JPH0931951A - Backfilling method for buried objects - Google Patents
Backfilling method for buried objectsInfo
- Publication number
- JPH0931951A JPH0931951A JP7180273A JP18027395A JPH0931951A JP H0931951 A JPH0931951 A JP H0931951A JP 7180273 A JP7180273 A JP 7180273A JP 18027395 A JP18027395 A JP 18027395A JP H0931951 A JPH0931951 A JP H0931951A
- Authority
- JP
- Japan
- Prior art keywords
- fluidized soil
- soil layer
- buried
- backfilling
- fluidized
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Sewage (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、例えばガス管や通
信ケーブルなどの地下埋設物の埋戻し工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for backfilling underground objects such as gas pipes and communication cables.
【0002】[0002]
【従来の技術】従来より、地下埋設物を埋戻すときに用
いる埋戻し材としては、多くの場合、別の場所から採取
した良質の山砂などが利用されている。これは地下埋設
物の敷設時に発生する掘削土が埋戻し材に適している場
合が少ないためである。2. Description of the Related Art Conventionally, as a backfill material used when backfilling an underground buried object, in many cases, good quality sand or the like collected from another place is used. This is because excavated soil generated during the laying of underground buried objects is rarely suitable for backfill materials.
【0003】また、近年、天然資源である良質山砂の枯
渇化、その採取による環境破壊、その運搬による交通公
害および掘削土の処分問題などの観点から、埋戻し材と
して不適な掘削土や建設汚泥およびその他の不良土砂を
有効活用する動きが活発化している。In recent years, from the viewpoints of depletion of high-quality mountain sand, which is a natural resource, environmental damage due to its extraction, traffic pollution due to its transportation, and disposal problems of excavated soil, excavated soil and construction unsuitable as backfill materials. There is a growing movement to effectively utilize sludge and other bad soil.
【0004】良質の山砂などの埋戻し材を直接用いる従
来の埋戻し工法では、埋戻し後の陥没を防ぐために、埋
戻し材を埋設管周辺部などの狭隘部分にも隙間なく充填
し、ランマによる締め固めを十分に行う必要がある。し
かし、この従来法には、埋戻し材の充填やランマによる
締め固めはすべて人力作業であり、また騒音や振動を引
き起こすというような問題がある。In the conventional backfilling method in which a backfill material such as high-quality sand is directly used, the backfill material is filled in a narrow portion such as a peripheral portion of the buried pipe without any gap in order to prevent depression after backfilling. Sufficient compaction with a rammer is required. However, this conventional method has a problem in that the filling of the backfill material and the compaction by the rammer are all manual work and cause noise and vibration.
【0005】最近、上記良質の山砂などの特別な埋戻し
材を用いる代わりに、埋設物の敷設時に発生する掘削土
や安価な土砂を利用して、しかも上記のような従来法の
問題点を解決できる流動化埋戻し工法が開発され、一部
実用化されている。この工法は、掘削土や安価な土砂に
水と固化材を混合し、埋戻し材に流動性を持たせ、埋設
管周辺部などの狭隘部分にも隙間なく充填させるととも
に、固化材の作用により地山と同等以上の強度を発現し
ようというものである。Recently, instead of using a special backfill material such as the above-mentioned high quality mountain sand, excavated soil or cheap earth and sand generated when laying an embedded object is used, and the problems of the conventional method as described above. A fluidized backfilling method that can solve the problem has been developed and is partly in practical use. This method mixes water and solidified material with excavated soil and inexpensive earth and sand, gives the backfill material fluidity, fills narrow spaces around the buried pipe without gaps, and uses the effect of solidified material. It is intended to exhibit strength equal to or higher than that of the ground.
【0006】例えば、特開昭63ー233115号公
報、特開平1ー312118号公報、特開平4ー351
388号公報には、通常の土砂に水と固化材を混合し、
流動性を持たせた流動化土として埋設管などの埋戻しに
用いる工法が開示されている。[0006] For example, Japanese Patent Laid-Open Nos. 63-233115, 1-312118, and 4-351.
In Japanese Patent No. 388, water and a solidifying material are mixed with ordinary earth and sand,
A method is disclosed for backfilling buried pipes and the like as fluidized soil with fluidity.
【0007】また、特開平3ー287909号公報に
は、掘削土に予め固化材を配合混合し、この処理土を埋
戻し現場へ運搬し、埋戻しつつ処理土に注水するととも
に振動を与えて流動化して、埋戻し箇所の完全な充填を
行う工法が開示されている。Further, in Japanese Patent Laid-Open No. 3-287909, the excavated soil is mixed with a solidifying material in advance, and the treated soil is transported to the backfill site, and water is poured into the treated soil while backfilling and vibration is applied. A method of fluidizing and completely filling the backfilled portion is disclosed.
【0008】一方、ガス埋設配管工事などがその大部分
を占める都市街路の道路占有工事においては、即日交通
開放の条件下で施工することが余儀なくされており、し
たがって短時間の埋戻し作業が必須となっている。特
に、上記のような流動化埋戻し工法で行う場合は、流動
化土層打設後2時間以内に路床などの上層部の打設が可
能であることが要求されている。[0008] On the other hand, in the road occupancy work on the city streets, which occupies most of the gas burial piping work, it is unavoidable to construct it under the condition of opening the traffic on the same day, and therefore a short-term backfilling work is essential. Has become. In particular, when the fluidized backfilling method as described above is used, it is required that the upper layer portion such as the roadbed can be placed within 2 hours after the fluidized soil layer is placed.
【0009】[0009]
【発明が解決しようとする課題】しかしながら、上記の
特許公報に開示された流動化埋戻し工法では、その固化
時間が4〜5時間と長く、市街地における道路占有工事
には対応できない。However, with the fluidization backfilling method disclosed in the above-mentioned patent publication, the solidification time is as long as 4 to 5 hours, and it cannot be applied to road occupation work in urban areas.
【0010】流動化土に合わせて特殊な固化材を用いれ
ば、固化時間は短縮されるが、コスト高になり、またそ
の配合技術も複雑になるので厳しい品質管理が必要とな
る。If a special solidifying material is used in accordance with the fluidized soil, the solidifying time is shortened, but the cost is high and the compounding technique is complicated, so that strict quality control is required.
【0011】本発明は、このような課題を解決するため
になされたもので、安価な一般的配合の流動化土を用
い、しかも流動化土層打設後2時間以内で路床などの上
層部の打設が可能な埋設物の埋戻し工法を提供すること
を目的とする。The present invention has been made in order to solve the above problems, and uses inexpensive general fluidized soil having a general composition, and moreover, within 2 hours after placing the fluidized soil layer, the upper layer of a roadbed or the like. It is an object of the present invention to provide a method for backfilling a buried object that enables the placement of parts.
【0012】[0012]
【課題を解決するための手段】本発明者らが、安価な一
般的配合の流動化土を用いて短時間で埋設物の埋戻しが
可能な工法を鋭意検討した結果、ある程度固化の進んだ
流動化土層の上に盤状物を設けることにより上記課題が
解決されるという知見を見出した。Means for Solving the Problems The inventors of the present invention have earnestly studied a construction method capable of backfilling an embedded object in a short time by using an inexpensive general fluidized soil, and as a result, solidification has progressed to some extent. We have found that the above problems can be solved by providing a disc-shaped material on the fluidized soil layer.
【0013】すなわち、請求項1に記載の第1の発明
は、地表面下に埋設または構築された各種埋設物を埋戻
す埋戻し工法において、前記埋設物の周囲に流動化土か
らなる流動化土層を打設し、前記流動化土層の強度がコ
ーン指数で0.1kgf/cm 2 以上になった後、前記
流動化土層の上に前記流動化土層中に埋没しない盤状物
を設け、前記盤状物の上に路床などの上層部を打設する
ことを特徴とする埋設物の埋戻し工法である。That is, the first invention according to claim 1
Refills various buried objects buried or constructed under the ground surface
In the backfilling method, if fluidized soil is
When a fluidized soil layer consisting of
Index of 0.1 kgf / cm TwoAfter the above,
A disc-like object that is not buried in the fluidized soil layer on the fluidized soil layer
And place the upper layer part such as a roadbed on the board.
This is a backfilling method for buried objects.
【0014】流動化土層の強度がコーン指数で0.1k
gf/cm2 以上になった時点で、流動化土層上にこの
流動化土層中に埋没しない盤状物を設けると、その荷重
分散効果により流動化土層の強度が不足している場合で
も、路床などの上層部を支持できる。そのため、流動化
土層打設終了後2時間以内の短時間で流動化土層上に路
床などの上層部の打設が可能となる。流動化土層の強度
がコーン指数で0.1kgf/cm2 未満では、流動化
土層の強度が十分でないので、流動化土層上に盤状物を
設けても、上層部の打設ができない。The strength of the fluidized soil layer has a cone index of 0.1 k.
If a disc-like material that is not buried in the fluidized soil layer is provided on the fluidized soil layer at the time of gf / cm 2 or more, the strength of the fluidized soil layer is insufficient due to the load distribution effect. However, it can support the upper layers such as the roadbed. Therefore, the upper layer portion such as the roadbed can be placed on the fluidized soil layer in a short time within 2 hours after the completion of the placement of the fluidized soil layer. If the strength of the fluidized soil layer is less than 0.1 kgf / cm 2 in terms of cone index, the strength of the fluidized soil layer is not sufficient. Therefore, even if a disc-like material is provided on the fluidized soil layer, the upper layer portion cannot be placed. Can not.
【0015】請求項2に記載の第2の発明は、第1の発
明の盤状物が発泡性の軽量板であることを特徴とする第
1の発明と同様な埋設物の埋戻し工法に関するものであ
る。A second invention according to claim 2 relates to a backfilling method for buried objects similar to the first invention, characterized in that the board of the first invention is a foamable lightweight plate. It is a thing.
【0016】発泡性の軽量板を用いることにより、運
搬、加工がし易くなるので、より短時間で流動化土層上
に路床などの上層部の打設が可能となる。The use of the foamable lightweight plate facilitates transportation and processing, so that the upper layer portion such as a roadbed can be cast on the fluidized soil layer in a shorter time.
【0017】[0017]
【発明の実施の形態】図1に本発明の埋設物の埋戻し工
法の実施の形態を示す。図1で、1は流動化土層、2は
盤状物、3はガス管などの埋設物、4は路床、5は路
盤、6は舗装、7は地表面、8は土留め用鋼矢板であ
る。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an embodiment of a method for backfilling buried objects according to the present invention. In FIG. 1, 1 is a fluidized soil layer, 2 is a plate-like object, 3 is a buried object such as a gas pipe, 4 is a roadbed, 5 is a roadbed, 6 is pavement, 7 is the ground surface, 8 is steel for retaining soil It's a sheet pile.
【0018】流動化土層1の強度がコーン指数で0.1
kgf/cm2 以上になった時点で、流動化土層1上
に、流動化土層1中に埋没しない石膏ボード、ベニヤ
板、ブリキ板、厚手のビニールシートなどの盤状物2を
設けると、その荷重分散効果により流動化土層1の強度
が不足している場合でも、流動化土層打設終了後2時間
以内で流動化土層1上に路床4などの上層部の打設が可
能となる。The strength of the fluidized soil layer 1 is 0.1 in terms of cone index.
At the time of kgf / cm 2 or more, if the plasterboard, the plywood board, the tin plate, the thick vinyl sheet, or other plate-like material 2 that is not buried in the fluidized soil layer 1 is provided on the fluidized soil layer 1, Even if the strength of the fluidized soil layer 1 is insufficient due to the load distribution effect, the upper layer portion such as the roadbed 4 can be cast on the fluidized soil layer 1 within 2 hours after the completion of the fluidized soil layer casting. It will be possible.
【0019】また、盤状物2として発泡スチロールや発
泡ポリウレタンなどの発泡性の軽量板を用いると、その
運搬、加工が容易となるので、より短時間で流動化土層
1上に路床4などの上層部の打設が可能となる。If a foamable lightweight plate such as expanded polystyrene or expanded polyurethane is used as the board 2, it can be easily transported and processed, so that the subgrade 4 or the like is formed on the fluidized soil layer 1 in a shorter time. It is possible to set the upper layer part.
【0020】[0020]
(実施例1)地表面下にガス管を配設後、ガス管周囲に
安価な土砂に水と固化材を混合した表1に示す一般的配
合の流動化土を充填し、流動化土層を打設した。この流
動化土層の強度がコーン指数で0.7kgf/cm2 と
なったところで、流動化土層の上に9mmの石膏ボード
を敷設した。次いで、この石膏ボード上に路床材である
土砂を投入しランマにて締め固め、その上に舗装を構築
した。このとき、流動化土層の打設終了から路床材投入
までの時間は2時間であり、従来の施工時間4〜5時間
に比べ大幅に短縮できた。(Example 1) After arranging a gas pipe below the ground surface, fluidized soil having a general composition shown in Table 1 in which water and solidifying material are mixed with inexpensive earth and sand is filled around the gas pipe to form a fluidized soil layer. Was placed. When the strength of this fluidized soil layer reached 0.7 kgf / cm 2 in terms of cone index, a 9 mm gypsum board was laid on the fluidized soil layer. Then, earth and sand as a roadbed material were put on this gypsum board and compacted by a rammer, and a pavement was constructed on it. At this time, the time from the completion of pouring the fluidized soil layer to the introduction of the roadbed material was 2 hours, which was significantly shorter than the conventional construction time of 4 to 5 hours.
【0021】[0021]
【表1】 [Table 1]
【0022】(実施例2)地表面下にガス管を配設後、
ガス管周囲に実施例1と同様な流動化土を充填し、流動
化土層を打設した。この流動化土層の強度がコーン指数
で0.5kgf/cm2 となったところで、流動化土層
の上に30mmの発泡ポリウレタンシートを敷設した。
次いで、この発泡ポリウレタンシート上に路床材である
土砂を投入しランマにて締め固め、その上に舗装を構築
した。このとき、流動化土層の打設終了から路床材投入
までの時間は1時間40分であり、従来の施工時間に比
べ大幅に短縮できた。(Example 2) After arranging a gas pipe below the ground surface,
The same fluidized soil as in Example 1 was filled around the gas pipe, and a fluidized soil layer was placed. When the strength of the fluidized soil layer reached 0.5 kgf / cm 2 in terms of cone index, a 30 mm foamed polyurethane sheet was laid on the fluidized soil layer.
Next, earth and sand as a roadbed material was put on the foamed polyurethane sheet and compacted by a rammer, and a pavement was constructed on it. At this time, the time from the completion of pouring the fluidized soil layer to the introduction of the roadbed material was 1 hour and 40 minutes, which was significantly shorter than the conventional construction time.
【0023】(実施例3)地表面下に通信ケーブルを配
設後、通信ケーブル周囲に実施例1と同様な流動化土を
充填し、流動化土層を打設した。この流動化土層の強度
がコーン指数で0.2kgf/cm2 となったところ
で、流動化土層の上に30mmの発泡スチロール板を敷
設した。次いで、この発泡スチロール板上に路床材であ
る土砂を投入しランマにて締め固め、その上に舗装を構
築した。このとき、流動化土層の打設終了から路床材投
入までの時間は1時間10分であり、従来の施工時間に
比べ大幅に短縮できた。(Example 3) After arranging the communication cable under the ground surface, the same fluidized soil as in Example 1 was filled around the communication cable, and a fluidized soil layer was cast. When the strength of this fluidized soil layer reached a cone index of 0.2 kgf / cm 2 , a 30 mm styrofoam plate was laid on the fluidized soil layer. Next, earth and sand as a roadbed material was put on the styrofoam plate and compacted by a rammer, and a pavement was constructed on it. At this time, the time from the completion of the pouring of the fluidized soil layer to the introduction of the roadbed material was 1 hour and 10 minutes, which was significantly shorter than the conventional construction time.
【0024】[0024]
【発明の効果】本発明は以上説明したように構成されて
いるので、安価な一般的配合の流動化土を用いても、流
動化土層打設終了後2時間以内で路床などの上層部の打
設が可能な埋設物の埋戻し工法を提供することができ
る。EFFECTS OF THE INVENTION Since the present invention is constructed as described above, even if an inexpensive fluidized soil having a general composition is used, the upper layer of a roadbed or the like can be formed within 2 hours after the completion of placing the fluidized soil layer. It is possible to provide a method for backfilling a buried object in which a part can be placed.
【0025】また、本発明である埋戻し工法を用いれ
ば、流動化土層全体が完全に固化する前に、埋戻し工事
を完了できるため、土留め用鋼矢板の引抜きが容易に行
え、しかも鋼矢板の引抜き後に、流動化土層と地山との
間には空隙が生じることがないので、地盤低下も全く発
生しない。Further, when the backfilling method of the present invention is used, the backfilling work can be completed before the entire fluidized soil layer is completely solidified, so that the steel sheet pile for retaining soil can be easily pulled out, and After drawing the steel sheet pile, there is no gap between the fluidized soil layer and the ground, so no ground deterioration occurs.
【図1】本発明の埋設物の埋戻し工法の実施の形態を示
す図である。FIG. 1 is a view showing an embodiment of a method for backfilling a buried object according to the present invention.
1 流動化土層 2 盤状物 3 ガス管などの埋設物 4 路床 5 路盤 6 舗装 7 地表面 8 土留め用鋼矢板 1 Fluidized soil layer 2 Board-like objects 3 Buried objects such as gas pipes 4 Roadbed 5 Roadbed 6 Pavement 7 Ground surface 8 Steel sheet pile for retaining soil
───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 F16L 1/024 ─────────────────────────────────────────────────── ─── Continuation of the front page (51) Int.Cl. 6 Identification code Internal reference number FI technical display location F16L 1/024
Claims (2)
設物を埋戻す埋戻し工法において、前記埋設物の周囲に
流動化土からなる流動化土層を打設し、前記流動化土層
の強度がコーン指数で0.1kgf/cm2 以上になっ
た後、前記流動化土層の上に前記流動化土層中に埋没し
ない盤状物を設け、前記盤状物の上に路床などの上層部
を打設することを特徴とする埋設物の埋戻し工法。1. In a backfilling method for backfilling various buried objects buried or constructed under the ground surface, a fluidized soil layer made of fluidized soil is cast around the buried object, and the fluidized soil layer is formed. After the strength of corn index becomes 0.1 kgf / cm 2 or more, a disc-like material which is not buried in the fluidized soil layer is provided on the fluidized soil layer, and a subgrade is provided on the disc-shaped object. A method of backfilling buried objects, characterized by placing the upper layer of
を特徴とする請求項1に記載の埋設物の埋戻し工法。2. The backfilling method for the buried object according to claim 1, wherein the plate-shaped object is a foamable lightweight plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7180273A JPH0931951A (en) | 1995-07-17 | 1995-07-17 | Backfilling method for buried objects |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7180273A JPH0931951A (en) | 1995-07-17 | 1995-07-17 | Backfilling method for buried objects |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0931951A true JPH0931951A (en) | 1997-02-04 |
Family
ID=16080351
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7180273A Withdrawn JPH0931951A (en) | 1995-07-17 | 1995-07-17 | Backfilling method for buried objects |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0931951A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112064751A (en) * | 2020-08-08 | 2020-12-11 | 上海静安市政工程有限公司 | Deep groove construction method for drainage pipeline |
-
1995
- 1995-07-17 JP JP7180273A patent/JPH0931951A/en not_active Withdrawn
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112064751A (en) * | 2020-08-08 | 2020-12-11 | 上海静安市政工程有限公司 | Deep groove construction method for drainage pipeline |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109056798A (en) | Under a kind of urban road in deep basal pit contrary sequence method top plate bevelling construction method | |
CA2224277C (en) | Method of filling an excavated opening | |
JPH10140507A (en) | Fluidization treatment method | |
JPH0931951A (en) | Backfilling method for buried objects | |
JPH06344328A (en) | Fast-curing fluidized threaded soil and rapid construction of roadbed/road body using the same | |
KR102778342B1 (en) | Construction method for tunnel of slope | |
JP3230147B2 (en) | Fluidized soil construction structure and its construction method | |
JP3881916B2 (en) | Method for reducing settlement of soft ground | |
JP3664526B2 (en) | Burial backfilling method | |
CN210797245U (en) | Structure is backfilled to bridgehead abutment back of body | |
JPH0932969A (en) | Backfilling method for buried objects | |
JP3545641B2 (en) | Backfill method | |
JPH0995949A (en) | Burial pipe backfill method | |
JP2736299B2 (en) | How to backfill a trench | |
JP3341541B2 (en) | Backfilling method for buried objects | |
JP2004125100A (en) | Construction method for burying pipe | |
JPH10195853A (en) | Backfilling method for buried objects | |
JP2000080602A (en) | Filling method of extended ground | |
JPH1150438A (en) | Fluidized backfill method for buried objects | |
JPH0971967A (en) | Backfilling method for buried objects | |
JP3454332B2 (en) | Groove backfill method | |
JP3769521B2 (en) | Civil engineering groundwork, civil engineering methods using this civil engineering groundwork | |
JPH0931953A (en) | Backfilling method for buried objects | |
JPH03168489A (en) | Burying method of buried pipe | |
JPH11210929A (en) | Fluidized backfill method for buried objects |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20021001 |