JP2891113B2 - Installation method of reinforced concrete shear walls - Google Patents

Installation method of reinforced concrete shear walls

Info

Publication number
JP2891113B2
JP2891113B2 JP18328594A JP18328594A JP2891113B2 JP 2891113 B2 JP2891113 B2 JP 2891113B2 JP 18328594 A JP18328594 A JP 18328594A JP 18328594 A JP18328594 A JP 18328594A JP 2891113 B2 JP2891113 B2 JP 2891113B2
Authority
JP
Japan
Prior art keywords
steel plate
mortar
welded
existing
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP18328594A
Other languages
Japanese (ja)
Other versions
JPH0849330A (en
Inventor
耕喜 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP18328594A priority Critical patent/JP2891113B2/en
Publication of JPH0849330A publication Critical patent/JPH0849330A/en
Application granted granted Critical
Publication of JP2891113B2 publication Critical patent/JP2891113B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は資材搬入用の開口部を設
けて柱、梁、床を構築した後、その開口部に鉄筋コンク
リート造り耐震壁を設置する場合、耐震壁の設置場所の
決定が遅れ、先に柱、梁、床が構築されている開口部に
鉄筋コンクリート造り耐震壁を設置する場合、鉄筋コン
クリート造建造物の改修工事に伴って、それまで耐震壁
の無かった場所に鉄筋コンクリート造り耐震壁を設置す
る場合、などのように、四周に既に鉄筋コンクリート造
りもしくは鉄骨造り柱、梁、床が構築されている開口部
に鉄筋コンクリート造り耐震壁を設置する工法に関する
ものである。
BACKGROUND OF THE INVENTION The present invention relates to a method for installing a reinforced concrete-made earthquake-resistant wall in an opening after a column, a beam, and a floor are provided by providing an opening for carrying in a material. When installing a reinforced concrete shear wall in an opening where pillars, beams, and floors have been constructed earlier, a reinforced concrete shear wall will be installed in a place where there was no existing shear wall in connection with the repair work on the reinforced concrete structure. The present invention relates to a method of installing a reinforced concrete-made earthquake-resistant wall in an opening in which reinforced concrete or steel-frame columns, beams, and floors have already been built around four circumferences.

【0002】[0002]

【従来技術】かかる開口部に鉄筋コンクリート造り耐震
壁を設置する工法としては通常次の工法が採用されてい
る。(図2参照) (1)開口部四周の既存の柱、梁、床に鉄筋付き後施工
アンカーを打ち込んで(既存の柱、梁、床に予め取付け
金物が埋設されている場合は、その取付け金物に鉄筋を
とりつけて)鉄筋を開口部の中央に向けて突出させ、こ
の鉄筋に鉄筋を結束して縦横に配筋する。(2)配筋し
た鉄筋の両側に型枠を建て込む。片側の型枠の頂部は拡
大しており、この頂部からコンクリートを打設する。
(3)コンクリート硬化後、型枠を外し、頂部の出っ張
っているコンクリートをはつり取る。
2. Description of the Related Art The following method is generally employed as a method for installing a reinforced concrete earthquake-resistant wall in such an opening. (Refer to Fig. 2) (1) Driving post-installed anchors with reinforcing bars on the existing pillars, beams and floor around the opening (If the mounting hardware is already buried in the existing columns, beams and floor, install it The rebar is projected toward the center of the opening (with the rebar attached to the hardware), and the rebar is tied to this rebar and arranged vertically and horizontally. (2) The formwork is erected on both sides of the reinforced bar. The top of the formwork on one side is enlarged and concrete is poured from this top.
(3) After the concrete is hardened, the mold is removed and the protruding concrete on the top is removed.

【0003】[0003]

【発明が解決しようとする課題】従来の耐震壁の設置工
法では、(1)型枠の建て込み、撤去(2)型枠頂部か
らのコンクリートの打設のため足場の確保(3)コンク
リート打設時に床に流れ出る余剰水の処理(4)頂部の
出っ張っているコンクリートのはつり取り、などの多く
の作業を必要とする。また、コンクリートのはつり取り
の作業の際に騒音が発生するなどの問題点が指摘されて
いる。
According to the conventional method of installing a seismic wall, (1) building and removing a formwork; (2) securing a scaffold for placing concrete from the top of the formwork; and (3) concrete pouring. It requires a lot of work, such as treating excess water that flows to the floor at the time of construction and (4) removing the concrete that is protruding from the top. In addition, problems have been pointed out, such as the occurrence of noise during the work of concrete removal.

【0004】[0004]

【課題を解決するための手段】本発明は従来の耐震壁の
設置工法に関する上記の問題点に着目してなされたもの
で、(1)型枠の建て込み、撤去(2)床に流れ出る余
剰水の処理(3)出っ張りコンクリートのはつり取りな
どの作業を殆どなくし、作業用の足場も簡便なもので済
ますことができ、従来法の問題点を一挙に解決した耐震
壁の設置工法を提供するものである。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems relating to the conventional method of installing a seismic wall. (1) Building and removing a formwork (2) Surplus flowing out to the floor Water treatment (3) Providing a method of installing a seismic wall, which eliminates work such as stripping of projecting concrete and can simplify the work scaffolding, and solves the problems of the conventional method at once. Things.

【0005】即ち、本発明は、(A)垂直開口部に型鋼
板を建て込み該型鋼板の頂部を梁下に、該型鋼板の底部
を床に固定して、鉛直な耐震壁中央部を形成する操作、
(B)耐震壁中央部両側のそれぞれに、周囲の既存柱、
既存梁、既存床に一端が固定され、他端が型鋼板表面と
平行に延びている複数本の鉄筋および一端が型鋼板表面
に溶接され、他端が型鋼板表面から垂直に突出している
複数本のスペーサーを設置する操作、(C)複数枚の溶
接金網をスペーサーに固定して耐震壁中央部両側に型鋼
板表面と平行に配筋する操作、(D)溶接金網およびス
ペーサーを埋設するように、溶接金網の側方からモルタ
ルを吹きつけて打設する操作、よりなる鉄筋コンクリー
ト造り耐震壁の設置工法である。
That is, the present invention relates to (A) a steel plate is erected in a vertical opening, the top of the steel plate is fixed below the beam, the bottom of the steel plate is fixed to the floor, and the center of the vertical earthquake-resistant wall is fixed. Operation to form,
(B) On each side of the central part of the earthquake-resistant wall, the surrounding existing columns,
A plurality of rebars, one end of which is fixed to the existing beam and the existing floor, the other end of which extends parallel to the surface of the steel plate and the other end is welded to the surface of the steel plate, and the other end of which protrudes vertically from the surface of the steel plate (C) Fixing a plurality of welding wire meshes to the spacers and arranging reinforcing bars on both sides of the center of the earthquake-resistant wall in parallel with the surface of the shape steel plate. (D) Embedding the welding wire meshes and spacers. Then, the mortar is sprayed from the side of the welded wire mesh to drive the mortar.

【0006】本発明の要点は、型鋼板パネルで壁の中央
部を形成し、壁の主体はモルタルの吹き付けで造成する
点であり、このモルタルの吹き付けの施工に伴って、従
来のコンクリート打設による方法の際に使用する鉄筋に
比して小径の鋼棒から構成される溶接金網を補強筋とし
て使用する点である。
The gist of the present invention is that the central part of the wall is formed by a mold steel plate panel, and the main body of the wall is formed by spraying mortar. Is that a welded wire mesh composed of a steel rod having a smaller diameter than a reinforcing bar used in the method according to the above method is used as a reinforcing bar.

【0007】本発明においては、耐震壁中央部を形成す
る鋼板として鉛直方向の剛性確保や梁、床への固定の容
易さの面などから型鋼板が使用される。この型鋼板は通
常の溝型、波型でもよいが、二枚の平鋼板の間に溝型、
波型の型鋼板を挟んで相互に溶接したサンドイッチ型鋼
板が好ましい。
In the present invention, as the steel plate forming the central portion of the earthquake-resistant wall, a molded steel plate is used from the viewpoint of securing rigidity in the vertical direction and facilitating fixing to beams and floors. This type steel sheet may be a normal groove type or a corrugated type, but a groove type between two flat steel plates,
Sandwich type steel sheets welded to each other with a corrugated type steel sheet interposed therebetween are preferred.

【0008】本発明においては、造成されるモルタル壁
の厚さに応じて2〜4枚程度の溶接金網が使用される。
モルタルの厚さは通常150〜250mm程度であり、一
度のモルタルの吹き付け厚さ、モルタルの吹き付けに適
する溶接金網の目の粗さ、溶接金網を構成する鋼棒の径
などを勘案して溶接金網の枚数が決定され、通常は複数
枚の溶接金網を数十mm間隔でサンドイッチ型鋼板の両側
に平行に配筋する。
In the present invention, about 2 to 4 welded metal meshes are used depending on the thickness of the mortar wall to be formed.
The thickness of the mortar is usually about 150 to 250 mm, and the thickness of the mortar sprayed at one time, the roughness of the welding wire mesh suitable for spraying the mortar, the diameter of a steel rod constituting the welding wire mesh, and the like are taken into consideration. Usually, a plurality of welding wire meshes are arranged in parallel on both sides of the sandwich-type steel plate at intervals of several tens of mm.

【0009】溶接金網を配筋する場合、複数枚の溶接金
網を配筋した状態で一度にモルタルを吹き付け打設して
もよいが、一度のモルタルの吹き付け厚さには限度があ
り、その厚さを余り厚くすることは好ましくないので、
配筋−モルタルの吹き付け、を何回か繰り返して施工す
るのが好ましい。
[0009] When arranging a welded wire mesh, mortar may be sprayed and driven at a time with a plurality of welded wire meshes arranged, but there is a limit to the sprayed thickness of the mortar at one time. It is not preferable to make it too thick,
It is preferable to repeat the arrangement of the reinforcing bar and the spraying of the mortar several times.

【0010】本発明での(A)〜(D)の各操作は時間
的に(A)〜(D)の順序で施工することが必須である
という意味ではない。発明の内容を明瞭に説明するた
め、種々の操作を四つに分けて説明したものである。例
えば、(1)型鋼板の両側に多数のスペーサーを垂直に
溶接しておき、そのスペーサーに各2枚、計4枚の溶接
金網を固定する作業を現場以外の場所で行って、製造さ
れた複合部材を現場に運んで建て込む。(2)型鋼板の
両側に多数のスペーサーを垂直に溶接しておき、そのス
ペーサーに各1枚、計2枚の溶接金網を固定する作業を
現場以外の場所で行って、製造された複合部材を現場に
運んで建て込み、(B)の操作の中の複数本の鉄筋の設
置操作および(D)のモルタルの吹きつけを行い、その
後、モルタルの両表面より突出しているスペーサーに各
1枚、計2枚の溶接金網を固定する作業を現場で行い2
枚目の溶接金網を現場で配筋する。などの工法は本発明
工法の一例である。当然のことながら、現場での施工の
障害とならない範囲で可能な限り、使用部材の複合化を
進めておくことが好ましい。
The operations (A) to (D) in the present invention do not necessarily mean that it is necessary to perform the operations in the order of (A) to (D) in terms of time. In order to clearly explain the content of the invention, various operations are described in four parts. For example, (1) a large number of spacers are vertically welded to both sides of a type steel sheet, and two pieces of each of the spacers are fixed to the spacers, and a work of fixing a total of four welded metal meshes is performed at a place other than the site, and manufactured. Carry the composite member to the site and build it. (2) A composite member manufactured by welding a large number of spacers vertically on both sides of a mold steel plate and fixing a total of two welded metal meshes to each of the spacers at a place other than the site. Is carried to the site and built, and the operation of installing a plurality of rebars in the operation of (B) and the spraying of mortar in (D) are performed, and then one piece is placed on each of the spacers protruding from both surfaces of the mortar. , Work to fix two welded wire meshes on site
Arrange the second welding wire mesh on site. Such a method is an example of the method of the present invention. As a matter of course, it is preferable to promote the use of composite members as far as possible without hindering construction on site.

【0011】本発明で形成される耐震壁はコンクリート
の打設により形成される耐震壁に匹敵する品質が十分確
保されるが、モルタルに補強繊維を混入しておけばコン
クリート壁以上の高品質の壁を造成することは容易であ
る。
[0011] The earthquake-resistant wall formed by the present invention is sufficiently high in quality comparable to the earthquake-resistant wall formed by casting concrete, but if mortar is mixed with reinforcing fibers, it is of higher quality than concrete wall. Creating a wall is easy.

【0012】[0012]

【実施例】以下図面を参照しながら本発明の実施例を説
明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0013】図1は本発明工法の実施例を示すもので
(a)は一実施例の縦断面図であり、(b)は他の実施
例の縦断面図である。(なお、簡明にするため、吹き付
けたモルタルの図示は省略してある。) この実施例では型鋼板の両側にそれぞれ二枚の溶接金網
を配筋し、モルタルの吹き付けはそれぞれ2回に分けて
行った。以下の説明では一枚目の溶接金網を「内側の溶
接金網」と表現し、二枚目の溶接金網を「外側の溶接金
網」と表現する。また、型鋼板としては2枚の平鋼板の
間の溝型鋼板を溶接したサンドイッチ型鋼板を使用し
た。
FIGS. 1A and 1B show an embodiment of the method of the present invention. FIG. 1A is a longitudinal sectional view of one embodiment, and FIG. 1B is a longitudinal sectional view of another embodiment. (Incidentally, the illustration of the mortar sprayed is omitted for simplicity.) In this embodiment, two welding wire meshes are arranged on both sides of the mold steel plate, respectively, and the mortar is sprayed twice each. went. In the following description, the first welded mesh is referred to as “inner welded mesh”, and the second welded mesh is referred to as “outer welded mesh”. In addition, a sandwich-type steel sheet obtained by welding a groove-type steel sheet between two flat steel sheets was used as the type steel sheet.

【0014】まず、(a)の場合の施工手順を説明す
る。
First, the construction procedure in the case (a) will be described.

【0015】(1)型鋼板1の両表面に所定の間隔で多
数のスペーサー7・・の端を溶接し、内側の溶接金網
5,5がスペーサー7・・に結束されて型鋼板1表面と
平行に配筋されており、型鋼板1の頂端部には山型鋼1
5が底端部には溝型鋼16が溶接されているパネルを開
口部に建て込み、型鋼板1の頂端部を山型鋼15および
後施工アンカー9を介して既存梁2に固定し、型鋼板1
の底端部は溝型鋼16を既存床3に接着して固定して、
鉛直な耐震壁中央部を形成する。スペーサー7・・の先
端はそのままでもよいが、施工後の発錆を防止するた
め、先端にプラスチック製キャップ17を被せておくの
が好ましい。
(1) The ends of a number of spacers 7 are welded to both surfaces of the mold steel plate 1 at a predetermined interval, and the inner welding meshes 5 and 5 are bound to the spacers 7 and Bars are arranged in parallel.
5, a panel having a bottom end to which a channel steel 16 is welded is erected at the opening, and the top end of the shape steel plate 1 is fixed to the existing beam 2 via the angle steel 15 and the post-installed anchor 9; 1
At the bottom end, glue the channel steel 16 to the existing floor 3 and fix it.
Form a vertical central part of the shear wall. The tip of the spacer 7 may be left as it is, but it is preferable to cover the tip with a plastic cap 17 in order to prevent rusting after construction.

【0016】(2)型鋼板1の周囲の既存柱、既存梁
2、既存床3に適宜の間隔で鉄筋付き後施工アンカー8
(鉄筋付き後施工アンカーというのは、通常の後施工ア
ンカーに比較して鉄筋4が相当長く突出しているという
意味である。)を多数本打ち込み、鉄筋4を型鋼板1の
表面に平行に突出させる。(3)内側の溶接金網5,5
の表面からモルタルを吹き付ける。時々吹き付けを中断
してモルタルを押さえ、内側の溶接金網5,5が完全に
埋設され、スペーサー7の露出長さが所定の長さになる
までモルタルを吹き付ける。十分にモルタルを押さえ
る。
(2) Post-installed anchors 8 with reinforcing bars at existing columns, existing beams 2 and existing floor 3 around the shaped steel sheet 1 at appropriate intervals.
(The post-installed anchor with rebar means that the rebar 4 protrudes considerably longer than a normal post-installed anchor). Let it. (3) Inner welding wire mesh 5,5
Spray mortar from the surface. Spraying is interrupted from time to time to hold the mortar, and the mortar is sprayed until the inner welding meshes 5, 5 are completely buried and the exposed length of the spacer 7 becomes a predetermined length. Hold the mortar well.

【0017】(4)押さえられたモルタルの表面に外側
の溶接金網6,6をあてがい、外側の溶接金網6,6を
突出しているスペーサー7に結束または溶接して固定
し、外側の溶接金網6,6と内側の溶接金網5,5との
間隔が所定の値になるよう鉛直に配筋する。
(4) The outer welding meshes 6 and 6 are applied to the surface of the pressed mortar, and the outer welding meshes 6 and 6 are bound or welded to the projecting spacers 7 and fixed. , 6 and the inner wire meshes 5, 5 are arranged vertically so as to have a predetermined value.

【0018】(5)外側の溶接金網6,6の表面からモ
ルタルを吹き付ける。時々吹き付けを中断してモルタル
を押さえながら外側の溶接金網6,6が完全に埋設さ
れ、スペーサー7の先端のプラスチック製キャップ17
が見え隠れするまでモルタルを吹き付ける。モルタルを
押さえて所定のモルタル表面13にまで十分モルタルが
吹き付けられたことを確認して、施工を終了する。
(5) Mortar is sprayed from the surfaces of the outer welded metal meshes 6,6. The outer welding wire meshes 6, 6 are completely buried while holding the mortar by stopping the spraying from time to time, and the plastic cap 17 at the tip of the spacer 7 is provided.
Spray mortar until the glow disappears. It is confirmed that the mortar has been sufficiently sprayed to the predetermined mortar surface 13 by holding down the mortar, and the construction is completed.

【0019】上記の施工例では型鋼板1の建て込み前に
既に内側の溶接金網5,5まで取りつけられたパネルを
建て込んだが、型鋼板1のみを建て込み、現場でスペー
サー7、内側の溶接金網5,5を取りつけてもよい。
(b)で図示するものは既存梁2が鉄骨造りである点が
(a)と異なっているのみである。従って、型鋼板1お
よび鉄筋4の既存梁2への固定方法が若干異なっている
のみで、他は(a)と同じである。(b)の場合は既存
梁2が鉄骨で溶接可能であるので型鋼板1頂端部の山型
鋼15は既存梁2に溶接して固定され、鉄筋4の端も既
存梁2に溶接して固定されている。
In the above-mentioned construction example, the panels already attached to the inner welding meshes 5 and 5 were erected before the mold steel plate 1 was erected, but only the mold steel plate 1 was erected and the spacer 7 and the inner welder were welded on site. Wire meshes 5 and 5 may be attached.
(B) is different from (a) only in that the existing beam 2 is made of steel. Therefore, only the method of fixing the mold steel plate 1 and the reinforcing bar 4 to the existing beam 2 is slightly different, and the other is the same as (a). In the case of (b), since the existing beam 2 can be welded with a steel frame, the angle steel 15 at the top end of the shaped steel plate 1 is fixed to the existing beam 2 by welding, and the end of the reinforcing bar 4 is also fixed to the existing beam 2 by welding. Have been.

【0020】[0020]

【発明の効果】【The invention's effect】

(1)型枠の建て込み、撤去(2)床に流れ出る余剰水
の処理(3)余分のコンクリートのはつり取りなどの作
業は殆どなくなり、作業用の足場も人間専用の簡便なも
ので済ますことができるようになるので、作業量が大幅
に低下するだけでなく、はつり取りに伴う騒音を完全に
排除することができる。
(1) Installation and removal of formwork (2) Treatment of surplus water flowing to the floor (3) Elimination of extra concrete work such as stripping, and a simple scaffold for human work As a result, not only the amount of work is significantly reduced, but also the noise caused by the picking can be completely eliminated.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1は本発明工法の実施例を示すもので(a)
は一実施例の縦断面図であり、(b)は他の実施例の縦
断面図である。(なお、簡明にするため、吹き付けたモ
ルタルの図示は省略してある。)
FIG. 1 shows an embodiment of the method of the present invention (a).
FIG. 6 is a longitudinal sectional view of one embodiment, and FIG. 6B is a longitudinal sectional view of another embodiment. (Note that, for simplicity, the illustration of the sprayed mortar is omitted.)

【図2】従来法の例を示すもので(a)、(b)は既存
柱、既存梁、既存床がすべて鉄筋コンクリート造りの場
合であり、(a)は縦断面図、(b)は横断面図であ
る。(c)は既存柱、既存床が鉄筋コンクリート造りで
あり、既存梁が鉄骨造りの場合の縦断面図である。
FIG. 2 shows an example of a conventional method, in which (a) and (b) show the case where the existing columns, beams and existing floors are all made of reinforced concrete, (a) is a longitudinal sectional view, and (b) is a transverse view. FIG. (C) is a longitudinal sectional view when the existing pillars and the existing floor are made of reinforced concrete and the existing beams are made of steel.

【符号の説明】[Explanation of symbols]

1・・型鋼材、2・・既存梁、3・・既存床、4・・鉄
筋、5・・内側の溶接金網、6・・外側の溶接金網、7
・・スペーサー、8・・後施工アンカー、9・・後施工
アンカー、10・・型枠、11・・型枠拡大部、12・
・既存柱、13・・施工終了時のモルタル表面、14・
・鉄筋、15・・山型鋼、16・・溝型鋼、17・・プ
ラスチック製キャップ。
1 .... Steel steel, 2 .... Existing beam, 3 .... Existing floor, 4 .... Reinforcing bar, 5 ... Inner welding wire mesh, 6 ... Outer welding wire mesh, 7
··· Spacer, 8 ··· Post-installed anchor, 9 ··· Post-installed anchor, 10 ··· Formwork, 11 ··· Formwork enlarged part, 12
・ Existing pillar, 13 ・ ・ Mortar surface at the end of construction, 14.
・ Reinforcing bar, 15 ・ ・ Angle steel, 16 ・ ・ Groove, 17 ・ ・ Plastic cap.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 (A)垂直開口部に型鋼板を建て込み該
型鋼板の頂部を梁下に、該型鋼板の底部を床に固定し
て、鉛直な耐震壁中央部を形成する操作、(B)耐震壁
中央部両側のそれぞれに、周囲の既存柱、既存梁、既存
床に一端が固定され、他端が型鋼板表面と平行に延びて
いる複数本の鉄筋および一端が型鋼板表面に溶接され、
他端が型鋼板表面から垂直に突出している複数本のスペ
ーサーを設置する操作、(C)複数枚の溶接金網をスペ
ーサーに固定して耐震壁中央部両側に型鋼板表面と平行
に配筋する操作、(D)溶接金網およびスペーサーを埋
設するように、溶接金網の側方からモルタルを吹きつけ
て打設する操作、よりなる鉄筋コンクリート造り耐震壁
の設置工法。
(A) An operation of forming a vertical steel plate in a vertical opening, fixing a steel plate in a vertical opening, fixing a top of the steel plate below a beam, and fixing a bottom of the steel plate to a floor, (B) A plurality of rebars, one end of which is fixed to the existing pillars, existing beams, and the existing floor, and the other end extends in parallel with the surface of the steel plate, and one end of the steel plate surface, Welded to
An operation of installing a plurality of spacers, the other ends of which project perpendicularly from the surface of the steel sheet. (C) Fixing a plurality of welding wire meshes to the spacers and arranging reinforcing bars on both sides of the center of the earthquake-resistant wall in parallel with the surface of the steel sheet. (D) A method of installing a reinforced concrete earthquake-resistant wall, which comprises: blasting mortar from the side of the welded wire mesh so as to bury the welded wire mesh and spacer.
【請求項2】 複数枚の溶接金網を複数回に分けて1枚
毎に配筋するとともに、1枚の配筋の度に配筋した溶接
金網を埋設するように複数回に分けてモルタルを吹きつ
けて打設することを特徴とする請求項1記載の鉄筋コン
クリート造り耐震壁の設置工法。
2. A method of arranging a plurality of welding wire meshes in a plurality of times and arranging reinforcing bars for each piece, and dividing the mortar into a plurality of times so as to bury the welding wire meshes arranged in each one of the reinforcing wires. 2. The method for installing a reinforced concrete earthquake-resistant wall according to claim 1, wherein the installation is performed by spraying.
JP18328594A 1994-08-04 1994-08-04 Installation method of reinforced concrete shear walls Expired - Fee Related JP2891113B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18328594A JP2891113B2 (en) 1994-08-04 1994-08-04 Installation method of reinforced concrete shear walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18328594A JP2891113B2 (en) 1994-08-04 1994-08-04 Installation method of reinforced concrete shear walls

Publications (2)

Publication Number Publication Date
JPH0849330A JPH0849330A (en) 1996-02-20
JP2891113B2 true JP2891113B2 (en) 1999-05-17

Family

ID=16132981

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18328594A Expired - Fee Related JP2891113B2 (en) 1994-08-04 1994-08-04 Installation method of reinforced concrete shear walls

Country Status (1)

Country Link
JP (1) JP2891113B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6240420B2 (en) * 2013-07-05 2017-11-29 株式会社竹中工務店 Seismic reinforcement structure
CN104499608B (en) * 2014-12-19 2017-03-08 江苏鼎达建筑新技术有限公司 The design and construction method of prestressing force section steel reinforcement shear wall

Also Published As

Publication number Publication date
JPH0849330A (en) 1996-02-20

Similar Documents

Publication Publication Date Title
JP2915897B1 (en) Building construction method
JP2927402B2 (en) Column-beam joint structure of concrete building
JP2891113B2 (en) Installation method of reinforced concrete shear walls
JP3306632B2 (en) Construction method of building
JP2914183B2 (en) Thickening reinforcement method of existing earthquake-resistant wall
JP2929119B2 (en) Construction method of ramen type RC high-rise building
JP2004250904A (en) Antiseismic reinforcing method for existing building
JP3271810B2 (en) A method for manufacturing a heat-insulated half-PC plate.
JPH042743B2 (en)
JPH1025840A (en) Constructing method for building frame with precast anti-seismic wall
JPH0380946B2 (en)
JPH084203A (en) Steel framed reinforcement beam and execution method thereof
JPH0266246A (en) Insulating concrete with space truss and construction thereof
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPH07292855A (en) Steel encased reinforcing concrete girder
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JP3010355B1 (en) Construction method of joint of prestressed concrete floor
JPH09112042A (en) Method for reinforcing vibration resistance of building
JPH0211521Y2 (en)
JPH06136821A (en) Construction method for steel frame reinforced concrete structure
KR20020033125A (en) supporting structure for slab form of steel frame concrete structure
JPH0318561Y2 (en)
KR0137463Y1 (en) Deck panels of reinforced concrete slabs
JPS5833672A (en) Construction of concrete slab
JPH01223248A (en) Folded plate unit slab construction

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990126

LAPS Cancellation because of no payment of annual fees