SU1523675A1 - Method of supportting mine workings - Google Patents

Method of supportting mine workings Download PDF

Info

Publication number
SU1523675A1
SU1523675A1 SU874319218A SU4319218A SU1523675A1 SU 1523675 A1 SU1523675 A1 SU 1523675A1 SU 874319218 A SU874319218 A SU 874319218A SU 4319218 A SU4319218 A SU 4319218A SU 1523675 A1 SU1523675 A1 SU 1523675A1
Authority
SU
USSR - Soviet Union
Prior art keywords
injection
anchors
concrete
installation
rock
Prior art date
Application number
SU874319218A
Other languages
Russian (ru)
Inventor
Юлий Зиновьевич Заславский
Владимир Викторович Ковшов
Эдуард Константинович Фролов
Михаил Анатольевич Шатохин
Original Assignee
Макеевский Инженерно-Строительный Институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Макеевский Инженерно-Строительный Институт filed Critical Макеевский Инженерно-Строительный Институт
Priority to SU874319218A priority Critical patent/SU1523675A1/en
Application granted granted Critical
Publication of SU1523675A1 publication Critical patent/SU1523675A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

Изобретение относитс  к горнодобывающей промышленности, может быть использовано при строительстве подземных сооружений и позвол ет повысить работоспособность и расширить область применени  породобетонных конструкций крепи. В забое устанаваливаетс  временна  крепь с металлической сетчатой зат жкой. Затем бур т шпуры и производ т нагнетание в жущего раствора за зоной максимально разрыхленных пород, из которых формируют податливый слой. После нагнетани  в шпуры устанавливают анкера и закрепл ют ими сетку, на которую нанос т набрызгбетон. Временную крепь снимают, а контур выработки сглаживают поворотным набрызгом. 1 з.п. ф-лы, 5 ил.The invention relates to the mining industry, can be used in the construction of underground structures and allows to increase the efficiency and expand the field of application of rock-concrete lining structures. A temporary lining with a metal mesh tightening is installed in the bottom. Then the hole is drilled and the injection is carried out in the slurry solution beyond the zone of the maximally loosened rocks from which the malleable layer is formed. After injection, anchors are installed in the bore-holes and they secure the grid to which they apply sprayed concrete. Temporary lining is removed, and the contour of the mine is smoothed by swiveling spray. 1 hp f-ly, 5 ill.

Description

Изобретение относитс  к горной промышленности , в частности к способам креплени  горных выработок, и может быть использовано при строительстве подземных сооружений.The invention relates to the mining industry, in particular to methods of securing mine workings, and can be used in the construction of underground structures.

Целью изобретени   вл етс  повышение работоспособности и расширение области применени  породобетонных конструкций крепи.The aim of the invention is to improve the performance and expand the field of application of rock-concrete lining structures.

На фиг 1 изображена горна  выработка , продольный разрез (с последовательностью возведени  крепи); на фиг. 2 - сечение А-А на фиг. 1; на фиг, 3 - сечение Б-Б на фиг. 1; на фиг. 4 - сечение В-В на фиг. 1; на фиг. 5 - сечение Г-Г на фиг. 1.Fig. 1 depicts hearth making, a longitudinal section (with a succession of erection of lining); in fig. 2 is a section A-A in FIG. one; FIG. 3 is a section BB in FIG. one; in fig. 4 shows a section B-B in FIG. one; in fig. 5 is a cross-section of the FIG. one.

Способ креплени  горных выработок реализуетс  следующим образом.The method of securing mine workings is as follows.

По мере проходки в забое выработки устанавливают временную крепь 1 с металлической сетчатой зат жкой 2,As sinking in the mine working place, temporary support 1 with metal mesh tightening 2 is installed,

котора  расклиниваетс  и забучиваетс  согласно типовым паспортам. С отставанием от забо  после срабатывани  временной крепи в податливом режиме по периметр У выработки бур т шпуры 3 дл  нагнетани  в жущего раствора . Длина шпуров 3 определ етс - размером зоны разрушенных пород, образовавшейс  к этому времени, .Дл  нагнетани  используют инъектор 4 многоразового использовани , в конструкции которого предусмотрена возможность герметизации любого заданного отрезка шпура 3 (например, с помощью разжимных резиновых тампонов). Первоначально инъектор 4 устанавливают в ДО тй части шпура 3 и нагнетание ве- дут в режиме заданного давлени . При насыщении массива в обрабатываемой зоне (о чем св1адетельствует повышение давлени  на манометре нагнетагаwhich is wedged and forgotten according to the type sheets. Lagging behind the bottom after the time support is activated in a compliant mode around the perimeter. The drill hole 3 is being drilled to generate a bladder solution. The length of the holes 3 is determined by the size of the zone of destroyed rocks formed by this time. For injection, a reusable injector 4 is used, the design of which provides for the possibility of sealing any given piece of hole 3 (for example, using compression rubber tampons). Initially, the injector 4 is installed in the borehole part of the hole 3 and the injection is carried out in the predetermined pressure mode. When the array is saturated in the treated zone (as evidenced by the increase in pressure on the pressure gauge

юYu

соwith

« СП"JV

тельного оборудовани  нагнетание прекращают, инъектор 4 перемещают на следующий участок шпура 3,и процесс повтор етс . Последн   перестановка инъектора 4 должна соответствовать границе зоны максимально разрыхленных пород 5 приконтурного массива. При установке герметизирующего устройства инъектор 4 в пределах зоны максимально разрыхленных пород 5 приконтурного массива наблюдаетс  свободное изливание скрепл ющего раствора в полость выработки без подъема давлени  на манометре нагнетательного оборудовани . Это св зано с тем, что породы в пределах этой зоны разбиты сетью сообщающихс  трещин, имеющих выход в полость выработки. Таким образом, положение границы зоны максимально разрыхленных пород 5 приконтурного массива определ етс  при ведении работ по нагнетанию в жущего раствора . В результате выполнени  работ по нагнетанию в жущего раствора вокруг выработки образуютс  оболочка из упрочненных пород 6 и податлива  зона 7 из максимально разрыхленных пород 5 приконтурного массива. После выполнени  нагнетани  в жущего раствора инъектор 4 извлекаетс  из шпура 3, и. в этот шпур устанавливают анкер 8, закрепл   его на внешней границеThe injection equipment is stopped, the injector 4 is moved to the next part of the hole 3, and the process is repeated. The last permutation of the injector 4 should correspond to the boundary of the zone of maximally loosened rocks 5 of the marginal array. When installing the sealing device, injector 4 within the zone of maximally loosened rocks 5 of the marginal array, free flow of the fastening solution into the production cavity without pressure is observed on the pressure equipment pressure gauge. This is due to the fact that the rocks within this zone are broken by a network of communicating cracks that have access to the cavity of the mine. Thus, the position of the boundary of the zone of maximally loosened rocks 5 of the marginal massif is determined when conducting work on the injection into the slurry solution. As a result of works on injecting a slurry around the excavation, a shell is formed of reinforced rocks 6 and a zone 7 of the maximally loosened rocks 5 of the marginal mass is malleable. After the injection solution has been pumped, the injector 4 is removed from the hole 3, and. Anchor 8 is installed in this hole, fastened to the outer border

упрочненной зоны 6 и на контуре выработки . При этом металлическа  сетчата  зат жка 2 подшиваетс  к породному контуру. Затем на армированный сетчатой зат жкой породный контур нанос т слой набрызг-бетона 9. После набора прочности набрызг-бетона 9 временна  крепь 1 снимаетс  и контур выработки сглаживаетс  повторным наб- рызгом.hardened zone 6 and on the contour of production. At the same time, the metal mesh clamp 2 is stitched to the breed contour. Then, a rock contour reinforced with a mesh-reinforced mesh is applied a layer of sprayed concrete 9. After the strength of the sprayed concrete 9 has been established, temporary support 1 is removed and the development contour is smoothed by repeated impact.

Claims (2)

1.Способ креплени  горных выработок , включающий установку временной крепи с сетчатой зат жкой, бурение шпуров, нагнетание через них в породу в жущего раствора, установку анкеров, нанесение набрызг-бетона и сн тие временной крепи, отличающи й- с   тем, что, с целью повышени  работоспособности и расширени  области применени  породобетонных конструкций , нагнетание в жущего раствора производ т за зоной максимально разрыхленных пород приконтурного массива , а установку анкеров и нанесение набрызг-бетона выполн ют после нагнетани  в породы в жущего раствора.1. The method of securing the mine workings, including the installation of temporary lining with mesh tightening, drilling holes, forcing through them into the rock in the cement slurry, installation of anchors, spraying concrete and removing temporary lining, which differs from In order to increase the efficiency and expand the field of application of rock-concrete structures, the injection into the cement slurry is carried out beyond the zone of the maximally loosened rocks of the marginal massif, and the installation of anchors and spraying-concrete is carried out the binder solution. 2.Способ по п. 1, отличающийс  тем, что анкеры устанавливают в шпурах дл  нагнетани  в жущего раствора.2. A method according to Claim 1, characterized in that the anchors are mounted in boreholes for injection into the slurry solution. Фиг.11 Фиг. гFIG. g Составитель Л.Березкина Редактор О.Юрковецка  Техред Л.СердюковаCompiled by L. Berezkina Editor O. Yurkovetska Tehred L. Serdyukova Заказ 7015/31Order 7015/31 Тираж 449Circulation 449 ВНИИПИ Государственного комитета по изобретени м и открыти м при ГКНТ СССР 113035, Москва, Ж-35, Раушска  наб., д. 4/5VNIIPI State Committee for Inventions and Discoveries at the State Committee on Science and Technology of the USSR 113035, Moscow, Zh-35, Raushsk nab. 4/5 Производственно-издательский комбинат Патент, г. Ужгород, ул. Гагарина, 101Production and Publishing Combine Patent, Uzhgorod, st. Gagarin, 101 Фие.ЧFi.Ch. Фм.5Fm.5 Корректор Л.ПатайProofreader L. Patay ПодписноеSubscription
SU874319218A 1987-10-26 1987-10-26 Method of supportting mine workings SU1523675A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU874319218A SU1523675A1 (en) 1987-10-26 1987-10-26 Method of supportting mine workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU874319218A SU1523675A1 (en) 1987-10-26 1987-10-26 Method of supportting mine workings

Publications (1)

Publication Number Publication Date
SU1523675A1 true SU1523675A1 (en) 1989-11-23

Family

ID=21332817

Family Applications (1)

Application Number Title Priority Date Filing Date
SU874319218A SU1523675A1 (en) 1987-10-26 1987-10-26 Method of supportting mine workings

Country Status (1)

Country Link
SU (1) SU1523675A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2509893C1 (en) * 2012-07-17 2014-03-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Erection method of earthquake resistant concrete support
RU2520194C1 (en) * 2013-04-29 2014-06-20 Дмитрий Борисович Никишичев Mine working reinforcing method and device for its implementation
RU2805691C1 (en) * 2022-12-12 2023-10-23 федеральное государственное бюджетное образовательное учреждение высшего образования "Санкт-Петербургский горный университет" Method for conducting mining works in development of flat coal beds

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 625043, кл. Е 21 D 11/00, 1976. Авторское свидетельство СССР № 987108, кл Е 21 1) 20/00, 1981. *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2509893C1 (en) * 2012-07-17 2014-03-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Erection method of earthquake resistant concrete support
RU2520194C1 (en) * 2013-04-29 2014-06-20 Дмитрий Борисович Никишичев Mine working reinforcing method and device for its implementation
RU2805691C1 (en) * 2022-12-12 2023-10-23 федеральное государственное бюджетное образовательное учреждение высшего образования "Санкт-Петербургский горный университет" Method for conducting mining works in development of flat coal beds

Similar Documents

Publication Publication Date Title
EP1217167A2 (en) Multi-purpose anchor bolt assembly
JPH09217594A (en) Timbering method for tunnel
SU1523675A1 (en) Method of supportting mine workings
RU2134350C1 (en) Method for fortifying mine workings driven in rock matter liable to heaving
CN113107523B (en) Gap-expanding support method and grouting support process for rock burst support
RU2128773C1 (en) Method for supporting mining workings with loose roof rock by anchor support
RU2215150C1 (en) Method of supporting of underground mine workings with combined support
CN112459786A (en) Method for gob-side entry retaining by roof cutting in multiple times
JPH0813997A (en) Tunnel construction method
SU629347A1 (en) Mine working roof support
SU1273582A1 (en) Method of of bolting rock without hole-drilling
SU1481425A1 (en) Method of supporting mine workings
SU1578407A1 (en) Method of restoring mine workings
SU1567789A1 (en) Method of securing mine working
SU1537818A1 (en) Method of supporting mine workings
SU1677443A1 (en) Method for consolidation of mine workings
SU1406388A1 (en) Method of constructing a mine working
SU625044A1 (en) Method of supporting mine workings
SU987108A1 (en) Method of supporting mine workings
SU1765441A1 (en) Method at advanced anchoring during driving of working
RU2684629C1 (en) Method of grouting rocks during the construction of vertical shafts
SU1751349A1 (en) Method of controlling floor heaving in mine workings
SU1507895A1 (en) Method of supporting mine workings
SU1758232A1 (en) Method of consolidating rocks in vertical shaft sinking
SU877031A1 (en) Method of constructing a vertical shaft