JPH09317373A - Method of shaft construction - Google Patents

Method of shaft construction

Info

Publication number
JPH09317373A
JPH09317373A JP8153088A JP15308896A JPH09317373A JP H09317373 A JPH09317373 A JP H09317373A JP 8153088 A JP8153088 A JP 8153088A JP 15308896 A JP15308896 A JP 15308896A JP H09317373 A JPH09317373 A JP H09317373A
Authority
JP
Japan
Prior art keywords
ground
improved
continuous wall
shaft
injection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8153088A
Other languages
Japanese (ja)
Inventor
Kenjiro Oka
憲二郎 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toray Engineering Co Ltd
Original Assignee
Toyo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyo Construction Co Ltd filed Critical Toyo Construction Co Ltd
Priority to JP8153088A priority Critical patent/JPH09317373A/en
Publication of JPH09317373A publication Critical patent/JPH09317373A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To reinforce the periphery of the planning region of a shaft and a ground in the planning region precedently by utilizing a method of high-pressure injection agitation construction. SOLUTION: Improvement bodies 5 containing core materials 6 are arrayed to a ground 4 in the periphery of the planning region A of a shaft so as to be mutually lapped and a continuous wall 1 is prepared, and grout injection by an injection rod is executed intermittently into the ground 4 in the planning region A in the planning region A in the vertical direction and improvement bodies 8, 9 are formed. These improvement bodies 8, 9 are arranged so as to be mutually lapped and an improved batholith 2 and an improved intermediate ground 3 are prepared, the improved intermediate ground 3 is used as a precedent ground beam, the ground from a ground surface to the improved intermediate ground 3 is dug down first, the improved intermediate ground 3 is hollowed out, and the lower-side ground of the improved intermediate ground 3 is dug down up to the improved bathlith 2.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、地盤改良工法の一
つである高圧噴射攪拌工法を利用した立坑の構築工法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a vertical shaft construction method utilizing a high-pressure jet agitation method, which is one of the ground improvement methods.

【0002】[0002]

【従来の技術】立坑は、シールド工事の発進・到達基
地、橋脚の基礎、エネルギーの地下貯蔵槽、地下水槽、
地下駐車場等様々な用途があり、近年、その構築が盛ん
に行われている。ところで、立坑を構築する対象地盤
が、崩壊性の大きい砂礫層や転石層からなり、しかも地
下水位が高い場合は、土圧・水圧に対して特別の対策が
必要になる。このため、このような地盤を対象とする場
合は、立坑の計画域の周りや計画底の下方域を事前に地
盤改良すると共に、立坑の計画域内をわずか掘り下げる
(3m程度)ごとに支保作業(腹起し、切梁等)を行
い、土砂の噴出や崩落、あるいは地下水の流入を防止す
るようにしている。
2. Description of the Related Art Vertical shafts are the starting and reaching bases for shield work, foundations for piers, underground energy storage tanks, underground water tanks,
It has various uses such as an underground parking lot, and its construction has been actively performed in recent years. By the way, if the target ground for constructing the shaft consists of highly collapsible gravel layer and boulder layer and the groundwater level is high, special measures against earth pressure and water pressure are required. Therefore, when such a ground is targeted, the ground around the planned area of the shaft and the lower area of the planned bottom are improved in advance, and the support work is carried out every time when the shaft is dug slightly (about 3 m) ( Uplifting, cutting, etc. are performed to prevent the eruption and collapse of earth and sand and the inflow of groundwater.

【0003】そして、上記した地盤改良には、土質の影
響を受けにくく、一回の施工で広い範囲の地盤を改良で
き、しかも改良体相互の密着性に優れているところか
ら、高圧噴射攪拌工法を利用することが多くなってきて
いる。この高圧噴射攪拌工法は、注入ロッドを地盤内で
回転移動させながら、その先端の噴射ノズルから該注入
ロッドと直角方向へグラウト(地盤改良剤)を単独に、
あるいは水またはエアと混合して高圧噴射し、グラウト
と周辺土砂とを攪拌混合して円柱状の改良体を形成する
工法であり、この施工を改良体が相互にラップするよう
に繰返し行うことで、上記した連続壁または底盤の造成
が可能になる(例えば、特公昭50−14803号公
報、特公昭51−8493号公報等参照)。
For the above-mentioned ground improvement, the high-pressure jet agitation method is used because it is hardly affected by the soil quality, a wide range of ground can be improved by one-time construction, and the adhesion between the improved bodies is excellent. Are becoming more and more popular. This high-pressure jet agitation method, while rotating the injection rod in the ground, from the injection nozzle at the tip of the grout (ground improvement agent) in the direction perpendicular to the injection rod,
Alternatively, it is a method of mixing with water or air and injecting it at high pressure to stir and mix the grout and the surrounding earth and sand to form a columnar improved body.By repeating this construction so that the improved body wraps with each other, The above-mentioned continuous wall or bottom plate can be formed (see, for example, Japanese Patent Publication No. 50-14803 and Japanese Patent Publication No. 51-8493).

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記高
圧噴射攪拌工法により形成した改良体は、圧縮に対して
極めて強いが引張に対して弱いという性質を有してお
り、この工法を利用して立坑の計画域の周りに連続壁を
造成しても、土圧に対する抵抗は不十分で、依然として
わずか掘り下げるごとに支保作業を行わなければなら
ず、工期の延長および工費の増大が避けられないという
問題があった。
However, the improved body formed by the above-mentioned high-pressure injection stirring method has the property of being extremely strong against compression but weak against tension. Even if a continuous wall is constructed around the planned area, the resistance to earth pressure is insufficient, and the support work must be carried out every time a little digging, so the extension of construction period and increase of construction cost cannot be avoided. was there.

【0005】本発明は、上記従来の問題点に鑑みてなさ
れたもので、その課題とするところは、高圧噴射攪拌工
法を有効利用して、立坑の計画域の周りに造成する連続
壁の補強を図ると共に、立坑の計画域内を先行補強し、
もって支保作業の回数を大幅に削減して高能率に立坑を
構築できるようにすることにある。
The present invention has been made in view of the above-mentioned problems of the prior art, and its problem is to reinforce a continuous wall formed around a planned area of a vertical shaft by effectively utilizing a high-pressure injection stirring method. In addition to aiming for
This is to reduce the number of supporting work drastically so that a vertical shaft can be constructed with high efficiency.

【0006】[0006]

【課題を解決するための手段】上記課題を解決するた
め、本発明は、高圧噴射攪拌工法により地盤改良して形
成した円柱状の改良体内に芯材を埋め込んで複合体とな
す施工を、立坑の計画線に沿って繰り返し行って連続壁
を造成し、次に、高圧噴射攪拌工法による改良体の形成
を前記連続壁内で繰り返し行って、前記立坑の計画底の
下方域並びにその計画深さの中間域にそれぞれ改良底
盤、改良中間盤を造成し、しかる後に、前記連続壁内の
地盤を地表から前記改良中間盤まで掘り下げ、さらに前
記改良中間盤をくり抜いてその下側地盤を前記改良底盤
まで掘り下げるようにしたことを特徴とする。
In order to solve the above-mentioned problems, the present invention provides a construction in which a core material is embedded in a columnar improved body formed by improving the ground by a high-pressure injection stirring method to form a composite body. To form a continuous wall by repeating the plan line, and then repeatedly forming the improved body by the high-pressure jet agitation method in the continuous wall, and the area below the planned bottom of the shaft and its planned depth. The improved bottom plate and the improved intermediate plate are formed in the respective intermediate regions, and thereafter, the ground in the continuous wall is dug down from the surface to the improved intermediate plate, and the improved intermediate plate is hollowed out, and the lower ground is the improved bottom plate. It is characterized by having been dug down to.

【0007】高圧噴射攪拌工法により形成した改良体内
に芯材を埋め込んで複合体となす工法は、既に特開平3
−208936号公報に開示されており、本願発明は、
この工法を利用して連続壁を造成するようにしたもので
ある。そして、このように造成した連続壁は、各改良体
内に埋め込まれた芯材が引張力に対して強く抵抗し、全
体として剛性が著しく高いものとなる。また、高圧噴射
攪拌工法により立坑の計画深さの中間域に改良中間盤を
造成することで、この改良中間盤が先行地中梁として、
前記した剛性の高い連続壁を内側から支保し、立坑の計
画域周りの地盤がより安定する。
A method of forming a composite body by embedding a core material in an improved body formed by a high-pressure jet agitation method has already been disclosed in Japanese Patent Laid-Open No. Hei 3
The invention of the present application is disclosed in JP-A-208936.
This method is used to create a continuous wall. Then, in the continuous wall thus formed, the core material embedded in each improved body strongly resists the tensile force, and the rigidity as a whole becomes extremely high. In addition, by constructing an improved intermediate plate in the intermediate area of the planned depth of the vertical shaft by the high-pressure jet agitation method, this improved intermediate plate is used as a leading underground beam,
The continuous wall with high rigidity described above is supported from the inside, and the ground around the planned area of the shaft becomes more stable.

【0008】本発明において、上記連続壁は円筒形状に
造成するのが望ましく、円筒形状とした場合は、土圧・
水圧に対して有利な構造となる。
In the present invention, it is preferable that the continuous wall is formed in a cylindrical shape.
The structure is advantageous for water pressure.

【0009】本発明は、改良底盤および改良中間盤を構
成する改良体を、注入ロッドの一回の回転移動で形成す
るようにしても良いものである。この場合、注入ロッド
を導管を挿通して延ばし、地盤改良中に発生する余剰ス
ライムを前記導管を通じて地上へ排出するようにするの
が望ましい。
According to the present invention, the improved body forming the improved bottom plate and the improved intermediate plate may be formed by one rotation movement of the injection rod. In this case, it is desirable that the injection rod be extended through the conduit so that excess slime generated during ground improvement is discharged to the ground through the conduit.

【0010】[0010]

【発明の実施の形態】以下、本発明の実施の形態を添付
図面に基づいて説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the accompanying drawings.

【0011】図1〜3は、立坑構築の途中段階を示した
ものである。これらの図において、1は、立坑の計画域
Aの周りに造成した円筒形状の連続壁、2は立坑の計画
底の下方域Bに造成した円盤状の改良底盤、3は立坑の
計画深さの中間域Cに造成した円盤状の改良中間盤であ
り、それぞれは、立坑の計画域A内の掘削に先行して、
後述する高圧噴射攪拌工法により地盤4内の所定区域を
地盤改良することで形成されたものである。連続壁1
は、図3に良く示されるように高圧噴射攪拌工法により
形成した円柱状の改良体5内に芯材6を埋め込んだ複合
体7を、前記改良体5が相互にラップするように円形に
配列してなるもので、十分なる止水性と大きな強度(剛
性)とを有している。また改良底盤2および改良中間盤
3は、同じく高圧噴射攪拌工法により形成した円柱状の
改良体8,9を相互にラップするように縦横に配列して
なるもので、十分なる止水性と大きな強度を有してい
る。
1 to 3 show an intermediate stage of shaft construction. In these figures, 1 is a cylindrical continuous wall formed around the planned area A of the shaft, 2 is a disk-shaped improved bottom plate formed in the area B below the planned bottom of the shaft, and 3 is the planned depth of the shaft. These are disc-shaped improved intermediate disks created in the intermediate area C of each, and each of them is prior to excavation in the planned area A of the shaft,
It is formed by improving the ground in a predetermined area in the ground 4 by a high-pressure injection stirring method described later. Continuous wall 1
As shown in FIG. 3, a composite body 7 in which a core material 6 is embedded in a cylindrical improved body 5 formed by a high-pressure injection stirring method is arranged in a circle so that the improved body 5 wraps with each other. It has sufficient water-stopping property and high strength (rigidity). Further, the improved bottom plate 2 and the improved intermediate plate 3 are formed by vertically and horizontally arranging cylindrical improved bodies 8 and 9 which are also formed by the high-pressure jet agitation method so as to wrap each other, and have a sufficient waterproofness and a large strength. have.

【0012】立坑の構築に際しては、始めに連続壁1を
造成した後、前記改良底盤2と改良中間盤3とを同時に
造成し、しかる後に、前記連続壁1内の地盤4を地表か
ら順に掘り下げる。そして、適当深さ(一例として1〜
2m)だけ掘り下げた時点で、掘削により露出し連続壁
1の内面(立て壁)にコンクリートを吹付けて所定の厚
さのコンクリート壁10を形成し、さらにこのコンクリ
ート壁10上に、例えばH形鋼からなる支保リング11
を構築する。その後、改良中間盤3まで一気に掘り下
げ、露出した立て壁にコンクリートを吹付けてコンクリ
ート壁10を形成する。この時、連続壁1を構成する各
改良体5内に埋め込まれた芯材6が引張力に対して強く
抵抗し、しかも、中間域に設けた改良中間盤3が先行地
中梁として連続壁1を内側側から支保し、連続壁1の内
側を一度に深く掘り下げても周辺土砂が崩落することは
ない。因みに、この一度に掘り下げる深さは、連続壁内
に前記芯材6を含まずかつ前記した改良中間盤3を設け
ない従来工法の場合は3m程度であるのに対し、本工法
によればその2〜3倍(6〜9m)となり、その分、施
工能率の向上を達成できる。
In constructing the shaft, first, the continuous wall 1 is formed, then the improved bottom plate 2 and the improved intermediate plate 3 are simultaneously formed, and thereafter, the ground 4 in the continuous wall 1 is dug down in order from the ground surface. . And an appropriate depth (1 to 1 as an example)
2m), the concrete wall 10 having a predetermined thickness is formed by spraying concrete on the inner surface (standing wall) of the continuous wall 1 which is exposed by the excavation, and is further formed on the concrete wall 10, for example, H-shaped. Support ring 11 made of steel
To build. After that, the concrete wall 10 is formed by digging down to the improved intermediate board 3 at once and spraying concrete on the exposed standing wall. At this time, the core material 6 embedded in each improvement body 5 constituting the continuous wall 1 strongly resists the tensile force, and the improved intermediate plate 3 provided in the intermediate region serves as the preceding underground beam to form the continuous wall. Even if 1 is supported from the inside and the inside of the continuous wall 1 is deeply dug at a time, the surrounding sediment will not collapse. Incidentally, the depth to be dug at one time is about 3 m in the case of the conventional construction method in which the core material 6 is not included in the continuous wall and the improved intermediate plate 3 is not provided, while according to the present construction method, It becomes 2 to 3 times (6 to 9 m), and the work efficiency can be improved accordingly.

【0013】その後、前記改良中間盤3を、例えば図1
に矢印Eにて示す切断線に沿って円形にくり抜いて、そ
の周縁部を支保リング3aとして残し、その下方を前記
改良底盤2まで掘り下げる。この時、連続壁1は、前記
改良中間盤3の残りである支保リング3aと改良底盤2
とで支保されているので、両者の間を一度に深く掘り下
げても周辺土砂が崩落することはない。そして、この掘
り下げを行った後は、露出した立て壁にコンクリートを
吹付けて上記同様のコンクリート壁10を形成する。な
お、改良中間盤3は、構築すべき立坑の深さが深い場合
は所定の間隔で複数造成するようにしても良いものであ
る。また、コンクリートの吹付けに際しては、立て壁と
の間に金網12(図2)を介装するようにしても良い。
Thereafter, the improved intermediate board 3 is, for example, shown in FIG.
It is hollowed out in a circular shape along the cutting line indicated by arrow E, leaving its peripheral edge as a support ring 3a, and the lower part thereof is dug down to the improved bottom plate 2. At this time, the continuous wall 1 has the support ring 3a and the improved bottom plate 2 which are the rest of the improved intermediate plate 3.
Since it is supported by and, even if you dig deep between the two at once, the surrounding sediment will not collapse. Then, after this digging, concrete is sprayed on the exposed standing wall to form a concrete wall 10 similar to the above. It should be noted that the improved intermediate board 3 may be formed in plural at predetermined intervals when the vertical shaft to be built is deep. In addition, when concrete is sprayed, a wire mesh 12 (FIG. 2) may be interposed between the wall and the standing wall.

【0014】こゝで、上記連続壁1を造成する工法につ
いて説明する。連続壁1の造成に際しては、図4に示す
ような自走式改良機械20を用意し、そのリーダー21
に連動可能に装着された2つの回転ユニット22,23
に前記芯材6となる鋼管24と注入ロッド25とを支持
させる。この時、鋼管24に挿入した注入ロッド25先
端の噴射ノズル26が鋼管24の先端から突出するよう
に両者を位置決めし、打込方向前側の回転ユニット22
に鋼管24の後端部を、打込方向後側の回転ユニット2
3に注入ロッド25の後端部をそれぞれ支持させる。ま
た、鋼管24および注入ロッド25の後端にはスイベル
27、28をそれぞれ装着し、鋼管24に装着したスイ
ベル27からは排泥ホース29を貯泥地(図示略)まで
延ばし、一方、注入ロッド25に装着したスイベル28
にはグラウトポンプ(図示略)から延ばしたグラウトホ
ース30をそれぞれ接続する。なお、噴射ノズル26か
らエアを同時噴射する場合は、注入ロッド25は二重管
構造となり、そのスイベル28にはグラウトとエアの注
入口が独立に設けられることになる。また、噴射ノズル
26の先端にカッタ31を設けるようにしても良い。さ
らに、リーダー21の先端部側には、通常、鋼管24を
案内するためのガイド32が設けられる。
The construction method for forming the continuous wall 1 will be described below. When constructing the continuous wall 1, a self-propelled improvement machine 20 as shown in FIG.
Two rotary units 22 and 23 mounted so that they can be linked to
The steel pipe 24 serving as the core material 6 and the injection rod 25 are supported by. At this time, both are positioned so that the injection nozzle 26 at the tip of the injection rod 25 inserted into the steel pipe 24 projects from the tip of the steel pipe 24, and the rotary unit 22 on the front side in the driving direction is positioned.
The rear end of the steel pipe 24 to the rotary unit 2 on the rear side in the driving direction.
The rear ends of the injection rods 25 are supported by the respective 3's. Further, swivels 27 and 28 are attached to the rear ends of the steel pipe 24 and the injection rod 25, respectively, and a sludge drain hose 29 is extended from the swivel 27 attached to the steel pipe 24 to a mud storage area (not shown). Swivel 28 attached to 25
A grout hose 30 extending from a grout pump (not shown) is connected to each. When air is simultaneously jetted from the jet nozzle 26, the injection rod 25 has a double pipe structure, and the swivel 28 is provided with grout and air injection ports independently. Further, the cutter 31 may be provided at the tip of the injection nozzle 26. Further, a guide 32 for guiding the steel pipe 24 is usually provided on the tip end side of the leader 21.

【0015】上記準備完了後、改良機械20のアーム2
0aの操作でリーダー21を地盤4上に垂直に立て、前
記回転ユニット22,23の作動により鋼管24と注入
ロッド25とを相互に逆方向へ回転させながら一体的に
地盤4中に打込む。そして、図5に示すように注入ロッ
ド25の先端が地表から所定距離だけ貫入した時点で、
注入ロッド25内にグラウトホース30およびスイベル
28を通じてグラウト(例えばセメントミルク)を圧送
する。すると、このグラウトは注入ロッド25の先端の
噴射ノズル26から、注入ロッド25と直角方向へジェ
ット流として噴射され、注入ロッド25の周りの土砂が
グラウトと攪拌混合される。この攪拌混合により、注入
ロッド25の周りには円柱状の混合層33が形成され、
この混合層33は、注入ロッド25の貫入に応じて次第
に下方へ拡張し、これと共に鋼管24がこの混合層33
内に貫入する。この間、グラウト注入により地盤4中に
発生した余剰スライムは、鋼管24と注入ロッド25と
の間隙を通じて上方へ流動し、スイベル27および排泥
ホース29を通じて図示を略す排泥地へ排出される。こ
のように地上から所定距離だけ貫入したところからグラ
ウトの噴射を介し、かつ鋼管24と注入ロッド25との
間隙を通じて余剰スライムを地上へ排出するので、地盤
改良中、土砂が地表へ噴き出すことはない。
After the above preparation is completed, the arm 2 of the improved machine 20
The leader 21 is erected vertically on the ground 4 by the operation of 0a, and the steel pipe 24 and the injection rod 25 are driven in the opposite directions by the operation of the rotating units 22 and 23, and are integrally driven into the ground 4. Then, as shown in FIG. 5, when the tip of the injection rod 25 penetrates a predetermined distance from the ground surface,
Grout (eg cement milk) is pumped into the injection rod 25 through the grout hose 30 and swivel 28. Then, the grout is jetted as a jet flow in a direction perpendicular to the pouring rod 25 from the jet nozzle 26 at the tip of the pouring rod 25, and the earth and sand around the pouring rod 25 is mixed with the grout by stirring. By this stirring and mixing, a cylindrical mixing layer 33 is formed around the injection rod 25,
The mixed layer 33 gradually expands downward in accordance with the penetration of the injection rod 25, and the steel pipe 24 moves with the mixed layer 33.
Penetrate inside. During this time, the excess slime generated in the ground 4 by the grout injection flows upward through the gap between the steel pipe 24 and the injection rod 25, and is discharged to the unillustrated waste mud through the swivel 27 and the mud hose 29. In this way, surplus slime is discharged to the ground from the place where it penetrates from the ground by a predetermined distance through the injection of grout and through the gap between the steel pipe 24 and the injection rod 25, so that the earth and sand will not be sprayed to the surface during the ground improvement. .

【0016】そして、所定深度まで注入ロッド25と鋼
管24とを貫入したら、鋼管24を残して注入ロッド2
5のみを引上げる。混合層33は次第に固化して前記改
良体5となり、この改良体5内に芯材6としての鋼管2
4が埋め込まれた一つの複合体7(図1)が形成され
る。したがって、この複合体7の形成を、立坑の計画線
L(図2)に沿って、相互に改良体5がラップするよう
に繰り返し行うことにより、上記した連続壁1が完成す
る。
When the injection rod 25 and the steel pipe 24 are penetrated to a predetermined depth, the injection rod 2 is left with the steel pipe 24 left.
Raise only 5. The mixed layer 33 gradually solidifies to become the improved body 5, and the steel pipe 2 as the core material 6 is provided in the improved body 5.
One complex 7 (FIG. 1) with 4 embedded is formed. Therefore, the continuous wall 1 described above is completed by repeating the formation of the composite body 7 along the planned line L (FIG. 2) of the vertical shaft so that the improvement bodies 5 wrap each other.

【0017】本実施の形態においては、改良底盤2およ
び改良中間盤3も、上記改良機械20を用いて造成す
る。この場合は、始めに上記噴射ノズル26からのグラ
ウトの噴射を停止した状態で、注入ロッド25と鋼管2
4とを立坑の計画底の下方域Bに貫入させ、該下方域B
の最下位置に噴射ノズル26が達した時点で、注入ロッ
ド25にグラウトを供給し、噴射ノズル26からのグラ
ウトの噴射を開始する。そして、注入ロッド25と鋼管
24とを一体的に一定速度で上昇させ、噴射ノズル26
が前記下方域Bの最上位置に到達したら、注入ロッド2
5へのグラウトの供給を断って、噴射ノズル26からの
グラウトの噴射を中止する。これにより、立坑の計画底
の下方域Bには所定の長さの円柱状の改良体8(図1)
が形成される。注入ロッド25と鋼管24との上昇は継
続されており、噴射ノズル26が中間域Cの最下位置に
到達したら、噴射ノズル26からのグラウトの噴射を再
開し、噴射ノズル26が該中間域Cの最上位置に到達し
た時点でグラウトの噴射を停止する。これにより、立坑
の中間域Cには所定の長さの円柱状の改良体9(図1)
が形成される。
In the present embodiment, the improved bottom plate 2 and the improved intermediate plate 3 are also constructed using the improved machine 20. In this case, with the injection of the grout from the injection nozzle 26 first stopped, the injection rod 25 and the steel pipe 2
4 and 4 penetrate into the lower area B of the planned bottom of the shaft,
When the injection nozzle 26 reaches the lowermost position of, the grout is supplied to the injection rod 25 and the injection of the grout from the injection nozzle 26 is started. Then, the injection rod 25 and the steel pipe 24 are integrally raised at a constant speed, and the injection nozzle 26
Reaches the uppermost position of the lower region B, the injection rod 2
The supply of grout to No. 5 is cut off, and the injection of grout from the injection nozzle 26 is stopped. As a result, in the lower area B of the planned bottom of the shaft, a cylindrical improvement body 8 of a predetermined length (Fig. 1)
Is formed. The ascent of the injection rod 25 and the steel pipe 24 is continued, and when the injection nozzle 26 reaches the lowermost position of the intermediate region C, the injection of grout from the injection nozzle 26 is restarted, and the injection nozzle 26 returns to the intermediate region C. The grout injection is stopped when it reaches the top position of. As a result, in the intermediate area C of the vertical shaft, a cylindrical improvement body 9 of a predetermined length (Fig. 1)
Is formed.

【0018】注入ロッド25と鋼管24とは、そのまま
地上まで引上げ、次に、改良機械20を操作して、上記
改良体8,9が相互にラップするように注入ロッド25
の貫入位置を変更し、上記した施工を繰返して新たな改
良体8,9を次々に連接していき、これにより改良底盤
2および改良中間盤3とが同時に効率良く造成される。
しかして、改良体8,9を形成する際、鋼管24と注入
ロッド25との隙を通じて余剰スライムが地上へ排出さ
れるので、地盤改良中、土砂が地表へ噴き出すことはな
い。したがって、ここで用いられる鋼管24は、芯材と
してではなく余剰スライムを排出するための導管として
機能することになる。
The injection rod 25 and the steel pipe 24 are pulled up to the ground as they are, and then the improved machine 20 is operated so that the improved bodies 8 and 9 wrap each other.
The penetration position is changed, and the above-described construction is repeated to connect new improved bodies 8 and 9 one after another, whereby the improved bottom plate 2 and the improved intermediate plate 3 are efficiently formed at the same time.
Then, when forming the improved bodies 8 and 9, the surplus slime is discharged to the ground through the gap between the steel pipe 24 and the injection rod 25, so that the earth and sand are not spouted to the ground surface during the ground improvement. Therefore, the steel pipe 24 used here functions not as a core material but as a conduit for discharging excess slime.

【0019】上記連続壁1の造成に際しては、例えば図
6に示すような工法を採用することができる。この工法
は、芯材6として複数の逆止弁35を設けた鋼管36を
用意し、先ず同図に示すようにこの鋼管36内に、先
端に偏心拡張ビット37を有する削孔ロッド38を挿入
し、削孔ロッド38と一体に偏心拡張ビット37を回転
させて地盤4を掘削しながら鋼管36を沈下させる。そ
して、鋼管36が所定深度まで沈下したところで、鋼管
36から削孔ロッド38を引抜いて、同図に示すよう
に注入機39を挿入する。注入機39は、拡縮可能な上
下一対の膨出体(ゴム製)39aを備えており、この一
対の膨出体39aを駆動手段(図示略)により膨出変形
させることで鋼管36内の任意の位置に固定される。注
入機39には、地上から延ばした注入管40を通じてグ
ラウトが圧送されるようになっており、このグラウト
は、前記一対の膨出体39aと鋼管36の内面との間に
形成される密閉の圧力室41に供給される。
In constructing the continuous wall 1, for example, a construction method as shown in FIG. 6 can be adopted. In this method, a steel pipe 36 provided with a plurality of check valves 35 as a core material 6 is prepared, and a drilling rod 38 having an eccentric expansion bit 37 at its tip is first inserted into the steel pipe 36 as shown in FIG. Then, the eccentric expansion bit 37 is rotated integrally with the drilling rod 38 to excavate the ground 4 and sink the steel pipe 36. Then, when the steel pipe 36 sinks to a predetermined depth, the drilling rod 38 is pulled out from the steel pipe 36, and the injector 39 is inserted as shown in FIG. The injector 39 includes a pair of upper and lower expandable bodies (made of rubber) 39a that can be expanded and contracted, and the pair of expanded bodies 39a is expanded and deformed by a driving means (not shown) to arbitrarily change the inside of the steel pipe 36. Fixed in position. The grout is pressure-fed to the pouring machine 39 through a pouring tube 40 extending from the ground, and the grout is a hermetic seal formed between the pair of swelling bodies 39a and the inner surface of the steel pipe 36. It is supplied to the pressure chamber 41.

【0020】そして、注入機39を鋼管36の先端部分
まで挿入した後、該注入機39を所定のピッチで引上
げ、図6乃至に示すように、各引上げ位置で一対の
膨出体39aを膨出変形させて圧力室41を形成し、こ
の圧力室41に注入管40を通じてグラウトを供給す
る。すると、各位置で鋼管36に設けた逆止弁35が開
弁して、鋼管36の周りにグラウトが噴射されて混合層
42が形成され、この混合層42が下方から上方へ順次
拡大し、この混合層42が固化して上記した改良体5
(図1〜3)となる。したがって、この改良体5内に前
記鋼管36をそのまま芯材6として残すことで、上記し
た複合体7(図1〜3)が形成される。
After inserting the injection machine 39 to the tip of the steel pipe 36, the injection machine 39 is pulled up at a predetermined pitch, and as shown in FIGS. 6 to 6, a pair of bulging bodies 39a is expanded at each pulling position. It is deformed to form a pressure chamber 41, and grout is supplied to the pressure chamber 41 through an injection pipe 40. Then, the check valve 35 provided in the steel pipe 36 is opened at each position, the grout is injected around the steel pipe 36 to form the mixed layer 42, and the mixed layer 42 sequentially expands from the lower side to the upper side, This mixed layer 42 is solidified to improve the above-mentioned improved body 5
(FIGS. 1 to 3). Therefore, by leaving the steel pipe 36 as the core material 6 in the improved body 5, the composite body 7 (FIGS. 1 to 3) described above is formed.

【0021】なお、立坑の計画線Lに沿って造成する連
続壁は、図7に示すような二重構造の連続壁45とする
ことができる。この場合、内側壁体46は、上記実施の
形態と同様に改良体47に芯材48を埋め込んだ複合体
49から構成し、この複合体49を相互に接して配列
し、一方、外側壁体50は、芯材を含まない円柱状の改
良体51から構成し、この改良体51を、前記内側壁体
46の複合体49の相互間に位置するようにかつ複合体
49に接するように配列することができる。
The continuous wall formed along the planned line L of the vertical shaft may be a continuous wall 45 having a double structure as shown in FIG. In this case, the inner wall body 46 is composed of the composite body 49 in which the core material 48 is embedded in the improvement body 47 as in the above-described embodiment, and the composite body 49 is arranged in contact with each other, while the outer wall body is arranged. Reference numeral 50 denotes a columnar improvement body 51 containing no core material, and the improvement body 51 is arranged so as to be located between the composite bodies 49 of the inner wall body 46 and in contact with the composite body 49. can do.

【0022】また、上記した連続壁1または45は、例
えば図8に示すように、複合体7をわずかラップするよ
うに配列し()、またはわずか離間するように配列し
て()、それらの相互間を、別途形成した改良柱52
により補強するようにしても、あるいは内側壁体46と
外側壁体50との相互間を、同じく別途形成した改良柱
52により補強するようにしても良い()。
Further, the continuous walls 1 or 45 described above are arranged so as to slightly wrap the composite 7 (), or arranged so as to be slightly separated (), as shown in FIG. Improved columns 52 formed separately from each other
Alternatively, the inner side wall body 46 and the outer side wall body 50 may be reinforced by the improved columns 52 which are also separately formed ().

【0023】また、立坑をシールド工事の発進・到達基
地として利用する場合は、掘削トンネルとの開通を容易
にするため、その開通部分に対応する複合体7,49の
芯材6,48を、プラスチックのような破壊性の良好な
材料から形成するのが望ましい。
When the vertical shaft is used as a starting and reaching base for shield construction, in order to facilitate the opening with the excavation tunnel, the core materials 6 and 48 of the composites 7 and 49 corresponding to the opening are It is desirable to form it from a material having good destructibility such as plastic.

【0024】[0024]

【発明の効果】以上、詳細に説明したように、本発明に
係る立坑構築工法によれば、立坑の計画域の周りを地盤
改良して造成した連続壁に杭を含ませ、かつ立坑の計画
域内の地盤中に地盤改良により先行梁として機能する改
良中間盤を設けるようにしたので、計画域周りの地盤が
著しく安定し、一度に掘り下げできる深さが大きくなっ
て、支保作業の回数が著しく削減され、工期の短縮と工
費の低減とを達成できる。
As described above in detail, according to the vertical shaft construction method of the present invention, the continuous wall formed by ground improvement around the planned area of the vertical shaft includes the piles and the vertical shaft is planned. Since an improved intermediate ground that functions as a leading beam is provided in the ground in the area by improving the ground, the ground around the planned area is remarkably stable, the depth that can be dug at one time becomes large, and the number of support operations is significant. It is possible to reduce the construction period and the construction cost.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る立坑構築の途中段階を示す断面図
である。
FIG. 1 is a cross-sectional view showing an intermediate stage of construction of a vertical shaft according to the present invention.

【図2】図1に示した立坑を上方から見た平面図であ
る。
FIG. 2 is a plan view of the shaft shown in FIG. 1 viewed from above.

【図3】連続壁の構造を示す斜視図である。FIG. 3 is a perspective view showing a structure of a continuous wall.

【図4】高圧噴射攪拌工法を実行する改良機とその使用
態様を示す側面図である。
FIG. 4 is a side view showing an improved machine for performing the high-pressure jet agitation method and its usage.

【図5】高圧噴射攪拌工法による改良体の形成過程を示
す模式図である。
FIG. 5 is a schematic diagram showing a process of forming an improved body by a high-pressure jet agitation method.

【図6】高圧噴射攪拌工法による改良体の、他の形成過
程を示す模式図である。
FIG. 6 is a schematic diagram showing another forming process of the improved body by the high-pressure injection stirring method.

【図7】連続壁の他の形態を示す模式的に示す平面図で
ある。
FIG. 7 is a plan view schematically showing another form of the continuous wall.

【図8】連続壁の、さらに他の態様を示す模式的に示す
平面図である。
FIG. 8 is a plan view schematically showing still another aspect of the continuous wall.

【符号の説明】[Explanation of symbols]

1 連続壁 2 改良底盤 3 改良中間盤 4 地盤 5 改良体 6 芯材 7 複合体 8,9 改良体 20 改良機 24 鋼管(芯材) 25 注入ロッド 26 噴射ノズル 35 逆止弁 36 鋼管(芯材) 37 偏心拡張ビット 38 削孔ロッド 41 注入機 A 立坑の計画域 B 立坑の下方域 C 立坑の中間域 L 立坑の計画線 1 continuous wall 2 improved bottom plate 3 improved intermediate plate 4 ground 5 improved body 6 core material 7 complex 8 and 9 improved body 20 improved machine 24 steel pipe (core material) 25 injection rod 26 injection nozzle 35 check valve 36 steel pipe (core material) ) 37 Eccentric extension bit 38 Drilling rod 41 Injector A Vertical planned area of vertical shaft B Lower area of vertical shaft C Intermediate area of vertical shaft L Vertical shaft planned line

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 高圧噴射攪拌工法により地盤改良して形
成した円柱状の改良体内に芯材を埋め込んで複合体とな
す施工を、立坑の計画線に沿って繰り返し行って連続壁
を造成し、次に、高圧噴射攪拌工法による改良体の形成
を前記連続壁内で繰り返し行って、前記立坑の計画底の
下方域並びにその計画深さの中間域にそれぞれ改良底
盤、改良中間盤を造成し、しかる後に、前記連続壁内の
地盤を地表から前記改良中間盤まで掘り下げ、さらに前
記改良中間盤をくり抜いてその下側地盤を前記改良底盤
まで掘り下げることを特徴とする立坑構築工法。
1. A continuous wall is constructed by repeatedly constructing a composite body by embedding a core material in a columnar improved body formed by improving the ground by a high-pressure jet agitation method, along a planned line of a shaft, Next, the formation of an improved body by a high-pressure jet agitation method is repeatedly performed in the continuous wall to form an improved bottom plate and an improved intermediate plate in the lower area of the planned bottom of the shaft and the intermediate area of the planned depth, respectively. Thereafter, the ground in the continuous wall is dug down from the ground surface to the improved intermediate ground, and the improved intermediate ground is hollowed out, and the lower ground is dug down to the improved bottom ground.
【請求項2】 連続壁を円筒形状に造成することを特徴
とする請求項1に記載の立坑構築工法。
2. The shaft construction method according to claim 1, wherein the continuous wall is formed into a cylindrical shape.
【請求項3】 改良底盤および改良中間盤を構成する改
良体を、注入ロッドの一回の回転移動で形成することを
特徴とする請求項1に記載の立坑構築工法。
3. The shaft construction method according to claim 1, wherein the improved bodies constituting the improved bottom plate and the improved intermediate plate are formed by a single rotational movement of the injection rod.
【請求項4】 注入ロッドを導管を挿通して延ばし、地
盤改良中に発生する余剰スライムを前記導管を通じて地
上へ排出することを特徴とする請求項3に記載の立坑構
築工法。
4. The shaft construction method according to claim 3, wherein the injection rod is extended through a conduit, and excess slime generated during ground improvement is discharged to the ground through the conduit.
JP8153088A 1996-05-24 1996-05-24 Method of shaft construction Pending JPH09317373A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8153088A JPH09317373A (en) 1996-05-24 1996-05-24 Method of shaft construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8153088A JPH09317373A (en) 1996-05-24 1996-05-24 Method of shaft construction

Publications (1)

Publication Number Publication Date
JPH09317373A true JPH09317373A (en) 1997-12-09

Family

ID=15554720

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8153088A Pending JPH09317373A (en) 1996-05-24 1996-05-24 Method of shaft construction

Country Status (1)

Country Link
JP (1) JPH09317373A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146770A (en) * 2000-11-10 2002-05-22 Shimizu Corp Soil improvement method
JP2002227180A (en) * 2001-01-31 2002-08-14 Newtech Kenkyusha:Kk Sheathing method and sheathing device
JP2013064315A (en) * 2012-12-03 2013-04-11 Mitsubishi Plastics Inc Reinforcing material mixed underground continuous wall and construction method therefor
JP2013064316A (en) * 2012-12-03 2013-04-11 Mitsubishi Plastics Inc Reinforcing material mixed underground continuous wall and construction method therefor
JP2014181531A (en) * 2013-03-21 2014-09-29 Penta Ocean Construction Co Ltd Construction method for earth retaining structure, and earth retaining structure
JP2016079569A (en) * 2014-10-10 2016-05-16 株式会社竹中工務店 Construction method for underground strut
CN112081176A (en) * 2020-09-11 2020-12-15 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
JP2021059856A (en) * 2019-10-03 2021-04-15 積水ハウス株式会社 Excavation agitator

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6311793A (en) * 1986-07-02 1988-01-19 東亜グラウト工業株式会社 Method of shaft construction
JPH01124896U (en) * 1988-02-20 1989-08-25
JPH0146648B2 (en) * 1984-04-26 1989-10-09 Tokyo Denryoku Kk
JPH05321511A (en) * 1992-05-21 1993-12-07 Nippon Steel Corp Construction method for underground vessel in weak ground

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0146648B2 (en) * 1984-04-26 1989-10-09 Tokyo Denryoku Kk
JPS6311793A (en) * 1986-07-02 1988-01-19 東亜グラウト工業株式会社 Method of shaft construction
JPH01124896U (en) * 1988-02-20 1989-08-25
JPH05321511A (en) * 1992-05-21 1993-12-07 Nippon Steel Corp Construction method for underground vessel in weak ground

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146770A (en) * 2000-11-10 2002-05-22 Shimizu Corp Soil improvement method
JP2002227180A (en) * 2001-01-31 2002-08-14 Newtech Kenkyusha:Kk Sheathing method and sheathing device
JP4633273B2 (en) * 2001-01-31 2011-02-16 有限会社ニューテック研究▲しゃ▼ Earth retaining method and equipment
JP2013064315A (en) * 2012-12-03 2013-04-11 Mitsubishi Plastics Inc Reinforcing material mixed underground continuous wall and construction method therefor
JP2013064316A (en) * 2012-12-03 2013-04-11 Mitsubishi Plastics Inc Reinforcing material mixed underground continuous wall and construction method therefor
JP2014181531A (en) * 2013-03-21 2014-09-29 Penta Ocean Construction Co Ltd Construction method for earth retaining structure, and earth retaining structure
JP2016079569A (en) * 2014-10-10 2016-05-16 株式会社竹中工務店 Construction method for underground strut
JP2021059856A (en) * 2019-10-03 2021-04-15 積水ハウス株式会社 Excavation agitator
CN112081176A (en) * 2020-09-11 2020-12-15 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
CN112081176B (en) * 2020-09-11 2022-02-01 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage

Similar Documents

Publication Publication Date Title
JPH07113214B2 (en) Excavation device for underground wall and construction method using the device
JP3769637B2 (en) Slope stabilization method
JP3850802B2 (en) Steel pile and its construction method
JPH09317373A (en) Method of shaft construction
JP2019039140A (en) Method for constructing ground improvement body and method for constructing pile
CN1504613A (en) Forming method for water-proof pile fender and screw drill therefor
JP2008031772A (en) Construction method of precast pile, and cover for use in the construction method
JP3750186B2 (en) Construction method of underground continuous wall
JP6730121B2 (en) Underground wall construction method
JPH1025734A (en) Bearing-pile reinforcing structure of existing structure and reinforcing method thereof
JP4615841B2 (en) Synthetic pile construction method and synthetic pile
JPH03119219A (en) Jet grout type underground retaining wall building method
JPH11158865A (en) Underground structure having wall using steel sheet pile as core and method for constructing the same
KR102260596B1 (en) Site Construction Method Of Base Top Pile For Ground Reinforcement
JPS6131244B2 (en)
JPH089862B2 (en) Chemical injection method
JPH0470422A (en) Open caisson method
JP3005741B2 (en) Ground improvement method
JP3455157B2 (en) Shoring construction method
KR800000650B1 (en) Method of forming continuous underground walls on weak footing
JPS58120918A (en) Burying method for pile
JP2001164550A (en) Improvement method of construction ground for underground structure
JP2002021063A (en) Method for constructing earth retaining wall
JP4031967B2 (en) Box-type buckets used in the construction method of underground underground walls, and impermeable wall construction methods for waste landfills
JP3944005B2 (en) Chemical injection method to press-fit shaft and its excavation ground