JPH0334963Y2 - - Google Patents

Info

Publication number
JPH0334963Y2
JPH0334963Y2 JP14668084U JP14668084U JPH0334963Y2 JP H0334963 Y2 JPH0334963 Y2 JP H0334963Y2 JP 14668084 U JP14668084 U JP 14668084U JP 14668084 U JP14668084 U JP 14668084U JP H0334963 Y2 JPH0334963 Y2 JP H0334963Y2
Authority
JP
Japan
Prior art keywords
column
concrete
bracket
pillar
rigid frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14668084U
Other languages
Japanese (ja)
Other versions
JPS6162102U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP14668084U priority Critical patent/JPH0334963Y2/ja
Publication of JPS6162102U publication Critical patent/JPS6162102U/ja
Application granted granted Critical
Publication of JPH0334963Y2 publication Critical patent/JPH0334963Y2/ja
Expired legal-status Critical Current

Links

Description

【考案の詳細な説明】 産業上の利用分野 この考案はビルデイング等の建設に用いる組立
型プレストレストコンクリートラーメン構造に関
するものである。
[Detailed description of the invention] Industrial field of application This invention relates to prefabricated prestressed concrete rigid frame structures used in the construction of buildings, etc.

従来の技術 従来この種のラーメン構造(以下P.C構造と言
う)は一般に第16図〜第18図に示すように形
成されている。同図においてaは柱、bは梁、c
は緊張材cであり、この緊張材cが、第16図に
示すように上縁材c1、吊上材c2、下縁材c3の三種
類から成つているものがあり、又第17図に示す
ように吊上材c2、下縁材c3から成つているものも
あり、又第18図に示すように上縁材c1及び下縁
材c3から成つているものもある。
BACKGROUND ART Conventionally, this type of rigid frame structure (hereinafter referred to as PC structure) is generally formed as shown in FIGS. 16 to 18. In the same figure, a is a column, b is a beam, and c
is a tension material c, and as shown in Fig. 16, this tension material c may consist of three types: an upper edge material c 1 , a hanging material c 2 , and a lower edge material c 3 . As shown in Fig. 17, some are made up of a hanging material c 2 and a lower edge material c 3 , while others are made of an upper edge material c 1 and a lower edge material c 3 as shown in Fig. 18. be.

考案が解決しようとする問題点 ところがここに問題がある。それは上記従来の
構造は次のような場合に、経済的に成り立たない
のである。
The problem that the invention attempts to solve However, here is the problem. This is because the conventional structure described above is not economically viable in the following cases.

即ち比較的中小のスパンで7m〜14m位の、し
かも大梁と桁梁で区画される単位の床面積が40m2
〜80m2位の範囲の構造である。これを図について
述べると、第15図は組立式P.C構造と鉄筋コン
クリート(以下R.C構造と略す)構造による建築
物などのラーメン構造について、積載し得る荷重
を一定と考えておき、桁梁方向のスパン長さを固
定した場合の大梁方向のスパン長さと工事費率、
また大梁と桁梁で区画される単位床面積と工事費
率の関係について示した概念図である。
In other words, it has a relatively small to medium span of about 7m to 14m, and the floor area of the unit divided by girders and girders is 40m 2
~80m This is a structure with a range of 2nd place. To explain this in terms of diagrams, Figure 15 shows a rigid frame structure such as a building made of a prefabricated PC structure and a reinforced concrete (hereinafter referred to as RC structure) structure, assuming that the load that can be carried is constant, and the span in the girder direction. Span length in the girder direction and construction cost rate when the length is fixed,
It is also a conceptual diagram showing the relationship between the unit floor area divided by girders and girders and the construction cost rate.

線L1は従来から実施されている組立式P.C構造
について、線L2は現場施工によるR.C構造につい
てのものである。従来の方法による線L1におい
て経済的に成立つ範囲は、大体においてスパンで
14mより長いもので、単位床面積で伝えば80m2
上の構造規模のものである。それ以下のものを試
みる場合は破線で示された延長線となり、線L2
と比較して、工事費の差が大きなものとなり、成
立し得なくなるものである。
Line L 1 is for the prefabricated PC structure that has been implemented in the past, and line L 2 is for the RC structure constructed on site. The economically viable range of line L 1 according to the conventional method is roughly the span.
It is longer than 14m and has a structural scale of 80m2 or more in terms of unit floor area. If you attempt something less than that, it will be an extension line shown as a dashed line, and the line L 2
The difference in construction costs would be so large that it would no longer be viable.

この考案はこのような問題を解決するためにな
されたもので、比較的小スパンの領域における、
従来の現場施工によるR.C構造と経済的に競合で
きるP.C構造のラーメン構造を得ることである。
This idea was made to solve this problem, and in a relatively small span area,
The aim is to obtain a PC rigid frame structure that is economically competitive with conventional RC structures constructed on-site.

この考案を、一実施例を示す第1図〜第3図に
ついて述べると、同図においてコンクリート製の
梁1の上下方向の中央部より下部に、かつ該梁1
のみに、長さ方向に設けられた第一緊張材2;長
さ方向の端部に上ブラケツト9を有する上記梁
1:高さ方向の途中に下ブラケツト8を有する鉄
筋コンクリート製の柱3;該柱3の上記下ブラケ
ツト8上に、前記上ブラケツト9を乗せることに
より前記梁1を支持している前記柱3;上記梁1
の長さ方向で、かつ上下方向の下部と、前記柱3
をそれぞれ貫いて設けられた第二緊張材4;前記
柱3と前記梁1の上部を連結する連結筋5,5
a;前記下ブラケツト8及び上ブラケツト9並び
に前記第二緊張材4の一部をそれぞれ埋設して、
前記梁1及び柱3間に打設されたコンクリートの
目地充填材10;前記連結筋5,5aを埋設して
前記梁1及び柱3間に打設されたコンクリート7
から成ることを特徴とする組立型プレストレスト
コンクリートラーメン構造である。なお、11は
通線孔、12は空洞、13は床板を示す。そして
前記両ブラケツト8,9は一例として断面T字状
に形成され、平面部において重ねられる。
This invention will be described with reference to FIGS. 1 to 3 showing one embodiment.
The beam 1 has an upper bracket 9 at the end in the length direction; the column 3 made of reinforced concrete has a lower bracket 8 halfway in the height direction; The pillar 3 supports the beam 1 by placing the upper bracket 9 on the lower bracket 8 of the pillar 3; the beam 1
in the longitudinal direction and the lower part in the vertical direction, and the pillar 3
a second tension member 4 provided through each; connecting bars 5, 5 connecting the upper part of the pillar 3 and the beam 1;
a; burying a portion of the lower bracket 8, the upper bracket 9, and the second tendon 4, respectively;
Concrete joint filler 10 placed between the beam 1 and column 3; concrete 7 placed between the beam 1 and column 3 by burying the connecting bars 5, 5a;
It is a prefabricated prestressed concrete rigid frame structure characterized by consisting of. Note that 11 is a wire hole, 12 is a cavity, and 13 is a floor plate. The brackets 8 and 9 are, for example, formed to have a T-shaped cross section, and are overlapped at the plane portion.

又、第4図〜第6図に示すものはこの考案の第
2の実施例を示すものであり、梁1は断面台形に
形成されている。14,15は連結部を示す。な
お柱3は鉄骨構造である。
4 to 6 show a second embodiment of this invention, in which the beam 1 is formed to have a trapezoidal cross section. 14 and 15 indicate connecting portions. Note that the pillar 3 has a steel structure.

第9図、第10図に連結筋5aの異つた種類を
示す。これらは床組に作用する荷重が小さい場合
と、大きい場合の処理方法を示すものである。
9 and 10 show different types of connecting bars 5a. These show methods for handling when the load acting on the floor assembly is small and when it is large.

作 用 梁1の上縁においてはその曲げ応力を緊張材に
頼らないように形成されており、これにより緊張
材の配置形状を単純化し、柱3、梁1接合が簡易
になつている。緊張は第11図〜第14図に示す
ように下縁材だけにたよつている。上縁材の代り
に連結筋(一例として鋼材)5,5aにより一体
的に構成し、後打のコンクリート7で肉付してお
り、これにより梁1の上縁が引張りとなる場合
の、曲げモーメントに耐えさせている。
Function: The upper edge of the beam 1 is formed so that the bending stress does not depend on the tension material, which simplifies the arrangement of the tension material and facilitates the joining of the column 3 and the beam 1. As shown in FIGS. 11 to 14, tension is exerted only on the lower edge material. Instead of the upper edge material, it is integrally constructed with connecting bars 5, 5a (steel material as an example), and is thickened with concrete 7 poured afterwards, which allows for bending when the upper edge of the beam 1 is in tension. It withstands the moment.

実施例 この考案のラーメン構造の工法について述べる
と次の通りである。
EXAMPLE The construction method of the rigid frame structure of this invention will be described as follows.

A;柱の建て込み……柱は3層分一体のもので
も、各層ごとに継ぎ足して行つてもよい。
A: Installing pillars...The pillars can be built into three layers, or they can be added to each layer.

B;梁の架設……梁は工場でプレテンシヨン等の
方式で一次のプレストレスが導入されてい
て、中央部で反り上つている。予め柱3に埋
め込まれたブラケツト等を介して定位置に架
設される。
B: Erection of the beam...The beam has been subjected to primary prestress using a pretension method at the factory, and is warped at the center. It is installed in a fixed position via a bracket or the like embedded in the pillar 3 in advance.

C;床板架設……プレキヤストの床板13を架設
することによつて、梁1中央の反り上りは減
少する。
C: Installation of floorboards: By installing the precast floorboards 13, the warpage at the center of the beam 1 is reduced.

D;緊張材の配置……梁1の下線部に沿つて用意
された、一般的には直線状の通線孔11と柱
3に設けた通線孔によつて、単スパンまたは
複数スパンについて、柱3、梁1を貫通して
緊張材4を配置する。このことは、従来の通
線作業量と比較すれば、格段に手間が省ける
作業となるのである。
D; Arrangement of tendons... for single span or multiple spans, depending on the generally straight wire passage hole 11 prepared along the underlined part of the beam 1 and the wire passage hole provided on the column 3. , the tension members 4 are placed through the columns 3 and the beams 1. Compared to the conventional wiring work, this is a much less labor-intensive work.

E;接合部目地施工と緊張……コンクリート等に
よる目地充填10を行い、その硬化を待つ
て、単スパンまたは複数スパンについて外側
柱の位置で、一挙に緊張することにより柱3
側面と梁1端との圧着接合を全体について同
時に完了し、これと共に梁1には二次のプレ
ストレスが導入されて必要な曲げ抵抗力が付
加される。この場合、緊張材4は一般的にい
つて直線状となし得るので、摩擦による緊張
力損失の少ない有効利用となるのである。
E; Construction and tensioning of joint joints...Fill the joints 10 with concrete, etc., wait for it to harden, and tension the outer columns of a single span or multiple spans at once to tighten the column 3.
The entire crimp bonding between the side surface and the end of the beam 1 is completed at the same time, and at the same time, a secondary prestress is introduced into the beam 1 to add the necessary bending resistance force. In this case, since the tendon material 4 can generally be formed into a straight line, it can be used effectively with less loss of tension force due to friction.

F;梁1端上縁にて連結部材5,5aによる柱3
への結合……柱3側面と梁1端において、連
結部材5,5aと後打のコンクリート7を施
すことで、柱3、梁1の接合が行はれること
と同時に梁1の中央部においても、梁1両側
より架設された床板13間の空間も、併せて
コンクリート打されれば、梁1と合成され、
梁丈についての嵩上げも容易であろう。
F; Column 3 with connecting members 5, 5a at the upper edge of beam 1 end
Connection to... By applying connecting members 5, 5a and post-cast concrete 7 on the side of the column 3 and the end of the beam 1, the connection between the column 3 and the beam 1 is completed, and at the same time at the center of the beam 1. Also, if the space between the floor plates 13 built from both sides of the beam 1 is also poured with concrete, it will be combined with the beam 1,
It would also be easy to raise the beam length.

第4図は、鉄骨の柱3を初めに建てておき、そ
れに梁1と床板13を架設した上で、鉄骨柱周囲
のコンクリートを打込んで進める場合を示してい
る。この場合では、第1図にみるような梁1端と
柱3側面との間に存在した目地部の区分はなく、
柱3コンクリート打に包含されることになる。
FIG. 4 shows a case in which a steel column 3 is first erected, a beam 1 and a floor plate 13 are erected thereon, and then concrete is poured around the steel column. In this case, there is no division of the joint that existed between the end of beam 1 and the side of column 3 as shown in Figure 1.
This will be included in column 3 concrete pouring.

この考案は前記のように構成され、第一緊張材
による梁1の緊張は予め工場において量産的に行
うことができる。又梁1と柱3を貫通する緊張作
業は第2緊張材4のみですむため、面倒な現場に
おける緊張作業を大巾に節減することができる。
従つて従来においては成り立たなかつた小規模の
組立型プレストレストコンクリートラーメン構造
を経済的に成り立たせることができる。
This invention is constructed as described above, and the tensioning of the beam 1 by the first tensioning material can be carried out in mass production in advance at a factory. Further, since only the second tension member 4 is required for tensioning work that penetrates the beam 1 and the column 3, the troublesome work of tensioning at the site can be greatly reduced.
Therefore, it is possible to economically create a small-scale assembled prestressed concrete rigid frame structure, which has not been possible in the past.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第3図はこの考案の実施例を示し、第
1図はプレストレストコンクリートラーメン構造
の概略を示す図、第2図は第1図の−線断面
図、第3図は同−線断面図、第4図は同第2
の実施例を示す第1図に相当する図、第5図は第
4図の−線断面図、第6図は同−線断面
図、第7図は第2図に示す梁の斜視図、第8図は
第5図に示す梁の斜視図、第9図、第10図はそ
れぞれこの考案の第3、第4の実施例を示し、梁
の断面図、第11図〜第14図はそれぞれこの考
案の第5〜第8の実施例を示し、プレストレスト
コンクリートコンクリートラーメン構造の概略
図、第15図は従来の同構造のスパン長さと工事
費との関係を示すグラフ、第16図〜第18図は
それぞれに従来のプレストレストコンクリートラ
ーメン構造の概略を示す図である。 1……梁、2……第一緊張材、3……柱、4…
…第二緊張材、5,5a……連結筋。
Figures 1 to 3 show examples of this invention, Figure 1 is a diagram showing the outline of a prestressed concrete rigid frame structure, Figure 2 is a sectional view taken along the - line in Figure 1, and Figure 3 is a cross-sectional view taken along the same line. Cross-sectional view, Figure 4 is the same as Figure 2.
FIG. 5 is a sectional view taken along the - line in FIG. 4, FIG. 6 is a sectional view taken along the same line, and FIG. 7 is a perspective view of the beam shown in FIG. 2. FIG. 8 is a perspective view of the beam shown in FIG. 5, FIGS. 9 and 10 show third and fourth embodiments of this invention, respectively, and cross-sectional views of the beam, and FIGS. 11 to 14 are 15 is a schematic diagram of a prestressed concrete rigid frame structure, FIG. 15 is a graph showing the relationship between the span length and construction cost of the conventional same structure, and FIGS. Figure 18 is a diagram showing an outline of a conventional prestressed concrete rigid frame structure. 1... Beam, 2... First tendon, 3... Column, 4...
...Second tension material, 5,5a...Connection bar.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] コンクリート製の梁1の上下方向の中央部より
下部に、かつ該梁1のみに、長さ方向に設けられ
た第一緊張材2;長さ方向の端部に上ブラケツト
9を有する上記梁1;高さ方向の途中に下ブラケ
ツト8を有する鉄筋コンクリート製の柱3;該柱
3の上記下ブラケツト8上に、前記上ブラケツト
9を乗せることにより前記梁1を支持している前
記柱3;上記梁1の長さ方向で、かつ上下方向の
下部と、前記柱3をそれぞれ貫いて設けられた第
二緊張材4;前記柱3と前記梁1の上部を連結す
る連結筋5,5a;前記下ブラケツト8及び上ブ
ラケツト9並びに前記第二緊張材4の一部をそれ
ぞれ埋設して前記梁1及び柱3間に打設されたコ
ンクリートの目地充填材10;前記連結筋5,5
aを埋設して前記梁1及び柱3間に打設されたコ
ンクリート7から成ることを特徴とする組立型プ
レストレストコンクリートラーメン構造。
A first tension member 2 provided in the longitudinal direction below the vertical center of a concrete beam 1 and only on the beam 1; the beam 1 having an upper bracket 9 at the end in the length direction; ; A column 3 made of reinforced concrete having a lower bracket 8 halfway in the height direction; The column 3 supporting the beam 1 by placing the upper bracket 9 on the lower bracket 8 of the column 3; a second tension member 4 provided in the longitudinal direction of the beam 1 and passing through the lower part in the vertical direction and the pillar 3; connecting bars 5, 5a connecting the pillar 3 and the upper part of the beam 1; Concrete joint filler 10 cast between the beam 1 and the column 3 by burying the lower bracket 8, the upper bracket 9, and a part of the second tendon 4; the connecting bars 5, 5;
An assembled prestressed concrete rigid frame structure characterized by comprising concrete 7 buried between the beam 1 and the column 3 by burying the concrete 7.
JP14668084U 1984-09-28 1984-09-28 Expired JPH0334963Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14668084U JPH0334963Y2 (en) 1984-09-28 1984-09-28

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14668084U JPH0334963Y2 (en) 1984-09-28 1984-09-28

Publications (2)

Publication Number Publication Date
JPS6162102U JPS6162102U (en) 1986-04-26
JPH0334963Y2 true JPH0334963Y2 (en) 1991-07-24

Family

ID=30704915

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14668084U Expired JPH0334963Y2 (en) 1984-09-28 1984-09-28

Country Status (1)

Country Link
JP (1) JPH0334963Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2618671B2 (en) * 1988-02-05 1997-06-11 株式会社竹中工務店 SRC precast beam and beam-column joint structure

Also Published As

Publication number Publication date
JPS6162102U (en) 1986-04-26

Similar Documents

Publication Publication Date Title
KR100211534B1 (en) The coupling structure between pc wall and pc slab, and the method thereof
JP2522714B2 (en) Construction method of building frame
JPH0334963Y2 (en)
JPH0475322B2 (en)
JPH0520817Y2 (en)
JP2754377B2 (en) Building structure
JPH05287801A (en) Bar arrangement structure of beam in rigid-frame structure made of precast iron reinforcing concrete
JPH0426483Y2 (en)
JPH0634994Y2 (en) Pre-stress introduction Pre-cast steel reinforced concrete girder
JPS60152755A (en) High strength construction of carry-out floor
JPH0673203U (en) Beam-column joint structure
JPH0230492Y2 (en)
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
JPH07139054A (en) Joining method for precast concrete wall plate
JP3154003B2 (en) Column and beam joint structure and construction method
JPS6134468Y2 (en)
JP2518568Y2 (en) Connection structure of steel beams to concrete columns
JPS6335773B2 (en)
JPS5925931Y2 (en) Composite girder using π-shaped steel
JP2784449B2 (en) Steel reinforced concrete foundation
JPH0814144B2 (en) Composite structure
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JP2001146715A (en) Half precast floor slab and its joint structure
JPH07279244A (en) Joint construction between column and beam in multi-story building
WO1989000224A1 (en) Floor structure for buildings