JPH084203A - Steel framed reinforcement beam and execution method thereof - Google Patents

Steel framed reinforcement beam and execution method thereof

Info

Publication number
JPH084203A
JPH084203A JP13723094A JP13723094A JPH084203A JP H084203 A JPH084203 A JP H084203A JP 13723094 A JP13723094 A JP 13723094A JP 13723094 A JP13723094 A JP 13723094A JP H084203 A JPH084203 A JP H084203A
Authority
JP
Japan
Prior art keywords
steel
bar
reinforcement
framed
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13723094A
Other languages
Japanese (ja)
Inventor
Hiroaki Minatogawa
博昭 湊川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP13723094A priority Critical patent/JPH084203A/en
Publication of JPH084203A publication Critical patent/JPH084203A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

PURPOSE:To shorten the construction period and the construction cost for execution of a steel framed reinforced beam by reducing welding parts. CONSTITUTION:Beam top reinforcement 19 is formed longer than steel framed beam 13, the beam top reinforcement 19 positioned on one side of the steel framed beam 13 is projected from one end part of the steel framed beam 13, the beam top reinforcement 19 positioned on the other side is projected from the other end part of the steel framed beam 13. In addition, these beam top reinforcement are constituted so that they are slidably provided in the lengthwise direction of the steel framed beam 13. When a steel framed reinforcement beam 12 of such constitution is constituted between pillars, the beam top reinforcement 19 are slidably arranged so as to be equally divided at the pillar core, and hence welding of the beam top reinforcement 19 is omitted. Hereby, the number of welding parts is reduced compared with that of a customary case, and the construction period and the construction cost required for execution of the steel framed reinforcement beam are remarkably reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄骨鉄筋梁およびこの
鉄骨鉄筋梁を柱に接続する鉄骨鉄筋梁の施工方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steel rebar beam and a method for constructing a steel rebar beam connecting the steel rebar beam to a column.

【0002】[0002]

【従来の技術】鉄骨鉄筋コンクリート造の構造物を構築
する際において、鉄骨鉄筋柱に鉄骨鉄筋梁を接合する場
合、例えば図6に示すように、鉄骨鉄筋柱1の、鉄骨鉄
筋梁2を接続する部位に仕口部3を形成し、この仕口部
3に鉄骨鉄筋梁2を接合することにより行なっている。
前記仕口部3は、鉄骨鉄筋柱1の外周部に、水平方向に
突出する3本の鉄骨4を形成するとともに、各鉄骨4の
周囲に4本の鉄筋(主筋)5…を配筋するとともに、鉄
骨4の側面側にそれぞれ2本、合計で4本の梁トップ筋
6…を配筋し、これら鉄筋5および梁トップ筋6の周囲
に肋筋7を巻回したものである。図6において、左右方
向に延びるそれぞれ4本の鉄筋5…および梁トップ筋6
…は、それらの端部が鉄骨4の端部と面一になるように
配筋されている。また、前記鉄骨鉄筋梁2は、鉄骨梁8
の周囲に、それぞれ4本の梁主筋9…を配筋するととと
もに、鉄骨梁8の両端部側面側にそれぞれ4本の梁トッ
プ筋10…を配筋し、これら梁主筋9…および梁トップ
筋10…の周囲に肋筋11を巻回してなるもので、前記
梁主筋9はその両端部が鉄骨梁8の両端部と面一になる
ように配筋され、梁トップ筋10は、その鉄骨梁8の端
部側を向く端部が鉄骨梁8の端部と面一になるように配
筋されている。
2. Description of the Related Art In constructing a structure made of steel reinforced concrete, when joining a steel reinforced beam to a steel reinforced column, for example, as shown in FIG. 6, the steel reinforced column 2 of the steel reinforced column 1 is connected. The joint portion 3 is formed in the region, and the steel frame rebar beam 2 is joined to the joint portion 3.
The joint part 3 forms three steel frames 4 protruding in the horizontal direction on the outer peripheral part of the steel-framed reinforcing bar column 1, and arranges four reinforcing bars (main bars) 5 around each steel frame 4. At the same time, two beam top reinforcements 6 ... Are arranged on the side surface of the steel frame 4 in total, and the ribs 7 are wound around the reinforcing bars 5 and the beam top reinforcements 6. In FIG. 6, four reinforcing bars 5 ...
Are arranged so that their ends are flush with the ends of the steel frame 4. Further, the steel rebar beam 2 is connected to the steel beam 8
4 beam main reinforcements 9 ... are arranged around the circumference of each of them, and 4 beam top reinforcements 10 ... are arranged on both side surfaces of both ends of the steel beam 8, and these beam main reinforcements 9 ... A rib 11 is wound around 10 ..., The beam main bar 9 is arranged so that both ends thereof are flush with both ends of the steel beam 8, and the beam top bar 10 is made of the steel frame. The end of the beam 8 facing the end is arranged so as to be flush with the end of the steel beam 8.

【0003】そして、対向する鉄骨鉄筋柱1,1間に鉄
骨鉄筋梁2を施工する場合、鉄骨鉄筋柱1,1のそれぞ
れの仕口部3,3の対向する鉄骨4,4間に鉄骨鉄筋梁
2を配設し、鉄骨鉄筋梁2の鉄骨梁8の両端部を、鉄骨
4,4に図示しない連結プレートによって連結するとと
もに、鉄骨鉄筋梁2の梁主筋9および梁トップ筋10
と、鉄骨4の周囲に配筋された鉄筋5およびトップ筋6
とを突き合わせて溶接することによって行なう。
When constructing the steel-framed reinforcing-bar beam 2 between the steel-framed reinforcing-bar columns 1 and 1 facing each other, the steel-framed reinforcing-bars are provided between the facing steel-frames 4 and 4 of the respective joint portions 3 and 3 of the steel-framed reinforcing-bar columns 1 and 1. The beam 2 is arranged, both ends of the steel beam 8 of the steel-framed reinforcing bar beam 2 are connected to the steel frames 4 and 4 by connecting plates (not shown), and the beam main bar 9 and the beam top bar 10 of the steel-framed reinforcing bar beam 2 are connected.
And a reinforcing bar 5 and a top bar 6 arranged around the steel frame 4.
It is done by butt welding and.

【0004】[0004]

【発明が解決しようとする課題】ところが、前記鉄骨鉄
筋梁2の施工では、溶接箇所が非常に多くなるという問
題がある。すなわち、4本の梁主筋8…と端部にそれぞ
れ4本のトップ筋10…を有する1本の鉄骨鉄筋梁2を
柱1,1間に施工するの場合、梁主筋9…と仕口部3の
鉄筋5…との溶接箇所が8箇所、梁トップ筋10…と、
仕口部3の梁トップ筋6…との溶接箇所が8箇所、合計
で16箇所と非常に多くなり、これら溶接に非常に手間
を要するため、鉄骨鉄筋梁2の施工に多大の工期と費用
を要していた。
However, in the construction of the steel-framed reinforcing bar beam 2, there is a problem that the number of welded spots becomes very large. That is, in the case of constructing one steel-framed rebar beam 2 having four beam main bars 8 ... And four top bars 10 ... At the ends, between the columns 1 and 1, the beam main bars 9 ... 8 welding points with the reinforcing bar 5 of No. 3, beam top bar 10 ...
The number of welding points with the beam top reinforcement 6 of the joint portion 3 is 8 points, which is a total of 16 points, which is extremely large, and it takes a lot of time and labor to construct the steel-framed reinforced beam 2. Was needed.

【0005】本発明は上記事情に鑑みてなされたもの
で、溶接箇所を少なくすることによって、鉄骨鉄筋梁の
施工の工期、費用を低減することができる鉄骨鉄筋梁お
よびその施工方法を提供することを目的としている。
The present invention has been made in view of the above circumstances, and provides a steel-framed reinforcing bar beam and a method for constructing the same which can reduce the construction period and cost of the steel-framed steel beam by reducing the number of welded portions. It is an object.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明の請求項1の鉄骨鉄筋梁は、梁トップ筋を鉄
骨梁より長く形成し、該梁トップ筋のうち、鉄骨梁の一
方の側面側に位置する梁トップ筋を、該鉄骨梁の一端部
から突出させ、かつ鉄骨梁の他方の側面側に位置する梁
トップ筋を、該鉄骨梁の他端部から突出させ、さらに、
これら梁トップ筋を、鉄骨梁の長手方向にスライド自在
に設けたものである。
In order to achieve the above object, in the steel-framed reinforcing bar beam according to claim 1 of the present invention, the beam top bar is formed longer than the steel beam, and the beam top bar of the beam top bar is A beam top bar located on one side surface is projected from one end of the steel beam, and a beam top bar located on the other side surface of the steel beam is projected from the other end of the steel beam, and ,
These beam top bars are provided slidably in the longitudinal direction of the steel beam.

【0007】請求項2の鉄骨鉄筋梁は、請求項1記載の
鉄骨鉄筋梁の周囲に型枠パネルを設けてなり、この型枠
パネルが型枠フレームに金網を張設し、当該金網の内側
面に、小径の孔が多数形成された合成樹脂性のフイルム
を張設してなるものである。
According to a second aspect of the present invention, there is provided a formwork panel around the steel-framed reinforcement beam according to the first aspect. The formwork panel stretches a wire mesh on the formwork frame, and On the side surface, a synthetic resin film having a large number of small holes is stretched.

【0008】請求項3の鉄骨鉄筋梁の施工方法は、請求
項1または2記載の鉄骨鉄筋梁を柱間に位置させた後、
該柱に突出形成された仕口部の鉄骨に、前記鉄骨鉄筋梁
の鉄骨梁を接合し、次いで、前記仕口部の鉄筋に、鉄骨
鉄筋梁の梁主筋を溶接するとともに、前記鉄骨鉄筋梁の
梁トップ筋を鉄骨梁から突出している側にスライドさせ
て、柱芯等分割で配筋することを特徴としている。
According to a third aspect of the present invention, there is provided a method for constructing a steel-framed reinforcing bar beam, after the steel-framed reinforcing bar beam according to claim 1 or 2 is positioned between columns,
The steel frame of the joint portion projectingly formed on the column is joined to the steel beam of the steel-framed reinforcing bar beam, and then the main bar of the steel-framed reinforcing bar beam is welded to the reinforcing bar of the joint section, It is characterized in that the beam top reinforcement of is slid to the side projecting from the steel beam, and the reinforcement is arranged by dividing the core into equal parts.

【0009】[0009]

【作用】本発明の請求項1の鉄骨鉄筋梁にあっては、鉄
骨鉄筋梁を柱間に架設する際、鉄骨鉄筋梁の梁トップ筋
を鉄骨梁から突出している側にスライドさせて、柱芯等
分割で配筋することにより、梁トップ筋の溶接を省略す
ることができる。
In the steel-framed reinforcing bar beam according to the first aspect of the present invention, when the steel-framed reinforcing bar beam is installed between columns, the beam top bar of the steel-framed reinforcing bar beam is slid to the side projecting from the steel frame beam, By arranging the bars with the core divided, the welding of the beam top bars can be omitted.

【0010】請求項2の鉄骨鉄筋梁にあっては、型枠パ
ネル内にコンクリートを打設して、コンクリート硬化
後、型枠パネルを取り外すことなく、埋め殺しとするこ
とにより、型枠を解体する手間や解体した型枠を搬出す
る手間を省くことができるので、施工現場での作業能率
を高めることができ、また、打設したコンクリート中の
水分のみをフイルムの微小孔さらには金網の目を通して
外部へ排出させることができるので、型枠パネルの受け
る側圧を軽減させることができる。
In the steel frame rebar beam of claim 2, concrete is cast in the formwork panel, and after the concrete is hardened, the formwork panel is removed without removing the formwork panel to dismantle the formwork. Since it is possible to save time and labor for carrying out the dismantled formwork, it is possible to improve the work efficiency at the construction site, and only the water in the placed concrete is filled with the fine holes in the film and the wire mesh. Since it can be discharged to the outside through the through, it is possible to reduce the lateral pressure received by the formwork panel.

【0011】請求項3の鉄骨鉄筋梁の施工方法にあって
は、請求項1または2記載の鉄骨鉄筋梁を柱間に架設す
る際、鉄骨鉄筋梁の梁トップ筋を鉄骨梁から突出してい
る側にスライドさせて、柱芯等分割で配筋することによ
り、梁トップ筋の溶接を省略することができ、これによ
って、従来の比して溶接箇所が少なくなるので、鉄骨鉄
筋梁の施工に要する工期、費用を大幅に低減することが
できる。また、鉄骨梁の側面側にそれぞれ配筋された梁
トップ筋のうち、鉄骨梁の一方の側面側に位置する梁ト
ップ筋が、該鉄骨梁の一端部から突出され、かつ鉄骨梁
の他方の側面側に位置する梁トップ筋が、該鉄骨梁の他
端部から突出されているので、鉄骨鉄筋梁を対向する仕
口部の鉄骨間に横方向から挿入して、当該鉄骨間に配設
することができる。
In the method for constructing a steel-framed reinforcing-bar beam according to claim 3, when the steel-framed reinforcing-bar beam according to claim 1 or 2 is installed between columns, the beam top reinforcement of the steel-framed reinforcing-bar beam is projected from the steel-framed beam. By sliding to the side and arranging the bar cores in equal parts, the welding of the beam top bar can be omitted, which reduces the number of welding points compared with the conventional method, so it is suitable for the construction of steel-framed rebar beams. The required construction period and cost can be greatly reduced. Further, among the beam top reinforcements arranged on the side surface sides of the steel beam, the beam top reinforcements located on one side surface side of the steel beam are projected from one end of the steel beam and the other of the steel beam Since the beam top reinforcement located on the side surface is projected from the other end of the steel frame beam, the steel frame reinforcement beam is inserted laterally between the steel frames of the facing joints and disposed between the steel frames. can do.

【0012】[0012]

【実施例】以下、図面を参照して本発明の実施例を説明
する。図1および図2は本発明の鉄骨鉄筋梁の一実施例
を示すもので、これらの図において符号12は鉄骨鉄筋
梁を示す。この鉄骨鉄筋梁12は、鉄骨梁13と、この
鉄骨梁11の周囲に配設された4本の梁主筋14…と、
これら梁主筋14…に、鉄骨梁12を囲むようにして巻
回された複数本の肋筋15とを備えている。なお、梁主
筋14…は、鉄骨梁13にその長さ方向に所定間隔で固
定された複数のかんざし筋14a…によって配筋されて
いる。
Embodiments of the present invention will be described below with reference to the drawings. 1 and 2 show an embodiment of a steel-framed reinforcing-bar beam of the present invention. In these drawings, reference numeral 12 represents a steel-framed reinforcing-bar beam. The steel rebar beam 12 includes a steel beam 13 and four beam main bars 14 disposed around the steel beam 11.
These beam main bars 14 ... Are provided with a plurality of ribs 15 wound so as to surround the steel beam 12. The main beam reinforcements 14 are arranged by a plurality of knitting reinforcements 14a fixed to the steel beam 13 at predetermined intervals in the longitudinal direction.

【0013】前記鉄骨梁13はH鋼からなるもので、柱
16,16に形成された仕口部17,17の互いに対向
する鉄骨18,18間とほぼ同長さに形成されている。
前記梁主筋14…は、鉄骨梁13と平行に延びる異形棒
鋼であり、それらの両端部が鉄骨梁13の両端部と面一
になるように配筋されている。また、鉄骨梁13の側面
側には、それぞれ2本ずつの梁トップ筋19が仮配筋さ
れている。この仮配筋は、梁トップ筋19を前記肋筋1
5の内側に挿通することにより行なう。前記梁トップ筋
19…のうち、鉄骨梁13の一方の側面側に位置する2
本の梁トップ筋19,19は、それらの一端部が鉄骨梁
13の右端部から突出され、他端部は鉄骨梁13の左端
部と面一になるように仮配筋されている。また、鉄骨梁
13の他方の側面側に位置する2本の梁トップ筋19,
19は、それらの一端部が鉄骨梁13の左端部から突出
され、他端部は鉄骨梁13の右端部と面一になるように
仮配筋されている。また、前記肋筋15…は鉄骨梁13
の長さ方向に所定間隔で複数本配筋されている。
The steel beam 13 is made of H steel and is formed to have substantially the same length as the distance between the steel frames 18 and 18 of the joints 17 and 17 formed in the columns 16 and 16 facing each other.
The beam main bars 14 are deformed steel bars extending in parallel with the steel beam 13, and are arranged so that both ends thereof are flush with both ends of the steel beam 13. Further, two beam top reinforcements 19 are provisionally arranged on each side surface of the steel beam 13. This temporary bar is composed of the beam top bar 19 and the rib bar 1
It is carried out by inserting it inside 5. Of the beam top bars 19 ... Located on one side of the steel beam 13 2
The beam top reinforcements 19, 19 of the book are provisionally arranged so that one end thereof protrudes from the right end of the steel beam 13 and the other end thereof is flush with the left end of the steel beam 13. In addition, two beam top reinforcements 19, which are located on the other side surface side of the steel beam 13,
19 are provisionally laid out so that one end thereof projects from the left end of the steel beam 13, and the other end thereof is flush with the right end of the steel beam 13. Further, the ribs 15 ... Are steel beam 13
A plurality of bars are arranged at predetermined intervals in the length direction.

【0014】上記構成の鉄骨鉄筋梁12を鉄骨鉄筋柱
(図においては、鉄骨のみを示してあり、柱主筋、帯筋
等は省略していある)16,16間に施工する場合、ま
ず、鉄骨鉄筋梁12をクレーン等によって水平に吊り下
げて、鉄骨鉄筋柱16,16の仕口部17,17の互い
に対向する鉄骨18,18間に位置させる。この場合、
鉄骨18,18を結ぶ直線に対して鉄骨鉄筋梁12を水
平面内において若干傾けることによって、鉄骨18,1
8間に鉄骨鉄筋梁12を容易に挿入することができる。
一方、鉄骨鉄筋柱16,16の仕口部17,17におい
ては、仕口部17の鉄骨18の両側面側に、前記梁主筋
14に対向する鉄筋20…が配筋され、その両端部は仕
口部17の鉄骨18の端部と面一にされ、また、鉄筋2
0…には、複数本の肋筋15…が鉄骨18を囲むように
して巻回されている。
When the steel-framed reinforcing-bar beam 12 having the above-mentioned structure is installed between the steel-framed reinforcing-bar columns (only the steel frame is shown in the drawing, the column main bar, the stirrup, etc. are omitted) 16, 16, The reinforcing bar beam 12 is suspended horizontally by a crane or the like, and is positioned between the steel frames 18, 18 of the steel frame reinforcing bar columns 16, 16 facing each other. in this case,
By slightly inclining the steel rebar beam 12 with respect to the straight line connecting the steel frames 18 and 18 in the horizontal plane,
It is possible to easily insert the steel reinforced beam 12 between the eight.
On the other hand, in the joint portions 17 and 17 of the steel-framed rebar columns 16, 16, the reinforcing bars 20 facing the beam main bar 14 are arranged on both side surfaces of the steel frame 18 of the joint portion 17, and both ends thereof are It is made flush with the end of the steel frame 18 of the connection part 17, and
A plurality of ribs 15 ... Are wound around 0 ... so as to surround the steel frame 18.

【0015】次いで、鉄骨鉄筋梁12を、図2(a)に
示すように、矢印方向に回転させて、鉄骨鉄筋梁12の
鉄骨梁13の両端面をそれぞれ、鉄骨18,18の端面
に対向させて、これら端面どうしを当接させ、図示しな
い連結プレートによって、鉄骨梁13の両端部と、鉄骨
18,18のそれぞれの端部を接合する。これによっ
て、鉄骨梁13が柱16,16間に架設されるととも
に、鉄骨梁13と面一になっている梁主筋14…が、鉄
骨鉄筋柱16,16の仕口部17,17に配筋された鉄
筋20…に対向して当接する。
Next, as shown in FIG. 2 (a), the steel-frame reinforcing bar 12 is rotated in the direction of the arrow so that both end faces of the steel-frame beam 13 of the steel-frame reinforcing bar 12 face the end faces of the steel frames 18, 18, respectively. Then, these end faces are brought into contact with each other, and both end portions of the steel beam 13 and the respective end portions of the steel frames 18, 18 are joined by a connecting plate (not shown). As a result, the steel beam 13 is erected between the columns 16 and 16, and the beam main bar 14 which is flush with the steel beam 13 is arranged in the joints 17 and 17 of the steel rebar columns 16 and 16. The rebar 20 is abutted so as to face it.

【0016】次に、前記梁主筋14…の端部と、鉄骨鉄
筋柱16,16の仕口部17,17に配筋された鉄筋2
0…とを溶接する。また、鉄骨鉄筋梁12に仮配筋され
た梁トップ筋19…を鉄骨梁13から突出している側に
スライドさせて、柱芯等分割で配筋するとともに、前記
肋筋15…に固定する。これにより鉄骨鉄筋柱16,1
6間に鉄骨鉄筋梁12が施工される。なお、1本の鉄骨
鉄筋梁12では、その両側面側に仮配筋された梁トップ
筋19…が、それぞれ互いに対向する仕口部17,17
側に向けて互いに逆方向にスライドして柱芯等分割で配
筋されるので、一の仕口部17においては一方の側面側
にのみ梁トップ筋19が配筋されることになるが、この
仕口部17の他方の側面側には、前記1本の鉄骨鉄筋梁
12と隣接して架設される鉄骨鉄筋梁12に仮配筋され
た梁トップ筋19がスライドして配筋されるので、仕口
部17の両側面側にはそれぞれ梁トップ筋19が配筋さ
れることになる。このようにして、鉄骨鉄筋梁12を施
工すれば、梁主筋14…の溶接箇所数は従来と変わらな
いが、仕口部17…に配筋される梁トップ筋19の溶接
が不要となる。具体的には、本実施例では、梁主筋14
と仕口部17の鉄筋20との溶接箇所が8箇所、鉄骨鉄
筋柱16に梁トップ筋19をスライドさせて配筋するた
め、梁トップ筋19の溶接箇所は0箇所、合計で8箇所
となり、従来の16箇所に比して8箇所少なくなる、つ
まり溶接箇所が半減するので、この分だけ鉄骨鉄筋梁1
2の施工に要する工期と費用を低減することができる。
Next, the reinforcing bars 2 arranged at the ends of the beam main bars 14 ... And the joints 17, 17 of the steel-framed reinforcing bars 16, 16.
Weld 0 ... Further, the beam top reinforcements 19 ... Provisionally reinforced in the steel frame reinforcement bars 12 are slid to the side projecting from the steel frame beams 13 to arrange the core cores in equal divisions and fixed to the ribs 15. As a result, the steel rebar columns 16,1
The steel-framed reinforced beam 12 is constructed between the six. In addition, in the one steel-frame reinforcing bar beam 12, the beam top bars 19 ... Temporarily arranging on both side surfaces thereof are respectively facing the joint portions 17, 17.
Since the rod cores are slid in the opposite directions toward each other and the pillar cores are equally divided, the beam top reinforcement 19 is arranged only on one side surface side in the one joint portion 17, On the other side surface side of this connection part 17, a beam top reinforcement 19 tentatively arranged on the steel reinforcement beam 12 installed adjacent to the one steel reinforcement beam 12 is slid and arranged. Therefore, the beam top reinforcements 19 are arranged on both side surfaces of the joint portion 17, respectively. When the steel-framed reinforcing bar beam 12 is constructed in this manner, the number of welded portions of the beam main bars 14 ... Is the same as the conventional number, but the welding of the beam top bars 19 arranged in the joint portions 17 ... is unnecessary. Specifically, in this embodiment, the beam main bar 14
Since there are 8 welding points between the reinforcing bar 20 of the connection part 17 and the reinforcing bar 20 of the joint part 17 and the bar top reinforcing bar 19 is slid on the steel reinforcing bar column 16 to arrange the bar top reinforcing bar 19, the welding position of the beam top reinforcing bar 19 is 0 in total, 8 points in total. Since the number of welding points is reduced by 8 compared to the conventional 16 points, that is, the number of welding points is halved, the steel-framed reinforced beam 1
The construction period and cost required for construction 2 can be reduced.

【0017】図3は本発明の鉄骨鉄筋梁の他の実施例を
示すものである。この図に示す鉄骨鉄筋梁21は、前記
鉄骨鉄筋梁12の外側に型枠22を設けた構成となって
いる。前記型枠22は、矩形板状をなす3枚の型枠パネ
ル23を断面コ字状の溝形に組み立ててなるもので、そ
の組立は、断面コ字状をなし、前記梁主筋14の長さ方
向に延びるパネル支持フレーム24…を型枠22の3つ
の隅部にその開口部を互いに対向させて配設するととも
に、かんざし筋14aの両端部に固定されたステー26
に固定することによって、パネル支持フレーム24…
を、ステー26、かんざし筋14aを介して鉄骨梁13
に固定し、これら固定されたパネル支持フレーム24の
対向した開口部に型枠パネル23を挿入して、嵌め込む
ことにより行なわれている。
FIG. 3 shows another embodiment of the steel-framed reinforcing bar beam of the present invention. The steel-framed reinforcing bar beam 21 shown in this figure has a configuration in which a form 22 is provided outside the steel-framed reinforcing bar beam 12. The formwork 22 is formed by assembling three formwork panels 23 each having a rectangular plate shape into a groove shape having a U-shaped cross section. The assembly has a U-shaped cross section, and the length of the beam main bar 14 is long. The panel support frames 24 extending in the vertical direction are arranged at three corners of the mold 22 with their openings facing each other, and the stays 26 fixed to both ends of the knitting bar 14a.
By fixing to the panel support frame 24 ...
To the steel beam 13 via the stay 26 and the knitting muscle 14a.
It is carried out by inserting the form frame panel 23 into the facing openings of the fixed panel support frames 24 and fitting them.

【0018】前記型枠パネル23は、図4および図5に
示すように、型枠フレーム27と、この型枠フレーム2
7に張設された金網28と、この金網28の内側面に張
設された合成樹脂製のフイルム29とを主体として構成
されている。前記型枠フレーム27は矩形状をなすもの
で、その内側には上下に延びる複数条の補強フレーム3
0が所定間隔で形成されている。また、前記金網28
は、多数の目が形成された金網部28aと、左右に延び
る複数条の補強リブ28b…によって構成され、これら
補強リブ28bによって金網28の撓みが防止されるよ
うになっている。さらに、前記フイルム29は透明なも
ので、微小径(例えば、1.0mm)の孔が多数形成され
ている。
As shown in FIGS. 4 and 5, the mold frame panel 23 includes a mold frame 27 and the mold frame 2
The wire mesh 28 stretched around the wire mesh 7 and the film 29 made of synthetic resin stretched on the inner side surface of the wire mesh 28 are mainly constituted. The formwork frame 27 has a rectangular shape, and a plurality of vertically extending reinforcing frames 3 are provided inside the formwork frame 27.
Zeros are formed at predetermined intervals. Also, the wire net 28
Is composed of a wire mesh portion 28a in which a large number of eyes are formed and a plurality of reinforcing ribs 28b extending in the left-right direction. The reinforcing ribs 28b prevent the wire mesh 28 from bending. Further, the film 29 is transparent and has a large number of holes having a minute diameter (for example, 1.0 mm).

【0019】前記型枠フレーム27の補強フレーム30
には、その長さ方向に所定間隔で孔30a…が形成され
ており、各孔30aに、前記鉄骨鉄筋梁12との間隔を
保持するセパレータ31が挿通されるようになってい
る。セパレータ31の先端部は、図3に示すように、前
記鉄骨梁13のフランジ部13aに連結されている。こ
の連結は、前記フランジ部13aの所定の位置に連結ナ
ット33を固定し、この連結ナット33にセパレータ3
1の先端部をねじ込むことにより連結されている。そし
て、これらセパレータ31によって、型枠パネル23は
鉄骨鉄筋梁12との間隔が一定に保持されるとともに、
コンクリート打設時の型枠パネル23の撓みを防止して
いる。
Reinforcement frame 30 of the mold frame 27
Are formed with holes 30a at predetermined intervals in the lengthwise direction, and a separator 31 for holding the interval with the steel-framed reinforcing bar beam 12 is inserted into each hole 30a. As shown in FIG. 3, the tip of the separator 31 is connected to the flange portion 13 a of the steel beam 13. In this connection, a connection nut 33 is fixed at a predetermined position of the flange portion 13a, and the connection nut 33 is attached to the separator 3
They are connected by screwing in the tip portion of 1. Then, by these separators 31, the formwork panel 23 is kept at a constant distance from the steel-framed rebar 12,
The bending of the formwork panel 23 at the time of pouring concrete is prevented.

【0020】上記構成の鉄骨鉄筋梁201では、前記第
1実施例の鉄骨鉄筋梁12と同様にして、鉄骨鉄筋柱1
6,16間に架設されることにより、鉄骨鉄筋梁12と
同様の作用効果を得ることができる他、以下のような作
用効果を得ることができる。すなわち、本実施例の鉄骨
鉄筋梁21では、型枠パネル23で組み立てられた型枠
22内にコンクリートを打設し、該コンクリートを硬化
させることにより鉄骨鉄筋コンクリート梁が構築される
が、コンクリートが硬化した後は、型枠パネル23を取
り外すことなく、鉄骨鉄筋コンクリート梁の外装材の下
地として使用する。この際、型枠パネル23の表面の金
網28により、外装材を固定するモルタル等のくいつき
が良好になるので、当該モルタルの剥離やクッラクの発
生を防止することができる。また、型枠を解体する手間
や解体した型枠を搬出する手間を省くことができるの
で、施工現場での作業能率を高めることができ、また、
前記型枠パネル23は、金網28の内側面に微小孔が多
数形成されたフイルム29を張設した構成となっている
ので、打設したコンクリート中の水分のみをフイルム2
9の微小孔さらには金網28の目を通して外部へ排出さ
せることができるので、型枠パネル23の受ける側圧を
軽減させることができる。
In the steel-framed reinforcing-bar beam 201 having the above-described structure, the steel-framed reinforcing-bar column 1 is made in the same manner as the steel-framed reinforcing-bar beam 12 of the first embodiment.
By being installed between No. 6 and No. 16, it is possible to obtain the same action and effect as those of the steel-framed reinforcing bar beam 12, and also obtain the following action and effect. That is, in the steel-framed reinforced concrete beam 21 of this embodiment, concrete is placed in the formwork 22 assembled by the formwork panel 23 and the concrete is hardened to construct a steel-framed reinforced concrete beam. After that, the frame panel 23 is used as a base for the exterior material of the steel reinforced concrete beam without removing it. At this time, the metal net 28 on the surface of the mold panel 23 makes it possible to prevent the mortar or the like for fixing the exterior material from sticking well, and thus it is possible to prevent the mortar from peeling or cracking. Further, since it is possible to save the labor of dismantling the formwork and the labor of carrying out the dismantled formwork, it is possible to enhance the work efficiency at the construction site, and
Since the formwork panel 23 has a structure in which a film 29 having a large number of minute holes formed therein is stretched on the inner surface of a wire net 28, only the water in the cast concrete is removed.
Since it can be discharged to the outside through the fine holes of 9 and the meshes of the wire net 28, the lateral pressure received by the mold frame panel 23 can be reduced.

【0021】さらに、金網28と透明なフイルム29を
透してコンクリートの打設状況を外部より視認すること
ができるので、打設不良箇所を発見した場合には、コン
クリートに振動を加えて、かかる打設不良を速やかに解
消して、コンクリートの均質性を良好に保つことができ
る。また、合成樹脂性のフイルム29によって、打設さ
れたコンクリートの表面が覆われるので、コンクリート
の風化を防止して、鉄筋への錆の発生を防止することが
できる。
Further, since it is possible to visually confirm the placing condition of the concrete from the outside through the wire net 28 and the transparent film 29, when a defective placing place is found, the concrete is vibrated and applied. Improper placement can be promptly eliminated and good homogeneity of concrete can be maintained. Further, since the surface of the cast concrete is covered with the synthetic resin film 29, weathering of the concrete can be prevented and rust can be prevented from occurring on the reinforcing bar.

【0022】[0022]

【発明の効果】以上説明したように、本発明の請求項1
の鉄骨鉄筋梁によれば、鉄骨鉄筋梁を柱間に架設する
際、鉄骨鉄筋梁の梁トップ筋を鉄骨梁から突出している
側にスライドさせて、柱芯等分割で配筋することによ
り、梁トップ筋の溶接を省略することができる。したが
って、この分だけ従来に比して溶接箇所が少なくなるの
で、鉄骨鉄筋梁の施工に要する工期および費用を大幅に
低減することができる。
As described above, according to the first aspect of the present invention.
According to the steel-framed reinforced beam, when the steel-framed reinforced beam is installed between columns, by sliding the beam top reinforcement of the steel-framed reinforced beam to the side projecting from the steel-framed beam, and by arranging the column cores in equal divisions, Welding of beam top bar can be omitted. Therefore, since the number of welded portions is reduced as compared with the conventional one, the construction period and cost required for constructing the steel-framed reinforcing beam can be significantly reduced.

【0023】請求項2の鉄骨鉄筋梁によれば、前記請求
項1の鉄骨鉄筋梁と同様の作用効果を得られる他、型枠
パネルを、型枠フレームに金網を張設し、当該金網の内
側面に、小径の孔が多数形成された合成樹脂性のフイル
ムを張設した構成としたので、この型枠パネル内にコン
クリートを打設して、コンクリート硬化後、型枠パネル
を取り外すことなく、埋め殺しとすることにより、型枠
を解体する手間や解体した型枠を搬出する手間を省くこ
とができるので、施工現場での作業能率を高めることが
でき、また、打設したコンクリート中の水分のみをフイ
ルムの微小孔さらには金網の目を通して外部へ排出させ
ることができるので、型枠パネルの受ける側圧を軽減さ
せることができる。
According to the steel-framed reinforcing beam of claim 2, in addition to the same effect as the steel-framed reinforcing beam of claim 1, the formwork panel is provided with a wire mesh and the wireframe is stretched over the frame. Since a synthetic resin film with many small-diameter holes formed on the inner surface was stretched, concrete was placed in this formwork panel, and after the concrete was hardened, it was not necessary to remove the formwork panel. By burying it, it is possible to save the trouble of dismantling the formwork and the work of carrying out the dismantled formwork, so it is possible to improve the work efficiency at the construction site, Since only water can be discharged to the outside through the fine holes of the film and further through the meshes of the film, it is possible to reduce the lateral pressure received by the formwork panel.

【0024】また、合成樹脂性のフイルムによって、打
設されたコンクリートの表面が覆われるので、コンクリ
ートの風化を防止して、鉄筋への錆の発生を防止するこ
とができる。
Further, since the surface of the cast concrete is covered with the synthetic resin film, the weathering of the concrete can be prevented and the rust on the reinforcing bar can be prevented.

【0025】請求項3の鉄骨鉄筋梁の施工方法によれ
ば、請求項1または2記載の鉄骨鉄筋梁を柱間に架設す
る際、鉄骨鉄筋梁の梁トップ筋を鉄骨梁から突出してい
る側にスライドさせて、柱芯等分割で配筋することによ
り、梁トップ筋の溶接を省略することができ、これによ
って、従来の比して溶接箇所が少なくなるので、鉄骨鉄
筋梁の施工に要する工期、費用を大幅に低減することが
できる。また、鉄骨梁の側面側にそれぞれ配筋された梁
トップ筋のうち、鉄骨梁の一方の側面側に位置する梁ト
ップ筋が、該鉄骨梁の一端部から突出され、かつ鉄骨梁
の他方の側面側に位置する梁トップ筋が、該鉄骨梁の他
端部から突出されているので、鉄骨鉄筋梁を対向する仕
口部の鉄骨間に横方向から挿入して、当該鉄骨間に配設
することができ、よって、鉄骨鉄筋梁の柱間への配設を
容易に行なうことができる。
According to the method for constructing a steel-framed reinforcing-bar beam according to claim 3, when the steel-framed reinforcing-bar beam according to claim 1 or 2 is installed between columns, the beam top reinforcement of the steel-framed reinforcing-bar beam projects from the steel-framed beam. Welding of the beam top bar can be omitted by sliding it to the column core and dividing it into column cores, etc. This reduces the number of welding points compared to the conventional method, so it is necessary for the construction of steel-framed rebar beams. The construction period and cost can be significantly reduced. Further, among the beam top reinforcements arranged on the side surface sides of the steel beam, the beam top reinforcements located on one side surface side of the steel beam are projected from one end of the steel beam and the other of the steel beam Since the beam top reinforcement located on the side surface is projected from the other end of the steel frame beam, the steel frame reinforcement beam is inserted laterally between the steel frames of the facing joints and disposed between the steel frames. Therefore, it is possible to easily arrange the steel-reinforced bar beams between the columns.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の鉄骨鉄筋梁の一実施例を示す斜視図で
ある。
FIG. 1 is a perspective view showing an embodiment of a steel-framed reinforcing bar beam of the present invention.

【図2】同、平面および側面図である。FIG. 2 is a plan view and a side view of the same.

【図3】本発明の鉄骨鉄筋梁の他の実施例を示す断面図
である。
FIG. 3 is a sectional view showing another embodiment of the steel-framed reinforcing bar beam of the present invention.

【図4】図3に示す鉄骨鉄筋梁の型枠パネルを示す側面
図である。
FIG. 4 is a side view showing a formwork panel of the steel-framed reinforcing bar beam shown in FIG.

【図5】図4におけるA−A線視断面図である。5 is a cross-sectional view taken along the line AA in FIG.

【図6】従来の鉄骨鉄筋梁の一例を示す平面および側面
図である。
FIG. 6 is a plan view and a side view showing an example of a conventional steel-framed reinforcing bar beam.

【符号の説明】[Explanation of symbols]

12,21 鉄骨鉄筋梁 13 鉄骨梁 14 梁主筋 16 鉄骨鉄筋柱(柱) 17 仕口部 18 仕口部の鉄骨 19 梁トップ筋 20 仕口部の鉄筋 23 型枠パネル 27 型枠フレーム 28 金網 29 フイルム 12, 21 Steel rebar beam 13 Steel beam 14 Beam main bar 16 Steel rebar Column (column) 17 Joint part 18 Steel frame of joint part 19 Beam top bar 20 Reinforcing bar of joint part 23 Formwork panel 27 Formwork frame 28 Wire mesh 29 Film

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 鉄骨梁の周囲に複数の梁主筋と梁トップ
筋が配筋された鉄骨鉄筋梁において、 前記梁トップ筋は前記鉄骨梁より長く形成され、該梁ト
ップ筋のうち、鉄骨梁の一方の側面側に位置する梁トッ
プ筋が、該鉄骨梁の一端部から突出され、かつ鉄骨梁の
他方の側面側に位置する梁トップ筋が、該鉄骨梁の他端
部から突出され、さらに、これら梁トップ筋は、鉄骨梁
の長手方向にスライド自在に設けられていることを特徴
とする鉄骨鉄筋梁。
1. A steel-framed reinforcing bar beam having a plurality of beam main bars and beam top bars arranged around the steel beam, wherein the beam top bar is formed longer than the steel beam, and the beam top bar is a steel beam. Beam top reinforcement located on one side surface side is projected from one end of the steel frame beam, and beam top reinforcement located on the other side surface side of the steel frame beam is projected from the other end portion of the steel frame beam, Further, these beam top reinforcements are provided so as to be slidable in the longitudinal direction of the steel frame beam.
【請求項2】 請求項1記載の鉄骨鉄筋梁の周囲に型枠
パネルを設けてなり、この型枠パネルが型枠フレームに
金網を張設し、当該金網の内側面に、小径の孔が多数形
成された合成樹脂性のフイルムを張設してなるものであ
ることを特徴とする鉄骨鉄筋梁。
2. A formwork panel is provided around the steel rebar of claim 1, wherein the formwork panel stretches a wire mesh on the formwork frame, and a small-diameter hole is formed on the inner surface of the wire mesh. A steel-framed reinforcing bar beam comprising a large number of synthetic resin films stretched.
【請求項3】 請求項1または2記載の鉄骨鉄筋梁を柱
に接合する鉄骨鉄筋梁の施工方法であって、前記鉄骨鉄
筋梁を柱間に位置させた後、前記柱に突出形成された仕
口部の鉄骨に、前記鉄骨鉄筋梁の鉄骨梁を接合し、次い
で、前記仕口部の鉄筋に、鉄骨鉄筋梁の梁主筋を溶接す
るとともに、前記鉄骨鉄筋梁の梁トップ筋を鉄骨梁から
突出している側にスライドさせて、柱芯等分割で配筋す
ることを特徴とする鉄骨鉄筋梁の施工方法。
3. A method of constructing a steel-reinforced-steel-reinforced beam according to claim 1 or 2, wherein the steel-reinforced-steel-reinforced beam is joined to the pillar, wherein the steel-reinforced-steel-reinforced-beam is positioned between the pillars, and then is formed to project from the pillar. The steel frame of the joint part is joined to the steel beam of the steel frame reinforcement beam, and then the main bar of the steel reinforcement beam is welded to the reinforcement bar of the joint part, and the beam top reinforcement of the steel reinforcement beam is connected to the steel frame beam. A method for constructing a steel-framed reinforcing bar beam, which is characterized in that the bar is slid to the side projecting from it and the bar cores are divided into equal parts for reinforcement.
JP13723094A 1994-06-20 1994-06-20 Steel framed reinforcement beam and execution method thereof Pending JPH084203A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13723094A JPH084203A (en) 1994-06-20 1994-06-20 Steel framed reinforcement beam and execution method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13723094A JPH084203A (en) 1994-06-20 1994-06-20 Steel framed reinforcement beam and execution method thereof

Publications (1)

Publication Number Publication Date
JPH084203A true JPH084203A (en) 1996-01-09

Family

ID=15193829

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13723094A Pending JPH084203A (en) 1994-06-20 1994-06-20 Steel framed reinforcement beam and execution method thereof

Country Status (1)

Country Link
JP (1) JPH084203A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003321845A (en) * 2002-05-01 2003-11-14 Panahome Corp Reinforcement-steel frame core unit for foundation, and connection structure for the unit
CN102635232A (en) * 2012-04-25 2012-08-15 中国十七冶集团有限公司 Reinforcement method for transverse reinforcement interior edge at side of arc-shaped beam
JP2019044362A (en) * 2017-08-30 2019-03-22 株式会社竹中工務店 Construction method of src beam and formwork support structure of src beam
CN112853987A (en) * 2021-01-14 2021-05-28 深圳市市政设计研究院有限公司 Corrugated steel web structure adopting slidable stiffening ribs and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003321845A (en) * 2002-05-01 2003-11-14 Panahome Corp Reinforcement-steel frame core unit for foundation, and connection structure for the unit
CN102635232A (en) * 2012-04-25 2012-08-15 中国十七冶集团有限公司 Reinforcement method for transverse reinforcement interior edge at side of arc-shaped beam
JP2019044362A (en) * 2017-08-30 2019-03-22 株式会社竹中工務店 Construction method of src beam and formwork support structure of src beam
CN112853987A (en) * 2021-01-14 2021-05-28 深圳市市政设计研究院有限公司 Corrugated steel web structure adopting slidable stiffening ribs and construction method thereof

Similar Documents

Publication Publication Date Title
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
JP2000170285A (en) Connecting method for steel sheet concrete structural wall and junction structure
JPH084203A (en) Steel framed reinforcement beam and execution method thereof
JPH0711710A (en) Reinforced concrete column and steel frame beam jointing structure and building constructing method
KR102379888B1 (en) Method For Assembling Reinforced Concrete Columns Using Prefabricated Assembly
JP6576204B2 (en) Slab construction method
JPH0673786A (en) Junction of precast concrete column
JPH07217069A (en) Construction method of reinforced concrete pole and constituting precast concrete member thereof
JP2891113B2 (en) Installation method of reinforced concrete shear walls
JPS63533A (en) Slope frame construction work
JPH0960294A (en) Execution method for decorative floor board and decorative form
JPH06341167A (en) Working method for concrete structure
JPH06306931A (en) Construction of steel frame reinforced concrete structure
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPH02167937A (en) Connecting work of steel plate-concrete structure
JPH07292819A (en) Form panel
JPH10196027A (en) Deck panel for concrete form
JPS61290137A (en) Construction of columnar pillar
JPS6046219B2 (en) Construction method of concrete retaining wall
JP2602362B2 (en) Thick wall and beam or floor slab joining method
JP2984882B2 (en) Precast reinforced concrete column-beam joint structure
JPS6232303B2 (en)
JP2000355909A (en) Construction method for bridge floor
JPH0213694B2 (en)
JP2726554B2 (en) Construction method and positioning device for composite pier