JPH07331985A - Preceding lock bolt construction and boring method of large section tunnel by means of release blasting - Google Patents

Preceding lock bolt construction and boring method of large section tunnel by means of release blasting

Info

Publication number
JPH07331985A
JPH07331985A JP12494094A JP12494094A JPH07331985A JP H07331985 A JPH07331985 A JP H07331985A JP 12494094 A JP12494094 A JP 12494094A JP 12494094 A JP12494094 A JP 12494094A JP H07331985 A JPH07331985 A JP H07331985A
Authority
JP
Japan
Prior art keywords
lock bolt
relay rod
excavation
hole
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12494094A
Other languages
Japanese (ja)
Other versions
JP2723469B2 (en
Inventor
Michihiko Watanabe
道彦 渡辺
Yasunobu Shiraishi
康信 白石
Tomoyuki Nakanishi
智之 中西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP12494094A priority Critical patent/JP2723469B2/en
Publication of JPH07331985A publication Critical patent/JPH07331985A/en
Application granted granted Critical
Publication of JP2723469B2 publication Critical patent/JP2723469B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To lower the cost of production by making improvements in safety and productivity, in the natural ground of a medium hard rock. CONSTITUTION:A pilot tunnel B is constructed in the lower half part of a boring scheduled section A, while a lock bolting hole is bored in the inmost recess of the section A from the tunnel B, inserting each lock bolt 4 into the hole, and it is bonded by a fixer material, and peripheral natural ground is joined together by these lock bolts 4. Utilizing the rest holes, the natural ground is released to some extent by means of blasting and an upper half part A1 is bored and, after earth is discharged and concrete 13 is sprayed around, the lower half part is bored and earth is discharged as well, and thus those of boring, earth-moving and concrete spraying are parallelly carried out at the same time.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、先行ロックボルト施工
及び緩め発破による大断面トンネルの掘削方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of excavating a large-section tunnel by constructing a preceding rock bolt and loosening and blasting.

【0002】[0002]

【従来の技術】トンネルの掘削においては、切羽面の地
質に応じて発破やブレーカ、ショベル等により切羽面を
1〜2m掘進し、排土したのちに支保工の建込みやロッ
クボルトを施工して地山の緩みや切羽面の崩壊を防止し
ている。その後に、天端の崩落や肌落ちを防ぐため、吹
付けコンクリートを施工している。
2. Description of the Related Art When excavating a tunnel, the face of the face is excavated by blasting, breaking, shoveling, etc., depending on the geology of the face of the face by 1-2 m. It prevents loosening of the ground and collapse of the face. After that, shotcrete is applied to prevent the crown and the skin from falling off.

【0003】[0003]

【発明が解決しようとする課題】このように従来技術で
は、切羽の手前1〜2mの間で上記作業を施工する必要
があるため、危険性が高くて生産性が低くコストダウン
が図れない。
As described above, according to the prior art, it is necessary to carry out the above-mentioned work within 1 to 2 m before the face, so that the risk is high, the productivity is low, and the cost cannot be reduced.

【0004】本発明は、中硬岩の地山において、安全性
及び生産性を向上し、コストダウンを図る先行ロックボ
ルト施工及び緩め発破による大断面トンネルの掘削方法
を提供する事を目的としている。
It is an object of the present invention to provide a method for excavating a large-section tunnel by constructing a preceding rock bolt and loosening and blasting to improve the safety and productivity and reduce the cost in the medium-hard rock ground. .

【0005】[0005]

【課題を解決するための手段】本発明による掘削方法
は、掘削予定断面の下半部にパイロットトンネルを構築
するパイロットトンネル構築工程と、該パイロットトン
ネルから予定掘削断面の奥へ掘削巾の所定割合の深さま
でロックボルト用孔を削孔するロックボルト用孔削孔工
程と、ロックボルト用孔の孔尻に定着材を挿入する定着
材挿入工程と、ロックボルト用孔にロックボルト及びロ
ックボルト挿入用中継ロッドをねじ部で継ぎ足し回転し
ながら挿入するロックボルト及びロックボルト挿入用中
継ロッド挿入工程と、ロックボルトに回転を与えながら
押し込む事により孔尻の定着材を混合攪拌してロックボ
ルトと地山間を全面接着させる定着材混合攪拌工程と、
ロックボルト挿入用中継ロッドを逆回ししてロックボル
ト挿入用中継ロッドをロックボルトから分離するロック
ボルト挿入用中継ロッド分離工程と、ロックボルト挿入
用中継ロッドをパイロットトンネル内に引き戻し、ねじ
部を外して回収するロックボルト挿入用中継ロッド回収
工程と、前記ロックボルト用孔削孔工程からロックボル
ト挿入用中継ロッド回収工程までを繰り返して予定掘削
断面外の周辺地山を複数のロックボルトで縫地するロッ
クボルトによる縫地工程と、縫地工程で残った孔を利用
して掘削を容易にするための緩め発破工程と、パイロッ
トトンネル内に排土設備を設置する排土設備設置工程
と、掘削予定断面の上半部を掘削し、掘削土は排土設備
で排土する上半部掘削工程と、上半部掘削面にコンクリ
ートを吹き付けるコンクリート吹付工程と、大断面トン
ネルの下半部を掘削して掘削土を排土する下半部掘削工
程とを含む事を特徴としている。
The excavation method according to the present invention comprises a pilot tunnel construction step of constructing a pilot tunnel in the lower half of the planned excavation section, and a predetermined ratio of the excavation width from the pilot tunnel to the interior of the planned excavation section. Rock bolt hole drilling process to drill the lock bolt hole to the depth of the lock bolt, fixing material insertion process to insert the fixing material into the hole end of the lock bolt hole, and lock bolt and lock bolt insertion to the lock bolt hole Lock rod and relay rod insertion step for inserting the relay rod for rotation with the threaded portion while rotating, and the fixing material at the hole end is mixed and agitated by pushing while pushing the lock bolt while rotating the lock bolt and the ground bolt. Fixing material mixing and agitation process that adheres all the mountains together,
The relay rod for inserting the lock bolt is reversely rotated to separate the relay rod for inserting the lock bolt from the lock bolt, and the relay rod for inserting the lock bolt is pulled back into the pilot tunnel and the screw is removed. By repeating the process of collecting the relay rod for inserting the lock bolt and the hole drilling process for the lock bolt to the process of collecting the relay rod for inserting the lock bolt, the surrounding ground outside the planned excavation section is sewn with multiple lock bolts. The sewn process using the lock bolt, the loosening and blasting process to facilitate the excavation by using the holes left in the sewing process, the excavation facility installation process to install the excavation facility in the pilot tunnel, and the excavation The upper half of the planned section is excavated, and the excavated soil is excavated by the earth removing equipment. A cleat spraying step, and characterized by comprising a lower half of the excavation process of earth removal of soil excavated by drilling a lower half of the large cross-section tunnels.

【0006】[0006]

【作用】本発明の掘削方法においては、掘削予定断面の
外側の周辺地山を複数のロックボルトで縫地する。つい
で、緩め発破を行い、掘削予定断面の上半部を掘削し掘
削土を排土してコンクリートを吹付けたのち、下半部を
掘削して排土し、掘削排土及びコンクリートの吹付けを
同時に並行作業する。
In the excavating method of the present invention, the peripheral ground on the outer side of the planned excavation section is sewn with a plurality of lock bolts. Then, loosen and blast, excavate the upper half of the planned excavation section, discharge the excavated soil and spray the concrete, then excavate the lower half and discharge the soil, excavate the soil and spray the concrete. Work in parallel at the same time.

【0007】[0007]

【実施例】以下図面を参照して本発明の実施例を説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

【0008】(1) パイロットトンネル構築工程(図
1) 大断面トンネルの掘削予定断面Aの下半部に、パイロッ
トトンネルBを図示しないトンネルボーリングマシンで
構築する。そのトンネルBの内径Dは、高さH(例えば
7.4m)の掘削予定断面Aの巾W(例えば12m)に
対し例えば3m程度とする。
(1) Pilot tunnel construction step (FIG. 1) A pilot tunnel B is constructed in the lower half of the excavated section A of the large section tunnel by a tunnel boring machine (not shown). The inner diameter D of the tunnel B is, for example, about 3 m with respect to the width W (for example, 12 m) of the excavation planned cross section A having the height H (for example, 7.4 m).

【0009】(2) ロックボルト用孔削孔工程(図
2) パイロットトンネルB内から、削孔機1により掘削予定
断面Aの奥へ巾Wの例えば1/5〜1/3の深さhまで
ロックボルト用孔2を削孔する。
(2) Rock bolt hole drilling process (FIG. 2) From inside the pilot tunnel B to the depth of the planned excavation section A by the hole drilling machine 1, for example, a depth h of 1/5 to 1/3 of the width W Drill the hole 2 for the lock bolt.

【0010】(3) 定着材挿入工程(図3) ロックボルト用孔2の孔尻に、定着材(例えば急結材を
併用したセメントモルタル型やレジン型のカプセル)3
を挿入する。
(3) Fixing material insertion step (FIG. 3) At the bottom of the hole 2 for the lock bolt, a fixing material (for example, a cement mortar type or resin type capsule that also uses a quick-setting material) 3
Insert.

【0011】(4) ロックボルト及びロックボルト挿
入用中継ロッド挿入工程(図4) ロックボルト用孔2に、ロックボルト4及び複数(最終
的には図5に示すように3本)のロックボルト挿入用中
継ロッド5を相互にねじ部で継ぎ足し、削孔機1で回転
しながら挿入する。なお、ロッド5の表面には、定着材
3の付着を防止するコーティングが施されている。
(4) Inserting the lock bolt and the relay rod for inserting the lock bolt (FIG. 4) In the lock bolt hole 2, the lock bolt 4 and a plurality of lock bolts (finally three as shown in FIG. 5) are inserted. The relay rods 5 for insertion are reciprocally connected to each other by a threaded portion, and are inserted while rotating with the hole drilling machine 1. The surface of the rod 5 is coated to prevent the fixing material 3 from adhering thereto.

【0012】(5) 定着材混合攪拌工程(図5) ロックボルト4に回転を与えながら押し込むことによ
り、定着材3を混合攪拌し、ロックボルト4と地山間を
全面接着させる。
(5) Fixing Material Mixing and Stirring Step (FIG. 5) The fixing material 3 is mixed and stirred by pushing the lock bolt 4 while rotating it, and the lock bolt 4 and the ground are bonded together.

【0013】(6) ロックボルト挿入用中継ロッド分
離工程(図6) ロックボルト挿入用中継ロッド5を逆回転し、ロックボ
ルト4から分離する。この時、ロックボルトとロックボ
ルト挿入用中継ロッドとのねじ径は他のねじ径より小さ
く、緩めトルクが小さくなるように作られているので、
削孔機でロックボルト挿入用中継ロッドを逆回転させる
と、まずロックボルトとロックボルト挿入用中継ロッド
間のねじ部が先に分離する。
(6) Step of separating relay rod for inserting lock bolt (FIG. 6) The relay rod 5 for inserting lock bolt is reversely rotated and separated from the lock bolt 4. At this time, the screw diameter of the lock bolt and the relay rod for inserting the lock bolt is smaller than the other screw diameters, and the loosening torque is made smaller.
When the relay rod for inserting the lock bolt is rotated in the reverse direction with the drilling machine, first, the screw portion between the lock bolt and the relay rod for inserting the lock bolt is separated first.

【0014】(7) ロックボルト挿入用中継ロッド回
収工程(図7) ロックボルト挿入用中継ロッド5をパイロットトンネル
B内に逐次引き戻し、ねじ部を外して回収する。
(7) Collection Step of Relay Rod for Inserting Lock Bolt (FIG. 7) The relay rod 5 for insertion of the lock bolt is sequentially pulled back into the pilot tunnel B, and the screw portion is removed to collect.

【0015】(8) ロックボルトによる縫地工程(図
8) (2)ロックボルト用孔削孔工程から(7)ロックボル
ト挿入用中継ロッド回収工程までを繰り返し、予定掘削
断面Aの外側の周辺地山Cを、複数のロックボルト4で
縫地する。
(8) Sewing process using lock bolts (FIG. 8) (2) Drilling process for rock bolts to (7) Collecting process of relay rods for inserting lock bolts are repeated until the periphery of the planned excavation section A The ground C is sewn with a plurality of lock bolts 4.

【0016】(9) 緩め発破工程(図9) (8)ロックボルトによる縫地工程で生じた緩め発破用
孔Dにダイナマイト6、電気雷管7、込物8、母線9を
設置し、緩め発破を行う。図9では説明上、1孔のみを
図示しているが地山の地質に応じて、ダイナマイト6の
装薬量及び孔Dの数を決定する。
(9) Loose blasting process (FIG. 9) (8) Install dynamite 6, electric detonator 7, insert 8, busbar 9 in the loosing and blasting hole D created in the sewing process with the lock bolt, and loosen and blast I do. Although only one hole is shown in FIG. 9 for the sake of explanation, the amount of dynamite 6 to be charged and the number of holes D are determined according to the geology of the natural ground.

【0017】(10) 排土設備設置工程(図10) パイロットトンネルB内に、掘削土搬出用の排土設備、
例えばベルトコンベア10を設置する。
(10) Excavation equipment installation process (Fig. 10) In the pilot tunnel B, an excavation equipment for excavating soil,
For example, the belt conveyor 10 is installed.

【0018】(11) 上半部掘削工程(図11) 掘削予定断面Aの上半部A1を、大型ショベル11で掘
削し、掘削土を、例えばベルトコンベア10でトンネル
外に排土する。
(11) Upper half excavation process (FIG. 11) The upper half A1 of the planned excavation section A is excavated by the large excavator 11 and excavated soil is discharged outside the tunnel by the belt conveyor 10, for example.

【0019】(12) コンクリート吹付工程(図1
2) 上半部A1の内周壁に、コンクリート吹付機12により
掘削面の風化防止及び天端の崩落や肌落ち防止用のコン
クリート13を吹付ける。
(12) Concrete spraying process (see FIG. 1)
2) The concrete spraying machine 12 sprays concrete 13 for preventing weathering of the excavated surface and for the collapse of the top and the skin from falling onto the inner peripheral wall of the upper half A1.

【0020】(13) 下半部掘削工程(図13) 掘削予定断面Aの下半部A2を、大型ショベル11で掘
削したのち、例えばベルトコンベア10等のパイロット
トンネルB内の設備を撤去する。
(13) Lower Half Excavation Step (FIG. 13) After excavating the lower half A2 of the planned excavation section A with the large excavator 11, the equipment in the pilot tunnel B such as the belt conveyor 10 is removed.

【0021】[0021]

【発明の効果】以上説明したように本発明によれば、中
硬岩の地山でも緩め発破により掘削が容易となり、その
後の掘削、排土及びコンクリート吹付けを同時に並行し
て作業する事が出来る。したがって、安全性及び生産性
を向上し、コストダウンを図る事が出来る。
As described above, according to the present invention, excavation can be facilitated by loosening and blasting even medium-sized rocks, and subsequent excavation, earth removal and concrete spraying can be performed simultaneously in parallel. I can. Therefore, it is possible to improve safety and productivity and reduce costs.

【図面の簡単な説明】[Brief description of drawings]

【図1】パイロットトンネル構築工程を説明する断面
図。
FIG. 1 is a sectional view illustrating a pilot tunnel construction step.

【図2】ロックボルト用孔削孔工程を説明する断面図。FIG. 2 is a cross-sectional view illustrating a rock bolt hole drilling process.

【図3】定着材挿入工程を説明する断面図。FIG. 3 is a sectional view illustrating a fixing material insertion step.

【図4】ロックボルト及びロックボルト挿入用中継ロッ
ド挿入工程を説明する断面図。
FIG. 4 is a cross-sectional view illustrating a lock bolt and a relay rod insertion step for inserting the lock bolt.

【図5】定着材混合攪拌工程を説明する断面図。FIG. 5 is a sectional view illustrating a fixing material mixing and stirring step.

【図6】ロックボルト挿入用中継ロッド分離工程を説明
する断面図。
FIG. 6 is a cross-sectional view illustrating a relay rod separating step for inserting a lock bolt.

【図7】ロックボルト挿入用中継ロッド回収工程を説明
する断面図。
FIG. 7 is a cross-sectional view illustrating a relay rod insertion step for inserting a lock bolt.

【図8】ロックボルトによる縫地工程を説明する断面
図。
FIG. 8 is a cross-sectional view illustrating a sewing process using lock bolts.

【図9】緩め発破工程を説明する断面図。FIG. 9 is a sectional view illustrating a loosening and blasting step.

【図10】排土設備設置工程を説明する断面図。FIG. 10 is a cross-sectional view illustrating an earth removal facility installation process.

【図11】上半部掘削工程を説明する断面図。FIG. 11 is a sectional view illustrating an upper half excavation process.

【図12】コンクリート吹付け工程を説明する断面図。FIG. 12 is a sectional view illustrating a concrete spraying step.

【図13】下半部掘削工程を説明する断面図。FIG. 13 is a cross-sectional view illustrating a lower half excavation process.

【符号の説明】[Explanation of symbols]

A・・・掘削予定断面 A1・・・上半部 A2・・・下半部 B・・・パイロットトンネル C・・・周辺地山 D・・・緩め発破用孔 1・・・削孔機 2・・・ロックボルト用孔 3・・・定着材 4・・・ロックボルト 5・・・・ロックボルト挿入用中継ロッド 6・・・ダイナマイト 7・・・電気雷管 8・・・込物 9・・・母線 10・・・ベルトコンベアなどの排土設備 11・・・大型ショベル 12・・・コンクリート吹付機 13・・・吹付けコンクリート A ... Planned excavation section A1 ... Upper half A2 ... Lower half B ... Pilot tunnel C ... Surrounding ground D ... Loose blast hole 1 ... Drilling machine 2・ ・ ・ Lock bolt hole 3 ・ ・ ・ Fixing material 4 ・ ・ ・ Lock bolt 5 ・ ・ ・ ・ Lock bolt insertion relay rod 6 ・ ・ ・ Dynamite 7 ・ ・ ・ Electric detonator 8 ・ ・ ・ Insert 9・ Bus 10 ・ ・ ・ Exhaust equipment such as belt conveyor 11 ・ ・ ・ Large excavator 12 ・ ・ ・ Concrete spraying machine 13 ・ ・ ・ Shot concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 掘削予定断面の下半部にパイロットトン
ネルを構築するパイロットトンネル構築工程と、該パイ
ロットトンネルから予定掘削断面の奥へ掘削巾の所定割
合の深さまでロックボルト用孔を削孔するロックボルト
用孔削孔工程と、ロックボルト用孔の孔尻に定着材を挿
入する定着材挿入工程と、ロックボルト用孔にロックボ
ルト及びロックボルト挿入用中継ロッドをねじ部で継ぎ
足し回転しながら挿入するロックボルト及びロックボル
ト挿入用中継ロッド挿入工程と、ロックボルトに回転を
与えながら押し込む事により孔尻の定着材を混合攪拌し
てロックボルトと地山間を全面接着させる定着材混合攪
拌工程と、ロックボルト挿入用中継ロッドを逆回しして
ロックボルト挿入用中継ロッドをロックボルトから分離
するロックボルト挿入用中継ロッド分離工程と、ロック
ボルト挿入用中継ロッドをパイロットトンネル内に引き
戻し、ねじ部を外して回収するロックボルト挿入用中継
ロッド回収工程と、前記ロックボルト用孔削孔工程から
ロックボルト挿入用中継ロッド回収工程までを繰り返し
て予定掘削断面外の周辺地山を複数のロックボルトで縫
地するロックボルトによる縫地工程と、縫地工程で残っ
た孔を利用して掘削を容易にするための緩め発破工程
と、パイロットトンネル内に排土設備を設置する排土設
備設置工程と、掘削予定断面の上半部を掘削し、掘削土
は排土設備で排土する上半部掘削工程と、上半部掘削面
にコンクリートを吹き付けるコンクリート吹付工程と、
大断面トンネルの下半部を掘削して掘削土を排土する下
半部掘削工程とを含む事を特徴とする先行ロックボルト
施工及び緩め発破による大断面トンネルの掘削方法。
1. A pilot tunnel construction step of constructing a pilot tunnel in the lower half of a planned excavation section, and drilling a rock bolt hole from the pilot tunnel to the depth of the planned excavation section to a depth of a predetermined proportion of the excavation width. Lock bolt hole drilling process, fixing material inserting process to insert fixing material into the hole end of the lock bolt hole, and lock bolt and lock bolt inserting relay rod are added to the screw hole with the screw part while rotating. A lock bolt to be inserted and a relay rod insertion step for inserting the lock bolt, and a fixing material mixing and stirring step of mixing and agitating the fixing material at the hole end by pushing the lock bolt while applying rotation to adhere the entire area between the rock bolt and the ground. , Reversely rotate the relay rod for inserting the lock bolt to separate the relay rod for inserting the lock bolt from the lock bolt. Inserting relay rod, separating the lock bolt inserting relay rod into the pilot tunnel, removing the screw, and collecting the relay rod for inserting the lock bolt, and inserting the lock bolt from the hole for drilling the lock bolt. The relay rod recovery process is repeated to sew the surrounding ground outside the planned excavation cross section with multiple lock bolts, and the drilling process is facilitated using the lock bolt sewing process and the holes remaining in the sewing process. Loosening and blasting process, earth unloading equipment installation process to install earth unloading equipment in the pilot tunnel, excavation of the upper half of the planned excavation section, and excavation soil is excavated by the earth unloading equipment. And a concrete spraying process of spraying concrete onto the upper half excavation surface,
A method for excavating a large-section tunnel by constructing a preceding rock bolt and loosening and blasting, the method comprising: excavating a lower half of the large-section tunnel to remove excavated soil.
JP12494094A 1994-06-07 1994-06-07 Excavation method of large section tunnel by preceding rock bolt construction and loosening blasting Expired - Fee Related JP2723469B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12494094A JP2723469B2 (en) 1994-06-07 1994-06-07 Excavation method of large section tunnel by preceding rock bolt construction and loosening blasting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12494094A JP2723469B2 (en) 1994-06-07 1994-06-07 Excavation method of large section tunnel by preceding rock bolt construction and loosening blasting

Publications (2)

Publication Number Publication Date
JPH07331985A true JPH07331985A (en) 1995-12-19
JP2723469B2 JP2723469B2 (en) 1998-03-09

Family

ID=14897959

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12494094A Expired - Fee Related JP2723469B2 (en) 1994-06-07 1994-06-07 Excavation method of large section tunnel by preceding rock bolt construction and loosening blasting

Country Status (1)

Country Link
JP (1) JP2723469B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011052536A (en) * 2004-11-29 2011-03-17 Seo Dong Hyun Tip supporting tunnel construction method of large cross-section tunnel
JP5845330B1 (en) * 2014-10-23 2016-01-20 鹿島建設株式会社 Geological exploration method
CN107218043A (en) * 2017-08-27 2017-09-29 中铁二十局集团第六工程有限公司 A kind of breaking surrounding rock cavern excavation method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011052536A (en) * 2004-11-29 2011-03-17 Seo Dong Hyun Tip supporting tunnel construction method of large cross-section tunnel
JP5845330B1 (en) * 2014-10-23 2016-01-20 鹿島建設株式会社 Geological exploration method
CN107218043A (en) * 2017-08-27 2017-09-29 中铁二十局集团第六工程有限公司 A kind of breaking surrounding rock cavern excavation method

Also Published As

Publication number Publication date
JP2723469B2 (en) 1998-03-09

Similar Documents

Publication Publication Date Title
JPH08170484A (en) Construction method of large cross section tunnel
EP1217167A2 (en) Multi-purpose anchor bolt assembly
JPH09217594A (en) Timbering method for tunnel
JP2614396B2 (en) Shaft excavation method by pre-boring
JPH07331985A (en) Preceding lock bolt construction and boring method of large section tunnel by means of release blasting
JP4170867B2 (en) Tunnel excavation method
KR20190011887A (en) Method for digging huge tunnel using tnnnel boring mechine
JP2743986B2 (en) Excavation method of large section tunnel by preceding rock bolt construction
KR101333096B1 (en) Steel wire supplying apparatus for assembling segments of shield tunnel, and method using the same
GB2137678A (en) Method and apparatus for pile construction
SU1523675A1 (en) Method of supportting mine workings
JPH09328999A (en) Method for excavating large scale underground cavity
RU2194858C2 (en) Method of combined mining of bedded mineral deposits
RU2132461C1 (en) Method for developing kimberlite pipe in ascending procedure with dry gobbing
JP2000337077A (en) Method for constructing tunnel
JPS63251600A (en) Method of forming underground cavity
JPH0823266B2 (en) Construction method of underground space
JPH06100080B2 (en) Large-section tunnel construction method and ground solidification column construction device
JPH0335467B2 (en)
AU768956B2 (en) Shaft sinking method
RU1786261C (en) Method for mining pillars
RU2042814C1 (en) Method for passing hollows of gas-dynamic phenomena
JP3015868B2 (en) Drilling method and equipment for connecting holes
JPS6124511B2 (en)
JPH09158197A (en) Rock mass excavation method in pneumatic caisson method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees