JPS60152755A - High strength construction of carry-out floor - Google Patents

High strength construction of carry-out floor

Info

Publication number
JPS60152755A
JPS60152755A JP564784A JP564784A JPS60152755A JP S60152755 A JPS60152755 A JP S60152755A JP 564784 A JP564784 A JP 564784A JP 564784 A JP564784 A JP 564784A JP S60152755 A JPS60152755 A JP S60152755A
Authority
JP
Japan
Prior art keywords
precast
plate
cast
floor
concrete layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP564784A
Other languages
Japanese (ja)
Other versions
JPH0214499B2 (en
Inventor
敏夫 小西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP564784A priority Critical patent/JPS60152755A/en
Publication of JPS60152755A publication Critical patent/JPS60152755A/en
Publication of JPH0214499B2 publication Critical patent/JPH0214499B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、コンクリート打ちによシ構築するバルコニー
や階上廊下などの持出し床の高強度構築工法に関するも
のである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a high-strength construction method for corrugated floors such as balconies and upstairs hallways constructed by pouring concrete.

(従来技術) 従来、持出し床1の構築は、第1図に示すように所定幅
の長尺基板部2Bの前端部に鼻先2bを立て、その隣接
上面に排水溝2Cを設けたプレキャストコンクリート類
のプレキャスト型枠2を用い、これを支柱3で基板部2
aが水平となるように仮固定し、基板部2aの上に建物
の床4と一緒に現場打ちでコンクリートを打設して現場
打ちコンクリートWI5を形成し、プレキャスト型枠2
と一体化させて持出し床1を形成していた。この場合、
プレキャスト型枠2と現場打ちコンクリート層5との結
合はボルトやワイヤー等のアンカーで行っていた。この
ような持出し床1は、プレキャスト型枠2が床1の一部
となるので、専用の型枠が不要になシ、また型枠の摩り
出し作業が不要になシ、施工が簡単でコストの低減も図
れる等の利点がある。
(Prior art) Conventionally, as shown in FIG. 1, the construction of the raised floor 1 was performed using precast concrete, in which a snout 2b is erected at the front end of a long base plate 2B of a predetermined width, and a drainage groove 2C is provided on the upper surface adjacent to the snout 2b. A precast formwork 2 is used, and this is attached to the base plate part 2 with supports 3.
A is temporarily fixed so that it is horizontal, and concrete is cast on site together with the floor 4 of the building on top of the base plate part 2a to form cast-in-place concrete WI5, and the precast formwork 2
The floor 1 was formed by integrating with the floor 1. in this case,
The precast formwork 2 and the cast-in-place concrete layer 5 were connected using anchors such as bolts and wires. In such a portable floor 1, the precast formwork 2 becomes a part of the floor 1, so there is no need for a dedicated formwork, and there is no need to grind out the formwork, making construction easy and cost-effective. This has the advantage that it can also reduce the amount of water.

しかしながら、このような従来の持出し床1は。However, such a conventional corrugated floor 1.

プレキャスト型枠2と現場打ちコンクリート層5とが完
全一体の構造とはなっていす、プレキャスト型枠2が現
場打ちコンクリート層5に吊シ下けられた構造であシ、
持出し床1の強度は現場打ちコンクリート層5のみが負
担しておシ、特に付は根部分の強度が十分でない欠点が
あった。
The precast formwork 2 and the cast-in-place concrete layer 5 are not completely integrated, but the precast formwork 2 is suspended from the cast-in-place concrete layer 5,
The strength of the raised floor 1 is provided only by the cast-in-place concrete layer 5, and there is a drawback that the strength of the root portion is not sufficient, especially at the base.

また、従来の持出し床1では、鼻先2JLにおける手摺
やフェンス等の荷重によシ、第2図に示すようにプレキ
ャスト型枠2と現場打ちコンクリート層5との継ぎ目が
α、βの角度で開き、そこに雨水が侵入し、両者をつな
ぐアンカーが腐蝕し、永年の使用によシプレキャスト型
枠2が落下する危険があった。
In addition, in the conventional corrugated floor 1, the joint between the precast formwork 2 and the cast-in-place concrete layer 5 opens at angles α and β, as shown in FIG. There was a risk that rainwater would enter there, corrode the anchors connecting the two, and that the cyprecast formwork 2 would fall after years of use.

(発明の目的) 本発明の目的は、持出し7床の強度を著しく向上させる
ことができる持出し床の高強度構築工法を提供するにあ
る。
(Object of the Invention) An object of the present invention is to provide a high-strength construction method for a corbelled floor that can significantly improve the strength of the seven-corbelled floor.

(発明の構成) 本発明は、基板部の先端に鼻先を有するプレキャスト型
枠を、その基板部が水平となる向きに仮固定し、前記基
板部の上に現場打ちで建物の床と一緒に現場打ちコンク
リート層を打設し、前記プレキャスト型枠と前記現場打
ちコンクリート層を一体化させて持出し床を構築する持
出し床の構築工法において、前記プレキャスト型枠とし
てプレキャストコンクリート板の表面にトラス筋がその
基部の1対ボトム筋側を該プレキャストコンクリート板
に埋設しその先端のトップ部側を該ブレキャストコンク
リート板の表面に突出させ且つ前記プレキャストコンク
リート板の先端には鼻先を、その手前には厚肉で表面が
平らな溝底板部を設けてなるグレキャス))ラス板を用
い、前記プレキャストトラス板をそのプレキャストコン
クリート板が水平な向きとなるように仮固定し、また前
記トラス筋のトップ筋に前記現場打ちコンクリート層の
補強筋を溶接して固定し、かかる状態で前記プレキャス
トコンクリート板上に現場打ちでコンクリートを打設し
て前記現場打ちコンクリート層を形成すると共にこの現
場打ちコンクリート層の一部を前記溝底板部上に立上シ
段部として重ねて打設し前記鼻先の立上シ部と共に溝を
形成することを特徴とするものである。
(Structure of the Invention) The present invention provides for temporarily fixing a precast formwork having a snout at the tip of the base plate in a direction in which the base plate is horizontal, and casting it on-site on the base together with the floor of the building. In a construction method for a corrugated floor in which a cast-in-place concrete layer is poured and the precast formwork and the cast-in-place concrete layer are integrated to construct a corrugated floor, truss reinforcements are provided on the surface of the precast concrete plate as the precast formwork. The pair of bottom reinforcement sides of the base are buried in the precast concrete plate, and the top side of the tip thereof is made to protrude from the surface of the precast concrete plate, and the tip of the precast concrete plate has a snout, and the front side thereof has a thick Temporarily fix the precast truss plate so that the precast concrete plate is oriented horizontally using a lath plate (Grecas), which has a grooved bottom plate with a flat surface, and attach it to the top bar of the truss bar. The reinforcing bars of the cast-in-place concrete layer are welded and fixed, and in this state, concrete is cast on the precast concrete plate to form the cast-in-place concrete layer, and a part of this cast-in-place concrete layer. This is characterized in that the groove bottom plate portion is overlaid with a raised step portion formed on the groove bottom plate portion, and a groove is formed together with the raised step portion of the nose tip.

このような構築工法によればプレキャストトラス板のト
ラス筋の存在によシ持出し床の付は根部分の応力が分散
して付は根部分の応力集中を避けることができ、1だ現
場打ちコンクリート層の補強筋をブレキャス))ラス板
のトラス筋の突出部クリ−)iとプレキャストトラス板
即ちプレキャスト型枠との完全一体化を図れて高強度の
持出し床を得ることができる。また、このように両者を
高強度で結合すると、その継ぎ目が開くのを防止でき、
且つ溝底板部のところでは水平打ち継ぎのため一層継ぎ
目の開きを防止でき、アンカーとしてのトラス筋の腐蝕
を防止でき、寿命をのばすことができる。
According to this construction method, due to the presence of truss bars in the precast truss plates, the stress at the roots of the raised floor can be dispersed, and stress concentration at the roots can be avoided. A high-strength corrugated floor can be obtained by completely integrating the reinforcing bars of the layers (bracing)) with the protruding portions of the truss bars of the lath plate (i) and the precast truss plate, that is, the precast formwork. Also, by joining the two with high strength in this way, the seam can be prevented from opening,
In addition, since the groove bottom plate is horizontally spliced, opening of the seam can be further prevented, corrosion of the truss bars serving as anchors can be prevented, and the service life can be extended.

(実施例) 以下本発明の実施例を第3図及び第4図を弁皿して詳細
に説明する。本発明では、プレキャスト型枠としてプレ
キャストコンクリート板6の表面にトラス筋7がその基
部の一端のボトム筋7g。
(Example) Examples of the present invention will be described in detail below with reference to FIGS. 3 and 4. In the present invention, a truss reinforcement 7 is provided on the surface of a precast concrete plate 6 as a precast formwork, and a bottom reinforcement 7g is provided at one end of the base thereof.

T&を該プレキャストコンクリート板6に埋設し、ラチ
ス筋7b 、7bを介して支えられた先端のトップ筋7
C側を該プレキャストコンク’J −) 板6の表面に
突出させ、且つこのプレキャストコンクリート板6の先
端には鼻先8を、その手前には厚肉で表面が平らな溝底
板部9を設けてなるプレキャストトラス板10を用いる
、このプレキャストトラス板10は、補強筋11で隣接
するトラス筋7が溶接により連結され、また、この補強
筋11は鼻先8内にも立上げられて補強がなされている
T& is buried in the precast concrete plate 6, and the top reinforcement 7 at the tip is supported via the lattice reinforcements 7b, 7b.
The C side is made to protrude from the surface of the precast concrete board 6, and the tip of the precast concrete board 6 is provided with a snout 8, and in front of it is provided with a thick grooved bottom plate part 9 with a flat surface. This precast truss plate 10 uses a precast truss plate 10 in which adjacent truss bars 7 are connected by reinforcing bars 11 by welding, and the reinforcing bars 11 are also raised inside the nose tip 8 for reinforcement. There is.

このようなプレキャストトラス板10をそのプレキャス
トコンクリート板6が水平と々る向きに支柱3で仮固定
する。また、プレキャストトラス板10のトラス筋7を
連結している補強筋11は、建物12の梁13内に突出
させ、鼻先8内の補強筋14の一端は現場打ちコンクリ
ート層5の予定側に所要長さにわたって突出させておく
。現場打ちコンクリート層5の補強筋15は、各トラス
筋7のトップ筋7Cに溶接して連結する。この補強筋1
5の一端(111は建物12の床4側に突出させておく
。建物12の壁16内の補強筋1Tは先端を曲げて現場
打ちコンクリート層5の予定部側に突出させておく。
Such a precast truss plate 10 is temporarily fixed with a support 3 in a direction in which the precast concrete plate 6 is horizontally stretched. Further, the reinforcing bars 11 connecting the truss bars 7 of the precast truss plate 10 are made to protrude into the beams 13 of the building 12, and one end of the reinforcing bars 14 in the nose tip 8 is placed on the planned side of the cast-in-place concrete layer 5. Leave it protruding along its length. The reinforcing bars 15 of the cast-in-place concrete layer 5 are welded and connected to the top bars 7C of each truss bar 7. This reinforcing bar 1
One end (111) of 5 is made to protrude toward the floor 4 side of the building 12.The reinforcing bar 1T in the wall 16 of the building 12 is made to protrude toward the planned portion of the cast-in-place concrete layer 5 by bending its tip.

かかる状態で建物12の床4のコンクリート打ちと一緒
にコンクリートを打設して現場打ちコンクリート層5を
形成すると、この現場打ちコンクリート層5内にプレキ
ャス))ラス板10の各トラス筋Tの突出部分が一緒に
埋め込まれ、一体化される。1だ、現場打ちコンクリー
ト層5の一部を溝底板部9上に立上シ段部18として重
ねて打設し、鼻先8の立上シ部19と共に溝20を形成
する。鼻先8の上端には手摺21を設置する。かくして
持出し床1が図示のように成形される。
In this state, when concrete is poured together with the concrete pouring of the floor 4 of the building 12 to form the cast-in-place concrete layer 5, each truss reinforcement T of the lath plate 10 protrudes from the precast concrete layer 5. The parts are embedded together and integrated. 1, a part of the cast-in-place concrete layer 5 is overlaid on the groove bottom plate part 9 as a raised step part 18, and a groove 20 is formed together with the raised part 19 of the nose tip 8. A handrail 21 is installed at the upper end of the nose tip 8. The corrugated floor 1 is thus formed as shown.

次に、このような本発明の構築工法により作つた持出し
床と、従来の工法によυ作った持出し床との強度比較を
行ったところ下記のような結果が得られた。
Next, the strength of the corrugated floor made by the construction method of the present invention and the corrugated floor made by the conventional construction method was compared, and the following results were obtained.

試験体としては、本発明の工法によシ作った持出し床は
第5図及び第6図(この第6図においては、左半部は下
端配筋を示し、右半部上端配筋を示している。)に示す
構造とし、また従来の工法によシ作った持出し床は第7
 [1(従来のプレキャスト型枠は強度にはほとんど関
与してないので省略した。)及び第8図(この第8図に
おいては、左半部は下端配筋を示し、右半部は上端配筋
を示している。)に示す構造とした。
As a test specimen, the corrugated floor made by the construction method of the present invention is shown in Figures 5 and 6 (in Figure 6, the left half shows the lower end reinforcement, and the right half shows the upper end reinforcement). ), and the corrugated floor made using the conventional construction method is the 7th floor.
[1 (Conventional precast formwork is omitted as it has little to do with strength.) and Figure 8 (In Figure 8, the left half shows the lower end reinforcement, and the right half shows the upper end reinforcement. The structure is shown in (showing the lines).

このような試験体を、中央の梁の部分が上を向く姿勢に
し、との状態左右の持出し床の部分の下面を2点で支え
、梁の部分に荷重Pを加えて試験をしたところ本発明の
工法で作った持出し床の荷重−変位曲線は第9図のよう
になシ、従来の工法で作った持出し床の荷重−変位曲線
は第10図のようになり、また本発明の工法で作った持
出し床の荷重−変位曲線の包絡線Aと従来の工法で作っ
た持出し床の荷重−変位曲線の包絡線Bとの比較図を作
製したところ第11図に示すようになった。
When such a test specimen was placed in a position with the central beam facing upwards, the lower surfaces of the floor sections on the left and right sides were supported at two points, and a load P was applied to the beams. The load-displacement curve of the corrugated floor made by the construction method of the invention is as shown in Figure 9, and the load-displacement curve of the corrugated floor made by the conventional construction method is as shown in Figure 10. A comparison diagram between envelope A of the load-displacement curve of the corrugated floor made by the conventional construction method and envelope B of the load-displacement curve of the corrugated floor made by the conventional construction method was prepared, and the result was shown in Fig. 11.

これらの図から明らかなように本発明の工法で作った持
出し床は、従来の工法で作った持出し床よシ強度が著し
く犬となっていることが立証された。
As is clear from these figures, it has been proven that the corrugated floor made by the method of the present invention has significantly higher strength than the corrugated floor made by the conventional method.

(発明の効果) 以上説明したように本発明に係る持出し床の高強度構築
工法では、プレキャスト型枠としてトラス筋を組込んだ
プレキャストトラス板を用い、このプレキャストトラス
板のトラス筋の突出部分に現場打ちコンクリート層の補
強筋を溶接して固定し、この部分を現場打ちコンクリー
ト層中に埋込むので、持出し床の付は根に応力が年中す
るのを分散でき、しかも持出し床を構成するプレキャス
トトラス板と現場打ちコンクリート層との完全一体化を
図ることができて、高強度の持出し床を構築することが
できる。また、このようにプレキャストトラス板と現場
打ちコンクリート層が強く一体化されると、両者の継ぎ
目が開かなくなり、且つ溝底板部では現場打ちコンクリ
ート層は水平打ち継ぎとなシこの面でも継ぎ目の開きを
防止でき、雨水の侵入を肪止し長寿命化を図ることがで
きる。
(Effects of the Invention) As explained above, in the high-strength construction method for a corrugated floor according to the present invention, a precast truss board incorporating truss reinforcements is used as the precast formwork, and the protruding portions of the truss reinforcements of the precast truss board are The reinforcing bars of the cast-in-place concrete layer are welded and fixed, and this part is embedded in the cast-in-place concrete layer, so the stress applied to the roots of the corrugated floor can be dispersed throughout the year, and the corrugated floor can also be constructed. It is possible to completely integrate the precast truss plate and the cast-in-place concrete layer, making it possible to construct a high-strength corrugated floor. In addition, if the precast truss plate and the cast-in-place concrete layer are strongly integrated in this way, the joint between the two will not open, and the cast-in-place concrete layer will have a horizontal joint at the groove bottom plate, so the joint will not open on this side. It is possible to prevent rainwater from entering and extend the lifespan.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の持出し床の横断面図、第2図は従来の持
出し床の継き目の開き状態を示す断面図、第3図は本発
明の工法で構築された持出し床の一例を示す縦断面図、
第4図はトラス筋の一例を示す斜視図、第5図及び第6
図は本発明の工法で作った持出し床試験体の縦断面図及
び配筋状態を示す平面図、第7図及び第8図は従来の工
法で作った持出し床試験体の縦断面図及び配筋状態を示
す平面図、第9図は本発明の工法による試験体の荷重−
変位曲線図、第1O図は従来の工法による試験体の荷重
−変位曲線図、第11図は本発明の工法による試験体の
荷重−変位曲線の包絡線Aと従来の工法による試験体の
荷重−変位曲線の包絡線Bとの比較図である。 1・・・持出し床、3・・・支柱、4・・・建物の床、
5・・・現場打ちコンクリート層、6・・・プレキャス
トコンクリート板、7・・・トラス筋、TIL・・・ボ
トム筋、Tb・・・ラチス筋、7c・・・トップ筋、8
・・・鼻先、9・・・溝底板部、10・・・プレキャス
トトラス板、11・・・補強筋、12・・・建物、13
・・・梁。 特許出願人手 西 敏 夫 第1図 第2図 第3図 第5図 第7図 第9図 第10図 mン 第11図
Fig. 1 is a cross-sectional view of a conventional corrugated floor, Fig. 2 is a sectional view showing the open state of the joints of a conventional corrugated floor, and Fig. 3 is an example of a corrugated floor constructed using the construction method of the present invention. A longitudinal cross-sectional view showing,
Figure 4 is a perspective view showing an example of a truss muscle, Figures 5 and 6
The figure is a longitudinal cross-sectional view and a plan view showing the reinforcing condition of a test piece of a corrugated floor made using the construction method of the present invention, and FIGS. A plan view showing the condition of the striations, and Fig. 9 shows the load of the test specimen by the construction method of the present invention.
Displacement curve diagram, Figure 1O is a load-displacement curve diagram of the test specimen by the conventional construction method, and Figure 11 is the envelope A of the load-displacement curve of the specimen by the construction method of the present invention and the load of the specimen by the conventional construction method. - Comparison diagram of the displacement curve with the envelope B; 1... Extruded floor, 3... Support, 4... Building floor,
5... Cast-in-place concrete layer, 6... Precast concrete plate, 7... Truss bar, TIL... Bottom bar, Tb... Lattice bar, 7c... Top bar, 8
... Nose tip, 9 ... Groove bottom plate part, 10 ... Precast truss plate, 11 ... Reinforcement bar, 12 ... Building, 13
...beam. Patent applicant: Toshio Nishi Figure 1 Figure 2 Figure 3 Figure 5 Figure 7 Figure 9 Figure 10 Figure 11

Claims (1)

【特許請求の範囲】[Claims] (1) 基板部の先端に鼻先を有するプレキャスト型枠
を、その基板部が水平となる向きに仮固定し、前記基板
部の上に現場打ちで建物の床と一緒に現場打ちコンクリ
フト層を打設し、前記プレキャスト型枠と前記現場打ち
コンクリート層を一体化させて持出し床を構築する持出
し床の構築工法において、前記プレキャスト型枠として
プレキャストコンクリート板の表面にトラス筋がその基
部の1対のボトム部側を該プレキャストコンクリート板
に埋設しその先端のトップ部側を該プレキャストコンク
リート板の表面に突出させ且つ前記プレキャストコンク
リート板の先端には鼻先を、その手前には厚内で表面が
平らな溝底板部を設けて々るプレキャストトラス板を用
い、前記プレキャス))ラス板をそのプレキャストコン
クリート篇≠;索平方面Aμhふように仮固定し、また
前記トラス筋のトップ筋に前記現場打ちコンクリート層
の補強筋を済接して固定し、かかる世態で前記プレキャ
ストコンクリート板上に現場打ちでコンクリートを打設
して前記現場打ちコンクリート層を形成すると共にこの
現場打ちコンクリート層の一部を前記溝底板部上に立上
り段部として重ねて打設し前記鼻先の立上シ部と共に溝
を形成することを特徴とする持出し床の高強度構築工法
(1) A precast formwork having a snout at the tip of the base plate is temporarily fixed in an orientation where the base plate is horizontal, and a cast-in-place concrete layer is cast on the base together with the floor of the building. In the construction method of a corrugated floor, in which the precast formwork and the cast-in-place concrete layer are integrated to construct a corrugated floor, a pair of truss bars are provided on the surface of the precast concrete plate as the precast formwork at the base thereof. The bottom side of the plate is buried in the precast concrete plate, and the top side of the tip thereof is made to protrude from the surface of the precast concrete plate, and the tip of the precast concrete plate has a snout, and the front side thereof has a flat surface within the thickness. Using a precast truss plate having a grooved bottom plate, the precast lath plate is temporarily fixed in such a manner that the precast concrete section≠; The reinforcing bars of the concrete layer are connected and fixed, and in this state, concrete is poured on the precast concrete plate to form the cast-in-place concrete layer, and a part of the cast-in-place concrete layer is placed in the groove. 1. A high-strength construction method for a corrugated floor, characterized by forming a raised step on the bottom plate part and forming a groove together with the raised step part of the nose.
JP564784A 1984-01-18 1984-01-18 High strength construction of carry-out floor Granted JPS60152755A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP564784A JPS60152755A (en) 1984-01-18 1984-01-18 High strength construction of carry-out floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP564784A JPS60152755A (en) 1984-01-18 1984-01-18 High strength construction of carry-out floor

Publications (2)

Publication Number Publication Date
JPS60152755A true JPS60152755A (en) 1985-08-12
JPH0214499B2 JPH0214499B2 (en) 1990-04-09

Family

ID=11616921

Family Applications (1)

Application Number Title Priority Date Filing Date
JP564784A Granted JPS60152755A (en) 1984-01-18 1984-01-18 High strength construction of carry-out floor

Country Status (1)

Country Link
JP (1) JPS60152755A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03241127A (en) * 1990-02-19 1991-10-28 Shimizu Corp Construction member of trap of building and construction method by using the same
JPH03108121U (en) * 1990-02-20 1991-11-07
JPH06212687A (en) * 1993-01-14 1994-08-02 Arai Kensetsu Kk Complex building
JP2011001808A (en) * 2009-05-19 2011-01-06 Shimizu Corp Reinforcing structure of column-beam joint portion
JP2011032781A (en) * 2009-08-04 2011-02-17 Shimizu Corp Reinforcing structure for beam-column joint part

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03241127A (en) * 1990-02-19 1991-10-28 Shimizu Corp Construction member of trap of building and construction method by using the same
JPH03108121U (en) * 1990-02-20 1991-11-07
JPH06212687A (en) * 1993-01-14 1994-08-02 Arai Kensetsu Kk Complex building
JP2011001808A (en) * 2009-05-19 2011-01-06 Shimizu Corp Reinforcing structure of column-beam joint portion
JP2011032781A (en) * 2009-08-04 2011-02-17 Shimizu Corp Reinforcing structure for beam-column joint part

Also Published As

Publication number Publication date
JPH0214499B2 (en) 1990-04-09

Similar Documents

Publication Publication Date Title
US5809712A (en) System for joining precast concrete columns and slabs
US20140020317A1 (en) Modular Wall System with Footing Form II
JPS60152755A (en) High strength construction of carry-out floor
JPH0215707B2 (en)
CA2592820A1 (en) Composite floor and composite steel stud wall construction systems
JPH0475322B2 (en)
JPH02300439A (en) Prefabricating method
JPH0122827Y2 (en)
JPH05287801A (en) Bar arrangement structure of beam in rigid-frame structure made of precast iron reinforcing concrete
JPH0932311A (en) Reinforcement structure of existing building
JPH01137034A (en) Framework of composite building construction
JPH0868113A (en) Connecting structure for steel beam and reinforced concrete beam
JPH0334963Y2 (en)
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPH0459426B2 (en)
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPS6134468Y2 (en)
JPS5824968Y2 (en) assembly bridge
CA2522665C (en) Modular wall system with footing form
JPS5845378Y2 (en) Structure of concrete truss
JPS5926001Y2 (en) Precast beam and girder joint structure
JPH03151429A (en) Reinforcement preassembled beam with formwork and working method thereof
JPH0115764Y2 (en)
JPS6335773B2 (en)
JPH0826615B2 (en) Long-span precast concrete beam with a hollow part in the center of the span

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term