JP2001172913A - Elevated bridge and its construction method - Google Patents

Elevated bridge and its construction method

Info

Publication number
JP2001172913A
JP2001172913A JP35810299A JP35810299A JP2001172913A JP 2001172913 A JP2001172913 A JP 2001172913A JP 35810299 A JP35810299 A JP 35810299A JP 35810299 A JP35810299 A JP 35810299A JP 2001172913 A JP2001172913 A JP 2001172913A
Authority
JP
Japan
Prior art keywords
precast concrete
girder
tendon
viaduct
abutment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP35810299A
Other languages
Japanese (ja)
Inventor
Ryohei Kurosawa
亮平 黒沢
Keizo Tanabe
恵三 田辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurosawa Construction Co Ltd
Original Assignee
Kurosawa Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurosawa Construction Co Ltd filed Critical Kurosawa Construction Co Ltd
Priority to JP35810299A priority Critical patent/JP2001172913A/en
Publication of JP2001172913A publication Critical patent/JP2001172913A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily construct an elevated bridge with large quake-proof strength. SOLUTION: A bridge abutment beam 4 made of precast concrete with a jaw 8 for placing the beam is crimped and joined to the head part of a precast concrete post 3 being erected at an appropriate interval on a foundation 2, precast concrete girders 5 and 6 are erected between the jaws 8 for placing the beam of the bridge abutment beam 4 via a support 10, the end part of the precast concrete beams 5 and 6 being installed opposite to the jaw 8 for placing the beam of the bridge abutment beam 4 is crimped and joined to the bridge abutment beam 4 by a lower tendon 11 through the jaw 8 for placing the beam and an upper tendon 12 through the upper side of the jaw 8 for placing the beam.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は高架橋およびその構
築工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a viaduct and a construction method thereof.

【0002】[0002]

【従来の技術】従来の高架橋は、図6に示すように、基
礎21、柱22および梁23と、桁24、床板25およ
び防音壁26とがそれぞれ在来工法で一体的に形成さ
れ、各柱22間の桁24同士はエキスパンションジョイ
ントで接合されている。
2. Description of the Related Art In a conventional viaduct, as shown in FIG. 6, a foundation 21, columns 22 and beams 23, a girder 24, a floor plate 25 and a soundproof wall 26 are integrally formed by a conventional construction method. The girders 24 between the columns 22 are joined by an expansion joint.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記のような
高架橋は在来工法で構築するため手間がかかり、また桁
が柱に剛接合されておらず、桁同士がエキスパンション
ジョイントで接合されているため大地震が発生すると柱
から落下する恐れがあった。
However, such a viaduct as described above is troublesome because it is constructed by a conventional method, and the girders are not rigidly joined to the columns, and the girders are joined by expansion joints. Therefore, there was a risk of falling off the pillar when a large earthquake occurred.

【0004】本発明は上記のような問題に鑑みてなされ
たものであり、その目的は、耐震強度の大きな高架橋を
簡単に構築することである。
The present invention has been made in view of the above problems, and an object of the present invention is to easily construct a viaduct having a large earthquake resistance.

【0005】[0005]

【課題を解決するための手段】以上の課題を解決するた
めの手段は、請求項1の発明が、基礎上に適宜間隔ごと
に立設されたプレキャストコンクリート柱の頭部に、梁
載置用顎を備えた橋台梁が緊張材で圧着接合され、前記
橋台梁の梁載置用顎間にはプレキャストコンクリート桁
が支承を介して架設され、前記橋台梁の梁載置用顎に対
向して設置されたプレキャストコンクリート桁の端部同
士が、梁載置用顎を貫通した下部緊張材と、梁載置用顎
の上側を貫通した上部緊張材とにより橋台梁に圧着接合
されたことを特徴とする。
Means for solving the above problems are as follows. The invention according to claim 1 is characterized in that the invention according to claim 1 is provided on a head of a precast concrete column erected at an appropriate interval on a foundation. An abutment with a jaw is press-bonded with a tendon, and a precast concrete girder is erected between the beam mounting jaws of the abutment via a support, and faces the beam mounting jaw of the abutment. The ends of the installed precast concrete girder are crimped to the abutment by means of a lower tendon that penetrates the beam mounting jaw and an upper tendon that penetrates above the beam mounting jaw. And

【0006】請求項1の発明によれば、プレキャストコ
ンクリート桁が柱に緊張材で圧着接合、すなわち剛接合
されているので、耐震強度の大きな高架橋を簡単に構築
することができる。またプレキャストコンクリート桁の
端部同士を、下部緊張材と上部緊張材とによりプレキャ
ストコンクリートの橋台梁に圧着接合するので、大地震
による水平荷重または垂直荷重でプレキャストコンクリ
ート桁が破壊したとしても、柱にぶら下がった状態とな
って落下することがない。
According to the first aspect of the present invention, since the precast concrete girder is press-bonded to the column with a tension member, that is, rigidly connected, a viaduct having a large seismic strength can be easily constructed. In addition, since the ends of the precast concrete girder are crimped to the precast concrete abutment with the lower tendon and the upper tendon, even if the precast concrete girder is destroyed by a horizontal or vertical load due to a large earthquake, It will not hang and fall.

【0007】また請求項2の発明が、基礎上に適宜間隔
ごとに立設されたプレキャストコンクリート柱の頭部間
に支承を介して架設されたプレキャストコンクリート桁
が、緊張材で圧着接合され、前記プレキャストコンクリ
ート柱の頭部に対向して設置されたプレキャストコンク
リート桁の端部同士が、目地材を介して下部緊張材と上
部緊張材とにより圧着接合されたことを特徴とする。
According to a second aspect of the present invention, a precast concrete girder erected via a bearing between heads of precast concrete columns erected at appropriate intervals on a foundation is press-bonded with a tension member. The end of the precast concrete girder installed opposite the head of the precast concrete column is crimped by a lower tendon and an upper tendon via joint materials.

【0008】請求項2の発明によれば、プレキャストコ
ンクリート桁がプレキャストコンクリート柱の頭部に緊
張材で圧着接合され、プレキャストコンクリート桁の端
部同士も下部緊張材と上部緊張材とにより圧着接合され
たことにより、耐震強度の大きな高架橋を簡単に構築す
ることができる。また、大地震によりプレキャストコン
クリート桁が破壊したとしても、プレキャストコンクリ
ート柱に剛接合されているため落下することがない。
According to the second aspect of the present invention, the precast concrete girder is crimped to the head of the precast concrete column with a tendon, and the ends of the precast concrete girder are also crimped with the lower tendon and the upper tendon. This makes it possible to easily construct a viaduct having a large earthquake resistance. Also, even if the precast concrete girder is destroyed by a large earthquake, it does not fall because it is rigidly connected to the precast concrete column.

【0009】また請求項3の発明が、基礎上に適宜間隔
ごとに立設されたプレキャストコンクリート柱の頭部間
に支承を介してプレキャストコンクリート桁を架設し、
該プレキャストコンクリート桁の一方の端部をプレキャ
ストコンクリート柱に緊張材で圧着接合した後に、他方
の端部をプレキャストコンクリート柱に緊張材で圧着接
合することを特徴とする。
According to a third aspect of the present invention, there is provided a precast concrete girder via a bearing between heads of precast concrete columns erected at appropriate intervals on a foundation,
One end of the precast concrete girder is pressure-bonded to the precast concrete column with a tendon, and then the other end is pressure-bonded to the precast concrete column with a tendon.

【0010】請求項3の発明によれば、プレキャストコ
ンクリート柱にプレキャストコンクリート桁を接合する
場合、一方の端部を接合するときには他方の端部がフリ
ーになっており、一方の端部を接合した後に他方の端部
を接合するため不静定二次応力とプレストレス力の損失
とを小さくすることができる。
According to the third aspect of the present invention, when a precast concrete girder is joined to a precast concrete column, the other end is free when one end is joined, and the one end is joined. Since the other end is later joined, the indeterminate secondary stress and the loss of the prestress force can be reduced.

【0011】[0011]

【発明の実施の形態】以下、本発明の高架橋およびその
構築工法の実施の形態を図面に基づいて詳細に説明す
る。高架橋は2つの実施の形態があり、図1〜図4は第
1の実施の形態の高架橋、図5は第2の実施の形態の高
架橋をそれぞれ示す。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the viaduct of the present invention and a construction method thereof will be described below in detail with reference to the drawings. There are two embodiments of the viaduct, FIGS. 1 to 4 show the viaduct of the first embodiment, and FIG. 5 shows the viaduct of the second embodiment.

【0012】第1の実施の形態の高架橋1は基礎2上に
適宜間隔をもって立設されたプレストレストプレキャス
トコンクリート柱(以下柱という)3と、該柱3の頭部
に設置されたプレストレストプレキャストコンクリート
製の橋台梁(以下橋台梁という)4と、該橋台梁4間に
掛け渡されたプレストレストプレキャストコンクリート
製の主桁5とプレストレストプレキャストコンクリート
製の側桁6とからなるプレキャストコンクリート桁と、
これらの主桁5および側桁6上に現場打ちコンクリート
を打設して形成されたスラブ7とから構成されている。
The viaduct 1 of the first embodiment is made of a prestressed precast concrete column (hereinafter referred to as a column) 3 erected at an appropriate interval on a foundation 2 and a prestressed precast concrete column installed at the head of the column 3. A precast concrete girder comprising an abutment (hereinafter referred to as an abutment) 4, a main girder 5 made of prestressed precast concrete and a side girder 6 made of prestressed precast concrete stretched between the abutments 4;
The slab 7 is formed by casting cast-in-place concrete on the main girder 5 and the side girder 6.

【0013】橋台梁4は長さ方向に沿って梁載置用顎8
が突設され、基礎2からの緊張材9で柱3に圧着接合さ
れている。この圧着接合とは、プレストレストが付与さ
れたプレキャストコンクリート部材同士を、PC鋼線や
PC鋼棒などの緊張材で所定のプレストレスを付与して
接合することをいう。したがって、基礎2と柱3と橋台
梁4とが圧着接合され、かつ基礎2も杭2aに圧着接合
されている。
The abutment 4 has a beam mounting jaw 8 along its length.
Are protruded and crimp-bonded to the column 3 with the tendon 9 from the foundation 2. The term “compression bonding” refers to joining precast concrete members to which prestressing has been applied by applying a predetermined prestress with a tendon such as PC steel wire or PC steel rod. Therefore, the foundation 2, the pillar 3, and the abutment 4 are crimped and joined, and the foundation 2 is also crimped to the pile 2a.

【0014】主桁5は断面T字形であり、両側の端部が
梁載置用顎8に硬質ゴム、ステンレス板やテフロン(登
録商標)板などの支承10を介して設置されて、他の主
桁5a、5b…の端部と対向した状態になっている。そ
して、第一の主桁5aの端部から梁載置用顎8を通って
第二の主桁5bの端部にわたって下部緊張材11が配設
されるとともに、第一の主桁5aの端部から梁載置用顎
8の上側を通って第二の主桁5bの端部にわたって上部
緊張材12が配設され、これらに所定の緊張力を付与し
て定着すると各主桁5a、5b…が橋台梁4に剛接合さ
れる。また各主桁5a、5b…の端部と梁載置用顎8と
の間にはモルタルなどの目地材13が充填されている。
一方、側桁6も前記と同じように橋台梁4に圧着接合さ
れている。したがって、主桁5および側桁6が柱3に剛
接合された状態となり、これらの上に現場打ちコンクリ
ートを打設してスラブ7を構築するとラーメン架構の高
架橋1が構築される。
The main girder 5 has a T-shaped cross section. Both ends of the main girder 5 are mounted on a beam mounting jaw 8 through a bearing 10 such as a hard rubber, a stainless steel plate or a Teflon (registered trademark) plate. .. Are opposed to the ends of the main girders 5a, 5b. The lower tendon 11 is disposed from the end of the first main girder 5a to the end of the second main girder 5b through the beam mounting jaw 8 and the end of the first main girder 5a. An upper tendon 12 is arranged from the upper part of the second main girder 5b to the upper end of the second main girder 5b through the upper side of the beam mounting jaw 8. Are rigidly connected to the abutment 4. A joint material 13 such as mortar is filled between the ends of the main girders 5a, 5b,... And the beam mounting jaws 8.
On the other hand, the side girders 6 are also pressure-bonded to the abutment 4 in the same manner as described above. Therefore, the main girder 5 and the side girder 6 are rigidly joined to the column 3. When the slab 7 is constructed by casting cast-in-place concrete on these, the viaduct 1 of the ramen frame is constructed.

【0015】次に、上記の高架橋の構築工法を図4に基
づいて説明する。上記高架橋1を構成する柱3、橋台梁
4、主桁5および側桁6はそれぞれプレストレストプレ
キャストコンクリート製であるため、これらを工場で製
作してそれぞれ現場に搬入する。
Next, a method for constructing the above-mentioned viaduct will be described with reference to FIG. Since the pillar 3, the abutment 4, the main girder 5, and the side girder 6 that constitute the viaduct 1 are each made of prestressed precast concrete, they are manufactured at a factory and carried to the site.

【0016】次に、これらを使用して2体1組の柱3を
基礎2上に仮固定し、その頭部に橋台梁4を設置して基
礎2からの緊張材9で圧着接合すると門型の橋脚14が
形成される(図3参照)。
Next, a pair of columns 3 is temporarily fixed on the foundation 2 by using these, and an abutment 4 is installed on the head thereof and is bonded by crimping 9 with the tension member 9 from the foundation 2. A mold pier 14 is formed (see FIG. 3).

【0017】次に、主桁5および側桁6を橋台梁4間に
硬質ゴム、ステンレス板やテフロン板などの支承10を
介して架設するとともに、梁載置用顎8に対向設置され
た各主桁5a、5b…の端部に下部緊張材11と上部緊
張材12とを配線する。このとき主桁5と側桁6とは橋
台梁4に仮固定された状態であるため、第一および第二
の主桁5a、5bの端部と梁載置用顎8との間に目地材
13を充填するとともに、下部緊張材11と上部緊張材
12とに所定の緊張力を付与して定着すると、第1の主
桁5aは橋台梁間に圧着接合されるが、第2の主桁5b
は一方の端部のみが圧着接合され、他方の端部はフリ
ー、すなわち移動自在な状態となる。次に、前記と同じ
方法で第2の主桁5bの他方の端部と、第3の主桁5c
の一方の端部とを圧着接合すると、第2の主桁5bは橋
台梁4間に接合されるが、第3の主桁5cは他方の端部
が移動自在な状態となる。そして、同図の(2)に示す
ように、上記の方法で主桁5a、5b…を順に圧着接合
し、この上に現場打ちコンクリートを打設してスラブ7
を形成するとラーメン架構の高架橋1が構築される。こ
のように主桁5の他方の端部を移動可能な状態にして一
方の端部を接合すると不静定二次応力とプレストレス力
の損失とを減少させることができる。
Next, the main girder 5 and the side girder 6 are erected between the abutment 4 via a support 10 such as a hard rubber, a stainless steel plate or a Teflon plate, and each of the main girder 5 and the side girder 6 is installed opposite the beam mounting jaw 8. The lower tendon 11 and the upper tendon 12 are wired to the ends of the main girders 5a, 5b. At this time, since the main girder 5 and the side girder 6 are temporarily fixed to the abutment 4, joints are provided between the ends of the first and second main girder 5 a and 5 b and the beam mounting jaw 8. When the material 13 is filled and a predetermined tension is applied and fixed to the lower tendon 11 and the upper tendon 12, the first main girder 5 a is pressure-bonded between the abutments, while the second main girder is joined. 5b
Is press-bonded at only one end, and the other end is free, that is, freely movable. Next, the other end of the second main girder 5b and the third main girder 5c in the same manner as described above.
When the second main girder 5b is joined by crimping to one end of the third main girder 5b, the other end of the third main girder 5c is movable. Then, as shown in (2) of the figure, the main girders 5a, 5b,...
Is formed, the viaduct 1 of the ramen frame is constructed. In this manner, when the other end of the main girder 5 is movable and the one end is joined, the indeterminate secondary stress and the loss of the prestress force can be reduced.

【0018】図5は、第2の実施の形態の高架橋15で
あり、第1の実施の形態における橋台梁4を撤去して、
主桁5を柱3の頭部に硬質ゴム、ステンレス板やテフロ
ン板などの支承10を介して載せたものである。各主桁
5a、5b…の端部は、それぞれ緊張材9で柱3の頭部
に圧着接合されるとともに、配線された下部緊張材11
と上部緊張材12とによりプレストレストを付与されて
連結されている。また対向した端部間にはモルタルなど
の目地材13が充填されている。したがって、主桁5が
柱3に直接剛接合され、この上にコンクリートが打設さ
れてスラブ7が形成される。このように主桁5を柱3の
頭部に載せるとラーメン架構の高架橋15を簡単に構築
することができる。また各主桁5a、5b、5c…同士
が緊張材11、12でプレストレストを付与されて連結
され、かつ柱3に緊張材9で剛接合されている。したが
って大地震、いわゆる直下型の地震が直撃したとして
も、各主桁5a、5b、5c…が柱3から落下すること
はない。
FIG. 5 shows a viaduct 15 of the second embodiment, in which the bridge 4 in the first embodiment is removed.
The main girder 5 is mounted on the head of the pillar 3 via a bearing 10 such as a hard rubber, a stainless steel plate or a Teflon plate. The ends of the main girders 5a, 5b,... Are respectively crimp-bonded to the heads of the columns 3 with tendons 9 and the lower tendons 11 wired thereto.
The upper tension member 12 and the upper tension member 12 are connected by being prestressed. A joint material 13 such as mortar is filled between the opposed ends. Therefore, the main girder 5 is directly and rigidly connected to the column 3, and concrete is cast on this to form the slab 7. When the main girder 5 is placed on the head of the column 3 in this way, the viaduct 15 of the ramen frame can be easily constructed. Each of the main girders 5a, 5b, 5c,... Is prestressed and connected by tension members 11, 12, and is rigidly joined to the column 3 by a tension member 9. Therefore, even if a large earthquake, a so-called direct-type earthquake, strikes directly, the main girders 5a, 5b, 5c.

【0019】上記高架橋の構築工法を図5に基づいて説
明する。はじめに2体1組のPC柱3を基礎2上に仮固
定し、主桁5および側桁6を頭部間に硬質ゴム、ステン
レス板やテフロン板などの支承10を介して架設し、こ
れらの端部を基礎2からの緊張材9で仮固定する。
The construction method of the viaduct will be described with reference to FIG. First, a pair of PC columns 3 is temporarily fixed on the foundation 2 and the main girder 5 and the side girder 6 are erected between the heads via a bearing 10 such as a hard rubber, a stainless steel plate or a Teflon plate. The end is temporarily fixed with the tendon 9 from the foundation 2.

【0020】次に、同図の(1)に示すように、柱の頭
部に設置された主桁5の端部にわたって下部緊張材11
と上部緊張材12とを配線する。そして、第一の主桁5
aの端部と第二の主桁5bの端部との間に目地材13を
充填して下部緊張材11と上部緊張材12とにプレスト
レストを付与して定着すると、第一の主桁5aの他方の
端部と第二の主桁5bの一方の端部とが連結される。次
に、第一の主桁5aの他方の端部と第二の主桁5bの一
方の端部とを緊張材9で柱3に圧着接合すると、第二の
主桁5bの他方の端部はフリー、すなわち移動自在な状
態となる。次に、前記と同じ方法で第二の主桁5bの他
方の端部と、第三の主桁5cの一方の端部とを緊張材1
1、12で連結した後に、前記のようにこれらの端部を
緊張材9で柱3に圧着接合する。そして、この方法を順
次繰り返すと各主桁5a、5b、5c…が柱3間に固定
され、この上に現場打ちコンクリートを打設してスラブ
7を形成するとラーメン架構の高架橋15が構築され
る。この場合も、前記と同じように不静定二次応力とプ
レストレス力の損失とを減少させることができる。
Next, as shown in FIG. 1A, the lower tendon 11 extends over the end of the main girder 5 installed at the head of the column.
And the upper tendon 12 are wired. And the first main girder 5
When the joint material 13 is filled between the end of the first main girder 5a and the end of the second main girder 5b, and the lower tendon 11 and the upper tendon 12 are prestressed and fixed, the first main girder 5a Is connected to one end of the second main girder 5b. Next, when the other end of the first main girder 5a and one end of the second main girder 5b are press-bonded to the column 3 with the tension member 9, the other end of the second main girder 5b is joined. Are free, that is, freely movable. Next, the other end of the second main girder 5b and one end of the third main girder 5c are connected to the tendon 1 by the same method as described above.
After connecting at 1 and 12, these ends are crimped to the column 3 with the tendon 9 as described above. When this method is sequentially repeated, the main girders 5a, 5b, 5c... Are fixed between the columns 3, and cast-in-place concrete is cast thereon to form the slab 7, whereby the viaduct 15 of the rigid frame is constructed. . Also in this case, the static indeterminate secondary stress and the loss of the prestress force can be reduced in the same manner as described above.

【0021】[0021]

【発明の効果】主桁が柱に緊張材で圧着接合されている
ので、耐震強度の大きな高架橋を簡単に構築することが
できる。
According to the present invention, since the main girder is crimp-bonded to the column with a tension member, it is possible to easily construct a viaduct having a large earthquake resistance.

【0022】主桁の端部が、下部緊張材と上部緊張材と
により橋台梁に圧着接合されているので、大地震による
水平荷重または垂直荷重で主桁が破壊したとしても、柱
にぶら下がった状態となって落下することがない。
Since the end of the main girder is crimped to the abutment with the lower tendon and the upper tendon, even if the main girder is broken by a horizontal load or a vertical load due to a large earthquake, the main girder hangs on the column. It does not fall in a state.

【0023】柱に主桁を接合する場合、一方の端部を接
合するときには他方の端部がフリーとなり、一方の端部
を接合した後にフリー側の端部を接合するため、不静定
二次応力とプレストレス力の損失とを小さくすることが
できる。
When joining the main girder to the column, when joining one end, the other end is free, and after joining one end, the free end is joined. The secondary stress and the loss of the prestress force can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】高架橋の平面図である。FIG. 1 is a plan view of a viaduct.

【図2】図1のA−A線断面図である。FIG. 2 is a sectional view taken along line AA of FIG.

【図3】図1のB−B線断面図である。FIG. 3 is a sectional view taken along line BB of FIG. 1;

【図4】(1)および(2)は高架橋の構築工法の断面
図である。
FIGS. 4 (1) and (2) are cross-sectional views of a viaduct construction method.

【図5】(1)および(2)は高架橋の構築工法の断面
図である。
FIGS. 5 (1) and (2) are cross-sectional views of a viaduct construction method.

【図6】従来の高架橋の断面図である。FIG. 6 is a cross-sectional view of a conventional viaduct.

【符号の説明】[Explanation of symbols]

1、15 高架橋 2、21 基礎 3、22 柱 4、23 橋台梁 5、24 主桁 6 側桁 7 スラブ 8 梁載置用顎 9 緊張材 10 支承 11 下部緊張材 12 上部緊張材 13 目地材 14 橋脚 25 床板 26 防音壁 Reference Signs List 1,15 viaduct 2,21 foundation 3,22 pillar 4,23 abutment beam 5,24 main girder 6 side girder 7 slab 8 beam mounting jaw 9 tension member 10 bearing 11 lower tension member 12 upper tension member 13 joint member 14 Pier 25 Floor board 26 Soundproof wall

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 基礎上に適宜間隔ごとに立設されたプレ
キャストコンクリート柱の頭部に、梁載置用顎を備えた
橋台梁が緊張材で圧着接合され、前記橋台梁の梁載置用
顎間にはプレキャストコンクリート桁が支承を介して架
設され、前記橋台梁の梁載置用顎に対向して設置された
プレキャストコンクリート桁の端部同士が、梁載置用顎
を貫通した下部緊張材と、梁載置用顎の上側を貫通した
上部緊張材とにより橋台梁に圧着接合されたことを特徴
とする高架橋。
An abutment having a beam mounting jaw is crimp-bonded to a head of a precast concrete pillar erected at an appropriate interval on a foundation with a tension member, and the beam is mounted on the abutment. A precast concrete girder is installed between the jaws via a bearing, and the ends of the precast concrete girder installed opposite to the beam mounting jaw of the abutment bridge have a lower tension that penetrates the beam mounting jaw. A viaduct characterized by being crimped to an abutment by means of a material and an upper tendon which penetrates above a beam mounting jaw.
【請求項2】 基礎上に適宜間隔ごとに立設されたプレ
キャストコンクリート柱の頭部間に支承を介して架設さ
れたプレキャストコンクリート桁が、緊張材で圧着接合
され、前記プレキャストコンクリート柱の頭部に対向し
て設置されたプレキャストコンクリート桁の端部同士
が、目地材を介して下部緊張材と上部緊張材とにより圧
着接合されたことを特徴とする高架橋。
2. A precast concrete girder erected via a bearing between the heads of precast concrete columns erected at appropriate intervals on a foundation is crimp-bonded with a tension member, and the heads of the precast concrete columns are provided. A viaduct, wherein ends of precast concrete girders installed opposite to each other are press-bonded to each other by a lower tendon and an upper tendon via joint materials.
【請求項3】 基礎上に適宜間隔ごとに立設されたプレ
キャストコンクリート柱の頭部間に支承を介してプレキ
ャストコンクリート桁を架設し、該プレキャストコンク
リート桁の一方の端部をプレキャストコンクリート柱に
緊張材で圧着接合した後に、他方の端部をプレキャスト
コンクリート柱に緊張材で圧着接合することを特徴とす
る高架橋の構築工法。
3. A precast concrete girder is erected via a bearing between heads of precast concrete columns erected at appropriate intervals on a foundation, and one end of the precast concrete girder is tensioned to the precast concrete column. A method of constructing a viaduct, characterized in that after crimping with a material, the other end is crimped to a precast concrete column with a tension material.
JP35810299A 1999-12-16 1999-12-16 Elevated bridge and its construction method Pending JP2001172913A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35810299A JP2001172913A (en) 1999-12-16 1999-12-16 Elevated bridge and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35810299A JP2001172913A (en) 1999-12-16 1999-12-16 Elevated bridge and its construction method

Publications (1)

Publication Number Publication Date
JP2001172913A true JP2001172913A (en) 2001-06-26

Family

ID=18457559

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35810299A Pending JP2001172913A (en) 1999-12-16 1999-12-16 Elevated bridge and its construction method

Country Status (1)

Country Link
JP (1) JP2001172913A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004092075A (en) * 2002-08-29 2004-03-25 Nippon Ps:Kk Structure and construction method for cut-and-cover tunnel
JP2007039897A (en) * 2005-08-01 2007-02-15 Koken Sangyo Kk Precast bridge
JP2008127940A (en) * 2006-11-24 2008-06-05 Kurosawa Construction Co Ltd Structure and method for joining column and beam together
JP2009256873A (en) * 2008-04-11 2009-11-05 Oriental Shiraishi Corp Bridge equipped with precast cross girder and precast stringer, and its construction method
JP2010275829A (en) * 2009-06-01 2010-12-09 Taisei Corp Main girder, bridge, and bridge construction method
JP2014062403A (en) * 2012-09-21 2014-04-10 Kitagawa Kogyo Co Ltd Bridge girder and construction method of bridge girder
JP5539554B1 (en) * 2013-02-04 2014-07-02 黒沢建設株式会社 Girder bridge connection structure and girder bridge structure
JP2014227754A (en) * 2013-05-24 2014-12-08 北川工業株式会社 Bridge girder and construction method of bridge girder

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004092075A (en) * 2002-08-29 2004-03-25 Nippon Ps:Kk Structure and construction method for cut-and-cover tunnel
JP2007039897A (en) * 2005-08-01 2007-02-15 Koken Sangyo Kk Precast bridge
JP2008127940A (en) * 2006-11-24 2008-06-05 Kurosawa Construction Co Ltd Structure and method for joining column and beam together
JP2009256873A (en) * 2008-04-11 2009-11-05 Oriental Shiraishi Corp Bridge equipped with precast cross girder and precast stringer, and its construction method
JP2010275829A (en) * 2009-06-01 2010-12-09 Taisei Corp Main girder, bridge, and bridge construction method
JP2014062403A (en) * 2012-09-21 2014-04-10 Kitagawa Kogyo Co Ltd Bridge girder and construction method of bridge girder
JP5539554B1 (en) * 2013-02-04 2014-07-02 黒沢建設株式会社 Girder bridge connection structure and girder bridge structure
JP2014148868A (en) * 2013-02-04 2014-08-21 Kurosawa Construction Co Ltd Connection structure between girder bridge and girder bridge structure
JP2014227754A (en) * 2013-05-24 2014-12-08 北川工業株式会社 Bridge girder and construction method of bridge girder

Similar Documents

Publication Publication Date Title
JPH1096263A (en) Precast concrete support and assembling method of slab
JPS6114287B2 (en)
JP2001172913A (en) Elevated bridge and its construction method
JP2978903B1 (en) Viaduct
JP2967874B1 (en) How to build an overhead suspension bridge
JP2702365B2 (en) Building construction method using precast concrete members
KR200279918Y1 (en) beam-column connection detail of long-span pre-cast system
JP2006070679A (en) Continuous girder bridge in which triangle structures having damping/supporting devices at lower ends are connected by girder
JP2005060964A (en) Construction method for girder bridge
JP2566176B2 (en) Building construction method
JP2000336769A (en) Truss structural body and construction method therefor
JP3187347B2 (en) Column and beam joining method and joint structure
KR102543539B1 (en) Settlement support system in which the steel bar and support block of the composite ramen bridge are integrated
JPH02221535A (en) Connecting structure for pillar and beam
JPH0765297B2 (en) How to erection a cane ramen bridge
JPH0673203U (en) Beam-column joint structure
JPH0197744A (en) Shearing reinforcing structure of shear head section in flat plate building
KR200271767Y1 (en) Concrete beam
JP2003049487A (en) Connection structure between steel member and concrete member
JPH0334963Y2 (en)
JPH06220869A (en) Drop-in type steel frame bridge pier and process of construction thereof
JP2659329B2 (en) Construction method of PC structure
JPH0413494B2 (en)
JPH05280013A (en) Process for forming arch concrete with use of arch-like form timberwork
JPH08209630A (en) Reinforcing method for structure such as pillar, beam, or girder made of reinforced concrete