JPH0797865A - Assembly of beam steel reinforcement - Google Patents
Assembly of beam steel reinforcementInfo
- Publication number
- JPH0797865A JPH0797865A JP24291993A JP24291993A JPH0797865A JP H0797865 A JPH0797865 A JP H0797865A JP 24291993 A JP24291993 A JP 24291993A JP 24291993 A JP24291993 A JP 24291993A JP H0797865 A JPH0797865 A JP H0797865A
- Authority
- JP
- Japan
- Prior art keywords
- construction
- floor
- beam steel
- steel reinforcement
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、鉄筋コンクリート構造
の建物を構築する場合における梁鉄筋の組み立て方法に
関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of assembling beam reinforcing bars when a building having a reinforced concrete structure is constructed.
【0002】[0002]
【従来の技術】鉄筋コンクリート構造の建物を構築する
場合における従来の梁鉄筋の組み立て方法としては、構
築中の建物の構築階以外の場所で梁鉄筋を先き組みし、
これをクレーン等で揚重すると共に搬送して所定の位置
に梁鉄筋を構築する方法が知られている。しかしなが
ら、この構築方法は、先き組みする鉄筋体のストックス
ペースや、鉄筋の組み立てスペースを確保するだけの敷
地の余裕がなければ採用できない。2. Description of the Related Art As a conventional method for assembling a beam reinforcing bar in the case of building a building having a reinforced concrete structure, a beam reinforcing bar is first assembled in a place other than the construction floor of the building under construction,
A method is known in which this is lifted by a crane or the like and conveyed to construct a beam reinforcing bar at a predetermined position. However, this construction method cannot be adopted unless there is enough room in the site to secure the stock space of the rebar body to be assembled first and the rebar assembling space.
【0003】従って、敷地に余裕のない建物では、構築
階において、柱の配筋を行った後、壁のある場合は壁の
配筋を行い、ついで柱、梁、壁、スラブの型枠を組み、
このスラブの型枠上で、梁鉄筋の組み立てを行い、この
梁鉄筋を梁の型枠内に落し込んだ後、スラブの配筋を行
ってコンクリートを打設するといった構築方法も採用さ
れていた。Therefore, in a building where there is no room on the site, on the construction floor, after reinforcing the columns, if there are walls, reinforcing the walls, and then form the columns, beams, walls and slabs. Pair,
On the formwork of this slab, a beam reinforcing rod was assembled, this beam reinforcing rod was dropped into the beam formwork, and then the slab was reinforced and the concrete was placed. .
【0004】[0004]
【発明が解決しようとする課題】上述した従来の工法の
内の前者は、構築しようとする建物の敷地が十分なけれ
ば採用できないという問題点があった。また後者の構築
方法では、先き組みした鉄筋体のストックスペース等を
必要としない反面、鉄筋工事と型枠工事が交錯する為、
工事日程及び人員配置の調整が難しく、また、工期を短
縮する為の工程が組みにくいという問題点があった。The former of the above-mentioned conventional construction methods has a problem that it cannot be adopted unless the site of the building to be constructed is sufficient. In the latter construction method, the stock space of the rebar body that was assembled in advance is not required, but the rebar work and the formwork work are intermixed,
There was a problem that it was difficult to adjust the construction schedule and staffing, and it was difficult to construct a process to shorten the construction period.
【0005】[0005]
【課題を解決するための手段】上述の問題点を解決する
ため本発明においては、構築中の建物の構築階の床面上
において、その階の梁鉄筋の設定位置より下方で梁鉄筋
を組み立て、その組み立て後、揚重手段によって梁鉄筋
を設定位置に移動する。In order to solve the above-mentioned problems, in the present invention, on the floor surface of the building floor of the building under construction, the beam reinforcement is assembled below the set position of the beam reinforcement of that floor. After the assembly, the beam rebar is moved to the set position by the lifting means.
【0006】[0006]
【作用】上述のように本発明においては、構築中の建物
の構築階の床面上において、その梁鉄筋の設定位置より
下方で梁鉄筋を組み立て、その組み立て後、揚重手段に
よって梁鉄筋を設定位置に移動するようにしたので、先
き組みした鉄筋体を用いた従来の構築方法と同様に作業
能率のよい施工ができるだけでなく、本発明によれば、
柱、梁、壁の配筋後に型枠を建て込むことになるので、
鉄筋工事と型枠工事が交錯しなくなる。As described above, in the present invention, on the floor surface of the building floor of the building under construction, the beam reinforcing bars are assembled below the set position of the beam reinforcing bars, and after the assembly, the beam reinforcing bars are lifted by the lifting means. Since it is moved to the set position, not only can construction with good work efficiency be performed similarly to the conventional construction method using the pre-assembled rebar body, but according to the present invention,
Since the formwork will be built after the arrangement of columns, beams, and walls,
Reinforcing bar work and formwork work will not be mixed.
【0007】[0007]
【実施例】以下、図面について本発明の実施例を説明す
る。図1は鉄筋コンクリート構造の多層階の建物におい
て、下階のコンクリートの打設および養生が完了した
後、これから上階を構築しようとする状態の建物の床面
1の一部を示すもので、2は床面1上に突出している柱
の主筋の一部、3はクレーン(図示せず)等によって吊
り上げて床面1上に搬送しようとしている組み立てスタ
ンドで、床面1上にはすでに運ばれた組み立てスタンド
3が置かれている。この他図示してはいないが鉄筋等の
必要な資材は床面1上に運び込んでおく。Embodiments of the present invention will be described below with reference to the drawings. Fig. 1 shows a part of a floor surface 1 of a building of a multi-story building having a reinforced concrete structure, in which the construction and curing of the concrete of the lower floor are completed and the upper floor is about to be constructed. Is a part of the main bar of the pillar projecting on the floor 1 and 3 is an assembly stand that is being lifted by a crane (not shown) or the like to be transported onto the floor 1, and has already been transported to the floor 1. The assembly stand 3 is placed. Although not shown, necessary materials such as reinforcing bars are carried on the floor surface 1 in advance.
【0008】つぎに、図2に示すように、床面1上の所
定の位置(梁の直下の位置)に組み立てスタンド3を配
置し、これらの組み立てスタンド3を利用して図3に示
すように梁鉄筋A,B,C,Dを組み立てる。なおこれ
らの梁鉄筋A〜Dを組み立てる前に柱の主筋2を延長し
て立設すると共に、必要とするフープ筋4を主筋2の下
部に嵌め込んでおく。Next, as shown in FIG. 2, the assembly stand 3 is arranged at a predetermined position on the floor surface 1 (a position directly below the beam), and these assembly stands 3 are used as shown in FIG. Assemble the beam reinforcements A, B, C, and D. Before assembling these beam reinforcements A to D, the main reinforcement 2 of the column is extended and erected, and the necessary hoop reinforcement 4 is fitted into the lower portion of the main reinforcement 2.
【0009】梁鉄筋A〜Dを組み立てるには、図4に示
すように、まず、組み立てスタンド3上に2本の上端主
筋5,5を載置すると共に、これらの主筋5に必要数の
スタラップ筋6を嵌合しておき、これらのスタラップ筋
6内に2本の下端主筋7,7を挿入し、スタラップ筋6
を所定の間隔にセットすると共に、主筋5,7とそれぞ
れ固定する。この梁鉄筋A〜Dの組み立ては組み立てス
タンド3上の低い位置で行われるから作業が容易かつ能
率的に行われる。In order to assemble the beam rebars A to D, first, as shown in FIG. 4, two upper main rebars 5 and 5 are placed on the assembly stand 3, and a required number of stalaps are provided on these main rebars 5. The muscles 6 are fitted together, and the two lower end main muscles 7, 7 are inserted into these stirrup muscles 6,
Is set at a predetermined interval and is fixed to the main bars 5 and 7, respectively. Since the beam rebars A to D are assembled at a low position on the assembly stand 3, the work is easily and efficiently performed.
【0010】図3に示すように梁鉄筋A〜Dの組み立て
が了ったならば、図5に示すように、組み立ての完了し
た梁鉄筋A〜Dをクレーン、ハイリフト、油圧ジヤッキ
等で梁桁の設定位置まで揚重する。すなわち図6に示す
ように、梁鉄筋A〜Dの上端主筋5,5の下方にかんざ
し部材8を挿通し、そのかんざし部材8を介して設定位
置に揚重した状態でかんざし部材8の両端を支持部材
(サポート)9によって支承する。When the beam rebars A to D are assembled as shown in FIG. 3, the assembled beam rebars A to D are beamed by a crane, a high lift, a hydraulic jack, etc., as shown in FIG. Lift to the set position of. That is, as shown in FIG. 6, the hairpin members 8 are inserted under the upper end main bars 5, 5 of the beam rebars A to D, and both ends of the hairpin member 8 are lifted to a set position via the hairpin members 8. It is supported by a support member (support) 9.
【0011】つぎに図7に示すように、柱の主筋2の下
部に嵌合しておいた多数のフープ筋4を、梁鉄筋A〜D
の下方の柱の主筋2に対して略均等に分布して固定す
る。また図8は梁鉄筋B,Dと床面1との間に壁用の配
筋10を施行した状態を示すものである。Next, as shown in FIG. 7, a large number of hoop reinforcements 4 fitted under the main reinforcements 2 of the column are attached to beam reinforcements A to D.
Are fixed to the main bars 2 of the pillars below in a substantially even distribution. Further, FIG. 8 shows a state in which wall reinforcements 10 are provided between the beam reinforcements B and D and the floor surface 1.
【0012】尚、図8の配筋10には、施工機器の床面1
上の移動を容易にする為、開口10aを設けてある。この
ように開口10a を設けておくと、梁筋を揚重する機器(
施工ロボット) を工区ごとに移動する際、ロボットの移
動が容易になる。この施工ロボットは、揚重用の他、壁
の配筋、型枠の組み立て、非耐力壁の構築、ガラスの取
り付けに使用されるものを含む。また開口10a を設けら
れない場合は、バルコニー部分等を利用して次の工区へ
移動する。その際、施工ロボットの重量にもよるが、重
量を軽減するためには分割ロボットを使用するのが良
い。The bar arrangement 10 shown in FIG. 8 includes a floor surface 1 of construction equipment.
An opening 10a is provided to facilitate the upward movement. If the opening 10a is provided in this way, a device for lifting the beam reinforcement (
When moving the construction robot) to each work area, the movement of the robot becomes easy. The construction robots include those used for lifting, as well as wall reinforcement, formwork assembly, non-bearing wall construction, and glass attachment. If the opening 10a cannot be provided, use the balcony or the like to move to the next work area. At this time, although it depends on the weight of the construction robot, it is preferable to use a split robot in order to reduce the weight.
【0013】上述した図1〜図8に示した梁鉄筋A〜D
の接合部は、桁梁A,Cにおいては、梁の中央部が適し
ており、スパン梁B,Dの場合は、梁の中央又は両端部
で接合するのが良い。また桁梁A,Cのみを配筋後揚重
する様にして、耐震壁10のあるスパン梁B,Dは、型枠
を設置した後、その型枠内に落し込む様にしても良い。
すなわち、耐震壁10のあるスパン梁B,Dは、主筋径そ
のものが、小径であるり、かつ、主筋本数も少ないのが
通常であるためたわみが生じやすい場合があるから、多
数の支持部材が必要となる。したがって、このような場
合は、揚重方法によるよりも、落し込みの方が配筋しや
すい。Beam rebars A to D shown in FIGS. 1 to 8 described above.
In the case of the girder beams A and C, the central portion of the beam is suitable, and in the case of the span beams B and D, the central portion or both end portions of the beam are preferably joined. Alternatively, only the girder beams A and C may be lifted after the reinforcement, and the span beams B and D having the seismic wall 10 may be dropped into the form frame after the form frame is installed.
That is, in the span beams B and D with the seismic wall 10, since the diameter of the main bar itself is small and the number of main bars is usually small, bending may occur easily, and therefore a large number of supporting members are required. Will be needed. Therefore, in such a case, the drop-in method is easier than the lifting method.
【0014】図9はラーメン構造において、平面形状を
十字形に先き組みされた梁鉄筋A,B,Dを柱の主筋2
に対して支承する別の方法を示すもので、この方法は、
各梁鉄筋A,B,Dに挿通したかんざし部材8と、柱の
主筋2に取り付けた部材11との間を索12により支承する
ものである。そして柱と梁の鉄筋は、所定の位置におい
て接合治具または番線(図示せず)等によって連結固定
する。なお梁鉄筋同志は、この場合梁の中央部でそれぞ
れ連結すればよい。この方法によれば、前述の揚重手段
によって、揚重された梁筋を支持部材9により支承する
必要がなく、床面1上での機器の移動等、作業性が良く
なる。FIG. 9 shows a main frame 2 of a column with beam reinforcements A, B and D, which are assembled in a cruciform shape in plan view in a rigid frame structure.
This is another way to support
A rope 12 is used to support between a hairpin member 8 inserted through each beam rebar A, B, D and a member 11 attached to a main bar 2 of a column. Then, the reinforcing bars of the pillar and the beam are connected and fixed at a predetermined position by a joining jig or a wire (not shown). In this case, the beam reinforcements may be connected to each other at the center of the beam. According to this method, it is not necessary to support the beam reinforcement lifted by the above-mentioned lifting means by the support member 9, and workability such as movement of equipment on the floor surface 1 is improved.
【0015】以上、梁鉄筋の施工方法について説明した
が、実施工では、例えば、次の様な手順で行なわれる。
すなわち図10に示すように、1フロアーが8スパン(例
えば1スパンは、耐震壁13と耐震壁13の間)の建物で
は、2スパンごとに水平工区割りし、第1工区で上述の
柱、梁、壁の配筋施工を行い、完了後、第2工区へ移動
する。つぎに第1工区では、柱、梁、壁、床の型枠施工
を行い、その後、床スラブの下面までコンクリートを打
設する。その間に第2工区での配筋施工が完了する。つ
ぎに、配筋施工は、第3工区へ移り、柱、梁、壁、床の
型枠施工は第2工区へ移る。この時第1工区では、バル
コニー14および廊下部分15の型枠施工と、床16、バルコ
ニー14、廊下部分15の配筋が行なわれ、その後コンクリ
ートが打設される。The method of constructing the beam reinforcing bars has been described above, but the actual work is performed, for example, in the following procedure.
That is, as shown in FIG. 10, in a building in which one floor has 8 spans (for example, 1 span is between the seismic wall 13 and the seismic wall 13), the horizontal construction section is divided into 2 spans, and the above-mentioned pillars in the 1st section Beams and walls will be reinforced, and after completion, move to the 2nd work area. Next, in the 1st construction section, formwork for pillars, beams, walls, and floors is performed, and then concrete is placed up to the lower surface of the floor slab. In the meantime, the reinforcement work in the 2nd construction section is completed. Next, the bar arrangement work moves to the third work area, and the formwork work for columns, beams, walls, and floors moves to the second work area. At this time, in the first construction section, the formwork of the balcony 14 and the corridor portion 15 is performed, the floor 16, the balcony 14, and the corridor portion 15 are laid out, and then concrete is poured.
【0016】[0016]
【発明の効果】上述のように本発明においては、構築中
の建物の構築階の床面1上において、その梁鉄筋の設定
位置より下方で梁鉄筋A〜Dを組み立て、その組み立て
後、揚重手段によって梁鉄筋を設定位置に移動するよう
にしたので、低位置での梁鉄筋の組み立てが容易である
上に、余分な敷地を必要としない。したがって本発明は
先き組みした鉄筋体を用いた従来の構築方法と同様に作
業能率のよい施工ができるだけでなく、本発明によれ
ば、柱、梁、壁の配筋後に型枠を建て込むことになるの
で、鉄筋工事と型枠工事が交錯しなくなるという効果が
得られる。As described above, in the present invention, on the floor surface 1 of the building floor of the building under construction, the beam reinforcing bars A to D are assembled below the set position of the beam reinforcing bars, and after the assembly, the lifting is performed. Since the beam rebar is moved to the set position by the heavy means, the beam rebar can be easily assembled in the low position and no additional site is required. Therefore, according to the present invention, not only can the construction with good work efficiency be performed similarly to the conventional construction method using the previously assembled rebar body, but according to the present invention, the formwork is built after the reinforcement of the columns, beams and walls. As a result, it is possible to obtain the effect that the reinforcing bar construction and the formwork construction do not mix.
【図1】本発明方法による梁鉄筋の組み立て前における
床面上の斜視図である。FIG. 1 is a perspective view on a floor surface before assembling a beam reinforcing bar by a method of the present invention.
【図2】図1の床面上に組み立てスタンドを配置した状
態を示す斜視図である。FIG. 2 is a perspective view showing a state in which an assembly stand is arranged on the floor surface of FIG.
【図3】図2の組み立てスタンド上において梁鉄筋を組
み立てた状態を示す斜視図である。FIG. 3 is a perspective view showing a state where beam reinforcing bars are assembled on the assembly stand of FIG.
【図4】組み立てスタンド上で組み立てた梁鉄筋の部分
断面図である。FIG. 4 is a partial cross-sectional view of a beam reinforcing bar assembled on an assembly stand.
【図5】図3の各梁鉄筋を設定位置まで揚重した状態を
示す斜視図である。FIG. 5 is a perspective view showing a state in which each beam rebar of FIG. 3 is lifted to a set position.
【図6】図4の梁鉄筋を設定位置まで上昇させて支持部
材により支承した状態を示す立面図である。FIG. 6 is an elevational view showing a state where the beam reinforcing bar of FIG. 4 is raised to a set position and supported by a supporting member.
【図7】図5の柱のフープ筋を所定の位置に分布して固
定した状態を示す斜視図である。FIG. 7 is a perspective view showing a state in which the hoop muscles of the pillar of FIG. 5 are distributed and fixed at predetermined positions.
【図8】図7の梁鉄筋と床面上に必要な壁の配筋を施し
た状態を示す斜視図である。FIG. 8 is a perspective view showing a state in which necessary reinforcing bars are arranged on the beam reinforcing bar and the floor surface of FIG.
【図9】梁鉄筋の別な揚重方法を示す斜視図である。FIG. 9 is a perspective view showing another method of lifting a beam reinforcing bar.
【図10】実際の施工例を示す建物の平面図である。FIG. 10 is a plan view of a building showing an actual construction example.
1 床面 2 柱の主筋 3 組み立てスタンド A,B,C,D 梁鉄筋 4 フープ筋 5 上端主筋 6 スタラップ筋 7 下端主筋 8 かんざし部材 9 支持部材(サポート) 10 壁用の配筋 11 柱の主筋に取り付けた部材 12 索 13 耐震壁 14 バルコニー 15 廊下部分 16 床 1 Floor surface 2 Main reinforcement of columns 3 Assembly stand A, B, C, D Beam reinforcement 4 Hoop reinforcement 5 Upper main reinforcement 6 Strap reinforcement 7 Lower main reinforcement 8 Knocking member 9 Support member (support) 10 Main reinforcement for wall 11 Column reinforcement Member attached to 12 Cables 13 Seismic wall 14 Balcony 15 Corridor 16 Floor
Claims (1)
て、その階の梁鉄筋の設定位置より下方で梁鉄筋を組み
立て、その組み立て後、揚重手段によって梁鉄筋を設定
位置に移動することを特徴とする梁鉄筋の組み立て方
法。1. A beam reinforcing bar is assembled on a floor surface of a building floor of a building under construction below a setting position of a beam reinforcing bar of that floor, and after the assembly, the beam reinforcing bar is moved to a setting position by a lifting means. A method for assembling a beam rebar characterized by the following.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24291993A JP3187618B2 (en) | 1993-09-29 | 1993-09-29 | How to assemble beam reinforcement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24291993A JP3187618B2 (en) | 1993-09-29 | 1993-09-29 | How to assemble beam reinforcement |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0797865A true JPH0797865A (en) | 1995-04-11 |
JP3187618B2 JP3187618B2 (en) | 2001-07-11 |
Family
ID=17096166
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP24291993A Expired - Fee Related JP3187618B2 (en) | 1993-09-29 | 1993-09-29 | How to assemble beam reinforcement |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3187618B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102383608A (en) * | 2011-08-19 | 2012-03-21 | 中建三局第二建设工程有限责任公司 | Lifting device capable of being repeatedly used for steel reinforcement cage |
JP2013049973A (en) * | 2011-08-31 | 2013-03-14 | Toshiharu Horimoto | Construction method of skeleton structure made of reinforced concrete |
-
1993
- 1993-09-29 JP JP24291993A patent/JP3187618B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102383608A (en) * | 2011-08-19 | 2012-03-21 | 中建三局第二建设工程有限责任公司 | Lifting device capable of being repeatedly used for steel reinforcement cage |
JP2013049973A (en) * | 2011-08-31 | 2013-03-14 | Toshiharu Horimoto | Construction method of skeleton structure made of reinforced concrete |
Also Published As
Publication number | Publication date |
---|---|
JP3187618B2 (en) | 2001-07-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4023315A (en) | Prefabricated buildings | |
JPH0797865A (en) | Assembly of beam steel reinforcement | |
JPH0434161A (en) | Centrifugally molded hollow pc concrete column and column construction method | |
JP2852626B2 (en) | Construction method of slab using arch slab plate | |
KR950032934A (en) | Construction method of high-rise building | |
JPH04146345A (en) | Self-ascending device for large roof for architectural work, and constructing method for medium/high-rise building | |
JPH02311639A (en) | Construction of composite floor | |
JP2002194892A (en) | Construction method of building | |
JP2000160686A (en) | Composite structure of reinforced concrete column and steel frame beam, and its execution | |
JPH0447737B2 (en) | ||
JPH03187436A (en) | Supporting member for construction pillar of reinforced concrete building | |
JPH03197734A (en) | Lift up method by replacement of scaffold body | |
JPH0528248Y2 (en) | ||
JPH08193422A (en) | Construction method for building | |
JPH0437893B2 (en) | ||
JP2984626B2 (en) | PC pillar construction method and its PC pillar | |
JP2759360B2 (en) | Construction method of reinforced concrete building | |
JPH05222763A (en) | Construction method of prestressed concrete @(3754/24)pc) beam | |
JP2529610B2 (en) | Floating structure | |
JPH05179694A (en) | Construction method of building | |
JPH0571747B2 (en) | ||
JPH0715177B2 (en) | How to build a reinforced concrete structure | |
JPH04222731A (en) | Construction work of reinforced concrete-made extra-high building by use of precast post | |
JPH0621469B2 (en) | Multi-story building frame construction method | |
JPH05248020A (en) | Execution method for bearing floor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080511 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090511 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100511 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 10 Free format text: PAYMENT UNTIL: 20110511 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120511 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130511 Year of fee payment: 12 |
|
LAPS | Cancellation because of no payment of annual fees |