JPH076302B2 - Self-supporting utility pole and its construction method - Google Patents

Self-supporting utility pole and its construction method

Info

Publication number
JPH076302B2
JPH076302B2 JP18673290A JP18673290A JPH076302B2 JP H076302 B2 JPH076302 B2 JP H076302B2 JP 18673290 A JP18673290 A JP 18673290A JP 18673290 A JP18673290 A JP 18673290A JP H076302 B2 JPH076302 B2 JP H076302B2
Authority
JP
Japan
Prior art keywords
pole
pipe
steel pipe
flange
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP18673290A
Other languages
Japanese (ja)
Other versions
JPH0473381A (en
Inventor
彦逸 渡辺
Original Assignee
日本地工株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本地工株式会社 filed Critical 日本地工株式会社
Priority to JP18673290A priority Critical patent/JPH076302B2/en
Publication of JPH0473381A publication Critical patent/JPH0473381A/en
Publication of JPH076302B2 publication Critical patent/JPH076302B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、支線或は支柱に依存することなく電柱を自立
させた自立電柱及びその建柱工法に関する。
Description: TECHNICAL FIELD The present invention relates to a self-supporting utility pole in which a utility pole is self-supporting without depending on a branch line or a support pole, and a method for constructing a building pole therefor.

〔従来の技術〕[Conventional technology]

近年、市街地において環境美化のため或は通行の支障を
無くすため、または農耕地においても土地の有効利用や
機械化に伴う農耕上の支障を無くすために電柱の支線或
は支柱を無くすよう電柱自体を自立させて建柱する施工
法が採用されている。
In recent years, in order to beautify the environment or eliminate obstacles to traffic in urban areas, or to eliminate the obstacles on agricultural land due to effective use of land and mechanization, even on agricultural land, the utility pole itself must be removed to eliminate the utility pole branch line or support pole. The construction method of self-standing and building columns is adopted.

そこで、第5図に従来の自立電柱を示すと、この自立電
柱は、コンクリートポール或は鋼管ポールより形成され
た電柱51を土中54に埋設した基礎パイプ52の内腔に挿入
し、地表付近にて基礎パイプ52の上端部を露出した幅広
孔53に急硬セメント56を充填して電柱51と基礎パイプ52
と結合することにより電柱51を自立させてなるものであ
る。
Therefore, FIG. 5 shows a conventional self-supporting power pole. This self-supporting power pole is obtained by inserting a power pole 51 formed of a concrete pole or a steel pipe pole into the inner cavity of a foundation pipe 52 buried in soil 54, and near the surface of the earth. A wide hole 53 exposing the upper end of the foundation pipe 52 is filled with rapid-hardening cement 56, and the utility pole 51 and the foundation pipe 52 are
The utility pole 51 is self-supporting by being coupled with.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

ところで、上記の自立電柱51は長さ14メートルにも及ぶ
一本のポールにより形成されているため、特に市街地に
おいては運搬の際に特殊車両を必要とし、また狭隘な市
街地での建柱施工にも不都合が生じていた。
By the way, since the above-mentioned self-supporting utility pole 51 is formed by a single pole that is 14 meters in length, it requires a special vehicle for transportation, especially in urban areas, and is also suitable for building pillar construction in narrow urban areas. Was causing inconvenience.

なかでもコンクリートポールにより形成された電柱は重
量が大きく、建柱に非常な労力を有し、運搬及び施工に
おいても多大の危険を伴うものであった。
Above all, the utility pole formed by the concrete pole is heavy and requires a great deal of labor for the building pole, and is very dangerous in transportation and construction.

また、鋼管ポールより形成された電柱においては、電気
的絶縁性に問題があり、構造上撓みが生じやすく、また
高価であるという欠点があった。
In addition, the electric pole formed by the steel pipe pole has a problem in that it has a problem in electrical insulation, is liable to bend due to its structure, and is expensive.

さらに、コンクリートポール或は鋼管ポールのいずれに
より形成された電柱であっても、基礎パイプ52との結合
に特殊セメントを要し、また基礎パイプ52の埋設の際に
掘削した縦孔の掘削土の残土処分にも手間を要するもの
であった。
Furthermore, regardless of whether the utility pole is formed by a concrete pole or a steel pipe pole, special cement is required to connect with the foundation pipe 52, and the excavated soil of the vertical hole excavated when the foundation pipe 52 is buried. Disposing of the remaining soil was also laborious.

また、支線或は支柱を不要としたため、電柱51全体にか
かる荷重は地表境界部に集中的に発生し、そのため強度
的には電柱を大径にすべきであるが、一方では環境美化
のための小径化の要請もある。
Also, since no branch lines or columns are needed, the load applied to the entire utility pole 51 is concentrated at the boundary of the ground surface. Therefore, in terms of strength, the utility pole should have a large diameter, but on the other hand for environmental beautification. There is also a request for a smaller diameter.

〔課題を解決するための手段〕[Means for Solving the Problems]

本発明は、以上のような事情に鑑みてなされたもので、
本発明の課題を解決するための手段を、実施例に対応す
る第1図乃至第4図を用いて説明すると、上端にフラン
ジ(4)を固設した基礎パイプ(1)と、下端に前記基
礎パイプ(1)のフランジ(4)とボルト結合されるフ
ランジ(5)を固設し、内腔に縦状の補強板(2a)を固
設した鋼管ポール(2)と、下端に前記鋼管ポール
(2)の上端部に嵌合される縦鋼管(6)を一体結合し
たコンクリートポール(3)との組み合わせからなるこ
とを特徴とする自立電柱であって、その建柱工法は土中
(10)に掘削された縦孔(12)に基礎パイプ(1)を埋
設し、前記基礎パイプ(1)の上端に設けられたフラン
ジ(4)と鋼管ポール(2)の下端に固設されたフラン
ジ(5)とをボルト(8)により互いに結合することに
より前記鋼管ポール(2)を前記基礎パイプ(1)上に
自立させ、さらにコンクリートポール(3)の下端に一
体結合された縦鋼管(6)を前記鋼管ポール(2)の上
端部に嵌合して該コンクリートポール(3)を前記鋼管
ポール(2)の上に連結させたことを特徴とするもので
ある。
The present invention has been made in view of the above circumstances,
A means for solving the problems of the present invention will be described with reference to FIGS. 1 to 4 corresponding to an embodiment. A base pipe (1) having a flange (4) fixedly provided on an upper end thereof and the above-mentioned base pipe at a lower end thereof. A steel pipe pole (2) having a flange (5) fixed to the flange (4) of the base pipe (1) by bolts and a vertical reinforcing plate (2a) fixed to the inner cavity, and the steel pipe at the lower end. A self-supporting utility pole comprising a combination of a vertical steel pipe (6) fitted to an upper end portion of a pole (2) and a concrete pole (3) integrally coupled to the pole (2). The foundation pipe (1) was embedded in the vertical hole (12) excavated in 10), and the flange (4) provided at the upper end of the foundation pipe (1) and the lower end of the steel pipe pole (2) were fixed. By connecting the flange (5) and the flange (5) to each other by the bolt (8), the steel pipe pole (2 On the foundation pipe (1), and a vertical steel pipe (6) integrally connected to the lower end of the concrete pole (3) is fitted to the upper end of the steel pipe pole (2) to make the concrete pole (3). ) Is connected on the steel pipe pole (2).

また、前記基礎パイプ(1)は、土中(10)に掘削され
た縦孔(12)よりやや大径とし、その下端縁に切削刃
(7)を固着すると共に内腔の途中にスクリューオーガ
の先端銛(16)と係止するストッパ(17)を固設すれ
ば、前記スクリューオーガの先端銛(16)を前記ストッ
パ(17)に係合して押し下げることにより前記基礎パイ
プ(1)を前記縦孔(12)に埋設することができる。
Further, the foundation pipe (1) has a diameter slightly larger than that of the vertical hole (12) excavated in the soil (10), the cutting edge (7) is fixed to the lower end edge of the foundation pipe (1), and the screw auger is provided in the middle of the bore. If a stopper (17) that locks with the tip harpoon (16) of the screw auger is fixed, the tip harpoon (16) of the screw auger is engaged with the stopper (17) and pushed down to move the base pipe (1). It can be embedded in the vertical hole (12).

〔作用〕[Action]

従来一本のポールにより地中に一部を埋設して形成され
た電柱が、本発明においては、地表下の基礎パイプ
(1)と地表上の電柱部とを分離可能としたうえ、地表
上の電柱部をも鋼管ポール(2)とコンクリートポール
(3)との結合構造としたため、地表上の各構成部材を
概して従来の電柱の半分以下の長さに分割でき、運搬及
び建柱施工に利便となる。ただし、鋼管ポール(2)と
コンクリートポール(3)の長さは半分割に限定され
ず、強度等の関係から決定できる。
In the present invention, a utility pole that is conventionally formed by partially burying it in the ground with a single pole makes it possible to separate the subsurface foundation pipe (1) from the utility pole section on the surface of the earth, and Since the utility pole part is also the connection structure of the steel pipe pole (2) and the concrete pole (3), each component on the ground surface can be generally divided into less than half the length of conventional utility poles, and it can be used for transportation and construction pole construction. It will be convenient. However, the lengths of the steel pipe pole (2) and the concrete pole (3) are not limited to half-division, and can be determined from the relationship of strength and the like.

また、電柱の上側はコンクリートポール(3)により構
成されるから、電線を張るための腕金はコンクリートポ
ール(3)側に設けられ、電気的絶縁性を安全に確保で
きる。
Moreover, since the upper side of the electric pole is constituted by the concrete pole (3), the arm for tensioning the electric wire is provided on the concrete pole (3) side, and the electrical insulation can be secured safely.

また、鋼管ポール(2)は土中(10)に埋設された基礎
パイプ(1)の上端に互いのフランジ(4、5)を介し
てボルト(6)により結合されるから、従来のように基
礎構造と結合するための急硬セメントによる処置が不要
となり、また基礎パイプ(1)を土中に埋設したまま地
表部の電柱の立替工事が可能となる。
Further, since the steel pipe pole (2) is connected to the upper end of the foundation pipe (1) buried in the soil (10) with the bolts (6) via the flanges (4, 5) of each other, as in the conventional case. There is no need for treatment with rapid-hardening cement to connect with the foundation structure, and replacement work of the utility pole on the surface can be performed with the foundation pipe (1) buried in the soil.

さらに、鋼管ポール(2)はその内腔に縦状の補強板
(2a)が固設した構成としてあるから、電柱全体の荷重
が集中する鋼管ポール(2)の強度を増し、また補強板
(2a)を電柱全体に取付けるのに対し本発明では分割さ
れた長さの鋼管ポール(2)に取付ければよいから製作
上の手間が減縮される。
Further, since the steel pipe pole (2) has a structure in which a vertical reinforcing plate (2a) is fixedly installed in its inner cavity, the strength of the steel pipe pole (2) on which the load of the entire electric pole is concentrated is increased, and the reinforcing plate (2 2a) is attached to the entire electric pole, whereas in the present invention, it is sufficient to attach it to the steel pipe pole (2) having a divided length, which reduces the manufacturing labor.

〔実施例〕〔Example〕

以下、本発明の実施例を図面を参照しながら説明する。 Hereinafter, embodiments of the present invention will be described with reference to the drawings.

第1図は本発明による自立電柱の立面図、第2図(a)
は第1図のA−A線に沿う横断面図、第2図(b)は第
1図のB−B線に沿う横断面図、第2図(c)は第1図
のC−C線に沿う横断面図、第2図(d)は第2図
(c)の他の実施例を示す横断面図、第3図は第1図の
地表下付近を示す部分拡大側面図、第4図(a)乃至
(e)は第1図示の自立電柱を建柱する施工工程図であ
る。
FIG. 1 is an elevation view of a self-supporting utility pole according to the present invention, and FIG. 2 (a).
1 is a cross sectional view taken along the line AA of FIG. 1, FIG. 2 (b) is a cross sectional view taken along the line BB of FIG. 1, and FIG. 2 (c) is a line CC of FIG. FIG. 2 (d) is a cross-sectional view showing another embodiment of FIG. 2 (c), and FIG. 3 is a partially enlarged side view showing the vicinity of the ground surface of FIG. 4A to 4E are construction process diagrams for constructing the self-supporting utility pole shown in FIG.

第1図において、1は土中10に埋設された基礎パイプで
あり、2は基礎パイプ1上に結合して自立した鋼管ポー
ルであり、3は鋼管ポール2上に連結して自立したコン
クリートポールである。
In FIG. 1, 1 is a foundation pipe buried in the soil 10, 2 is a steel pipe pole that is connected to the foundation pipe 1 and is independent, and 3 is a concrete pole that is connected to the steel pipe pole 2 and is independent. Is.

基礎パイプ1は、土中10に掘削された縦孔12よりやや大
径を有し、その下端縁外周には複数の切削刃7,7・・・
が固着され、その内腔の途中にはスクリューオーガの先
端銛16と係止するストッパ17(第4図(a)及び
(b))を固設してなり、さらにその上端にはフランジ
4が固設されている。
The base pipe 1 has a diameter slightly larger than the vertical hole 12 excavated in the soil 10, and a plurality of cutting blades 7, 7 ...
Is fixed, and a stopper 17 (Figs. 4 (a) and (b)) that locks with the tip harpoon 16 of the screw auger is fixed in the middle of the lumen, and the flange 4 is further provided at the upper end. It is fixed.

鋼管ポール2は、下端に基礎パイプ1のフランジ4と同
径のフランジ5を固設され、これら基礎パイプ1と鋼管
ポール2とは第3図に示すように互いにボルト8により
結合される。
The steel pipe pole 2 has a lower end fixed with a flange 5 having the same diameter as the flange 4 of the foundation pipe 1, and the foundation pipe 1 and the steel pipe pole 2 are connected to each other by bolts 8 as shown in FIG.

なお、縦孔12の地表下には基礎パイプ1のフランジ4の
外径よりやや大径の幅広孔13が穿設され、基礎パイプ1
と鋼管ポール2のフランジ4及び5の結合構造を土中10
の地表下に収容してある。
Below the surface of the vertical hole 12, a wide hole 13 having a diameter slightly larger than the outer diameter of the flange 4 of the foundation pipe 1 is bored.
And the connection structure of the flanges 4 and 5 of the steel pipe pole 2 in the soil 10
It is housed under the ground.

また、鋼管ポール2の内腔は、第2図(c)及び(d)
に示すような十字またはY字状等の横断面形状を有する
補強板2aを該内腔の縦方向に固設して鋼管ポール2の強
度を増している。なお、補強板2aの構成は、強度及び製
作の都合上その他種々のものが考えられる。
The inner diameter of the steel pipe pole 2 is shown in FIGS. 2 (c) and (d).
The strength of the steel pipe pole 2 is increased by fixing a reinforcing plate 2a having a cross-sectional shape such as a cross or a Y shape as shown in FIG. It should be noted that the reinforcing plate 2a may have various configurations in consideration of strength and production.

コンクリートポール3は、第2図(a)に示すように、
内部に補強用鉄筋3aを縦状に配筋すると共に下端部外周
に縦鋼管6を一体的に結合し、縦鋼管6の下端を中空状
に突設してあり、該中空部6aに鋼管ポール2の上端部を
嵌合して連結してある。
The concrete pole 3 is, as shown in FIG. 2 (a),
A reinforcing steel bar 3a is vertically arranged inside and a vertical steel pipe 6 is integrally connected to the outer periphery of the lower end portion, and the lower end of the vertical steel pipe 6 is projected in a hollow shape, and a steel pipe pole is provided in the hollow portion 6a. The upper ends of the two are fitted and connected.

このような自立電柱の建柱工法について第4図を参照し
ながら説明すると、まず土中10の所要位置に対し地表面
からスクリューオーガ15により縦孔12を掘削する。但
し、縦孔12の孔径は挿入すべき基礎パイプ1の外径より
やや大径に形成する。
A method of constructing such a self-supporting utility pole will be described with reference to FIG. 4. First, a vertical hole 12 is excavated from the ground surface with a screw auger 15 at a required position in the soil 10. However, the hole diameter of the vertical hole 12 is formed to be slightly larger than the outer diameter of the base pipe 1 to be inserted.

次いで、縦孔12の地表下に基礎パイプ1のフランジ4が
収容される幅広孔13を穿孔しておいて、スクリューオー
ガ15の先端銛16を基礎パイプ1内のストッパ17に係合さ
せ下方に荷重をかけつつスクリューオーガ15を回転する
と、基礎パイプ12も回転して基礎パイプ12の下端縁の切
削刃7,7・・・によって縦孔12内壁が切り崩されながら
(第4図(b))、基礎パイプ12は縦孔12の内周に密実
に挿入される(第4図(c))。
Next, a wide hole 13 for accommodating the flange 4 of the foundation pipe 1 is bored below the surface of the vertical hole 12, and the tip harpoon 16 of the screw auger 15 is engaged with a stopper 17 in the foundation pipe 1 to move downward. When the screw auger 15 is rotated while applying a load, the foundation pipe 12 is also rotated and the inner wall of the vertical hole 12 is broken down by the cutting blades 7, 7 ... At the lower end edge of the foundation pipe 12 (Fig. 4 (b)). ), The foundation pipe 12 is densely inserted into the inner periphery of the vertical hole 12 (Fig. 4 (c)).

そこで、基礎パイプ1の上端に設けられたフランジ4に
対し、鋼管ポール2の下端に設けられたフランジ5とを
互いにボルト8で結合することにより鋼管ポール2を基
礎パイプ1上に自立させる(第4図(d))。基礎パイ
プ1のフランジ4及び鋼管ポール2のフランジ5の結合
後、幅広孔13の空所に砂11を埋めておく。
Therefore, the flange 4 provided at the upper end of the base pipe 1 is connected to the flange 5 provided at the lower end of the steel pipe pole 2 by bolts 8 so that the steel pipe pole 2 is self-supporting on the base pipe 1 ( FIG. 4 (d)). After the flange 4 of the base pipe 1 and the flange 5 of the steel pipe pole 2 are connected, sand 11 is filled in the void of the wide hole 13.

さらに、鋼管ポール2の上端部に対してコンクリートポ
ール3下端の縦鋼管6を嵌合することによりコンクリー
トポール3を鋼管ポール2の上に連結させ(第4図
(e))、第1図に示すような自立電柱を完成させる。
Further, by fitting the vertical steel pipe 6 at the lower end of the concrete pole 3 to the upper end portion of the steel pipe pole 2, the concrete pole 3 is connected onto the steel pipe pole 2 (Fig. 4 (e)), and as shown in Fig. 1. Complete a self-supporting utility pole as shown.

〔発明の効果〕〔The invention's effect〕

以上説明したように、本発明は、地表下の基礎パイプと
地表上の電柱部とを分離可能とした上、地表上の電柱部
をも鋼管ポールとコンクリートポールとの結合構造とし
たため、従来の1本よりなる電柱に比べると各部材の長
さを非常に短く構成でき、さらにこれら各構成部材を施
工現場にて組立可能としたため、製作、運搬及び施工面
での取り扱いを極めて容易とするものである。なかでも
市街地での施工にあたり特殊車両を必要とせずに簡便に
運搬でき、また狭隘な場所での取り扱いを容易とし、危
険を極力回避できるものである。
As described above, the present invention has a structure in which the foundation pipe below the surface of the earth and the electric pole portion on the surface of the earth can be separated, and the electric pole portion on the surface of the earth is also a combined structure of a steel pipe pole and a concrete pole, The length of each member can be made very short compared to a utility pole consisting of one piece, and since these constituent members can be assembled at the construction site, it is extremely easy to handle in production, transportation and construction. Is. In particular, it does not require a special vehicle for construction in urban areas, can be easily transported, and can be handled easily in narrow spaces, thus avoiding danger as much as possible.

また、電線を張るための腕金は電柱の上側を構成するコ
ンクリートポールに設けられるから、電気的絶縁性を安
全に確保できる。
In addition, since the arm for stretching the electric wire is provided on the concrete pole that constitutes the upper side of the electric pole, the electrical insulation can be secured safely.

さらに、地表上の鋼管ポールと地表下の基礎パイプとの
結合は互いのフランジを介してボルト結合により堅固に
行うことができるから、従来のように急硬セメントによ
る処置が不要となり、また基礎パイプを土中に埋設した
まま地表の電柱部材のみの立替工事が可能となる。
Furthermore, since the steel pipe pole on the surface of the ground and the foundation pipe below the surface of the ground can be firmly connected by bolt connection through the flanges of each other, there is no need for treatment with rapid hardening cement as in the past, and the foundation pipe It will be possible to replace only the utility pole members on the surface of the ground while burying it in the soil.

また、電柱全体の荷重が集中する鋼管ポール側は、内腔
の補強板を強化することによって高強度とすることがで
きるから、鋼管ポールの外径を大きくせずに高強度化を
実現し、さらには細径化をも可能とし、環境美化の保全
にも有益である。
In addition, the steel pipe pole side where the load of the entire electric pole is concentrated can be made to have high strength by strengthening the reinforcing plate of the inner cavity, so high strength is realized without increasing the outer diameter of the steel pipe pole, Furthermore, it is possible to reduce the diameter, which is beneficial for the preservation of environmental beautification.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明による自立電柱の立面図、第2図(a)
は第1図のA−A線に沿う横断面図、第2図(b)は第
1図のB−B線に沿う横断面図、第2図(c)は第1図
のC−C線に沿う横断面図、第2図(d)は第2図
(c)の他の実施例を示す横断面図、第3図は第1図の
地表下付近を示す部分拡大側面図、第4図(a)乃至
(e)は第1図示の自立電柱を建柱する施工工程図、第
5図は従来の自立電柱の側面図である。 1……基礎パイプ、2……鋼管ポール、2a……補強板、
3……コンクリートポール、4……基礎パイプ側のフラ
ンジ、5……鋼管ポールのフランジ、6……縦鋼管、7
……切削刃、8……ボルト。
FIG. 1 is an elevation view of a self-supporting utility pole according to the present invention, and FIG. 2 (a).
1 is a cross sectional view taken along the line AA of FIG. 1, FIG. 2 (b) is a cross sectional view taken along the line BB of FIG. 1, and FIG. 2 (c) is a line CC of FIG. FIG. 2 (d) is a cross-sectional view showing another embodiment of FIG. 2 (c), and FIG. 3 is a partially enlarged side view showing the vicinity of the ground surface of FIG. 4 (a) to (e) are construction process diagrams for constructing the self-supporting utility pole shown in FIG. 1, and FIG. 5 is a side view of a conventional self-supporting utility pole. 1 ... Foundation pipe, 2 ... Steel pipe pole, 2a ... Reinforcing plate,
3 …… Concrete pole, 4 …… Flange on the base pipe side, 5 …… Steel pipe pole flange, 6 …… Vertical steel pipe, 7
…… Cutting blade, 8 …… bolt.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】上端にフランジ(4)を固設した基礎パイ
プ(1)と、下端に前記基礎パイプ(1)のフランジ
(4)とボルト結合されるフランジ(5)を固設し、内
腔に縦状の補強板(2a)を固設した鋼管ポール(2)
と、下端に前記鋼管ポール(2)の上端部に嵌合される
縦鋼管(6)を一体結合したコンクリートポール(3)
との組み合わせからなることを特徴とする自立電柱。
1. A base pipe (1) having a flange (4) fixed to the upper end, and a flange (5) bolted to the flange (4) of the base pipe (1) at the lower end. Steel pipe pole (2) with a vertical reinforcing plate (2a) fixed in the cavity
And a concrete pole (3) integrally connected to the lower end with a vertical steel pipe (6) fitted to the upper end of the steel pipe pole (2)
A free-standing utility pole that is characterized by being combined with.
【請求項2】土中(10)に掘削された縦孔(12)に基礎
パイプ(1)を埋設し、前記基礎パイプ(1)の上端に
設けられたフランジ(4)と鋼管ポール(2)の下端に
固設されたフランジ(5)とをボルト(8)により互い
に結合することにより前記鋼管ポール(2)を前記基礎
パイプ(1)上に自立させ、さらにコンクリートポール
(3)の下端に一体結合された縦鋼管(6)を前記鋼管
ポール(2)の上端部に嵌合して該コンクリートポール
(3)を前記鋼管ポール(2)の上に連結させたことを
特徴とする自立電柱の建柱工法。
2. A foundation pipe (1) is embedded in a vertical hole (12) excavated in the soil (10), and a flange (4) and a steel pipe pole (2) provided at the upper end of the foundation pipe (1). ), The steel pipe pole (2) is made to stand on the foundation pipe (1) by connecting the flange (5) fixed to the bottom end of the concrete pipe (1) to each other with a bolt (8), and the bottom end of the concrete pole (3). A vertical steel pipe (6) integrally connected to the steel pipe pole (2) is fitted to the upper end of the steel pipe pole (2) to connect the concrete pole (3) to the steel pipe pole (2). Construction method of building pole.
【請求項3】前記基礎パイプ(1)は、土中(10)に掘
削された縦孔(12)よりやや大径とし、その下端縁に切
削刃(7)を固着すると共に内腔の途中にスクリューオ
ーガの先端銛(16)と係止するストッパ(17)を固設
し、前記スクリューオーガの先端銛(16)を前記ストッ
パ(17)に係合して押し下げることにより前記基礎パイ
プ(1)を前記縦孔(12)に埋設することを特徴とする
請求項2記載の自立電柱の建柱工法。
3. The foundation pipe (1) has a diameter slightly larger than that of a vertical hole (12) excavated in the soil (10), and a cutting blade (7) is fixed to the lower end edge of the foundation pipe (1) along the inner cavity. A stopper (17) that locks the tip harpoon (16) of the screw auger is fixed to the base pipe (1) by pushing the tip harpoon (16) of the screw auger into the stopper (17) and pushing it down. ) Is buried in the vertical hole (12), the method for constructing a self-supporting utility pole according to claim 2.
JP18673290A 1990-07-13 1990-07-13 Self-supporting utility pole and its construction method Expired - Lifetime JPH076302B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18673290A JPH076302B2 (en) 1990-07-13 1990-07-13 Self-supporting utility pole and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18673290A JPH076302B2 (en) 1990-07-13 1990-07-13 Self-supporting utility pole and its construction method

Publications (2)

Publication Number Publication Date
JPH0473381A JPH0473381A (en) 1992-03-09
JPH076302B2 true JPH076302B2 (en) 1995-01-30

Family

ID=16193676

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18673290A Expired - Lifetime JPH076302B2 (en) 1990-07-13 1990-07-13 Self-supporting utility pole and its construction method

Country Status (1)

Country Link
JP (1) JPH076302B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004048165A1 (en) * 2004-10-02 2006-04-06 BBL Bahnbau Lüneburg GmbH Device for founding signal towers
KR100758546B1 (en) * 2007-04-04 2007-09-13 주식회사 도화종합기술공사 The overthrow preventive construction of high pressure electricity steel tower
CN105715094B (en) * 2016-02-16 2019-05-03 国家电网公司 A kind of high-voltage wire protective device
ES2726226B2 (en) * 2018-04-02 2021-05-28 Structural Concrete & Steel S L PREFABRICATED CONCRETE POST
WO2023228517A1 (en) * 2022-05-26 2023-11-30 株式会社神戸製鋼所 Pole structure and production method therefor

Also Published As

Publication number Publication date
JPH0473381A (en) 1992-03-09

Similar Documents

Publication Publication Date Title
US7556752B1 (en) Multi-sectional form for forming bases for light poles
JP3986392B2 (en) Columnar reinforcement
US4107889A (en) Foundation system
US4052827A (en) Ground anchor and foundation support
JPH076302B2 (en) Self-supporting utility pole and its construction method
KR200257289Y1 (en) The concrete form constructed basic concrete structure of pole in electric railroads
JP4154492B2 (en) Pile head connection structure of ready-made piles
EP1208270B1 (en) Foundation and method for its production
JP2966765B2 (en) Underground construction members burying method
JPH09151463A (en) Column-integrated column base anchoring foundation structire and work execution method therefor
JPS6013863Y2 (en) building foundations
JP3077137U (en) Support structure of pillar
JP3114038B2 (en) Independent tree planting method and apparatus
JP3595070B2 (en) Basic structure of simple building
KR102152396B1 (en) The structure to extend the length for penetration of prestressed concrete pole and the method thereof
KR101003855B1 (en) Structure of road sign frame and construction method thereof
JPS6312195Y2 (en)
KR200257292Y1 (en) The concrete form constructed basic concrete structure of pole in electric railroads
JPH0417632Y2 (en)
KR900006911Y1 (en) Electric pole
JP3025865B2 (en) Construction method of pole foundation
JPS6127428Y2 (en)
CA1287730C (en) Fence posts
JPH0336369B2 (en)
JPH11256877A (en) Attaching construction for temporary long-sized pole member