JPH08239950A - Slab-opening curing reinforcement - Google Patents

Slab-opening curing reinforcement

Info

Publication number
JPH08239950A
JPH08239950A JP18510895A JP18510895A JPH08239950A JP H08239950 A JPH08239950 A JP H08239950A JP 18510895 A JP18510895 A JP 18510895A JP 18510895 A JP18510895 A JP 18510895A JP H08239950 A JPH08239950 A JP H08239950A
Authority
JP
Japan
Prior art keywords
parallel
hole
moving
reinforcing bar
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP18510895A
Other languages
Japanese (ja)
Other versions
JP3084349B2 (en
Inventor
Takuji Ono
拓司 大野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
AKUSU KK
Original Assignee
AKUSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by AKUSU KK filed Critical AKUSU KK
Priority to JP07185108A priority Critical patent/JP3084349B2/en
Publication of JPH08239950A publication Critical patent/JPH08239950A/en
Application granted granted Critical
Publication of JP3084349B2 publication Critical patent/JP3084349B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

PURPOSE: To improve workability by installing moving reinforcements, in which both ends are engaged slidably with a first parallel member arranged into the opening section of a hole for construction works and a second parallel member disposed in the direction different from the first parallel member respectively. CONSTITUTION: When concrete is placed on a floor board, anchors 4 projected to the outsides of form reinforcements 1 are combined with the concrete of the floor board, and a first parallel reinforcement 3 and a second parallel reinforcement 6 are fixed firmly onto the floor board. Since concrete is not flowed into the reinforcements 1 at that time, a hole for construction works is formed inside the reinforcements 1. First moving reinforcements 5 and second moving reinforcements 7 are slid to ends and the hole for construction works is bored at the time of requirement for construction works. When construction works are completed and concrete is poured into the hole for construction works and the hole is buried, the reinforcements 5, 7 are arranged at a regular interval so as to be fitted to concete placing. Accordingly, the reinforcements can be arranged simultaneously to the floor board and the hole for construction works, and the strength of the reinforcements can be increased, and the mounting and dismounting of the forms of the hole for construction works can be unnecessitated.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、鉄筋コンクリー
ト構造の床板に形成された工事用穴を工事終了時に鉄筋
コンクリートで埋めるためのスラブ開口養生鉄筋に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slab opening curing rebar for filling work holes formed in a floorboard of a reinforced concrete structure with reinforced concrete at the end of work.

【0002】[0002]

【従来の技術】鉄筋コンクリートの建築物を施工する際
には、床下において各種の工事を行うために、鉄筋コン
クリート構造の床板(スラブ)に通称「だめ穴」と呼ば
れる工事用穴をあけておく場合がある。
2. Description of the Related Art When constructing a reinforced concrete building, in order to perform various constructions under the floor, there are cases in which a construction hole commonly referred to as a "hole" is made in a reinforced concrete floor plate (slab). is there.

【0003】そこで、そのような工事用穴を形成するた
めに、工事用穴になる部分には床板用の鉄筋を張らずに
工事用穴の形に型枠を設置して、その型枠の周囲にコン
クリートを流し込んでいる。
Therefore, in order to form such a construction hole, a formwork is installed in the shape of the construction hole without installing a reinforcing bar for the floor plate in the portion to be the construction hole, and Concrete is poured around.

【0004】そして、工事中は工事用穴の開口を鉄板等
で塞いでおいて必要な時にはそれを開き、工事終了時
に、工事用穴に鉄筋を張ってからコンクリートを流し込
んで穴を埋めている。
During construction, the opening of the construction hole is closed with an iron plate or the like and opened when necessary, and at the end of the construction, reinforcing bars are stretched in the construction hole and then concrete is poured to fill the hole. .

【0005】[0005]

【発明が解決しようとする課題】しかし上述のような工
程では、床板に鉄筋を張ってコンクリートを打ち、その
後、また工事用穴の部分にだけ鉄筋を張る工事をしなけ
ればならないので、はなはだ面倒である。
[Problems to be Solved by the Invention] However, in the above-mentioned process, since it is necessary to stretch the floor plate with the reinforcing rod to hit the concrete, and then to construct the reinforcing rod only in the construction hole, it is troublesome. Is.

【0006】そして、工事用穴の部分に張られる鉄筋は
最初に床板の本体部分に打たれたコンクリートと結合し
ていないので、工事用穴を埋めた部分の強度が低くなる
ことは避けられない。
[0006] Since the reinforcing bars stretched over the construction holes are not joined to the concrete that was first struck in the main body of the floorboard, it is unavoidable that the strength of the construction holes is reduced. .

【0007】また、工事用穴を形成するために、最初の
コンクリート打ちの際に工事用穴の形状の型枠を配置し
て、コンクリート打ちが済んだらその型枠を取り除かな
ければならないので、その点でも工事が面倒である。
Further, in order to form the construction holes, it is necessary to arrange a formwork having the shape of the construction hole at the time of first concrete pouring, and to remove the formwork after the concrete pouring is completed. Construction is also troublesome.

【0008】そこで本発明は、工事用穴の形成と穴埋め
を簡単な工程で行うことができ、しかも穴埋め部分につ
いて優れた強度を得ることができるスラブ開口養生鉄筋
を提供することを目的とする。
[0008] Therefore, an object of the present invention is to provide a slab opening curing reinforcing bar capable of forming a work hole and filling the hole in a simple process and obtaining excellent strength in the hole filling portion.

【0009】[0009]

【課題を解決するための手段】上記の目的を達成するた
め、本発明のスラブ開口養生鉄筋は、鉄筋コンクリート
構造の床板に形成された工事用穴を工事終了時に鉄筋コ
ンクリートで埋めるためのスラブ開口養生鉄筋であっ
て、上記工事用穴内に設置されてその穴の開口部側から
見て平行に略真っ直ぐに配置された第1の平行部材と、
両端が上記第1の平行部材に対してスライド自在に係合
する一本又は複数の第1の移動鉄筋と、上記工事用穴内
に設置されてその穴の開口部側から見て上記第1の平行
部材と異なる方向に平行に略真っ直ぐに配置された第2
の平行部材と、両端が上記第2の平行部材に対してスラ
イド自在に係合して上記工事用穴の開口部側から見て上
記第1の移動鉄筋の移動範囲と重なる移動範囲を有する
一本又は複数の第2の移動鉄筋とを設けたことを特徴と
する。
In order to achieve the above object, a slab opening curing reinforcing bar of the present invention is a slab opening curing reinforcing bar for filling a construction hole formed in a floor plate of a reinforced concrete structure with reinforced concrete at the end of construction. A first parallel member installed in the construction hole and arranged substantially straight in parallel when viewed from the opening side of the hole;
One or a plurality of first moving rebars having both ends slidably engaged with the first parallel member, and the first moving rebar installed in the construction hole and viewed from the opening side of the hole. The second member arranged substantially straight in parallel to the direction different from the parallel member
And a moving range overlapping both ends of the first moving rebar when viewed from the opening side of the construction hole so that both ends are slidably engaged with the second parallel member. A book or a plurality of second moving reinforcing bars is provided.

【0010】第1の移動鉄筋はその両端部で第1の平行
部材に対してスライドし、第2の移動鉄筋はその両端部
で第2の平行部材に対してスライドする。そして、両移
動鉄筋の移動範囲は工事用穴の開口部側から見て重なる
部分がある。
The first moving reinforcing bar slides at its both ends with respect to the first parallel member, and the second moving reinforcing bar slides at its both ends with respect to the second parallel member. Then, the moving range of both moving reinforcing bars has a portion overlapping when viewed from the opening side of the construction hole.

【0011】したがって、スラブ開口養生鉄筋を工事用
穴内に設置して両移動鉄筋を移動させることにより、工
事に必要なときは両移動鉄筋を端へスライドさせて穴を
開き、工事用穴にコンクリートを流し込んで埋める際に
は、両移動鉄筋を等間隔に並べて配置することができ
る。
Therefore, by installing a slab opening curing rebar in the construction hole and moving both moving rebars, when necessary for construction, both moving rebars are slid to the end to open a hole, and the concrete is put in the construction hole. When pouring and filling, both moving rebars can be arranged side by side at equal intervals.

【0012】なお、上記第1及び第2の平行部材が鉄筋
であってもよく、その鉄筋の少なくとも一方の延長部
に、上記工事用穴の外側に突出するアンカー部が形成さ
れていてもよい。
The first and second parallel members may be rebars, and at least one extension of the rebars may be formed with an anchor portion projecting to the outside of the construction hole. .

【0013】また、上記平行部材が板状の部材であり、
上記工事用穴の外側に突出するアンカー部材の基部が上
記各板状部材に連結されていてもよく、上記各板状部材
から側方に適宜の間隔で上記アンカー部材が突出するよ
うに、上記各板状部材に対して複数のアンカー部材が連
結されていてもよい。
The parallel member is a plate-shaped member,
The base portion of the anchor member projecting outside of the construction hole may be connected to each of the plate members, and the anchor member projects laterally from each of the plate members at appropriate intervals. A plurality of anchor members may be connected to each plate member.

【0014】また、上記床板にコンクリートを流す際に
上記工事用穴の内周面となる部分に配置されて型枠とし
て機能する複数の鉄筋が、上記第1及び第2の平行部材
と連結して設けられていてもよく、上記型枠として機能
する鉄筋に、上記工事用穴の外側に突出するフック部が
突出形成されていてもよい。
Further, a plurality of reinforcing bars arranged at the inner peripheral surface of the construction hole when concrete is poured onto the floor plate and functioning as a formwork are connected to the first and second parallel members. Or a hook portion protruding outside the construction hole may be formed on the reinforcing bar functioning as the mold.

【0015】[0015]

【発明の実施の形態】図面を参照して実施の形態を説明
する。図1は、鉄筋コンクリート構造の床板に形成され
た工事用穴を工事終了時に鉄筋コンクリートで埋めるた
めのスラブ開口養生鉄筋の第1の実施の形態を示してお
り、その外周部には、床板にコンクリートを流す際に工
事用穴の内周面となる部分に配置されて型枠として機能
する複数の鉄筋1…(以下、「型枠鉄筋1」という)が
配置されている。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments will be described with reference to the drawings. FIG. 1 shows a first embodiment of a slab opening curing reinforcing bar for filling a construction hole formed in a floor plate of a reinforced concrete structure with reinforced concrete at the time of completion of the construction, and a concrete slab on the floor plate is provided on the outer peripheral portion thereof. A plurality of rebars 1 ... (Hereinafter, referred to as “form frame rebar 1”) are arranged in a portion which becomes an inner peripheral surface of a construction hole when flowing, and function as a formwork.

【0016】型枠鉄筋1…は、図2に分解して図示され
るように、U字形の一対の鉄筋を互いの開放端どうしで
溶接して長方形のリング状に形成し、その長方形状の鉄
筋を複数段(例えば5〜6段)積み重ねて形成されてい
る。
As shown in the exploded view of FIG. 2, the formwork rebars 1 ... Form a rectangular ring shape by welding a pair of U-shaped rebars at their open ends, and then the rectangular shape It is formed by stacking a plurality of reinforcing bars (for example, 5 to 6 steps).

【0017】各型枠鉄筋1…は、中央の溶接部だけが部
分的に上下に重ね合わされているので、それ以外の部分
では、各型枠鉄筋1…の間に各々鉄筋一本分の隙間が形
成されている。
In each of the formwork rebars 1 ..., only the central welded portion is partially overlapped vertically, so that in the other portions, a space for one rebar is provided between the formwork rebars 1 ... Are formed.

【0018】そして各型枠鉄筋1は、図1に示されるよ
うに、四隅に立設された支柱鉄筋2…に溶接されて固定
されている。なお、各支柱鉄筋2…の頂部は一番上の型
枠鉄筋1より少し上方に突出するようになっている。
As shown in FIG. 1, each formwork rebar 1 is welded and fixed to pillar rebars 2 ... Standing at four corners. In addition, the tops of the pillar rebars 2 ... Project slightly above the uppermost formwork rebar 1.

【0019】3は、工事用穴内に設置されてその穴の開
口部側(上方)から見て平行に略真っ直ぐに配置された
第1の平行鉄筋であり、型枠鉄筋1の両側の長辺のすぐ
内側に各々配置されていて、上方に配置されている二本
の型枠鉄筋1,1の隙間から外側に突出し、そこで支柱
鉄筋2に溶接されている。
Reference numeral 3 denotes a first parallel rebar installed in the construction hole and arranged substantially straight in parallel when viewed from the opening side (upper side) of the hole, and has long sides on both sides of the formwork rebar 1. Of the two form rebars 1, 1 which are respectively arranged immediately inside of the above, and which protrude outward from the gap between the two form frame rebars 1 and 1 which are welded to the column rebars 2.

【0020】この溶接部分からさらに外側に伸び出した
部分は、床板のコンクリート打ちの時にそのコンクリー
トと結合するアンカー部4であり、このアンカー部4が
床板のコンクリートと結合することにより、第1の平行
鉄筋3が床板と強力に一体化される。
The portion extending further outward from the welded portion is an anchor portion 4 that is joined to the concrete when the floor board is concrete-cast, and the anchor portion 4 is joined to the concrete of the floor board to form the first portion. The parallel reinforcing bars 3 are strongly integrated with the floor board.

【0021】この第1の平行鉄筋3に対して直角に配置
された第1の移動鉄筋5は、両端部が各々J字状に曲げ
られていて、その部分が第1の平行鉄筋3を緩く囲むよ
うに配置されている。図3は、第1の平行鉄筋3と第1
の移動鉄筋5だけに斜線を施したものである。
The first moving rebars 5 arranged at right angles to the first parallel rebars 3 have both ends bent in J-shapes, and the portions loosen the first parallel rebars 3. It is arranged so as to surround it. FIG. 3 shows the first parallel reinforcing bar 3 and the first parallel reinforcing bar 3.
The moving rebar 5 of FIG.

【0022】したがって、第1の移動鉄筋5は両端が第
1の平行鉄筋3に対してスライド自在に係合しており、
第1の平行鉄筋3に沿って、図3の矢印A方向に自由に
スライドさせることができる。第1の移動鉄筋5はこの
実施の形態では8本設けられているが、工事用穴の大き
さ等に対応して、1本以上何本に設定してもよい。
Therefore, both ends of the first moving reinforcing bar 5 are slidably engaged with the first parallel reinforcing bar 3,
It can be freely slid along the first parallel rebar 3 in the direction of arrow A in FIG. Although eight first moving reinforcing bars 5 are provided in this embodiment, one or more first moving reinforcing bars 5 may be set depending on the size of the construction hole or the like.

【0023】図1に戻って、6は、工事用穴内に設置さ
れてその穴の開口部側から見て第1の平行鉄筋3と直角
の向きに配置された第2の平行鉄筋であり、型枠鉄筋1
の両側の短辺のすぐ内側に各々配置されていて、下方に
配置されている二本の型枠鉄筋1,1の隙間から外側に
突出し、そこで支柱鉄筋2に溶接されている。その延長
部分もアンカー部4である。
Returning to FIG. 1, reference numeral 6 denotes a second parallel reinforcing bar which is installed in the construction hole and is arranged at a right angle to the first parallel reinforcing bar 3 when viewed from the opening side of the hole, Formwork rebar 1
Of the two form rebars 1 and 1 which are respectively arranged just inside the short sides on both sides of the above, and which protrude outward from the gap between the two formwork rebars 1 and 1 arranged below and are welded to the column rebars 2. The extended portion is also the anchor portion 4.

【0024】この第2の平行鉄筋6に対して直角に配置
された第2の移動鉄筋7は、第1の移動鉄筋5と同様に
両端部が各々J字状に曲げられて、その部分が第2の平
行鉄筋6を緩く囲むように配置されている。図4は、第
2の平行鉄筋6と第2の移動鉄筋7だけに斜線を施した
ものである。
The second moving reinforcing bar 7 arranged at a right angle to the second parallel reinforcing bar 6 has its both ends bent in a J-shape like the first moving reinforcing bar 5 and its portion is bent. It is arranged so as to loosely surround the second parallel reinforcing bars 6. In FIG. 4, only the second parallel reinforcing bars 6 and the second moving reinforcing bars 7 are shaded.

【0025】したがって、第2の移動鉄筋7は両端が第
2の平行鉄筋6に対してスライド自在に係合しており、
第2の平行鉄筋6に沿って、図4の矢印B方向に自由に
スライドさせることができる。第2の移動鉄筋7はこの
実施の形態では4本設けられているが、工事用穴の大き
さ等に対応して、1本以上何本に設定してもよい。
Therefore, both ends of the second movable reinforcing bar 7 are slidably engaged with the second parallel reinforcing bar 6,
It can be freely slid along the second parallel reinforcing bar 6 in the direction of arrow B in FIG. In this embodiment, four second movable reinforcing bars 7 are provided, but one or more may be set depending on the size of the construction hole or the like.

【0026】なお、アンカー部4はこの実施の形態にお
いてはJ字状に曲げられているが、真っ直ぐでもよく、
あるいは他の各種形状に形成してもよい。また、第1及
び第2の平行鉄筋3,6は単線でも撚り線でもよい。
Although the anchor portion 4 is bent in a J shape in this embodiment, it may be straight.
Alternatively, it may be formed in various other shapes. The first and second parallel reinforcing bars 3 and 6 may be single wires or stranded wires.

【0027】このようにして、型枠鉄筋1の内側のほぼ
全範囲において第1と第2の移動鉄筋5,7を直角方向
に自由にスライドさせることができる。したがって、第
1と第2の移動鉄筋5,7をともに外方に寄せれば、図
5に示されるように、型枠鉄筋1内に大きな開口が形成
される。
In this manner, the first and second moving reinforcing bars 5 and 7 can be freely slid in the right angle direction in almost the entire area inside the form rebar 1. Therefore, if both the first and second moving reinforcing bars 5 and 7 are moved outward, a large opening is formed in the form frame reinforcing bar 1 as shown in FIG.

【0028】上述のように構成されたスラブ開口養生鉄
筋は、床板にコンクリート打ちを行う際に、工事用穴を
形成する部分に設置される。そして、型枠鉄筋1が、工
事用穴を形成するための型枠になる。
The slab opening curing reinforcing bar constructed as described above is installed in a portion forming a construction hole when concrete is poured into a floorboard. And the formwork rebar 1 becomes a formwork for forming the construction hole.

【0029】そして、床板にコンクリート打ちをする
と、型枠鉄筋1の外側に突出するアンカー部4が床板の
コンクリートと結合して平行鉄筋3,6が床板と強力に
一体化され、平行鉄筋3,6の固定状態に優れた強度が
得られる。そして、型枠鉄筋1の内側にはコンクリート
が流れ込まないので、そこに工事用穴が形成される。
Then, when concrete is poured on the floor plate, the anchor portion 4 projecting to the outside of the form rebar 1 is connected to the concrete of the floor plate, and the parallel rebars 3 and 6 are strongly integrated with the floor plate. 6 has excellent strength in the fixed state. Then, since concrete does not flow into the inside of the form rebar 1, a construction hole is formed there.

【0030】そして、両移動鉄筋5,7をスライドさせ
ることにより、工事に必要なときは両移動鉄筋5,7を
端へスライドさせて穴を開き、工事が終了して工事用穴
にコンクリートを流し込んで埋める際には、両移動鉄筋
5,7をコンクリート打ちに適するように等間隔に並べ
て配置することができる。その時、型枠鉄筋1は工事用
穴内にいっしょに埋め込まれる。
Then, by sliding both moving rebars 5 and 7, when necessary for construction, both moving rebars 5 and 7 are slid to the end to open a hole, and when the construction is completed, concrete is put in the working hole. When pouring and filling, both moving rebars 5 and 7 can be arranged at equal intervals so as to be suitable for concrete pouring. At that time, the formwork rebar 1 is embedded together in the construction hole.

【0031】また、工事用穴を利用した工事のない状態
のときは、図6に示されるように、型枠鉄筋1の上に養
生蓋10を被せておけばよく、支柱鉄筋2の上端が型枠
鉄筋1の上端より突出しているので、養生蓋10の足1
0aが支柱鉄筋2に係合して、養生蓋10の位置ずれを
防止することができる。
Further, when there is no construction using the construction holes, it is sufficient to cover the form rebar 1 with the curing lid 10 as shown in FIG. Since it protrudes from the upper end of the formwork rebar 1, the foot 1 of the curing lid 10
It is possible to prevent the position shift of the curing lid 10 by engaging the support rod 0 with 0a.

【0032】図7ないし図10は、本発明の第2の実施
の形態を示しており、図7はスラブ開口養生鉄筋の平面
図、図8はその正面断面図である。ただし、図8は、判
りやすくするために実際より縦長に図示されている。
7 to 10 show a second embodiment of the present invention. FIG. 7 is a plan view of a slab opening curing reinforcing bar and FIG. 8 is a front sectional view thereof. However, FIG. 8 is illustrated vertically longer than it actually is for the sake of clarity.

【0033】この実施の形態の特徴は、第1及び第2の
移動鉄筋15,17の両端をスライド自在に支えている
のが、例えば鉄板により形成された第1及び第2の平行
板13,16であり、アンカー鉄筋14…が、床板のコ
ンクリート中に所定の間隔で網目状に張られているスラ
ブ鉄筋100…に対応して、4枚の平行鉄板13,16
の各外面に多数突設されている点である。
A feature of this embodiment is that both ends of the first and second moving reinforcing bars 15 and 17 are slidably supported. For example, the first and second parallel plates 13 and 13 are formed of iron plates. 16 and the anchor rebars 14 ... Corresponding to the slab rebars 100 ... stretched in the concrete of the floorboard at predetermined intervals in a mesh shape, the four parallel steel plates 13, 16
The point is that a large number are projected on each outer surface.

【0034】第1の平行鉄板13は、図9の斜視図にも
示されるように横長の向きに立てて配置されていて、第
1の移動鉄筋15の一端部をスライド自在に係合させる
ための溝18が水平方向に形成されている。
As shown in the perspective view of FIG. 9, the first parallel iron plate 13 is arranged in an upright orientation so that one end of the first moving rebar 15 can be slidably engaged. Groove 18 is formed in the horizontal direction.

【0035】第1の平行鉄板13からは、上下2列に各
5本ずつのアンカー鉄筋14…が、スラブ鉄筋100…
の位置に対応するように外方に向けて突出しており、各
アンカー鉄筋14…の根部は第1の平行鉄板13に溶接
固定されている。なお、この実施の形態においては、ア
ンカー鉄筋14…の基端部にナットが螺合されていて、
第1の平行鉄板13に対して組み付け易くなっている。
From the first parallel iron plate 13, there are five anchor rebars 14 in upper and lower two rows, and slab rebars 100.
Of the anchor rebars 14 ... Are fixed to the first parallel iron plate 13 by welding. In addition, in this embodiment, a nut is screwed to the base end portion of the anchor reinforcing bar 14 ...
It is easy to assemble to the first parallel iron plate 13.

【0036】そして、一対の第1の平行鉄板13が平行
に配置されていて、各第1の平行鉄板13の側端面13
aが型枠鉄筋1の内周面部分に溶接固定されている。一
対の第2の平行鉄板16も同様に構成されていて、その
側端面が第1の平行鉄板13に溶接固定されている。図
8に示される19は、第2の移動鉄筋17をスライド自
在に係合させるために、第2の平行鉄板16に形成され
た溝である。
The pair of first parallel iron plates 13 are arranged in parallel, and the side end faces 13 of each of the first parallel iron plates 13 are arranged.
a is welded and fixed to the inner peripheral surface portion of the form rebar 1. The pair of second parallel iron plates 16 are also configured in the same manner, and their side end faces are welded and fixed to the first parallel iron plates 13. Reference numeral 19 shown in FIG. 8 is a groove formed in the second parallel iron plate 16 in order to slidably engage the second moving reinforcing bar 17.

【0037】第1及び第2の移動鉄筋15,17は、各
々一端部15a,17aが溝18,19の外側において
溝18,19の幅より太く形成されていて、他端側に
は、溝18,19の幅より太い外径を有するナットが、
溝18,19の外側に螺合させてある。
The first and second movable reinforcing bars 15 and 17 have one end portions 15a and 17a formed outside the grooves 18 and 19 to be thicker than the widths of the grooves 18 and 19, respectively, and the other ends thereof are formed with grooves. A nut with an outer diameter larger than the width of 18, 19
It is screwed onto the outside of the grooves 18, 19.

【0038】したがって、第1及び第2の移動鉄筋1
5,17は、溝18,19から抜け出すことなく溝1
8,19に沿って移動自在であり、工事に必要なときは
両移動鉄筋15,17を、図10に示されるように端へ
スライドさせて穴を開き、工事用穴にコンクリートを流
し込んで埋める際には、図7に示されるように、両移動
鉄筋15,17を等間隔に並べて配置することができ
る。
Therefore, the first and second moving rebars 1
5 and 17 do not come out of the grooves 18 and 19
It is movable along 8 and 19 and when necessary for construction, slide both moving rebars 15 and 17 to the end to open a hole as shown in FIG. 10 and pour concrete into the construction hole to fill it. At this time, as shown in FIG. 7, both moving reinforcing bars 15 and 17 can be arranged at equal intervals.

【0039】なお、第1及び第2の移動鉄筋15,17
が溝18,19から抜け出さないようにする手段はどの
ようなものでもよく、例えば鉄筋の端部を折り曲げた
り、リベット等を利用してもよい。
The first and second moving reinforcing bars 15, 17
Any means may be used to prevent the rod from coming out of the grooves 18 and 19, and for example, the end portion of the reinforcing bar may be bent or rivets may be used.

【0040】図7に示されるように、第1及び第2の移
動鉄筋15,17は、コンクリートに埋め込まれる際に
スラブ鉄筋100…とアンカー鉄筋14…とに対応して
配列できるだけの本数が設けられている。また、支柱鉄
筋2…は型枠鉄筋1の4辺の各中央部分付近に溶接され
ている。
As shown in FIG. 7, the first and second moving reinforcing bars 15 and 17 are provided in such a number that they can be arranged corresponding to the slab reinforcing bars 100 and the anchor reinforcing bars 14 when being embedded in concrete. Has been. Further, the column rebars 2 ... Are welded near the central portions of the four sides of the form rebar 1.

【0041】このように構成された第2の実施の形態に
おいては、最後にコンクリートに埋め込まれたときに、
各アンカー鉄筋14…を介してスラブ鉄筋100…と移
動鉄筋15…,17…が連結された状態になるので、非
常に優れた強度を確保することができる。
In the second embodiment constructed as described above, when it is finally embedded in concrete,
Since the slab reinforcing bars 100 and the moving reinforcing bars 15 and 17 are connected to each other through the anchor reinforcing bars 14 and so on, it is possible to secure extremely excellent strength.

【0042】なお、第1の平行鉄板13と第2の平行鉄
板16は、図11に示されるように上下に位置をずらし
て配置してもよい。また、図12に示されるように、型
枠鉄筋1の辺部の各々から外方に例えば半円状のフック
部1aを突出させれば、スラブ鉄筋100に加わる力が
それと直角方向に張られたスラブ鉄筋100にフック部
1aを介して伝達されるので、応力が分散されて補強強
度を向上させることができる。
The first parallel iron plate 13 and the second parallel iron plate 16 may be arranged so as to be vertically displaced as shown in FIG. Further, as shown in FIG. 12, if a semicircular hook portion 1a is projected outward from each of the side portions of the form rebar 1, the force applied to the slab rebar 100 is stretched in a direction perpendicular to it. Since it is transmitted to the slab rebar 100 through the hook portion 1a, the stress is dispersed and the reinforcing strength can be improved.

【0043】なお、本発明は上記各実施の形態に限定さ
れるものではなく、例えば型枠鉄筋1は円形その他の形
状であってもよく、型枠鉄筋1を省略したものであって
もよい。
The present invention is not limited to the above-described embodiments. For example, the form rebar 1 may have a circular shape or another shape, or the form rebar 1 may be omitted. .

【0044】[0044]

【発明の効果】本発明によれば、スラブ開口養生鉄筋を
工事用穴内に設置して、工事に必要なときは移動鉄筋を
端へスライドさせて穴を開き、工事用穴にコンクリート
を流し込んで埋める際には、両移動鉄筋を等間隔に並べ
て配置すればよいので、工事用穴用の養生鉄筋の工事を
床板の鉄筋工事と一緒に行うことができ、工程を簡素化
することができる。
According to the present invention, the slab opening curing rebar is installed in the construction hole, and when necessary for construction, the moving rebar is slid to the end to open the hole, and concrete is poured into the construction hole. When burying, since both moving rebars may be arranged side by side at equal intervals, the work of the curing rebar for the work hole can be performed together with the rebar work of the floor plate, and the process can be simplified.

【0045】そして、平行部材に形成されたアンカー部
材を床板のコンクリートと結合させることにより、平行
部材が床板側と一体化されるので、非常に優れた強度を
得ることができる。
By connecting the anchor member formed in the parallel member with the concrete of the floorboard, the parallel member is integrated with the floorboard side, so that very excellent strength can be obtained.

【0046】また、複数のアンカー部材を平行部材から
突出させて、スラブ鉄筋と対応するように配置すれば、
より優れた強度を得ることができる。
If a plurality of anchor members are projected from the parallel member and arranged so as to correspond to the slab rebar,
More excellent strength can be obtained.

【0047】また、平行部材と連結された複数の鉄筋
を、床板にコンクリート打ちを行う際に工事用穴を形成
するための型枠として機能させることにより、その後で
工事用穴にコンクリートを流し込んで埋める際にはその
まま一緒に埋められるので、工事用穴形成のための型枠
の着脱が不要であり、工程が非常に簡素化される。
Further, a plurality of reinforcing bars connected to the parallel members are made to function as a formwork for forming a construction hole when concrete is poured into the floorboard, so that concrete can be poured into the construction hole after that. When filling it, it is filled together as it is, so there is no need to attach and detach the formwork for forming the construction hole, and the process is greatly simplified.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1の実施の形態のスラブ開口養生鉄
筋の斜視図である。
FIG. 1 is a perspective view of a slab opening curing reinforcing bar according to a first embodiment of the present invention.

【図2】本発明の第1の実施の形態の型枠鉄筋の分解斜
視図である。
FIG. 2 is an exploded perspective view of the formwork rebar according to the first embodiment of this invention.

【図3】本発明の第1の実施の形態の第1の平行鉄筋と
第1の移動鉄筋に斜線を施して示す斜視図である。
FIG. 3 is a perspective view showing a first parallel reinforcing bar and a first moving reinforcing bar of the first embodiment of the present invention with diagonal lines.

【図4】本発明の第1の実施の形態の第2の平行鉄筋と
第2の移動鉄筋に斜線を施して示す斜視図である。
FIG. 4 is a perspective view showing a second parallel reinforcing bar and a second moving reinforcing bar of the first embodiment of the present invention with diagonal lines.

【図5】本発明の第1の実施の形態のスラブ開口養生鉄
筋を開いた状態の斜視図である。
FIG. 5 is a perspective view showing a state where the slab opening curing reinforcing bar of the first embodiment of the invention is opened.

【図6】本発明の第1の実施の形態の養生蓋が載せられ
た状態の側面部分断面図である。
FIG. 6 is a side partial cross-sectional view of a state in which the curing lid of the first embodiment of the present invention is placed.

【図7】本発明の第2の実施の形態のスラブ開口養生鉄
筋の平面図である。
FIG. 7 is a plan view of a slab opening curing reinforcing bar according to a second embodiment of the present invention.

【図8】本発明の第2の実施の形態のスラブ開口養生鉄
筋の正面断面図である。
FIG. 8 is a front sectional view of a slab opening curing reinforcing bar according to a second embodiment of the present invention.

【図9】本発明の第2の実施の形態の平行鉄板部分の斜
視図である。
FIG. 9 is a perspective view of a parallel iron plate portion according to the second embodiment of the present invention.

【図10】本発明の第2の実施の形態のスラブ開口養生
鉄筋を開いた状態の平面図である。
FIG. 10 is a plan view showing a state where the slab opening curing reinforcing bar of the second embodiment of the invention is opened.

【図11】本発明の第3の実施の形態のスラブ開口養生
鉄筋の正面断面図である。
FIG. 11 is a front sectional view of a slab opening curing reinforcing bar according to a third embodiment of the present invention.

【図12】本発明の第4の実施の形態の型枠鉄筋の斜視
図である。
FIG. 12 is a perspective view of a formwork reinforcing bar according to a fourth embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 型枠鉄筋 3 第1の平行鉄筋 4 アンカー部 5 第1の移動鉄筋 6 第2の平行鉄筋 7 第2の移動鉄筋 1 Formwork Reinforcing Bar 3 First Parallel Reinforcing Bar 4 Anchor Section 5 First Moving Reinforcing Bar 6 Second Parallel Reinforcing Bar 7 Second Moving Reinforcing Bar

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】鉄筋コンクリート構造の床板に形成された
工事用穴を工事終了時に鉄筋コンクリートで埋めるため
のスラブ開口養生鉄筋であって、 上記工事用穴内に設置されてその穴の開口部側から見て
平行に略真っ直ぐに配置された第1の平行部材と、両端
が上記第1の平行部材に対してスライド自在に係合する
一本又は複数の第1の移動鉄筋と、上記工事用穴内に設
置されてその穴の開口部側から見て上記第1の平行部材
と異なる方向に平行に略真っ直ぐに配置された第2の平
行部材と、両端が上記第2の平行部材に対してスライド
自在に係合して上記工事用穴の開口部側から見て上記第
1の移動鉄筋の移動範囲と重なる移動範囲を有する一本
又は複数の第2の移動鉄筋とを設けたことを特徴とする
スラブ開口養生鉄筋。
1. A slab opening curing bar for filling a construction hole formed in a floorboard of a reinforced concrete structure with reinforced concrete at the end of construction, which is installed in the construction hole and viewed from the opening side of the hole. A first parallel member arranged substantially straight in parallel, one or a plurality of first moving rebars having both ends slidably engaged with the first parallel member, and installed in the construction hole. A second parallel member arranged substantially straight in parallel with the first parallel member in a direction different from that of the first parallel member when viewed from the opening side of the hole, and both ends slidable with respect to the second parallel member. A slab provided with one or a plurality of second moving reinforcing bars which are engaged with each other and have a moving range overlapping with the moving range of the first moving reinforcing bar when viewed from the opening side of the construction hole. Opening rebar.
【請求項2】上記第1及び第2の平行部材が鉄筋である
請求項1記載のスラブ開口養生鉄筋。
2. The slab opening curing reinforcing bar according to claim 1, wherein the first and second parallel members are reinforcing bars.
【請求項3】上記第1及び第2の平行部材の少なくとも
一方の延長部に、上記工事用穴の外側に突出するアンカ
ー部が形成されている請求項2記載のスラブ開口養生鉄
筋。
3. The slab opening curing reinforcing bar according to claim 2, wherein an anchor portion projecting to the outside of the construction hole is formed in an extension portion of at least one of the first and second parallel members.
【請求項4】上記平行部材が板状の部材であり、上記工
事用穴の外側に突出するアンカー部材の基部が上記各板
状部材に連結されている請求項1記載のスラブ開口養生
鉄筋。
4. The slab opening curing reinforcing bar according to claim 1, wherein the parallel member is a plate-shaped member, and a base portion of an anchor member protruding outside the construction hole is connected to each plate-shaped member.
【請求項5】上記各板状部材から側方に適宜の間隔で上
記アンカー部材が突出するように、上記各板状部材に対
して複数のアンカー部材が連結されている請求項4記載
のスラブ開口養生鉄筋。
5. The slab according to claim 4, wherein a plurality of anchor members are connected to the plate members so that the anchor members project laterally from the plate members at appropriate intervals. Opening rebar.
【請求項6】上記床板にコンクリートを流す際に上記工
事用穴の内周面となる部分に配置されて型枠として機能
する複数の鉄筋が、上記第1及び第2の平行部材と連結
して設けられている請求項1、2、3、4又は5記載の
スラブ開口養生鉄筋。
6. A plurality of rebars, which are arranged in a portion which becomes an inner peripheral surface of the construction hole when concrete is poured into the floor board and function as a formwork, are connected to the first and second parallel members. The slab opening curing rebar according to claim 1, 2, 3, 4, or 5, which is provided.
【請求項7】上記型枠として機能する鉄筋に、上記工事
用穴の外側に突出するフック部が突出形成されている請
求項6記載のスラブ開口養生鉄筋。
7. The slab opening curing reinforcing bar according to claim 6, wherein the reinforcing bar functioning as the form is formed with a hook part projecting outside the construction hole.
JP07185108A 1995-01-05 1995-07-21 Slab opening curing bar Expired - Fee Related JP3084349B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07185108A JP3084349B2 (en) 1995-01-05 1995-07-21 Slab opening curing bar

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP23395 1995-01-05
JP7-233 1995-01-05
JP07185108A JP3084349B2 (en) 1995-01-05 1995-07-21 Slab opening curing bar

Publications (2)

Publication Number Publication Date
JPH08239950A true JPH08239950A (en) 1996-09-17
JP3084349B2 JP3084349B2 (en) 2000-09-04

Family

ID=26333162

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07185108A Expired - Fee Related JP3084349B2 (en) 1995-01-05 1995-07-21 Slab opening curing bar

Country Status (1)

Country Link
JP (1) JP3084349B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100953989B1 (en) * 2007-12-07 2010-04-21 주식회사 빌드썬 Concrete mold for slab opening
JP2021147940A (en) * 2020-03-23 2021-09-27 ジオスター株式会社 Half-precast structure slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100953989B1 (en) * 2007-12-07 2010-04-21 주식회사 빌드썬 Concrete mold for slab opening
JP2021147940A (en) * 2020-03-23 2021-09-27 ジオスター株式会社 Half-precast structure slab

Also Published As

Publication number Publication date
JP3084349B2 (en) 2000-09-04

Similar Documents

Publication Publication Date Title
JP5317949B2 (en) Concrete assembly structure and construction method thereof
JP2006283333A (en) Construction method of reinforced concrete column/steel beam building
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
JPH05311747A (en) Pole-beam structure
JPH08239950A (en) Slab-opening curing reinforcement
JP2000038710A (en) Structure of concrete floor slab
JPH05287901A (en) Construction of stairs
JPH09195438A (en) Precast concrete plate and reinforcing structure of building
JP5318294B2 (en) Concrete assembly structure and construction method thereof
JPH0913399A (en) Reinforcement holding device
CN107060072B (en) The plug-in board construction method of overall assembled building based on BIM technology
JP4881509B2 (en) Opening reinforcing structure of concrete foundation and opening reinforcing method thereof
JP4435714B2 (en) Floor slab structure, method for manufacturing floor slab structure, and method for constructing floor slab
JP2596174Y2 (en) Joint structure of concrete filled steel pipe column
JP5869802B2 (en) Wall-type structure of reinforced concrete structure and construction method thereof
JPH07252882A (en) Connecting method for building frame
JP2000120170A (en) Concrete charged steel pipe pillar
JPH10219894A (en) Concrete formwork structure
JPH0657905A (en) External wall of building, construction thereof, and net supporting metal tool therefor
JPH0633073Y2 (en) Precast concrete beam
JPH084177A (en) Joint method of beam/slab
JPH06306977A (en) Precast wall form, earthquake-resisting wall using this form and execution method thereof
JPH0860859A (en) Execution method of sloped form
JPH11343665A (en) Hollow precast concrete column and construction method thereof
JPS63261037A (en) Execution of waffle slab and lower constitution body of waffle slab

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110630

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110630

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120630

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120630

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130630

Year of fee payment: 13

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130630

Year of fee payment: 13

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130630

Year of fee payment: 13

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees