JPH08270205A - Lifting device of prefabricated scaffold and assembling and disassembling work thereof - Google Patents

Lifting device of prefabricated scaffold and assembling and disassembling work thereof

Info

Publication number
JPH08270205A
JPH08270205A JP7488795A JP7488795A JPH08270205A JP H08270205 A JPH08270205 A JP H08270205A JP 7488795 A JP7488795 A JP 7488795A JP 7488795 A JP7488795 A JP 7488795A JP H08270205 A JPH08270205 A JP H08270205A
Authority
JP
Japan
Prior art keywords
frame
lifting
scaffold
frame scaffold
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7488795A
Other languages
Japanese (ja)
Inventor
Shozo Naemura
正三 苗村
Noriaki Aoyama
憲明 青山
Toshiharu Ogawa
敏治 小川
Masao Fukui
真男 福井
Yoshisato Yamaguchi
善郷 山口
Hiromoto Ikegame
弘基 池亀
Kota Ueno
弘太 上野
Hironobu Ekuni
洋伸 江國
Katsuro Aoki
勝郎 青木
Junichi Ujiie
純一 氏家
Yasuhisa Aida
泰久 会田
Yutaka Yamahana
豊 山花
Yukitake Kitano
幸壯 北野
Tadashi Koike
正 小池
Tomozo Kagaya
智三 加賀屋
Yoshiteru Aota
義輝 青田
Toru Watanabe
徹 渡辺
Toshihiro Ukai
敏宏 鵜飼
Hitoshi Inoue
齊 井上
Kenichi Mitamura
健一 三田村
Toshihiko Nakusa
俊比古 名草
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHUO BIRUTO KOGYO KK
KOYO KIKAI SANGYO KK
Minister for Public Works for State of New South Wales
Mitsui Construction Co Ltd
Kajima Corp
Obayashi Corp
Fujita Corp
Matsumura Gumi Corp
Zenitaka Corp
Nishimatsu Construction Co Ltd
Toa Corp
Penta Ocean Construction Co Ltd
Kumagai Gumi Co Ltd
Sato Kogyo Co Ltd
Nisso Industries Co Ltd
Toda Corp
Sumitomo Construction Co Ltd
Tokyu Construction Co Ltd
Sumikin Kozai Kogyo KK
Advanced Construction Technology Center ACTEC
National Research and Development Agency Public Works Research Institute
Original Assignee
CHUO BIRUTO KOGYO KK
KOYO KIKAI SANGYO KK
Minister for Public Works for State of New South Wales
Mitsui Construction Co Ltd
Kajima Corp
Obayashi Corp
Fujita Corp
Matsumura Gumi Corp
Zenitaka Corp
Nishimatsu Construction Co Ltd
Toa Corp
Penta Ocean Construction Co Ltd
Public Works Research Institute Ministry of Construction
Kumagai Gumi Co Ltd
Sato Kogyo Co Ltd
Nisso Industries Co Ltd
Toda Corp
Sumitomo Construction Co Ltd
Tokyu Construction Co Ltd
Sumikin Kozai Kogyo KK
Advanced Construction Technology Center ACTEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHUO BIRUTO KOGYO KK, KOYO KIKAI SANGYO KK, Minister for Public Works for State of New South Wales, Mitsui Construction Co Ltd, Kajima Corp, Obayashi Corp, Fujita Corp, Matsumura Gumi Corp, Zenitaka Corp, Nishimatsu Construction Co Ltd, Toa Corp, Penta Ocean Construction Co Ltd, Public Works Research Institute Ministry of Construction, Kumagai Gumi Co Ltd, Sato Kogyo Co Ltd, Nisso Industries Co Ltd, Toda Corp, Sumitomo Construction Co Ltd, Tokyu Construction Co Ltd, Sumikin Kozai Kogyo KK, Advanced Construction Technology Center ACTEC filed Critical CHUO BIRUTO KOGYO KK
Priority to JP7488795A priority Critical patent/JPH08270205A/en
Publication of JPH08270205A publication Critical patent/JPH08270205A/en
Pending legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

PURPOSE: To dispense with works at a high level as prefabricated scaffolds can be assembled and disassembled only on the ground and hence increase the safety because there is no danger such as falling of workers or dropping of scaffold materials and also operate with ease because of works free from life-lines and further, increase the working efficiency since the working space is not restricted and much area thereof is not required and dispense with cranes. CONSTITUTION: A lifting device in which a lifting girder 9 having detachable claws 20 at prefabricated scaffolds is equipped between masts 8 erected on the ground, is used. The prefabricated scaffold is hooked and hoisted by the lifting girder 9. A lower scaffold is assembled in the lower side. The same processes are repeated to assemble a multi-layer scaffold in turn. The periphery of the second layer from the lowermost one, in the multi-layer scaffold assembled by the lifting girder 9, is surrounded and the prefabricated scaffold is hooked and hoisted as the whole. Then the lowermost scaffold layer suspended afloat is disassembled and removed. The same processes are repeated thereafter to disassemble and remove the lowermost scaffold layer in turn.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建築、土木の構造物の
築造および補修時に使用する枠組足場の組立・解体工法
およびそれに使用する装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for assembling and disassembling a frame scaffold used for construction and construction of civil engineering structures and equipment used therefor.

【0002】[0002]

【従来の技術】図29にも示すように枠組足場は周知のご
とく、対向して並べる建枠1を側部では交差筋違い2
で、上部では布枠3で連結し、順次水平方向に繋げてい
くとともに、上下方向では建枠1の相互を連結ピン4で
結合していく。図中5はアームロックである。
2. Description of the Related Art As shown in FIG. 29, a frame scaffold is well known, and a building frame 1 arranged facing each other has a crosswise streak 2 at the side.
Then, in the upper part, the cloth frames 3 are connected and sequentially connected in the horizontal direction, and in the vertical direction, the building frames 1 are connected to each other by the connecting pins 4. In the figure, 5 is an arm lock.

【0003】このような建枠1を用いる枠組足場の組立
および解体方法は、組立て作業の場合の一例を図30〜図
32に示すと、まず、最下層の1層目は地上にて組立てを
行い、2層目からは両端部と数スパン(例えば10スパ
ン)ずつ組立てる。(作業時には、下部の足場に安全帯
をつける。)
The method of assembling and disassembling a frame scaffolding using such a building frame 1 is an example of an assembling work, as shown in FIGS.
As shown in 32, first, the first layer of the lowermost layer is assembled on the ground, and from the second layer, both ends and several spans (for example, 10 spans) are assembled. (When working, attach a safety belt to the lower scaffold.)

【0004】図31に示すように、組んだ2層目の最上部
に親綱6をはり、図32に示すように、前記親綱6を利用
して2層分の残りを組立てる。2層部分の組立てが完了
したならば、今まで使用していた親綱6を利用して、3
層部を前記2層部と同じく両端部と数スパン毎に組立
て、以下、同様にして、順次上層に組み上げていく。
As shown in FIG. 31, the master rope 6 is put on the uppermost portion of the assembled second layer, and as shown in FIG. 32, the remaining two layers are assembled using the master rope 6. When the assembly of the two-layer part is completed, use the parent rope 6 that has been used until now to
As with the two-layer portion, the layer portion is assembled at both end portions and every several spans, and thereafter, the layer portions are sequentially assembled in the same manner.

【0005】一方、解体作業の場合は図33に示すように
最上階床に親綱6をはわせ、この親綱6を利用して最上
階のものから解体を行う。
On the other hand, in the case of the dismantling work, as shown in FIG. 33, the master rope 6 is attached to the floor on the uppermost floor, and the master rope 6 is used to dismantle from the top floor.

【0006】図34に示すように前記親綱6を利用して下
部の解体を行い、この親綱6を取付けている枠まで解体
した段階で床に新たな親綱6を設置し、この床上の親綱
6を利用して、上部の親綱6と両側の足場を解体し、以
下、同様にして上の層から順次解体していく。
As shown in FIG. 34, the lower part of the master rope 6 is dismantled, and a new master rope 6 is installed on the floor when the frame to which the master rope 6 is attached is dismantled. Using the master rope 6, the upper master rope 6 and the scaffolds on both sides are dismantled, and thereafter, in the same manner, the upper layers are sequentially dismantled.

【0007】以上は枠組足場の組立および解体方法の一
例であり、この他にも図示は省略するが、最上層の枠組
足場の床上に親綱支柱を立設し、この親綱支柱で親綱を
一定高さに張りながら作業を行う方法もある。
The above is one example of the method of assembling and disassembling the frame scaffold, and although not shown in the drawings, a master rope is erected on the floor of the uppermost frame scaffold, and the master rope is used by this pillar. There is also a method to work while tensioning a certain height.

【0008】[0008]

【発明が解決しようとする課題】このように従来の枠組
足場の組立および解体方法では、いずれも高所作業を伴
うものであり、作業員の墜落や足場材の落下の危険性が
あり、墜落防止としては親綱を張って命綱を使用しなけ
ればならない。その分、作業性が阻害され、効率が低下
する。
As described above, all of the conventional methods for assembling and disassembling frame scaffolds involve work at high places, and there is a risk of a worker falling or scaffolding materials falling. As a preventive measure, you must use a lifeline with a masterline. As a result, workability is hindered and efficiency is reduced.

【0009】さらに、上層の組立のためにクレーンで足
場材を既設組立層の床まで揚重することや、解体した上
層の足場材をクレーンで地上に降ろすなどでクレーンの
設置を必要とすることも多い。
Furthermore, it is necessary to install the crane by hoisting the scaffolding material to the floor of the existing assembly layer with a crane for assembling the upper layer and dismounting the disassembled upper layer scaffolding material with the crane. There are also many.

【0010】本発明の目的は前記従来例の不都合を解消
し、地上作業のみで枠組足場の組立・解体ができるの
で、高所作業がなくなり、作業員の墜落や足場材の落下
の危険性がなく安全性が向上するとともに、命綱で拘束
されることもないので楽に作業ができ、しかも、作業ス
ペースが固定して多くの面積を必要とせず、作業効率も
良く、さらに、クレーンの設置も必要としない枠組足場
の昇降装置および枠組足場の組立・解体工法を提供する
ことにある。
The object of the present invention is to eliminate the inconveniences of the above-mentioned conventional examples and to assemble and disassemble the frame scaffolding only by ground work, which eliminates the work at high places, and the risk of worker's fall and scaffold material falling. Not only does it improve safety, but it is not tied up by a lifeline, so you can work easily. In addition, the work space is fixed and does not require a large area, work efficiency is good, and you also need to install a crane. An object of the present invention is to provide a frame scaffold lifting device and a method for assembling and disassembling the frame scaffold.

【0011】[0011]

【課題を解決するための手段】本発明は前記目的を達成
するため、枠組足場の昇降装置としては、第1に、地上
に立設するマストに昇降機構を設け、このマスト間に枠
組足場に係脱可能な爪を有するリフティングガータを前
記昇降機構で昇降自在に設けたこと、第2に、昇降機構
は、モータで回転駆動する転造ネジ軸にボールネジナッ
トを螺合し、このボールネジナットでリフティングガー
タを支承すること、第3に、枠組足場に係脱可能な爪
は、その回動軸をリフティングガータに設けたモータで
チェーンを介して回動させること、第4に、リフティン
グガータの側部から先端にローラを設けたつなぎ材を水
平方向に突設し、構造物側に設けたチャンネルレール状
の止め金具にこのつなぎ材を摺動自在に係合させるこ
と、第5に、リフティングガータの上面にピンを突設
し、このピンが挿入する孔を端部近くに設けたバーを枠
組足場の建枠に着脱自在に取り付けることを要旨とする
ものである。
In order to achieve the above object, the present invention relates to a frame scaffold lifting device. Firstly, a lifting mechanism is provided on a mast standing on the ground, and the frame scaffold is provided between the masts. The lifting gutter having the disengageable claw is provided so as to be able to move up and down by the elevating mechanism. Secondly, the elevating mechanism screws a ball screw nut to a rolling screw shaft that is rotationally driven by a motor. The lifting gutter is supported, thirdly, the claw that can be engaged with and disengaged from the frame scaffold is rotated by a motor provided in the lifting gutter through a chain, and fourth, the lifting gutter side. A connecting member provided with a roller at its tip from the above portion is projected in the horizontal direction, and the connecting member is slidably engaged with a channel rail-shaped stopper provided on the structure side; Pins projecting into the upper surface of Gugata, it is an gist removably attached to the bar provided with holes the pin is inserted near the end to Kenwaku of framework scaffolding.

【0012】枠組足場の組立工法としては、第1に、枠
組足場に係脱可能な爪を有するリフティングガータを地
上に立設するマスト間に設けた昇降装置を使用し、リフ
ティングガータでその内部に組立てた枠組足場の同一層
の周囲を囲い、該枠組足場を掛止して上昇させ、その下
方に下層の枠組足場を組み、リフティングガータを下降
させて、この新たに組み立てた枠組足場の同一層の周囲
を囲い、該枠組足場を掛止して上昇させ、以下同様の工
程を繰り返して、順次枠組足場を多層に組立てていくこ
と、および第2に、枠組足場の建枠の側部に先端にロー
ラを設けたつなぎ材を設け、構造物側に設けたチャンネ
ルレール状の止め金具にこのつなぎ材を摺動自在に係合
させることを要旨とするものである。
As a method of assembling the frame scaffold, firstly, an elevating device provided between the masts which vertically installs a lifting gutter having disengageable claws on the frame scaffold is used. Enclose the same frame of the assembled frame scaffold, hook the frame scaffold to raise it, assemble the lower frame scaffolding below it, lower the lifting gutter, and make the same layer of the newly assembled frame scaffold. The frame scaffold, and the frame scaffold is hooked and raised, and then the same steps are repeated to sequentially assemble the frame scaffold in multiple layers, and secondly, the tip on the side of the building frame of the frame scaffold. The gist of the present invention is to provide a connecting member provided with a roller on and to slidably engage the connecting member with a channel rail-shaped stopper provided on the structure side.

【0013】枠組足場の解体工法としては、枠組足場に
係脱可能な爪を有するリフティングガータを地上に立設
するマスト間に設けた昇降装置を使用し、リフティング
ガータで多層に組立てた枠組足場の下から2層目の周囲
を囲い、該枠組足場を掛止して枠組足場全体を上昇さ
せ、地上から浮いた最下層の枠組足場を解体撤去し、リ
フティングガータを下降させて、下から2層目を地上に
接地させ、リフティングガータを上昇させてその上の層
を掛止して枠組足場全体を上昇させ、以下、同様の工程
を繰り返して、順次最下層の枠組足場を解体撤去してい
くことを要旨とするものである。
As a method of disassembling the frame scaffold, a lifting girder provided between the masts, which is provided on the ground, with a lifting gutter having detachable claws on the frame scaffold is used, and the frame scaffold assembled in multiple layers by the lifting gutter is used. Enclose the perimeter of the second layer from the bottom, hang the frame scaffold to raise the entire frame scaffold, dismantle and remove the bottom frame scaffold floating from the ground, lower the lifting gata, and lower the second layer Ground your eyes on the ground, raise the lifting gutter and hook the layer above it to raise the entire framework scaffolding, and repeat the same process below to dismantle and remove the bottommost framework scaffolding. This is the summary.

【0014】[0014]

【作用】請求項1記載の本発明によれば、リフティング
ガータで枠組足場を爪を介して掛止めながら昇降させ、
これにより最下層の部分で組立て解体ができるので、地
上作業のみで高所作業がなくなり、安全性が向上すると
ともに、作業スペースが固定して効率も良い。
According to the first aspect of the present invention, the lifting scaffold is used to lift and lower the frame scaffold while hooking the frame scaffold via the claws.
As a result, assembling and disassembling can be performed in the lowermost layer portion, work at a high place is eliminated by only ground work, safety is improved, and work space is fixed and efficiency is good.

【0015】請求項2記載の本発明によれば、前記作用
に加えて、リフティングガータの昇降機構は、回転駆動
する転造ネジ軸とボールネジナットの組合せで、繊細な
動きにも対応できる確実な力強い昇降動作が得られる。
According to the second aspect of the present invention, in addition to the above operation, the lifting mechanism of the lifting garter is a combination of a rolling screw shaft that is rotationally driven and a ball screw nut, and can reliably handle delicate movements. A powerful lifting operation can be obtained.

【0016】請求項3記載の本発明によれば、枠組足場
に係脱可能な爪は、モータでチェーンを解して回動させ
ることにより、単一の駆動源で複数の爪を一度に同じ動
作で回転駆動できる。
According to the present invention as set forth in claim 3, the claws that can be engaged with and disengaged from the frame scaffold are the same when a plurality of claws are made to be the same at a time by a single drive source by rotating the chain by unraveling it by a motor. Can be rotationally driven by operation.

【0017】請求項4記載の本発明によれば、昇降装置
自体をつなぎ材を介して構造物にとめることができ転倒
防止に役立つ。
According to the fourth aspect of the present invention, the elevating device itself can be fixed to the structure through the connecting member, which is useful for preventing overturning.

【0018】請求項5記載の本発明によれば、バーでリ
フティングガータの開きを阻止することができ、爪の枠
組足場への確実な掛止めが確保できる。
According to the fifth aspect of the present invention, it is possible to prevent the lifting garter from opening with the bar, and it is possible to ensure that the pawl is securely hooked to the framework scaffold.

【0019】請求項6記載の本発明によれば、枠組足場
の昇降装置を使用し、リフティングガータの内部に組立
てた最下層の枠組足場を上昇させ、その下方に下層の枠
組足場を組み、以下、順次枠組足場を地上で下層ごとに
組立てて多層にしていくことができる。
According to the sixth aspect of the present invention, by using the lifting device for the frame scaffold, the lowermost frame scaffold assembled inside the lifting gutter is raised, and the lower frame scaffold is assembled below the frame scaffold. , Sequential frame scaffolds can be assembled on the ground for each lower layer to form multiple layers.

【0020】請求項7記載の本発明によれば、前記作用
に加えて、枠組足場をつなぎ材を介して構造物にとめる
ことができ、枠組足場、ひいては枠組足場の昇降装置の
転倒防止が得れる。
According to the present invention as set forth in claim 7, in addition to the above-mentioned action, the frame scaffold can be fixed to the structure through the connecting member, and the frame scaffold, and consequently the lifting device for the frame scaffold, can be prevented from falling. Be done.

【0021】請求項8記載の本発明によれば、枠組足場
の昇降装置を使用し、リフティングガータで多層に組立
てた枠組足場の下から2層目の枠組足場を掛止して全体
を上昇させ、地上から浮いた最下層の枠組足場を地上で
解体撤去し、以下、順次最下層の枠組足場を地上で解体
撤去していくことができる。
According to the eighth aspect of the present invention, by using the lifting device for the frame scaffold, the second frame scaffold from the bottom of the frame scaffold assembled in multiple layers by the lifting gutter is hooked to raise the whole structure. , The bottom frame scaffolding floating from the ground can be dismantled and removed on the ground, and then the bottom frame scaffolding can be dismantled and removed on the ground.

【0022】[0022]

【実施例】以下、本発明の実施例を図面について詳細に
説明する。先に本発明の枠組足場の昇降装置について説
明すると、図1は側面図、図2は平面図である。
Embodiments of the present invention will now be described in detail with reference to the drawings. First, the elevating device for a framed scaffold of the present invention will be described. FIG. 1 is a side view and FIG. 2 is a plan view.

【0023】ネジシャフトで高さ調節可能なベース7を
基台部19に設け、このベース7で地上に立設するマスト
8を左右に配設し、該マスト8間にリフティングガータ
9を架設し、マスト8にはこのリフティングガータ9の
昇降機構10を設けた。
A base 7 whose height can be adjusted with a screw shaft is provided on a base portion 19, masts 8 standing on the ground are arranged on the left and right by the base 7, and a lifting gutter 9 is installed between the masts 8. The lifting mechanism 10 for the lifting gutter 9 is provided on the mast 8.

【0024】かかる昇降機構10の構成としては油圧ジャ
ッキを用いたものやウインチと巻き上げワイヤーによる
ものなど種々考えられるが、本実施例ではマスト8の高
さ方向に転造ネジ軸11を配設し、図10、図11に示すよう
にこの転造ネジ軸11と前記基台部19に設置したギヤード
モータ14で回転駆動する水平駆動軸12とを傘歯車28を内
蔵したギヤーボックス13で連結した。
There are various conceivable constitutions of the elevating mechanism 10 such as one using a hydraulic jack and one using a winch and a hoisting wire. In this embodiment, the rolling screw shaft 11 is arranged in the height direction of the mast 8. As shown in FIGS. 10 and 11, the rolling screw shaft 11 and the horizontal drive shaft 12 which is rotationally driven by the geared motor 14 installed on the base 19 are connected by a gear box 13 having a bevel gear 28 built therein. .

【0025】図中34は転造ネジ軸11や水平駆動軸12を取
り付けるためのボールベアリング、15はギヤードモータ
14側のスプロケットとチェーンで連結する水平駆動軸12
側のスプロケットである。
In the figure, 34 is a ball bearing for mounting the rolling screw shaft 11 and the horizontal drive shaft 12, and 15 is a geared motor.
Horizontal drive shaft 12 that connects to the sprocket on the 14 side with a chain
It is a sprocket on the side.

【0026】転造ネジ軸11に図14に示すようなボールネ
ジナット16を螺合し、図5に示すようにこのボールネジ
ナット16でリフティングガータ9の端部を支承する。
A ball screw nut 16 as shown in FIG. 14 is screwed onto the rolled screw shaft 11, and the end of the lifting garter 9 is supported by the ball screw nut 16 as shown in FIG.

【0027】マスト8は前記基台部19にベース7に並べ
てキャスター18を設け、このベース7で支承しない場合
はキャスター18で移動できるようにした。
The mast 8 is provided with casters 18 on the base portion 19 side by side with the base 7. When the mast 8 is not supported by the base 7, the mast 8 can be moved by the casters 18.

【0028】前記リフティングガータ9には枠組足場に
係脱可能な爪20を水平内側方向に向けて回動するように
設け、該リフティングガータ9の一方の端にギヤードモ
ータ21を取付け、図6〜図9に示すようにこのギヤード
モータ21のスプロケット22と爪20の回動軸に設けたスプ
ロケット23をチェーン24で連結するが、爪20は枠組足場
の建枠1が並ぶ間隔でリフティングガータ9の長さ方向
に配列され、これら複数の爪20を一個のギヤードモータ
21で回転させるようにする。なお、リフティングガータ
9は左右のマスト8に対して桁が平行するものであり、
爪20もこの桁同士で対向するように配置される。
The lifting garter 9 is provided with a claw 20 which can be engaged with and disengaged from the frame scaffold so as to rotate in the horizontal inward direction, and a geared motor 21 is attached to one end of the lifting garter 9, as shown in FIGS. As shown in FIG. 9, the sprocket 22 of the geared motor 21 and the sprocket 23 provided on the rotating shaft of the claw 20 are connected by a chain 24, and the claw 20 is arranged at an interval between the building frames 1 of the frame scaffolding and the lifting gutter 9 is arranged. These multiple claws 20 are arranged in the length direction, and a plurality of claws 20 are arranged in one geared motor.
Turn it at 21. The lifting garter 9 has a girder parallel to the left and right masts 8,
The claws 20 are also arranged so that the girders face each other.

【0029】さらに、図4に示すようにこのリフティン
グガータ9の側部から先端にローラ25aを設けたつなぎ
材25を水平方向に突設し、一方、構造物26側に設けたチ
ャンネルレール状の止め金具27にこのつなぎ材25の先端
ローラ25a部分を摺動自在に係合させる。
Further, as shown in FIG. 4, a connecting member 25 provided with a roller 25a at its tip is horizontally projected from the side portion of the lifting gutter 9, and on the other hand, a channel rail-like member provided on the structure 26 side is provided. The tip roller 25a portion of the connecting member 25 is slidably engaged with the stopper 27.

【0030】図3に示すように、この先端にローラ25a
を設けたつなぎ材25は後述する枠組足場の1層毎もしく
は間隔を存した層毎の建枠1の側部にも設け、構造物26
側に設けたチャンネルレール状の止め金具27にこのつな
ぎ材25の先端ローラ25a部分を摺動自在に係合させる。
As shown in FIG. 3, the roller 25a is attached to the tip of the roller 25a.
The tie member 25 provided with is also provided on the side portion of the building frame 1 for each layer of the frame scaffold described later or for each layer with a space, and the structure 26
The tip roller 25a portion of the connecting member 25 is slidably engaged with a channel rail-shaped stopper 27 provided on the side.

【0031】なお、他の実施例として昇降機構10のギヤ
ーボックス13の構成は図12、図13に示すように傘歯車の
代わりにウォームギヤ29と平歯車30を用いたものでもよ
い。
As another embodiment, the structure of the gear box 13 of the lifting mechanism 10 may use a worm gear 29 and a spur gear 30 instead of the bevel gear as shown in FIGS.

【0032】次に、かかる本発明の枠組足場の昇降装置
を用いて行う枠組足場の組立工法について説明する。
Next, a method of assembling a frame scaffold using the lifting device for the frame scaffold of the present invention will be described.

【0033】図16に示すように本発明の枠組足場の昇降
装置を組立て場所に設置する。その際、構造物26側のリ
フティングガータ9の側部からのつなぎ材25を止め金具
27に係合させておく。
As shown in FIG. 16, the lifting device for the frame scaffold of the present invention is installed at the assembly site. At that time, the connecting member 25 from the side of the lifting gutter 9 on the structure 26 side is fastened with a metal fitting.
Keep it engaged with 27.

【0034】リフティングガータ9内で1層5スパンの
枠組足場を組立てる。これによりリフティングガータ9
は枠組足場の1層目の周囲を囲うことになる。
Assembling a frame scaffold of one layer and five spans in the lifting gutter 9. This makes lifting garter 9
Will surround the first layer of the frame scaffold.

【0035】ギヤードモータ21を駆動してリフティング
ガータ9に設けた爪20を内側に突出させ、この爪20を枠
組足場の建枠1に掛止する。この建枠1が図29に示す鳥
居型枠の場合は水平補剛材1aに爪20を掛止するが、鳥
居型枠と形状の異なるはしご型枠や簡易型枠等の場合の
建枠では布枠を引っ掛ける梁部材やその他横架材の何れ
かに掛止してもよい。
The geared motor 21 is driven to cause the claw 20 provided on the lifting gutter 9 to project inward, and the claw 20 is hooked on the building frame 1 of the frame scaffolding. When this building frame 1 is the torii formwork shown in FIG. 29, the claws 20 are hooked on the horizontal stiffener 1a, but in the case of a ladder form or a simple formwork having a shape different from that of the torii formwork, The cloth frame may be hooked on any of beam members and other horizontal members.

【0036】図15に示すように2および4スパン目の建
枠1の支柱にリフティングガータ9の開き止め用のバー
31としてアンクル材をUボルト等のボルト32で着脱自在
に固定し、この開き止め用のバー31の左右端近くに孔31
aを設け、この孔31aに挿入するピン33をリフティング
ガータ9の上面に突設している。そこで、ピン33を孔31
aに差し入れてリフティングガータ9上に直交する向き
にバー31を架け渡す。
As shown in FIG. 15, a bar for preventing the lifting garter 9 from opening is attached to the pillars of the building frame 1 of the second and fourth spans.
Anchor material is detachably fixed as a bolt with U bolts 32, and holes 31 are provided near the left and right ends of the bar 31 for opening prevention.
A is provided, and a pin 33 to be inserted into this hole 31a is provided on the upper surface of the lifting garter 9 so as to project. Therefore, the pin 33 is inserted into the hole 31.
Insert it in a and hang the bar 31 on the lifting gutter 9 in a direction orthogonal to it.

【0037】ギヤードモータ14を駆動すれば転造ネジ軸
11が正転してボールネジナット16が上昇するのでリフテ
ィングガータ9も上昇するが、図17に示すように1層5
スパンの枠組足場を上昇させ、地上より1.9 m程吊り上
げる。
If the geared motor 14 is driven, the rolled screw shaft
11 rotates forward and the ball screw nut 16 rises, so the lifting gutter 9 also rises, but as shown in FIG.
Raise the frame scaffolding of the span and lift it about 1.9 m above the ground.

【0038】この1層目の下に2層目の枠組足場の建枠
1を取り付け、該下側2層目に交差筋違い2を取付け
る。1層目の建枠1と2層目の建枠1とは連結ピン4で
連結するが、この連結ピン4は差し込みロック式等のも
ので1層目の建枠1に2層目の建枠1が吊り下がる。
Under the first layer, the building frame 1 of the frame scaffolding of the second layer is attached, and the cross bracing 2 is attached to the lower second layer. The first-layer building frame 1 and the second-layer building frame 1 are connected by a connecting pin 4, and the connecting pin 4 is of an insertion lock type or the like, and the first-layer building frame 1 is connected to the second-layer building frame 1. The frame 1 hangs.

【0039】図18に示すようにリフティングガータ9を
20cm程度下降させ、2層5スパンを地上に降ろす。そし
てこの下側2層5スパンに布枠3を取付け、爪20を回転
して建枠1の水平補剛材1aから取り外す。
As shown in FIG. 18, the lifting gutter 9
Descend about 20 cm and lower the two layers and five spans to the ground. Then, the cloth frame 3 is attached to the lower two-layer 5 span, and the claw 20 is rotated to remove it from the horizontal stiffener 1a of the building frame 1.

【0040】図19に示すように、リフティングガータ9
を下降させ、下側2層5スパンの建枠1の水平補剛材1
aの位置に移動する。そして、爪20を回転させて建枠1
の水平補剛材1aに掛止めする。
As shown in FIG. 19, the lifting gutter 9
To lower the horizontal stiffener 1 of the building frame 1 with the lower two layers and five spans
Move to the position of a. Then, rotate the claw 20 to construct the building frame 1
It is hooked on the horizontal stiffener 1a.

【0041】下側2層5スパンの3および4スパン目の
建枠1にリフティングガータ9の開き止め用のバー31を
設置し、このバー31にピン33を差し入れる。
A bar 31 for preventing the lifting of the lifting garter 9 is installed on the building frame 1 of the third and fourth spans of the lower two layers and five spans, and the pin 33 is inserted into this bar 31.

【0042】図20に示すように2層5スパンをリフティ
ングガータ9を上昇させることで地上から1.9 m程吊り
上げ、上側2層5スパンの建枠1に下側3層目の建枠1
を挿入し、ロックする。この最下層の3層目の5スパン
に交差筋違い2を取付ける。
As shown in FIG. 20, by lifting the lifting gutter 9 from the two-story five-span, it is lifted about 1.9 m from the ground, and the upper two-story five-span building frame 1 and the lower three-story building frame 1
Insert and lock. The cross streaks 2 are attached to the 5th span of the 3rd layer of the bottom layer.

【0043】図21に示すようにリフティングガータ9を
20cm程度下降させ、3層5スパンを地上に降ろす。そし
て最下層の3層目5スパンに布枠3を取付け、爪20を回
転して建枠1の水平補剛材1aから取り外す。
As shown in FIG. 21, the lifting gutter 9
Descend by about 20 cm and lower 3 layers and 5 spans to the ground. Then, the cloth frame 3 is attached to the lowermost third layer 5 span, and the claw 20 is rotated to remove it from the horizontal stiffener 1a of the building frame 1.

【0044】以下同様に積層し、所定層、例えば、6層
5スパンを組み上げる。その際、地上より3層以上は図
3にも示すように建枠1より構造物26側にスライド自在
につなぎ材25を1層分ずつ順次分割し、設置する。
Thereafter, the layers are laminated in the same manner, and a predetermined layer, for example, 6 layers and 5 spans are assembled. At this time, as shown in FIG. 3, three or more layers from the ground are installed by sequentially dividing one layer of the connecting material 25 slidably from the building frame 1 to the structure 26 side.

【0045】枠組足場の組立て完了後は、本発明の枠組
足場の昇降装置を適宜分解して撤去する。
After completion of the assembly of the frame scaffold, the lifting device for the frame scaffold of the present invention is disassembled and removed.

【0046】なお、図3に示すように、前記図16でのリ
フティングガータ9内で1層5スパンの枠組足場を組立
ての際に手摺35を取り付けるようにすることもできる。
この手摺35は最上階に位置するものとして、1層5スパ
ンの枠組足場とともにそのまま上昇できる。
As shown in FIG. 3, the handrail 35 may be attached when assembling the frame scaffold having one layer and five spans in the lifting gutter 9 shown in FIG.
Since this handrail 35 is located on the top floor, it can be lifted as it is together with the frame scaffolding of one layer and five spans.

【0047】次に、解体工法について説明する。図22に
示すように本発明の枠組足場の昇降装置を組立て場所に
設置する。その際、構造物26側のリフティングガータ9
の側部からのつなぎ材25を止め金具27に係合させてお
く。
Next, the dismantling method will be described. As shown in FIG. 22, the lifting device for the frame scaffold of the present invention is installed at the assembly place. At that time, the lifting gutter 9 on the structure 26 side
The tie member 25 from the side of the is engaged with the stopper 27.

【0048】なお、地上より3層目〜6層目まで建枠1
より構造物26に設置したつなぎ材25は、最下層解体ごと
に6層目から順に3層目まで撤去する。爪20を回転させ
て建枠1の水平補剛材1aにぶつからないようにしてお
く。
The building frame 1 from the third floor to the third to sixth floors
The tie member 25 installed on the structure 26 is removed from the sixth layer to the third layer in each lowermost layer dismantling. The claw 20 is rotated so as not to hit the horizontal stiffener 1a of the building frame 1.

【0049】図23に示すようにリフティングガータ9を
上昇し、下から2層目の建枠1の水平補剛材1aの位置
に移動して、この2層目の周囲を囲い、地上より2層目
の3および4スパン目の建枠1に設置した開き止め用の
バー31の孔31aにリフティングガータ9の上面に突設し
たピン33を挿入し固定する。
As shown in FIG. 23, the lifting gutter 9 is moved up and moved to the position of the horizontal stiffener 1a of the second frame of the building frame 1 from the bottom to enclose the circumference of the second layer, and to move from the ground 2 A pin 33 protruding from the upper surface of the lifting garter 9 is inserted into and fixed to the hole 31a of the bar 31 for opening prevention installed in the building frame 1 of the third and fourth spans.

【0050】爪20を回転して2層目の建枠1の水平補剛
材1aに掛止し、1層目5スパンの布枠3を取り外す。
The pawl 20 is rotated and hooked on the horizontal stiffener 1a of the second-layer building frame 1, and the cloth frame 3 of the first-layer 5 span is removed.

【0051】図24に示すように、リフティングガータ9
を上昇させ、3層5スパンを地上より20cm程度吊り上げ
る。
As shown in FIG. 24, the lifting gutter 9
And raise 3 layers and 5 spans from the ground by about 20 cm.

【0052】このようにしてから、最下層5スパンの交
差筋違い2を取り外し、最下層5スパンの建枠1を取り
外す。
After this, the cross streaks 2 of the lowermost 5 spans are removed, and the building frame 1 of the lowermost 5 spans is removed.

【0053】図25に示すようにリフティングガータ9を
下降し、2層5スパンを地上に降ろす。そして、爪20を
回転して下側5スパンの建枠1の水平補剛材1aよりこ
の爪20を外し、下側の3および4スパンの建枠1に設置
した開き止め用のバー31を撤去する。
As shown in FIG. 25, the lifting garter 9 is lowered to lower the two-layer, five-span to the ground. Then, the pawl 20 is rotated to remove the pawl 20 from the horizontal stiffening material 1a of the building frame 1 having the lower 5 spans, and the bar 31 for preventing the opening installed on the lower 3 and 4 span building frames 1 is installed. To remove.

【0054】図26に示すようにリフティングガータ9を
上昇し、上側5スパンの建枠1の水平補剛材1aの位置
に移動し、上側2層目の3および4スパン目の建枠1に
設置した開き止め用のバー31の孔31aにリフティングガ
ータ9の上面に突設したピン33を挿入し固定する。
As shown in FIG. 26, the lifting gutter 9 is moved up and moved to the position of the horizontal stiffener 1a of the building frame 1 with the upper 5 spans, and the building frame 1 with the 3rd and 4th spans on the upper second layer is moved. The pin 33 protruding from the upper surface of the lifting gutter 9 is inserted into and fixed to the hole 31a of the installed bar 31 for preventing the opening.

【0055】爪20を回転して上側2層目5スパンの建枠
1の水平補剛材1aに掛止する。下側1層5スパンの布
枠3を取り外す。
The claw 20 is rotated and hooked on the horizontal stiffener 1a of the building frame 1 of the upper second layer and the fifth span. The lower one layer 5 span fabric frame 3 is removed.

【0056】図27に示すようにリフティングガータ9を
上昇し、2層5スパンを地上より20cm程度吊り上げ、下
側5スパンの交差筋違い2を取り外し、下側5スパンの
建枠1を取り外す。
As shown in FIG. 27, the lifting garter 9 is lifted, the two-layer five-span is lifted by about 20 cm from the ground, the cross braces 2 of the lower five spans are removed, and the building frame 1 of the lower five spans is removed.

【0057】図28に示すようにリフティングガータ9を
下降し、1層5スパンを地上に降ろす。爪20を回転して
建枠1の水平補剛材1aよりこの爪20を外し、3および
4スパンの建枠1に設置した開き止め用のバー31を撤去
する。1層5スパンを解体する。
As shown in FIG. 28, the lifting garter 9 is lowered to lower one layer and 5 spans to the ground. The claw 20 is rotated to remove the claw 20 from the horizontal stiffening member 1a of the building frame 1, and the bar 31 for preventing the opening installed on the building frame 1 of 3 and 4 spans is removed. Dismantle 5 spans per layer.

【0058】以下、同様の工程を繰り返して、順次最下
層の枠組足場を解体撤去し、最後に本発明の枠組足場の
昇降装置を撤去する。
Thereafter, the same steps are repeated to sequentially dismantle and remove the lowermost frame scaffold, and finally remove the frame scaffold lifting device of the present invention.

【0059】[0059]

【発明の効果】以上述べたように本発明の枠組足場の昇
降装置および枠組足場の組立・解体工法は、地上作業の
みで枠組足場の組立・解体ができるので、高所作業がな
くなるものである。その結果、作業員の墜落や足場材の
落下の危険性がなく安全性が向上するとともに、命綱で
拘束されることもないので楽に作業ができ、さらに、ク
レーンの設置も必要としないものである。
As described above, the method of assembling / disassembling a frame scaffold according to the present invention can assemble / disassemble the frame scaffold only by ground work, which eliminates work at height. . As a result, there is no risk of workers falling or scaffolding falling, and safety is improved, and since it is not restricted by a lifeline, it is easy to work, and it does not require the installation of a crane. .

【0060】また、作業スペースが固定して、多くのス
ペースを必要とすることもない。
Further, the working space is not fixed and a large amount of space is not required.

【0061】最上部になる部分に安全ネットや親綱支
柱、巾木などを最初から取り付けることができる。
A safety net, a main rope support, a skirting board, etc. can be attached to the uppermost portion from the beginning.

【0062】また、リフティングガータの昇降機構を、
回転駆動する転造ネジ軸とボールネジナットの組合せで
構成することで、繊細な動きにも対応できる確実な力強
い昇降動作が得られる。
Also, the lifting mechanism of the lifting gutter is
By using a combination of a rolling screw shaft that is driven to rotate and a ball screw nut, it is possible to obtain a reliable and strong lifting operation that can respond to delicate movements.

【0063】さらに、枠組足場に係脱可能な爪は、モー
タでチェーンを介して回動させることにより、単一の駆
動源で複数の爪を一度に同じ動作で回転駆動できる。
Further, the claws that can be engaged with and disengaged from the frame scaffold can be rotationally driven by a single drive source at the same time with the same operation by rotating the claws via a chain by a motor.

【0064】また、昇降装置自体をつなぎ材を介して構
造物にとめるようにすれば、転倒防止が得られる。
If the elevating device itself is fixed to the structure through the connecting member, the fall can be prevented.

【0065】さらに、枠組足場に設けるバーでリフティ
ングガータの開きを阻止するようにすれば、リフティン
グガータの爪の枠組足場への確実な掛止めが確保でき
る。
Further, if the bar of the frame scaffold is used to prevent the lifting gutter from opening, it is possible to ensure that the pawls of the lifting gutter are locked to the frame scaffold.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の枠組足場の昇降装置の1実施例を示す
要部の側面図である。
FIG. 1 is a side view of essential parts showing an embodiment of a lifting device for a framed scaffolding according to the present invention.

【図2】本発明の枠組足場の昇降装置の1実施例を示す
平面図である。
FIG. 2 is a plan view showing an embodiment of a lifting device for a frame scaffold according to the present invention.

【図3】本発明の枠組足場の昇降装置の1実施例を示す
側面図である。
FIG. 3 is a side view showing an embodiment of a lifting device for a framed scaffolding according to the present invention.

【図4】本発明の枠組足場の昇降装置の要部の平面図で
ある。
FIG. 4 is a plan view of a main part of a lifting device for a frame scaffold according to the present invention.

【図5】本発明の枠組足場の昇降装置のリフティングガ
ータの昇降機構の要部の側面である。
FIG. 5 is a side view of the main part of the lifting mechanism of the lifting gutter of the lifting device for a framed scaffold of the present invention.

【図6】本発明の枠組足場の昇降装置のリフティングガ
ータの爪の回転駆動機構の側面図である。
FIG. 6 is a side view of a rotation driving mechanism for a pawl of a lifting gutter of the lifting device for a framed scaffolding according to the present invention.

【図7】本発明の枠組足場の昇降装置のリフティングガ
ータの爪の回転駆動機構の平面図である。
FIG. 7 is a plan view of a rotation driving mechanism for a pawl of a lifting gutter of the lifting device for a framed scaffolding according to the present invention.

【図8】本発明の枠組足場の昇降装置のリフティングガ
ータの爪の回転駆動機構の他の部分の側面図である。
FIG. 8 is a side view of another portion of the rotary drive mechanism for the pawls of the lifting gutter of the lifting device for a framed scaffolding according to the present invention.

【図9】本発明の枠組足場の昇降装置のリフティングガ
ータの爪の回転駆動機構の他の部分平面図である。
FIG. 9 is another partial plan view of the rotation driving mechanism of the claw of the lifting gutter of the lifting device for the framed scaffolding of the present invention.

【図10】本発明の枠組足場の昇降装置のリフティング
ガータの昇降機構の伝達部材の1例を示す正面図であ
る。
FIG. 10 is a front view showing an example of a transmission member of the lifting mechanism of the lifting gutter of the lifting device for a framed scaffold of the present invention.

【図11】本発明の枠組足場の昇降装置のリフティング
ガータの昇降機構の伝達部材の1例を示す側面図であ
る。
FIG. 11 is a side view showing an example of a transmission member of the lifting mechanism of the lifting gutter of the lifting device for a framed scaffold of the present invention.

【図12】本発明の枠組足場の昇降装置のリフティング
ガータの昇降機構の伝達部材の他の1例を示す正面図で
ある。
FIG. 12 is a front view showing another example of the transmission member of the lifting mechanism of the lifting gutter of the lifting device for a framed scaffolding of the present invention.

【図13】本発明の枠組足場の昇降装置のリフティング
ガータの昇降機構の伝達部材の他の1例を示す側面図で
ある。
FIG. 13 is a side view showing another example of the transmission member of the lifting mechanism of the lifting gutter of the lifting device for a framed scaffold of the present invention.

【図14】本発明の枠組足場の昇降装置のリフティング
ガータの昇降機構の要部を示す一部切り欠いた斜視図で
ある。
FIG. 14 is a partially cutaway perspective view showing an essential part of the lifting mechanism of the lifting gutter of the lifting device for a framed scaffold of the present invention.

【図15】リフティングガータの開き防止用のバーを取
り付けた枠組足場の斜視図である。
FIG. 15 is a perspective view of a frame scaffolding to which a bar for preventing the lifting of the lifting gutter is attached.

【図16】本発明の枠組足場の組立工法の第1工程を示
す正面図である。
FIG. 16 is a front view showing a first step of the method for assembling the frame scaffold of the present invention.

【図17】本発明の枠組足場の組立工法の第2工程を示
す正面図である。
FIG. 17 is a front view showing a second step of the method for assembling the frame scaffold of the present invention.

【図18】本発明の枠組足場の組立工法の第3工程を示
す正面図である。
FIG. 18 is a front view showing a third step of the method for assembling the frame scaffold of the present invention.

【図19】本発明の枠組足場の組立工法の第4工程を示
す正面図である。
FIG. 19 is a front view showing a fourth step of the method for assembling the frame scaffold of the present invention.

【図20】本発明の枠組足場の組立工法の第5工程を示
す正面図である。
FIG. 20 is a front view showing a fifth step of the method for assembling the frame scaffold of the present invention.

【図21】本発明の枠組足場の組立工法の第6工程を示
す正面図である。
FIG. 21 is a front view showing a sixth step of the method for assembling the frame scaffold of the present invention.

【図22】本発明の枠組足場の解体工法の第1工程を示
す正面図である。
FIG. 22 is a front view showing a first step of the method for disassembling a frame scaffold of the present invention.

【図23】本発明の枠組足場の解体工法の第2工程を示
す正面図である。
FIG. 23 is a front view showing a second step of the method for disassembling a frame scaffold of the present invention.

【図24】本発明の枠組足場の解体工法の第3工程を示
す正面図である。
FIG. 24 is a front view showing a third step of the method for disassembling a frame scaffold of the present invention.

【図25】本発明の枠組足場の解体工法の第4工程を示
す正面図である。
FIG. 25 is a front view showing a fourth step of the method for disassembling a frame scaffold of the present invention.

【図26】本発明の枠組足場の解体工法の第5工程を示
す正面図である。
FIG. 26 is a front view showing a fifth step of the method for disassembling a frame scaffold of the present invention.

【図27】本発明の枠組足場の解体工法の第6工程を示
す正面図である。
FIG. 27 is a front view showing a sixth step of the method for disassembling a frame scaffold of the present invention.

【図28】本発明の枠組足場の解体工法の第7工程を示
す正面図である。
FIG. 28 is a front view showing a seventh step of the method for disassembling a frame scaffold of the present invention.

【図29】枠組足場の1セット分を示す斜視図である。FIG. 29 is a perspective view showing one set of frame scaffolds.

【図30】従来の枠組足場の組立て方法の第1工程を示
す斜視図である。
FIG. 30 is a perspective view showing a first step of a conventional method for assembling a frame scaffold.

【図31】従来の枠組足場の組立て方法の第2工程を示
す正面図である。
FIG. 31 is a front view showing a second step of the conventional method for assembling a frame scaffold.

【図32】従来の枠組足場の組立て方法の第3工程を示
す斜視図である。
FIG. 32 is a perspective view showing a third step of the conventional method for assembling a frame scaffold.

【図33】従来の枠組足場の解体方法の第1工程を示す
斜視図である。
FIG. 33 is a perspective view showing a first step of a conventional method for disassembling a frame scaffold.

【図34】従来の枠組足場の解体方法の第2工程を示す
斜視図である。
FIG. 34 is a perspective view showing a second step of the conventional method for disassembling a frame scaffold.

【符号の説明】[Explanation of symbols]

1…建枠 1a…水平補剛
材 2…交差筋違い 3…布枠 4…連結ピン 5…アームロッ
ク 6…親綱 7…ベース 8…マスト 9…リフティン
グガータ 10…昇降機構 11…転造ネジ軸 12…水平駆動軸 13…ギヤーボッ
クス 14…ギヤードモータ 15…スプロケッ
ト 16…ボールネジナット 18…キャスター 19…基台部 20…爪 21…ギヤードモ
ータ 22,23 …スプロケット 24…チェーン 25…つなぎ材 25a…ローラ 26…構造物 27…止め金具 28…傘歯車 29…ウォームギ
ヤ 30…平歯車 31…バー 31a…孔 32…ボルト 33…ピン 34…ボールベア
リング 35…手摺
1 ... Building frame 1a ... Horizontal stiffening material 2 ... Cross streaks 3 ... Cloth frame 4 ... Connecting pin 5 ... Arm lock 6 ... Parent rope 7 ... Base 8 ... Mast 9 ... Lifting gutter 10 ... Elevating mechanism 11 ... Rolling screw shaft 12 ... Horizontal drive shaft 13 ... Gear box 14 ... Geared motor 15 ... Sprocket 16 ... Ball screw nut 18 ... Caster 19 ... Base 20 ... Pawl 21 ... Geared motor 22,23 ... Sprocket 24 ... Chain 25 ... Binder 25a ... Roller 26 ... Structure 27 ... Stopper 28 ... Bevel Gear 29 ... Worm Gear 30 ... Spur Gear 31 ... Bar 31a ... Hole 32 ... Bolt 33 ... Pin 34 ... Ball Bearing 35 ... Handrail

───────────────────────────────────────────────────── フロントページの続き (71)出願人 000001373 鹿島建設株式会社 東京都港区元赤坂1丁目2番7号 (71)出願人 000001317 株式会社熊谷組 福井県福井市中央2丁目6番8号 (71)出願人 000167233 光洋機械産業株式会社 大阪府大阪市北区同心1丁目5番13号 (71)出願人 000166627 五洋建設株式会社 東京都文京区後楽2丁目2番8号 (71)出願人 000172813 佐藤工業株式会社 富山県富山市桜木町1番11号 (71)出願人 000182948 住金鋼材工業株式会社 兵庫県尼崎市扶桑町1番21号 (71)出願人 000183325 住友建設株式会社 東京都新宿区荒木町13番地の4 (71)出願人 000148346 株式会社銭高組 大阪府大阪市西区西本町2丁目2番11号 (71)出願人 000210883 中央ビルト工業株式会社 東京都中央区日本橋堀留町1丁目10番12号 (71)出願人 000219406 東亜建設工業株式会社 東京都千代田区四番町5 (71)出願人 000219875 東急建設株式会社 東京都渋谷区渋谷1丁目16番14号 (71)出願人 000166432 戸田建設株式会社 東京都中央区京橋1丁目7番1号 (71)出願人 000195971 西松建設株式会社 東京都港区虎ノ門1丁目20番10号 (71)出願人 000227146 日綜産業株式会社 東京都中央区日本橋蠣殻町1丁目10番1号 (71)出願人 000112668 株式会社フジタ 東京都渋谷区千駄ヶ谷四丁目6番15号 (71)出願人 591214804 株式会社松村組 大阪府大阪市北区東天満1丁目10番20号 (71)出願人 000174943 三井建設株式会社 東京都千代田区岩本町3丁目10番1号 (72)発明者 苗村 正三 茨城県つくば市大字旭1番地 建設省土木 研究所内 (72)発明者 青山 憲明 茨城県つくば市大字旭1番地 建設省土木 研究所内 (72)発明者 小川 敏治 東京都文京区音羽二丁目10番2号 財団法 人先端建設技術センター内 (72)発明者 福井 真男 大阪府大阪市中央区北浜東4番33号 株式 会社大林組内 (72)発明者 山口 善郷 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 池亀 弘基 東京都新宿区津久戸町2番1号 株式会社 熊谷組内 (72)発明者 上野 弘太 大阪府寝屋川市黒原新町9番7号 光洋機 械産業株式会社内 (72)発明者 江國 洋伸 東京都文京区後楽2丁目2番8号 五洋建 設株式会社内 (72)発明者 青木 勝郎 東京都中央区日本橋本町四丁目12番20号 佐藤工業株式会社内 (72)発明者 氏家 純一 東京都中央区八重洲2−2−1 住金鋼材 工業株式会社内 (72)発明者 会田 泰久 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 山花 豊 大阪府大阪市西区西本町2丁目2番11号 株式会社錢高組内 (72)発明者 北野 幸壯 東京都中央区日本橋堀留町1丁目10番12号 中央ビルト工業株式会社内 (72)発明者 小池 正 東京都千代田区四番町5 東亜建設工業株 式会社内 (72)発明者 加賀屋 智三 東京都渋谷区渋谷一丁目16番14号 東急建 設株式会社内 (72)発明者 青田 義輝 東京都中央区京橋一丁目7番1号 戸田建 設株式会社内 (72)発明者 渡辺 徹 神奈川県大和市下鶴間2570番地4 西松建 設株式会社技術研究所内 (72)発明者 鵜飼 敏宏 東京都中央区日本橋蛎殻町1丁目10番1号 日綜産業株式会社内 (72)発明者 井上 齊 東京都渋谷区千駄ヶ谷四丁目6番15号 株 式会社フジタ内 (72)発明者 三田村 健一 大阪府大阪市北区東天満1丁目10番20号 株式会社松村組内 (72)発明者 名草 俊比古 東京都千代田区岩本町三丁目10番1号 三 井建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (71) Applicant 000001373 Kashima Construction Co., Ltd. Moto Akasaka 1-2-7, Minato-ku, Tokyo (71) Applicant 000001317 Kumagai Gumi Co., Ltd. Fukui-shi Fukui-shi 2-6-8 (71) Applicant 000167233 Koyo Machine Industry Co., Ltd. 1-5-13, Doshin, Kita-ku, Osaka-shi, Osaka (71) Applicant 000166627 Goyo Construction Co., Ltd. 2-2-8, Koraku, Bunkyo-ku, Tokyo (71) Application People 000172813 Sato Industry Co., Ltd. 1-11 Sakuragicho, Toyama City, Toyama Prefecture (71) Applicant 000182948 Sumikin Steel Products Co., Ltd. 1-21 Fusocho, Amagasaki City, Hyogo Prefecture (71) Applicant 000183325 Sumitomo Construction Co., Ltd.Shinjuku, Tokyo 4 (71) Applicant 000148346, Arakicho, Tokyo 000148346 Zentakagumi Co., Ltd. 2-21-11 Nishi-Honmachi, Nishi-ku, Osaka-shi, Osaka (71) Applicant 000210883 Chuo Built Industrial Co., Ltd. Ceremony Company 1-10-12 Nihonbashi Horidomecho, Chuo-ku, Tokyo (71) Applicant 000219406 Toa Construction Industry Co., Ltd. 5 Yonbancho, Chiyoda-ku, Tokyo (71) Applicant 000219875 Tokyu Corporation 1 Shibuya, Shibuya-ku, Tokyo Chome 16-14 (71) Applicant 000166432 Toda Construction Co., Ltd. 1-7-1, Kyobashi, Chuo-ku, Tokyo (71) Applicant 000195971 Nishimatsu Construction Co., Ltd. 1-20-10 Toranomon, Minato-ku, Tokyo (71) Applicant 000227146 Nikkiso Sangyo Co., Ltd. 1-10-10 Nihonbashi Koshikaracho, Chuo-ku, Tokyo (71) Applicant 000112668 Fujita Co., Ltd. 4-6-15 Sendagaya, Shibuya-ku, Tokyo (71) Applicant 591214804 Co., Ltd. Matsumura Gumi 1-10-20 Higashitenma, Kita-ku, Osaka-shi, Osaka (71) Applicant 000174943 Mitsui Construction Co., Ltd. 3-101-1, Iwamoto-cho, Chiyoda-ku, Tokyo (72) Inventor Shozo Naemura Tsukuba, Ibaraki Asahi No. 1 Civil Engineering Research Institute, Ministry of Construction (72) Inventor Noriaki Aoyama No. 1 Asahi, Tsukuba City, Ibaraki Prefecture Civil Engineering Research Institute, Ministry of Land, Infrastructure and Construction (72) Inventor Toshiharu Ogawa 2-10-2 Otowa, Bunkyo-ku, Tokyo Inside Foundation for Advanced Construction Technology (72) Inventor Masao Fukui 4th Kitahama East, Chuo-ku, Osaka City, Osaka Prefecture No. 33 Stock Company Obayashi (72) Inventor Zengo Yamaguchi 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Hiroki Ikegame No. 2 Tsukudo-cho, Shinjuku-ku, Tokyo Stocks Company Kumagai Gumi (72) Inventor Kota Ueno 9-7 Kurohara Shinmachi, Neyagawa-shi, Osaka Koyo Kikai Sangyo Co., Ltd. (72) Innovator Hironobu Ekuni 2-8, Koraku, Bunkyo-ku, Tokyo Goyo Construction company (72) Inventor Katsuro Aoki 4-12-20 Nihonbashi Honcho, Chuo-ku, Tokyo Sato Kogyo Co., Ltd. (72) Inventor Junichi Ujiie 2-2-1 Yaesu, Chuo-ku, Tokyo Sumikin Steel Industrial Co., Ltd. In-house (72) Inventor Yasuhisa Aida 4 13 Araki-cho, Shinjuku-ku, Tokyo Sumitomo Construction Co., Ltd. (72) Inventor Yama Toyohashi 2-12-11 Nishihonmachi, Nishi-ku, Osaka-shi, Osaka (72) Inventor Koyuki Kitano 1-10-12 Nihonbashi-Horidome-cho, Chuo-ku, Tokyo Chuo-Built Kogyo Co., Ltd. (72) Inventor Tadashi Koike 5 Yonban-cho, Chiyoda-ku, Tokyo Toa Construction Industry Co., Ltd. (72) Inventor Tomomi Kagaya 1-16-14 Shibuya, Shibuya-ku, Tokyo Tokyu Construction Co., Ltd. (72) Inventor Yoshiteru Aota Tokyo 1-7-1 Kyobashi, Chuo-ku, Toda Construction Co., Ltd. (72) Inventor Toru Watanabe 2570 Shimotsuruma, Yamato City, Kanagawa Prefecture Nishimatsu Construction Co., Ltd. Technical Research Institute (72) Toshihiro Ukai Central Tokyo Nihonbashi, Kunigami-cho, 1-10-1 Nikko Sangyo Co., Ltd. (72) Inventor, Tetsu Inoue 4-6-15 Sendagaya, Shibuya-ku, Tokyo Fujita Co., Ltd. (72) Inventor Kenichi Mitamura Osaka, Osaka Matsumura Gumi Co., Ltd. 1-10-20 Higashitenma, Kita-ku, Japan (72) Inventor Shunbiko Iwa, Chiyoda-ku, Tokyo Town Third Street No. 10 No. 1 Mitsui Construction Co., Ltd.

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 地上に立設するマストに昇降機構を設
け、このマスト間に枠組足場に係脱可能な爪を有するリ
フティングガータを前記昇降機構で昇降自在に設けたこ
とを特徴とする枠組足場の昇降装置。
1. A frame scaffolding characterized in that an elevating mechanism is provided on a mast standing on the ground, and a lifting gutter having a claw that can be engaged with and disengaged from the frame scaffold is provided between the masts by the elevating mechanism. Lifting device.
【請求項2】 昇降機構は、モータで回転駆動する転造
ネジ軸にボールネジナットを螺合し、このボールネジナ
ットでリフティングガータを支承する請求項1記載の枠
組足場の昇降装置。
2. The elevating device for a frame scaffold according to claim 1, wherein the elevating mechanism has a ball screw nut screwed onto a rolling screw shaft that is rotationally driven by a motor, and the lifting gutter is supported by the ball screw nut.
【請求項3】 枠組足場に係脱可能な爪は、その回動軸
をリフティングガータに設けたモータでチェーンを介し
て回動させる請求項1または請求項2記載の枠組足場の
昇降装置。
3. The elevating device for a frame scaffold according to claim 1, wherein the pawl detachable from the frame scaffold is rotated by a motor provided on a lifting gutter via a chain.
【請求項4】 リフティングガータの側部から先端にロ
ーラを設けたつなぎ材を水平方向に突設し、構造物側に
設けたチャンネルレール状の止め金具にこのつなぎ材を
摺動自在に係合させる請求項1、請求項2または請求項
3のいずれかに記載の枠組足場の昇降装置。
4. A connecting member provided with a roller at its tip from a side portion of the lifting gutter projecting in the horizontal direction, and the connecting member is slidably engaged with a channel rail-shaped stopper provided on the structure side. The lifting device for a frame scaffold according to any one of claims 1, 2 and 3.
【請求項5】 リフティングガータの上面にピンを突設
し、このピンが挿入する孔を端部近くに設けたバーを枠
組足場の建枠に着脱自在に取り付ける請求項1乃至請求
項4いずれかに記載の枠組足場の昇降装置。
5. A bar provided with a pin protruding from the upper surface of the lifting gutter and having a hole into which the pin is inserted near the end is detachably attached to the building frame of the frame scaffold. Lifting device for the frame scaffold described in.
【請求項6】 枠組足場に係脱可能な爪を有するリフテ
ィングガータを地上に立設するマスト間に設けた昇降装
置を使用し、リフティングガータでその内部に組立てた
枠組足場の同一層の周囲を囲い、該枠組足場を掛止して
上昇させ、その下方に下層の枠組足場を組み、リフティ
ングガータを下降させて、この新たに組み立てた枠組足
場の同一層の周囲を囲い、該枠組足場を掛止して上昇さ
せ、以下同様の工程を繰り返して、順次枠組足場を多層
に組立てていくことを特徴とした枠組足場の組立工法。
6. A lifting girder provided between masts that vertically installs a lifting garter having detachable claws on the frame scaffold is used, and the same layer of the frame scaffold assembled inside the lifting gutter is surrounded by the lifting device. Enclose and raise the frame scaffolding, assemble the lower frame scaffolding below it and lower the lifting gata to enclose the same layer of this newly assembled frame scaffolding and suspend the frame scaffolding. A method for assembling frame scaffolds, characterized by stopping and raising, and then repeating the same steps to sequentially assemble the frame scaffolds in multiple layers.
【請求項7】 枠組足場の建枠の側部に先端にローラを
設けたつなぎ材を設け、構造物側に設けたチャンネルレ
ール状の止め金具にこのつなぎ材を摺動自在に係合させ
る請求項6記載の枠組足場の組立工法。
7. A connecting member provided with a roller at a tip thereof is provided on a side portion of a building frame of a frame scaffold, and the connecting member is slidably engaged with a channel rail-shaped stopper provided on the structure side. Item 6. A method for assembling a frame scaffold according to Item 6.
【請求項8】 枠組足場に係脱可能な爪を有するリフテ
ィングガータを地上に立設するマスト間に設けた昇降装
置を使用し、リフティングガータで多層に組立てた枠組
足場の下から2層目の周囲を囲い、該枠組足場を掛止し
て枠組足場全体を上昇させ、地上から浮いた最下層の枠
組足場を解体撤去し、リフティングガータを下降させ
て、下から2層目を地上に接地させ、リフティングガー
タを上昇させてその上の層を掛止して枠組足場全体を上
昇させ、以下、同様の工程を繰り返して、順次最下層の
枠組足場を解体撤去していくことを特徴とした枠組足場
の解体工法。
8. The second layer from the bottom of the frame scaffold assembled in multiple layers with the lifting gutter by using an elevating device provided between masts that vertically installs a lifting gutter having detachable claws on the frame scaffold. Enclose the perimeter, hook the frame scaffold to raise the entire frame scaffold, dismantle and remove the bottom frame scaffold floating from the ground, lower the lifting gata, and ground the second layer from the ground A framework characterized by lifting the lifting girder to lock the layers above it to raise the entire framework scaffolding, and then repeating the same process to dismantle and remove the bottommost framework scaffolding. Scaffold dismantling method.
JP7488795A 1995-03-31 1995-03-31 Lifting device of prefabricated scaffold and assembling and disassembling work thereof Pending JPH08270205A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7488795A JPH08270205A (en) 1995-03-31 1995-03-31 Lifting device of prefabricated scaffold and assembling and disassembling work thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7488795A JPH08270205A (en) 1995-03-31 1995-03-31 Lifting device of prefabricated scaffold and assembling and disassembling work thereof

Publications (1)

Publication Number Publication Date
JPH08270205A true JPH08270205A (en) 1996-10-15

Family

ID=13560337

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7488795A Pending JPH08270205A (en) 1995-03-31 1995-03-31 Lifting device of prefabricated scaffold and assembling and disassembling work thereof

Country Status (1)

Country Link
JP (1) JPH08270205A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264958A (en) * 2014-10-09 2015-01-07 浙江镜湖建设集团有限公司 Liftable equipment
JP2018004433A (en) * 2016-07-01 2018-01-11 日立Geニュークリア・エナジー株式会社 Vent device with filter and method of disposing thermal insulation material around vent device with filter

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264958A (en) * 2014-10-09 2015-01-07 浙江镜湖建设集团有限公司 Liftable equipment
JP2018004433A (en) * 2016-07-01 2018-01-11 日立Geニュークリア・エナジー株式会社 Vent device with filter and method of disposing thermal insulation material around vent device with filter

Similar Documents

Publication Publication Date Title
JP3172719B2 (en) Building construction safety fence
CN211923476U (en) Electric hoist lifting system attached to lifting scaffold
JP3179045B2 (en) Wall construction method with work scaffold
JP3579816B2 (en) Multipurpose stage for building frame
KR200430674Y1 (en) High place working gondola in building
JPH08270205A (en) Lifting device of prefabricated scaffold and assembling and disassembling work thereof
WO1992021838A1 (en) Work platform system for multi-storey buildings
CN210857952U (en) Novel attached lifting scaffold
KR20000009699A (en) Safety fence for construction
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
JP2004232366A (en) Suspended scaffolding
JP5150313B2 (en) Three-dimensional parking device in void and its construction method
CN116181041B (en) Building machine of multilayer quick construction
CN116335398B (en) Multilayer rapid construction method
JP2532116B2 (en) Lifting scaffolding
JP3241896B2 (en) Steel frame stair hang down method
CN217732381U (en) Elevator shaft with lifting platform
JPH08120936A (en) Method and device for constructing multistoried building
JPH09296610A (en) Outside curing unit
CN219569531U (en) Construction platform for additionally installing elevator
JPH06100020B2 (en) Scaffolding equipment
JP2003027740A (en) Self-ascending external scaffolding for building work
JP2843042B2 (en) Steel framing unit scaffolding method
JPH09310484A (en) Large space applicable suspended scaffold constructing system
KR20230054932A (en) Dropping prevention net mounted with climbing system and method for mounting the same

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19991130