JPS63251600A - Method of forming underground cavity - Google Patents

Method of forming underground cavity

Info

Publication number
JPS63251600A
JPS63251600A JP62086689A JP8668987A JPS63251600A JP S63251600 A JPS63251600 A JP S63251600A JP 62086689 A JP62086689 A JP 62086689A JP 8668987 A JP8668987 A JP 8668987A JP S63251600 A JPS63251600 A JP S63251600A
Authority
JP
Japan
Prior art keywords
cavity
tunnel
planned
underground
blasting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP62086689A
Other languages
Japanese (ja)
Other versions
JPH0480199B2 (en
Inventor
荒木 秀登
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dowa Holdings Co Ltd
Original Assignee
Dowa Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dowa Mining Co Ltd filed Critical Dowa Mining Co Ltd
Priority to JP62086689A priority Critical patent/JPS63251600A/en
Publication of JPS63251600A publication Critical patent/JPS63251600A/en
Publication of JPH0480199B2 publication Critical patent/JPH0480199B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 この発明は、地下空洞形成法に係り、特に所望の形状を
有する大型空洞を地下岩盤中に開削するに際し、工事中
の保安は勿論、空洞開削後の安定維持に対しても信頼性
のある地下空洞形成法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an underground cavity forming method, and in particular, when excavating a large cavity with a desired shape in underground rock, it is necessary not only for security during construction but also for maintaining stability after excavation of the cavity. Concerning a reliable underground cavity formation method.

地下深部岩盤中に大型空洞を開削し、石油備蓄をはじめ
、放射性廃棄物の処分あるいは保管、エネルギー供給に
年5犬型機械設備などの用に供することが必要となって
きた。
It has become necessary to excavate large cavities deep underground in bedrock and use them to store oil, dispose of or store radioactive waste, and supply energy to mechanical equipment.

もともと地下の深部岩盤中に大型空洞を開削するに当っ
ては、いかに硬い岩盤中であろうとも、必然的に発生す
る強大な地圧を制御しなければならず、工事中の保安及
び空洞開削後の空洞の安定維持については細心の注意と
周到な管理を要する。
Originally, when excavating a large cavity in deep underground bedrock, no matter how hard the rock is, it is necessary to control the strong ground pressure that inevitably occurs, and it is necessary to control security during construction and cavity excavation. Careful attention and careful management are required to maintain the stability of the cavity afterwards.

従来、塊状型金属鉱床における鉱山採掘跡あるいは石灰
石鉱山の坑内グローリーホール採掘跡のよ5に、有価鉱
物の採掘が終了したため、結果的に地下に大型空洞が残
存している例があシ、これらを上記のような目的に利用
しようとする試みがなされてはいるが、これら大型空洞
は地域的に限定される上に空洞形状が採掘形態によって
左右されており、維持保全の点にも難点があって利用さ
れるまでに到っていない。
In the past, there have been examples of large cavities remaining underground as a result of the completion of mining of valuable minerals, such as mining sites in massive metal deposits or underground glory hole mining sites in limestone mines. Attempts have been made to use these large cavities for the above purposes, but these large cavities are limited to certain regions, and the shape of the cavities depends on the type of mining, making maintenance difficult. However, it has not yet been put to use.

問題点を解決するための手段 本発明の目的は、所望の形状を有し、かつ空洞完成後の
維持管理をも充分に配慮した大型空洞を地下に形成する
方法を提供することである。
Means for Solving the Problems An object of the present invention is to provide a method for forming a large cavity underground that has a desired shape and takes into account maintenance and management after the cavity is completed.

本発明者は上記目的を達成すべく研究の結果、地下空洞
開削方式として基本的には鉱山における大型坑内採掘法
として公知の中段採掘法を採用し、空洞予定部の縦断面
において、空洞予定部の周縁に位置して空洞の輪郭を規
定する複数の水平又は略水平の坑道(以下輪郭坑道とい
う)ならびに空洞予定部内に設けられた水平または略水
平の穿孔開削用中段坑道(以下中段坑道という)を開削
し、これら坑道からの穿孔・スムーズブラスティングに
より空洞予定部内の岩盤を起砕、除去することを基本と
する。一方、これら空洞開削工程に先立って、空洞内壁
面近傍を強固に安定させるために、輪郭坑道よりもさら
に外周に設けられた水平又は略水平の外周坑道から空洞
予定部方向にロックボルトを打設するとともに、空洞内
壁面が平滑になるように上記輪郭坑道相互間にプレスプ
リッティング穿孔・発破を行う工程を実施し、かつ、上
記空洞開削工程の進展に伴い、空洞予定部の上方に位置
する外周坑道から空洞内に坑井を通じて起砕した研 ズ
リ などの固形物を装入して固形物が坑井の少なくとも
一部を満たすことによって空洞天盤を支持させる工程を
実施し、その後前記空洞開削工程に移行すれば、上記本
発明の目的が達成できることを見出し、本発明に到った
As a result of research to achieve the above object, the present inventor adopted the middle stage mining method, which is basically known as a large-scale underground mining method in mines, as an underground cavity excavation method. A plurality of horizontal or nearly horizontal tunnels located on the periphery of the cavity to define the outline of the cavity (hereinafter referred to as contour tunnels), and a horizontal or nearly horizontal intermediate tunnel for drilling provided within the planned cavity area (hereinafter referred to as middle tunnel) The basic idea is to excavate the tunnels and crush and remove the rock within the planned cavity area by drilling and smooth blasting from these tunnels. On the other hand, prior to these cavity excavation processes, in order to strongly stabilize the vicinity of the inner wall surface of the cavity, rock bolts were driven from the horizontal or nearly horizontal peripheral tunnel provided further outside the contour tunnel in the direction of the planned cavity area. At the same time, a process of pre-splitting drilling and blasting is carried out between the contour tunnels so that the inner wall surface of the cavity is smooth, and as the cavity excavation process progresses, the outer periphery located above the planned cavity area is A process is carried out in which a solid material such as crushed grinding sludge is charged into the cavity from the tunnel through the well, and the solid material fills at least a part of the well to support the cavity ceiling, and then the cavity top plate is supported. The inventors have discovered that the above object of the present invention can be achieved by proceeding to the process, and have arrived at the present invention.

したがって本発明の方法は、 中段採掘法によって地下に空洞を形成するに際し、 (1)空洞予定部周縁の外側に開削された複数の外周坑
道から空洞予定部方向にロックボルトを打設するロック
ボルト工程、 (2)空洞予定部周縁の複数箇所に外周坑道に並行に開
削された空洞輪郭規定坑道からプレスプリッティング穿
孔及び発破を行うプレスプリッティング工程、 (3)空洞予定部内の複数箇所に空洞輪郭規定坑道に並
行して開削された穿孔中段坑道のうち、プレスプリッテ
ィングの終了した部分において、下方の穿孔中段坑道か
ら穿孔・発破して順次空洞を形成するスムーズプラステ
ィング工程、および (4)空洞予定部の上方に位置する外周坑道から空洞内
に連通されfc草井を通じて固形物を空洞内に装入し、
装入さ′た固形物が坑井の少なくとも一部を満た° 、
とにより空洞天盤を支持させる装入工程、 の各工程からなることを特徴とする0 以下に本発明の詳細な説明する。
Therefore, in the method of the present invention, when forming a cavity underground by the middle stage mining method, (1) rock bolts are driven in the direction of the planned cavity from a plurality of peripheral tunnels excavated outside the periphery of the planned cavity; (2) A pre-splitting process in which pre-splitting drilling and blasting is carried out from a cavity contour defined tunnel drilled at multiple locations around the circumference of the planned cavity in parallel to the outer tunnel; (3) Cavity contour defined at multiple locations within the planned cavity. A smooth blasting process in which a cavity is sequentially formed by drilling and blasting from the lower middle-level tunnel in the part where pre-splitting has been completed in a middle-level tunnel drilled in parallel with the tunnel, and (4) a planned cavity area. The solid material is charged into the cavity through an FC well connected to the cavity from a peripheral tunnel located above,
The charged solids fill at least a portion of the wellbore;
A charging step of supporting the hollow top plate by the steps of: 0 The present invention will be described in detail below.

この発明における基本的な空洞開削方式としては、鉱山
における大型坑内採掘法として公知の中段採掘法が採用
される。この方法が他の例えば同じく坑内採掘法である
上向採掘法あるいは下向段欠採掘法に比べると作業者の
稼働する範囲が広大な裸天井から疎外される、つまり裸
天盤の崩落による危険を回避できる点で保安上優れてい
るからである。
As the basic cavity excavation method in this invention, the middle stage mining method, which is known as a large-scale underground mining method in mines, is adopted. Compared to other underground mining methods such as the upward mining method or the downward stepped mining method, this method means that the working area of the worker is isolated from the vast bare ceiling, which means there is a risk of the bare ceiling collapsing. This is because it is superior in terms of security because it can avoid this.

本発明の方法によp形成される地下空洞の形状は前述の
ような使用目的に応じて、例えば第5図に示すように、
トンネル形状(A図)またはこれを環状に結んだ形状(
B図)など自由に選定できるが、盤圧制御上から有利な
形状として、空洞の輪郭を卵形ないし長円形に近似させ
るために空洞の断面形状を多角形とするのが好ましい。
The shape of the underground cavity formed by the method of the present invention depends on the purpose of use as described above, for example, as shown in FIG.
Tunnel shape (Figure A) or a ring-shaped shape (
Although the shape can be freely selected from the shape shown in Fig. B), it is preferable to make the cross-sectional shape of the cavity polygonal in order to approximate the outline of the cavity to an oval or ellipse, as it is an advantageous shape from the viewpoint of controlling the plate pressure.

第1図は本発明における好ましい空洞断面形状の1例を
示したものであり、空洞断面である多角形の頂点位置に
輪郭坑道、及び空洞予定部内部に中段坑道が配列される
。これらの坑道から斜め下向きあるいは直下等に扇状穿
孔を行い、中段発破によって空洞が形成されて行くこと
になる。
FIG. 1 shows an example of a preferable cross-sectional shape of a cavity according to the present invention, in which a contour tunnel is arranged at the apex position of a polygonal shape that is the cavity cross section, and a middle tunnel is arranged inside the planned cavity portion. Fan-shaped holes are made diagonally downward or directly below these tunnels, and cavities are formed by middle stage blasting.

空洞仕上り内壁面が大型発破によシ損傷し更には常時発
生する深部岩盤特有の強大な地圧によシ加速度的に損壊
することを防止するために、上記多角形の頂点に位置す
る輪郭坑道からそれぞれ隣接する輪郭坑道に向けてプレ
スプリッティングを実施する。
In order to prevent the finished inner walls of the cavity from being damaged by large-scale blasting and furthermore, from being damaged at an accelerating rate due to the strong ground pressure unique to deep rock that occurs constantly, a contoured tunnel is located at the apex of the polygon. Pre-splitting will be carried out from each to the adjacent contour tunnel.

第2図は第1図に示す断面をもつ空洞予定・部の斜視図
であり、空洞の輪郭に沿って並行する多数のプレスプリ
ッティング用穿孔列が点線で示されている。
FIG. 2 is a perspective view of the cavity section having the cross-section shown in FIG. 1, with a number of parallel pre-splitting rows of perforations along the contour of the cavity shown in dotted lines.

このプレスプリッティングを施しておくことにより空洞
内壁面は平滑に仕上げることができ、しかも中段坑道か
らの大型発破の影響をうけて亀裂が空洞壁の外側に発生
、進展することを防止する。
By applying this pre-splitting, the inner wall surface of the cavity can be finished smoothly, and it also prevents cracks from forming and propagating on the outside of the cavity wall due to the influence of large-scale blasting from the middle tunnel.

さらには、上記大型発破を実施する以前に、空洞予定部
周縁の外側の岩盤中に空洞の長軸に略並行に開削した複
数の外周坑道からそれぞれ空洞予定部に向けてロックボ
ルトCケ・−プルボルトその他岩盤中に打設するものを
含む)を打設して空洞壁面となる部位を固定しておく必
要がある。
Furthermore, before carrying out the above-mentioned large-scale blasting, rock bolts C-- were drilled into the rock outside the periphery of the planned cavity from a plurality of outer tunnels that were cut approximately parallel to the long axis of the cavity. It is necessary to fix the part that will become the cavity wall by driving pull bolts (including pull bolts and other bolts driven into the rock).

ただし、空洞予定部周縁の外側の岩盤が比較的強固な場
合には、ロックボルトの打設は必要に応じ、大型発破実
施後にしてもよい。
However, if the rock mass outside the periphery of the planned cavity is relatively strong, rock bolts may be installed after large-scale blasting if necessary.

空洞予定部内で起砕した  ズリ は同予定部下方に開
削しfcjIJ抜坑道よシ全部引抜けば形状としての空
洞は準備できたことになるが、地下深部岩盤中のことで
あり、不用意にズリを抜きとることは空洞の自立性に悪
影響を及ぼし、空洞開削進行中であっても作業継続不能
の事態をもたらすおそれが常に存在する。起砕したズリ
はある程度抜取らないと中段発破継続のための必要発破
自由面が確保できぬこともあり、最小限の童は抜き取ら
ねばならないが、そのため起砕ズILi:面が空洞天盤
から離隔するので、盤圧配分が定まらぬ開削期間中ある
いは開削完了後しばらくの期間中、不意の天盤崩落が発
生し、深部であるが故に大規模崩落な一挙に誘起させる
恐れがある。
If the debris that was crushed within the planned cavity area is excavated below the planned area and pulled out completely through the FCJIJ tunnel, the hollow shape will be ready, but since it is deep underground in the bedrock, carelessly Removing the sludge will have a negative effect on the self-sustainability of the cavity, and there is always a risk that work will not be able to continue even while excavation of the cavity is in progress. Unless a certain amount of crushed debris is removed, it may not be possible to secure the necessary blasting free surface for continuing middle-stage blasting, and the minimum amount of debris must be removed. Because they are separated, unexpected collapse of the roof may occur during the excavation period when the distribution of plate pressure is not determined or for some time after the completion of excavation, and because it is deep, there is a risk that a large-scale collapse may occur all at once.

そこで本発明においては、空洞上部に人為的にズリを投
入して要所要所にて空洞天盤を起砕ズリによって支持さ
せる。すなわち、空洞頂部外周に位置する前記外周坑道
(ロックボルト穿孔坑道)からy’を投入坑井を開削し
割を投入する。
Therefore, in the present invention, scraps are artificially introduced into the upper part of the cavity, and the hollow ceiling plate is supported by the crushed scraps at key points. That is, from the outer tunnel (rock bolt drilling tunnel) located on the outer periphery of the top of the cavity, a well is excavated to introduce y', and the y' is injected into the well.

ズリはズリ抜坑道により地表に搬出されるものの一部を
使用するほか、別途地表から搬入するもの、あるいは暫
定的強度をもたせるためにセメントペースト、モルタル
、コンクリートなどの固化性流動体でもよい。
In addition to using a portion of the waste that is carried to the surface through the waste extraction tunnel, it is also possible to use material that is separately brought in from the surface, or solidifying fluids such as cement paste, mortar, and concrete to provide temporary strength.

空洞開削中は肉眼的監視のほか、盤圧計、伸長計、AE
 (aco%atic amiaaion)カウントな
どの計器による盤圧監視を続行し、これらにより空洞周
辺の盤圧状態を解析し、空洞内のズリを適宜引抜き、盤
圧の再配分が円滑に安定して行われるように制御してい
くことが必要である。
During cavity drilling, in addition to visual monitoring, plate pressure gauges, extensometers, and AE
(aco%atic amiaaion) We will continue to monitor the plate pressure using instruments such as counters, analyze the plate pressure state around the cavity, pull out gaps in the cavity as appropriate, and redistribute the plate pressure smoothly and stably. It is necessary to control the situation so that the

なお、これらの計器類による監視体制は空洞完成後の維
持管理に対しても極めて重要な役割をもつことは言うま
でもない。
It goes without saying that the monitoring system using these instruments will also play an extremely important role in maintenance and management after the cavity is completed.

次に、本発明を実施例によって更に具体的に説明する。Next, the present invention will be explained in more detail with reference to Examples.

実施例 第1図に示すような略卵形に近い多角形断面を有する空
洞予定部周縁の外側に空洞予定部の長軸に並行する複数
の外周坑道3を開削し、空洞壁面となる箇所全般に亘っ
て壁面となる部位を保護固定するために、これらの外周
坑道群からロックボルト3αを図示の如く打設施工する
Example A plurality of outer tunnels 3 parallel to the long axis of the planned cavity are excavated outside the periphery of the planned cavity having a polygonal cross section close to an oval shape as shown in FIG. In order to protect and fix the parts that will become the wall surfaces over the period, rock bolts 3α are driven from these outer tunnel groups as shown in the figure.

次いで、空洞頂部外周を規定する多角形の頂点に位置す
る各輪郭坑道1α、1b、1c・・・・・・を開削する
とともに、空洞予定部内部にも複数の中段坑道6を開削
し、一方それぞれの輪郭坑道から隣接する輪郭坑道に向
ってプレスプリッティング穿孔2を実施する。
Next, each contour tunnel 1α, 1b, 1c, . Pre-splitting drilling 2 is carried out from each contour tunnel to the adjacent contour tunnel.

以上により、中段坑道及び輪郭坑道からの穿孔・発破に
よる空洞予定部の岩盤起砕の準備が完了したことになる
As a result of the above, preparations for rock crushing in the planned hollow area by drilling and blasting from the middle level tunnel and contour tunnel have been completed.

第3図は空洞予定部の長軸方向の断面を示したもので1
、図面左方の地山中に設けられた外周坑道3ならびにロ
ックボルト3cLが第1図と同様に示されており、中段
坑道6からの穿孔・発破により岩盤が起硬されて空洞が
順次形成されるに従い、谷中段坑道も図面右方に後退す
ることとなる。
Figure 3 shows a cross section of the planned cavity in the longitudinal direction.
, the outer tunnel 3 and rock bolts 3cL installed in the ground on the left side of the drawing are shown in the same way as in FIG. Accordingly, the valley middle tunnel will also retreat to the right in the drawing.

起硬ズリ7は下部ズリ抜坑道4から搬出される〇起硬ズ
リの搬出により起硬ズリ上面が空洞天盤から離隔するこ
とを防止するために、空洞上方の外周坑道3からズリ投
入坑井群5aを経てズリあるいは必要によシセメントコ
ンクリートを投入し、空洞天盤を起欲IJによって支持
させる。
The hardened waste 7 is carried out from the lower waste extraction tunnel 4. In order to prevent the upper surface of the hardened waste from separating from the cavity ceiling due to the removal of the hardened waste, a waste injection well is carried out from the outer circumferential tunnel 3 above the cavity. Cement concrete is poured into the gap or as necessary through group 5a, and the hollow ceiling is supported by IJ.

第4図は上記ズ1改入方法を示したもので一ズリ投入坑
井5Gから投入された上記ズリなどの固形物8が起硬ズ
リ7上に堆積されている。
FIG. 4 shows the method for reinserting the sludge 1, in which solid matter 8 such as the sludge introduced from the sludge injection well 5G is deposited on the hardened sludge 7.

発明の効果 本発明の方法によれば、空洞内壁面の保護安定、特に空
洞天盤の崩落防止対策が充分配慮されているので、空洞
開削工事中は勿論、空洞完成後の維持管理についても信
頼性のある大型地下空洞を所望の規模、形状に従って形
成することが可能である0
Effects of the Invention According to the method of the present invention, sufficient consideration has been given to the protection and stability of the inner wall surface of the cavity, and in particular to the prevention of collapse of the cavity ceiling, so that it is reliable not only during the excavation work of the cavity but also for maintenance and management after the completion of the cavity. It is possible to form a large-scale underground cavity according to the desired scale and shape.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の方法により形成される地下空洞縦断面
の1例を示す模式図、第2図は、第1図に示す断面をも
つ空洞予定部におけるプレスプリッティング穿孔列を示
す斜視図である。 第3図は本発明の方法で形成される地下空洞の横断面の
1例を示す模式図、第4図は空洞予定部の上方に位置す
る外周坑道から坑井を通して固形物を搬入し空洞天盤を
支持する工程を示す模式断面図である。 第5図は、本発明の方法で形成される地下空洞としての
トンネル型(A図)あるいはこれを環状に結んだ例(B
図)を示す鳥諏図である。 1a、1b、1G・・・:空洞輪郭規定坑道2    
     :プレスプリツテイング用穿孔3     
   :外周坑道 3G      −ロックボルト 4         :ズリ引抜坑道 5α、5b・・・  :固形物投入坑井6      
 :中段坑道 7       :起硬ズリ 8       :固形物
FIG. 1 is a schematic diagram showing an example of a longitudinal section of an underground cavity formed by the method of the present invention, and FIG. 2 is a perspective view showing a pre-splitting perforation row in a planned cavity section having the cross section shown in FIG. 1. be. Fig. 3 is a schematic diagram showing an example of a cross section of an underground cavity formed by the method of the present invention, and Fig. 4 is a schematic diagram showing an example of a cross section of an underground cavity formed by the method of the present invention. FIG. 3 is a schematic cross-sectional view showing a process of supporting the board. Figure 5 shows a tunnel type (Figure A) as an underground cavity formed by the method of the present invention or an example of a ring-shaped underground cavity (Figure B).
It is a bird's eye diagram showing the figure. 1a, 1b, 1G...: Cavity contour defined tunnel 2
:Drilling hole 3 for press plyzing
: Peripheral tunnel 3G - Rock bolt 4 : Sludge extraction tunnel 5α, 5b... : Solid material input well 6
: Middle tunnel 7 : Hardening waste 8 : Solid matter

Claims (1)

【特許請求の範囲】 中段採掘法によつて地下に空洞を形成するに際し、 (1)空洞予定部周縁の外側に開削された複数の外周坑
道から空洞予定部方向にロックボルトを打設するロック
ボルト工程、 (2)空洞予定部周縁の複数箇所に外周坑道に並行に開
削された空洞輪郭規定坑道からプレスプリツテイング穿
孔及び発破を行うプレスプリツテイング工程、 (3)空洞予定部内の複数箇所に空洞輪郭規定坑道に並
行して開削された穿孔中段坑道のうち、プレスプリツテ
イングの終了した部分において、下方の穿孔中段坑道か
ら穿孔・発破して順次空洞を形成するスムーズプラステ
イング工程、および (4)空洞予定部の上方に位置する外周坑道から空洞内
に連通された坑井を通じて固形物を空洞内に装入し、装
入された固形物が坑井の少なくとも一部を満たすことに
より空洞天盤を支持させる装入工程、 の各工程からなることを特徴とする、地下空洞形成法。
[Claims] When forming a cavity underground by the middle stage mining method, (1) a lock in which rock bolts are driven in the direction of the planned cavity from a plurality of peripheral tunnels cut outside the periphery of the planned cavity; bolting process, (2) pre-spritting process in which pre-split drilling and blasting are performed from a cavity contour defined tunnel drilled parallel to the outer tunnel at multiple locations on the periphery of the planned hollow area, (3) multiple locations within the planned hollow area. A smooth plasting process in which holes are sequentially formed by drilling and blasting from the lower boring middle tunnel in the part where pre-spritting has been completed in the hollow middle tunnel drilled parallel to the hollow contour defined tunnel; and (4) charging solids into the cavity through a well connected to the cavity from a peripheral tunnel located above the planned cavity, and filling at least a portion of the well with the charged solids. A method for forming an underground cavity, characterized by comprising the steps of: a charging step of supporting a cavity top plate;
JP62086689A 1987-04-08 1987-04-08 Method of forming underground cavity Granted JPS63251600A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62086689A JPS63251600A (en) 1987-04-08 1987-04-08 Method of forming underground cavity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62086689A JPS63251600A (en) 1987-04-08 1987-04-08 Method of forming underground cavity

Publications (2)

Publication Number Publication Date
JPS63251600A true JPS63251600A (en) 1988-10-19
JPH0480199B2 JPH0480199B2 (en) 1992-12-17

Family

ID=13893948

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62086689A Granted JPS63251600A (en) 1987-04-08 1987-04-08 Method of forming underground cavity

Country Status (1)

Country Link
JP (1) JPS63251600A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5869232B2 (en) * 2011-04-27 2016-02-24 大成建設株式会社 Excavation soil transport system

Also Published As

Publication number Publication date
JPH0480199B2 (en) 1992-12-17

Similar Documents

Publication Publication Date Title
CN110454172B (en) Tunnel cross tunnel and main tunnel intersection construction method and bench blasting method
CN111997639B (en) Method for getting rid of trouble and reinforcing and improving geology of TBM construction tunnel bad geology section card machine
EP0590760B1 (en) Undercut excavation method
JPS63251600A (en) Method of forming underground cavity
JP3750043B2 (en) Large section underground hollow quarry
RU2059810C1 (en) Method for mining of steeply dipping mineral deposits
RU2095571C1 (en) Method for hydraulic mining of ore bodies layer-by-layer
CN206280089U (en) Large-inclination-angle coal bed big gun is adopted and turns fully mechanized mining open-off cut supporting facility
RU2059073C1 (en) Method for development of mineral deposits
RU2099527C1 (en) Method for mining of mineral deposits
JP2723469B2 (en) Excavation method of large section tunnel by preceding rock bolt construction and loosening blasting
JPWO2020193960A5 (en)
RU2132461C1 (en) Method for developing kimberlite pipe in ascending procedure with dry gobbing
RU1786261C (en) Method for mining pillars
CN106761749A (en) Large-inclination-angle coal bed breaking roof big gun is adopted and turns fully mechanized mining
RU2081324C1 (en) Method for hydraulic bore-hole mining of minerals
SU750072A1 (en) Method of working sloping ore deposits
JP2743986B2 (en) Excavation method of large section tunnel by preceding rock bolt construction
JPS5894598A (en) Level drilling method and drill guide used therein
RU1789737C (en) Method for formation of vertical working
JPS6220358B2 (en)
KR20230025512A (en) Non-vibration rock excavating method that can shorten the construction period
SU1765401A1 (en) Rock pressure control method
CN113565513A (en) Upper and lower step reserved core soil excavation method for tunnel excavation
SU1631174A1 (en) Method of mining thick mineral deposits