JP2885199B2 - Underground burial method for pipelines - Google Patents

Underground burial method for pipelines

Info

Publication number
JP2885199B2
JP2885199B2 JP8250214A JP25021496A JP2885199B2 JP 2885199 B2 JP2885199 B2 JP 2885199B2 JP 8250214 A JP8250214 A JP 8250214A JP 25021496 A JP25021496 A JP 25021496A JP 2885199 B2 JP2885199 B2 JP 2885199B2
Authority
JP
Japan
Prior art keywords
soil
block
underground
excavated
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP8250214A
Other languages
Japanese (ja)
Other versions
JPH09105123A (en
Inventor
武 川地
博 久保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OOBAYASHIGUMI KK
Original Assignee
OOBAYASHIGUMI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OOBAYASHIGUMI KK filed Critical OOBAYASHIGUMI KK
Priority to JP8250214A priority Critical patent/JP2885199B2/en
Publication of JPH09105123A publication Critical patent/JPH09105123A/en
Application granted granted Critical
Publication of JP2885199B2 publication Critical patent/JP2885199B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、管路の地下埋設
工法に関し、特に、ガス・電気・水道などの各種の管の
周囲地盤の掘削により生じた掘削残土を用いた管路の地
下埋設工法に関する。
TECHNICAL FIELD The present invention relates to underground <br/> method in line, in particular, the conduit using the drilling waste soil caused by excavation of the surrounding ground of the various tubes, such as gas, electricity and water Land of
It relates to the lower burial method.

【0002】[0002]

【従来の技術】近時、ビル地下室,地下鉄,地下道,地
下街,地下駐車場など地下空間の利用が非常に高まって
いる。これらの地下工事では、膨大な量の掘削残土が発
生し、その処理が社会的問題として取り上げられてい
る。この種の地下工事では、基本的に地下空間を創成す
るものであるから、掘削残土は不要なものであり、これ
をまったく発生させないで地下空間を創成することはで
きない。掘削残土の利用方法として、地下工事で作られ
た構造物と掘削部との間隙を埋め戻す土砂として用いる
ことが従来から行われている。
2. Description of the Related Art In recent years, the use of underground spaces such as basements of buildings, subways, underpasses, underground shopping malls, and underground parking lots has been extremely increasing. In these underground works, a huge amount of excavated soil is generated, and its disposal is taken up as a social problem. In this kind of underground construction, since an underground space is basically created, excavated soil is unnecessary, and it is impossible to create an underground space without generating it. As a method of using the excavated soil, it has been conventionally used as earth and sand to fill a gap between a structure made by underground construction and an excavated portion.

【0003】掘削残土を埋め戻しに用いる方法として
は、残土をそのまま埋め戻し土として利用する方法、
掘削残土に生石灰やセメントなどの結合材を添加して
混合し、残土を塑性状態に改良して埋め戻し土として利
用する方法、残土に比較的多量の水と、硬化に必要な
量のセメントなどを添加して、硬化性を有する残土スラ
リーに改質して埋め戻し土として利用する方法が知られ
ている。
[0003] As a method of using the excavated surplus soil for backfilling, there are methods of using the surplus soil as backfill soil as it is,
A method in which a binder such as quicklime or cement is added to and mixed with the excavated surplus soil, and the surplus soil is improved to a plastic state and used as backfill soil. There is known a method in which a slurry is added to the slurry to modify it into a hardenable residual soil slurry and use it as backfill soil.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、これら
の方法を用いて管路を埋め戻すには、いずれも以下に説
明する技術的課題があった。
However, backfilling pipes using these methods has the following technical problems.

【0005】すなわち、上記の方法では、残土の性状
が良好で、例えば、山砂と同質の土が発生した際しか採
用することができず、このような良質の土は限られてい
るので、利用できる量が少い。また、良質な残土がどの
時点にどれだけ発生するかは予想が困難で、工事計画が
立てられないという問題もある。さらに、埋め戻し土
は、一般に数ケ月程度ストックする必要があるが、この
際に、広い面積を占め、工事に支障を及ぼすこともあ
る。
[0005] That is, in the above method, the properties of the remaining soil are good and can be adopted only when, for example, soil of the same quality as mountain sand is generated, and such high-quality soil is limited. Available amount is small. In addition, it is difficult to predict how much good soil will be generated at which point in time, and there is also a problem that a construction plan cannot be made. In addition, backfill soil generally needs to be stocked for several months, but at this time, it occupies a large area and may hinder construction work.

【0006】一方、の方法では、土質改良した埋め戻
し土の性状は、ドライ状で、特に粘土質の土では、硬い
団粒ができ、ボソボソの状態に近くなる。このような状
態の土は、埋め戻しの際に機械により転圧して十分に締
固めなければ、強度がでないだけでなく、沈下や陥没の
原因となる。また、管路は、一般に狭いので、転圧機を
乗り入れることが困難である。仮に、転圧が可能な場合
であっても、埋戻し土を転圧すると管に横方向の力、振
動が加わるので破損のおそれがある。加えて、管が破損
しないように慎重に転圧作業をしなければならず、工期
の増大をもたらす。さらにまた、ボソボソ状の改良土
は、間隙が多く、かさ張り、運搬効率が悪く、ストック
の際に広い場所が必要になる。
[0006] On the other hand, in the first method, the properties of the backfill soil improved in soil quality are dry, and particularly in the case of clayey soil, hard aggregates are formed, and the state is close to the state of lumps. If the soil in such a state is not sufficiently compacted by rolling by a machine at the time of backfilling, not only the strength is deteriorated, but also the settlement or the sinking is caused. In addition, since the pipeline is generally narrow, it is difficult to mount the compactor. Even if rolling is possible, if the backfill soil is rolled, lateral force and vibration are applied to the pipe, and there is a risk of breakage. In addition, the rolling operation must be performed carefully so as not to damage the pipe, which leads to an increase in the construction period. Furthermore, the loose-shaped improved soil has many gaps, is bulky, has poor transportation efficiency, and requires a large space for stocking.

【0007】他方、の方法では、残土スラリーは、施
工の際に飛散して汚れるだけでなく、比較的多量の水を
添加するので、所定の強度まで固化させるのに必要なセ
メント量が多くなる。また、スラリー状なので、初期強
度が非常に小さく、その後も徐々に強度が増大するの
で、工期が長くなり、道路工事のように早急に埋め戻す
必要がある場合には問題がある。残土スラリーは、適切
な流動性を保つ必要があるが、このためには掘削残土の
性状に応じて水分量などを調整しなければならず、その
管理が非常に面倒であった。
[0007] On the other hand, in the other method, the residual soil slurry is not only scattered and soiled at the time of construction, but also a relatively large amount of water is added, so that the amount of cement required to solidify to a predetermined strength increases. . In addition, since the slurry is in the form of a slurry, its initial strength is very low, and the strength gradually increases thereafter. Therefore, the construction period is prolonged, and there is a problem in the case where it is necessary to refill immediately as in the case of road construction. It is necessary to maintain appropriate fluidity of the residual soil slurry, but for this purpose, the amount of water and the like must be adjusted according to the properties of the excavated residual soil, and its management is very troublesome.

【0008】この発明は以上の欠点に鑑みなされたもの
であって、その目的とするところは、ストック時や運搬
時に広い面積を必要とせず、比較的大きい初期強度を有
し、施工現場で締固める必要もなく、施工の工期が短縮
できる管路の地下埋設工法を提供することにある。
The present invention has been made in view of the above-mentioned drawbacks, and has as its object the purpose of the present invention which does not require a large area at the time of stocking and transportation, has a relatively large initial strength, and is fastened at a construction site. It is an object of the present invention to provide a method of burying pipes underground , which does not need to be solidified and can shorten the construction period.

【0009】[0009]

【課題を解決するための手段】前記目的を達成するた
め、この発明は、予定される管路の周囲地盤を掘削し、
掘削により生じた掘削残土と消却灰およびベントナイ
ト、カオリンなどの粘土とを混合してブロックを加圧成
形し、得られたブロックを掘削孔の底部に設置し、該ブ
ロックの上に管路を載置し、の周囲に前記ブロック
を積載することを特徴とする(請求項1)。
SUMMARY OF THE INVENTION In order to achieve the above object, the present invention excavates ground around a scheduled pipeline ,
The excavated soil generated by excavation is mixed with the ashes, as well as clay such as bentonite and kaolin to form a block under pressure, and the obtained block is placed at the bottom of the drilling hole.
The conduit is placed on the lock, the block around the conduit
The characterized in that the loading (claim 1).

【0010】ここで、本発明においては、ブロック化す
る掘削残土は、その性状はとわないが、例えば、粘土分
の多い土砂、砂質土、礫質土などが使用される。ただ
し、礫の粒径が余り大きい(2〜3cm以上)と、加圧成
形が困難になるので、前記数値以下が望ましい。また、
掘削残土と焼却灰およびベントナイト,カオリンなどの
粘土とが混合されているので、ブロック化したときの性
状、強度,密度,耐水性,遮水性などが向上する。加圧
圧力としては、5〜100kgf /cm2 程度が望ましい。
[0010] In the present invention, the properties of the excavated soil to be blocked are not limited, but, for example, earth and sand, sandy soil, gravel soil, etc., having a high clay content are used. However, if the particle size of the gravel is too large (2 to 3 cm or more), it becomes difficult to perform pressure molding. Also,
Since the excavated soil and incineration ash and clay such as bentonite and kaolin are mixed, the properties, strength, density, water resistance, water shielding and the like when blocked are improved. The pressure is preferably about 5 to 100 kgf / cm2.

【0011】また、掘削残土をブロック化する際に、石
灰系(消石灰,生石灰)、セメント系(普通ポルトラン
ドセメント,早強ポルトランドセメント,高炉セメン
ト,フライアッシュ,その他の特殊セメント)、石膏、
高炉水滓スラグ粉末、アスファルト、水ガラス天然高分
子、合成高分子など硬化性を有する材料(結合材)を単
独あるいは2以上組合せて添加混合した状態で加圧して
も良い(請求項2)。
When the excavated soil is blocked, lime-based (slaked lime, quicklime), cement (ordinary Portland cement, early-strength Portland cement, blast furnace cement, fly ash, other special cement), gypsum,
Pressurization may be carried out in a state where a curable material (binder) such as blast furnace slag slag powder, asphalt, water glass natural polymer, or synthetic polymer is added alone or in combination of two or more (claim 2).

【0012】さらに、掘削残土をブロック化する際に、
綿,パルプ,麻,羊毛なとの天然繊維、ポリエチレン,
ポリプロピレン,アクリルなどの合成繊維、炭素繊維、
ガラス繊維、金属繊維などの各種の繊維を単独ないしは
2以上組合せて添加しても良い。繊維の太さは、直径数
μm 程度の極細から1〜2mmという極太まで使用でき、
単繊維でも撚繊維でも良い。繊維の長さは、5mm程度か
ら5cm程度までが使用される。一般には、繊維長さが
2cm程度以上になると混合する際に繊維が絡まってダ
ンゴ状になるので、この長さ以下の方が望ましい。
Further, when the excavated soil is blocked,
Cotton, pulp, hemp, wool and other natural fibers, polyethylene,
Synthetic fiber such as polypropylene and acrylic, carbon fiber,
Various fibers such as glass fibers and metal fibers may be added alone or in combination of two or more. The thickness of the fiber can be used from a very small diameter of about several μm to a very thick of 1-2 mm.
A single fiber or a twisted fiber may be used. The length of the fiber is about 5 mm to about 5 cm. Generally, when the fiber length is about 2 cm or more, the fibers become entangled and become dango-like when mixed, so that the length is desirably less than this length.

【0013】ブロックの大きさとしては、埋め戻す個所
や機能を考慮した各種の形状が採用され、小さいもので
レンガ程度、大きいもので1m角程度までが推奨され
る。埋め戻し個所を再掘削する予定がある場合には、取
出しが容易になるように、例えば、吊り金具付きのもの
も採用できる。埋め戻し部分に求められる機能によって
は、ブロックを単に縦横に積載するが、ブロックの固
定,遮水性が必要な場合には、ブロック間にモルタルな
どの目詰め材を充填すれば良い(請求項3)。
As the size of the block, various shapes are adopted in consideration of the places and functions to be buried, and it is recommended that the size of the block is about a brick for a small one and about 1 m square for a large one. If the backfill location is to be re-excavated, for example, one with a hanger may be employed to facilitate removal. Depending on the function required for the backfill portion, the blocks are simply stacked vertically and horizontally, but if fixing and water-blocking of the blocks are required, a plugging material such as mortar may be filled between the blocks. ).

【0014】本発明の実施では、ブロック化した掘削残
土のみで埋め戻すが、必要に応じて他の材料、例えば、
砂(購入したものを含む)、粘土、モルタル、コンクリ
―ト廃材、上述したものを任意に組合せて用いることも
可能である。
In the practice of the present invention, backfilling is performed only with the excavated soil remaining in the block, but other materials, for example,
Sand (including purchased), clay, mortar, concrete waste, and any of the above can be used in any combination.

【0015】[0015]

【0016】以上の構成の管路の地下埋設工法において
は、掘削残土は、加圧されてブロック化されるので、そ
の強度が増すとともに、密度,耐水性,遮水性なども向
上する。
In the underground burial method for a pipeline having the above-described structure, the excavated soil is pressurized and blocked, so that its strength is increased and the density, water resistance, water shielding and the like are also improved.

【0017】以下に本発明の好適な実施例について添付
図面に基づいて説明する。図1は本発明にかかる管路
地下埋設工法の実施例を示している。管路の地下埋設工
事では、まず図1(A)に示すように、路面舗装12が
切断され、路床14を所定深度までほぼ垂直に掘削し
て、凹状の掘削孔16が形成される。この時発生した掘
削残土は、工事現場に隣接設置されたブロック製造プラ
ント18まで運搬され、加圧されてブロック20に加圧
成形される。
Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. Figure 1 is a pipe according to the present invention
1 shows an embodiment of an underground burial method. In the underground burial work of a pipeline, first, as shown in FIG. 1A, the road surface pavement 12 is cut, and the subgrade 14 is excavated almost vertically to a predetermined depth to form a concave excavation hole 16. The excavated residual soil generated at this time is transported to a block manufacturing plant 18 installed adjacent to the construction site, where it is pressurized and formed into a block 20.

【0018】この加圧成形の際に、必要に応じて前述し
たように粘土や結合材が添加混合される。そして、この
実施例では、まず、掘削孔16の底部(敷設される管の
下方)に複数のブロック20が設置される。次いで、ブ
ロック20上に管10が載置され、その外周の空間に、
管10の側方、管10の上方の順に多数のブロック20
が縦横に積載され、掘削孔16が埋め戻される。このと
き、必要に応じてブロック20間にモルタルなどの目詰
め材が充填される。掘削孔16内にブロック20が積載
されると、路面舗装12を再び施して、図1(C)に示
すように、工事が完了する。
At the time of this pressure molding, clay and a binder are added and mixed as necessary, as described above. Then, in this embodiment, first, a plurality of blocks 20 are installed at the bottom of the drilling hole 16 (below the pipe to be laid). Next, the tube 10 is placed on the block 20, and in the space around the tube 10,
A number of blocks 20 are arranged on the side of the tube 10 and above the tube 10.
Are loaded vertically and horizontally, and the borehole 16 is backfilled. At this time, a plugging material such as mortar is filled between the blocks 20 as needed. When the block 20 is loaded in the excavation hole 16, the road surface pavement 12 is applied again, and the construction is completed as shown in FIG.

【0019】[0019]

【発明の効果】以上、発明の実施形態によって詳細に説
明したように、この発明にかかる管路の地下埋設工法に
よれば、管路地盤の掘削により生じた掘削残土と焼却灰
およびベントナイト,カオリンなどの粘土とを混合して
ブロックを加圧成形し、得られたブロックにより管の周
囲を埋め戻すので、各種の掘削残土に適用できるととも
に、ブロックは、強度,密度,耐水性,遮水性が高くな
っているので、品質が安定していて、運搬効率,ストッ
ク性に優れ、掘削残土の利用率も高くなる。また、ブロ
ックは、スラリーに比べて大きな初期強度を有している
ので、管路工事に好適であるとともに、養生時間や転圧
も必要でなく、管の損傷や変形を抑えることができると
ともに、工期の大幅な短縮が可能になる。さらに、再掘
削を行う場合には、ブロックの取出しだけで済み、しか
も、取出したブロックの再利用ができる
As described above in detail with the embodiments of the present invention, according to the underground pipe burying method according to the present invention, excavated residual soil, incinerated ash, bentonite, kaolin The block is press-molded by mixing with clay, etc., and the surrounding area of the pipe is backfilled with the obtained block, so that it can be applied to various types of excavated soil, and the block has sufficient strength, density, water resistance, and water shielding. Because of the high quality, the quality is stable, the transportation efficiency and stocking are excellent, and the utilization rate of excavated soil is high. In addition, since the block has a higher initial strength than the slurry, it is suitable for pipeline construction, requires no curing time or rolling pressure, and can suppress damage and deformation of the pipe, The construction period can be significantly reduced. Furthermore, when performing re-digging, it is only necessary to take out the blocks, and the taken-out blocks can be reused .

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかる管路の地下埋設工法の実施例を
工程順に示す説明図である。
FIG. 1 is an explanatory view showing an embodiment of a method of burying a pipe underground according to the present invention in the order of steps.

【符号の説明】[Explanation of symbols]

10 管 12 路面舗装 14 路床 16 掘削孔 18 ブロック製造プラント 20 ブロック DESCRIPTION OF SYMBOLS 10 Pipe 12 Road surface pavement 14 Subgrade 16 Drilling hole 18 Block manufacturing plant 20 Block

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E02F 7/00 F16L 1/024 F16L 1/038 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 6 , DB name) E02F 7/00 F16L 1/024 F16L 1/038

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 予定される管路の周囲地盤を掘削し、
削により生じた掘削残土と消却灰およびベントナイト、
カオリンなどの粘土とを混合してブロックを加圧成形
し、得られたブロックを掘削孔の底部に設置し、該ブロ
ックの上に管路を載置し、の周囲に前記ブロックを
積載することを特徴とする管路の地下埋設工法。
(1) excavating ground surrounding a planned pipeline, excavated soil, extinguished ash and bentonite produced by excavation;
The block is mixed with clay such as kaolin to form a block under pressure, and the obtained block is placed at the bottom of a borehole.
The conduit is placed on the click, the block around the conduit
Underground burial method of pipeline characterized by loading .
【請求項2】 前記ブロックは、前記掘削残土に結合材
を混合して加圧成形されることを特徴とする請求項1に
記載の管路の地下埋設工法。
Wherein said block is underground construction method of the conduit according to claim 1, characterized in that the mixture to pressure molding the binder to the excavated residual soil.
【請求項3】 前記ブロックは、前記掘削個所に縦横に
積載され、各ブロック間にモルタルなどの目詰め材を充
填することを特徴とする請求項1または2に記載の管路
の地下埋設工法。
3. The pipeline according to claim 1, wherein the blocks are stacked vertically and horizontally at the excavation point, and a filling material such as mortar is filled between the blocks.
Underground burial method.
JP8250214A 1996-09-20 1996-09-20 Underground burial method for pipelines Expired - Lifetime JP2885199B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8250214A JP2885199B2 (en) 1996-09-20 1996-09-20 Underground burial method for pipelines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8250214A JP2885199B2 (en) 1996-09-20 1996-09-20 Underground burial method for pipelines

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP3095003A Division JP2611564B2 (en) 1991-04-02 1991-04-02 Backfill method

Publications (2)

Publication Number Publication Date
JPH09105123A JPH09105123A (en) 1997-04-22
JP2885199B2 true JP2885199B2 (en) 1999-04-19

Family

ID=17204532

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8250214A Expired - Lifetime JP2885199B2 (en) 1996-09-20 1996-09-20 Underground burial method for pipelines

Country Status (1)

Country Link
JP (1) JP2885199B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100365957B1 (en) * 1999-12-30 2003-02-07 한국후라이애쉬시멘트공업(주) Method of filling a pipe line with bottom ash

Also Published As

Publication number Publication date
JPH09105123A (en) 1997-04-22

Similar Documents

Publication Publication Date Title
Patel Geotechnical investigations and improvement of ground conditions
CN110273424A (en) A kind of construction method of yard piping
JP2885199B2 (en) Underground burial method for pipelines
CN110344439A (en) A kind of construction method of rear-mounted retaining wall drain hole
JP2611564B2 (en) Backfill method
KR20100030293A (en) Method for laying pipes under the ground
CN114251051A (en) Subway tunnel construction process
CN102182867B (en) Method for laying ore pulp pipelines in quicksand bed section
JP3230147B2 (en) Fluidized soil construction structure and its construction method
JPH01312118A (en) Strength-applied backfilled material and backfilling construction with its material
CN216194920U (en) Large immersed tube tunnel backfill structure with seismic isolation performance
CN216999114U (en) Road is reformed transform and is expanded high fill road bed widening section mosaic structure
JP5274776B2 (en) Construction method of artificial soil material consisting of construction by-products
JP3341541B2 (en) Backfilling method for buried objects
Lee et al. Cost comparison of pipeline asset replacement: Open-cut and pipe-bursting
JP2001354960A (en) Method for utilizing construction surplus soil
JP2004183364A (en) Underground continuous cut off wall structure in land
Huber Coquitlam Lake water tunnel upgrading—design and construction, a case history
KR0167035B1 (en) Method of laying hume pipes
CN102535315B (en) Treatment method for suspending concrete pavement slab
JPH10120453A (en) Artificial coagulating material
JP3664526B2 (en) Burial backfilling method
JP2003221825A (en) Work execution method for foundation ground
KR20230089079A (en) Method for installing underground transmission line using industrial by-product backfill material
CN115288197A (en) Construction method of prefabricated inspection well