JPH0765297B2 - How to erection a cane ramen bridge - Google Patents
How to erection a cane ramen bridgeInfo
- Publication number
- JPH0765297B2 JPH0765297B2 JP1157309A JP15730989A JPH0765297B2 JP H0765297 B2 JPH0765297 B2 JP H0765297B2 JP 1157309 A JP1157309 A JP 1157309A JP 15730989 A JP15730989 A JP 15730989A JP H0765297 B2 JPH0765297 B2 JP H0765297B2
- Authority
- JP
- Japan
- Prior art keywords
- diagonal
- cane
- main
- bridge
- erection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は支間数十m程度のコンクリートを主体とした方
杖ラーメン橋の架設方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of use] The present invention relates to a method for constructing a cane ramen bridge mainly made of concrete having a span of several tens of meters.
従来の中規模径間(支間50m程度)のコンクリート橋の
架設は、概ね支保工を用いるか、押し出し工法で連続架
設することにより行われている。Conventional concrete bridges with medium-scale spans (branches of about 50 m) are generally erected by shoring or continuously erected by extrusion.
このうち、方杖ラーメン橋については場所打ちコンクリ
ート施工、プレキャストブロック施工とも、一般に支保
工による架橋が行われている。Of these, bridge construction by shoring is generally used for cast-in-place concrete construction and precast block construction for the cane ramen bridge.
しかし、支保工による施工は、橋梁下の条件に左右され
るため、連続施工、多径間の橋梁にはあまり適さない。
また、V字谷などにおける施工では、大規模な架設設備
が必要となり、不経済である。一方、押し出し工法は多
径間の施工には適しているが、単径間あるいは数径間程
度の施工には仮設設備が大きすぎ、コスト的に不適当と
考えられる。つまり、コンクリート橋の中規模径間で
は、汎用の経済性に富んだ橋梁仮設工法が確立されてい
ないのが現状である。However, since the construction by shoring depends on the conditions under the bridge, it is not suitable for continuous construction and bridges with multiple spans.
In addition, construction in a V-shaped valley is uneconomical because large-scale erection equipment is required. On the other hand, although the extrusion method is suitable for multi-span construction, the temporary equipment is too large for construction with a single span or several spans, and is considered to be unsuitable in terms of cost. In other words, for the medium-scale spans of concrete bridges, a general-purpose economical bridge temporary construction method has not yet been established.
本発明は上述のような事情のもとに発明されたものであ
り、現場施工が簡略化され、使用架設資材を減少でき、
従って、工期工費の削減が図れ、また多径間架橋にも適
用可能な方杖ラーメン橋の架設方法を提供することを目
的としている。The present invention was invented under the circumstances as described above, the on-site construction is simplified, and the erection materials used can be reduced,
Therefore, it is an object of the present invention to provide a method for erection of a cane ramen bridge which can reduce the construction period construction cost and can be applied to multi span span bridges.
以下、本発明の概要を実施例に対応する図面の符号を用
いて説明する。Hereinafter, the outline of the present invention will be described using the reference numerals of the drawings corresponding to the embodiments.
本発明は所定間隔をおいて構築される主橋脚1と、主橋
脚1間に架設される上床版2と、上床版2を方杖状に斜
めに支持する斜材3および必要に応じ斜材3上に設置さ
れ、上床版2を支持する支柱4により構成される方杖ラ
ーメン橋の構造を応用し、その架設を行うものである。BEST MODE FOR CARRYING OUT THE INVENTION The present invention relates to a main bridge pier 1 constructed at predetermined intervals, an upper floor slab 2 installed between the main piers 1, a diagonal member 3 for diagonally supporting the upper floor slab 2 in a cane shape, and a diagonal member if necessary. The construction is performed by applying the structure of a cane ramen bridge which is installed on 3 and is composed of columns 4 supporting the upper floor slab 2.
本発明の架設方法では主橋脚1の構築後、主橋脚1の斜
材支持位置にヒンジ6を設け、このヒンジ6上に斜材3
を仮支持の状態で構築する。斜材3はプレキャストコン
クリート製でも、場所打ちにより製作されるものであっ
てもよい。次に、斜材3を仮支持の状態からヒンジ回り
に回転させ、所定の高さで、高張力鋼などからなる吊り
材5により主橋脚1に対し斜めに支持する。この状態か
ら吊り材5の緊張力を調整し、後から作用する上載荷重
に耐えるようにしながら、主橋脚1および斜材3上での
上床版2の架設を連続的に行い、1径間の施工を完了す
る。多径間の橋梁ではこの作業を繰り返すか、あるいは
平行作業により架設して行くことができる。In the erection method of the present invention, after the main pier 1 is constructed, the hinge 6 is provided at the diagonal member supporting position of the main pier 1, and the diagonal member 3 is placed on the hinge 6.
Is built with temporary support. The diagonal member 3 may be made of precast concrete or cast in place. Next, the diagonal member 3 is rotated around the hinge from the temporarily supported state, and is obliquely supported to the main pier 1 at a predetermined height by the suspending member 5 made of high-tensile steel or the like. From this state, the tension of the suspension member 5 is adjusted to withstand the load applied later, and the upper deck 2 is continuously erected on the main bridge pier 1 and the diagonal member 3 and the span of one span is maintained. Complete the construction. For bridges with multiple diameters, this work can be repeated or laid in parallel.
なお、完成系では架設時の吊り材5が上部工反力を受け
持つ引張部材として働き、斜材3および上床版2の部材
断面を大幅に減少することができる。In the completed system, the suspending member 5 at the time of installation works as a tension member that bears the reaction force of the upper work, and the member cross sections of the diagonal member 3 and the upper floor slab 2 can be greatly reduced.
次に実施例として支間50m程度の橋梁の架設について、
図面を参照しながら説明する。Next, as an example, regarding the construction of a bridge with a span of about 50 m,
A description will be given with reference to the drawings.
後述する実施例において、上床版2は5径間連続構造と
する。In the examples described later, the upper floor slab 2 has a continuous structure with 5 spans.
例−1 例−1は連続径間橋における空中施工を想定して、一方
向よりの施工を前提とした場合であり、以下の手順で施
工を行う。Example-1 Example-1 is based on the assumption that the continuous span bridge will be constructed in the air, and is constructed in one direction.
主橋脚1の斜材支持位置に仮支持用ヒンジ6を設置す
る(第1図参照)。A temporary support hinge 6 is installed at the diagonal support position of the main pier 1 (see FIG. 1).
プレキャスト部材または場所打ちコンクリート部材に
より、仮支持用ヒンジ6上に斜材3を垂直に組み立て
る。The diagonal member 3 is vertically assembled on the temporary supporting hinge 6 by a precast member or a cast-in-place concrete member.
斜吊工法もしくは揚重機で、斜材3を所定の架設位置
に設置し、主橋脚1から張り出した吊り材5としての高
張力鋼で固定する(第2図参照)。The slant member 3 is installed at a predetermined erection position by the oblique suspension method or a lifting machine, and is fixed with the high-strength steel as the suspending member 5 protruding from the main pier 1 (see FIG. 2).
斜材3上に所定間隔で支柱4を設ける(本実施例では
斜材3上の1箇所だけとなっている)。The support columns 4 are provided on the diagonal member 3 at predetermined intervals (in the present embodiment, there is only one position on the diagonal member 3).
上床版2を片側の主橋脚1から順次施工する(第3図
参照)。上床版2の自重および作業荷重によって、斜材
3の断面力が過大になる場合は、主橋脚1より高張力鋼
を適用した第2の吊り材5aを設置し、断面力を調整する
(第4図参照)。上床版2の施工は1径間ずつ、プレキ
ャスト工法または場所打ちコンクリート工法にて構築
し、架設時の断面力に対してプレストレスを導入する。
この手順を繰り返し主橋脚1より相対する主橋脚1まで
上床版2の構築が終了すれば、架設時のプレストレスに
追加して完成系のプレストレスを導入する(第5図〜第
7図参照)。The upper deck slab 2 is constructed sequentially from the main pier 1 on one side (see Fig. 3). If the cross-sectional force of the diagonal members 3 becomes excessive due to the weight of the upper deck 2 and the work load, a second suspension member 5a made of high-tensile steel is installed from the main pier 1 to adjust the cross-sectional force (No. (See Fig. 4). The construction of the upper floor slab 2 is constructed by a pre-cast method or a cast-in-place concrete method for every one span, and pre-stress is introduced to the cross-sectional force at the time of erection.
When this procedure is repeated and the construction of the upper deck 2 from the main pier 1 to the main pier 1 opposite to the main pier 1 is completed, the prestress of the completed system is introduced in addition to the prestress at the time of erection (see Figs. 5 to 7). ).
以上の〜の手順を繰り返し、次径間の架設を行
う。Repeat steps (1) to (3) above to construct the next span.
例−2 例−2は架設ヤードの設置が可能な場合であり、任意の
部分(例えば、中央部)から上床版2を架設することが
でき、例えば以下の手順で施工を行う。Example-2 Example-2 is a case where a construction yard can be installed, and the upper floor slab 2 can be erected from an arbitrary portion (for example, the central portion). For example, the construction is performed by the following procedure.
例−1の、と同様の手順により、隣合う両主橋脚
1について、仮支持用ヒンジ6上に斜材3を垂直に組み
立てる。By the same procedure as in Example-1, the diagonal members 3 are vertically assembled on the temporary supporting hinges 6 for the two adjacent main piers 1.
例−1のと同様、斜吊工法もしくは揚重機で、相対
する斜材3を所定の架設位置に設置し、それぞれ主橋脚
1から張り出した吊り材5で固定する(第8図参照)。In the same manner as in Example-1, the diagonal slanting method or the lifting machine is used to install the opposing slant members 3 at predetermined erection positions and fix them with the suspending members 5 projecting from the main pier 1 (see Fig. 8).
両斜材3上に所定間隔で支柱4を設ける。上床版2の
自重および作業荷重によって、斜材3の断面力が過大に
なる場合は、第2吊り材5aを設置し、断面力を調整する
(第9図参照)。Supports 4 are provided on both diagonal members 3 at predetermined intervals. If the sectional force of the diagonal member 3 becomes excessive due to the weight of the upper floor slab 2 and the work load, the second suspending member 5a is installed to adjust the sectional force (see FIG. 9).
中央の上床版2を架設し、両斜材3を連結する(第10
図参照)。The central upper floor slab 2 is erected and both diagonal members 3 are connected (No. 10
See figure).
両斜材3の連結後、不要となった第2吊り材5aを撤去
し、順次両側の上床版2の架設を行う。両主橋脚1間の
上床版2の構築が終了すれば、架設時のプレストレスに
追加して完成系のプレストレスを導入する(第11図〜第
12図参照)。After connecting the both diagonal members 3, the unnecessary second hanging member 5a is removed, and the upper floor slabs 2 on both sides are sequentially erected. When the construction of the upper floor slab 2 between both main piers 1 is completed, the prestress of the completed system is introduced in addition to the prestress at the time of erection (Fig. 11-Fig.
(See Figure 12).
以上の〜の手順を繰り返し、次径間の架設を行
う。Repeat steps (1) to (3) above to construct the next span.
例−3 例−3は上床版2を第18図に示すように鋼板2bと現場打
ちコンクリート2aからなる合成スラブとした場合(図
中、右半分が支間中央部、左半分が横桁部の断面)であ
り、以下の手順で施工を行う。Example-3 In Example-3, the upper floor slab 2 is a composite slab consisting of steel plate 2b and cast-in-place concrete 2a as shown in Fig. 18 (in the figure, the right half is the center of the span and the left half is the cross beam part). It is a cross section) and the construction is performed according to the following procedure.
例−2の〜と同様の手順により、隣合う両主橋脚
1について、相対する斜材3を所定の架設位置に設置
し、それぞれ主橋脚1から張り出した吊り材5で固定す
る(第13図参照)。By the same procedure as in Example-2, the opposing diagonal members 3 are installed at the predetermined erection positions for the two adjacent main piers 1 and are fixed by the suspension members 5 projecting from the main pier 1 (Fig. 13). reference).
両斜材3上に所定間隔で支柱4を設ける。上床版2の
自重および作業荷重によって、斜材3の断面力が過大に
なる場合は、第2吊り材5aを設置し、断面力を調整する
(第14図参照)。Supports 4 are provided on both diagonal members 3 at predetermined intervals. If the sectional force of the diagonal member 3 becomes excessive due to the weight of the upper floor slab 2 and the work load, the second suspending member 5a is installed to adjust the sectional force (see FIG. 14).
合成スラブ構造の上床版2を構成する支保工兼用型枠
2bを架設する(第15図参照)。Formwork that also serves as a support for the upper floor slab 2 of the synthetic slab structure
Install 2b (see Figure 15).
鋼板2b上にコンクリート2aを打設し、上床版2を構成
する(第16図参照) 不要となった第2吊り材5aを撤去し、架設時のプレス
トレスに追加して完成系のプレストレスを導入する(第
17図参照)。Precast concrete 2a by placing concrete 2a on steel plate 2b to form upper floor slab 2 (see Fig. 16). Remove unnecessary second suspension material 5a and add it to the prestress during erection. Introduce (No.
(See Figure 17).
以上の〜の手順を繰り返し、次径間の架設を行
う。Repeat steps (1) to (3) above to construct the next span.
〔発明の効果〕 方杖ラーメン橋の構造における吊り材と、コンクリー
トの特性を組み合わせた施工法であり、部材断面を抑え
ることができる。すなわち、架設時においては、斜材と
吊り材が自重や上床版等の上載荷重に応じて荷重を静的
に負担し、完成系においては斜材とそのまま緊張力が導
入された吊り材との組み合わせによりラーメン構造にお
ける軸力と曲げを負担し座屈に対する部材断面を小さく
することができる。[Advantages of the Invention] This is a construction method in which the characteristics of concrete and hanging materials in the structure of a cane ramen bridge are combined, and the member cross section can be suppressed. That is, at the time of erection, the diagonal members and the hanging members statically bear the load according to the dead weight and the top load such as the floor slab. The combination can bear the axial force and bending in the rigid frame structure and reduce the member cross section against buckling.
支保工を使用しないので、架橋地点の施工条件に左右
されずに架設できる。Since no support work is used, it can be installed regardless of the construction conditions at the bridge.
プレキャスト部材を用いることができるので、施工工
期が短縮できる。Since a precast member can be used, the construction period can be shortened.
第1図〜第7図は本発明の実施例としての例−1におけ
る施工手順を示す方杖ラーメン橋の側面図、第8図〜第
12図は同じく例−2における施工手順を示す側面図、第
13図〜第17図は同じく例−3における施工手順を示す側
面図、第18図は例−3における橋軸直角方向の断面図で
ある。 1……主橋脚、2……上床版、2a……場所打ちコンクリ
ート、2b……合成スラブ工法用支保工兼用型枠、3……
斜材、4……支柱、5……吊り材、5a……第2吊り材、
6……仮支持用ヒンジ1 to 7 are side views of a cane ramen bridge showing the construction procedure in Example-1 as an embodiment of the present invention, and FIGS.
Figure 12 is a side view showing the construction procedure of Example-2,
13 to 17 are side views showing the construction procedure in Example-3, and FIG. 18 is a cross-sectional view in the direction perpendicular to the bridge axis in Example-3. 1 ... Main bridge pier, 2 ... Upper slab, 2a …… Spot-cast concrete, 2b …… Synthetic slab method and supporting formwork, 3 ……
Slanting material, 4 ... Support pillar, 5 ... Hanging material, 5a ... Second hanging material,
6 ... Hinges for temporary support
Claims (2)
橋脚間に架設される上床版と、該上床版の方杖状に斜め
に支持する斜材とからなる方杖ラーメン橋の架設方法で
あって、主橋脚の構築後、主橋脚の斜材支持位置にヒン
ジを設け、該ヒンジ上に仮支持の状態で構築した斜材を
ヒンジ回りに回転させ、所定の高さで吊り材により主橋
脚に対し斜めに支持し、該吊り材の緊張力を後から作用
する上載荷重に耐えるように調整しながら、前記主橋脚
および前記斜材上に上床版を連続的に架設することを特
徴とする方杖ラーメン橋の架設方法。1. A cane ramen bridge comprising a main bridge pier constructed at predetermined intervals, an upper deck slab installed between the main bridge piers, and a diagonal member diagonally supporting the upper deck slab in the shape of a cane. A method of erection, in which after construction of the main pier, a hinge is provided at the diagonal support position of the main pier, and the diagonal constructed in the temporarily supported state on the hinge is rotated around the hinge and hung at a predetermined height. Supporting the main bridge pier diagonally with timber and adjusting the tension of the hanging material so as to withstand the overload that acts later, while continuously installing the upper deck on the main pier and the diagonal timber. A method of erection of a cane ramen bridge characterized by.
を調整しながら、さらに1または2以上の支柱を設け、
前記上床版を前記主橋脚、前記支柱および前記斜材上に
連続的に架設する請求項1記載の方杖ラーメン橋の架設
方法。2. An upper middle portion of the diagonal member is provided with one or more columns while adjusting the tension of the hanging member.
The method for constructing a cane ramen bridge according to claim 1, wherein the upper deck slab is continuously erected on the main bridge piers, the columns and the diagonal members.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1157309A JPH0765297B2 (en) | 1989-06-20 | 1989-06-20 | How to erection a cane ramen bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1157309A JPH0765297B2 (en) | 1989-06-20 | 1989-06-20 | How to erection a cane ramen bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0325107A JPH0325107A (en) | 1991-02-01 |
JPH0765297B2 true JPH0765297B2 (en) | 1995-07-19 |
Family
ID=15646857
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1157309A Expired - Fee Related JPH0765297B2 (en) | 1989-06-20 | 1989-06-20 | How to erection a cane ramen bridge |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0765297B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5050228B2 (en) * | 2005-11-10 | 2012-10-17 | 株式会社横河ブリッジ | Ramen bridge construction method with cane member |
DE102006039551B3 (en) * | 2006-08-23 | 2007-09-20 | Kollegger, Johann, Prof. Dr.-Ing. | Bridge manufacturing method involves articulating end point of support rod with bridge carrier, and column, a bridge carrier with end points and support rod with end points is manufactured in perpendicular position |
JP5189546B2 (en) * | 2009-04-01 | 2013-04-24 | 三井住友建設株式会社 | Construction method of Nakaji arch bridge |
JP6573277B2 (en) * | 2015-11-02 | 2019-09-11 | 三井住友建設株式会社 | How to build a main tower or pier |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3403140C1 (en) * | 1984-01-31 | 1985-07-11 | Dyckerhoff & Widmann AG, 8000 München | Structure, in particular bridge structure |
JPH01151604A (en) * | 1987-12-07 | 1989-06-14 | Oriental Concrete Kk | Method of erecting arch ring by lower ring system |
-
1989
- 1989-06-20 JP JP1157309A patent/JPH0765297B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0325107A (en) | 1991-02-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113638304B (en) | Concrete beam type bridge hidden cover beam structure system and construction method thereof | |
JP3844743B2 (en) | Box girder bridge structure and its construction method | |
JP3737475B2 (en) | Box girder bridge structure and construction method | |
JP4336659B2 (en) | Construction method of upper-floor type suspension floor slab bridge | |
JP4220295B2 (en) | Corrugated steel sheet web PC bridge closure method | |
JP2001348815A (en) | Cantilever type installing construction method of bridge | |
JP2967874B1 (en) | How to build an overhead suspension bridge | |
JPH0765297B2 (en) | How to erection a cane ramen bridge | |
JPS6282147A (en) | Novel prestressed synthetic beam and its construction | |
JP2001172913A (en) | Elevated bridge and its construction method | |
JP4375788B2 (en) | Construction method of upper-floor type suspension floor slab bridge | |
JP2852626B2 (en) | Construction method of slab using arch slab plate | |
JPH0634465Y2 (en) | Simple PC panel | |
JP2000104220A (en) | Erection of combined truss bridge | |
JP3908816B2 (en) | Construction method of suspended floor slab bridge | |
JP2536373B2 (en) | Concrete beam construction method | |
JP3171676B2 (en) | Construction method of cast-in-place concrete horizontal member | |
JP2584418B2 (en) | Overhang construction method and stress improvement device for synthetic cable-stayed bridge | |
JP2796943B2 (en) | Construction method of multi-span continuous steel girder with reinforced concrete slab | |
JPH06146472A (en) | Precast ferro-concrete beam | |
RU2046878C1 (en) | Bridge | |
JPH1088522A (en) | High level bridge supportless construction method | |
JP2541366B2 (en) | Concrete beams and lower concrete beam members for concrete beams | |
JP2003074020A (en) | Structure of expansion gap part in bridge, and method for erecting bridge | |
JPH052781B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |