JPH0947806A - Roll shop - Google Patents

Roll shop

Info

Publication number
JPH0947806A
JPH0947806A JP20212395A JP20212395A JPH0947806A JP H0947806 A JPH0947806 A JP H0947806A JP 20212395 A JP20212395 A JP 20212395A JP 20212395 A JP20212395 A JP 20212395A JP H0947806 A JPH0947806 A JP H0947806A
Authority
JP
Japan
Prior art keywords
roll
guide rail
pull
carriage
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20212395A
Other languages
Japanese (ja)
Other versions
JP3644082B2 (en
Inventor
Hiroo Sakuma
博郎 佐久間
Mikio Soya
幹雄 曽家
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP20212395A priority Critical patent/JP3644082B2/en
Publication of JPH0947806A publication Critical patent/JPH0947806A/en
Application granted granted Critical
Publication of JP3644082B2 publication Critical patent/JP3644082B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Grinding Of Cylindrical And Plane Surfaces (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve working rate of maintaining devices by shortening a time required for replacing rolls which are placed on the maintaining devices such as roll grinders. SOLUTION: Pulling-in guide rails 8b for roll grinders are formed so that three roll sets 13 are longitudinally placed. During regenerating process is executed by the roll grinder 10, the roll set 13 to which maintaining process is next executed is carried by a traverse truck 14 and placed in the inlet-side position A on this side of the pulling-in guide rails 8b. Next, this roll set is pulled in by the pulling-in device 17, moved to the anti-inlet-side position C on the farthest side of the pulling-in guide rails 8b and stood by here. When regenerating process by the roll grinder 10 is completed, the roll set 13 after regeneration is place din the loading position B between the inlet-side position A and anti-inlet side position C by a loading device 21, this set is moved to the inlet-side position A by the pulling-in device 17 and also the roll set 13 in the anti-inlet-side position C is moved to the loading position B and the roll set 13 in the loading position B is placed on the roll grinder 10 and the regenerating process is executed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、圧延作業の基本と
なるロール,チョック等の整備を行うロールショップに
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a roll shop for servicing rolls, chocks, etc., which are the basis of rolling work.

【0002】[0002]

【従来の技術】従来、ロールショップのロール搬送方法
としては、例えば、特開平5−111705号公報,特
開平5−111706号公報,特開平5−111707
号公報に記載されたロールショップが知られている。こ
れら公報においては、位置決め時間のかかるクレーン搬
送によるロール,或いはチョックの搬送を回避するため
に、ロール,チョック等を車輪が配設された台車に積載
し、これをガイドレールに沿って移動させることによっ
て搬送するようにしている。
2. Description of the Related Art Conventionally, as a roll conveying method of a roll shop, for example, JP-A-5-111705, JP-A-5-111706, and JP-A-5-111707.
A roll shop described in Japanese Patent Publication is known. In these publications, in order to avoid roll or chock transport by crane transport that requires positioning time, rolls, chock, etc. are loaded on a trolley provided with wheels and moved along a guide rail. I am trying to carry it.

【0003】そして、例えば、ミルヤード内ではロール
或いはチョックを案内ガイドレールに沿って走行させて
ミルヤードの搬入出口まで搬送する。そして、予めロー
ルショップ内には、案内ガイドレールと直角な方向に移
動可能な横行台車を配置し、さらに、横行台車を挟んで
案内ガイドレールと平行に引き込みガイドレールを敷設
し、この引き込みガイドレールの脇に、例えば、ロール
グラインダ,ロール保管ラック等のメンテナンス装置を
配設しておく。そして、ミルヤードの搬入出口まで搬送
されたロール,チョック等を台車ごと横行台車上に積載
し、横行台車を案内ガイドレールと直角方向に移動さ
せ、所望とするメンテナンス装置に対応する引き込みガ
イドレールに対向する位置まで、ロール,チョック等を
搬送する。
Then, for example, in the mill yard, a roll or chock is run along the guide rails and is transported to the loading / unloading port of the mill yard. Then, in the roll shop, a transverse carriage that can move in a direction perpendicular to the guide rail is arranged in advance, and a pull-in guide rail is laid parallel to the guide rail with the transverse carriage interposed therebetween. A maintenance device such as a roll grinder or a roll storage rack is arranged beside the side of the. Then, the rolls, chocks, etc. transported to the loading / unloading port of the mill yard are loaded on the traverse carriage together with the carriage, and the traverse carriage is moved in the direction perpendicular to the guide guide rail to face the pull-in guide rail corresponding to the desired maintenance device. The rolls, chocks, etc. are transported to the desired position.

【0004】そして、所定の位置まで移動したときに、
横行台車上のロール,チョック等を引き込みガイドレー
ル上に移載し、メンテナンス装置に積載可能な所定の位
置までロール,チョックを引き込みガイドレールに沿っ
て移動させ、その後、所定のメンテナンス装置に載置す
るようになっている。
Then, when it moves to a predetermined position,
Rolls, chocks, etc. on the traverse trolley are transferred onto the guide rails, moved to a predetermined position where they can be loaded on the maintenance device, moved along the guide rails, and then placed on the specified maintenance device. It is supposed to do.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記従
来のロールショップにおいては、例えば、ロールグライ
ンダ上のロールに対してメンテナンス処理が終了し、ロ
ールの入れ替えを行う場合等には、ロールグラインダ上
のロールを引き込みガイドレール上に載置し、この引き
込みガイドレール上の再生処理後のロールを横行台車上
に載置して、例えば、ロール保管ラックに対応する引き
込みガイドレールに対向する位置まで搬送し、横行台車
上のロールをロール保管ラックの引き込みガイドレール
上に移載した後、次に再生処理を行う別のロールが載置
されている引き込みガイドレールに対向する位置まで横
行台車を移動させて、このロールを横行台車上に載置
し、再度ロールグラインダに対応する引き込みガイドレ
ールに対向する位置まで横行台車を移動させ、前述と同
様に、ロールをロールグラインダに対応する引き込みガ
イドレール上に引き込んで、ロールをロールグラインダ
上に設置するようになっている。
However, in the above-mentioned conventional roll shop, for example, when the rolls on the roll grinder have been subjected to the maintenance process and the rolls have been replaced, the rolls on the roll grinder can be replaced. Is placed on the pull-in guide rail, the roll after the regeneration treatment on this pull-in guide rail is placed on the traverse trolley, and, for example, it is conveyed to a position facing the pull-in guide rail corresponding to the roll storage rack, After transferring the roll on the traverse trolley to the pull-in guide rail of the roll storage rack, move the traverse trolley to a position facing the pull-in guide rail on which another roll to be regenerated next is placed, Place this roll on the traverse trolley and position it again facing the pull-in guide rail corresponding to the roll grinder. In moving the transverse trolley, in the same manner as described above, draw on the pull guide rails corresponding roles to roll grinder, so as to install the roll on the roll grinder.

【0006】そのため、ロールグラインダで再生処理す
るロールの入れ替えを行うためには、横行台車がロール
グラインダとロール保管ラックとの間を往復しなければ
ならず、横行台車の移動時間がかかるため、ロールグラ
インダでのロールの入れ替えに時間がかかってしまうと
いう問題がある。また、ロール入れ替えに時間がかかる
ことから、その間、ロールグラインダは空き状態となっ
てしまい、ロールグラインダの稼働効率が悪いという未
解決の課題もある。
Therefore, in order to replace the rolls to be regenerated by the roll grinder, the traverse carriage must reciprocate between the roll grinder and the roll storage rack, and it takes time for the traverse carriage to move. There is a problem that it takes time to switch rolls in the grinder. Further, since it takes time to replace the rolls, the roll grinder becomes empty during that time, and there is an unsolved problem that the operation efficiency of the roll grinder is poor.

【0007】そこで、この発明は上記従来の未解決の課
題に着目してなされたものであり、ロールグラインダの
稼働効率を向上させることのできるロールショップを提
供することを目的としている。
Therefore, the present invention has been made in view of the above-mentioned unsolved problems of the prior art, and an object thereof is to provide a roll shop capable of improving the operating efficiency of a roll grinder.

【0008】[0008]

【課題を解決するための手段】上記目的を達成するため
に、請求項1に係るロールショップは、整備部材を所定
の載置領域に搬送する搬送手段と、前記載置領域に搬送
された整備部材を整備装置に載置する載置装置と、を備
えたロールショップにおいて、前記搬送手段及び前記整
備装置間の前記整備部材の移動領域外に、前記載置領域
と隣接し、且つ、前記整備部材を一時待機可能な待機領
域を有することを特徴としている。したがって、予め待
機領域に整備部材を待機させておけば、整備装置への整
備部材の入れ替え時には、整備装置から載置領域に載置
された整備部材が搬送手段により搬送され載置領域が空
いた時点で、待機領域の整備部材が載置領域に移動され
これが整備装置に載置されて整備処理が開始される。
In order to achieve the above object, a roll shop according to a first aspect of the present invention is a roll shop that conveys a maintenance member to a predetermined placement area, and maintenance that is conveyed to the placement area. In a roll shop including a placement device for placing a member on a maintenance device, the roll shop is adjacent to the placement region, outside the movement region of the maintenance member between the transfer means and the maintenance device, and the maintenance device. It is characterized in that it has a standby area in which a member can temporarily stand by. Therefore, if the maintenance member is made to stand by in the standby area in advance, when the maintenance member is replaced with the maintenance device, the maintenance member placed in the placement area is transported from the maintenance device by the transport means, and the placement area is emptied. At this point, the maintenance member in the standby area is moved to the placement area, is placed on the maintenance device, and the maintenance process is started.

【0009】また、請求項2に係るロールショップは、
前記待機領域を、前記載置領域の奥側に設けたことを特
徴としている。よって、載置領域の奥側、すなわち、搬
送手段の載置領域への整備部材の搬送方向の延長上に待
機領域があるから、整備部材は直線移動で待機領域に移
送される。さらに、請求項3に係るロールショップは、
前記載置領域と前記搬送手段の移動領域との間に前記整
備部材を一時待機可能な副待機領域を有することを特徴
としている。よって、整備装置から載置領域に載置され
た整備部材を副待機領域に移送し副待機領域から搬送手
段により搬送すれば、搬送手段による整備部材の搬送状
況に関係なく待機領域の整備部材が載置領域に移送さ
れ、これが整備装置へ載置される。
The roll shop according to claim 2 is
The standby area is provided on the back side of the placement area. Therefore, since the standby area is on the back side of the placement area, that is, on the extension of the maintenance member in the conveyance direction to the placement area of the conveyance means, the maintenance member is linearly transferred to the standby area. Further, the roll shop according to claim 3 is
It is characterized in that it has a sub-standby region capable of temporarily holding the maintenance member between the placement region and the movement region of the transport means. Therefore, if the maintenance member placed on the placement area from the maintenance device is transferred to the sub-standby area and is conveyed from the sub-standby area by the conveying means, the maintenance member in the standby area is irrespective of the conveyance state of the maintenance member by the conveying means. It is transferred to the mounting area, which is mounted on the maintenance device.

【0010】[0010]

【発明の実施の形態】以下に、本発明の実施の形態を説
明する。図1は、本発明におけるロールショップの実施
の形態の一例を示したものであり、このロールショップ
1は、ミルヤード2に壁3を隔てて隣接していて、ロー
ルショップ1とミルヤード2とは搬入出口4を介して連
通している。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below. FIG. 1 shows an example of an embodiment of a roll shop according to the present invention. The roll shop 1 is adjacent to a mill yard 2 with a wall 3 therebetween, and the roll shop 1 and the mill yard 2 are carried in. It communicates through the outlet 4.

【0011】そして、ロールショップ1内の壁3と平行
な位置には、横行ピット5と、この横行ピット5内に連
通するように横行ピット5長手方向と直角な方向へ延び
る複数の移載ピット6とが形成され、前記横行ピット5
内には横行ガイドレール7が敷設されている。そして、
前記各移載ピット6上部には、前記横行ガイドレール7
に対して直角方向に延びる引き込みガイドレール8a,
8bが敷設され、この引き込みガイドレール8a,8b
敷設位置に、例えば、ロール保管ラック9,或いは、整
備装置としてのロールグラインダ10等のメンテナンス
装置が設置されている。
At a position parallel to the wall 3 in the roll shop 1, a transverse pit 5 and a plurality of transfer pits extending in a direction perpendicular to the longitudinal direction of the transverse pit 5 so as to communicate with the transverse pit 5. 6 and the transverse pit 5 is formed.
A transverse guide rail 7 is laid inside. And
The transverse guide rails 7 are provided above the transfer pits 6.
A pull-in guide rail 8a extending in a direction perpendicular to
8b is laid, and the pull-in guide rails 8a and 8b are provided.
At the laying position, for example, a roll storage rack 9 or a maintenance device such as a roll grinder 10 as a maintenance device is installed.

【0012】そして、このロール保管ラック9用の引き
込みガイドレール8aは、後述の、整備部材としてのロ
ールセット13を1組保管可能な長さに形成され、引き
込みガイドレール8a上にロールセット13を保管する
ようになっている。また、ロールグラインダ10用の引
き込みガイドレール8bは、ロールセット13を3組縦
列して保管可能な長さに形成されている。
The pull-in guide rail 8a for the roll storage rack 9 is formed to have a length capable of storing one roll set 13 as a maintenance member, which will be described later, and the roll set 13 is placed on the pull-in guide rail 8a. It is supposed to be stored. In addition, the pull-in guide rail 8b for the roll grinder 10 is formed to have a length such that three roll sets 13 can be arranged in a row and stored.

【0013】ここで、このロールセット13は、図2に
示すように、上ロール11a及びこれを回転自在に支持
する一対の上ロール用チョック11bからなる上ロール
チョック11と、下ロール12b及びこれを回転自在に
支持する一対の下ロール用チョック12bからなる下ロ
ールチョック12とから形成され、上ロールチョック1
1を上段に、下ロールチョック12を下段にして上下に
積み重ねて形成されている。そして、下ロールチョック
12の下部には、前記引き込みガイドレール8a,8b
のレール幅に応じた4つの車輪が配設され、引き込みガ
イドレール8a,8bを走行可能に形成されている。
As shown in FIG. 2, the roll set 13 includes an upper roll chock 11 including an upper roll 11a and a pair of upper roll chocks 11b that rotatably support the upper roll 11a, a lower roll 12b, and the lower roll 12b. An upper roll chock 1 which is formed from a lower roll chock 12 including a pair of lower roll chock 12b rotatably supported.
The upper roll 1 and the lower roll chock 12 are formed on the upper and lower sides. Then, at the lower part of the lower roll chock 12, the pull-in guide rails 8a, 8b are provided.
Four wheels are arranged according to the rail width of the rail and are formed so as to be able to travel on the pull-in guide rails 8a and 8b.

【0014】そして、前記横行ガイドレール7を案内と
して、搬送手段としての横行台車14が往復動するよう
になっている。この横行台車14は、例えば、モータ及
びベベル減速機等から形成される図示しない駆動装置に
よって駆動される駆動輪及び従動輪を有し、横行台車1
4の上面には、前記引き込みガイドレール8a,8bと
平行に、且つ、これらガイドレール8a,8bと同一の
レール幅に形成された二組の誘導ガイドレール14aが
敷設され、この誘導ガイドレール14aは、前記引き込
みガイドレール8a,8bと同一平面上に位置するよう
に敷設される。また、横行台車14は、横行台車14と
ミルヤード2側、或いは、前記引き込みガイドレール8
a,8bとの間でロールセット13を移動可能に形成さ
れた移載装置15を有している。この移載装置15は後
述の引き込み装置17と同一に形成されている。そし
て、横行台車14は、その上面に移載されたロールセッ
ト13を保持した状態で横行ガイドレール7に沿って横
行可能に形成されている。
A traverse carriage 14 as a conveying means reciprocates by using the traverse guide rail 7 as a guide. The transverse carriage 14 has drive wheels and driven wheels driven by a drive device (not shown) formed of, for example, a motor and a bevel speed reducer.
On the upper surface of 4, there are laid two sets of guide guide rails 14a formed in parallel with the pull-in guide rails 8a, 8b and with the same rail width as these guide rails 8a, 8b. Is laid so as to be located on the same plane as the pull-in guide rails 8a and 8b. In addition, the traverse carriage 14 includes the traverse carriage 14 and the mill yard 2 side, or the pull-in guide rail 8
It has a transfer device 15 formed so that the roll set 13 can be moved between a and 8b. The transfer device 15 is formed in the same manner as the retracting device 17 described later. The traverse carriage 14 is formed so as to traverse along the traverse guide rail 7 while holding the roll set 13 transferred to the upper surface thereof.

【0015】一方、前記ロールグラインダ用の引き込み
ガイドレール8bの下部に形成された前記移載ピット6
の延長上の、引き込みガイドレール8bに沿った位置に
は、引き込みピット16が形成されている。この引き込
みピット16には、引き込み装置17が配設され、引き
込みガイドレール8b上のロールセット13を、入り側
位置A,載置位置B,反入り側位置Cの三つの位置にそ
れぞれ移動可能に形成されている。
On the other hand, the transfer pit 6 formed below the pull-in guide rail 8b for the roll grinder.
A lead-in pit 16 is formed at a position along the lead-in guide rail 8b on the extension of the. A pull-in device 17 is arranged in the pull-in pit 16, and the roll set 13 on the pull-in guide rail 8b can be moved to three positions of an entrance side position A, a mounting position B, and an anti-entrance side position C, respectively. Has been formed.

【0016】ここで、入り側位置Aが副待機領域に対応
し、載置位置Bが載置領域に対応し、反入り側位置Cが
待機領域に対応している。そして、引き込みガイドレー
ル8bの載置位置Bに該当する位置の両側に、前述のロ
ールグラインダ10が配設され、片側には、上ロールチ
ョック11用のロールグラインダ10aが配置され、他
方には下ロールチョック12用のロールグラインダ10
bが配置されている。
Here, the entrance side position A corresponds to the sub standby area, the placement position B corresponds to the placement area, and the non-entrance side position C corresponds to the standby area. The roll grinders 10 are arranged on both sides of the position corresponding to the mounting position B of the pull-in guide rail 8b, the roll grinder 10a for the upper roll chock 11 is arranged on one side, and the lower roll chock is arranged on the other side. Roll grinder 10 for 12
b is arranged.

【0017】そして、引き込みガイドレール8bの上部
には、横行ガイドレール7を平行に、ロールグラインダ
10a,10bの上部まで移動可能な載置装置21が配
置され、この載置装置21により引き込みガイドレール
8b上のロールセット13をそれぞれ所定のロールグラ
インダ10a,10bに載置するようになっている。一
方、ミルヤード2内には、前記横行ピット5内に連通す
るように横行ピット5長手方向と直角な方向へ延びる複
数の移載ピット26が形成され、この移載ピット26は
前記移載ピット6と同一に形成されている。そして、こ
の移載ピット26上部には、前記横行ガイドレール7に
対して直角方向に延びる案内ガイドレール27が敷設さ
れ、この案内ガイドレール27は、ミルヤード2内の各
圧延機から搬入出口4を経て移載ピット6と平行になる
ように敷設され、そのレール幅は、前記ロールセット1
3に配設された車輪幅と同一に形成され、また、引き込
みガイドレール8a,8bと、走行台車14の誘導ガイ
ドレール14aと、案内ガイドレール27とは同一平面
上に形成されている。
On the upper part of the pull-in guide rail 8b, there is arranged a placing device 21 which can move the transverse guide rail 7 in parallel to the upper parts of the roll grinders 10a and 10b. The roll set 13 on 8b is mounted on predetermined roll grinders 10a and 10b, respectively. On the other hand, a plurality of transfer pits 26 extending in a direction perpendicular to the longitudinal direction of the transverse pits 5 are formed in the mill yard 2 so as to communicate with the transverse pits 5. The transfer pits 26 are the transfer pits 6. It is formed the same as. A guide guide rail 27 extending in a direction perpendicular to the transverse guide rail 7 is laid on the upper part of the transfer pit 26, and the guide guide rail 27 extends from the rolling mills in the mill yard 2 to the loading / unloading port 4. It is laid so as to be parallel to the transfer pit 6, and its rail width is the same as that of the roll set 1
The wheel guides 8a, 8b, the guide guide rails 14a of the traveling carriage 14, and the guide guide rails 27 are formed on the same plane.

【0018】図2は、引き込みピット16に配設された
引き込み装置17の概略構成を示したものであり、この
引き込み装置17は、前記ロールセット13を引き込む
連結装置31を二組有する引き込み台車32と、この引
き込み台車32を駆動する駆動装置33とから構成さ
れ、前記連結装置31は、前記引き込み台車32の上面
に、引き込み台車32の進行方向に前後に所定間隔をお
いて配設されている。
FIG. 2 shows a schematic structure of a drawing device 17 arranged in the drawing pit 16. The drawing device 17 has a drawing carriage 32 having two connecting devices 31 for drawing the roll set 13. And a drive device 33 for driving the pull-in carriage 32. The connecting device 31 is arranged on the upper surface of the pull-in carriage 32 at predetermined intervals in the front-rear direction in the traveling direction of the pull-in carriage 32. .

【0019】前記駆動装置33は、モータ34の回転駆
動力をベベル減速機35を介して、スクリュー36に伝
達し、このスクリュー36に回転に伴い、スクリュー3
6に螺合し、且つ、引き込み台車32に取り付けられた
ナット36bが移動することによって、引き込み台車3
2を駆動するようになっている。このスクリュー36
は、前記引き込みピット16長手方向と平行に、軸受け
ユニット37a及び37bによって、その両端が回転自
在に支持されている。
The driving device 33 transmits the rotational driving force of the motor 34 to the screw 36 via the bevel speed reducer 35, and the screw 36 rotates as the screw 3 rotates.
6 and the nut 36b attached to the pull-in carriage 32 is moved to move the pull-in carriage 3
It is designed to drive 2. This screw 36
Both ends are rotatably supported by bearing units 37a and 37b in parallel with the longitudinal direction of the pull-in pit 16.

【0020】そして、このスクリュー36と平行に走行
レール38が敷設され、この走行レール38上を引き込
み台車32が駆動装置33によって駆動されて移動する
ようになっている。引き込み台車32の連結装置31
は、例えば、前記一対の下ロール用チョック12bの下
面にそれぞれ形成された連結穴12cと係合するように
形成された連結ピン41と、この連結ピン41を上下駆
動する電動シリンダ42とから構成されている。そし
て、引き込み台車32が駆動装置33により所定の位置
まで移動したとき、電動シリンダ42を作動して連結ピ
ン41を上方に突出させて下ロール用チョック12bの
下面に形成された連結穴12cに係合させ、この状態で
駆動装置33により引き込み台車32を駆動することに
よって、引き込み台車32の移動と共にロールセット1
3を前記引き込みガイドレール8bに沿って移動させ、
所定の位置に移動するようになっている。
A traveling rail 38 is laid parallel to the screw 36, and the pulling carriage 32 is driven by a drive device 33 to move on the traveling rail 38. Connecting device 31 for pull-in cart 32
Is composed of, for example, a connecting pin 41 formed so as to engage with a connecting hole 12c formed in the lower surface of each of the pair of lower roll chocks 12b, and an electric cylinder 42 for vertically driving the connecting pin 41. Has been done. Then, when the retracting carriage 32 is moved to a predetermined position by the drive device 33, the electric cylinder 42 is operated to cause the connecting pin 41 to project upward to engage the connecting hole 12c formed in the lower surface of the lower roll chock 12b. The pulling carriage 32 is driven by the drive device 33 in this state, so that the pulling carriage 32 moves and the roll set 1 moves.
3 is moved along the pull-in guide rail 8b,
It is designed to move to a predetermined position.

【0021】次に、図3に基づいて載置装置21の構成
を説明する。この図3は、図1のX−X断面の詳細を示
したものである。載置装置21は、引き込みガイドレー
ル8bを含む、ロールグラインダ10a,10bの上部
に、横行ガイドレール7と平行に配設された走行フレー
ム20と、この走行フレーム20に沿って走行する上部
台車45とから構成されている。
Next, the structure of the mounting device 21 will be described with reference to FIG. FIG. 3 shows details of the XX cross section of FIG. The placement device 21 includes a traveling frame 20 disposed in parallel with the traverse guide rail 7 on top of the roll grinders 10a and 10b including the pull-in guide rail 8b, and an upper carriage 45 traveling along the traveling frame 20. It consists of and.

【0022】この上部台車45には、モータ46aとベ
ベル減速機46bとが配設され、モータ46aの駆動力
が駆動輪46cに伝達されて、走行フレーム20上を走
行するようになっている。また、上部台車45には、走
行フレーム20を基準として上下方向に移動可能な昇降
アーム48a,48bが固定され、上部台車45に設け
られた、昇降アーム用駆動装置49によって駆動される
ようになっている。
A motor 46a and a bevel speed reducer 46b are arranged on the upper carriage 45, and the driving force of the motor 46a is transmitted to the drive wheels 46c so that the upper frame 45 travels on the traveling frame 20. Lifting arms 48a and 48b that are vertically movable with respect to the traveling frame 20 are fixed to the upper carriage 45, and are driven by a lifting arm driving device 49 provided in the upper carriage 45. ing.

【0023】この昇降アーム用駆動装置49は、例え
ば、モータ50,ベベル減速機51,ピニオン52,昇
降アーム48に固定されたラック53から構成され、モ
ータ50を駆動することにより、その駆動力がベベル減
速機51,ピニオン52を介してラック53に伝達さ
れ、これによって昇降アーム48a及び48bが上下方
向に移動するように形成されている。また、昇降アーム
48a及び48bのそれぞれの下部には、電動シリンダ
54により水平方向に駆動される水平アーム55が配設
されている。そして、上部台車45を引き込みガイドレ
ール8b上に位置させた状態で、昇降アーム48a,4
8bを下降させ、水平アーム55を水平方向に駆動して
その先端に固定された係合ピン56を、上ロールチョッ
ク11に形成されたフランジ部11aに係合させた状
態、または、下ロールチョック12の下面に係合させた
状態で、昇降アーム48a,48bを上昇させることに
よって、上ロールチョック11又は下ロールチョック1
2を持ち上げるようになっている。
The elevating arm driving device 49 is composed of, for example, a motor 50, a bevel speed reducer 51, a pinion 52, and a rack 53 fixed to the elevating arm 48. It is transmitted to the rack 53 via the bevel speed reducer 51 and the pinion 52, whereby the elevating arms 48a and 48b are formed to move in the vertical direction. A horizontal arm 55, which is horizontally driven by an electric cylinder 54, is disposed below each of the elevating arms 48a and 48b. Then, with the upper carriage 45 positioned on the retractable guide rail 8b, the elevating arms 48a, 48a.
8b is lowered, the horizontal arm 55 is driven in the horizontal direction, and the engagement pin 56 fixed to the tip of the horizontal arm 55 is engaged with the flange portion 11a formed on the upper roll chock 11 or the lower roll chock 12. The upper roll chock 11 or the lower roll chock 1 is lifted by raising the elevating arms 48a and 48b while engaging the lower surface.
It is designed to lift 2.

【0024】そして、この載置装置21が平行に2組配
設されて、各載置装置21がロールセット13の各チョ
ック11a,11b又は12a,12bをそれぞれ同時
に支持することによって、上ロールチョック11又は下
ロールチョック12を持ち上げて移動するようになって
いる。次に、上記実施の形態の動作を図4に基づいて説
明する。
Two sets of the mounting devices 21 are arranged in parallel, and each mounting device 21 simultaneously supports the respective chocks 11a, 11b or 12a, 12b of the roll set 13, whereby the upper roll chock 11 is formed. Alternatively, the lower roll chock 12 is lifted and moved. Next, the operation of the above embodiment will be described with reference to FIG.

【0025】今、例えば、ロールグラインダ10でロー
ルセット13Mに対して、再生処理を行っているものと
する(状態1)。この状態で、例えば、ロール保管ラッ
ク9に保管されているロールセット13Nに対して次に
再生処理を行うものする。まず、横行台車14を移動さ
せて、ロール保管ラック9のロールセット13Nが保管
されている引き込みガイドレール8aに対向する位置ま
で横行台車14を移動させる。そして、所定の位置に横
行台車14がきたとき、横行台車14の移載装置15を
駆動して、引き込みガイドレール8a上に保管されてい
るロールセット13Nの連結穴12cに移載装置15の
連結ピン41を係合させて横行台車14上にロールセッ
ト13Nを移載する。そして、この状態で横行台車14
を移動させて、ロールグラインダ用引き込みガイドレー
ル8bに対向する位置まで横行台車14を移動させる。
Now, for example, it is assumed that the roll grinder 10 is performing the reproduction process on the roll set 13M (state 1). In this state, for example, the roll set 13N stored in the roll storage rack 9 is next regenerated. First, the traverse carriage 14 is moved to a position facing the pull-in guide rail 8a in which the roll set 13N of the roll storage rack 9 is stored. Then, when the transverse carriage 14 comes to a predetermined position, it drives the transfer device 15 of the transverse carriage 14 to connect the transfer device 15 to the connection hole 12c of the roll set 13N stored on the pull-in guide rail 8a. The pin 41 is engaged and the roll set 13N is transferred onto the transverse carriage 14. Then, in this state, the transverse carriage 14
Is moved to move the transverse carriage 14 to a position facing the pulling guide rail 8b for the roll grinder.

【0026】そして、再度移載装置15を駆動して、横
行台車14上のロールセット13Nを引き込みガイドレ
ール8b上に載置する。これによって、ロールセット1
3Nが引き込みガイドレール8b上の入り側位置Aに移
動される(状態2)。この状態から、図2に示すよう
に、引き込み装置17を駆動する。そして、引き込み台
車32を軸受けユニット37a側まで移動させ、軸受け
ユニット37a側の電動シリンダ42を駆動して連結ピ
ン41を突出させて、連結ピン41を反入り側位置側の
連結穴12cに係合させた状態で、モータ34を逆回転
させて引き込み台車32を反入り側位置C方向に移動さ
せて所定位置で停止させる。
Then, the transfer device 15 is driven again to place the roll set 13N on the traverse carriage 14 on the pull-in guide rail 8b. This allows roll set 1
3N is moved to the entry side position A on the pull-in guide rail 8b (state 2). From this state, the retracting device 17 is driven as shown in FIG. Then, the retracting carriage 32 is moved to the bearing unit 37a side, the electric cylinder 42 on the bearing unit 37a side is driven to project the connecting pin 41, and the connecting pin 41 is engaged with the connecting hole 12c on the side opposite to the entry side. In this state, the motor 34 is rotated in the reverse direction to move the pull-in carriage 32 in the direction C toward the non-entrance side and stop it at a predetermined position.

【0027】これによって、連結ピン41aがロールセ
ット13Nの連結穴12cに係合されていることから、
引き込み台車32の移動に伴って、ロールセット13N
が引き込みガイドレール8bを案内として反入り側位置
C方向に移動し、反入り側位置Cにて停止する(状態
3)。この状態で、ロールグラインダ10でのロールセ
ット13Mに対する再生処理が終了すると、図3に示す
ように、上部台車45を駆動して、下ロールチョック1
2が載置されたロールグラインダ10bの上部まで上部
台車45を移動させる。次に、昇降アーム駆動装置49
を駆動して、昇降アーム48a及び48bを下降させ、
これらアーム48a及び48bの下部が下ロールチョッ
ク12の下面まできたときに、次に、電動シリンダ54
を駆動して水平アーム55を互いに対向する水平方向に
突出させ、水平アーム55の先端に固定された係合ピン
56で下ロールチョック12の下面の車輪にぶつからな
い位置を支持し、この状態で、再度昇降アーム48a及
び48bを上昇させて下ロールチョック12を持ち上げ
る。そして、この状態で上部台車45を駆動して、下ロ
ールチョック12を引き込みガイドレール8bの上部ま
で移動し、再度昇降アーム48a及び48bを下降させ
て引き込みガイドレール8b上に載置する。同様にし
て、上ロールチョック11をロールグラインダ10aか
ら引き込みガイドレール8b上の下ロールチョック12
上に載置する。これによって、図4の状態4に示すよう
に、ロールグラインダ10は空き状態となり、引き込み
ガイドレール8b上の載置位置Bに再生処理後のロール
セット13Mが位置することになる。このとき、反入り
側位置Cには再生処理前のロールセット13Nが位置し
ている。
As a result, since the connecting pin 41a is engaged with the connecting hole 12c of the roll set 13N,
Along with the movement of the pulling carriage 32, the roll set 13N
Moves toward the counter-entrance side position C using the pull-in guide rail 8b as a guide, and stops at the counter-entrance side position C (state 3). In this state, when the regeneration processing for the roll set 13M by the roll grinder 10 is completed, the upper carriage 45 is driven to move the lower roll chock 1 as shown in FIG.
The upper carriage 45 is moved to the upper part of the roll grinder 10b on which 2 is placed. Next, the lifting arm drive device 49
To lower the elevating arms 48a and 48b,
When the lower portions of the arms 48a and 48b reach the lower surface of the lower roll chock 12, the electric cylinder 54
Is driven to project the horizontal arms 55 in the horizontal direction opposite to each other, and the engagement pin 56 fixed to the tip of the horizontal arm 55 supports a position on the lower surface of the lower roll chock 12 that does not hit the wheels. The elevating arms 48a and 48b are again raised to raise the lower roll chock 12. Then, in this state, the upper carriage 45 is driven to move the lower roll chock 12 to the upper part of the pull-in guide rail 8b, and the elevating arms 48a and 48b are lowered again to be placed on the pull-in guide rail 8b. Similarly, the upper roll chock 11 is pulled in from the roll grinder 10a, and the lower roll chock 12 on the guide rail 8b.
Place on top. As a result, as shown in state 4 of FIG. 4, the roll grinder 10 is in an empty state, and the roll set 13M after the regeneration processing is located at the mounting position B on the pull-in guide rail 8b. At this time, the roll set 13N before the regeneration process is located at the counter-entrance side position C.

【0028】次に、引き込み装置17を駆動して引き込
み台車32を、載置位置B及び反入り側位置Cの中間位
置まで移動し、この状態で、連結装置31を駆動し、軸
受けユニット37a側の連結ピン41をロールセット1
3Mの反入り側位置側の連結穴12cに係合させ、軸受
けユニット37b側の連結ピン42をロールセット13
Nの入り側位置側の連結穴12cに係合させる。そし
て、この状態で、引き込み台車32を軸受けユニット3
7b方向に移動させる。これによって、引き込み台車3
2の移動に伴って、ロールセット13M及び13Nが引
き込みガイドレール8b上を共に、横行ガイドレール7
方向に移動し、再生処理済のロールセット13Mは入り
側値Aに、再生処理前のロールセット13Nは載置位置
Bに移動される(状態5)。
Next, the retraction device 17 is driven to move the retraction carriage 32 to an intermediate position between the mounting position B and the counter-entry side position C, and in this state, the coupling device 31 is driven to the bearing unit 37a side. Roll set 1 connecting pin 41 of
The connection pin 42 on the side of the bearing unit 37b is engaged with the connection hole 12c on the side opposite to the 3M side, and the connection pin 42 on the side of the bearing unit 37b.
The connection hole 12c on the N entry side position side is engaged. Then, in this state, the pull-in carriage 32 is mounted on the bearing unit 3
Move in 7b direction. As a result, the retractable carriage 3
As the roll set 13 moves, the roll sets 13M and 13N move together on the pull-in guide rail 8b and the transverse guide rail 7
The roll set 13M that has been regenerated is moved to the entry side value A, and the roll set 13N that has not been regenerated is moved to the mounting position B (state 5).

【0029】よって、載置装置21を駆動し、上述と同
様にして昇降アーム48a及び48bの駆動と上部台車
45の移動とを繰り返し行い、載置位置B上のロールセ
ット13Nの上ロールチョック11をロールグラインダ
10aの所定位置に載置し、下ロールチョック12をロ
ールグラインダ10bの所定位置に載置する。これによ
って、ロールグラインダ10での処理が開始される(状
態6)。
Therefore, the loading device 21 is driven, and the lifting arms 48a and 48b are driven and the upper carriage 45 is moved repeatedly in the same manner as described above to set the upper roll chock 11 of the roll set 13N on the loading position B. The lower roll chock 12 is placed at a predetermined position of the roll grinder 10a, and the lower roll chock 12 is placed at a predetermined position of the roll grinder 10b. As a result, the processing by the roll grinder 10 is started (state 6).

【0030】そして、例えば、載置装置21を駆動する
一方、横行台車14を駆動して、ロールグラインダ用の
引き込みガイドレール8bに対向する位置まで横行台車
14を移動させ、所定位置にきたとき横行台車14の移
載装置15を駆動して、入り側位置Aにある再生処理済
のロールセット13Nを横行台車14上に移載する(状
態7)。そして、横行台車14を駆動し、例えば、ミル
ヤード2側の所定の案内ガイドレール27に対向する位
置、或いは、ロール保管ラック9の所定の引き込みガイ
ドレール8aに対向する位置まで、横行台車14を移動
させる。そして、所定の位置にきたときに、横行台車1
4上のロールセット13Nを案内ガイドレール27上又
は、引き込みガイドレール8a上に移載する。これによ
って、ロールセット13Mに対する再生処理が終了す
る。
Then, for example, while driving the placing device 21, the transverse carriage 14 is driven to move the transverse carriage 14 to a position facing the pull-in guide rail 8b for the roll grinder, and when the carriage reaches a predetermined position. The transfer device 15 of the carriage 14 is driven to transfer the regenerated roll set 13N at the entrance position A onto the traverse carriage 14 (state 7). Then, the traverse carriage 14 is driven, and the traverse carriage 14 is moved to, for example, a position facing a predetermined guide guide rail 27 on the mill yard 2 side or a position facing a predetermined pull-in guide rail 8a of the roll storage rack 9. Let Then, when it comes to a predetermined position, the transverse carriage 1
The roll set 13N on 4 is transferred onto the guide guide rail 27 or the pull-in guide rail 8a. As a result, the reproduction process for the roll set 13M ends.

【0031】そして、例えば、新たに再生処理を行う必
要があるロールセット13がある場合には、上記と同様
にして、このロールセット13を横行台車14上に載置
し、横行台車14を駆動して引き込みガイドレール8b
に対向する位置まで移動し、引き込みガイドレール8b
上にロールセット13を移載する。そして、引き込み装
置17を駆動して、ロールセット13を反入り側位置C
まで移動させ、この位置で待機させ、以後上記と同様に
処理を行う。
Then, for example, when there is a roll set 13 that needs to be newly regenerated, the roll set 13 is placed on the traverse carriage 14 and the traverse carriage 14 is driven in the same manner as above. And pull in guide rail 8b
To the position opposite to the pull-in guide rail 8b
The roll set 13 is transferred on top. Then, the retraction device 17 is driven to move the roll set 13 to the reverse entrance side position C.
It is moved to, and is made to stand by at this position, and thereafter the same processing is performed.

【0032】よって、上記実施の形態によれば、ロール
グラインダ10のロールセットの入れ替えを引き込みガ
イドレール8b上で行うことができるから、ロールセッ
トの入れ替えに要する時間は、再生処理中のロールセッ
ト13を引き込みガイドレール8b上の載置位置Bに移
載した時点から、反入り側位置Cで待機中の再生処理前
のロールセット13を載置位置Bまで移動し、これをロ
ールグラインダ10の所定位置に載置するまでの間のみ
となり、ロールセットの入れ替えに要する時間を大幅に
短縮することができる。
Therefore, according to the above-described embodiment, the roll sets of the roll grinder 10 can be exchanged on the pull-in guide rail 8b. Therefore, the time required for the exchange of the roll sets is the roll set 13 being regenerated. From the time when the paper is transferred to the mounting position B on the pull-in guide rail 8b, the roll set 13 before the regenerating process, which is waiting at the counter-entry side position C, is moved to the mounting position B, and the roll set 13 is moved to the predetermined position of the roll grinder 10. It is only until it is placed in the position, and the time required to replace the roll set can be greatly shortened.

【0033】また、ロールセットの入れ替え時間を短縮
することができることから、ロールグラインダ10の稼
働率を向上させることができるため、ロールグラインダ
10の数を削減することができる。よって、コスト削減
を図ることができると共に、削減されるロールグライン
ダの分だけロールショップのスペースを小さくすること
ができる。また、ロールグラインダの稼働率が向上する
から、保持しておくべき予備のロールセットを削減する
ことができるから、コスト削減を図ることも可能であ
る。
Further, since the roll set replacement time can be shortened, the operating rate of the roll grinder 10 can be improved, and the number of roll grinders 10 can be reduced. Therefore, the cost can be reduced, and the space of the roll shop can be reduced by the amount of the reduced roll grinder. Further, since the operation rate of the roll grinder is improved, it is possible to reduce the number of spare roll sets to be held, and thus it is possible to reduce the cost.

【0034】ちなみに、横行台車14がロールグライン
ダ10と例えばロール保管ラックとの間を往復する従来
のロールセット入れ替えの方法と、本発明によるロール
セット入れ替え方法とを比較した場合、従来のロールセ
ット入れ替え方法では、入れ替え時間は7分,ロールグ
ラインダ10の稼働率は89%であるのに対し、本発明
によるロールセット入れ替え方法では、入れ替え時間は
2分,稼働率は96%となり、入れ替え時間を大幅に短
縮できると共に、稼働率を大幅に向上させることができ
ることがわかる。
Incidentally, when comparing the conventional roll set replacement method in which the traverse carriage 14 reciprocates between the roll grinder 10 and, for example, the roll storage rack, the conventional roll set replacement method is compared. In the method, the replacement time is 7 minutes and the operation rate of the roll grinder 10 is 89%, whereas in the roll set replacement method according to the present invention, the replacement time is 2 minutes and the operation rate is 96%. It can be seen that the operating rate can be greatly improved while being shortened to.

【0035】なお、上記実施の形態においては、載置位
置Bを挟んで、入り側位置A及び反入り側位置Cに再生
処理前及び再生処理後のロールセットを待機させるよう
にした場合について説明したが、例えば、反入り側位置
Cのみを設けて再生処理前のロールセットを待機させて
おき、再生処理後のロールセットが横行台車14の移載
装置15によって移動されるのとほぼ同時に、引き込み
装置17によって反入り側位置Cのロールセットを載置
位置Bに移動させるようにした場合でも、上記と同様
に、ロールグラインダ10でのロールセット入れ替えに
要する時間を削減することが可能である。しかしなが
ら、上記載置位置Bを挟んで入り側位置A及び反入り側
位置Cにロールセットを待機させるようにしているか
ら、再生処理後のロールセットの横行台車14への載置
状態とは無関係に、ロールグラインダでの処理状態のみ
に応じてロールセットの入れ替えを行うことができる。
In the above embodiment, the case where the roll set before and after the regeneration process is made to stand by at the entrance side position A and the counter entrance side position C with the placing position B sandwiched is explained. However, for example, only when the anti-entry side position C is provided and the roll set before the regenerating process is on standby, and at the same time when the roll set after the regenerating process is moved by the transfer device 15 of the traverse carriage 14, Even when the retracting device 17 is used to move the roll set at the non-entrance side position C to the mounting position B, it is possible to reduce the time required to replace the roll set in the roll grinder 10 as in the above. . However, since the roll set is made to stand by at the entry side position A and the counter entry side position C with the placement position B interposed therebetween, it is irrelevant to the placement state of the roll set after the regeneration processing on the transverse carriage 14. In addition, the roll set can be replaced according to only the processing state of the roll grinder.

【0036】また、上記実施の形態においては、引き込
みガイドレール8b上の入り側位置A及び反入り側位置
Cにそれぞれロールセット13を1組待機させるように
した場合について説明したが、例えば、入り側位置A及
び反入り側位置Cにそれぞれ複数組のロールセット13
を待機させるようにすることも可能であり、例えば、次
に再生処理を行うロールセット13を横行台車14がす
ぐに搬送できない場合でも、ロールグラインダ10が空
き状態となることはなく、より有効にロールグラインダ
を稼働させることができる。
In the above embodiment, the case where one roll set 13 is set to stand by at the entrance side position A and the counter entrance side position C on the pull-in guide rail 8b has been described. A plurality of roll sets 13 are provided at the side position A and the counter-entry side position C, respectively.
It is also possible to make the roll grinder 10 stand by, even if the traverse carriage 14 cannot immediately convey the roll set 13 to be next subjected to the regeneration processing, the roll grinder 10 will not be in an empty state and will be more effective. The roll grinder can be operated.

【0037】また、上記実施の形態においては、引き込
み装置17に、連結装置31を引き込み台車32の進行
方向前後に2組配設し、図4の状態4の状態において、
載置位置B及び反入り側位置Cにあるロールセットを同
時に移動させる場合について説明したが、例えば、載置
位置Bのロールセットを入り側位置Aに移動した後、反
入り側位置Cのロールセットを載置位置Bに移動させる
ようにすることも可能であるが、載置位置B及び反入り
側位置Cにあるロールセットを同時に移動させるように
することにより、ロールグラインダにおけるロールセッ
ト入れ替えに要する時間をより短縮させることができ
る。
Further, in the above embodiment, two sets of connecting devices 31 are arranged in the retracting device 17 before and after the retracting carriage 32 in the traveling direction, and in the state of state 4 in FIG.
The case where the roll sets at the mounting position B and the counter-entry side position C are moved at the same time has been described. For example, after the roll set at the mounting position B is moved to the entrance side position A, the rolls at the counter-entry side position C are moved. Although it is possible to move the set to the mounting position B, it is possible to replace the roll sets in the roll grinder by simultaneously moving the roll sets at the mounting position B and the counter-entry side position C. The time required can be further shortened.

【0038】また、上記実施の形態においては、ロール
グラインダに対してロールチョックを搬送する場合につ
いて説明したが、これに限らず、例えば、チョックリム
ーバ等、その他のメンテナンス装置に搬送する場合でも
上記と同等の効果を得ることができる。さらに、上記実
施の形態においては、入り側位置A,載置位置B,反入
り側位置Cを直線上に設け、ロールセット13を直線移
動させる場合について説明したが、これに限らず、載置
位置Bが空き状態となった時点で、反入り側位置Cにあ
るロールセット13を載置位置Bに移動させることがで
きるように配置されていればよく、例えば、ロールグラ
インダの横行ガイドレール7とは逆側の隣の位置を反入
り側位置Cとしてここにロールセット13を待機させる
ようにし、ロールセット13を引き込みガイドレール8
bに対して斜め方向に移動させるようにすることも可能
である。また、例えば、ロールグラインダが引き込みガ
イドレール8bの片側にのみあるような場合には、引き
込みガイドレール8bを挟んでロールグラインダの向か
い側に反入り側位置Cを設定するようにすることも可能
である。しかしながら、本実施の形態のように一直線上
に設ければ、ロールセット13の移動距離は最短となり
引き込みガイドレール8bも最短長でよいから、低コス
トで実現することができまた、少ないスペースですむか
ら、最適である。
Further, in the above embodiment, the case where the roll chock is conveyed to the roll grinder has been described, but the present invention is not limited to this, and is the same as in the case where the roll chock is conveyed to another maintenance device such as a chock remover. The effect of can be obtained. Further, in the above embodiment, the case where the entrance side position A, the placement position B, and the counter entrance side position C are provided on a straight line and the roll set 13 is linearly moved has been described, but the present invention is not limited to this. It is sufficient that the roll set 13 located at the counter-entry side position C can be moved to the mounting position B when the position B becomes empty. For example, the traverse guide rail 7 of the roll grinder can be used. The adjacent position on the opposite side to is set as the counter entrance side position C so that the roll set 13 is made to stand by here, and the roll set 13 is pulled in and the guide rail 8
It is also possible to move in an oblique direction with respect to b. Further, for example, when the roll grinder is provided only on one side of the pull-in guide rail 8b, it is possible to set the counter-entry side position C on the opposite side of the roll grinder with the pull-in guide rail 8b sandwiched therebetween. . However, if the roll set 13 is provided on a straight line as in the present embodiment, the moving distance of the roll set 13 is the shortest, and the pull-in guide rail 8b may be the shortest length, which can be realized at low cost and requires a small space. Is the best.

【0039】[0039]

【発明の効果】以上説明したように、請求項1に係るロ
ールショップによれば、搬送手段及び整備装置間の整備
部材の移動領域以外の領域に、載置領域と隣接する待機
領域が形成されているから、処理終了時に整備装置から
移載された整備部材が載置領域から搬送手段により搬送
され載置領域が空いた時点で待機領域の整備部材を載置
領域に移送しこれを整備装置に設置することができる。
よって、整備部材の入れ替えを短時間で行うことがで
き、整備装置の稼働率を向上させることができる。
As described above, according to the roll shop of the first aspect, the standby area adjacent to the placing area is formed in the area other than the moving area of the maintenance member between the conveying means and the maintenance device. Therefore, when the processing is completed, the maintenance member transferred from the maintenance device is conveyed from the placement area by the conveying means, and when the placement area is empty, the maintenance member in the standby area is transferred to the placement area and the maintenance device is moved. Can be installed in
Therefore, the maintenance members can be replaced in a short time, and the operating rate of the maintenance device can be improved.

【0040】また、請求項2に係るロールショップによ
れば、載置領域の奥側、すなわち、搬送手段の載置領域
への整備部材の搬送方向の延長上に待機領域があるか
ら、整備部材を直線移動で待機領域に移送することがで
き、より短い移送距離で整備部材を待機領域に移送する
ことができ、より短時間で整備部材の入れ替えを行うこ
とができる。
Further, according to the roll shop of the second aspect, since there is the standby area on the inner side of the placement area, that is, on the extension of the maintenance member in the carrying direction to the placement area of the carrying means, the maintenance member is provided. Can be transferred to the standby area by linear movement, the maintenance member can be transferred to the standby area with a shorter transfer distance, and the maintenance member can be replaced in a shorter time.

【0041】さらに、請求項3に係るロールショップに
よれば、整備装置での整備終了後の整備部材を載置領域
と搬送手段の移動領域との間に形成された副待機領域に
待機させれば載置領域が空き領域となって次の整備部材
を整備装置に移載することができるから、搬送手段の搬
送状態に関わらず整備部材の入れ替えを行うことがで
き、搬送手段の搬送を待つ時間を削減することができる
から整備装置の稼働率をより向上させることができる。
Further, according to the roll shop of the third aspect, the maintenance member after the maintenance by the maintenance device is made to stand by in the sub-standby area formed between the placing area and the moving area of the conveying means. For example, since the placement area becomes an empty area and the next maintenance member can be transferred to the maintenance device, the maintenance member can be replaced regardless of the transportation state of the transportation means, and the transportation means waits for transportation. Since the time can be reduced, the operating rate of the maintenance device can be further improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明によるロールショップの実施の形態の一
例を示す構成図である。
FIG. 1 is a configuration diagram showing an example of an embodiment of a roll shop according to the present invention.

【図2】引き込み装置の概略構成を示す構成図である。FIG. 2 is a configuration diagram showing a schematic configuration of a retractor.

【図3】載置装置の概略構成を示す構成図である。FIG. 3 is a configuration diagram showing a schematic configuration of a mounting device.

【図4】本発明の動作説明に供する説明図である。FIG. 4 is an explanatory diagram for explaining the operation of the present invention;

【符号の説明】[Explanation of symbols]

1 ロールショップ 2 ミルヤード 4 搬入出口 7 横行ガイドレール 8 引き込みガイドレール 10 ロールグラインダ 11 上ロールチョック 12 下ロールチョック 13 ロールセット 14 横行台車 17 引き込み装置 21 載置装置 27 案内ガイドレール 31 連結装置 32 引き込み台車 45 上部台車 48 昇降アーム 1 Roll Shop 2 Mill Yard 4 Carrying Out Exit 7 Traverse Guide Rail 8 Retracting Guide Rail 10 Roll Grinder 11 Upper Roll Chock 12 Lower Roll Chock 13 Roll Set 14 Traverse Cart 17 Retractor 21 Placement Machine 27 Guide Guide Rail 31 Coupling Machine 32 Top Cart 45 Top Cart 48 Lifting arm

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 整備部材を所定の載置領域に搬送する搬
送手段と、前記載置領域に搬送された整備部材を整備装
置に載置する載置装置と、を備えたロールショップにお
いて、前記搬送手段及び前記整備装置間の前記整備部材
の移動領域外に、前記載置領域と隣接し、且つ、前記整
備部材を一時待機可能な待機領域を有することを特徴と
するロールショップ。
1. A roll shop, comprising: a conveying unit that conveys a maintenance member to a predetermined placement area; and a placing device that places the maintenance member that has been conveyed to the placement area on a maintenance device. A roll shop, characterized by having a standby area adjacent to the placement area and capable of temporarily waiting for the maintenance member, outside the movement area of the maintenance member between the conveying means and the maintenance device.
【請求項2】 前記待機領域を、前記載置領域の奥側に
設けたことを特徴とする請求項1記載のロールショッ
プ。
2. The roll shop according to claim 1, wherein the waiting area is provided on the back side of the placing area.
【請求項3】 前記載置領域と前記搬送手段の移動領域
との間に前記整備部材を一時待機可能な副待機領域を有
することを特徴とする請求項1又は2に記載のロールシ
ョップ。
3. The roll shop according to claim 1, further comprising a sub-standby area between the placing area and the moving area of the transporting means, the sub-waiting area capable of temporarily waiting for the maintenance member.
JP20212395A 1995-08-08 1995-08-08 Roll shop Expired - Fee Related JP3644082B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20212395A JP3644082B2 (en) 1995-08-08 1995-08-08 Roll shop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20212395A JP3644082B2 (en) 1995-08-08 1995-08-08 Roll shop

Publications (2)

Publication Number Publication Date
JPH0947806A true JPH0947806A (en) 1997-02-18
JP3644082B2 JP3644082B2 (en) 2005-04-27

Family

ID=16452352

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20212395A Expired - Fee Related JP3644082B2 (en) 1995-08-08 1995-08-08 Roll shop

Country Status (1)

Country Link
JP (1) JP3644082B2 (en)

Also Published As

Publication number Publication date
JP3644082B2 (en) 2005-04-27

Similar Documents

Publication Publication Date Title
JP5344928B2 (en) Method and apparatus for operating and transporting work rolls and backup rolls
JP3042099B2 (en) Roll shop and bogie for rolling rolls
JPH0947806A (en) Roll shop
JPS61189803A (en) Conveying device
KR100856302B1 (en) Coil transfer apparatus between conveyors
JP3047574B2 (en) Roll chock moving device
JPH07185828A (en) Welding equipment of panel member
JP4648555B2 (en) Wheel temporary press-fitting equipment
CN115231269B (en) Production unit, automatic needle machine production line and production method
JPH0252113A (en) Roll changing device for rolling mill
JP2004255404A (en) Conveying device for coil in horizontal hole position
JP4335792B2 (en) Mechanical parking device
JP3888755B2 (en) Elevator parking system
JPH1122202A (en) Simplified lifting and carrying device
JP3038354B2 (en) Roll separator
JP3657829B2 (en) Plane reciprocating parking device and method for loading and unloading the same
JP3314558B2 (en) Mechanical parking device
JPH07317368A (en) Fork type multistory parking device
JP2993234B2 (en) Roll shop
JP2023058222A (en) Axle transfer device and moving device
JPH0199708A (en) Device for carrying roll stand or roll stand group
KR20110054451A (en) Fork type parking system
JPH06102216B2 (en) Winding wire transfer device
JPH04173603A (en) Rack equipment with load transferring device
JPH11256861A (en) Parking device

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050111

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050124

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080210

Year of fee payment: 3

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090210

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100210

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100210

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110210

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120210

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120210

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130210

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130210

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees