JPH06146472A - Precast ferro-concrete beam - Google Patents

Precast ferro-concrete beam

Info

Publication number
JPH06146472A
JPH06146472A JP29878492A JP29878492A JPH06146472A JP H06146472 A JPH06146472 A JP H06146472A JP 29878492 A JP29878492 A JP 29878492A JP 29878492 A JP29878492 A JP 29878492A JP H06146472 A JPH06146472 A JP H06146472A
Authority
JP
Japan
Prior art keywords
concrete
steel pipe
steel
steel pipes
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP29878492A
Other languages
Japanese (ja)
Inventor
Kazuhiro Kaneda
和浩 金田
Takeyoshi Korenaga
健好 是永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP29878492A priority Critical patent/JPH06146472A/en
Publication of JPH06146472A publication Critical patent/JPH06146472A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To prevent a concrete beam from deflection or cracking due to a long period load and reduce the dead load of the beam. CONSTITUTION:A precast concrete beam A is so structured that a pair of steel pipes 1 are installed confronting up and down as stretching in the longitudinal direction in the central part of the beam section to be manufactured and that a plurality of beam main rods 2 are arranged at the periphery of the steel pipes. At certain intervals, rib rods 3 are arranged for a plurality of beam main rods 2, anti concrete 4 is placed in the condition that the two steel pipes 1 are tightened. When curing of the placed concrete attains a certain specified strength, the tension on the steel pipes 1 is released, and thus manufacture is completed. The beam A thus manufactured transported to the site, lifted, and set over the columns 5 to be erected.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、プレストレスを導入
し、主にロングスパンの梁に使用されるプレキャスト鉄
筋コンクリート梁に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast reinforced concrete beam which is prestressed and mainly used for a long span beam.

【0002】[0002]

【従来の技術】鉄筋コンクリート構造は、優れた経済性
故に多くの建築構造物に使用されているが、コンクリー
トは曲げ引張応力に弱いという材料特性から、梁として
横架される際の許容スパンは通常5〜8m程度までであ
る。このため、鉄筋コンクリート梁に10m以上のロン
グスパンが要求される場合には、上記コンクリート梁の
引張強度の不足を補うために、緊張材として複数のPC
鋼材をコンクリート内に埋設して、該コンクリート梁に
所定のプレストレスを導入している。
2. Description of the Related Art Reinforced concrete structures are used in many building structures because of their excellent economic efficiency. However, due to the material property that concrete is weak in bending tensile stress, the allowable span when it is laid horizontally as a beam is usually It is up to about 5 to 8 m. Therefore, when a long span of 10 m or more is required for a reinforced concrete beam, a plurality of PCs are used as a tension material in order to make up for the lack of tensile strength of the concrete beam.
A steel material is embedded in concrete to introduce a predetermined prestress to the concrete beam.

【0003】上記PC鋼材は、複数本のPC鋼線を束ね
た鋼材束やPC鋼棒からなっている。そして、そのPC
鋼材に緊張力を付与した状態で、その周りにコンクリー
トを打設し、そのコンクリートの硬化後に上記PC鋼材
に付与していた緊張を緩めて鉄筋コンクリート梁にプレ
ストレスを導入したり、コンクリートが硬化した後に上
記PC鋼材を緊張させ定着装置にて定着して、鉄筋コン
クリート梁にプレストレスを導入している。
The PC steel material comprises a steel material bundle in which a plurality of PC steel wires are bundled or a PC steel rod. And that PC
In the state where tension is applied to the steel material, concrete is placed around it, and after the concrete is hardened, the tension applied to the PC steel material is relaxed and prestress is introduced into the reinforced concrete beam, or the concrete is hardened. Later, the PC steel material was tensioned and fixed by a fixing device to introduce prestress to the reinforced concrete beam.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、スパン
が大きくなると必然的に梁せいも大きくなって重量が増
大し、プレキャスト工法によって工場等で製造した梁の
現場までの運搬や揚重作業が煩雑になる。また、上記自
重の増大に加え、材齢の経過と共に発生するPC鋼材の
レラクセーションによって、長期荷重によるたわみやひ
び割れが梁に発生する恐れもある。
However, when the span is increased, the beam is inevitably increased and the weight is increased, which complicates the transportation and hoisting work of the beam manufactured in the factory by the precast method to the site. Become. In addition to the increase in the self-weight, the relaxation of the PC steel material that occurs with the passage of material age may cause bending and cracking of the beam due to long-term load.

【0005】本発明は、上記のような問題点に着目して
なされたもので、長期荷重によるたわみやひび割れを防
止すると共に、梁自重の軽減を図ることを目的としてい
る。
The present invention has been made in view of the above problems, and it is an object of the present invention to prevent bending and cracking due to long-term load and to reduce the weight of a beam.

【0006】[0006]

【課題を解決するための手段】上記のような目的を達成
するために、本発明のプレキャスト鉄筋コンクリート梁
は、鉄筋コンクリート梁の断面中央部に、鋼管をプレテ
ンション方式で緊張させて埋設し、上記梁にプレストレ
スを導入したことを特徴としている。
In order to achieve the above-mentioned object, the precast reinforced concrete beam of the present invention comprises a steel pipe tensed by a pretensioning method and embedded in the center of the cross section of the reinforced concrete beam. It is characterized by the introduction of pre-stress.

【0007】[0007]

【作用】鋼管の内部が形成する中空部にはコンクリート
が充填されないので、鉄筋コンクリート梁の自重が軽減
されて、従来よりも運搬や揚重作業が楽になると共に、
地震時等に入力される剪断力の低減につながる。さら
に、従来の緊張材であるPC鋼材やPC鋼棒等と比較し
て、本発明の鋼管は、コンクリートと接触する表面積が
広くなることで、コンクリートに対する付着性が向上
し、これによってコンクリートと一体化する。それに加
えて、上記鋼管自身が、上下方向の荷重を支持可能であ
るので、梁の剪断剛性が増大し、もって、長期荷重によ
る梁の撓みやひび割れが防止される。また、鋼管は、P
C鋼材に比べて格段にローコストである。
[Function] Since the hollow part formed inside the steel pipe is not filled with concrete, the self-weight of the reinforced concrete beam is reduced, which makes transportation and lifting work easier than before, and
This will reduce the shearing force input during earthquakes. Furthermore, the steel pipe of the present invention has a larger surface area in contact with the concrete, as compared with the conventional tendon materials such as PC steel material and PC steel rod, thereby improving the adhesion to the concrete, thereby making it integral with the concrete. Turn into. In addition, since the steel pipe itself can support the load in the vertical direction, the shear rigidity of the beam is increased, so that the bending and cracking of the beam due to long-term load are prevented. In addition, the steel pipe is P
It is much lower cost than C steel.

【0008】なお、本発明のように緊張材として鋼管を
使用すると、上記のように剪断剛性が増大して、該鋼管
に付与する緊張力はPC鋼材を使用する場合よりも小さ
くて済むので、鋼管の肉厚を梁の強度に応じて薄くして
該鋼管自身の重量を軽量化しても構わない。また、上記
鋼管の中空部による断面欠損の影響については、剪断応
力に関しては、スパンが長い場合にはその応力レベルが
低いためにさほど問題にならず、また、曲げ応力に関し
ても、鋼管を梁断面の中央部に設けることで圧縮領域か
らはずれてその影響は小さい。更に、断面2次モーメン
トの減少による曲げ剛性の低下についても、鋼管を断面
中央部に配置することで最小限に止どめることができ
る。
When a steel pipe is used as a tension member as in the present invention, the shear rigidity increases as described above, and the tension force applied to the steel pipe can be smaller than when PC steel is used. The wall thickness of the steel pipe may be reduced according to the strength of the beam to reduce the weight of the steel pipe itself. Regarding the effect of cross-section loss due to the hollow portion of the steel pipe, shear stress is not so problematic because the stress level is low when the span is long, and bending stress is not a problem. Since it is provided in the central portion of, the effect is small as it deviates from the compression area. Further, the decrease in bending rigidity due to the decrease in the second moment of area can be minimized by arranging the steel pipe in the center of the cross section.

【0009】[0009]

【実施例】本発明の実施例を図面に基づいて説明する。
本実施例のプレキャスト鉄筋コンクリート梁Aは、図1
に示すような構成をしていて、製造する梁断面中央部
に、長手方向に沿って一対の鋼管1を上下に対向して配
置し、更に、その外周に複数の梁主筋2を配筋すると共
に、上記複数の梁主筋2に対して所定間隔毎に肋筋3を
配筋した後、上記一対の鋼管1を緊張させた状態でコン
クリート4を打設し、その打設したコンクリート4が所
定強度に達したら、上記鋼管1に付与している緊張力を
解除することで梁Aが製造される。
Embodiments of the present invention will be described with reference to the drawings.
The precast reinforced concrete beam A of this embodiment is shown in FIG.
A pair of steel pipes 1 are vertically opposed to each other along the longitudinal direction at the center of the cross section of the beam to be manufactured, and further a plurality of beam main bars 2 are arranged on the outer periphery thereof. At the same time, after arranging the ribs 3 at predetermined intervals with respect to the plurality of beam main bars 2, concrete 4 is placed in a state in which the pair of steel pipes 1 is tensioned, and the placed concrete 4 is predetermined. When the strength is reached, the tension force applied to the steel pipe 1 is released to manufacture the beam A.

【0010】そして、上記のようにして製造された梁A
を、現場まで運搬・揚重して、図2に示すように、立設
する柱5間に架設する。さらに、上記架設された梁A間
にオムニヤ板6を橋架し、その上にスラブ筋7を配筋す
ると共に、上記梁Aから上方に突設している肋筋3に沿
って梁上端主筋2aを現場で配設する。
The beam A manufactured as described above
Is transported to the site and hoisted, and is erected between the columns 5 to be erected, as shown in FIG. Further, an omnier plate 6 is bridged between the bridges A, and slab reinforcements 7 are arranged on the bridges, and the beam top main reinforcements 2a are arranged along the ribs 3 projecting upward from the above-mentioned beams A. Is installed on site.

【0011】その後に、現場打ちコンクリート8を打設
して、建物の梁A及びその梁Aの上に載るスラブが構築
される。上記のように製造されて柱5間に架設されるプ
レキャスト鉄筋コンクリート梁Aは、埋設された鋼管1
の中空部1aにコンクリート4が充填されないので、梁
Aの自重が軽減されて、従来よりも、現場への梁Aの運
搬や揚重等の作業が楽になると共に、地震時等に入力さ
れる剪断力を従来よりも小さくできる。
After that, the cast-in-place concrete 8 is poured to construct the beam A of the building and the slab to be mounted on the beam A. The precast reinforced concrete beam A manufactured as described above and installed between the pillars 5 is the embedded steel pipe 1
Since the hollow 4a is not filled with the concrete 4, the self-weight of the beam A is reduced, and the work of transporting and lifting the beam A to the site is easier than before, and it is input during an earthquake. The shearing force can be made smaller than before.

【0012】このとき、長期荷重による梁に発生する撓
みやひび割れを防止するためには、上記鋼管1で導入す
るプレストレスの大きさは、全断面平均で5〜10kgf/
cm2程度で充分である。このため、鋼管1全体に付与す
べき緊張力は小さくて済み、よって上記鋼管1の肉厚を
薄くても構わない。また、鋼管は、従来の緊張材である
PC鋼棒等に比べて表面積が広いので、コンクリートへ
の付着力が向上し、且つ、該鋼管自身が上下荷重に抵抗
可能であることによって、梁の剪断剛性が増大する。
At this time, in order to prevent bending and cracking of the beam due to long-term load, the magnitude of prestress introduced in the steel pipe 1 is 5 to 10 kgf /
A cm 2 is sufficient. Therefore, the tension force to be applied to the entire steel pipe 1 may be small, and thus the thickness of the steel pipe 1 may be thin. In addition, since the steel pipe has a larger surface area than PC steel rods or the like, which are conventional tension materials, the adhesive force to concrete is improved, and the steel pipe itself can resist vertical load, so that Shear stiffness is increased.

【0013】この剪断剛性の増大に加えて、上記のよう
に梁自重が軽量化されるので、長期荷重によって梁に発
生する許容以上の撓みやひび割れが防止される。なお、
鋼管1は、それぞれの梁Aの中に単独で配し、柱5や他
の部材との力の伝達は行わないものとする。また、上記
のように鋼管1のコンクリート4への付着性は大きいの
で、梁両端部に定着部を設ける必要はないが、定着部を
設けても構わない。
In addition to the increase in shear rigidity, the weight of the beam itself is reduced as described above, so that the beam is prevented from being bent or cracked more than allowable due to long-term load. In addition,
The steel pipes 1 are individually arranged in the respective beams A, and the force transmission with the columns 5 and other members is not performed. Further, since the adhesion of the steel pipe 1 to the concrete 4 is large as described above, it is not necessary to provide the fixing portions at both ends of the beam, but the fixing portions may be provided.

【0014】また、上記実施例では、円形の鋼管1を緊
張材としてコンクリート4内に埋設したが、図3に示す
ように、角形の鋼管1を緊張材として使用するなど、鋼
管の断面形状は、円形に限定されるものではない。ま
た、図4に示すように、緊張材として鋼管1を埋設する
と共に、従来の緊張材であるPC鋼棒や鋼線9を配設し
てもよい。
Further, in the above embodiment, the circular steel pipe 1 is embedded in the concrete 4 as a tension material, but as shown in FIG. 3, the square steel pipe 1 is used as a tension material, and the sectional shape of the steel pipe is However, the shape is not limited to a circle. Further, as shown in FIG. 4, the steel pipe 1 may be embedded as a tension material and a conventional PC steel rod or steel wire 9 may be arranged.

【0015】また、梁A内に鉄骨11を配設してもよ
い。この場合には、例えば、図5に示すように、梁断面
中央にH形鋼11を配置し、そのウェブ両面に1対の角
形鋼管1をそれぞれ当接するように配置して、該H形鋼
11と角形鋼管1を共に梁断面中央部に配置させる。
Further, the steel frame 11 may be arranged in the beam A. In this case, for example, as shown in FIG. 5, an H-shaped steel 11 is arranged at the center of the beam cross section, and a pair of square steel pipes 1 are arranged so as to abut on both sides of the web, respectively. 11 and the square steel pipe 1 are both arranged at the center of the beam cross section.

【0016】[0016]

【発明の効果】以上説明してきたように、本発明のプレ
キャスト鉄筋コンクリート梁は、従来よりも、長期荷重
によるたわみやひび割れが防止できると共に、断面内中
空部によって梁自重を軽減できるという効果がある。
As described above, the precast reinforced concrete beam of the present invention is more effective than the conventional one in that it is possible to prevent bending and cracking due to long-term load, and to reduce the weight of the beam due to the hollow section.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る実施例のプレキャスト鉄筋コンク
リート梁の断面図である。
FIG. 1 is a sectional view of a precast reinforced concrete beam according to an embodiment of the present invention.

【図2】本発明に係る実施例における梁の架設状態を示
す側面図である。
FIG. 2 is a side view showing a erected state of the beam in the embodiment according to the present invention.

【図3】本発明に係る第2実施例のプレキャスト鉄筋コ
ンクリート梁の断面図である。
FIG. 3 is a sectional view of a precast reinforced concrete beam according to a second embodiment of the present invention.

【図4】本発明に係る第3実施例のプレキャスト鉄筋コ
ンクリート梁の断面図である。
FIG. 4 is a sectional view of a precast reinforced concrete beam according to a third embodiment of the present invention.

【図5】本発明に係る第4実施例のプレキャスト鉄筋コ
ンクリート梁の断面図である。
FIG. 5 is a sectional view of a precast reinforced concrete beam according to a fourth embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 鋼管 1a 中空部 2 梁主筋 A プレキャスト鉄筋コンクリート梁 1 Steel pipe 1a Hollow part 2 Beam main bar A Precast reinforced concrete beam

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 梁を形成する鉄筋コンクリートの断面中
央部に、鋼管を、所定の緊張力を付与した状態で埋設し
てなることを特徴とするプレキャスト鉄筋コンクリート
梁。
1. A precast reinforced concrete beam, characterized in that a steel pipe is embedded in a central portion of a cross section of reinforced concrete forming the beam in a state in which a predetermined tension is applied.
JP29878492A 1992-11-09 1992-11-09 Precast ferro-concrete beam Pending JPH06146472A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29878492A JPH06146472A (en) 1992-11-09 1992-11-09 Precast ferro-concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29878492A JPH06146472A (en) 1992-11-09 1992-11-09 Precast ferro-concrete beam

Publications (1)

Publication Number Publication Date
JPH06146472A true JPH06146472A (en) 1994-05-27

Family

ID=17864179

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29878492A Pending JPH06146472A (en) 1992-11-09 1992-11-09 Precast ferro-concrete beam

Country Status (1)

Country Link
JP (1) JPH06146472A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100682629B1 (en) * 2005-06-28 2007-02-15 박재만 Steel girder
KR100806821B1 (en) * 2006-12-19 2008-02-22 삼성중공업 주식회사 Hollow core beam using the u-type precast concrete box, construction method and connection thereof
WO2009157601A1 (en) * 2008-06-26 2009-12-30 Cowi Korea Co., Ltd. Pipe rack as constructed using precast concrete members
KR20220038883A (en) * 2020-09-21 2022-03-29 송성민 Precast hollow beam and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100682629B1 (en) * 2005-06-28 2007-02-15 박재만 Steel girder
KR100806821B1 (en) * 2006-12-19 2008-02-22 삼성중공업 주식회사 Hollow core beam using the u-type precast concrete box, construction method and connection thereof
WO2009157601A1 (en) * 2008-06-26 2009-12-30 Cowi Korea Co., Ltd. Pipe rack as constructed using precast concrete members
KR20220038883A (en) * 2020-09-21 2022-03-29 송성민 Precast hollow beam and construction method thereof

Similar Documents

Publication Publication Date Title
JP4040980B2 (en) Prestressed synthetic truss girder and manufacturing method thereof
US4493177A (en) Composite, pre-stressed structural member and method of forming same
KR100682794B1 (en) Manufacturing method for prestressed steel composite girder
KR102387052B1 (en) End Reinforced half preecast concrete beam and construction method of the same
US3260024A (en) Prestressed girder
KR100500156B1 (en) Prestress composite beam and method of manufacturing the same
KR102440832B1 (en) Precat girder-column structure with large depth truss and construction method for the same
KR101536659B1 (en) Prestressed steel composite structure
JP2003213623A6 (en) Bridge superstructure
JP3877995B2 (en) How to build a string string bridge
JPH06146472A (en) Precast ferro-concrete beam
RU2323305C1 (en) Method for high-reliability pre-stressed reinforced concrete building skeleton production
KR20110019623A (en) Process for producing prestressed concrete girder and concrete girder structure
KR101751699B1 (en) Void slab having mesh for preventing floating and increasing shear strength
KR101170077B1 (en) Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same
JP2003138520A (en) Bridge girder structure
KR101004221B1 (en) One Way Waffle Slab System Continued by Post-tensioning and Post-tensioning method of the same
JPH0542553B2 (en)
KR100416217B1 (en) Composite structural material
KR20120030206A (en) A precast concrete deck and construction method for slab structure by using it
KR20010068055A (en) PSC Girder having Anchoring Sleeves and Strengthening Method
KR101402620B1 (en) Construction method of slab type rahmen birdge using Half-PC slab for slab bridge
JP2659329B2 (en) Construction method of PC structure
KR102625479B1 (en) Construction method using precast module with prestressing force
KR20180070097A (en) Prestressed Hybrid Wide Flange Girder System Suitable For Resisting Negative Moments At Construction Stage