructing an upper layer portion such as a roadbed. It usually has to be 4
As it is ~ 5 hours long, we cannot deal with the same day restoration work in urban areas.

【0010】流動化土に合わせて特殊な固化材を用いれ
ば、固化時間は短縮されるが、コスト高になるととも
に、その配合技術も複雑になるので厳しい品質管理が必
要となる。
If a special solidifying material is used according to the fluidized soil, the solidifying time is shortened, but the cost is high and the compounding technique is complicated, so that strict quality control is required.

【0011】本発明は、このような課題を解決するため
になされたもので、安価な一般的配合の流動化土を用
い、しかも流動化土層打設後2時間以内で路床などの上
層部の施工が可能な埋設管の埋戻し工法を提供すること
を目的とする。
The present invention has been made in order to solve the above problems, and uses inexpensive general fluidized soil having a general composition, and moreover, within 2 hours after placing the fluidized soil layer, the upper layer of a roadbed or the like. It is an object of the present invention to provide a backfilling method for buried pipes capable of constructing a section.

【0012】[0012]

【課題を解決するための手段】上記課題は、地表面下に
埋設または構築された各種埋設管を埋戻す埋戻し工法に
おいて、前記埋設管の下端部より前記埋設管の径の1/
5以上の高さまで流動化土からなる流動化土層を打設
後、前記流動化土層の上に土砂からなる土砂層を、前記
土砂と前記流動化土が混合されてなる混合層上に締め固
めるに必要な所定層厚の土砂層が形成されるように設
け、前記土砂層を締め固めた後、路床などの上層部を施
工することを特徴とする埋設管の埋戻し工法により解決
される。
[Means for Solving the Problems] In the backfilling method for backfilling various buried pipes buried or constructed under the ground surface, the above-mentioned problem is 1 / one of the diameter of the buried pipe from the lower end of the buried pipe.
After pouring a fluidized soil layer made of fluidized soil to a height of 5 or more, a sediment layer made of earth and sand is placed on the fluidized soil layer on a mixed layer formed by mixing the soil and the fluidized soil. Set up so that a sediment layer with a predetermined layer thickness necessary for compaction is formed, and after compacting the sediment layer, the upper layer part such as the roadbed is constructed and solved by the backfilling method of the buried pipe To be done.

【0013】埋設管の下端部より埋設管の径の1/5以
上の高さまで流動化土からなる流動化土層を打設するこ
とにより、埋設管の下端部周辺の空隙の発生を防げ、充
填性よく埋戻しができる。1/5未満では、埋設管の下
端部周辺に発生する空隙により施工後に陥没することが
ある。
By pouring a fluidized soil layer made of fluidized soil from the lower end of the buried pipe to a height of ⅕ or more of the diameter of the buried pipe, generation of voids around the lower end of the buried pipe can be prevented, Can be backfilled with good filling property. If it is less than ⅕, it may be dented after construction due to voids generated around the lower end of the buried pipe.

【0014】流動化土層を打設後、流動化土層の上に土
砂からなる土砂層を形成すると、土砂層は土砂と流動化
土の混合した混合層とその上の土砂のみからなる土砂層
との2層構造となる。このとき、土砂のみからなる土砂
層の層厚が所定の層厚であれば、その荷重分散効果によ
り、流動化土が固化し流動化土層の強度が高くなるのを
待つことなく、この土砂層を締め固められるので、短時
間の埋戻しが可能となる。
After forming the fluidized soil layer, when a sediment layer made of earth and sand is formed on the fluidized soil layer, the earth and sand layer will be a mixed layer of earth and fluidized soil and earth and sand only on the mixed layer. It has a two-layer structure with layers. At this time, if the layer thickness of the earth and sand layer consisting of only the earth and sand is a predetermined layer thickness, the load distribution effect will not cause the fluidized soil to solidify and the strength of the fluidized soil layer to increase without waiting Since the layers can be compacted, backfilling in a short time is possible.

【0015】土砂のみからなる土砂層の締め固めるのに
必要な層厚は、土砂の種類や特性によって変わり、薄い
と流動化土層から吸収された水分が多いため締め固めが
困難になり、厚過ぎると締め固めが十分にできなくな
る。したがって、最適な層厚、すなわち最適な土砂の投
入量を予め適宜決めておく必要がある。
The layer thickness required for compaction of the sediment layer consisting of only the sediment depends on the type and characteristics of the sediment, and if it is thin, it will be difficult to compact because of the large amount of water absorbed from the fluidized soil layer. If too much, compaction cannot be performed sufficiently. Therefore, it is necessary to appropriately determine in advance the optimum layer thickness, that is, the optimum amount of earth and sand input.

【0016】土砂層に水硬化性材料を含有させると、流
動化土層からの吸水により土砂層中の水硬化性材料が硬
化するため、流動化土が固化し流動化土層の強度が高く
なるのを待つ必要がなく、しかもこの土砂層の締め固め
作業も不要になる。したがって、より短時間の埋戻しが
可能となる。
When the soil-hardening material contains a water-curable material, water-absorbing water from the fluidizing soil layer hardens the water-hardening material in the soil-sand layer, so that the fluidized soil is solidified and the fluidized soil layer has high strength. There is no need to wait for it to become dry, and the work of compacting this layer of sand is also unnecessary. Therefore, backfilling can be performed in a shorter time.

【0017】土砂中に含有させる水硬化性材料の量は、
多過ぎると長期強度が高くなり過ぎ再掘削が困難にな
り、少な過ぎると強度不足になるため、重量比で3〜2
0%にする必要がある。
The amount of the water-curable material contained in the earth and sand is
If the amount is too large, the long-term strength will be too high, making it difficult to re-excavate, and if it is too small, the strength will be insufficient.
It needs to be 0%.

【0018】また、水硬化性材料を含有した土砂層上に
散水すると、土砂層上部からも水硬化性材料を硬化でき
るため、より短時間の埋戻しが可能となる。
Further, when water is sprinkled on the earth-and-sand layer containing the water-curable material, the water-curable material can be hardened from the upper part of the earth-and-sand layer, so that backfilling can be performed in a shorter time.

【0019】こうした水硬化性材料を含む土砂層の形成
とその土砂層上への散水を繰り返して行えば、新たな路
床の打設は不要になり、その土砂層上へ直接路盤などの
上層部を施工できるので、より短時間の埋戻しが可能と
なる。土砂層の層数は、埋設物の設置条件や土砂、水硬
化性材料の種類により、適宜決める必要がある。
By repeatedly forming the sediment layer containing the water-curable material and sprinkling water on the sediment layer, it is not necessary to place a new subgrade, and the upper layer such as a roadbed is directly placed on the sediment layer. Since the parts can be constructed, it is possible to backfill in a shorter time. It is necessary to appropriately determine the number of layers of earth and sand depending on the installation conditions of the buried object, the type of earth and sand, and the water-curable material.

【0020】水硬化性材料が石膏、早強性のセメントあ
るいは固化材であると、硬化速度が促進されるので望ま
しい。
It is desirable that the water-curable material is gypsum, a fast-setting cement or a solidifying material because the curing rate is accelerated.

【0021】水硬化性材料が急結剤を含有したセメント
であると、さらに硬化速度が促進されるので望ましい。
It is desirable that the water-curable material is cement containing a quick-setting agent, because the curing rate is further accelerated.

【0022】水硬化性材料を含有する土砂の含水状態
は、水硬化性材料を混合するとき、水硬化性材料と反応
して水硬化性材料を固化したり、水硬化性材料を凝結さ
せ塊状にすることのないように、表面乾燥状態以下にす
ることが望ましい。
The water content of the sand containing the water-curable material is such that when the water-curable material is mixed, it reacts with the water-curable material to solidify the water-curable material or to condense the water-curable material to form a lump. It is desirable to keep the surface dry condition or less so as not to cause the above.

【0023】[0023]

【発明の実施の形態】図1に本発明の埋設管の埋戻し工
法の実施の形態の1例を示す。図で、1は流動化土層、
2は土砂層、21は流動化土と土砂の混合層、22は土
砂のみからなる土砂層、3はガス管などの埋設管、4は
路床、5は路盤、6は舗装、7は地表面、8は土留め用
鋼矢板である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an example of an embodiment of a backfilling method for a buried pipe according to the present invention. In the figure, 1 is a fluidized soil layer,
2 is a sediment layer, 21 is a mixed layer of fluidized soil and sediment, 22 is a sediment layer consisting only of sediment, 3 is a buried pipe such as a gas pipe, 4 is a roadbed, 5 is a roadbed, 6 is pavement, 7 is ground The surface, 8 is a steel sheet pile for retaining soil.

【0024】図2に本発明の埋設管の埋戻し工法の実施
の形態の別の1例を示す。図中の番号は図1の番号で示
したものと同じものを表す。
FIG. 2 shows another example of the embodiment of the backfilling method for a buried pipe according to the present invention. The numbers in the figure represent the same as the numbers shown in FIG.

【0025】図1は埋設管3が1本の場合であるが、図
2は埋設管3が並列に2本、上下に2段の計4本の場合
である。図2のような場合は、上段の埋設管3の径の1
/5以上の高さまで流動化土を充填する必要がある。
FIG. 1 shows a case where there is one buried pipe 3, whereas FIG. 2 shows a case where there are two buried pipes 3 in parallel and two stages above and below, a total of four. In the case of FIG. 2, the diameter of the upper buried pipe 3 is 1
It is necessary to fill with fluidized soil to a height of / 5 or more.

【0026】流動化土層1上に投入する土砂としては、
安価で入手し易い通常の土砂、例えば通常の山砂を用い
ることができる。
As the earth and sand to be put on the fluidized soil layer 1,
It is possible to use ordinary earth and sand that is inexpensive and easily available, for example, ordinary mountain sand.

【0027】土砂に含有させる水硬化性材料としては、
各種セメント、固化材、石膏、生石灰、フライアッシ
ュ、高炉水砕スラグなどを用いることができるが、上記
のように、石膏、早強性のセメントあるいは固化材を用
いることが好ましい。
As the water-curable material contained in the earth and sand,
Various cements, solidifying materials, gypsum, quick lime, fly ash, granulated blast furnace slag and the like can be used, but as described above, it is preferable to use gypsum, fast-setting cement or solidifying material.

【0028】水硬化性材料を含む土砂層2に水を散布す
るときの散水量は、この層2の短期強度、長期強度の観
点から決定する必要があるが、水硬化性材料の種類や含
有量によってその適性量は変化する。目安としては、砂
の場合、含水比で15〜20%ぐらいになるような水量
が好ましい。こうして、水硬化性材料を含む土砂層2の
上に散水することにより、層2自らが硬化するため、締
め固め作業が不要となる。
The amount of water sprayed when water is sprayed on the earth and sand layer 2 containing a water-curable material needs to be determined from the viewpoint of short-term strength and long-term strength of the layer 2. The appropriate amount changes depending on the amount. As a guide, in the case of sand, a water content of about 15 to 20% is preferable. Thus, by spraying water on the earth and sand layer 2 containing the water-curable material, the layer 2 itself hardens, so that compaction work is unnecessary.

【0029】水硬化性材料を含む土砂層2を、その上に
散水しながら数層設けることにより、新たな路床4の打
設を省略でき、直接路盤5などの上層部の施工が可能と
なる。
By providing several layers of earth-and-sand layer 2 containing a water-curable material while sprinkling water thereon, it is possible to omit placing a new roadbed 4 and directly construct an upper layer portion such as a roadbed 5. Become.

【0030】[0030]

【実施例】【Example】

(実施例1)地表面下にその直径が200mmのガス管
を図1に示す例のように埋設後、ガス管の下端部から直
径の1/4に相当する高さまで、表1に示す一般的配合
の流動化土を0.14t/m打設した。その後、直ちに
流動化土層上に含水比10%、比重2.7の山砂を0.
5t/m投入し、その表面を均して、ランマにて締め固
めた。そして、路床などの上層部を施工した。このと
き、流動化土層打設から路床などの上層部の施工開始ま
での時間は約30分で、従来法に比べ4時間以上の短縮
ができた。なお、流動化土と山砂の混合層の28日後の
強度は、一軸圧縮強度で1.8kgf/cm2 で、再掘
削が可能な強度であった。
(Example 1) After burying a gas pipe having a diameter of 200 mm under the ground surface as in the example shown in FIG. 1, from the lower end of the gas pipe to a height corresponding to ¼ of the diameter, shown in Table 1 Fluidized soil having a specific composition was placed at 0.14 t / m. Immediately thereafter, the sand with a water content of 10% and a specific gravity of 2.7 was added to the fluidized soil layer.
5 t / m was charged, the surface was leveled, and compacted with a rammer. Then, the upper layers such as the subgrade were constructed. At this time, the time from the pouring of the fluidized soil layer to the start of construction of the upper layer portion such as the roadbed was about 30 minutes, which was shortened by 4 hours or more as compared with the conventional method. The strength of the mixed layer of fluidized soil and mountain sand after 28 days was 1.8 kgf / cm 2 in uniaxial compressive strength, and was a strength capable of being re-excavated.

【0031】(実施例2)地表面下にその直径が50m
mの通信ケーブルを、図2に示す例のように並列に2
本、上下に2段の計4本埋設後、上段の通信ケーブルの
上端部まで、表1に示す一般的配合の流動化土を0.2
4t/m打設した。その後、直ちに流動化土層上に、重
量比で4%の普通ポルトランドセメントを含む含水比3
%の風乾状態の山砂を0.5t/m投入し、その上に含
水比が15〜20%になるように水を均一に散布した。
引続き、セメントを混合した同様な山砂の投入と散水を
2回繰り返して行い、路盤などの上層部の施工を行っ
た。このとき、流動化土層打設から路盤などの上層部の
施工開始までの時間は約50分であった。なお、セメン
ト混合山砂層の28日後の強度は、一軸圧縮強度で2.
0kgf/cm2 で、再掘削が可能な強度であった。
(Example 2) The diameter is 50 m below the ground surface.
2 communication cables in parallel as in the example shown in FIG.
After burying a total of four, two in the upper and the other in the upper and lower parts, 0.2 parts of the fluidized soil of the general composition shown in Table 1 up to the upper end of the upper communication cable.
4t / m was placed. Immediately after that, the fluidized soil layer immediately contained 4% by weight of ordinary Portland cement and had a water content of 3
% Air-dried mountain sand was added at 0.5 t / m, and water was evenly sprayed thereon so that the water content ratio was 15 to 20%.
Subsequently, the same pile of sand mixed with cement and water sprinkling were repeated twice to construct the upper layer of the roadbed. At this time, the time from the pouring of the fluidized soil layer to the start of construction of the upper layer portion such as the roadbed was about 50 minutes. The strength of the cement mixed pile sand layer after 28 days was uniaxial compressive strength of 2.
At 0 kgf / cm 2 , the strength was such that re-excavation was possible.

【0032】[0032]

【表1】 [Table 1]

【0033】[0033]

【発明の効果】本発明は以上説明したように構成されて
いるので、安価な一般的配合の流動化土を用いても、2
時間以内で路床などの上層部の施工が可能な埋設管の埋
戻し工法を提供することができる。
EFFECTS OF THE INVENTION Since the present invention is constructed as described above, even if an inexpensive fluidized soil having a general composition is used,
It is possible to provide a backfilling method for a buried pipe that enables construction of an upper layer portion such as a roadbed within the time.

【0034】また、本発明である埋戻し工法を用いれ
ば、流動化土層全体が完全に固化する前に、埋戻し工事
を完了できるため、土留め用鋼矢板の引抜きが容易に行
え、しかも鋼矢板の引抜き後に、流動化土層と地山との
間には空隙が生じることがないので、地盤低下も全く発
生しない。
Further, when the backfilling method of the present invention is used, the backfilling work can be completed before the entire fluidized soil layer is completely solidified, so that the steel sheet pile for retaining soil can be easily pulled out, and After drawing the steel sheet pile, there is no gap between the fluidized soil layer and the ground, so no ground deterioration occurs.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の埋設管の埋戻し工法の実施の形態の1
例を示す図である。
FIG. 1 is a first embodiment of a method for backfilling a buried pipe according to the present invention.
It is a figure showing an example.

【図2】本発明の埋設管の埋戻し工法の実施の形態の別
の1例を示す図である。
FIG. 2 is a diagram showing another example of the embodiment of the backfilling method for the buried pipe of the present invention.

【符号の説明】[Explanation of symbols]

1 流動化土層 2 土砂層 21 流動化土と土砂の混合層 22 土砂のみからなる土砂層 3 ガス管などの埋設管 4 路床 5 路盤 6 舗装 7 地表面 8 土留め用鋼矢板 1 fluidized soil layer 2 earth and sand layer 21 mixed layer of fluidized soil and earth and sand 22 earth and sand layer 3 earth and sand layer 3 buried pipe such as gas pipe 4 roadbed 5 roadbed 6 pavement 7 ground surface 8 steel sheet pile for retaining soil

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 地表面下に埋設または構築された各種埋
設管を埋戻す埋戻し工法において、前記埋設管の下端部
より前記埋設管の径の1/5以上の高さまで流動化土か
らなる流動化土層を打設後、前記流動化土層の上に土砂
からなる土砂層を、前記土砂と前記流動化土が混合され
てなる混合層上に締め固めるに必要な所定層厚の土砂層
が形成されるように設け、前記土砂層を締め固めた後、
路床などの上層部を施工することを特徴とする埋設管の
埋戻し工法。
1. In a backfilling method for backfilling various buried pipes buried or constructed under the surface of the earth, fluidized soil is formed from the lower end of the buried pipe to a height of ⅕ or more of the diameter of the buried pipe. After pouring the fluidized soil layer, a layer of earth and sand consisting of earth and sand on the fluidized soil layer, a predetermined layer thickness necessary for compaction on a mixed layer formed by mixing the earth and sand and the fluidized soil Provided so that a layer is formed, after compacting the sediment layer,
A method of backfilling buried pipes, which is characterized by constructing the upper layer of the subgrade.
【請求項2】 地表面下に埋設または構築された各種埋
設管を埋戻す埋戻し工法において、前記埋設管の下端部
より前記埋設管の径の1/5以上の高さまで流動化土か
らなる流動化土層を打設後、前記流動化土層の上に重量
比で3〜20%の水硬化性材料を含有する土砂からなる
土砂層を設け、路床などの上層部を施工することを特徴
とする埋設管の埋戻し工法。
2. In a backfilling method for backfilling various buried pipes buried or constructed under the surface of the ground, fluidized soil is formed from the lower end of the buried pipe to a height of ⅕ or more of the diameter of the buried pipe. After placing the fluidized soil layer, a layer of earth and sand containing 3 to 20% by weight of a water-curable material is provided on the fluidized soil layer, and an upper layer portion such as a roadbed is constructed. The backfilling method for buried pipes characterized by.
【請求項3】 前記水硬化性材料を含有する土砂からな
る土砂層を設けた後、前記土砂層上に散水することを特
徴とする請求項2に記載の埋設管の埋戻し工法。
3. The backfilling method for a buried pipe according to claim 2, wherein after providing a sediment layer made of sediment containing the water-curable material, water is sprinkled on the sediment layer.
【請求項4】 地表面下に埋設または構築された各種埋
設管を埋戻す埋戻し工法において、前記埋設管の下端部
より前記埋設管の径の1/5以上の高さまで流動化土か
らなる流動化土層を打設後、前記流動化土層の上に重量
比で3〜20%の水硬化性材料を含有する土砂からなる
土砂層を、前記土砂層上に散水しながら所定の層数設
け、路盤などの上層部を施工することを特徴とする埋設
管の埋戻し工法。
4. A backfilling method for backfilling various buried pipes buried or constructed under the surface of the earth, comprising fluidized soil from the lower end portion of the buried pipe to a height of ⅕ or more of the diameter of the buried pipe. After pouring the fluidized soil layer, a layer of earth and sand containing 3 to 20% by weight of a water-curable material on the fluidized soil layer is sprinkled onto the layer of sand to form a predetermined layer. A backfilling method for buried pipes, characterized in that a number of them are provided and the upper layer of the roadbed is constructed.
【請求項5】 前記水硬化性材料が石膏、早強性のセメ
ントあるいは固化材であることを特徴とする請求項2ま
たは請求項4に記載の埋設管の埋戻し工法。
5. The method of backfilling a buried pipe according to claim 2, wherein the water-curable material is gypsum, a fast-setting cement or a solidifying material.
【請求項6】 前記水硬化性材料が急結剤を含有したセ
メントであることを特徴とする請求項2または請求項4
に記載の埋設管の埋戻し工法。
6. The method according to claim 2, wherein the water-curable material is cement containing a quick-setting agent.
The method of backfilling the buried pipe described in.
【請求項7】 前記水硬化性材料を含有する土砂の含水
状態が表面乾燥状態以下であることを特徴とする請求項
2から請求項6のいずれか1項に記載の埋設管の埋戻し
工法。
7. The backfilling method for a buried pipe according to claim 2, wherein the water content of the soil containing the water-curable material is not more than a surface dry state. .
JP7253553A 1995-09-29 1995-09-29 Back filling construction method for buried pipe Pending JPH0995949A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7253553A JPH0995949A (en) 1995-09-29 1995-09-29 Back filling construction method for buried pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7253553A JPH0995949A (en) 1995-09-29 1995-09-29 Back filling construction method for buried pipe

Publications (1)

Publication Number Publication Date
JPH0995949A true JPH0995949A (en) 1997-04-08

Family

ID=17252974

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7253553A Pending JPH0995949A (en) 1995-09-29 1995-09-29 Back filling construction method for buried pipe

Country Status (1)

Country Link
JP (1) JPH0995949A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012007690A (en) * 2010-06-25 2012-01-12 Sumitomo Osaka Cement Co Ltd Pipe embedding method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012007690A (en) * 2010-06-25 2012-01-12 Sumitomo Osaka Cement Co Ltd Pipe embedding method

Similar Documents

Publication Publication Date Title
JP6230883B2 (en) Delay hardening type fluidized soil and filling method of underground cavities
CA2224277C (en) Method of filling an excavated opening
JPH10140507A (en) Fluidization treatment method
JPH0995949A (en) Back filling construction method for buried pipe
CN111908853A (en) Self-compacting soil, preparation method thereof and construction method for backfilling municipal cavity
JPH06344328A (en) Fast-curing fluidized threaded soil and rapid construction of roadbed/road body using the same
KR20240003601A (en) Construction method for tunnel of slope
JP3341541B2 (en) Backfilling method for buried objects
JP3230147B2 (en) Fluidized soil construction structure and its construction method
JPH0932969A (en) Back filling method for buried object
JPH11209907A (en) Paving material and road paving method
JPH0967573A (en) Backfilling method for buried item
JPH0790272A (en) Super-plasticizable back-filling material and back-filling process
JPH10195853A (en) Backfilling construction method of buried object
JPH0931951A (en) Back-filling work for buried structure
JP3599303B2 (en) Light earth method
JPH0913357A (en) Backfill method of buried article
JP2885199B2 (en) Underground burial method for pipelines
JPH1150438A (en) Superplasticization backfilling method of buried substance
JP2001354960A (en) Method for utilizing construction surplus soil
JPH03168489A (en) Burying method of buried pipe
JPH0617415A (en) Fluidization backfill and backfilling method
JPH0971967A (en) Method for back-filling of buried article
JP3769521B2 (en) Civil engineering groundwork, civil engineering methods using this civil engineering groundwork
JPH11210929A (en) Fluidization back filling method for buried substance

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041015

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041116

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050419