JPH08245114A - Installation method of hydraulic elevator - Google Patents

Installation method of hydraulic elevator

Info

Publication number
JPH08245114A
JPH08245114A JP4734695A JP4734695A JPH08245114A JP H08245114 A JPH08245114 A JP H08245114A JP 4734695 A JP4734695 A JP 4734695A JP 4734695 A JP4734695 A JP 4734695A JP H08245114 A JPH08245114 A JP H08245114A
Authority
JP
Japan
Prior art keywords
jack
hoistway
hydraulic
workbench
plunger
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4734695A
Other languages
Japanese (ja)
Inventor
Yoshitaka Ando
善高 安東
Toshiyuki Tadokoro
俊之 田所
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Engineering and Service Co Ltd
Hitachi Building Systems Engineering Co Ltd
Original Assignee
Hitachi Building Systems Engineering and Service Co Ltd
Hitachi Building Systems Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Engineering and Service Co Ltd, Hitachi Building Systems Engineering Co Ltd filed Critical Hitachi Building Systems Engineering and Service Co Ltd
Priority to JP4734695A priority Critical patent/JPH08245114A/en
Publication of JPH08245114A publication Critical patent/JPH08245114A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE: To connect an upper part jack and a lower part jack to each other without requiring installation of a jig except for those jigs provided herewith by practicing processes of assembling a workbench attached on an upper part of a cage frame, etc., after providing a working floor on an upper part of an elevator shaft and centering and erecting a guide rail. CONSTITUTION: A working floor is at first assembled on an upper part of an elevator shaft 1, a lower part guide rail 9a is centered and erected on a wall surface of the elevator shaft 1 through a bracket 11 at the time of installing a hydraulic elevator. Thereafter, a cage frame 7 to engage with the lower part guide rail 9a and a workbench 24 attached on its upper part are assembled. Thereafter, a jack base 2 is centered and fixed on a lower part of the elevator shaft 1, a lower part jack 5b is erected on the jack base 2, an upper part jack 5a is temporarily placed on the lower part of the elevator shaft 1, and a pulley 12 is installed on a plunger 5d of the upper part jack 5a. Thereafter, the upper part jack 5a is lifted, the lower part jack 5b is rotated by the workbench 24 and the lower and upper part jacks 5b, 5a are connected to each other.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、乗かごのかご枠上部に
仮設される作業台を油圧ジャッキにより昇降させ、この
作業台から昇降路内の機器の設置作業を行う油圧エレベ
ータの据付方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of installing a hydraulic elevator, in which a workbench temporarily installed on the upper part of a car frame of a car is moved up and down by a hydraulic jack, and equipment in the hoistway is installed from this workbench. .

【0002】[0002]

【従来の技術】一般に油圧エレベータは、昇降路内に立
設される油圧ジャッキと、この油圧ジャッキ内を摺動す
るプランジャーの上端に装着され、一端が昇降路側、他
端が乗かご側に連結されるロープを備えたプーリーとを
有し、前記油圧ジャッキの動作に応じて前記ロープを介
して前記乗りかごを昇降させるようになっている。
2. Description of the Related Art Generally, a hydraulic elevator is mounted on a hydraulic jack standing upright in a hoistway and an upper end of a plunger sliding in the hydraulic jack, with one end on the hoistway side and the other end on the car side. And a pulley provided with a rope to be connected, and the carriage is moved up and down via the rope according to the operation of the hydraulic jack.

【0003】そして、このように構成される油圧エレベ
ータの据付方法は、例えば特開平2−204292号公
報に記載されるように、まず、前記昇降路の上部に作業
床を設け、ガイドレールの芯出しを行って昇降路内に立
設し、昇降路下部にかご枠を組み立てて前記ガイドレー
ルに係合させるとともに、前記かご枠上に作業台を付設
する。次いで、プランジャーレールを立設し、油圧ジャ
ッキの一方を構成する下部ジャッキを昇降路下部のジャ
ッキ台に仮固定するとともに、揚重手段に接続されると
ともに、回動可能に前記油圧ジャッキの他方を構成する
上部ジャッキを保持するガイド金具を、この上部ジャッ
キの上端に装着し、前記ガイド金具を前記プランジャー
レールに係合させ、前記揚重手段により前記上部ジャッ
キを前記プランジャーレールに沿って吊り上げ、この状
態で前記上部ジャッキを回転させて、この上部ジャッキ
と前記下部ジャッキとを連結して立設する。
In the hydraulic elevator installation method thus constructed, for example, as described in JP-A-2-204292, first, a work floor is provided above the hoistway, and a guide rail core is provided. Then, the car frame is taken out to stand upright in the hoistway, a car frame is assembled at the lower part of the hoistway and engaged with the guide rail, and a work table is attached on the car frame. Next, the plunger rail is erected, the lower jack constituting one of the hydraulic jacks is temporarily fixed to the jack base at the lower part of the hoistway, and the other one of the hydraulic jacks is rotatably connected to the lifting means. A guide metal fitting for holding the upper jack constituting the above is attached to an upper end of the upper jack, the guide metal fitting is engaged with the plunger rail, and the upper jack is moved along the plunger rail by the lifting means. The upper jack is rotated in this state by lifting, and the upper jack and the lower jack are connected to each other to stand upright.

【0004】この後、前記油圧ジャッキと油圧パワーユ
ニットとを油送管を介して接続するとともに、油圧パワ
ーユニットと工事用ケーブルを介して接続可能な仮設操
作盤を前記作業台に装着する。次いで、前記油圧ジャッ
キを上昇させ前記ガイド金具を取外し、また、前記プー
リーを前記油圧ジャッキの上部に取付け、このプーリー
へロープを巻き掛けるとともに、ロープの一端を昇降路
側、他端をかご枠側に固定する。しかる後、前記仮設操
作盤を操作して前記油圧ジャッキを作動させ、前記ロー
プを介して前記かご枠および作業台を昇降させる。そし
て、作業者は前記作業台から昇降路内の配線、配管等機
器の設置作業を行うようになっている。
After that, the hydraulic jack and the hydraulic power unit are connected via an oil feed pipe, and a temporary operation panel connectable to the hydraulic power unit via a construction cable is mounted on the workbench. Next, the hydraulic jack is lifted to remove the guide fitting, the pulley is attached to the upper part of the hydraulic jack, and the rope is wound around this pulley, and one end of the rope is on the hoistway side and the other end is on the car frame side. Fix it. Then, the temporary operation panel is operated to operate the hydraulic jack, and the car frame and the workbench are moved up and down via the rope. Then, the worker is to install equipment such as wiring and piping in the hoistway from the workbench.

【0005】[0005]

【発明が解決しようとする課題】ところで、前述した従
来の油圧エレベータの据付方法では、上部ジャッキと下
部ジャッキとを連結させる際、前記上部ジャッキを回動
可能に保持するガイド金具を要するが、このガイド金具
は本設品以外の治具となり、したがって、取外し作業を
要し作業行程の増加を招くものとなっている。
By the way, in the above-mentioned conventional hydraulic elevator installation method, when connecting the upper jack and the lower jack, a guide fitting for rotatably holding the upper jack is required. The guide metal fittings are jigs other than the main fittings, and therefore require removal work, resulting in an increase in work steps.

【0006】本発明はこのような従来技術における実情
に鑑みてなされたもので、その目的は、本設品以外の治
具の装着を要することなく上部ジャッキと下部ジャッキ
の連結を行うことができる油圧エレベータの据付方法を
提供することにある。
The present invention has been made in view of the situation in the prior art as described above, and an object thereof is to connect the upper jack and the lower jack without the need for mounting a jig other than the main component. It is to provide a method of installing a hydraulic elevator.

【0007】[0007]

【課題を解決するための手段】この目的を達成するため
に本発明は、昇降路内に立設される油圧ジャッキと、こ
の油圧ジャッキ内を摺動するプランジャーの上端に装着
されるプーリーと、このプーリーに巻き掛けられるロー
プの一端が連結されるかご枠とを有する油圧エレベータ
に用いられ、前記油圧ジャッキの動作に応じて前記ロー
プを介して前記かご枠を昇降させて昇降路内の機器の設
置作業を行う油圧エレベータの据付方法において、ま
ず、昇降路の上部に作業床を設け、この作業床で昇降路
頂部に設置した芯出し用のテンプレートから垂下させた
ピアノ線に基づいて、前記昇降路の下部に対となるガイ
ドレールを芯出して立設し、これらのガイドレールに係
合するかご枠、および、かご枠の上部に付設される作業
台を組み立て、次いで、前記油圧ジャッキの一方を構成
する下部ジャッキを前記昇降路の下部へ立設するととも
に、前記プーリーを、前記油圧ジャッキの他方を構成す
る上部ジャッキ内を摺動するプランジャーの上端に取り
付け、この後、前記上部ジャッキを吊り上げ、前記作業
台にて前記下部ジャッキを回転させてこの下部ジャッキ
と上部ジャッキとを連結し、次に、プランジャーレール
を吊り上げ、前記作業台から前記プランジャーレールへ
前記プーリーに備えられるガイド装置を係合させるとと
もに前記プランジャーレール下部を固定し、しかる後、
前記油圧ジャッキと油圧パワーユニットとを油送管を介
して接続し、前記油圧ジャッキを作動させて前記作業床
からロープを前記プーリーに掛けるとともに、このロー
プの一端を前記昇降路側、他端を前記かご枠側に取付
け、次いで、前記かご枠を昇降させて前記作業台から前
記昇降路内の機器の設置作業を行うようになっている。
In order to achieve this object, the present invention provides a hydraulic jack which is erected in the hoistway and a pulley which is mounted on the upper end of a plunger sliding in the hydraulic jack. , A device in a hoistway used for a hydraulic elevator having a car frame to which one end of a rope wound around this pulley is connected, and raising and lowering the car frame via the rope according to the operation of the hydraulic jack. In the installation method of the hydraulic elevator to perform the installation work, first, a work floor is provided on the upper part of the hoistway, and based on the piano wire hung from the centering template installed at the top of the hoistway on this work floor, Set up a pair of guide rails at the bottom of the hoistway, centering them upright, and assemble the car frame that engages with these guide rails and the workbench attached to the top of the car frame. A lower jack that constitutes one of the hydraulic jacks is erected at a lower portion of the hoistway, and the pulley is attached to an upper end of a plunger that slides in an upper jack that constitutes the other of the hydraulic jacks. After that, the upper jack is lifted, the lower jack is rotated on the workbench to connect the lower jack and the upper jack, then the plunger rail is lifted, and the workbench is moved from the workbench to the plunger rail. While engaging the guide device provided in the pulley and fixing the lower portion of the plunger rail, after that,
The hydraulic jack and the hydraulic power unit are connected via an oil feeding pipe, the hydraulic jack is operated to hang a rope from the working floor to the pulley, and one end of the rope is on the hoistway side and the other end is the car. It is attached to the frame side, and then the car frame is moved up and down to perform installation work of equipment in the hoistway from the work table.

【0008】[0008]

【作用】本発明は前記のように、まず、昇降路の上部に
作業床を設け、この作業床上にて昇降路頂部に設置した
芯出し用のテンプレートから垂下させたピアノ線に基づ
いて、前記昇降路の下部に対となるガイドレールを芯出
して立設し、これらのガイドレールに係合するかご枠、
および、かご枠の上部に付設される作業台を組み立て
る。次いで、下部ジャッキを前記昇降路の下部へ立設す
るとともに、プーリーを上部ジャッキ内を摺動するプラ
ンジャーの上端に取り付け、この後、前記上部ジャッキ
を吊り上げ、前記作業台にて前記下部ジャッキを回転さ
せてこの下部ジャッキと上部ジャッキとを連結する。
As described above, according to the present invention, first, the working floor is provided on the upper part of the hoistway, and based on the piano wire hung from the centering template installed on the top of the hoistway on the working floor, A pair of guide rails are centered and erected at the bottom of the hoistway, and a car frame that engages with these guide rails,
Also, assemble the work table attached to the top of the car frame. Next, the lower jack is erected at the lower part of the hoistway, and a pulley is attached to the upper end of the plunger that slides in the upper jack.After that, the upper jack is lifted and the lower jack is lifted on the work table. Rotate to connect the lower jack and the upper jack.

【0009】次に、プランジャーレールを吊り上げ、前
記作業台から前記プランジャーレールへ前記プーリーの
ガイド装置を係合させるとともに前記プランジャーレー
ル下部を固定する。しかる後、前記油圧ジャッキと油圧
パワーユニットとを油送管を介して接続し、前記油圧ジ
ャッキを作動させて前記作業床からロープを前記プーリ
ーに掛けるとともに、このロープの一端を前記昇降路
側、他端を前記かご枠側に取付ける。次いで、前記かご
枠を昇降させて前記作業台から前記昇降路内の機器の設
置作業を行うようになっている。
Next, the plunger rail is lifted, the guide device of the pulley is engaged with the plunger rail from the work table, and the lower portion of the plunger rail is fixed. Then, the hydraulic jack and the hydraulic power unit are connected via an oil feeding pipe, and the hydraulic jack is operated to hang a rope from the working floor to the pulley, and one end of the rope is connected to the hoistway side and the other end. To the car frame side. Next, the car frame is moved up and down, and the work for installing the equipment in the hoistway is performed from the work table.

【0010】このように、下部ジャッキを回転させてこ
の下部ジャッキと上部ジャッキとを連結することによ
り、本設品以外の治具の装着を要することなく油圧ジャ
ッキの取付けを行うことができる。
As described above, by rotating the lower jack and connecting the lower jack and the upper jack, the hydraulic jack can be attached without the need to mount a jig other than the main component.

【0011】[0011]

【実施例】以下、本発明の油圧エレベータの据付方法の
実施例を図に基づいて説明する。図1は本発明の油圧エ
レベータの据付方法の一実施例を示すフローチャート、
図2はプーリーと油圧ジャッキとの接続を説明する側面
図、図3は上部ジャッキと下部ジャッキとの接続を説明
する側面図、図4はガイドレールとプランジャーレール
との立設状態を示す側面図、図5はプーリーへのロープ
の巻き掛け作業を示す側面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a hydraulic elevator installation method according to the present invention will be described below with reference to the drawings. FIG. 1 is a flow chart showing an embodiment of a hydraulic elevator installation method according to the present invention.
2 is a side view for explaining the connection between the pulley and the hydraulic jack, FIG. 3 is a side view for explaining the connection between the upper jack and the lower jack, and FIG. 4 is a side view showing the standing state of the guide rail and the plunger rail. 5 and 6 are side views showing the operation of winding the rope around the pulley.

【0012】一般に油圧エレベータは図5に示すよう
に、昇降路1内下部のジャッキ台2に立設され、油送管
3を介して油圧パワーユニット4と接続される油圧ジャ
ッキ5と、油圧ジャッキ5の動作に応じてロープ6を介
して昇降路1内を昇降するかご枠7と、油圧ジャッキ5
の上下方向への動作を案内するプランジャーレール8
と、かご枠7の昇降を案内するガイドレール9と、プラ
ンジャーレール8を昇降路1に固定するブラケット10
と、ガイドレール9を昇降路1に固定するブラケット1
1とを有している。また、図3に示すように前記の油圧
ジャッキ5は上部ジャッキ5aと下部ジャッキ5bとに
分割可能であるとともに、シリンダ5cとその内部を摺
動するプランジャー5dとからなっており、プランジャ
ー5dの上部には、プランジャーレール8に係合可能な
図示しないガイド装置を備え、かつ、一端が昇降路1
側、他端がかご枠7側に連結されるロープ6が巻き掛け
られるプーリー12が取付けられている。なお、上部ジ
ャッキ5aのプランジャー5dと下部ジャッキ5bのプ
ランジャー5dとの接続合部には、互いに螺合する図示
しないねじ部がそれぞれ設けられている。
Generally, as shown in FIG. 5, a hydraulic elevator is provided upright on a jack stand 2 in the lower part of a hoistway 1 and connected to a hydraulic power unit 4 via an oil feed pipe 3, and a hydraulic jack 5. According to the operation of the car 6, the car frame 7 that moves up and down in the hoistway 1 via the rope 6, and the hydraulic jack 5
Plunger rail 8 for guiding the vertical movement of the
And a guide rail 9 for guiding the raising and lowering of the car frame 7, and a bracket 10 for fixing the plunger rail 8 to the hoistway 1.
And a bracket 1 for fixing the guide rail 9 to the hoistway 1.
1 and. Further, as shown in FIG. 3, the hydraulic jack 5 can be divided into an upper jack 5a and a lower jack 5b, and includes a cylinder 5c and a plunger 5d that slides inside the cylinder 5c. A guide device (not shown) engageable with the plunger rail 8 is provided on the upper part of the
A pulley 12 around which a rope 6 whose side and other ends are connected to the car frame 7 side is wound is attached. In addition, screw portions (not shown) that are screwed into each other are respectively provided at connection portions of the plunger 5d of the upper jack 5a and the plunger 5d of the lower jack 5b.

【0013】また、このように構成される油圧エレベー
タの据付時には図2に示すように、昇降路1の最上階位
置に組み立てられる作業床20と、昇降路1の上部に設
置される上部テンプレート21と、昇降路1の下部に設
置される下部テンプレート22と、作業床20の近傍に
取付けられ機器を揚重するチェーンブロック23と、か
ご枠7の上部に組み立てられる作業台24が配置され
る。
When the hydraulic elevator constructed as described above is installed, as shown in FIG. 2, a work floor 20 assembled at the uppermost floor position of the hoistway 1 and an upper template 21 installed at the upper part of the hoistway 1 are installed. A lower template 22 installed at the lower part of the hoistway 1, a chain block 23 mounted near the work floor 20 for hoisting equipment, and a work table 24 assembled on top of the car frame 7 are arranged.

【0014】この実施例にあっては、まず、手順S1と
して昇降路の上部に作業床20を組み立て、手順S2と
して作業床20の上方に上部テンプレート21、およ
び、昇降路1の下部に下部テンプレート22をそれぞれ
付設し、手順S3として上部テンプレート21と下部テ
ンプレート22との間に図示しないピアノ線を張設す
る。次いで、手順S4として前記のピアノ線に基づいて
昇降路の下部に対となる下部ガイドレール9aを芯出
し、昇降路1の壁面にブラケット11を介して立設し、
手順S5として下部ガイドレール9cに係合するかご枠
7を組み立てるとともに、手順S6としてかご枠7の上
部に付設される作業台24を組み立てる。
In this embodiment, first, as step S1, the work floor 20 is assembled on the upper part of the hoistway, and as step S2, the upper template 21 is arranged above the work floor 20 and the lower template is formed on the lower part of the hoistway 1. 22 is attached respectively, and a piano wire (not shown) is stretched between the upper template 21 and the lower template 22 in step S3. Next, as step S4, a pair of lower guide rails 9a are centered on the lower part of the hoistway based on the above-mentioned piano wire, and are erected on the wall surface of the hoistway 1 via brackets 11,
In step S5, the car frame 7 that engages with the lower guide rail 9c is assembled, and in step S6, the workbench 24 attached to the upper part of the car frame 7 is assembled.

【0015】次いで、手順S7としてジャッキ台2を昇
降路1下部へ芯出し固定し、このジャッキ台2へ下部ジ
ャッキ5bを立設するとともに、手順S8として上部ジ
ャッキ5aを昇降路1下部に仮置きし、図2に示すよう
にチェーンブロック23によりプーリー12を吊り上
げ、このプーリー12を上部ジャッキ5aのプランジャ
ー5dに取付け、この後、図3に示すようにチェーンブ
ロック23の取付けワイヤーを上部ジャッキ5aのシリ
ンダ5cへ取付け、このチェーンブロック23により上
部ジャッキ5aを下部ジャッキ5bの上方へ吊り上げ、
手順S9として作業台24にて下部ジャッキ5bを回転
させてこの下部ジャッキ5bと上部ジャッキ5aとを連
結し、芯出し固定する。
Next, in step S7, the jack base 2 is centered and fixed to the lower portion of the hoistway 1, and the lower jack 5b is erected on the jack base 2, and in step S8, the upper jack 5a is temporarily placed under the hoistway 1. Then, as shown in FIG. 2, the pulley 12 is hoisted by the chain block 23, the pulley 12 is attached to the plunger 5d of the upper jack 5a, and then the attachment wire of the chain block 23 is attached to the upper jack 5a as shown in FIG. Attached to the cylinder 5c, and the chain block 23 lifts the upper jack 5a above the lower jack 5b.
As step S9, the lower jack 5b is rotated on the workbench 24 to connect the lower jack 5b and the upper jack 5a, and centering and fixing.

【0016】次に、手順S10として図4に示すよう
に、上部ガイドレール9aをチェーンブロック23によ
り吊り上げ、作業台24にて中間部ガイドレール9bと
接続し、それをまた吊り上げ、既に芯出し固定されてい
る下部ガイドレール9cと接続し、ブラケット11を介
して昇降路1の壁面へ仮固定する。また、プランジャー
レール8をチェーンブロック23により吊り上げ、作業
台24にてプランジャーレール8へプーリー12に備え
られる図示しないガイド装置を係合させるとともに、こ
のプランジャーレール8をブラケット10を介して昇降
路1の壁面へ仮固定する。しかる後、手順S11として
油圧パワーユニット4を設置し、この油圧パワーユニッ
ト4と油圧ジャッキ5とを油送管3を介して接続し、か
つ、作業台24に図示しない仮設操作盤を装着し、この
仮設操作盤と油圧パワーユニット4との間に図示しない
工事用ケーブルを配設する。手順S12として図5に示
すように仮設操作盤を操作して油圧ジャッキ5を上昇さ
せ、手順S13として作業床24からロープ6をプーリ
ー12に掛けるとともに、このロープ12の一端を昇降
路1側、他端をかご枠7側に取付け、手順S14として
かご枠7を昇降させて作業台24からプランジャーレー
ル8およびガイドレール9の芯出し固定を順次、行う。
Next, as step S10, as shown in FIG. 4, the upper guide rail 9a is hoisted by the chain block 23, connected to the intermediate guide rail 9b at the workbench 24, and then hoisted again, and centered and fixed. It is connected to the lower guide rail 9c which is provided and is temporarily fixed to the wall surface of the hoistway 1 via the bracket 11. Further, the plunger rail 8 is lifted by the chain block 23, a guide device (not shown) provided on the pulley 12 is engaged with the plunger rail 8 at the work table 24, and the plunger rail 8 is moved up and down via the bracket 10. Temporarily fix it to the wall of Road 1. Then, in step S11, the hydraulic power unit 4 is installed, the hydraulic power unit 4 and the hydraulic jack 5 are connected via the oil feed pipe 3, and a temporary operation panel (not shown) is attached to the workbench 24 to perform the temporary installation. A construction cable (not shown) is arranged between the operation panel and the hydraulic power unit 4. In step S12, the temporary operation panel is operated to raise the hydraulic jack 5 as shown in FIG. 5, and in step S13, the rope 6 is hung from the work floor 24 on the pulley 12, and one end of the rope 12 is connected to the hoistway 1 side. The other end is attached to the car frame 7 side, and in step S14, the car frame 7 is moved up and down to sequentially perform centering and fixing of the plunger rail 8 and the guide rail 9 from the workbench 24.

【0017】次いで、手順S15として不必要となった
作業床20、上部テンプレート21および下部テンプレ
ート22を解体し、手順S16としてその他のエレベー
タの部品を取付け、手順S17として昇降路1内の配管
作業及び配線作業を行い、手順S18としてかご枠7の
上部に組み立てた作業台24を解体し、手順S19とし
て図示しない側板、天井等を装着して乗かごを組み立
て、手順S20として試運転、調整を行う。
Next, in step S15, the unnecessary work floor 20, upper template 21, and lower template 22 are dismantled, other elevator parts are attached in step S16, and piping work in the hoistway 1 is performed in step S17. Wiring work is performed, the workbench 24 assembled on the upper part of the car frame 7 is disassembled in step S18, a side plate (not shown), a ceiling, and the like are attached to assemble the car in step S19, and test operation and adjustment are performed in step S20.

【0018】このように構成した実施例では、下部ジャ
ッキ5bを回転させてこの下部ジャッキ5bと上部ジャ
ッキ5aとを連結することにより、本設品以外の治具の
装着を要することなく油圧ジャッキ5の取付けを行うこ
とができる。
In the embodiment constructed as described above, the lower jack 5b is rotated to connect the lower jack 5b and the upper jack 5a to each other, so that the hydraulic jack 5 does not need to be equipped with any jig other than the main component. Can be installed.

【0019】[0019]

【発明の効果】本発明は以上のように構成したので、本
設品以外の治具の装着を要することなく油圧ジャッキの
取付けを行うことができ、これによって、据付作業の行
程を低減させることができ、したがって、据付作業時間
の短縮、作業者の労力の低減を図ることができる。
EFFECTS OF THE INVENTION Since the present invention is constructed as described above, the hydraulic jack can be attached without the need to attach a jig other than the main component, thereby reducing the process of installation work. Therefore, it is possible to reduce the installation work time and the labor of the operator.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の油圧エレベータの据付方法の一実施例
を示すフローチャートである。
FIG. 1 is a flow chart showing an embodiment of a hydraulic elevator installation method according to the present invention.

【図2】プーリーと油圧ジャッキとの接続を説明する側
面図である。
FIG. 2 is a side view illustrating a connection between a pulley and a hydraulic jack.

【図3】上部ジャッキと下部ジャッキとの接続を説明す
る側面図である。
FIG. 3 is a side view illustrating a connection between an upper jack and a lower jack.

【図4】ガイドレールとプランジャーレールとの立設状
態を示す側面図である。
FIG. 4 is a side view showing an upright state of a guide rail and a plunger rail.

【図5】プーリーへのロープの巻き掛け作業を示す側面
図である。
FIG. 5 is a side view showing a work of winding a rope around a pulley.

【符号の説明】[Explanation of symbols]

1 昇降路 2 ジャッキ台 4 油圧パワーユニット 5 油圧ジャッキ 5a 上部ジャッキ 5b 下部ジャッキ 5c シリンダ 5d プランジャー 6 ロープ 7 かご枠 8 プランジャーレール 9 ガイドレール 12 プーリー 20 作業床 24 作業台 1 Hoistway 2 Jack stand 4 Hydraulic power unit 5 Hydraulic jack 5a Upper jack 5b Lower jack 5c Cylinder 5d Plunger 6 Rope 7 Car frame 8 Plunger rail 9 Guide rail 12 Pulley 20 Working floor 24 Working platform

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 昇降路内に立設される油圧ジャッキと、
この油圧ジャッキ内を摺動するプランジャーの上端に装
着されるプーリーと、このプーリーに巻き掛けられるロ
ープの一端が連結されるかご枠とを有する油圧エレベー
タに用いられ、前記油圧ジャッキの動作に応じて前記ロ
ープを介して前記かご枠を昇降させて昇降路内の機器の
設置作業を行う油圧エレベータの据付方法において、 まず、昇降路の上部に作業床を設け、この作業床上で昇
降路頂部に設置した芯出し用のテンプレートから垂下さ
せたピアノ線に基づいて、前記昇降路の下部に対となる
ガイドレールを芯出して立設し、これらのガイドレール
に係合するかご枠、および、かご枠の上部に付設される
作業台を組み立て、次いで、前記油圧ジャッキの一方を
構成する下部ジャッキを前記昇降路の下部へ立設すると
ともに、前記プーリーを、前記油圧ジャッキの他方を構
成する上部ジャッキ内を摺動するプランジャーの上端に
取り付け、この後、前記上部ジャッキを吊り上げ、前記
作業台にて前記下部ジャッキを回転させてこの下部ジャ
ッキと上部ジャッキとを連結し、次に、プランジャーレ
ールを吊り上げ、前記作業台から前記プランジャーレー
ルへ前記プーリーに備えられるガイド装置を係合させる
とともに前記プランジャーレール下部を固定し、しかる
後、前記油圧ジャッキと油圧パワーユニットとを油送管
を介して接続し、前記油圧ジャッキを作動させて前記作
業床からロープを前記プーリーに掛けるとともに、この
ロープの一端を前記昇降路側、他端を前記かご枠側に取
付け、次いで、前記かご枠を昇降させて前記作業台から
前記昇降路内の機器の設置作業を行うことを特徴とする
油圧エレベータの据付方法。
1. A hydraulic jack installed upright in the hoistway,
It is used in a hydraulic elevator having a pulley mounted on the upper end of a plunger that slides in the hydraulic jack and a car frame to which one end of a rope wound around the pulley is connected, and is used according to the operation of the hydraulic jack. In the installation method of the hydraulic elevator, in which the car frame is moved up and down via the rope to install the equipment in the hoistway, first, a work floor is provided on the upper part of the hoistway, and the work floor is installed on the top of the hoistway. Based on the piano wire hung from the installed centering template, a pair of guide rails are centered and erected at the lower part of the hoistway, and a car frame and a car are engaged with these guide rails. The workbench attached to the upper part of the frame is assembled, and then the lower jack that constitutes one of the hydraulic jacks is erected on the lower part of the hoistway and Is attached to the upper end of a plunger that slides in the upper jack that constitutes the other of the hydraulic jacks, then the upper jack is lifted, and the lower jack is rotated on the workbench to make the lower jack Connect the upper jack, then lift the plunger rail, engage the guide device provided on the pulley from the workbench to the plunger rail and fix the lower portion of the plunger rail, and then, A hydraulic jack and a hydraulic power unit are connected via an oil feeding pipe, the hydraulic jack is operated to hang a rope from the working floor to the pulley, and one end of the rope is on the hoistway side and the other end is the car frame. Side, and then raises and lowers the car frame to perform equipment installation work from the workbench in the hoistway. The method of mounting a hydraulic elevator, characterized and.
JP4734695A 1995-03-07 1995-03-07 Installation method of hydraulic elevator Pending JPH08245114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4734695A JPH08245114A (en) 1995-03-07 1995-03-07 Installation method of hydraulic elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4734695A JPH08245114A (en) 1995-03-07 1995-03-07 Installation method of hydraulic elevator

Publications (1)

Publication Number Publication Date
JPH08245114A true JPH08245114A (en) 1996-09-24

Family

ID=12772603

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4734695A Pending JPH08245114A (en) 1995-03-07 1995-03-07 Installation method of hydraulic elevator

Country Status (1)

Country Link
JP (1) JPH08245114A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6357556B1 (en) * 1997-03-07 2002-03-19 Kone Corporation Procedure and apparatus for the installation of an elevator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6357556B1 (en) * 1997-03-07 2002-03-19 Kone Corporation Procedure and apparatus for the installation of an elevator
US7559409B2 (en) 1997-03-07 2009-07-14 Kone Corporation Procedure and apparatus for the installation of an elevator

Similar Documents

Publication Publication Date Title
JPH0585681A (en) Elevator hoist way work platform and installation method for elevator system structual part
JPH08245114A (en) Installation method of hydraulic elevator
JP3155693B2 (en) Hydraulic elevator installation method
JPH09151053A (en) Fixing device for car of elevator
JP3347968B2 (en) Hydraulic elevator installation method
JP3348018B2 (en) Elevator installation method
JP2001335255A (en) Elevator installation construction method, and elevator installation unit
JP3193609B2 (en) Elevator installation method
JP2000169059A (en) Installation method of elevator
JP2000226169A (en) Elevator erection method
JPH05319729A (en) Attaching work device of guide rail of elevator and attaching work method of guide rail using that device
JP3214325B2 (en) Elevator installation method
JP3301948B2 (en) Elevator installation method
JP2674392B2 (en) Hydraulic elevator installation method
JPH082850A (en) Work method in elevator shaft
JP2939064B2 (en) Elevator installation template
JP3378806B2 (en) Elevator installation method
JP2877593B2 (en) Elevator installation method
JPH021066B2 (en)
JPH0741746Y2 (en) Elevator installation device
JPH11292424A (en) Installation method for small size elevator
JP2003034473A (en) Elevator installing method
JPH10167613A (en) Installation device for elevator guide rail
JPH07206314A (en) Installing method for elevator