JPH0835328A - Construction of arch concrete - Google Patents
Construction of arch concreteInfo
- Publication number
- JPH0835328A JPH0835328A JP19191994A JP19191994A JPH0835328A JP H0835328 A JPH0835328 A JP H0835328A JP 19191994 A JP19191994 A JP 19191994A JP 19191994 A JP19191994 A JP 19191994A JP H0835328 A JPH0835328 A JP H0835328A
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- bar
- arch
- blocks
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims description 15
- 238000009415 formwork Methods 0.000 claims abstract description 42
- 239000002131 composite material Substances 0.000 claims abstract description 35
- 230000003014 reinforcing effect Effects 0.000 claims description 16
- 238000000034 method Methods 0.000 claims description 5
- 230000003387 muscular Effects 0.000 claims 1
- 230000002787 reinforcement Effects 0.000 abstract description 10
- 238000009434 installation Methods 0.000 description 7
- 239000000203 mixture Substances 0.000 description 7
- 239000000463 material Substances 0.000 description 5
- 125000006850 spacer group Chemical group 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000012779 reinforcing material Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、アーチ橋等のアーチコ
ンクリートの施工において行われる、型枠体及び配筋体
の設置を能率よく安全に行えるようにした施工方法に関
するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method which is used in construction of arch concrete such as an arch bridge so as to efficiently and safely install a form frame and a reinforcing bar.
【0002】[0002]
【従来の技術】アーチ橋等のアーチコンクリートの施工
では、例えば図1に示すように、橋台や橋脚等の脚部構
造物1,1にトラス構造によるアーチ状の支保工Aの両
下端を支持して架設し、支保工A上に型枠体Dを設置し
た後、型枠体D上にアーチコンクリートCの配筋体Eを
設置してコンクリートを打設するようにしている。2. Description of the Related Art In the construction of arch concrete such as an arch bridge, as shown in FIG. 1, for example, as shown in FIG. 1, both lower ends of an arch-shaped supporting work A of a truss structure are supported by leg structures 1, 1 such as abutments and piers. After installing the formwork D on the support A, the bar E of arch concrete C is installed on the formwork D and the concrete is placed.
【0003】上記の型枠体Dを設置するには、支保工A
の上に、アーチ状に弯曲した縦バタ材7,7を、支保工
Aの奥行き方向に間隔をおいて配列し、それぞれ多数の
支持具10,10を介して支保工Aに固定し、それら縦バタ
材7,7上に多数の横バタ材8,8を配設して、その上
にベニヤ板等による型枠板9を取り付けるようにしてい
る。また、配筋体Eの設置は、上記のようにして設置さ
れた型枠体D上に鉄筋等配筋用の資材を運び上げ、人手
によって組み付けることにより行われている。In order to install the above-mentioned form D, support work A
The vertical flaps 7, 7 curved in an arch shape are arranged at intervals in the depth direction of the supporting structure A, and are fixed to the supporting structure A via a large number of supporting members 10, 10 respectively. A large number of horizontal flap members 8, 8 are arranged on the vertical flap members 7, 7 and a form plate 9 made of a veneer plate or the like is mounted thereon. Further, the reinforcing bar E is installed by carrying up a reinforcing bar or other reinforcing material on the form frame D installed as described above and manually assembling it.
【0004】上記のように、従来の型枠体及び配筋体の
設置は、殆んど人手による作業で、多くの労力と時間を
要するばかりでなく、高所でしかもアーチ斜面上での極
めて足場の悪いところで行うものであるから、作業性が
悪く危険率も高い困難なものであった。As described above, the conventional installation of the formwork and the bar arrangement is almost manual work and requires a lot of labor and time. Moreover, the installation of the formwork and the bar arrangement is extremely difficult at a high place and on the arch slope. Since it is carried out on a poor footing, workability is poor and the risk rate is high.
【0005】本発明は、上記従来の型枠及び配筋の設
置、組み付けにおける難点を解決するためになされたも
ので、地上で、型枠、配筋ブロックを形成し、そのブロ
ックを支保工上に運んで組み付けるようにし、支保工上
での人手による作業を大巾に削減し、型枠、配筋の設置
の能率化と安全性の向上を図れるようにしようとするも
のである。The present invention has been made in order to solve the above-mentioned conventional problems in the installation and assembly of the formwork and the bar arrangement, and the formwork and the bar arrangement block are formed on the ground, and the blocks are used for supporting work. It aims to reduce the amount of manual work on the supporting work and to improve the efficiency and safety of the installation of formwork and bar arrangement.
【0006】[0006]
【課題を解決するための手段】上記の目的を達成するた
めの本発明の構成について、実施例に対応する図面を参
照して説明すると、請求項1の施工方法は、支保工A上
に、アーチコンクリートCの型枠体D及び配筋体Eを設
置するにあたり、上記型枠体D及び配筋体Eを、それぞ
れ複数個に分割した大きさのブロックを連設して形成す
るものとし、地上において、上記型枠ブロックd1 〜d
4 とその上に配筋ブロックe1 〜e4 を組み付けた、型
枠、配筋複合ブロックB1 〜B4 を形成し、これを支保
工A上に吊り上げて固定し、型枠体D及び配筋体Eの全
体を形成することを特徴とするものである。The structure of the present invention for achieving the above object will be described with reference to the drawings corresponding to the embodiments. In installing the formwork D and the bar arrangement E of the arch concrete C, the formwork D and the bar arrangement E are to be formed by successively connecting blocks each having a size divided into a plurality of pieces. On the ground, the formwork blocks d 1 to d
4 and the bar arrangement blocks e 1 to e 4 assembled thereon to form a form and bar arrangement composite blocks B 1 to B 4 , which are hung and fixed on the supporting work A, and the form body D and It is characterized in that the entire muscle arrangement body E is formed.
【0007】また、請求項2の施工方法は、支保工A上
に、アーチコンクリートCの型枠体D及び配筋体Eを設
置するにあたり、上記型枠体D及び配筋体Eの一部を、
型枠の上に配筋を組み付けた、型枠、配筋複合ブロック
B1 ,B4 として、地上において形成し、これを支保工
A上に吊り上げて固定した後、残余の部分B0 の型枠及
び配筋組みを行い、型枠体D及び配筋体Eの全体を形成
することを特徴とするものである。Further, in the construction method of claim 2, in installing the form D and the bar E of arch concrete C on the support A, a part of the form D and the bar E is installed. To
Formed on the ground as formwork / reinforcement composite blocks B 1 and B 4 in which reinforcements are assembled on the formwork, and after suspending and fixing them on the support A, the mold of the remaining part B 0 It is characterized in that a frame and a reinforcing bar are assembled to form the entire formwork body D and reinforcing bar E.
【0008】[0008]
【実施例】以下、本発明の実施例について、図面を参照
して説明する。図1〜図3はトラス構造によるアーチ状
支保工を使用してアーチコンクリートを施工する場合を
示したものであり、図5は図1の一部拡大図である。支
保工Aは、対向した橋台等の脚部構造物1,1に取付台
2,2を介して両下端をピン結合して架設される。そし
て、支保工Aの上面には型枠体Dを設置し、さらにその
上に配筋組みをして、コンクリートを打設し、アーチコ
ンクリートCが形成される。Embodiments of the present invention will be described below with reference to the drawings. 1 to 3 show a case where arch concrete is constructed using an arch-like support structure having a truss structure, and FIG. 5 is a partially enlarged view of FIG. The support work A is erected by pin-connecting both lower ends to the leg structure 1, 1 such as an opposing abutment via mounting bases 2, 2. Then, the form frame D is installed on the upper surface of the supporting structure A, and the reinforcing frame is laid on the form frame D, and concrete is poured to form arch concrete C.
【0009】支保工Aは、アーチ状のトラス架構体aの
複数個を施工するアーチコンクリートCの巾方向(奥行
き方向)に間隔をおいて配置し、それぞれ脚部構造物
1,1にピン結合するとともに、相互に連結材及び斜材
(いずれも図示を略す)により結合して構成されてい
る。図示の支保工Aは、上弦材4と一対の側杆5,5に
より三角状に形成した支保要素3を、互に上弦材4,4
どうしで連結し、側杆5,5の結合端どうしを下弦材
6,6で結合した構造となっているが、この支保工Aは
従来公知の手段による一般的なトラス構造であってもよ
い。また、支保工Aは、上記のようなトラス構造物に限
らず、例えば、地上に多数の支柱を立設して上端をアー
チ状に形成したような構造物であってもよい。The supporting works A are arranged at intervals in the width direction (depth direction) of the arch concrete C on which a plurality of arch-shaped truss frame structures a are to be constructed, and are connected to the leg structures 1 and 1 by pins. In addition, they are connected to each other by a connecting member and a diagonal member (both not shown). The supporting work A shown in the figure is that the supporting elements 3 formed in a triangular shape by the upper chord member 4 and the pair of side rods 5 and 5 are arranged on top of each other.
Although the structure is such that they are connected to each other and the connecting ends of the side rods 5 and 5 are connected to each other by the lower chord members 6 and 6, this support A may be a general truss structure by a conventionally known means. . Further, the support work A is not limited to the truss structure as described above, and may be a structure in which a large number of columns are erected on the ground and the upper end is formed in an arch shape.
【0010】上記のように架設された支保工Aの上面に
は、型枠体Dが設置される。この型枠体Dは一般に、支
保工Aを構成する各トラス架構体a,a上に、そのスパ
ン方向に沿って縦バタ材7,7を、多数の高さ調節自在
とした支持具10,10を介して載置して、取付ボルト11,
11により固定し、それら縦バタ材7,7上に多数の横バ
タ材8,8を、縦バタ材7,7と格子状をなすように配
列、固定し、横バタ材8,8上に型枠板9を取り付けて
設置される。そして、この型枠体D上には配筋体Eが設
置される。配筋体Eは、一般に、アーチコンクリートC
のスパン方向に延長する上端筋12と下端筋13とを配列
し、互に連結筋14,14等で結合して形成され、下端筋13
と型枠板9との間にスぺーサ15,15を介装して型枠体D
に止着される。A mold frame D is installed on the upper surface of the supporting work A constructed as described above. This form D is generally a support tool 10, in which a large number of vertical flaps 7, 7 are adjustable along the span direction on each truss frame structure a, a constituting the support A, Placed via 10, mounting bolts 11,
11 by fixing, and a large number of horizontal flaps 8, 8 are arranged and fixed on the vertical flaps 7, 7 so as to form a grid pattern with the vertical flaps 7, 7, and are then fixed on the horizontal flaps 8, 8. The form board 9 is attached and installed. Then, the bar arrangement E is installed on the form D. Reinforcing bar E is generally arch concrete C
Is formed by arranging an upper end bar 12 and a lower end bar 13 extending in the span direction of and connecting each other with connecting bars 14, 14 and the like.
And the mold plate 9 with spacers 15, 15 interposed between them to form frame D.
Fastened to.
【0011】本発明では、図1に示すように、上記型枠
体D及び配筋体Eを、例えば支保工Aのスパン方向にそ
れぞれ複数に分割した大きさの型枠ブロックd1 〜d4
及び配筋ブロックe1 〜e4 の組み合せによる、型枠・
配筋複合ブロック(以下複合ブロックという)B1 〜B
4 を形成し、それらを支保工A上に連設して構成する。According to the present invention, as shown in FIG. 1, the formwork blocks D and the reinforcing bar E are divided into a plurality of formwork blocks d 1 to d 4 in the span direction of the support A, for example.
And the formwork by the combination of the bar arrangement blocks e 1 to e 4.
Reinforcement composite block (hereinafter referred to as composite block) B 1 ~ B
4 are formed, and they are continuously arranged on the support work A.
【0012】上記の各複合ブロックB1 〜B4 は、地上
において組成する。図2はその一例を示したもので、図
4にも示すように地上に、上面を型枠ブロックのアーチ
形に沿う弯曲面とした組付台16,16を用意し、その上に
おいて、まず、支保工Aの両端部に配置する型枠ブロッ
クd1 、d4 を組成する。この場合、縦バタ材7,7
は、各トラス架構体a,aに載る間隔で配列する。そし
て、従来同様に、縦バタ材7,7上に横バタ材8,8を
並べて固定し、型枠板9を取り付ける。次に、この型枠
ブロックd1 ,d4 上に配筋ブロックe1 ,e4 を設置
する。すなわち、さきに説明したように、上端筋12と下
端筋13とを連結筋14,14で結合して形成した配筋ブロッ
クe1 、e4 を型枠板9上にスペーサ15,15を介して止
着する。なお、配筋ブロックe1 、e4 は、型枠ブロッ
クd1 ,d4 の上で組み付けてもよく、或は、別の場所
で配筋ブロックe1 、e4 を組み付け、これを型枠ブロ
ックd1 ,d4 上に運んで止着してもよい。The above composite blocks B 1 to B 4 are composed on the ground. FIG. 2 shows an example of this. As shown in FIG. 4, assembling bases 16 and 16 having a curved surface whose upper surface follows the arch shape of the formwork block are prepared on the ground. Forming block blocks d 1 and d 4 arranged at both ends of the supporting structure A. In this case, the vertical flap material 7,7
Are arranged at intervals so as to be mounted on each truss frame structure a, a. Then, as in the conventional case, the horizontal flap members 8, 8 are arranged and fixed on the vertical flap members 7, 7 and the form frame plate 9 is attached. Next, the rebar blocks e 1 and e 4 are installed on the formwork blocks d 1 and d 4 . That is, as described above, the rebar blocks e 1 and e 4 formed by connecting the upper end bar 12 and the lower end bar 13 with the connecting bar 14, 14 are formed on the formwork plate 9 via the spacers 15, 15. And fasten. Incidentally, Haisuji block e 1, e 4 may be assembled on a mold block d 1, d 4, or, assembled reinforcement block e 1, e 4 elsewhere, this formwork It may be carried on the blocks d 1 and d 4 and fastened.
【0013】次に、図3に示すように、組成を終えた複
合ブロックB1 ,B4 をそれぞれクレーン(図示を略
す)で吊り上げ、支保工A上に載置する。その際、縦バ
タ材7,7と支保工Aの上弦材4,4との間には高さ調
節自在とした支持具10,10を介装して、複合ブロックB
1 ,B4 の高さ位置及び弯曲度の調整を行い、縦バタ材
7と上弦材4とを取付ボルト11, 11により結合し、複合
ブロックB1 ,B4 を固定するとともに、各上端筋12と
下端筋13の一端部を、脚部構造物1に突設された鉄筋1
7,17に結合する。また、複合ブロックB1 ,B4 の吊
り上げ、設置を行う間に、できれば地上において次の複
合ブロックB2 ,B3 の組成を行う。Next, as shown in FIG. 3, the composite blocks B 1 and B 4 whose composition has been finished are lifted by a crane (not shown) and placed on the support A. At that time, between the vertical flap members 7, 7 and the upper chord members 4, 4 of the supporting work A, the height-adjustable supporting members 10, 10 are interposed to form the composite block B.
The height position of 1 and B 4 and the degree of curvature are adjusted, the vertical flap material 7 and the upper chord material 4 are connected by the mounting bolts 11 and 11, and the composite blocks B 1 and B 4 are fixed and the upper end bars are Reinforcing bar 1 with one end of 12 and bottom bar 13 protruding from leg structure 1
Combine with 7, 17. While the composite blocks B 1 and B 4 are being lifted and installed, the composition of the next composite blocks B 2 and B 3 is performed on the ground, if possible.
【0014】続いて、組成した複合ブロックB2 ,B3
をクレーンで吊り上げ、支保工Aに支持具10,10を介し
て載置し、取付ボルトにより固定するとともに、各配筋
ブロックe1 〜e4 の上端筋12,12と下端筋13,13どう
しを結合する。それによって、図1に示すように、型枠
体D及び配筋体E全体の載置が完了する。その後は、型
枠体D上にコンクリートを打設し、アーチコンクリート
Cが構築される。なお、コンクリートの打設は、各複合
ブロックB1 〜B4 の設置の都度、その部分のコンクリ
ート打ちを行うようにしてもよい。Subsequently, the composite blocks B 2 and B 3 having the composition are formed.
Is lifted by a crane, placed on the support A via the support tools 10, 10 and fixed with mounting bolts. The upper bar 12, 12 and the lower bar 13, 13 of each bar arrangement block e 1 to e 4 are connected to each other. To join. As a result, as shown in FIG. 1, the placement of the entire mold frame D and the reinforcing bar E is completed. After that, concrete is placed on the form D to construct arch concrete C. The concrete may be poured into the concrete blocks B 1 to B 4 each time the composite blocks B 1 to B 4 are installed.
【0015】上記の実施例では、型枠体Bを支保工Aの
スパン方向に4分割して配筋ブロックb1 〜b4 を形成
するようにしているが、この分割数は、クレーンの大き
さや作業性を勘案して適宜増減できるものであり、複合
ブロックはさらに支保工Aの巾方向(奥行き方向)にも
分割してブロック化することもできる。また、複合ブロ
ックB1 〜B4 の組成は、地上の条件が良好であれば、
組付台16を使用しないでも行うことができる。In the above-mentioned embodiment, the form B is divided into four in the span direction of the support A to form the bar arrangement blocks b 1 to b 4 , but the number of divisions is the size of the crane. The composite block can be appropriately increased / decreased in consideration of workability, and the composite block can be further divided into blocks in the width direction (depth direction) of the supporting structure A to form blocks. Further, the composition of the composite blocks B 1 to B 4 is
It can be performed without using the mounting base 16.
【0016】次に、本発明では、支保工A上に設置する
型枠体D及び配筋体Eのすべてを、上記のように、地上
で組成した複合ブロックB1 〜B4 の吊り上げ、連設に
より行うのではなく、一部の範囲、例えば、特にアーチ
斜面の急な支保工の両端近くの部分だけに複合ブロック
を設置し、その他の部分を従来同様の支保工A上での手
組み作業によって型枠、配筋の設置を行うようにするこ
とができる。Next, in the present invention, all of the formwork D and the bar arrangement E to be installed on the support A are lifted and connected to the composite blocks B 1 to B 4 composed on the ground as described above. Rather than constructing the structure, a composite block is installed only in a part of the area, for example, only near the two ends of the sudden arch support on the arch slope, and the other parts are manually assembled on the arch support A similar to the conventional method. It is possible to install the formwork and the bar arrangement by the work.
【0017】この場合の実施例について説明すると、図
6に示すように、型枠体D及び配筋体Eを、支保工A上
のアーチ斜面の急な両端近くの部分と他の部分とに区分
し、両端近くの部分では、上記したように、複合ブロッ
クB1 ,B4 を地上で組成し、支保工A上に吊り上げて
設置する(図3〜図5参照)。そして、その後は、他の
部分即ち両複合ブロックB1 ,B2 間の部分B0 (手組
み部分)を、従来同様に、型枠、配筋の関係部材を支保
工A上運び上げて、人手作業により型枠体を組成、設置
した後、その上に配筋組みを行い、型枠体D及び配筋体
E全体の設置が完了する。その後は、型枠体D上にコン
クリートを打設してアーチコンクリートCが構築され
る。この場合も、コンクリートの打設は、複合ブロック
B1 ,B4 の設置後その部分のコンクリート打ちをして
から、手組み部分B0 の型枠、配筋の設置を行うように
してもよい。Explaining the embodiment in this case, as shown in FIG. 6, the form D and the bar arrangement E are divided into a portion near the steep ends of the arch slope on the support A and another portion. division and, at both ends close to the portion, as described above, and the composition of the composite block B 1, B 4 on the ground, placed in lifting on shoring a (see FIGS. 3 to 5). Then, after that, the other part, that is, the part B 0 (the hand-assembled part) between the composite blocks B 1 and B 2 is carried up on the supporting work A by the related members such as the formwork and the bar arrangement as in the conventional case. After manually constructing and installing the formwork body, the reinforcement is laid on the formwork body, and the installation of the entire formwork body D and the reinforcement body E is completed. After that, arch concrete C is constructed by placing concrete on the form D. Also in this case, the concrete may be placed after placing the composite blocks B 1 and B 4 and then placing the concrete in that portion, and then installing the formwork and the bar arrangement of the hand-assembled portion B 0. .
【0018】この実施例では、複合ブロックを支保工A
の両端部に設置するようにしているが、複合ブロックは
両端部だけに限らず、他の所要部分に、互に隣接或は間
隔をおいて設置し、残余の部分を型枠、配筋の手組みに
より行うようにすることもできる。In this embodiment, the composite block is supported by the support A
The composite blocks are installed not only at both ends, but also at other required parts adjacent to each other or at intervals, and the remaining part of the formwork and bar arrangement. It can also be done by hand.
【0019】[0019]
【発明の効果】以上説明したように、請求項1の工法
は、アーチコンクリートの施工において設置する型枠体
及び配筋体の全部または一部を型枠と配筋とを組み合せ
た複合ブロックとして地上で組成し、これを支保工上に
吊り上げて設置することにより型枠体及び配筋体の全体
を設置するようにしたので、アーチ斜面上の滑り易く足
場の悪い高所での繁雑な作業が極めて少なくなり、作業
の簡易化と能率化が図れるとともに、安全性も向上され
る。As described above, according to the construction method of claim 1, all or a part of the form body and the bar arrangement to be installed in the construction of arch concrete is a composite block in which the form frame and the bar arrangement are combined. Since it was constructed on the ground and the whole of the formwork and bar arrangement was installed by hoisting it on the support work and installing it, complicated work at a high place where it is slippery on the arch slope and the footing is bad Is extremely small, which simplifies and improves work efficiency and improves safety.
【0020】また、複合ブロックは地上で組成するの
で、作業は容易で能率よく行えるとともに、複合ブロッ
クの吊り上げや設置中にも、次の複合ブロックの組成作
業を進めることができ、全体として型枠体や配筋体の施
工が短期間に行えることになるばかりでなく、アーチ支
保工の製作や架設する間でも複合ブロックを組成して準
備することも可能であり、そうすれば、全体の工期も著
しく短縮できることになる。Further, since the composite block is formed on the ground, the work can be performed easily and efficiently, and the composition work of the next composite block can be carried out even while the composite block is being lifted or installed, and the formwork as a whole can be formed. Not only will the construction of the body and the bar arrangement be possible in a short period of time, but it is also possible to formulate and prepare a composite block during the construction and construction of the arch support work, and then the whole construction period Will be significantly shortened.
【0021】また、請求項2の工法では、アーチ形が比
較的扁平である場合のように、支保工の両端部を除き、
型枠や配筋の手組みによる設置作業が容易、かつ安全に
行うことができ、クレーンの吊り上げによるよりも作業
が能率的にできるような場合に適している。したがっ
て、施工現場の状況に応じて、請求項1の方法か請求項
2の方法かのいずれかが選択され、施工がより効果的に
実施できる。Further, in the construction method of claim 2, as in the case where the arch shape is relatively flat, except for both ends of the support work,
It is suitable for cases where the installation work by hand assembling the formwork and the bar arrangement can be performed easily and safely and the work can be done more efficiently than by lifting the crane. Therefore, either the method of claim 1 or the method of claim 2 is selected according to the situation of the construction site, and the construction can be carried out more effectively.
【図1】本発明工法により型枠体及び配筋体を設置した
状態を示す正面図である。FIG. 1 is a front view showing a state in which a mold body and a reinforcing bar are installed by the method of the present invention.
【図2】複合ブロックの地上での組成状態を示した正面
図である。FIG. 2 is a front view showing a composition state of the composite block on the ground.
【図3】同拡大正面図である。FIG. 3 is an enlarged front view of the same.
【図4】複合ブロックの吊り上げ、設置状態を示した正
面図である。FIG. 4 is a front view showing how the composite block is lifted and installed.
【図5】図1の一部拡大正面図である。5 is a partially enlarged front view of FIG.
【図6】本発明工法の他の実施例による型枠体及び配筋
体の設置状態を示す正面図である。FIG. 6 is a front view showing an installation state of a mold body and a bar arrangement according to another embodiment of the method of the present invention.
A 支保工 B1 〜B4 複合ブロック B0 手組み部分 C アーチコンクリート D 型枠体 E 配筋体 a トラス架構体 d1 〜d4 型枠ブロック e1 〜e1 配筋ブロック 1 脚部構造物 3 支保要素 4 上弦材 5 側杆 6 下弦材 7 縦バタ材 8 横バタ材 9 型枠板 10 支持具 11 取付ボルト 12 上端筋 13 下端筋 14 連結筋 15 スペーサ 16 取付台 17 鉄筋A shoring B 1 .about.B 4 composite block B 0 hand-part C arcuate concrete D-type frame E Haisujitai a truss rack structure d 1 to d 4 Formwork block e 1 to e 1 Haisuji block first leg structure Object 3 Support element 4 Upper chord member 5 Side rod 6 Lower chord member 7 Vertical flap material 8 Horizontal flap material 9 Formwork plate 10 Supporting tool 11 Mounting bolt 12 Upper end bar 13 Lower end bar 14 Connecting bar 15 Spacer 16 Mounting base 17 Reinforcing bar
Claims (2)
体及び配筋体を設置するにあたり、上記型枠体及び配筋
体を、それぞれ複数個に分割した大きさのブロックを連
設して形成するものとし、地上において、上記型枠ブロ
ックとその上に配筋ブロックを組み付けた、型枠、配筋
複合ブロックを形成し、これを支保工上に吊り上げて固
定し、型枠体及び配筋体の全体を形成することを特徴と
する、アーチコンクリートの施工方法。1. When installing a formwork and a reinforcing bar of arch concrete on a supporting work, a block having a size obtained by dividing each of the formwork and the reinforcing bar into a plurality of blocks is continuously provided. On the ground, form the above-mentioned form block and the bar arrangement block on it, form a form and reinforcing bar composite block, and hang it on the supporting structure and fix it, and A method for constructing arch concrete, characterized by forming the entire muscular body.
体及び配筋体を設置するにあたり、上記型枠体及び配筋
体の一部を、型枠の上に配筋を組み付けた、型枠、配筋
複合ブロックとして、地上において形成し、これを支保
工上に吊り上げて固定した後、残余の部分の型枠及び配
筋組みを行い、型枠体及び配筋体の全体を形成すること
を特徴とする、アーチコンクリートの施工方法。2. A mold in which a part of the mold body and the bar arrangement is assembled on the formwork when the form frame body and the bar arrangement body of arch concrete are installed on the support work. Formed on the ground as a frame and reinforcing bar composite block, hoisting and fixing it on the support work, form the remaining part of the formwork and bar arrangement, and form the entire formwork frame and bar arrangement Arch concrete construction method characterized by the following.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19191994A JPH0835328A (en) | 1994-07-22 | 1994-07-22 | Construction of arch concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19191994A JPH0835328A (en) | 1994-07-22 | 1994-07-22 | Construction of arch concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0835328A true JPH0835328A (en) | 1996-02-06 |
Family
ID=16282634
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19191994A Pending JPH0835328A (en) | 1994-07-22 | 1994-07-22 | Construction of arch concrete |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0835328A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105887682A (en) * | 2015-01-26 | 2016-08-24 | 任丘市永基建筑安装工程有限公司 | Steel bow bridge casting and concrete construction technology |
CN110219232A (en) * | 2019-07-09 | 2019-09-10 | 中国十七冶集团有限公司 | A kind of Deck Arch Bridges concreting method |
-
1994
- 1994-07-22 JP JP19191994A patent/JPH0835328A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105887682A (en) * | 2015-01-26 | 2016-08-24 | 任丘市永基建筑安装工程有限公司 | Steel bow bridge casting and concrete construction technology |
CN110219232A (en) * | 2019-07-09 | 2019-09-10 | 中国十七冶集团有限公司 | A kind of Deck Arch Bridges concreting method |
CN110219232B (en) * | 2019-07-09 | 2020-12-04 | 中国十七冶集团有限公司 | Concrete pouring method for deck type arch bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3918222A (en) | Prefabricated modular flooring and roofing system | |
US3981038A (en) | Bridge and abutment therefor | |
JPH05287901A (en) | Construction of stairs | |
JPH0835328A (en) | Construction of arch concrete | |
JPH0849417A (en) | Method for installing formwork during construction of arch concrete | |
CN114395988A (en) | Design template construction platform | |
JPH04161542A (en) | Connecting work of column and beam and its structure | |
JPH0849214A (en) | Construction method for installing arch concrete bar arrangement body | |
JP2700162B2 (en) | Mobile formwork construction method for arch concrete | |
JPH06228915A (en) | Strut of elevated bridge, etc., and construction method thereof | |
JPH0913505A (en) | Adjustment of height of front end of cantilever roof | |
CN216765629U (en) | Design template construction platform | |
KR101022249B1 (en) | Manufacturing method of wall type rahmen bridge | |
JP2812177B2 (en) | Bridge pier construction method by slip form method | |
JP2719635B2 (en) | Stair construction method using precast concrete block | |
JP2568987B2 (en) | Support member for reinforcing steel assembly and bridge construction method using the same | |
JP3792276B2 (en) | Building foundations and construction methods | |
JPH0455090Y2 (en) | ||
JPH0492021A (en) | Foundation structure of building and construction method thereof | |
JPH0674590B2 (en) | Block for building legal framework and method for building legal framework | |
JPH11166323A (en) | Construction method for rc molded frame installed in building | |
CN115162697A (en) | I-shaped steel cantilever platform for special-shaped column construction and construction method | |
JPS63251527A (en) | Construction of independent foundation and foundation block used therefor | |
JP2700637B2 (en) | Slope stable structure | |
JP3041754U (en) | Half precast slab |