KR20020033125A - supporting structure for slab form of steel frame concrete structure - Google Patents
supporting structure for slab form of steel frame concrete structure Download PDFInfo
- Publication number
- KR20020033125A KR20020033125A KR1020020011983A KR20020011983A KR20020033125A KR 20020033125 A KR20020033125 A KR 20020033125A KR 1020020011983 A KR1020020011983 A KR 1020020011983A KR 20020011983 A KR20020011983 A KR 20020011983A KR 20020033125 A KR20020033125 A KR 20020033125A
- Authority
- KR
- South Korea
- Prior art keywords
- bracket
- concrete structure
- formwork
- beams
- insertion hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 33
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 16
- 239000010959 steel Substances 0.000 title claims abstract description 16
- 238000009415 formwork Methods 0.000 claims abstract description 35
- 238000003780 insertion Methods 0.000 claims abstract description 13
- 230000037431 insertion Effects 0.000 claims abstract description 13
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 claims description 20
- 229910052802 copper Inorganic materials 0.000 claims description 19
- 239000010949 copper Substances 0.000 claims description 19
- 238000010276 construction Methods 0.000 abstract description 13
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 239000012779 reinforcing material Substances 0.000 description 4
- 210000000078 claw Anatomy 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 239000011178 precast concrete Substances 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000003566 sealing material Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/02—Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
본 발명은 철골콘크리트 구조물의 상판 시공후 거푸집의 해체 작업이 용이함과 더불어, 구조물의 정밀시공이 가능하여 품질의 향상을 기할 수 있도록 된 철골콘크리트 구조물의 상판 거푸집 지지구조에 관한 것이다.The present invention relates to the top plate formwork structure of the steel concrete structure to facilitate the dismantling of the formwork after the top plate construction of the steel concrete structure, and to improve the quality of the structure.
본 발명에 따르면, PC빔(5)을 구조재로 사용하여 교량이나 건물의 상판을 시공하도록 된 철골콘크리트 구조물에 있어서, 상기 PC빔(5)의 상면에 거치되며 그 양단부에는 PC빔(5)의 양측으로 돌출되는 연결부재(15)가 구비된 지지부재(10)와, 마주보는 한 쌍의 PC빔(5) 사이에 소정 간격으로 배치되는 다수개의 동바리(20)와, 이 동바리(20)의 양단부에서 수평방향으로 외향돌출되며 그 중앙부에는 볼트삽입공(34)이 형성된 브라켓(32)과, 상기 브라켓(32)의 볼트삽입공(34)과 연결부재(15)의 관통공(17)을 통과하여 체결되는 볼트부재(40) 및 너트부재(50)를 포함하여 구성되며, 상기 브라켓(32)의 볼트삽입공(34)과 연결부재(15)의 관통공(17)을 통해 볼트부재(40)와 너트부재(50)를 체결하여, 상기 동바리(20)를 서로 대향하는 한 쌍의 PC빔(5) 사이에 거치한 후, 상기 동바리(20)의 상면에 거푸집패널(2)을 배치하도록 된 것을 특징으로 하는 철골콘크리트 구조물의 상판 거푸집 지지구조가 제공된다.According to the present invention, in a steel concrete structure configured to construct a top plate of a bridge or a building using the PC beam 5 as a structural member, the PC beam 5 is mounted on the upper surface of the PC beam 5 at both ends of the PC beam 5. The support member 10 is provided with a connecting member 15 protruding to both sides, and a plurality of clubs 20 arranged at predetermined intervals between the pair of PC beams 5 facing each other, and the Protruding outwardly from both ends in the horizontal direction and having a bracket 32 having a bolt insertion hole 34 formed therein, a bolt insertion hole 34 of the bracket 32 and a through hole 17 of the connection member 15; It comprises a bolt member 40 and the nut member 50 is fastened to pass through, through the bolt insertion hole 34 of the bracket 32 and the through hole 17 of the connecting member 15 bolt member ( 40 and the nut member 50 are fastened to each other, and the pinwheel 20 is mounted between a pair of PC beams 5 facing each other. The upper die support structure of the steel-concrete structures, characterized in that the arrangement for the formwork panel (2) is provided at the surface.
Description
본 발명은 철골콘크리트 구조물의 상판 거푸집 지지구조에 관한 것으로서, 보다 상세하게는 철골콘크리트 구조물의 상판 시공후 거푸집의 해체 작업이 용이함과 더불어, 구조물의 정밀시공이 가능하여 품질의 향상을 기할 수 있도록 된 철골콘크리트 구조물의 상판 거푸집 지지구조에 관한 것이다.The present invention relates to a top plate formwork supporting structure of steel concrete structure, and more particularly, to facilitate the dismantling of the formwork after the top plate of the steel concrete structure, the precision construction of the structure is possible to improve the quality It relates to a top plate formwork structure of steel concrete structure.
일반적으로, 철골콘크리드구조의 교량이나 건물의 시공하는 경우에, 교량이나 건물 상판에 콘크리트를 타설하기 위해서는, 수평방향으로 평행 연장되는 프리캐스트 콘크리트빔(이하, PC빔이라 함)을 소정 간격으로 다수개 시공하고, 서로 마주보는 PC빔 사이에 다수개의 동바리를 소정 간격으로 설치한 다음, 이 동바리 위에 거푸집패널을 깔아서 상판용 거푸집을 가설한다. 다시 말해서, 상기 PC빔의 상면에는 수평 방향으로 다수개의 앵커철근이 돌출설치되어 있으므로, 와이어에 의해 상기 동바리의 양단부를 서로 마주보는 PC빔의 앵커철근에 결속함으로써, 상기 동바리를 PC빔 사이에 고정 설치한다. 그리고, 이러한 방법으로 다수개의 동바리를 PC빔의 수평방향을 따라 소정 간격으로 설치한 다음, 상기 동바리 위에 거푸집패널을 깔아서 상판용 거푸집을 가설하게 되는 것이다.In general, in the case of constructing a steel concrete bridge or building, in order to place concrete on a bridge or a building deck, precast concrete beams (hereinafter referred to as PC beams) extending in parallel in a horizontal direction are spaced at predetermined intervals. A plurality of constructions are installed, and a plurality of clubs are installed at predetermined intervals between the PC beams facing each other, and then the formwork panel is laid by laying a form panel on the clubs. In other words, since a plurality of anchor bars protrude in the horizontal direction on the upper surface of the PC beam, the copper bars are fixed between the PC beams by binding both ends of the copper bars to anchor bars of the PC beams facing each other by wires. Install. In this way, a plurality of copper bars are installed at predetermined intervals along the horizontal direction of the PC beam, and then a form panel for the upper plate is laid by laying a form panel on the copper bars.
그런데, 이러한 거푸집구조에 의한 콘크리트 구조물의 시공방법은 상기 동바리와 와이어의 결속 부위를 충분히 조여주지 못해 취약하므로, 상기 동바리와 이에설치되는 거푸집패널의 높이가 균일하지 못하게 된다. 따라서, 정밀한 시공이 이루어지지 못하므로, 구조물의 품질이 저하되는 문제점이 있다. 또한, 상판의 시공 후에는 상기 와이어를 절단하여 동바리와 거푸집 패널을 분리하게 되는데, 이렇게 절단되고 남은 와이어가 콘크리트 구조물의 외부로 노출됨과 더불어, 장기간이 소요되면 녹슬게 되므로, 미관의 손상을 야기할 뿐만 아니라, 구조물에 취약부가 발생되면서 균열이 생기게 되는 등의 여러 가지 문제점이 있다.However, the construction method of the concrete structure by such a form structure is fragile enough to tighten the binding portion of the copper bar and the wire, so that the height of the copper bar and the formwork panel installed thereon is not uniform. Therefore, since the precise construction is not made, there is a problem that the quality of the structure is reduced. In addition, after the construction of the top plate to cut the wire to separate the copper bar and the formwork panel, the wire cut and remaining so exposed to the outside of the concrete structure, and will be rusted for a long time, causing damage to the appearance In addition, there are various problems such as cracks generated while the weak part is generated in the structure.
본 발명은 전술한 바와 같은 문제점에 착안하여 제안된 것으로서, 본 발명의 목적은 철골콘크리트 구조물의 상판 시공후 거푸집의 해체 작업이 용이함과 더불어, 구조물의 정밀시공이 가능하여 품질의 향상을 기할 수 있도록 된 철골콘크리트 구조물의 상판 거푸집 지지구조를 제공하고자 하는 것이다.The present invention has been proposed in view of the problems described above, the object of the present invention is to facilitate the dismantling of the formwork after the top plate of steel concrete structure, and to enable the precise construction of the structure to improve the quality It is to provide a top plate formwork supporting structure of the steel frame concrete structure.
도 1은 본 발명의 실시예에 따른 구조물의 개략적인 단면도1 is a schematic cross-sectional view of a structure according to an embodiment of the present invention.
도 2는 도 1의 주요부의 단면도2 is a cross-sectional view of the main part of FIG.
도 3은 콘크리트가 타설된 상태의 단면도3 is a cross-sectional view of a state where concrete is poured
도 4는 거푸집패널이 배치된 상태의 평면도4 is a plan view of the formwork panel is disposed
<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>
2. 거푸집패널 5. PC빔2. Formwork panel 5. PC beam
10. 지지부재 15. 연결부재10. Support member 15. Connection member
20. 동바리 32. 브라켓20.Dongbar 32.Bracket
40. 볼트부재 50. 너트부재40. Bolt member 50. Nut member
본 발명에 따르면, PC빔(5)을 구조재로 사용하여 교량이나 건물의 상판을 시공하도록 된 철골콘크리트 구조물에 있어서, 상기 PC빔(5)의 상면에 거치되며 그 양단부에는 PC빔(5)의 양측으로 돌출되는 연결부재(15)가 구비된 지지부재(10)와, 마주보는 한 쌍의 PC빔(5) 사이에 소정 간격으로 배치되는 다수개의 동바리(20)와, 이 동바리(20)의 양단부에서 수평방향으로 외향돌출되며 그 중앙부에는 볼트삽입공(34)이 형성된 브라켓(32)과, 상기 브라켓(32)의 볼트삽입공(34)과 연결부재(15)의 관통공(17)을 통과하여 체결되는 볼트부재(40) 및 너트부재(50)를 포함하여 구성되며, 상기 브라켓(32)의 볼트삽입공(34)과 연결부재(15)의 관통공(17)을 통해 볼트부재(40)와 너트부재(50)를 체결하여, 상기 동바리(20)를 서로 대향하는 한 쌍의 PC빔(5) 사이에 거치한 후, 상기 동바리(20)의 상면에 거푸집패널(2)을 배치하도록 된 것을 특징으로 하는 철골콘크리트 구조물의 상판 거푸집 지지구조가 제공된다.According to the present invention, in a steel concrete structure configured to construct a top plate of a bridge or a building using the PC beam 5 as a structural member, the PC beam 5 is mounted on the upper surface of the PC beam 5 at both ends of the PC beam 5. The support member 10 is provided with a connecting member 15 protruding to both sides, and a plurality of clubs 20 arranged at predetermined intervals between the pair of PC beams 5 facing each other, and the Protruding outwardly from both ends in the horizontal direction and having a bracket 32 having a bolt insertion hole 34 formed therein, a bolt insertion hole 34 of the bracket 32 and a through hole 17 of the connection member 15; It comprises a bolt member 40 and the nut member 50 is fastened to pass through, through the bolt insertion hole 34 of the bracket 32 and the through hole 17 of the connecting member 15 bolt member ( 40 and the nut member 50 are fastened to each other, and the pinwheel 20 is mounted between a pair of PC beams 5 facing each other. The upper die support structure of the steel-concrete structures, characterized in that the arrangement for the formwork panel (2) is provided at the surface.
이하, 본 발명의 바람직한 실시예를 첨부한 도면에 의거하여 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.
도 1은 본 발명의 일 실시예에 따른 구조물의 개략 단면도이고, 도 2는 도 1의 주요부의 확대도이고, 도 3은 콘크리트가 타설된 상태의 단면도이며, 도 4는 거푸집패널이 배치된 상태의 평면도를 도시한 것이다. 이를 참조하면, 상기 철골콘크리트구조물의 상판 거푸집 지지구조는 다수개의 프리캐스트 콘크리트빔(PC빔)(5)이 소정 간격으로 나란하게 배치되고, 대향하는 한 쌍의 PC빔(5) 사이에는 다수개의 동바리(20)가 설치된다. 상기 동바리(20)는 대략 1m 정도의 간격으로 배치되며, 이 동바리(20)의 상면에 거푸집패널(2)을 올려놓게 된다.1 is a schematic cross-sectional view of a structure according to an embodiment of the present invention, FIG. 2 is an enlarged view of a main part of FIG. 1, FIG. 3 is a cross-sectional view of a state in which concrete is poured, and FIG. 4 is a state in which formwork panels are disposed. A top view of the is shown. Referring to this, in the formwork supporting structure of the steel plate concrete structure, a plurality of precast concrete beams (PC beams) 5 are arranged side by side at a predetermined interval, and a plurality of opposing pairs of PC beams 5 are disposed. The club 20 is installed. The clubs 20 are arranged at intervals of about 1 m, and the formwork panel 2 is placed on the top surface of the clubs 20.
상기 지지부재(10)는 수직의 평철로 이루어져 상기 PC빔(5)의 상면에 거치되는 것으로, 그 양단부에는 평철로 이루어진 연결부재(15)가 수평하게 용접되며, 이 연결부재(15)의 중앙부에는 볼트부재(40)가 삽입되는 관통공(17)이 형성되어 있다. 상기 동바리(20)는 그 양단부에 용접된 브라켓(32)에 의해 서로 마주보는 한 쌍의PC빔(5) 사이에 소정 간격으로 다수개 거치되는 것으로, 그 상면에 거푸집패널(2)을 배치하도록 구성된다. 다시 말해서, 상기 동바리(20)의 양단부에는 ??자형의 브라켓(32)이 용접되어 있고, 상기 브라켓(32)의 상면 중앙부에는 볼트삽입공(34)이 형성되어 있으므로, 상기 볼트삽입공(34)의 하부에서 상기 연결부재(15)의 관통공(17)을 관통시키고, 이 볼트부재(40)에 너트부재(50)를 체결하면, 서로 마주보는 한 쌍의 PC빔(5) 사이에 동바리(20)를 거치할 수 있다.The support member 10 is made of vertical flat iron and is mounted on the upper surface of the PC beam 5, and both ends thereof are welded horizontally with a connecting member 15 made of flat iron, and a central portion of the connecting member 15 is formed. The through-hole 17 is inserted into the bolt member 40 is formed. The clubs 20 are mounted at a plurality of predetermined intervals between the pair of PC beams 5 facing each other by the brackets 32 welded at both ends thereof, so that the formwork panel 2 is disposed on the upper surface thereof. It is composed. In other words, the bracket 32 is welded to both ends of the copper bar 20, and the bolt insertion hole 34 is formed at the center of the upper surface of the bracket 32, so that the bolt insertion hole 34 Penetration through the through-hole 17 of the connecting member 15 from the lower portion of the), and fastening the nut member 50 to the bolt member 40, between the pair of PC beams (5) facing each other 20 can be mounted.
상기 브라켓(32)은 대략 ??자형으로 이루어진 것으로, 상기 동바리(20)의 양단부에 용접되며, 그 상면 중앙부에는 볼트삽입공(34)이 형성되어 있다. 이에 따라, 상기 지지부재(10) 양단부의 연결부재(15)가 PC빔(5)의 양측으로 돌출되도록 다수개의 지지부재(10)를 PC빔(5)의 상면에 거치시키고, 상기 볼트부재(40)를 동바리(20)의 양단부에 용접된 브라켓(32)의 볼트삽입공(34) 하부에서 연결부재(15)의 관통공(17)을 통과시키고, 상기 연결부재(15)의 상면에서 볼트부재(40)에 너트부재(50)를 체결하면, 상기 동바리(20)를 서로 대향하는 PC빔(5) 사이에 거치할 수 있다. 그리고, 이러한 방법에 의해 다수개의 동바리(20)를 한 쌍의 PC빔(5) 사이에 소정 간격으로 다수개 설치하고, 상기 동바리(20) 위에 거푸집패널(2)을 배치할 수 있다. 이때, 상기 거푸집패널(2)의 상면과 연결부재(15)의 저면 사이에, 도 2에 도시된 바와 같이, 별도의 스페이서(18)를 개재시켜, 상기 동바리(20)와 연결부재(15) 사이의 간격을 조절할 수 있다. 또한, 상기 브라켓(32)과 거푸집패널(2) 사이에는 동바리(20)와 교차되는 방향으로 별도의 보강재(41)를 설치할 수도 있다.The bracket 32 is formed in a substantially? -Shape, and is welded to both ends of the copper club 20, and a bolt insertion hole 34 is formed at the center of the upper surface thereof. Accordingly, the plurality of supporting members 10 are mounted on the upper surface of the PC beam 5 so that the connecting members 15 at both ends of the supporting member 10 protrude to both sides of the PC beam 5, and the bolt member ( 40 through the through hole 17 of the connection member 15 through the lower portion of the bolt insertion hole 34 of the bracket 32 welded to both ends of the copper club 20, the bolt on the upper surface of the connection member 15 When the nut member 50 is fastened to the member 40, the club 20 can be mounted between the PC beams 5 facing each other. In this manner, a plurality of copper claws 20 may be provided between the pair of PC beams 5 at predetermined intervals, and the formwork panel 2 may be disposed on the copper claws 20. At this time, between the upper surface of the formwork panel 2 and the bottom surface of the connecting member 15, as shown in Figure 2, through a separate spacer 18, the copper plate 20 and the connecting member 15 You can adjust the spacing between them. In addition, a separate reinforcing material 41 may be installed between the bracket 32 and the formwork panel 2 in a direction intersecting with the grouping 20.
시공시에는, 도 4에 도시된 바와 같이, 상기 동바리(20)의 상면에 거푸집패널(2)을 종횡으로 깔아주어 상판용 거푸집을 시공한다. 한편, 상기 동바리(20)의 상면에 동바리(20)와 교차되는 방향으로 다수개의 보강재(41)를 설치할 수도 있는데, 상기 보강재(41) 중에서 두 개의 보강재(41)는, 도 2에 도시된 바와 같이, 상기 거푸집패널(2)과 브라켓(32) 사이에 위치되도록 설치하는 것이 바람직하다. 이때, 상기 거푸집패널(2)이 맞닿는 부위에는 실링재를 충전하는 등과 같이 타설될 생콘크리트의 누설이 방지되도록 하는 것이 바람직하다. 이렇게 상기 거푸집패널(2)과 브라켓(32) 사이와 이와 같이 상판용 거푸집이 완성되면, 그 위에 철근을 배근하고 생콘트리트를 타설하여 시공하게 된다. 그리고, 상기 콘크리트가 완전히 경화된 후에 볼트부재(40)를 풀어주게 되면, 상기 동바리(20)와 거푸집패널(2) 및 보강재(41)를 간편하게 제거할 수 있다. 또한, 이처럼 콘크리트가 완전히 양생되어 거푸집을 해체한 후에도, 상기 지지부재(10)와 연결부재(15)가 콘크리트 구조물의 외부로 노출되지 않고 은폐된다. 한편, 상기 볼트부재(40)가 빠진 구멍에 별도의 콘크리트몰탈을 충진하여 마감함으로써, 콘크리트 구조물의 공사를 마무리한다.At the time of construction, as shown in Figure 4, the formwork panel (2) on the upper surface of the copper bar (20) is laid vertically and horizontally to form the formwork for the top plate. On the other hand, a plurality of reinforcement 41 may be provided on the upper surface of the copper bar 20 in the direction crossing with the copper bar 20, two of the reinforcing material 41 of the reinforcing material 41, as shown in FIG. Likewise, it is preferable to install so as to be located between the formwork panel 2 and the bracket (32). At this time, it is preferable to prevent the leakage of the raw concrete to be poured, such as filling the sealing material in the site where the formwork panel 2 abuts. When the formwork for the upper plate is completed in this way between the formwork panel 2 and the bracket 32, the reinforcing bar is placed thereon and the raw concrete is poured. Then, when the bolt member 40 is released after the concrete is completely hardened, the copper wheel 20, the formwork panel 2 and the reinforcing material 41 can be easily removed. In addition, even after the concrete is completely cured and dismantled, the support member 10 and the connection member 15 are concealed without being exposed to the outside of the concrete structure. On the other hand, the bolt member 40 is finished by filling a separate concrete mortar in the missing hole, thereby finishing the construction of the concrete structure.
따라서, 상기 철골콘크리트구조물의 상판 거푸집 지지구조는 콘크리트 구조물의 시공후, 상기 볼트부재(40)를 풀어주기만 하면, 상기 동바리(20)와 거푸집패널(2)을 제거할 수 있으므로, 거푸집의 해체 작업이 신속하면서도 간편한 장점이 있다. 또한, 상기 동바리(20)를 와이어로 결속하여 PC빔(5)에 설치하였던 종래와 달리, 상기 동바리(20)와 지지부재(10)의 결속부위가 균일하면서도 견고하게 조여지므로, 상기 동바리(20)와 이에 설치되는 거푸집패널(2)의 높이가 균일하다. 이에 따라, 콘크리트 구조물의 정밀한 시공이 가능하므로, 품질의 향상을 기할 수 있다. 또한, 상기 와이어를 절단하여 동바리(20)를 제거함으로 인하여 와이어의 외부 노출과 부식이 불가피하였던 종래와 달리, 상기 지지부재(10)와 연결부재(15)가 구조물의 외부로 노출되지 않으므로, 미관의 손상을 방지할 수 있으며, 장기간이 소요되더라도 종래와 같이 와이어의 부식 등에 의해 구조물에 취약부가 발생되는 것을 효율적으로 방지할 수 있다.Therefore, the upper formwork support structure of the steel concrete structure is to remove the bolts 20 and the formwork panel 2 only after releasing the bolt member 40 after the construction of the concrete structure, the dismantling work of the formwork This has the advantage of being quick and easy. In addition, unlike the prior art, which binds the group 20 with a wire and is installed on the PC beam (5), since the binding part of the group 20 and the support member 10 is uniformly and firmly tightened, the group 20 And the height of the formwork panel (2) installed thereon is uniform. As a result, precise construction of the concrete structure is possible, thereby improving quality. In addition, unlike the prior art in which the external exposure and corrosion of the wire was inevitable by cutting the wire to remove the copper claw 20, the support member 10 and the connecting member 15 are not exposed to the outside of the structure, and thus aesthetics The damage can be prevented, and even if a long period of time can be effectively prevented from generating a weak point in the structure due to corrosion of the wire, as in the prior art.
이상에서와 같이 본 발명에 의하면, 상기 철골콘크리트구조물의 상판 거푸집 지지구조는 콘크리트 구조물의 시공후 신속하면서도 간편하게 거푸집을 해체할 수 있고, 구조물의 정밀한 시공이 가능하므로, 품질의 향상을 기할 수 있으며, 장기간이 소요되더라도 구조물에 부분적인 취약부가 발생되는 것을 방지할 수 있다.As described above, according to the present invention, the top plate formwork structure of the steel concrete structure can be quickly and easily dismantled formwork after the construction of the concrete structure, it is possible to precise construction of the structure, it is possible to improve the quality, Even if it takes a long time, partial weakening of the structure can be prevented.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020020011983A KR20020033125A (en) | 2002-03-06 | 2002-03-06 | supporting structure for slab form of steel frame concrete structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020020011983A KR20020033125A (en) | 2002-03-06 | 2002-03-06 | supporting structure for slab form of steel frame concrete structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| KR20020033125A true KR20020033125A (en) | 2002-05-04 |
Family
ID=19719633
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020020011983A Ceased KR20020033125A (en) | 2002-03-06 | 2002-03-06 | supporting structure for slab form of steel frame concrete structure |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR20020033125A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100914546B1 (en) * | 2009-04-23 | 2009-09-01 | 주식회사 예경산업개발 | Multi-axis punching drill device and construction method using the same |
| KR100928166B1 (en) * | 2007-08-09 | 2009-11-25 | 주식회사 동아기술공사 | Plain formwork installed prefabricated on the lower flange of type I concrete beam, and construction method of upper slab bridge and disassembly form of formless formwork using the same |
| CN111271123A (en) * | 2020-01-15 | 2020-06-12 | 中铁第四勘察设计院集团有限公司 | Subway station prefabricated rail top air duct structure and construction method |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR19990014533A (en) * | 1998-11-20 | 1999-02-25 | 이호산 | Top plate formwork structure of steel concrete structure |
| KR19990073084A (en) * | 1999-04-19 | 1999-10-05 | 김태환 | Formwork method using no prop for the floor concrete of the bridge |
| KR19990078743A (en) * | 1998-11-06 | 1999-11-05 | 김장열 | Construction method using mold equipped with shape steel and plywood |
| KR20020001480A (en) * | 2000-06-26 | 2002-01-09 | 김준규 | Steel form for slab concrete applicable to P.C. beam or Steel Box methods |
-
2002
- 2002-03-06 KR KR1020020011983A patent/KR20020033125A/en not_active Ceased
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR19990078743A (en) * | 1998-11-06 | 1999-11-05 | 김장열 | Construction method using mold equipped with shape steel and plywood |
| KR19990014533A (en) * | 1998-11-20 | 1999-02-25 | 이호산 | Top plate formwork structure of steel concrete structure |
| KR19990073084A (en) * | 1999-04-19 | 1999-10-05 | 김태환 | Formwork method using no prop for the floor concrete of the bridge |
| KR20020001480A (en) * | 2000-06-26 | 2002-01-09 | 김준규 | Steel form for slab concrete applicable to P.C. beam or Steel Box methods |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100928166B1 (en) * | 2007-08-09 | 2009-11-25 | 주식회사 동아기술공사 | Plain formwork installed prefabricated on the lower flange of type I concrete beam, and construction method of upper slab bridge and disassembly form of formless formwork using the same |
| KR100914546B1 (en) * | 2009-04-23 | 2009-09-01 | 주식회사 예경산업개발 | Multi-axis punching drill device and construction method using the same |
| CN111271123A (en) * | 2020-01-15 | 2020-06-12 | 中铁第四勘察设计院集团有限公司 | Subway station prefabricated rail top air duct structure and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US8359797B2 (en) | Structure constructed using precast members and method of constructing the same | |
| JP2994222B2 (en) | Construction method of cast-in-place slab of precast concrete girder and its formwork | |
| JP2915897B1 (en) | Building construction method | |
| JPS627344B2 (en) | ||
| KR100469638B1 (en) | Support construction for slab of prestressed concrete beam of bridge | |
| KR20020033125A (en) | supporting structure for slab form of steel frame concrete structure | |
| JP2000234410A (en) | Driving formwork and slab construction method using the same | |
| JP3945668B2 (en) | Construction method of concrete pier | |
| KR101078292B1 (en) | Concrete slab mold assembly and method for constructing slab | |
| KR20090120289A (en) | Double layer slab formwork and supporting method | |
| KR100626326B1 (en) | Concrete structure | |
| JPH09195438A (en) | Reinforced structures for precast concrete boards and buildings | |
| KR101296320B1 (en) | Basic structure for sound-insulation wall enabling easy assembly and deviation correction | |
| KR100339440B1 (en) | Construction method using mold equipped with shape steel and plywood | |
| KR20020082966A (en) | The construction method and device for slab panel which can instal psc bridge beam | |
| KR200307607Y1 (en) | Temporang construction sfuctare for culvating slad | |
| KR20070027431A (en) | Binding tool for fixing rebar assemblies, formwork and ceiling panels by spot welding | |
| JP2891113B2 (en) | Installation method of reinforced concrete shear walls | |
| JPH0380946B2 (en) | ||
| KR101446241B1 (en) | T-typed girder and method for constructing a steel-concrete composite bridge using the same | |
| KR200296952Y1 (en) | Deck panel for reinforced concrete slab | |
| KR20040017560A (en) | Deck panel for reinforced concrete slab | |
| JP7371315B2 (en) | Precast floor slab construction method | |
| JP2759131B2 (en) | Foundation beam construction method for steel reinforced concrete columns | |
| KR100596067B1 (en) | Slab formwork for steel box bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A201 | Request for examination | ||
| PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20020306 |
|
| PA0201 | Request for examination | ||
| PG1501 | Laying open of application | ||
| E902 | Notification of reason for refusal | ||
| PE0902 | Notice of grounds for rejection |
Comment text: Notification of reason for refusal Patent event date: 20040609 Patent event code: PE09021S01D |
|
| E601 | Decision to refuse application | ||
| PE0601 | Decision on rejection of patent |
Patent event date: 20040818 Comment text: Decision to Refuse Application Patent event code: PE06012S01D Patent event date: 20040609 Comment text: Notification of reason for refusal Patent event code: PE06011S01I |