JPH08144224A - Erection method of bridge - Google Patents

Erection method of bridge

Info

Publication number
JPH08144224A
JPH08144224A JP6284923A JP28492394A JPH08144224A JP H08144224 A JPH08144224 A JP H08144224A JP 6284923 A JP6284923 A JP 6284923A JP 28492394 A JP28492394 A JP 28492394A JP H08144224 A JPH08144224 A JP H08144224A
Authority
JP
Japan
Prior art keywords
erection
leg
girder
bridge
launching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6284923A
Other languages
Japanese (ja)
Other versions
JP2768283B2 (en
Inventor
Matsuo Tsuruoka
松生 鶴岡
Nobuhide Wada
信秀 和田
Taketatsu Yamauchi
丈樹 山内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP6284923A priority Critical patent/JP2768283B2/en
Publication of JPH08144224A publication Critical patent/JPH08144224A/en
Application granted granted Critical
Publication of JP2768283B2 publication Critical patent/JP2768283B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE: To cope with a short-sized erection girder, and to improve workability and profitability by devising the bearing and moving methods of an erection girder in the erection method of a bridge by a method of cantilever erection precast block construction. CONSTITUTION: Blocks 3 are built and joined left and right alternately or simultaneously by utilizing an erection girder 11, and projected gradually while giving prestress. Erection work during a single span is completed, and a front leg is retreated along the erection girder 11, and moved onto a bridge girder 2, which is built perfectly. The erection girder 11 is borne by a rear leg 34 and the front leg 32, and a launching leg 33 is moved up to the place of the front leg 32. The erection girder 11 is borne by the rear leg 34 and the launching leg 33, the erection girder is forwarded, and the front leg 32 is shifted up to a next built pier 1. The launching leg 33 is moved up to the upper section of the pier 1, on which the front leg 32 is fixed temporarily. The erection girder 11 is sent out second.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本願発明は、橋脚を中心にバラン
スを取り、左右交互または同時にブロックを接合してプ
レストレスを与えながら張り出して行く片持ち架設プレ
キャストブロック工法による橋梁の架設方法の改良に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement of a bridge erection method by a cantilever erection precast block construction method in which balance is centered around a bridge pier, and blocks are joined alternately at the same time or at the same time to project while prestressing. It is a thing.

【0002】[0002]

【従来の技術】プレキャストブロック工法は、工場ある
いは製作ヤードで橋軸方向または橋軸直角方向に分割し
て構造物を製作し、架設現場に搬入し、プレストレスを
導入して一体構造物に作り上げる工法であり、橋梁の施
工等に用いられている。
2. Description of the Related Art In the precast block method, a structure is manufactured by dividing it into a bridge axis direction or a direction perpendicular to the bridge axis at a factory or a manufacturing yard, and then the structure is carried into the erection site, and prestress is introduced to form an integrated structure. It is a construction method and is used for construction of bridges.

【0003】プレキャストブロック工法を橋梁の架設に
適用した場合の利点としては、以下のようなものが挙げ
られる。
The following are some of the advantages of applying the precast block construction method to bridge construction.

【0004】 プレキャストブロックを下部工の施工
中に製作し、ストックできるので、製作工程と架設工程
を別々に設定でき、工期が大幅に短縮できる。
Since the precast block can be manufactured and stocked during the construction of the substructure, the manufacturing process and the erection process can be set separately, and the construction period can be significantly shortened.

【0005】 プレキャストブロックの製作は、工場
または製作ヤードでの繰り返し作業となり、品質の安定
した構造物を造ることができる。また、機械化施工を行
うことで合理化、省力化が可能である。
The production of the precast block is a repetitive operation in a factory or a production yard, and a structure having stable quality can be produced. Moreover, rationalization and labor saving can be achieved by performing mechanized construction.

【0006】 ストックヤードでブロックを保管する
ことにより、架設後の乾燥収縮、クリープによる変形が
小さくなる。
By storing the blocks in the stockyard, drying shrinkage after installation and deformation due to creep are reduced.

【0007】上述の点からして、プレキャストブロック
工法は、PC橋工事の分野で最も急速施工、省力化施工
が期待できる工法であるが、そのためにはブロックの製
作では型枠設備等の自動化、ブロックの架設では架設機
械の大型化を前提とし、大規模な橋梁工事において有利
な工法となる。
From the above point of view, the precast block construction method is the construction method which is expected to be the most rapid construction and labor-saving construction in the field of PC bridge construction. The block erection is an advantageous construction method for large-scale bridge construction, assuming that the erection machine is large.

【0008】なお、プレストレスの導入に関し、諸外国
では外ケーブルを使用する例が多く、それにより施工
性、経済性の向上が図られている。
With respect to the introduction of prestress, there are many cases in which foreign cables are used in other countries, which improves workability and economy.

【0009】また、プレキャストブロック工法の代表的
な架設方法としては、工場またはヤードで製作された1
径間分のブロックを架設ガーダー上に運搬して、所定の
位置決め後、接合し、プレストレスを与えながら1径間
ずつ架設して行くスパンバイスパン工法と、橋脚を中心
にバランスを取り、左右交互または同時にブロックを接
合してプレストレスを与えながら張り出して行く片持ち
架設工法があり、前者は支間40〜60m、後者は支間
60〜100m程度のPC桁橋に適している。
Further, as a typical erection method of the precast block construction method, it is manufactured in a factory or a yard.
The span-by-span construction method, in which blocks for spans are transported onto the erection girder, and after predetermined positioning, they are joined and erected one span at a time while prestressing, the balance is centered around the pier, There is a cantilever erection method in which blocks are alternately or simultaneously joined and overhanged while prestressing. The former is suitable for a PC girder bridge with a span of 40 to 60 m and the latter with a span of 60 to 100 m.

【0010】[0010]

【発明が解決しようとする課題】本願発明が対象とする
片持ち架設プレキャストブロック工法についても、ブロ
ックの架設方法について、数種の方法があるが、架設ガ
ーダーを用いる場合、通常、支持脚としての最前部のフ
ロントレグ、中間部のランチングレグ、および最後部の
リアーレグを有する架設ガーダーを用いる。
In the cantilever precast block construction method, which is the subject of the present invention, there are several types of block erection methods. When an erection girder is used, it is usually used as a support leg. A erected girder with a front leg at the front, a launching leg at the middle, and a rear leg at the rear is used.

【0011】この場合、ブロック架設時は、架設完了し
た橋桁上に固定したリアーレグと、施工方向前方に先行
施工された橋脚上部に固定した中間のランチングレグと
で架設ガーダーを支持し、橋脚を中心にバランスを取り
ながら、架設ガーダーを利用してブロックの架設、接合
を左右交互または同時に行い、プレストレスを与えなが
ら張り出して行く。
In this case, when the block is erected, the erection girder is supported by the rear leg fixed on the bridge girder that has been erected and the intermediate launching leg fixed on the upper part of the pier, which is pre-constructed in the construction direction. While balancing, use the erection girder to erection and join blocks at the same time, either left or right, or at the same time, and overhang while applying prestress.

【0012】また、架設ガーダーの移動に関しては、2
径間以上の長さを有する架設ガーダーを用い、単径間の
架設が完了した段階で架設ガーダーを送り出し、リアー
レグとフロントレグで架設ガーダー支持した状態でラン
チングレグをフロントレグのある次架設の橋脚に移動
し、続いてリアーレグとランチングレグで架設ガーダー
を支持した状態でフロントレグを送り出すといった方法
が採られている。
Regarding the movement of the erection girder, 2
When using a erection girder with a length greater than the span, send out the erection girder when the erection of a single span is completed, and with the rear leg and front leg supporting the erection girder, the launching leg is the pier of the next erection with the front leg. Then, the front leg is sent out while the erection girder is supported by the rear leg and the launching leg.

【0013】しかし、従来の方法では大きな支間に対応
させるため、架設ガーダーも長大なものとなり、その支
持や移動が困難となる。
However, since the conventional method accommodates a large span, the erection girder also becomes large and it is difficult to support and move it.

【0014】本願発明は、このような片持ち架設プレキ
ャストブロック工法による橋梁の架設方法において、架
設ガーダーの支持および移動方法を工夫することで、従
来より短い架設ガーダーで対処できるようにし、施工
性、経済性の向上を図ったものである。
According to the present invention, in such a bridge erection method by the cantilever erection precast block method, by devising a method of supporting and moving the erection girder, a erection girder shorter than the conventional construction can be dealt with. It is intended to improve economic efficiency.

【0015】[0015]

【課題を解決するための手段】本願発明は、架設ガーダ
ーを用い、架設完了した橋桁上に固定したリアーレグ
と、施工方向前方に先行施工された橋脚上部に固定した
中間のランチングレグとで架設ガーダーを支持し、橋脚
を中心にバランスを取りながら、架設ガーダーを利用し
てブロックの架設、接合を左右交互または同時に行い、
プレストレスを与えながら張り出して行く工程を、単径
間ごと架設ガーダーを送り出しながら繰り返す片持ち架
設プレキャストブロック工法による橋梁の架設方法にお
いて、架設ガーダーの送り出しを2回に分けて行うよう
にしたものである。
SUMMARY OF THE INVENTION The present invention is an erection girder that uses an erection girder and includes a rear leg that is fixed on the bridge girder that has been erected and an intermediate launching leg that is fixed on the upper part of the pier that has been installed ahead in the construction direction. While maintaining balance around the bridge pier, using the erection girder, the blocks are erected, joined left and right alternately or simultaneously,
In the bridge erection method by the cantilever erection precast block method, which repeats the process of overhanging while applying prestress while sending out the erection girder for each single span, the erection girder is sent out in two steps. is there.

【0016】すなわち、単径間の架設作業完了後、フロ
ントレグを架設ガーダーに沿って後退させ、架設完了し
た橋桁上に移動し、リアーレグとフロントレグで架設ガ
ーダーを支持した状態でランチングレグを架設ガーダー
に沿ってフロントレグ近傍に移動して橋桁上に固定し、
リアーレグとランチングレグで支持した状態で架設ガー
ダーを送り出し(1回目の送り出し)、フロントレグを
次架設の橋脚上部に移動して仮固定し、続いてリアーレ
グとフロントレグで架設ガーダーを支持した状態でラン
チングレグを架設ガーダーに沿ってフロントレグを仮固
定した橋脚上まで移動して固定し、続いてリアーレグと
ランチングレグで架設ガーダーを支持した状態で架設ガ
ーダーを次架設のための所定位置まで移動させる(2回
目の送り出し)ことを特徴とする。
That is, after completion of the erection work of a single diameter, the front leg is retracted along the erection girder, moved to the bridge girder that has been erected, and the launching leg is erected with the rear leg and the front leg supporting the erection girder. Move along the girder near the front leg and secure it on the bridge girder,
With the rear leg and the launching leg supported, send the erection girder (first delivery), move the front leg to the upper part of the pier for the next erection and temporarily fix it, and then with the rear leg and front leg supporting the erection girder. Move the launching leg along the erection girder to the bridge pier where the front leg was temporarily fixed and fix it, and then move the erection girder to the predetermined position for the next erection while supporting the erection girder with the rear leg and the launching leg. It is characterized by (second delivery).

【0017】なお、架設ガーダー上に屋根装置(天蓋)
を装備することで、全天候型の施工が可能となる他、屋
根装置をプレキャストブロックの養生を目的として利用
することもできる。このような屋根装置としては、例え
ば、架設ガーダーの外側にレールを敷設し、施工スパン
全長に渡りジャバラ式に開閉するようなものが考えられ
る。
A roof device (canopy) is mounted on the erection girder.
By installing the above, not only can all-weather construction be possible, but the roof device can also be used for the purpose of curing the precast block. As such a roof device, for example, one in which rails are laid outside the erection girder and opened / closed in a bellows manner over the entire length of the construction span can be considered.

【0018】[0018]

【実施例】次に、図示した実施例について説明する。な
お、以下に述べる実施例はあくまで一実施例であり、本
願発明は実施例に限定されるものではない。
EXAMPLES Next, the illustrated examples will be described. Note that the embodiment described below is merely an embodiment, and the present invention is not limited to the embodiment.

【0019】図1は、本願発明の対象となる架設ガーダ
ーを用いた片持ち架設プレキャストブロック工法におけ
る施工および機械構成の概要を示したものである。
FIG. 1 shows an outline of the construction and mechanical construction in the cantilever erection precast block method using the erection girder to which the present invention is applied.

【0020】(1) 本実施例における施工方針は以下の通
りである。
(1) The construction policy in this embodiment is as follows.

【0021】 施工支間は、60〜100m程度とす
る。
The construction span is about 60 to 100 m.

【0022】 ブロック3単体の重量は100t程度
までとする。
The weight of the block 3 alone is up to about 100 t.

【0023】 架設は、架設ガーダー11により橋脚
1を中心に、交互または同時に接合しながらブロック3
を張り出し架設する。
The erection is performed by the erection girder 11 centering on the pier 1 while alternately or simultaneously joining the blocks 3
And erection.

【0024】 架設ガーダー11は、フロントレグ3
2、ランチングレグ33、リアーレグ34の3本の脚を
使用し、手延桁方式にて単スパンごとに架設し、移動す
る。
The erection girder 11 includes the front leg 3
2. The three legs of the launching leg 33 and the rear leg 34 are used, and they are erected and moved for each single span by a hand girder system.

【0025】 架設ガーダー11は、フロントレグ3
2、ランチングレグ33、リアーレグ34の3本の脚に
より支持され、平行かつ横断勾配、縦断勾配、平面線形
に合わせて設置する。
The erection girder 11 includes the front leg 3
2. It is supported by the three legs of the launching leg 33 and the rear leg 34, and is installed in parallel and in cross slope, longitudinal slope, and plane alignment.

【0026】 ブロック3は、ブロック製作ヤードか
ら架設地点まで、架設完了した橋桁2上をトレーラー2
4または自動搬送車を用いて運搬することを原則とす
る。架設地点まで、仮設道路を使用し、架設地点直下よ
り架設ガーダー11のクラブトロリー16にて直接架設
することも可能である。
The block 3 is a trailer 2 on the completed bridge girder 2 from the block manufacturing yard to the erection point.
4 In principle, it should be transported using an automated guided vehicle. It is also possible to use a temporary road up to the erection point and to erect directly from below the erection point with the club trolley 16 of the erection girder 11.

【0027】 柱頭部の施工は、場所打ち、プレキャ
ストブロック双方の施工が可能である。
As for the construction of the column head, both cast-in-place and precast blocks can be constructed.

【0028】(2) 本実施例における機械構成は以下の通
りである。
(2) The mechanical structure of this embodiment is as follows.

【0029】 架設ガーダー11 2本の桁で構成され、架設ブロック3を支える。架設ガ
ーダー11上部は、クラブトロリー16の走行路として
使用される。
The erection girder 11 is composed of two girders and supports the erection block 3. The upper part of the erection girder 11 is used as a traveling path for the club trolley 16.

【0030】 クラブトロリー16 ブロック3を搬送車より吊り上げ、架設位置まで移動さ
せるためのクレーンで、橋軸方向に走行、横行が可能で
ある。
The club trolley 16 is a crane for hoisting the block 3 from the carrier and moving it to the erection position, which can travel and traverse in the bridge axis direction.

【0031】 フロントレグ32 架設ガーダー11最前部の脚で、送り出し、高さ調整、
横移動の機能がある。
Front leg 32 The front leg of the erection girder 11 is used for feeding, height adjustment,
There is a function of lateral movement.

【0032】 ランチングレグ33 架設ガーダー11中間部の脚で、送り出し、高さ調整、
横移動の機能がある。
Launching leg 33 With the leg in the middle part of the erection girder 11, feeding, height adjustment,
There is a function of lateral movement.

【0033】 リアーレグ34 架設ガーダー11最後部の脚で、高さ調整、横移動の機
能があり、架設完了した桁2上を走行する走行装置を装
備している。
The rear leg 34 is the last leg of the erection girder 11 and has the functions of height adjustment and lateral movement, and is equipped with a traveling device that travels on the girder 2 that has been erected.

【0034】 作業足場23(ワーキングステージ) ブロック3の位置決め、接合作業用の足場で架設ガーダ
ー11に沿い移動可能である。この作業足場23は中央
で左右に分離できるようになっており、分離した状態で
移動させることができる。
Working scaffold 23 (working stage) It is a scaffold for positioning and joining work of the block 3 and is movable along the erection girder 11. The work scaffold 23 can be separated into left and right parts at the center, and can be moved in a separated state.

【0035】 ハンガー クラブトロリー16により運搬されたブロック3を所定
位置に仮吊りする支持材。
A support material for temporarily suspending the block 3 carried by the hanger club trolley 16 at a predetermined position.

【0036】(3) 本実施例におけるブロック3の架設作
業は、以下のように行う。
(3) The erection work of the block 3 in this embodiment is performed as follows.

【0037】ブロック製作ヤードから架設地点まで、架
設完了した橋桁2上をトレーラー24または自動搬送車
を用いて運搬されたブロック3は、架設ガーダー11の
クラブトロリー16で吊り上げ、橋脚1両側から橋脚1
を中心に、交互または同時に接合しながらブロック3を
張り出し架設する。
From the block manufacturing yard to the erection point, the block 3 transported by the trailer 24 or the automated guided vehicle on the bridge girder 2 that has been completely erected is lifted by the club trolley 16 of the erection girder 11, and the pier 1 from both sides
The block 3 is extended and erected while alternately or at the same time joining with each other.

【0038】架設地点で、ブロック3はクラブトロリー
16により所定間隔で転回、調整、位置決めされた後、
ハンガーにより仮固定される。
At the erection point, the block 3 is turned, adjusted, and positioned by the club trolley 16 at predetermined intervals,
Temporarily fixed by a hanger.

【0039】ハンガーにより仮固定された状態で、作業
足場23上での接着剤の塗布、ブロック3の引き寄せ接
合を実施する。ブロック3の緊張完了後、ハンガーを解
放してブロック3の架設を完了する。
In a state where the work scaffold 23 is temporarily fixed by a hanger, an adhesive is applied on the work scaffold 23 and the blocks 3 are pulled together and joined. After the tension of the block 3 is completed, the hanger is released to complete the erection of the block 3.

【0040】柱頭部の施工は、プレキャスト、現場打ち
双方の施工法が採用可能である。
For the construction of the column head, both precast and in-situ construction methods can be adopted.

【0041】プレキャストブロック3の養生を目的とし
て、架設ガーダー11上の施工スパン全長にわたりジャ
バラ式上屋(架設ガーダー外側に敷設されたレール上を
移動する)を装備している。
For the purpose of curing the precast block 3, a bellows type shed (moving on a rail laid outside the erection girder) is equipped over the entire construction span of the erection girder 11.

【0042】(4) 本実施例における架設ガーダー11の
移動は、以下のように行う。
(4) The erection girder 11 in this embodiment is moved as follows.

【0043】単径間の1サイクルの施工における架設ガ
ーダー11の送り出しを2回に分けて行う。
The feeding of the erection girder 11 in one cycle of construction for a single diameter is carried out in two steps.

【0044】まず、フロントレグ32を架設完了したブ
ロック3上に引き戻す形で移動し、橋桁2上に仮支持す
る。フロントレグ32は橋桁2上に固定した状態で、架
設ガーダー11とは送り出し装置を介して接続されてい
る。また、リアーレグ34の脚部は、ガーダー走行装置
(またはガーダー送り出し装置)となっており、上部で
架設ガーダー11を支持している。
First, the front leg 32 is moved so as to be pulled back onto the block 3 which has been installed, and is temporarily supported on the bridge girder 2. The front leg 32 is fixed to the bridge girder 2 and is connected to the erection girder 11 via a feeding device. Further, the leg portion of the rear leg 34 serves as a girder traveling device (or a girder feeding device), and the erection girder 11 is supported at the upper part.

【0045】ランチングレグ33の支持を解放(移動時
にせりが出ない高さまで引き上げる)し、フロントレグ
32、リアーレグ34で架設ガーダー11を支持して、
ランチングレグ33をフロントレグ32と同位置まで送
り出した後(ランチングレグ33は付属している送り出
し装置で、自力でフロントレグ32の位置まで移動可能
であり、架設ガーダー11のバランス、作業性を考慮し
ながら送り出す)、ランチングレグ33を橋桁2上に仮
固定する。
The support of the launching leg 33 is released (raised to a height that does not give rise to curling when moving), and the erection girder 11 is supported by the front leg 32 and the rear leg 34,
After feeding the launching leg 33 to the same position as the front leg 32 (The launching leg 33 can be moved to the position of the front leg 32 by itself with the attached feeding device, and consider the balance and workability of the erection girder 11. While sending), the launching leg 33 is temporarily fixed on the bridge girder 2.

【0046】リアーレグ34脚部に装備した走行装置を
用いて、架設ガーダー11の1回目の送り出しを行う。
ランチングレグ33と架設ガーダー11との取合い部分
に設けられた移動装置をガイドとして架設ガーダー11
が移動する。架設ガーダー11の送り出しにより、架設
ガーダー11先端のフロントレグ32支持位置が先方の
次架設の橋脚1上部に到達した段階で、フロントレグ3
2を橋脚1上に仮固定する。
The traveling girder mounted on the leg of the rear leg 34 is used to feed the erection girder 11 for the first time.
The erection girder 11 using the moving device provided at the joint between the launching leg 33 and the erection girder 11 as a guide.
Moves. When the front leg 32 supporting position at the tip of the erection girder 11 reaches the upper part of the pier 1 of the next next erection by sending out the erection girder 11, the front leg 3
2 is temporarily fixed on the pier 1.

【0047】再び、ランチングレグ33の支持を解放
し、フロントレグ32、リアーレグ34で架設ガーダー
11を支持して、ランチングレグ33をフロントレグ3
2と同位置まで送り出し、ランチングレグ33を橋脚上
に固定する。
Again, the support of the launching leg 33 is released, the erection girder 11 is supported by the front leg 32 and the rear leg 34, and the launching leg 33 is moved to the front leg 3.
Send it to the same position as 2 and fix the launching leg 33 on the pier.

【0048】フロントレグ32の支持を解放し、架設ガ
ーダーの2回目の送り出しを行う。
The support of the front leg 32 is released, and the erection girder is fed out for the second time.

【0049】(5) 次に、本実施例における施工手順を、
図2(a) 〜(d) および図3(e) 〜(h)に基づいて説明す
る。
(5) Next, the construction procedure in this embodiment is
2 (a) to 2 (d) and 3 (e) to 3 (h).

【0050】 ブロック3の架設開始(図2(a) 参
照) 先行施工された柱頭部の両側から交互にブロック3の架
設を行う。ブロック3は、架設ガーダー11に搭載され
たクラブトロリー16により吊り上げられ、90度方向
転回した後、架設場所まで運搬して位置決めし、接合す
る。
Start of erection of the block 3 (see FIG. 2 (a)) The erection of the block 3 is alternately performed from both sides of the column head previously constructed. The block 3 is hoisted by the club trolley 16 mounted on the erection girder 11, and after being turned by 90 degrees, transported to the erection site for positioning and joining.

【0051】なお、図中左側の部分は足場を組んで、移
動式クレーン等を用いて橋桁2を架設した部分である。
The left side portion in the figure is a portion where scaffolding is assembled and the bridge girder 2 is erected using a mobile crane or the like.

【0052】 ブロック3の架設、接合(図2(b) 参
照) ブロック3は、クラブトロリー16により吊り上げられ
た状態で位置決め調整を行う。作業足場23上から接着
剤の塗布、引寄せ鋼棒を用いた引寄せ、接合を行う。
Construction and Joining of Block 3 (See FIG. 2B) The block 3 is positioned and adjusted by being lifted by the club trolley 16. Application of an adhesive, drawing using a drawing steel rod, and joining are performed on the work scaffold 23.

【0053】 外ケーブルの敷設、緊張(図2(c) 参
照) 必要数のブロック架設、仮緊張完了後、間詰めコンクリ
ートの施工を行う。同時に外ケーブルの敷設後、外ケー
ブルの緊張を行い、単径間の施工を完了する。
Laying of external cables and tension (see FIG. 2 (c)) After erection of the required number of blocks and completion of temporary tension, the filling concrete is applied. At the same time, after laying the outer cable, the outer cable is tensioned to complete the construction of the single span.

【0054】 架設ガーダー11の移動準備(図2
(d) 参照) フロントレグ32を架設完了したブロック3上に移動
し、仮支持し、ランチングレグ33をフロントレグ32
近傍の移動時支点まで移動し、橋桁2上に固定する。こ
の際、クラブトロリー16の固定、作業足場23の移動
準備をしておく。
Preparation for moving the erection girder 11 (see FIG. 2
(See (d)) The front leg 32 is moved onto the block 3 on which the installation has been completed, is temporarily supported, and the launching leg 33 is attached to the front leg 32.
When moving to a nearby fulcrum, fix it on the bridge girder 2. At this time, the club trolley 16 is fixed and the work scaffold 23 is prepared for movement.

【0055】 架設ガーダー11の送り出し(図3
(e) 参照) リアーレグ34脚部に装備した走行装置を用いて、架設
ガーダー11の送り出しを行う。ランチングレグ33と
架設ガーダー11との取合い部分に設けられた移動装置
をガイドとして架設ガーダー11が移動する。架設ガー
ダー11の送り出しにより、架設ガーダー11先端のフ
ロントレグ32支持位置が先方の次架設の橋脚1上部に
到達した段階で、フロントレグ32を橋脚1上に仮固定
する。
Sending out the erection girder 11 (see FIG.
(Refer to (e)) The erection girder 11 is sent out using the traveling device equipped on the leg of the rear leg 34. The erection girder 11 is moved by using a moving device provided at a connecting portion between the launching leg 33 and the erection girder 11 as a guide. The front leg 32 is temporarily fixed onto the pier 1 when the front leg 32 support position at the tip of the erection girder 11 reaches the upper part of the pier 1 of the next next erection by sending out the erection girder 11.

【0056】 ランチングレグ33の固定(図3(f)
参照) フロントレグ32を仮固定した後、フロントレグ32、
リアーレグ34で架設ガーダー11を支持し、ランチン
グレグ33を解放し、ランチングレグ33に装備した移
動装置を駆動し、先方橋脚1上までランチングレグ33
を移動し、位置決め後、固定する。なお、橋脚1上の基
準ブロックは事前に移動式クレーン13により架設して
おく。
Fixing the launching leg 33 (FIG. 3 (f)
(See) After temporarily fixing the front leg 32, the front leg 32,
The erection girder 11 is supported by the rear leg 34, the launching leg 33 is released, the moving device mounted on the launching leg 33 is driven, and the launching leg 33 is reached up to the destination pier 1.
Move, position and fix. The reference block on the pier 1 is installed by the mobile crane 13 in advance.

【0057】 架設ガーダー11の再移動(図3(g)
参照) ランチングレグ33を支持点および移動時のガイドとし
て、リアーレグ34の走行装置を駆動し、再度、架設ガ
ーダー11を移動させる。リアーレグ34の支点固定位
置まで架設ガーダー11を移動したら、ランチングレグ
33、リアーレグ34の位置決め調整後、固定する。
Removing the erection girder 11 (Fig. 3 (g)
With reference to the launching leg 33 as a support point and a guide at the time of movement, the traveling device of the rear leg 34 is driven to move the erection girder 11 again. After moving the erection girder 11 to the fulcrum fixing position of the rear leg 34, the positioning of the launching leg 33 and the rear leg 34 is adjusted and then fixed.

【0058】 架設ガーダー11の移動完了(ブロッ
ク架設準備)(図3(h) 参照) 架設ガーダー11の移動完了後、架設ガーダー11各部
の点検、固定部まわりの再確認を行い、計画位置に正し
く設置していることを確認する。クラブトロリー16、
作業足場23を所定の位置に移動し、ブロック3の架設
の準備を行う。
Completion of movement of the erection girder 11 (preparation for block erection) (see FIG. 3 (h)) After the movement of the erection girder 11 is completed, the parts of the erection girder 11 are inspected and the surroundings of the fixed part are reconfirmed to make sure that the position is correct Make sure it is installed. Club trolley 16,
The work scaffold 23 is moved to a predetermined position, and the block 3 is prepared for installation.

【0059】[0059]

【発明の効果】本願発明では架設ガーダー送り出し移動
に際し、フロントレグ、ランチングレグ、リアーレグに
よる支点の盛り替え、移動を繰り返しながら、架設ガー
ダーを2回に分けて移動させることで、架設ガーダーの
長さを実質的に2径間以下に抑えることが可能である。
According to the invention of the present application, the length of the erection girder can be increased by moving the erection girder in two steps while relocating and moving the fulcrum by the front leg, the launching leg, and the rear leg when the erection girder is sent out. Can be substantially suppressed to 2 or less.

【0060】すわなち、従来より短い架設ガーダーで橋
梁の架設作業を行うことができ、単に架設ガーダーの長
さが短くなるだけでなく、自重や架設ガーダーに作用す
るモーメント等が小さくなることから架設ガーダーの断
面寸法の減少、それに伴うさらなる自重の低減、架設ガ
ーダーの支持に関する各部の応力の低減等が図れ、全体
として大幅な施工性、経済性の向上が図れる。
That is, since the bridge erection work can be performed with the erection girder shorter than before, not only the length of the erection girder is shortened, but also the self-weight and the moment acting on the erection girder are reduced. The cross-sectional size of the erection girder can be reduced, the weight of the erection girder can be further reduced, and the stress of each part related to the support of the erection girder can be reduced. As a result, the workability and economy can be greatly improved.

【0061】上記の効果は、特に大スパンの橋梁の架設
において大きい。
The above-mentioned effect is great especially in the construction of a bridge having a large span.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本願発明の対象となる片持ち架設プレキャス
トブロック工法の概要を示したもので、(a) は架設中の
橋梁の側面図、(b) はA−A線断面図、(c)はB−B線
断面図、(d) はC−C線断面図である。
FIG. 1 shows an outline of a cantilever erection precast block construction method which is the subject of the present invention. (A) is a side view of a bridge being erected, (b) is a sectional view taken along line AA, (c) Is a sectional view taken along line BB, and (d) is a sectional view taken along line CC.

【図2】 (a) 〜(d) は本願発明の対象となる片持ち架
設プレキャストブロック工法の一実施例における施工手
順を示す側面図である。
2 (a) to 2 (d) are side views showing a construction procedure in one embodiment of a cantilever erection precast block construction method which is an object of the present invention.

【図3】 (e) 〜(h) は図2(d) に続く施工手順を示す
側面図である。
3 (e) to (h) are side views showing a construction procedure following FIG. 2 (d).

【符号の説明】[Explanation of symbols]

1…橋脚、2…橋桁、3…ブロック、11…架設ガーダ
ー、16…クラブトロリー、23…作業足場、24…ト
レーラー、32…フロントレグ、33…ランチングレ
グ、34…リアーレグ
1 ... Bridge pier, 2 ... Bridge girder, 3 ... Block, 11 ... Erection girder, 16 ... Club trolley, 23 ... Work scaffolding, 24 ... Trailer, 32 ... Front leg, 33 ... Launching leg, 34 ... Rear leg

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 支持脚としての最前部のフロントレグ、
中間部のランチングレグ、および最後部のリアーレグを
有する架設ガーダーを用い、架設完了した橋桁上に固定
したリアーレグと、施工方向前方に先行施工された橋脚
上部に固定した中間のランチングレグとで前記架設ガー
ダーを支持し、前記橋脚を中心にバランスを取りなが
ら、架設ガーダーを利用してブロックの架設、接合を左
右交互または同時に行い、プレストレスを与えながら張
り出して行く工程を、単径間ごと架設ガーダーを送り出
しながら繰り返す片持ち架設プレキャストブロック工法
による橋梁の架設方法において、単径間の架設作業完了
後、フロントレグを架設ガーダーに沿って後退させ、架
設完了した橋桁上に移動し、リアーレグとフロントレグ
で架設ガーダーを支持した状態でランチングレグを架設
ガーダーに沿ってフロントレグ近傍に移動して橋桁上に
固定し、リアーレグとランチングレグで支持した状態で
架設ガーダーを送り出し、フロントレグを次架設の橋脚
上部に移動して仮固定し、続いてリアーレグとフロント
レグで架設ガーダーを支持した状態でランチングレグを
架設ガーダーに沿ってフロントレグを仮固定した橋脚上
まで移動して固定し、続いてリアーレグとランチングレ
グで架設ガーダーを支持した状態で架設ガーダーを次架
設のための所定位置まで移動させることを特徴とする橋
梁の架設方法。
1. A front leg of a front portion as a supporting leg,
Using the erection girder that has the launching leg in the middle part and the rear leg in the rearmost part, the above-mentioned erection with the rear leg fixed on the bridge girder that has been erected and the intermediate launching leg fixed on the upper part of the bridge pier that was constructed ahead in the construction direction. While supporting the girder and balancing around the bridge pier, using the erection girder, the blocks are erected and joined alternately left and right or at the same time, and the process of overhanging with prestressing is carried out for each single span girder. In the bridge erection method using the cantilever precast block method, the front leg is retracted along the erection girder after the erection work of a single span is completed, and the rear leg and front leg are moved. Support the erection girder with the launching leg along the erection girder. Move to the vicinity of the bridge and fix it on the bridge girder, send out the erection girder while being supported by the rear leg and the launching leg, move the front leg to the upper part of the pier for the next erection and temporarily fix it, and then erect it with the rear leg and front leg. While supporting the girder, move the launching leg along the erection girder to the bridge pier where the front leg was temporarily fixed and fix it, and then, while supporting the erection girder with the rear leg and the launching leg, for the next erection A method of constructing a bridge, characterized by moving the bridge to a predetermined position.
【請求項2】 フロントレグおよびランチングレグを架
設ガーダーに対し、それぞれ架設ガーダー長手方向に相
対移動させるための送り出し装置を介して接続し、リア
ーレグの下部に橋桁上を移動するための走行装置または
送り出し装置を設けてある請求項1記載の橋梁の架設方
法。
2. A front leg and a launching leg are connected to the erection girder via respective delivery devices for moving the erection girder in the longitudinal direction, and a traveling device or a delivery device for moving on the bridge girder to the lower part of the rear leg. The method of constructing a bridge according to claim 1, wherein a device is provided.
JP6284923A 1994-11-18 1994-11-18 Bridge construction method Expired - Fee Related JP2768283B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6284923A JP2768283B2 (en) 1994-11-18 1994-11-18 Bridge construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6284923A JP2768283B2 (en) 1994-11-18 1994-11-18 Bridge construction method

Publications (2)

Publication Number Publication Date
JPH08144224A true JPH08144224A (en) 1996-06-04
JP2768283B2 JP2768283B2 (en) 1998-06-25

Family

ID=17684814

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6284923A Expired - Fee Related JP2768283B2 (en) 1994-11-18 1994-11-18 Bridge construction method

Country Status (1)

Country Link
JP (1) JP2768283B2 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004063469A1 (en) * 2003-01-13 2004-07-29 Hankookb & B Apparatus and method for constructing bridge moving
JP2008274586A (en) * 2007-04-26 2008-11-13 Kajima Corp Pillar head construction method
JP2009127317A (en) * 2007-11-26 2009-06-11 Sanshin Kogyo Kk Bridge construction apparatus
JP2009191458A (en) * 2008-02-12 2009-08-27 Jfe Engineering Corp Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
CN106400700A (en) * 2015-08-03 2017-02-15 北京万桥兴业机械有限公司 Double-line cantilever type bridge formation machine
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN109868723A (en) * 2019-03-29 2019-06-11 四川迈铁龙科技有限公司 Overhead rail traffic steel bridge stud connection construction
CN110616637A (en) * 2019-08-14 2019-12-27 中交二航局第二工程有限公司 Overlength multifunctional integrated bridge girder erection machine and construction method for installing prefabricated bridge
CN113802462A (en) * 2021-09-28 2021-12-17 中交二航局第二工程有限公司 Section-splicing bridge girder erection machine and front supporting leg for hoisting
CN114753264A (en) * 2022-03-07 2022-07-15 中铁工程机械研究设计院有限公司 Dual-mode bridge girder erection machine and span-variable girder erection method
CN114875810A (en) * 2022-05-09 2022-08-09 中铁九桥工程有限公司 Bridge erecting method
CN115094776A (en) * 2022-07-27 2022-09-23 中铁二局集团有限公司 Method for anchoring supporting legs of bridge girder erection machine
CN115418969A (en) * 2022-09-30 2022-12-02 中冶(上海)钢结构科技有限公司 Construction method for high-position beam falling of large-span through tied steel arch bridge

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004063469A1 (en) * 2003-01-13 2004-07-29 Hankookb & B Apparatus and method for constructing bridge moving
JP2008274586A (en) * 2007-04-26 2008-11-13 Kajima Corp Pillar head construction method
JP2009127317A (en) * 2007-11-26 2009-06-11 Sanshin Kogyo Kk Bridge construction apparatus
JP2009191458A (en) * 2008-02-12 2009-08-27 Jfe Engineering Corp Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
CN106400700A (en) * 2015-08-03 2017-02-15 北京万桥兴业机械有限公司 Double-line cantilever type bridge formation machine
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN109868723A (en) * 2019-03-29 2019-06-11 四川迈铁龙科技有限公司 Overhead rail traffic steel bridge stud connection construction
CN110616637B (en) * 2019-08-14 2021-06-15 中交二航局第二工程有限公司 Overlength multifunctional integrated bridge girder erection machine and construction method for installing prefabricated bridge
CN110616637A (en) * 2019-08-14 2019-12-27 中交二航局第二工程有限公司 Overlength multifunctional integrated bridge girder erection machine and construction method for installing prefabricated bridge
CN113802462A (en) * 2021-09-28 2021-12-17 中交二航局第二工程有限公司 Section-splicing bridge girder erection machine and front supporting leg for hoisting
CN114753264A (en) * 2022-03-07 2022-07-15 中铁工程机械研究设计院有限公司 Dual-mode bridge girder erection machine and span-variable girder erection method
CN114875810A (en) * 2022-05-09 2022-08-09 中铁九桥工程有限公司 Bridge erecting method
WO2023216325A1 (en) * 2022-05-09 2023-11-16 中铁九桥工程有限公司 Bridge erecting method
CN115094776A (en) * 2022-07-27 2022-09-23 中铁二局集团有限公司 Method for anchoring supporting legs of bridge girder erection machine
CN115094776B (en) * 2022-07-27 2023-02-28 中铁二局集团有限公司 Method for anchoring supporting legs of bridge girder erection machine
CN115418969A (en) * 2022-09-30 2022-12-02 中冶(上海)钢结构科技有限公司 Construction method for high-position beam falling of large-span through tied steel arch bridge

Also Published As

Publication number Publication date
JP2768283B2 (en) 1998-06-25

Similar Documents

Publication Publication Date Title
JP6702835B2 (en) Bridge girder erection method for multi span span bridge
JP3671777B2 (en) Bridge construction method
JPH08144224A (en) Erection method of bridge
CN101787678B (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
JP4403051B2 (en) Corrugated steel web bridge construction method
CN111778860A (en) Process method for assembling sections of high-speed rail bridge
JP2894226B2 (en) Bridge construction method
JP5184248B2 (en) Construction method of level crossing
JP2768282B2 (en) Bridge construction method
CN112160246B (en) Method for installing composite beam
JP4104910B2 (en) How to build arch ribs for concrete arch bridges
JPH0643686B2 (en) Construction method of arch bridge by precast members
CN210766418U (en) Prefabricated assembled bridge multi-span synchronous mounting bridge girder erection machine
JP2000045231A (en) Erection method for arch bridge
JPH0959932A (en) Construction method of column head of overhanging erection girder bridge
JP2768280B2 (en) Bridge construction method
JP2001348816A (en) Installing method and device of precast segment overhanging installing bridge
CN113216013B (en) Self-balancing construction method for post-loading cantilever arm of composite section girder bridge
JP2768281B2 (en) Bridge construction method
JP2768279B2 (en) Construction girder for precast block method
JPS6041165B2 (en) Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.
CN105088962A (en) Integrated hoisting method for corrugated steel web part
CN112813832B (en) Rapid integrated installation method of segmental beam and prefabricated pier column
JPH11100902A (en) Installation method of girder
Heggade Segmental precast technology for multi-span bridges (production, transportation and launching)

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980310

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees