JP3455157B2 - Shoring construction method - Google Patents

Shoring construction method

Info

Publication number
JP3455157B2
JP3455157B2 JP2000088893A JP2000088893A JP3455157B2 JP 3455157 B2 JP3455157 B2 JP 3455157B2 JP 2000088893 A JP2000088893 A JP 2000088893A JP 2000088893 A JP2000088893 A JP 2000088893A JP 3455157 B2 JP3455157 B2 JP 3455157B2
Authority
JP
Japan
Prior art keywords
pipe
injection
construction method
hardening material
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000088893A
Other languages
Japanese (ja)
Other versions
JP2001280063A (en
Inventor
豊次 澤村
渉 中西
Original Assignee
株式会社エヌ・アイ・ティ
ジオテクノ株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社エヌ・アイ・ティ, ジオテクノ株式会社 filed Critical 株式会社エヌ・アイ・ティ
Priority to JP2000088893A priority Critical patent/JP3455157B2/en
Publication of JP2001280063A publication Critical patent/JP2001280063A/en
Application granted granted Critical
Publication of JP3455157B2 publication Critical patent/JP3455157B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はトンネル等、横坑の掘削
にあたり、地山の支保覆工や軟弱部分の安定を目的とし
て掘削鏡の周囲側面に挿入管をパイプルーフ状に並列打
設して坑壁の崩壊を防止する支保工の補強芯材とすると
共に、これを基礎としてラスメッシュの張設、防水シー
トの張設、支保配筋、内装コンクリート型枠の構築を行
う支保工の構築工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention, when excavating a horizontal shaft such as a tunnel, inserts insertion pipes in parallel in a pipe roof shape on the peripheral side surface of the excavating mirror for the purpose of supporting the lining of the natural ground and stabilizing the weak portion. The reinforcement core material of the support work to prevent collapse of the mine wall, and the construction of the support work to build the lath mesh, the waterproof sheet, the support reinforcement bar, and the interior concrete formwork on the basis of this reinforcement core material. It is related to the construction method.

【0002】[0002]

【従来の技術】支保工の補強芯材として鋼管による挿入
管を並列打設して支保工を構築する工法は従来から様々
な方法によって行われてきているが、いずれも、挿入管
による補強芯材を中心として周囲に硬化材層を造成して
並列するものとなっている。
2. Description of the Related Art Conventionally, various methods have been used for constructing a supporting structure by placing an insertion pipe made of a steel pipe in parallel as a reinforcing core material for a supporting structure. A hardened material layer is formed around the material and arranged in parallel.

【0003】また、挿入管の地山への挿入は掘進方向に
若干拡開する角度方向に挿入され、挿入管後端部の所定
長さを前工程において挿入された挿入管先端部と重合ラ
ップさせて打設することにより、補強芯材の掘進方向へ
の連続性を確保すると共に挿入口でのパック工程スペー
スとして利用してきた。
In addition, the insertion tube is inserted into the ground by inserting it in an angular direction in which it slightly expands in the direction of excavation, and a predetermined length of the rear end of the insertion tube is overlapped with the tip of the insertion tube inserted in the previous step. By placing the reinforcing core material in the excavation direction, the reinforcement core material is used as a packing process space at the insertion port.

【0004】更に、地山内に存在する帯水層の地下水に
対しては、別途に水抜き管を設定して対応してきたほ
か、挿入管挿入部より前方の深奥部に更に硬化材注入を
行うことによって、掘進方向への連続性を確保する挿入
口でのパック工程スペースとすることはなかった。
Further, for groundwater in the aquifer existing in the ground, a drainage pipe has been set separately, and a hardening agent is further injected deep inside the insertion pipe insertion portion. As a result, the packing process space at the insertion opening that ensures continuity in the digging direction was not provided.

【0005】挿入管による補強芯材を中心として周囲に
柱状の硬化材層を造成する工法は、隣接させる柱状の硬
化材層挿入管を通じて補強芯材の内外に注入材を圧送充
填するにあたっては、挿入管及び挿入孔に封入されたエ
アーが地山などに貯留され注入圧等によって噴発するの
を防ぐため、挿入管及び挿入孔に封入されたエアーを抜
くエアー抜き管、注入材を圧送噴出する噴出管、所定位
置に設けたパッカー嚢体に膨張圧を封入するパッカー作
動管等のインサート管を挿入管内に挿通して行なってい
る。
In the method of forming a columnar hardening material layer around the reinforcing core material by the insertion tube, the injection material is pressure-fed into and out of the reinforcing core material through the adjoining pillar-shaped hardening material layer insertion tube. In order to prevent the air enclosed in the insertion tube and the insertion hole from being stored in the ground and ejected by injection pressure, etc., the air enclosed in the insertion tube and the insertion hole is removed and the injection material is ejected under pressure. Insertion pipes such as a jetting pipe and a packer actuating pipe that seals inflation pressure in a packer bag provided at a predetermined position are inserted into the insertion pipe.

【0006】[0006]

【発明が解決しようとする問題点】従来の挿入管による
補強芯材を中心として周囲に硬化材層を造成する工法
は、隣接する柱状硬化材層の境界重合部が注入材の浸透
或いは噴流到達域によって重合範囲が決定され、どの程
度の重合ラップが行なわれているのか確認できないとい
う極めて不確実な要素を含んでいる。
[Problems to be Solved by the Invention] In the conventional method of forming a hardening material layer around a reinforcing core material by an insertion tube, the boundary polymerized portion of the adjacent column hardening material layers penetrates the injection material or reaches the jet flow. There is a very uncertain factor that the area determines the extent of polymerization and it cannot be confirmed how much polymerization wrap is performed.

【0007】更に、一番弱い重合ラップ部に補強芯材が
存在せず、重合ラップ部の構造が不完全なためにその部
分の地山が抜け落ちるなどの問題も生じている。
Further, since the reinforcing core material does not exist in the weakest overlapped lap portion and the structure of the overlapped lap portion is incomplete, there is a problem that the ground in that portion falls off.

【0008】また、地山内に存在する帯水層の地下水に
対しては、別途に水抜き管を設定しなければならないほ
か、挿入管挿入部より前方の深奥部には硬化材注入が行
われないため、入口から更に深奥部に支保工を延進して
構築していく場合に、延進部の掘削開始部に支保手段を
講じなければならない。
Further, for groundwater in the aquifer existing in the ground, a drainage pipe must be separately set, and a hardening material is injected into the deep depth in front of the insertion pipe insertion portion. Since there is no such structure, when the support work is further extended from the entrance to the deeper part, the support means must be provided at the excavation start part of the extension part.

【0009】補強芯材の打設は、前工程において挿入さ
れた挿入管先端部と新たに打設する挿入管後端部を所定
長さだけ重合ラップさせるため、挿入管の挿入口は前工
程による並列挿入管から1段下げた位置に採らなければ
ならなかった。
When the reinforcing core material is cast, the tip of the insertion tube inserted in the previous step and the rear end of the insert tube to be newly placed are overlapped by a predetermined length. Had to be taken one step down from the parallel insertion tube by.

【0010】そのため、芯材の打設に次ぐ防水工事、H
鋼による支保配筋とコンクリート吹き付けによって構成
される支保層が、打設工程ごとに段差を生じ坑壁が波打
ち状態となってしまうほか、3mから3.5 mに及ぶ重合
ラップ部分に資材面と労力面の双方から大きな無駄を生
じるという問題があった。
For this reason, waterproofing work following the placement of the core material, H
The supporting layer made up of steel supporting bars and concrete spraying creates a step at each pouring process, causing the corrugated wall to become wavy, and the material and labor aspects of the overlapped lap extending from 3 m to 3.5 m. There was a problem that a big waste is generated from both sides.

【0011】[0011]

【問題点を解決するための手段】本発明は、以上のよう
な問題点に対処し、挿入管と挿入管の中間位置を中心と
し、両端に挿入管を取り込んだ柱状の硬化材層を隣接さ
せて順次造成することにより、柱状硬化材層の重合ラッ
プ部に支保工の補強芯材として挿入される挿入管を位置
させ、重合ラップ部を強化すると共に、挿入管を水抜き
管や延進深奥部への硬化材注入のためのケーシングガイ
ドとしても利用できるようにした。
SUMMARY OF THE INVENTION The present invention addresses the above-mentioned problems, and adjoins a column-shaped hardening material layer having insertion tubes at both ends with the insertion tube and the intermediate position of the insertion tube as the center. By doing so, the insertion pipe to be inserted as a reinforcing core material for supporting work is positioned in the overlapped lap portion of the columnar hardened material layer to strengthen the overlapped lap portion, and the insertion pipe is drained or extended. It can also be used as a casing guide for injecting hardener into the deep interior.

【0012】また、挿入管後端部の所定長さを破砕など
によって切り離し可能に構成することにより、地山への
挿入打設後重合ラップ部分を、ショベル等で切削して挿
入管の切り離し可能部分を挿入部地山と共に切除して坑
壁段差を均せるように構成した。
Further, by constructing the predetermined length of the rear end portion of the insertion tube so that it can be cut off by crushing or the like, it is possible to cut off the insertion tube by cutting the overlapped lap portion after insertion and placement into the natural ground with a shovel or the like. The part was cut out together with the ground of the insertion part so that the pit wall level could be leveled.

【0013】[0013]

【実施例】以下図面に従って本発明の実施例を説明す
る。1は挿入管で管壁に複数の開放孔11・・が設けら
れ、本体は鋼管等によって構成されるが、後端部の所定
長さは塩ビにガラス繊維を加えたような脆い素材でショ
ベル等により破砕可能な切離部12として構成されてい
る。なお、地山内に帯水層が存在しない等、施工環境に
よって必要がない場合には、開放孔11・・を設けないこ
とは勿論である。
Embodiments of the present invention will be described below with reference to the drawings. Reference numeral 1 is an insertion tube, which is provided with a plurality of open holes 11 ... on the tube wall, and the main body is made of steel pipe, etc., but the predetermined length of the rear end is a shovel made of a brittle material such as glass fiber added to PVC. It is configured as a separating portion 12 that can be crushed by the above. In addition, it is needless to say that the opening hole 11 ... Is not provided when there is no need for the construction environment such as when there is no aquifer in the ground.

【0014】2は推進杆で先端部にダウンザホールハン
マー22、又は適当な掘削ビットを備えると共に、挿入管
1を脱離可能に支持する支持機構を備え、推進装置Aの
ドリフタBの駆動により、挿入管1を支持したまま地山
Gに穿孔推進される。
Reference numeral 2 denotes a propulsion rod, which is provided with a down-the-hole hammer 22 or an appropriate excavating bit at the tip thereof and a support mechanism for detachably supporting the insertion tube 1, and is inserted by driving the lifter B of the propulsion device A. The pipe 1 is pierced and propelled by the natural ground G while supporting the pipe 1.

【0015】挿入管1の地山Gへの挿入を完了すると、
推進装置AのドリフタBにより、推進杆2を挿入管1か
ら離脱後退させて引き抜くと共に、挿入された挿入管1
から所定間隔をもった位置に掘削鏡面の側周に沿って挿
入管をパイプルーフ状に並列打設して行くものである。
なお、この挿入管挿入手段は一例であり、適宜手段によ
って挿入管を地山に挿入すれば良いことは勿論である。
When the insertion of the insertion tube 1 into the natural ground G is completed,
By the lifter B of the propulsion device A, the propulsion rod 2 is detached from the insertion tube 1 and retracted and pulled out, and the inserted insertion tube 1 is inserted.
The insertion pipes are placed in parallel in a pipe roof shape along the side circumference of the excavation mirror surface at a position spaced by a predetermined distance from.
It should be noted that this insertion tube insertion means is an example, and it goes without saying that the insertion tube may be inserted into the natural ground by an appropriate means.

【0016】挿入管1が地山G内に挿入されると、地山
内の帯水層からの飽和地下水は開放孔11・・によって挿
入管1内に導入され、管内を流下して挿入口から外部に
排出されて挿入管の挿入部は適度な含水率による乾燥状
態とされる。
When the insertion pipe 1 is inserted into the natural ground G, saturated groundwater from the aquifer in the natural ground is introduced into the insertion pipe 1 through the open holes 11 ... After being discharged to the outside, the insertion portion of the insertion tube is brought into a dry state with an appropriate water content.

【0017】掘削鏡面の側周に沿った挿入管の並列打設
を完了した段階で、挿入管と挿入管の中間位置Xに注入
管3を挿入し、硬化材を注入管3内に圧送して先端から
噴出もしくは噴射させつつ後退させることにより、挿入
管と挿入管の中間位置を中心とし、両端に挿入管を取り
込んだ柱状の硬化材層を造成するものである。
At the stage where the parallel placement of the insertion tubes along the side circumference of the excavation mirror surface is completed, the injection tube 3 is inserted at an intermediate position X between the insertion tube and the insertion tube, and the hardening material is pumped into the injection tube 3. By ejecting from the tip or retreating while ejecting, the columnar hardening material layer with the insertion tube at both ends and the insertion tube taken in at the middle position is formed.

【0018】この場合、地盤硬化材を高圧噴射する場合
の注入管3は、先端側壁に噴射ノズルを開口して回動手
段を備えたものを用い、単純に硬化材を噴出する場合は
先端部を開放したものでも、先端部を閉鎖して先端側壁
に噴出孔を設けたものでも良い。
In this case, the injection pipe 3 for high-pressure injection of the ground hardening material is provided with a turning means by opening an injection nozzle on the side wall of the tip, and when the hardening material is simply ejected, the tip portion is used. May be opened, or the tip may be closed and a jet hole is provided in the side wall of the tip.

【0019】この柱状硬化材層の造成方法の選択は、挿
入管と挿入管の間隔の長さにより、施工環境に応じて選
択されるものである。また、注入管3による柱状硬化材
層の造成後、更に、挿入管1内に地盤硬化材を圧送し開
放孔11・・から周辺土壌に噴出させて柱状硬化材層の隣
接接合部に重合硬化層Zを構成すれば、支保構造は一層
強化される。
The method of forming the columnar hardened material layer is selected according to the construction environment depending on the length of the interval between the insertion pipes. Further, after the columnar hardened material layer is formed by the injection pipe 3, the ground hardened material is further pumped into the insertion pipe 1 and ejected from the open holes 11 ... By constructing the layer Z, the supporting structure is further strengthened.

【0020】地盤硬化材の噴射もしくは噴出により両端
に挿入管1a、1bを取り込んだ柱状の硬化材層が造成さ
れ、隣接する硬化材層D1とD2の接合部には重合ラップ部
Yが構成されてその中央部に挿入管1が補強芯材として
位置するようになる。
A column-shaped hardening material layer incorporating the insertion pipes 1a and 1b is formed at both ends by jetting or jetting of the ground hardening material, and a superposition wrap portion Y is formed at a joint portion between adjacent hardening material layers D1 and D2. The insertion tube 1 is positioned at the center of the lever as a reinforcing core material.

【0021】柱状硬化材層が並列造成されて第1シフト
の基礎施工が終わった段階で、挿入管1内に注入ロッド
31を更に挿入し、挿入管1の終端より先の延進深奥部に
注入ロッド31を推進して地盤硬化材を圧送して延進深奥
部に注入して硬化材層Eを造成する。
At the stage where the columnar hardening material layers are formed in parallel and the first shift foundation construction is completed, the injection rod is inserted into the insertion tube 1.
Further, 31 is inserted, and the injection rod 31 is propelled to the deep inside of the extension beyond the end of the insertion tube 1 to pump the ground hardening material and inject it into the deep inside of the extension to form the hardened material layer E.

【0022】この硬化材層Eは、第1シフトの奥に支保
工を延進して構築していく場合に、延進部の第2シフト
掘削開始部を支保するものとなり、特別の支保手段を講
ずることなく第2シフトの挿入管並列打設を開始するこ
とができる。
The hardened material layer E supports the second shift excavation start portion of the extension portion when the support work is extended and constructed in the depth of the first shift, and special support means is provided. It is possible to start the insertion pipe parallel placement of the second shift without taking the above procedure.

【0023】注入ロッド31による注入を終わった段階
で、注入ロッド31は挿入管1から引き抜かれるが、前記
のように、更に、挿入管1内に地盤硬化材を圧送し開放
孔11・・から周辺土壌に噴出させて柱状硬化材層の隣接
接合部に重合硬化層Zを構成すれば、支保構造は一層強
化され、挿入管1内には硬化材等が充填されて補強芯材
としての強度が高められる。また、注入ロッド31による
注入は硬化材の噴出、噴射など施工環境に応じた適宜手
段によって行なわれる。
At the stage where the injection by the injection rod 31 is completed, the injection rod 31 is pulled out from the insertion tube 1, but as described above, the ground hardening material is further pressure-fed into the insertion tube 1 through the open hole 11 .. If the polymerized hardened layer Z is formed at the adjacent joint portion of the columnar hardened material layer by being ejected to the surrounding soil, the supporting structure is further strengthened, and the insertion tube 1 is filled with the hardened material or the like to have strength as a reinforcing core material. Is increased. Further, the injection by the injection rod 31 is performed by an appropriate means according to the construction environment, such as jetting and jetting of the hardening material.

【0024】このようにして挿入管1の打設とこれを連
接する柱状硬化材層の造成を終わると、支保された切羽
部分を掘削して横坑が掘進される。
When the insertion pipe 1 and the columnar hardened material layer connecting the insertion pipe 1 are finished in this manner, the supported face portion is excavated and the side shaft is excavated.

【0025】並列挿入管の先端部近くまで掘削した段階
で、前工程による並列挿入管から1段下げた位置に挿入
口を設定して、再び同様の工程により挿入管並列打設と
柱状硬化材層の造成、深奥注入を行って支保を確保しな
がら横坑を掘進して行くと共に、前の打設工程により段
差を生じ、坑壁に突出する挿入部の地山を挿入管1の切
離可能部分12と共に切除して均平化する。
At the stage where the parallel insertion tube has been excavated near the tip, the insertion port is set at a position one step lower than the parallel insertion tube in the previous step, and the insertion tube is placed in parallel and the columnar hardened material is again subjected to the same steps. While excavating the side pit while securing support by performing layer formation and deep injection, a step is created by the previous placing process, and the ground of the insertion part protruding to the mine wall is separated from the insertion pipe 1. Cut with the feasible part 12 and level.

【0026】均平化した坑壁にラスメッシュの張設、防
水シートの張設、H鋼による支保配筋とコンクリート吹
き付けによって支保層を構成し、コンクリート型枠を組
んで坑壁の内装仕上げを行うものである。
A lath mesh is laid on a leveled pit wall, a waterproof sheet is laid, a supporting layer is constructed by supporting steel reinforcement bars and concrete spraying, and a concrete formwork is assembled to finish the interior of the pit wall. It is something to do.

【0027】本発明は以上のように構成したので、従
来、一番弱いとされる重合ラップ部に補強芯材が配設さ
れて支保構造を極めて強度の高いものにできると共に、
これまで別途に手当しなければならなかった水抜きや後
続工程開始部の支保を一挙に行なうことができるように
なったものである。
Since the present invention is configured as described above, the reinforcing core member is disposed in the overlapping lap portion, which is conventionally considered to be the weakest, and the supporting structure can be made extremely strong.
It is now possible to perform drainage and support for the subsequent process start part, which had to be separately treated until now.

【0028】[0028]

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例で、挿入管の対象地盤中におけ
る挿入打設の施工状況を示す全体側面図
FIG. 1 is an overall side view showing a construction situation of an insertion driving in an object ground of an insertion pipe in an embodiment of the present invention.

【図2】同じく、挿入管を対象地盤に挿入打設した後、
挿入管の切離可能部分を切除して均平化する施工状況を
示す全体側面図
[Fig. 2] Similarly, after inserting and inserting the insertion pipe into the target ground,
Overall side view showing a construction situation in which the separable part of the insertion tube is cut out and leveled

【図3】横坑の掘削鏡面に並列挿入された挿入管打設状
況と連接される柱状硬化材層の状態を示す横坑の全体正
面図
FIG. 3 is an overall front view of a horizontal shaft showing a state of a columnar hardened material layer that is connected to an insertion pipe inserted in parallel with the excavation mirror surface of the horizontal shaft.

【図4】並列挿入された挿入管と連接造成された柱状硬
化材層の重合ラップ部の状況を示す拡大正面図
FIG. 4 is an enlarged front view showing a state of an overlapped lap portion of a columnar hardened material layer which is continuously connected to an insertion tube inserted in parallel.

【図5】推進杆を装填して挿入管を対象地盤中に推進挿
入する状況を示す挿入管先端部の拡大側面図
FIG. 5 is an enlarged side view of the tip of the insertion tube, showing a state in which the propulsion rod is loaded and the insertion tube is propelledly inserted into the target ground.

【図6】深奥部への注入状況を示す挿入管先端部と管内
に挿入された注入ロッド先端部の状態を示す側面図
FIG. 6 is a side view showing a state of a distal end portion of an insertion tube and a distal end portion of an injection rod inserted into the tube, showing a state of injection into a deep portion.

【符号の説明】[Explanation of symbols]

1 挿入管 11 開放孔 12 挿入管の切離部 1a、1b 柱状硬化材層の両端に取り込まれた挿入管 2 推進杆 22 ダウンザホールハンマー 3 注入管 31 深奥部注入ロッド A 推進装置 B ドリフタ C 横坑掘削部 D 柱状硬化材層 D1、D2 隣接する硬化材層 E 延進深奥部硬化材層 G 地山 X 挿入管と挿入管の中間位置 Y 隣接する硬化材層の重合ラップ部 Z 隣接する硬化材層の接合部に造成される重
合硬化層
1 Insertion pipe 11 Open hole 12 Separation part 1a, 1b of insertion pipe Insertion pipe 2 taken into both ends of columnar hardened material layer 2 Propulsion rod 22 Down the hole hammer 3 Injection pipe 31 Deep injection rod A Propulsion device B Drifter C Horizontal shaft Excavation section D Column-shaped hardening material layers D1 and D2 Adjacent hardening material layer E Extension hardening part at deep depth G Ground X X Intermediate position between insertion tube and insertion tube Y Overlap lap portion of adjoining hardening material layer Z Adjacent hardening material Polymerized hardened layer formed at the junction of layers

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平8−302665(JP,A) 特開 平9−317373(JP,A) 特開 平3−197794(JP,A) 特開 平5−280033(JP,A) 特開 平11−193686(JP,A) (58)調査した分野(Int.Cl.7,DB名) E21D 9/04 E02D 3/12 101 ─────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A 8-302665 (JP, A) JP-A 9-317373 (JP, A) JP-A 3-197794 (JP, A) JP-A 5- 280033 (JP, A) JP-A-11-193686 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) E21D 9/04 E02D 3/12 101

Claims (6)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 トンネル等、横坑の掘削鏡面の側周に所
定間隔をもって挿入管をパイプルーフ状に並列打設し、
並列した挿入管と挿入管の中間位置に、注入管を挿入
し、所定深度において注入管に地盤硬化材を圧送しつつ
後退させることにより、挿入管と挿入管の中間位置を中
心とし、両端に挿入管を取り込んだ柱状の硬化材層を隣
接させて順次造成することを特徴とする支保工の構築工
1. An insertion pipe is placed in parallel in a pipe roof shape at a predetermined interval on a side circumference of an excavation mirror surface of a horizontal shaft such as a tunnel,
By inserting the injection pipe at the intermediate position between the insertion pipe and the insertion pipe that are arranged in parallel, and retreating while pumping the ground hardening material to the injection pipe at a predetermined depth, centering the intermediate position between the insertion pipe and the insertion pipe, Construction method for supporting work, characterized in that columnar hardened material layers incorporating the insertion tube are adjacently constructed in sequence
【請求項2】 注入管を先端部側壁に噴射孔を設けた注
入ロッドとし、硬化材を噴射しつつ回動後退させること
により、柱状の硬化材層を円柱状に造成するようにした
請求項1記載の支保工の構築工法
2. A column-shaped hardening material layer is formed in a cylindrical shape by using the injection pipe as an injection rod having an injection hole formed in a side wall of a tip portion thereof and rotating and retracting while injecting a hardening material. Construction method of support work described in 1.
【請求項3】 挿入管を側周壁面に多数の開放孔を設け
た多孔管に構成し、地山内に存在する帯水層の地下水を
多孔管に導入して水抜きを行うようにした請求項1又は
請求項2記載の支保工の構築工法
3. The insertion pipe is configured as a perforated pipe having a large number of open holes on its side wall surface, and groundwater in an aquifer existing in the ground is introduced into the perforated pipe to drain water. Construction method for supporting work according to claim 1 or claim 2.
【請求項4】 挿入管をケーシングガイドとして、挿入
管内に注入ロッドを挿入して挿入管の挿入先端より前方
に注入ロッドを挿入し、挿入管挿入部より前方の深奥部
に硬化材注入を行うようにした請求項1又は請求項2又
は請求項3記載の支保工の構築工法
4. The injection tube is used as a casing guide, the injection rod is inserted into the insertion tube, the injection rod is inserted forward of the insertion tip of the insertion tube, and the hardening material is injected deep inside the insertion tube insertion portion. Construction method for supporting work according to claim 1 or claim 2 or claim 3
【請求項5】 側周壁面に多数の開放孔を設けた挿入管
内に地盤硬化材を圧送し、開放孔を通じて周辺土壌に噴
出させ、柱状硬化材層の隣接接合部に重合硬化層を造成
するようにした請求項3又は請求項4記載の支保工の構
築工法
5. A ground hardening material is pressure-fed into an insertion pipe having a large number of open holes formed in its side wall surface and ejected to surrounding soil through the open holes to form a polymerized hardened layer at an adjacent joint portion of columnar hardening material layers. The construction method for supporting work according to claim 3 or claim 4
【請求項6】 挿入管後端部の所定長さを切除可能に構
成し、構築施工完了後に坑壁に突出する挿入部の地山を
切除して坑壁の均らし仕上げを行なうようにした請求項
1又は請求項2又は請求項3又は請求項4又は請求項5
記載の支保工の構築工法
6. A predetermined length of the rear end portion of the insertion pipe is configured to be cut, and the ground of the insertion portion projecting into the mine wall is cut off after completion of the construction work so that the pit wall is evenly finished. Claim 1 or Claim 2 or Claim 3 or Claim 4 or Claim 5
Construction method of the support work described
JP2000088893A 2000-03-28 2000-03-28 Shoring construction method Expired - Fee Related JP3455157B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000088893A JP3455157B2 (en) 2000-03-28 2000-03-28 Shoring construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000088893A JP3455157B2 (en) 2000-03-28 2000-03-28 Shoring construction method

Publications (2)

Publication Number Publication Date
JP2001280063A JP2001280063A (en) 2001-10-10
JP3455157B2 true JP3455157B2 (en) 2003-10-14

Family

ID=18604709

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000088893A Expired - Fee Related JP3455157B2 (en) 2000-03-28 2000-03-28 Shoring construction method

Country Status (1)

Country Link
JP (1) JP3455157B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103104265A (en) * 2013-02-05 2013-05-15 北京首尔工程技术有限公司 Advanced lining method and lining equipment used in construction of weak surrounding rock tunnel

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101825039B1 (en) * 2016-05-11 2018-02-27 강릉건설(주) Ground reinforcement method of messer shield tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103104265A (en) * 2013-02-05 2013-05-15 北京首尔工程技术有限公司 Advanced lining method and lining equipment used in construction of weak surrounding rock tunnel

Also Published As

Publication number Publication date
JP2001280063A (en) 2001-10-10

Similar Documents

Publication Publication Date Title
US3429126A (en) Method of producing a continuous bore pile wall
JP5282541B2 (en) How to prevent lifting of the lining body
JP4625815B2 (en) Non-open-cutting construction method for underground structures
JP3714395B2 (en) Reinforcement method for the ground below existing structures
JP3455157B2 (en) Shoring construction method
KR101442822B1 (en) Apparatus for inserting steel pipe and simultaneous horizontal high pressure jet-grouting in a tunnel supporting, and Method for inserting steel pipe and high pressure jet grouting with it
JP3931123B2 (en) Non-open-cutting construction method for underground structures
JP4083336B2 (en) How to build a tunnel
JP4214033B2 (en) Construction method of shaft
JPH09317373A (en) Method of shaft construction
JP2594864B2 (en) Widening method of underground tunnel
JP4480907B2 (en) Tunnel excavation method
JP4633273B2 (en) Earth retaining method and equipment
JP5282542B2 (en) Ground deformation prevention method and ground deformation prevention structure
JP2762935B2 (en) Horizontal mortar pile construction method
JP2966173B2 (en) Tunnel excavation ground reinforcement method
JP2000328560A (en) Method of creating steel pipe column row earth retaining wall
KR102117392B1 (en) Method for constructing earth retaining wall
JP4180347B2 (en) Construction method of underground continuous wall and underground continuous wall
JP2000328561A (en) Underground water flowing construction method in soil cement column row earth retaining wall
JP4414844B2 (en) Reinforcement method of natural ground
JP2004238981A (en) Method for constructing tunnel
JPH0776819A (en) Improving method for ground of tunnel excavation part and peripheral part thereof
JP3944005B2 (en) Chemical injection method to press-fit shaft and its excavation ground
KR20220128814A (en) Construction method of retaining wall using cip wall

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees