JPH08305750A - Work supporting device - Google Patents

Work supporting device

Info

Publication number
JPH08305750A
JPH08305750A JP11034895A JP11034895A JPH08305750A JP H08305750 A JPH08305750 A JP H08305750A JP 11034895 A JP11034895 A JP 11034895A JP 11034895 A JP11034895 A JP 11034895A JP H08305750 A JPH08305750 A JP H08305750A
Authority
JP
Japan
Prior art keywords
work
graph
information
procedure
item
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP11034895A
Other languages
Japanese (ja)
Inventor
Tatsuo Kondo
竜生 近藤
Hiroyuki Yoshida
裕之 吉田
Rieko Yamamoto
里枝子 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP11034895A priority Critical patent/JPH08305750A/en
Publication of JPH08305750A publication Critical patent/JPH08305750A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE: To reduce the labor and time for manual input while holding consistency and to reduce also revision omission or an error by storing only working information (work input information and work output information) and its dependence relation in a computer and automatically generating work item and working procedure. CONSTITUTION: This work supporting device is provided with a graph expressing work input and output information 1 and dependence relation 2a between these information 1 by arcs (working procedure), a means for adding a work items 3 detected and extracted from the graph to the graph, a means for collecting the work items 3 of arcs having the same node as their terminals in the added graph, a means for adding an arc (working procedure) 4 having the nodes of the work item 3 of the collected graph as start and end point, and a means for extracting only the work item 3 and the arc (working procedure) 4 from the added graph and generating a new graph.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、作業入力情報および作
業出力情報と依存関係をアークで表したグラフを用い、
作業項目とアーク(作業手順)を表すグラフを自動生成
する作業支援装置に関するものである。
BACKGROUND OF THE INVENTION The present invention uses a graph in which work input information, work output information, and dependency relationships are represented by arcs.
The present invention relates to a work support device that automatically generates a graph showing a work item and an arc (work procedure).

【0002】[0002]

【従来の技術】従来の作業支援装置は、例えば図16の
(a)に示す作業と作業手順の関係、(b)に示す作業
入力情報と作業出力情報の関係、および(c)に示す作
業と作業入力情報および作業出力情報の関係の3者をそ
れぞれ独立にコンピュータ上に持ち、管理していた。以
下図16の構成を簡単に説明する。
2. Description of the Related Art A conventional work support apparatus is, for example, a relation between a work and a work procedure shown in FIG. 16A, a relation between work input information and work output information shown in FIG. 16B, and a work shown in FIG. And the work input information and the work output information are independently managed on the computer. The configuration of FIG. 16 will be briefly described below.

【0003】図16は、従来技術の説明図を示す。図1
6の(a)は、作業と作業手順を示す。ここでは、“設
計”、“プログラム作成”が作業(作業名)を表し、ア
ークが作業手順(設計の次にプログラム作成を行うとい
う作業手順)を表す。
FIG. 16 is an explanatory view of the prior art. FIG.
6A shows the work and the work procedure. Here, “design” and “program creation” represent work (work name), and arc represents work procedure (work procedure of creating a program after design).

【0004】図16の(b)は、作業入力情報と作業出
力情報の関係を示す。ここでは、アークの向きによっ
て、“仕様書”が作業入力情報を表し、“プログラム”
が作業出力情報を表す。
FIG. 16B shows the relationship between work input information and work output information. Here, "specifications" represent work input information depending on the direction of the arc, and "program"
Represents work output information.

【0005】図16の(c)は、作業と作業入力情報お
よび作業出力情報の依存関係を示す。ここでは、図示の
ように作業名“設計”の作業出力情報が“仕様書”であ
り、作業名“プログラム作成”の作業入力情報が“仕様
書”であり、作業出力情報が“プログラム”である旨を
それぞれ表す。
FIG. 16C shows the dependency relationship between the work and the work input information and the work output information. Here, as shown in the figure, the work output information of the work name "design" is "specifications", the work input information of the work name "program creation" is "specifications", and the work output information is "programs". Indicates that there is.

【0006】[0006]

【発明が解決しようとする課題】上述したように、従来
は、図16の(a)、(b)、(c)に示すようにして
それぞれを独立にコンピュータ上で管理していたため、
管理者が作業入力情報や作業出力情報に変更した場合、
図16の(b)の該当する作業入力情報や作業出力情報
の変更のみならず、図16の(a)の作業と作業手順、
特に作業手順も変更となる場合が多くてこれも合わせて
手作業によって変更せざるを得ないという問題があっ
た。また、図16の(a)の作業手順の細分化を手入力
した場合、図16の(b)の作業入力情報や作業出力情
報も変更となる場合が多くてこれも合わせて手作業によ
って変更せざるを得ないという問題があった。
As described above, conventionally, as shown in FIGS. 16 (a), 16 (b) and 16 (c), each is managed independently on the computer.
When the administrator changes to work input information and work output information,
Not only the corresponding work input information and work output information in FIG. 16B are changed, but also the work and work procedure in FIG.
In particular, the work procedure is often changed, and there is a problem that the work procedure must be changed accordingly. Further, when the subdivision of the work procedure of FIG. 16 (a) is manually input, the work input information and work output information of FIG. 16 (b) are often changed, which is also changed manually. There was a problem that I had to do it.

【0007】このように、従来の図16の(a)、
(b)、(c)のように独立にコンピュータ上に管理し
ていた場合には、一方を手入力によって変更すると、他
方も合わせて手入力によって変更する必要が生じてしま
い、変更漏れや不適切な変更が行われ易いという問題も
あった。
In this way, as shown in FIG.
In the case of independent management on a computer as in (b) and (c), if one is changed by manual input, the other also needs to be changed by manual input. There was also a problem that it was easy to make appropriate changes.

【0008】本発明は、これの問題を解決するため、作
業情報(作業入力情報および作業出力情報)とその依存
関係のみをコンピュータ上で保持し、作業項目と作業手
順を自動生成し、一貫性を保持しつつ手入力の手間を削
減すると共に変更もれや誤りを低減することを目的とし
ている。
In order to solve this problem, the present invention holds only work information (work input information and work output information) and its dependencies on a computer, automatically creates work items and work procedures, and provides consistency. The purpose of this is to reduce the trouble of manual input while maintaining the value, and to reduce the omission of changes and errors.

【0009】[0009]

【課題を解決するための手段】図1を参照して課題を解
決するための手段を説明する。図1において、作業情報
1は、作業入力情報および作業出力情報とこれらの間の
依存関係2をアークで表したグラフ中の、作業入力情報
および作業出力情報である(図2参照)。
[Means for Solving the Problems] Means for solving the problems will be described with reference to FIG. In FIG. 1, work information 1 is work input information and work output information, and work input information and work output information in a graph in which a dependency relationship 2 between them is represented by an arc (see FIG. 2).

【0010】作業項目3は、作業項目の作業手順4をア
ークで表したグラフ中の、当該作業項目である(図3参
照)。
Work item 3 is the work item in the graph representing the work procedure 4 of the work item by an arc (see FIG. 3).

【0011】[0011]

【作用】本発明は、作業情報1である作業入力情報およ
び作業出力情報とこれらの間の依存関係2をアークで表
したグラフを入力とし(S1)、このグラフから検出し
抽出した作業項目を付加し(S2)、この付加後のグラ
フ中で同一ノードを終端とするアークの作業項目をまと
め(S3)、このまとめたグラフの作業項目3のノード
を始点および終点とするアーク(作業手順4)を付加し
(S4)、この付加後のグラフから作業項目3とアーク
(作業手順4)のみを取り出してグラフを生成する(S
6)ようにしている。
According to the present invention, a graph in which work input information and work output information which are work information 1 and dependency relation 2 between them is represented by an arc is input (S1), and the work items detected and extracted from this graph are extracted. After adding (S2), the work items of arcs that terminate the same node in the graph after this addition are summarized (S3), and the arcs that have the nodes of work item 3 of this summarized graph as the start point and end point (work procedure 4 ) Is added (S4), and only the work item 3 and the arc (work procedure 4) are taken out from the graph after this addition to generate a graph (S).
6) I am doing so.

【0012】この際、アーク(作業手順4)を付加した
後のグラフから冗長なアーク(作業手順4)を除去(S
5)した後、このグラフから作業項目3とアーク(作業
手順4)のみを取り出してグラフを生成する(S6)よ
うにしている。
At this time, the redundant arc (work procedure 4) is removed from the graph after the arc (work procedure 4) is added (S).
After 5), only the work item 3 and the arc (work procedure 4) are extracted from this graph to generate a graph (S6).

【0013】また、グラフから作業項目3とアーク(作
業手順4)のみを取り出して生成したグラフ(S6)を
提示し、作業情報1である作業入力情報、作業出力情報
あるいはこれらの間の依存関係2の修正、追加あるいは
削除に対応して再処理し再提示するようにしている。
Also, a graph (S6) generated by extracting only the work item 3 and the arc (work procedure 4) from the graph is presented, and the work input information which is the work information 1, the work output information, or the dependency relation between them. It is reprocessed and presented again in response to the correction, addition or deletion of item 2.

【0014】従って、作業情報(作業入力情報および作
業出力情報)1とその依存関係2のみをコンピュータ上
で保持し、作業項目3と作業手順4を自動生成すること
により、一貫性を保持しつつ手入力の手間を削減すると
共に変更もれや誤りを低減することが可能となる。
Therefore, by maintaining only the work information (work input information and work output information) 1 and its dependency 2 on the computer and automatically generating the work item 3 and the work procedure 4, it is possible to maintain consistency. It is possible to reduce the time and effort for manual input and reduce changes and errors.

【0015】[0015]

【実施例】次に、図1から図15を用いて本発明の実施
例の構成および動作を順次詳細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, the construction and operation of an embodiment of the present invention will be sequentially described in detail with reference to FIGS.

【0016】図1は、本発明の1実施例構成フローチャ
ートを示す。図1において、S1は、作業情報1と依存
関係2の取り込みを行う。これは、後述する図2に示す
ように、グラフで表したときのノードの情報である作業
情報1およびアーク(矢印)で表した依存関係2を取り
込む。
FIG. 1 is a flowchart showing the configuration of an embodiment of the present invention. In FIG. 1, S1 fetches the work information 1 and the dependency relationship 2. As shown in FIG. 2, which will be described later, this takes in work information 1 that is information of the node when represented by a graph and dependency 2 represented by an arc (arrow).

【0017】S2は、アークから作業項目3の検出・抽
出する。これは、S1で取り込んだ図2のグラフのアー
ク(依存関係2)から作業項目1を検出してこの段階で
は、後述する図4のグラフのノード(楕円で表す)とし
て作業項目3を検出する(この作業項目3の実際の名前
(作業名)はS7の段階で辞書を参照して決定あるいは
管理者から入力された名前(作業名)に決定する)。
In S2, work item 3 is detected and extracted from the arc. This is to detect the work item 1 from the arc (dependency relationship 2) of the graph of FIG. 2 fetched in S1, and to detect the work item 3 as a node (represented by an ellipse) of the graph of FIG. 4 described later at this stage. (The actual name (work name) of this work item 3 is determined by referring to the dictionary in step S7 or determined by the name (work name) input by the administrator).

【0018】以上のS1で取り込んだ図2のグラフ(作
業情報1とその依存関係2を表すグラグ)中のアーク
(依存関係2)から作業項目3を検出し、図4のグラフ
を生成する。
The work item 3 is detected from the arc (dependency relationship 2) in the graph (work information 1 and the graph representing the dependence relationship 2) of FIG. 2 captured in S1 described above, and the graph of FIG. 4 is generated.

【0019】S3は、同一のノードを終端とするアーク
の作業項目3をまとめる。これは、S2で生成した図4
のグラフ中で、同一のノードを終端とするアークの作業
項目3、例えばノード“出荷内容”を終端とするアーク
の作業項目3 ・producer(出荷内容)=consumer(プログラム) ・producer(出荷内容)=consumer(仕様書) ・producer(出荷内容)=consumer(テストパッケー
ジ) の3つをまとめ、図6に示すようにする。ここで、cons
umerの( )は後述する図4で説明するように作業入力
情報であり、producerの( )は後述する図4で説明す
るように作業出力情報である。
In S3, work items 3 of arcs terminating at the same node are put together. This is shown in FIG. 4 generated in S2.
In the graph, the work item 3 of an arc terminating at the same node, for example, the work item 3 of an arc terminating at the node “shipping content” • producer (shipping content) = consumer (program) = Consumer (specification) -producer (shipping content) = consumer (test package) are summarized as shown in Fig. 6. Where cons
The umer () is work input information as described later with reference to FIG. 4, and the producer () is work output information as described later with reference to FIG.

【0020】S4は、ノードを始点・終点とするアーク
の作業項目3間にアーク(作業手順4)を付加する。こ
れは、後述する図6の太線で示したアーク(作業手順
4)に示すように、ノードを始点/終点とするアークの
作業項目3間にアーク(作業手順4)を付加する。
In step S4, an arc (work procedure 4) is added between the work items 3 of the arcs whose start and end points are nodes. This adds an arc (work procedure 4) between work items 3 of an arc having a node as a start point / end point, as shown by an arc (work procedure 4) indicated by a thick line in FIG. 6 described later.

【0021】S5は、冗長なアーク(作業手順)の除去
を行う。これは、後述する図6に示すように、点線の冗
長なアーク(作業手順)を除去する。S6は、作業項目
とアーク(作業手順4)のみを取り出す。これは、後述
する図6のグラフから作業項目3とアーク(作業手順
4)のみを取り出し、図7に示す新たなグラフを作成す
る。
In step S5, redundant arcs (work procedure) are removed. This removes the redundant arc (work procedure) of the dotted line, as shown in FIG. 6 described later. In S6, only the work item and arc (work procedure 4) are taken out. This takes out only the work item 3 and the arc (work procedure 4) from the graph of FIG. 6 described later, and creates a new graph shown in FIG. 7.

【0022】S7は、作業項目名を入力する。これは、
図7のグラフのノードの作業項目名(例えば“設計”)
を図示外の辞書を参照して設定、辞書に無い場合には管
理者に入力を促し入力された作業項目名を入力する。
In step S7, the work item name is input. this is,
Work item name of the node in the graph of FIG. 7 (for example, “design”)
Is set by referring to a dictionary (not shown), and if it is not in the dictionary, the administrator is prompted to input the input work item name.

【0023】S8は、確認する。以上によって、作業情
報1およびその依存関係2をアークで表すグラフを入力
とし、作業項目3およびその作業手順4をアークで表す
グラフを自動生成することができたこととなる。
At S8, confirmation is made. As described above, it is possible to automatically generate the graph in which the work information 1 and its dependency relationship 2 are represented by arcs, and the work item 3 and its work procedure 4 are represented in arcs.

【0024】S9は、良いか判別する。これは、S8で
画面上に表示された例えば図7の作業項目3およびその
作業手順4をアークで表すグラフを画面上に表示し、管
理者が良いか判別する。YESの場合には、終了する
(E)。一方、NOの場合には、S10に進む。
In step S9, it is determined whether it is good. This is done by displaying on the screen a graph representing the work item 3 and its work procedure 4 of FIG. If YES, the process ends (E). On the other hand, if NO, the process proceeds to S10.

【0025】S10は、作業項目3及びアーク(作業手
順4)の追加・削除を行う。これは、図7の自動生成し
た作業項目3およびその作業手順4をアークで表したグ
ラフを画面上に表示し、管理者が不足の作業項目3とア
ーク(作業手順4)を追加したり、余分な作業項目3と
アーク(作業手順4)を削除する(図13参照)。
In step S10, work item 3 and arc (work procedure 4) are added / deleted. This is to display on the screen a graph representing the automatically generated work item 3 and its work procedure 4 in FIG. 7 on the screen, and the administrator can add the shortage work item 3 and arc (work procedure 4), Excess work item 3 and arc (work procedure 4) are deleted (see FIG. 13).

【0026】S11は、追加した作業項目の前の作業で
出力された情報を入力情報とするか判断する。S12
は、あるもののみ、入力情報として決定し、アーク追加
し(図14参照)、S8以降を繰り返す。
In step S11, it is determined whether the information output in the work before the added work item is used as the input information. S12
Determines only certain information as input information, adds an arc (see FIG. 14), and repeats S8 and subsequent steps.

【0027】以上のS9のNO、S10からS12を繰
り返し、自動生成した作業項目3およびその作業手順を
アークで表すグラフの修正を行う。これにより、S1で
取り込んだ作業情報1およびその依存関係2をアークと
するグラフに不足情報があったときに付加したり、余分
情報があったときに削除したり、所望の作業項目3およ
びその作業手順4をアークとするグラフに容易に修正す
ることが可能となる。以下順次詳細に説明する。
The above NO of S9 and S10 to S12 are repeated to correct the automatically generated work item 3 and the graph representing the work procedure by an arc. As a result, the work information 1 and its dependency 2 captured in S1 are added when there is insufficient information in the graph, and deleted when there is extra information. It is possible to easily modify the work procedure 4 into a graph having an arc. The details will be sequentially described below.

【0028】図2は、本発明の作業情報と依存関係例を
示す。図2において、作業情報1は、作業入力情報と作
業出力情報とから構成され、グラフ上でノードに対応し
ている。作業入力情報は例えば“仕様書”であり、その
ときの作業出力情報は例えば“プログラム”である。同
様に、“プログラム”が作業入力情報であり、“出荷内
容”が作業出力情報である。
FIG. 2 shows an example of work information and dependency relationships according to the present invention. In FIG. 2, work information 1 is composed of work input information and work output information, and corresponds to a node on the graph. The work input information is, for example, a "specification document", and the work output information at that time is, for example, a "program". Similarly, the "program" is work input information, and the "shipment content" is work output information.

【0029】依存関係2は、作業入力情報と作業出力情
報との依存関係を表し、グラフ上でアークに対応してい
る図3は、本発明の作業項目と作業手順例を示す。
The dependency relationship 2 represents the dependency relationship between the work input information and the work output information, and FIG. 3 corresponding to the arc on the graph shows a work item and a work procedure example of the present invention.

【0030】図3において、作業項目3は、作業名であ
って、グラフ上でノードに対応している。作業項目3
は、図中に示すように、“設計”、“コーディング”、
“統合テスト”、“テストパッケージ作成”、“出荷準
備”、“承認”が対応している。
In FIG. 3, work item 3 is a work name and corresponds to a node on the graph. Work item 3
, As shown in the figure, "design", "coding",
"Integration test", "test package creation", "shipping preparation", "approval" are supported.

【0031】作業手順4は、作業項目3の関連を示すも
のであって、グラフ上でアークに対応している。図4
は、本発明の規則例を示す。図2のグラフに示す作業情
報1およびその依存関係2のみが与えられた場合、作業
項目3および作業手順4を生成するときに以下の規則を
用いる。
The work procedure 4 shows the relation of the work item 3, and corresponds to an arc on the graph. FIG.
Shows an example rule of the present invention. When only the work information 1 and its dependency 2 shown in the graph of FIG. 2 are given, the following rules are used when generating the work item 3 and the work procedure 4.

【0032】規則1は、全ての作業情報(作業入力情報
と作業出力情報)1は、その情報を出力する作業項目の
1つと、入力として使用する作業項目を少なくとも1つ
持つ。ここで、作業入出力情報Aの出力作業項目をprod
ucer(A)、入力作業項目をconsumer(A)を表記し、両
者を合わせて作業情報1と表記する。
According to rule 1, all work information (work input information and work output information) 1 has one work item for outputting the information and at least one work item to be used as input. Here, the output work item of the work input / output information A is prod
ucer (A), the input work item is expressed as consumer (A), and both are expressed as work information 1.

【0033】1つの作業入出力情報Aに対して複数の出
力作業項目P1、P2、・・・Pnが存在するときは、そ
れらを1つの出力作業項目P*とまとめる。P*の出力情
報はAであり、入力情報はP1、P2、・・・Pnの入力
情報すべてである。
When there are a plurality of output work items P 1 , P 2 , ... P n for one work input / output information A, they are combined into one output work item P * . The output information of P * is A, and the input information is all the input information of P 1 , P 2 , ... P n .

【0034】ここで、Pの中にAが作業入力情報である
ものがある場合、それらを除かなければならない。Pの
うちAが作業入力情報でないものはAが出力されていな
くても作業が可能であるが、Aが作業入力情報であるも
のはAが出力されて初めて作業可能となるという違いが
ある。作業が可能となるタイミングがAの有無(出力済
みか否か)によって異なるため、Aを作業入力情報とす
るものだけでまとめる必要がある。
Here, if some of P is work input information in P, they must be removed. Those of which P is not work input information can work even if A is not output, but there is a difference that work of which A is work input information becomes possible only after A is output. Since the timing at which work becomes possible differs depending on the presence / absence of A (whether it has been output or not), it is necessary to collect only A as work input information.

【0035】規則2は、作業入出力情報Aに対してprod
ucer(A)→consumer(A)といつ作業手順が存在する。規
則3は、作業入力情報A、Bに対してA→Bという直接
の依存関係があるとき、consumer(A)=producer(B)
である。
Rule 2 is prod for the work input / output information A.
When there is a work procedure such as ucer (A) → consumer (A). Rule 3 is that when there is a direct dependency of A → B on the work input information A and B, consumer (A) = producer (B)
Is.

【0036】図5は、本発明の動作説明図(その1、作
業項目抽出)を示す。これは、図2の作業情報1とその
依存関係2のグラフをもとに、図4で説明した作業項目
3を抽出したものである。例えば図2のグラフ上の作業
項目1“仕様書”について、図4の(a)の規則1を適
用し、 を生成する。また、作業項目(作業入出力情報)“仕様
書”と、“プログラム”とについて、図4の(c)の規
則3を適用し、 ・consumer(仕様書)=producer(プログラム) を生成する。これらを合わせて図5のグラフの左側の ・producer(仕様書)→仕様書→producer(プログラム)
=consumer(仕様書) が生成される。同様に、規則1、2、3のいずれかを適
用し、図2から図5に示すように作業項目(作業入出力
情報)を自動生成することが可能となる。
FIG. 5 is a diagram for explaining the operation of the present invention (No. 1, work item extraction). This is an extraction of the work item 3 described with reference to FIG. 4 based on the graph of the work information 1 and its dependency 2 in FIG. For example, with respect to work item 1 “specification” on the graph of FIG. 2, rule 1 of FIG. Generate Further, with respect to the work item (work input / output information) “specification” and “program”, rule 3 in FIG. 4C is applied, and consumer (specification) = producer (program) is generated. On the left side of the graph in Fig. 5 including them together: ・ producer (specification) → specification → producer (program)
= Consumer (specification) is generated. Similarly, it becomes possible to automatically generate work items (work input / output information) as shown in FIGS. 2 to 5 by applying any one of the rules 1, 2, and 3.

【0037】図6は、本発明の動作説明図(その2、作
業手順付加/冗長作業手順削除)を示す。これは、図2
から図4の規則1、2、3のいずれかを適用して作業項
目(作業入出力情報)3を抽出するときに、図4の規則
2に示す太線の矢印である作業手順4を合わせて抽出
し、図中で太線の矢印でグラフ上の表すと共に冗長な作
業手順4を点線の矢印で示すように削除して表したもの
である。概念的に言えば、図2から図5に示すように作
業項目(作業入出力情報)3を自動生成した後、これら
作業項目3の上位から下位に向かって作業手順4をアー
クを付加したものである。また、点線の矢印は、冗長な
作業手順4として削除したものであって、概念的に言え
ば、作業情報1から作業項目3へのうちの冗長するもの
を削除したものである。
FIG. 6 is a diagram for explaining the operation of the present invention (No. 2, work procedure addition / redundant work procedure deletion). This is shown in Figure 2.
4 to apply any one of the rules 1, 2 and 3 in FIG. 4 to extract the work item (work input / output information) 3, match the work procedure 4 indicated by the bold arrow in the rule 2 in FIG. It is extracted and shown on the graph with a bold arrow in the figure, and the redundant work procedure 4 is deleted as shown by a dotted arrow. Conceptually speaking, a work item (work input / output information) 3 is automatically generated as shown in FIG. 2 to FIG. 5, and an arc is added to the work procedure 4 from the higher order to the lower order of these work items 3. Is. Further, the dotted arrow is the one deleted as the redundant work procedure 4, and conceptually, the redundant one of the work information 1 to the work item 3 is deleted.

【0038】図7は、本発明の動作説明図(その3、作
業項目/作業手順抽出)を示す。これは、図6のグラフ
上から作業項目3(楕円のノードのみ)および作業手順
4(太線の矢印のアークのみ)を抽出し、作業項目3お
よび作業手順4のグラフを自動生成したものである。こ
の自動生成した時点では、ノード(楕円)の作業項目3
の名前は未設定である。このノードの作業項目3の名前
は、辞書を検索して設定、例えば“設計”と設定し、あ
るいは辞書を検索しても見つからないときは画面にその
旨を表示し、管理者に入力を促し、入力された名前(例
えば“設計”)を入力する。
FIG. 7 is a diagram for explaining the operation of the present invention (No. 3, work item / work procedure extraction). This is a graph in which work item 3 (only elliptical nodes) and work procedure 4 (only arcs of thick arrows) are extracted from the graph of FIG. 6 and the work item 3 and work procedure 4 graphs are automatically generated. . At the time of this automatic generation, work item 3 of the node (ellipse)
The name of is not set. The name of work item 3 of this node is set by searching the dictionary, for example, setting it as “design”, or if it is not found even after searching the dictionary, the fact is displayed on the screen, and the administrator is prompted to enter it. , Input the input name (for example, "design").

【0039】この図7の作業項目3と作業手順4のグラ
フを、図3の目的とするグラフとを比較すると、“統合
テスト”が自動抽出されていなく抜けていることが判明
する。この“統合テスト”は、最終作業の“承認”を除
くと他の全ての作業項目3が必ず何らかの出力情報であ
る。この“統合テスト”には出力情報がなかったために
自動抽出されなかったものと判明し、作業情報(作業入
出力情報)1を入力する図2の段階で不足していたもの
であり、後述する図8に示すように、作業情報1“テス
ト結果”を付加し、再処理すればよい。
By comparing the work item 3 graph of FIG. 7 and the work procedure 4 graph with the target graph of FIG. 3, it is found that the “integration test” is not automatically extracted and is omitted. In this "integration test", all work items 3 other than the final work "approval" are always output information. Since there was no output information in this "integration test", it was found that it was not automatically extracted, and it was insufficient at the stage of FIG. 2 for inputting the work information (work input / output information) 1 and will be described later. As shown in FIG. 8, work information 1 “test result” may be added and reprocessed.

【0040】図8は、本発明の他の動作説明図(その
1)を示す。これは、図2の作業情報1とその依存関係
2に対して、“テスト結果”とその依存関係を図示のよ
うに付加したものである。
FIG. 8 shows another operation explanatory view (1) of the present invention. This is obtained by adding the "test result" and its dependency relationship to the work information 1 and its dependency relationship 2 in FIG.

【0041】図9は、本発明の他の動作説明図(その
2、作業項目抽出)を示す。これは、図8の“テスト結
果”を付加したグラフから図5と同様に、図1のフロー
チャートに従って、作業項目3を自動抽出したグラフで
ある。
FIG. 9 is a diagram for explaining another operation of the present invention (No. 2, work item extraction). This is a graph in which the work item 3 is automatically extracted according to the flowchart of FIG. 1 from the graph of FIG.

【0042】図10は、本発明の他の動作説明図(その
3、作業項目/作業手順抽出)を示す。これは、図9か
ら既述した図6と同様にして太線の矢印の作業手順4を
自動抽出および点線の冗長な作業手順4を削除したもの
である。
FIG. 10 shows another operation explanatory diagram of the present invention (part 3, work item / work procedure extraction). This is the same as in FIG. 6 described above from FIG. 9, except that the work procedure 4 indicated by the thick arrow is automatically extracted and the redundant work procedure 4 indicated by the dotted line is deleted.

【0043】図11は、本発明の他の動作説明図(その
4、作業項目/作業手順抽出)を示す。これは、既述し
た図7と同様に、図10から作業項目3および作業手順
4のみを自動抽出して生成したグラフである。このグラ
フと、図3の目的とする作業項目3および作業手順4を
表すグラフとを比較すると、一致することが判明する。
FIG. 11 is a diagram for explaining another operation of the present invention (No. 4, work item / work procedure extraction). This is a graph generated by automatically extracting only the work item 3 and the work procedure 4 from FIG. 10, as in the case of FIG. 7 described above. When this graph is compared with the graph showing the target work item 3 and work procedure 4 in FIG. 3, it is found that they match.

【0044】以上のように、図2の作業情報1とその依
存関係2を表すグラフを入力とすると、図7に示す作業
項目3とその作業手順4を表すグラフが自動生成される
が、このグラフでは“統合テスト”が自動抽出されな
く、図2のグラフ上で出力情報が不足したものであると
判明するので、図8に示すように“テスト結果”を入力
して再処理すると、図11のグラフが自動生成し、この
図11のグラフと、図3の目的とするグラフとが一致
し、所望の結果を得ることが可能となる。
As described above, when the graph showing the work information 1 and its dependency 2 in FIG. 2 is input, the graph showing the work item 3 and its work procedure 4 shown in FIG. 7 is automatically generated. In the graph, "Integration test" is not automatically extracted, and it is found that the output information is insufficient on the graph in Fig. 2. Therefore, when "Test result" is input and reprocessed as shown in Fig. 8, The graph of 11 is automatically generated, the graph of FIG. 11 and the target graph of FIG. 3 match, and it is possible to obtain a desired result.

【0045】図12は、本発明の他の動作説明図(その
11)を示す。これは、“テスト結果”という作業情報
(作業入出力情報)1の不足により、“統合テスト”が
抜けってしまったときのグラフ(作業項目3と作業手順
4を表すグラフ)であって、既述した図6からproducer
/consumerを除き、作業項目3の名前(作業名)を設定
したものである。
FIG. 12 shows another operation explanatory diagram (11) of the present invention. This is a graph (a graph showing work item 3 and work procedure 4) when the “integration test” is omitted due to lack of work information (work input / output information) 1 called “test result”. Producer from FIG. 6 already mentioned
The name (work name) of work item 3 is set excluding / consumer.

【0046】図13は、本発明の他の動作説明図(その
12)を示す。これは、図12に“統合テスト”を入れ
た状態である。この作業項目3の名前(作業名)“統合
テスト”をグラフ上に追加したことにより、作業情報
(作業入出力情報)1の存在が明らかとなる。
FIG. 13 is another operation explanatory view (12) of the present invention. This is a state in which the "integration test" is included in FIG. The existence of the work information (work input / output information) 1 becomes clear by adding the name of the work item 3 (work name) “integration test” to the graph.

【0047】図14は、本発明の他の動作説明図(その
13)を示す。これは、図13の作業名“統合テスト”
について、他の作業項目3からの作業手順4を、図中の
太線の矢印として追加したものである。この段階では、
“統合テスト”の作業情報1はまだ不明であるが、作業
情報(作業入出力情報)1として、“コーディングが出
力するプログラム”と、“テストパッケージ作成が出力
するテストパッケージ”が使用される可能性は判るの
で、これらを候補として管理者に提示し、選択されたも
のを使用する、あるいは新規に定義された作業情報1を
使用するかを決定する。ここでは、図15に示すよう
に、上記両者を作業情報1の作業入力情報として選択さ
れ、更にその作業出力情報として“テスト結果”が定義
されたので、図15に示すグラフが自動生成される。
FIG. 14 shows another operation explanatory view (13) of the present invention. This is the work name “Integration test” in FIG.
Regarding the above, the work procedure 4 from the other work item 3 is added as a thick arrow in the figure. At this stage,
The work information 1 of the "integration test" is still unknown, but the "program output by the coding" and the "test package output by the test package creation" can be used as the work information (work input / output information) 1. Since the sex is known, these are presented to the administrator as candidates, and it is determined whether to use the selected one or use the newly defined work information 1. Here, as shown in FIG. 15, since both of the above are selected as the work input information of the work information 1 and the “test result” is defined as the work output information thereof, the graph shown in FIG. 15 is automatically generated. .

【0048】図15は、本発明の他の動作説明図(その
14)を示す。これは、図14のグラフ上で、?のつい
た“統合テスト”の作業情報1のうちの作業入力情報の
候補として、 ・プログラム ・テストパッケージ を表示し、両者が選択されたので両者の間に図示のよう
にアークを持たせ、更に、作業出力情報として管理者か
ら“テスト結果”が定義されて入力されたので、図示の
ように設定およびアークを持たせてグラフを自動作成す
る。この際、点線の矢印のアークは冗長するので削除す
る。
FIG. 15 shows another operation explanatory view (14) of the present invention. This is? As a candidate for the work input information in the work information 1 of the "Integrated test" with the following items: -Program-Test package is displayed. Since both are selected, an arc is provided between them as shown in the figure. Since the “test result” is defined and input as the work output information by the administrator, the graph is automatically created with the settings and arcs as shown in the figure. At this time, the arc of the dotted arrow is redundant and is therefore deleted.

【0049】以上の図12から図15によって、図10
と同一のグラフが得られ、これから作業項目3および作
業手順4のみを抽出すると目的とする図11のグラフを
得ることが可能となる。
From FIG. 12 to FIG. 15 above, FIG.
The same graph as the above is obtained, and if only the work item 3 and the work procedure 4 are extracted from this, the target graph of FIG. 11 can be obtained.

【0050】[0050]

【発明の効果】以上説明したように、本発明によれば、
作業情報(作業入力情報および作業出力情報)1および
その依存関係2のみをコンピュータ上で保持し、作業項
目3と作業手順4を自動生成する構成を採用しているた
め、作業情報1である作業入力情報および作業出力情報
と作業手順4との間の一貫性を保持しつつ手入力の手間
を削減することができると共に、従来の別個に管理して
いた場合の両者のいずれかの変更もれや誤りを低減する
ことができる。これらにより、作業情報(作業入力情報
と作業出力情報)1とその依存関係2を一元管理するの
みで作業項目3およびその作業手順4を自動生成し、作
業情報1とその依存関係2のみを更新すればよく更新の
信頼性を高めることが可能となると共に、更新作業に要
する時間を節約することが可能となる。
As described above, according to the present invention,
Only the work information (work input information and work output information) 1 and its dependency 2 are held on the computer, and the work item 3 and the work procedure 4 are automatically generated. It is possible to maintain the consistency between the input information and the work output information and the work procedure 4, while reducing the time and effort of manual input, and to avoid the change of either of them when the conventional separate management is performed. And errors can be reduced. With these, the work information (work input information and work output information) 1 and its dependency relationship 2 are centrally managed, the work item 3 and its work procedure 4 are automatically generated, and only the work information 1 and its dependency relationship 2 are updated. By doing so, it is possible to improve the reliability of the update well and save the time required for the update work.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の1実施例動作フローチャートである。FIG. 1 is an operation flowchart of an embodiment of the present invention.

【図2】本発明の作業情報と依存関係例である。FIG. 2 is an example of work information and dependency relationships according to the present invention.

【図3】本発明の作業項目と作業手順例である。FIG. 3 is an example of work items and work procedures of the present invention.

【図4】本発明の規則例である。FIG. 4 is an example of a rule of the present invention.

【図5】本発明の動作説明図(その1、作業項目抽出)
である。
FIG. 5 is an operation explanatory view of the present invention (No. 1, work item extraction)
Is.

【図6】本発明の動作説明図(その2、作業手順付加/
冗長作業手順削除)である。
FIG. 6 is a diagram for explaining the operation of the present invention (No. 2, work procedure addition /
Redundant work procedure deletion).

【図7】本発明の動作説明図(その3、作業項目/作業
手順抽出)である。
FIG. 7 is an operation explanatory diagram of the present invention (part 3, work item / work procedure extraction).

【図8】本発明の他の動作説明図(その1)である。FIG. 8 is another operation explanatory view (1) of the present invention.

【図9】本発明の他の動作説明図(その2、作業項目抽
出)である。
FIG. 9 is another operation explanatory view (No. 2, work item extraction) of the present invention.

【図10】本発明の他の動作説明図(その3、作業項目
/作業手順抽出)である。
FIG. 10 is another operation explanatory view of the present invention (part 3, work item / work procedure extraction).

【図11】本発明の他の動作説明図(その4、作業項目
/作業手順抽出)である。
FIG. 11 is another operation explanatory view of the present invention (No. 4, work item / work procedure extraction).

【図12】本発明の他の動作説明図(その11)であ
る。
FIG. 12 is another operation explanatory diagram (11) of the present invention.

【図13】本発明の他の動作説明図(その12)であ
る。
FIG. 13 is another diagram (No. 12) for explaining the operation of the present invention.

【図14】本発明の他の動作説明図(その13)であ
る。
FIG. 14 is another operation explanatory view (13) of the present invention.

【図15】本発明の他の動作説明図(その14)であ
る。
FIG. 15 is another operation explanatory view (14) of the present invention.

【図16】従来技術の説明図である。FIG. 16 is an explanatory diagram of a conventional technique.

【符号の説明】[Explanation of symbols]

1:作業情報(作業入力情報、作業出力情報) 2:依存関係 3:作業項目 4:作業手順 1: Work information (work input information, work output information) 2: Dependency 3: Work item 4: Work procedure

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】作業入力情報および作業出力情報とこれら
の間の依存関係をアークで表したグラフと、 このグラフから検出し抽出した作業項目を上記グラフに
付加する手段と、 この付加後のグラフ中で同一ノードを終端とするアーク
の作業項目をまとめる手段と、 このまとめたグラフの作業項目のノードを始点および終
点とするアーク(作業手順)を付加する手段と、 この付加後のグラフから作業項目とアーク(作業手順)
のみを取り出してグラフを生成する手段とを備えたこと
を特徴とする作業支援装置。
1. A graph in which work input information, work output information, and dependency relationships between them are represented by arcs, a means for adding work items detected and extracted from the graph to the graph, and a graph after the addition. Of the work items of arcs ending at the same node among them, a means of adding arcs (work procedure) whose starting points and end points are the nodes of the work items of this summarized graph, and work from the graph after this addition Items and arcs (work procedure)
And a means for generating only a graph by taking out only the work supporting apparatus.
【請求項2】上記アーク(作業手順)を付加した後のグ
ラフから冗長なアーク(作業手順)を除去した後、この
グラフから作業項目とアーク(作業手順)のみを取り出
してグラフを生成する手段とを備えたことを特徴とする
請求項1記載の作業支援装置。
2. A means for removing a redundant arc (work procedure) from a graph after adding the arc (work procedure) and then extracting only work items and arcs (work procedure) from the graph to generate a graph. The work support apparatus according to claim 1, further comprising:
【請求項3】上記グラフから作業項目とアーク(作業手
順)のみを取り出して生成したグラフを提示し、作業入
力情報、作業出力情報あるいはこれらの間の依存関係の
修正、追加、削除に対応して再処理し再提示する手段を
備えたことを特徴とする請求項1あるいは請求項2記載
の作業支援装置。
3. A graph generated by extracting only work items and arcs (work procedure) from the graph is presented to support correction, addition, or deletion of work input information, work output information, or a dependency between them. The work support apparatus according to claim 1 or 2, further comprising means for reprocessing and re-presenting.
JP11034895A 1995-05-09 1995-05-09 Work supporting device Withdrawn JPH08305750A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11034895A JPH08305750A (en) 1995-05-09 1995-05-09 Work supporting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11034895A JPH08305750A (en) 1995-05-09 1995-05-09 Work supporting device

Publications (1)

Publication Number Publication Date
JPH08305750A true JPH08305750A (en) 1996-11-22

Family

ID=14533489

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11034895A Withdrawn JPH08305750A (en) 1995-05-09 1995-05-09 Work supporting device

Country Status (1)

Country Link
JP (1) JPH08305750A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPWO2007105298A1 (en) * 2006-03-13 2009-07-23 三菱電機株式会社 Manufacturing system development support equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPWO2007105298A1 (en) * 2006-03-13 2009-07-23 三菱電機株式会社 Manufacturing system development support equipment
JP4629771B2 (en) * 2006-03-13 2011-02-09 三菱電機株式会社 Manufacturing system development support equipment

Similar Documents

Publication Publication Date Title
JP2009009462A (en) Sequence program editing apparatus
JP6446819B2 (en) Document difference display program and information processing apparatus
JPH08305750A (en) Work supporting device
JP2001357095A (en) Semiconductor device design supporting device
JP2003084813A (en) Editing device for ladder circuit and its editing method
JP7100991B2 (en) Data conversion device and data conversion method
JP2010224659A (en) Information processing device, information processing method, program and storage medium
JP3324830B2 (en) Machine translation equipment
JP2000148738A (en) Device and method for mathematical expression input and display, and recording medium where mathematical input and display program is recorded
JP2609820B2 (en) Program management method
JPH0744343A (en) Automatic generating device for operation support information
WO2023238358A1 (en) Display control device, display control method, and display control program
JP2003345781A (en) Device and method for editing structuring data, and program
JP2007219586A (en) Source code analysis device
JPH11272708A (en) Documentation support system
JP2009122866A (en) Electronic file storage device and electronic file storage method
JPH0546552A (en) On-line environment addition system
JPH06332684A (en) Program correction supporting device
JP2004151324A (en) Voice synthesis database correction method, voice synthesis database correction device, and voice synthesis database correction program
CN117827911A (en) Metadata and data model comparison method, device, equipment and storage medium
JP2000207188A (en) Device and method for automatically generating program and recording medium thereof
JP3051747B2 (en) Machine translation method and machine translation system
JPH1074201A (en) Machine translation system
JP2000215217A (en) Device and method for logical synthesis
JPH1153411A (en) Circuit diagram editor

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20020806