SU877031A1 - Method of constructing a vertical shaft - Google Patents

Method of constructing a vertical shaft Download PDF

Info

Publication number
SU877031A1
SU877031A1 SU802888259A SU2888259A SU877031A1 SU 877031 A1 SU877031 A1 SU 877031A1 SU 802888259 A SU802888259 A SU 802888259A SU 2888259 A SU2888259 A SU 2888259A SU 877031 A1 SU877031 A1 SU 877031A1
Authority
SU
USSR - Soviet Union
Prior art keywords
drilling
holes
wells
barrel
constructing
Prior art date
Application number
SU802888259A
Other languages
Russian (ru)
Inventor
Гарри Григорьевич Литвинский
Геннадий Васильевич Бабиюк
Original Assignee
Коммунарский горно-металлургический институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Коммунарский горно-металлургический институт filed Critical Коммунарский горно-металлургический институт
Priority to SU802888259A priority Critical patent/SU877031A1/en
Application granted granted Critical
Publication of SU877031A1 publication Critical patent/SU877031A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Description

(54) СПОСОБ СООРУЖЕНИЯ ВЕРТИКАЛЬНОГО СТВОЛА(54) METHOD OF CONSTRUCTING A VERTICAL STEM

II

Изобретение относитс  к горному делу, а именно к проходке и креплению вертикальных стволов, и может быть использовано при строительстве вертикальных горных выработок в угольной, горнорудной и других отрасл х промышленности.The invention relates to mining, in particular, to sinking and fastening vertical shafts, and can be used in the construction of vertical mine workings in the coal, mining and other industries.

. Известны способы сооружени  вертикальных стволов с помощью буровзрывных работ и с возведением крепи из искусственвых материалов (бетона, тюбингов н т, д.) П).. There are known methods for constructing vertical shafts using drilling and blasting operations and with the erection of lining from artificial materials (concrete, tubing, nt, e) P).

Недостатками способов  вл ютс  малые скорости сооружени  стволов, незначительна  несуща  способность крепи и большой расход материалов на ее возведение.The disadvantages of the methods are the low speed of construction of the shafts, the insignificant bearing capacity of the lining and the high consumption of materials for its construction.

Наиболее близким по техиической сущности и достигаемому результату к предлагаемому  вл етс  способ сооружени  вертикального ствола по совмещенной схеме с последующим тампонажем горных пород, включающий бурение щпуров и взрывание зар дов взрывчатого вещества в забое выработки , уборку разрушенной породы, бурение тампонажных скважин и подачу в них скрепл ющего раствора 2.The closest in technical essence and the achieved result to the proposed is a method of constructing a vertical wellbore according to a combined scheme with subsequent plugging of rocks, including drilling shpurov and blasting explosive charges in the mine working, cleaning of the destroyed rock, drilling of wellheads and feeding in clamps 2.

Недостатки данного способа состо т в больших затратах материалов на возведение крепи н упрочнение пород и малой скорости сооружени  стволов.The disadvantages of this method are the high cost of materials for the construction of lining and hardening of rocks and low speed of construction of shafts.

Цель изобретени  - снижение стоимости сооружени  ствола.The purpose of the invention is to reduce the cost of building a trunk.

Указанна  цель достигаетс  тем, что в способе, включающем бурение шпуров и This goal is achieved by the fact that in the method including drilling holes and

взрывание зар дов в забое ствола, уборку разрушенной породы, бурение тампонажных скважин и подачу в них скрепл ющего раствора, после взрывани  .зар дов в забое ствола и уборки разрушенной породы вокQ руг ствола создают зону искусственной трещиноватости путем бурени  в радиальном направлении шпуров и взрывани  в ких зар дов, причем одновременно с бурением радиальных шпуров бур т тампонажиые скважины в зону искусственной трещиноваfS ТОСТИ. blasting of charges in the bottom of the borehole, cleaning of the destroyed rock, drilling of cement wells and supplying a bonding solution to them, after blasting the heads in the bottom of the trunk and cleaning the destroyed rock, the wok of the trunk creates an artificial fracture zone by drilling in the radial direction charges, and simultaneously with the drilling of radial holes, tamponage wells are drilled into the zone of artificial fracture fS.

Кроме того, радиальные шпуры и там; понажные скважины бур т в шахматном пор дке .In addition, radial holes and there; the wells are drilled in a checkerboard pattern.

На фиг. I изображен ствол в момент бурени  радиальных шпуров н тампонаж20 ных скважин, вертикальный разрез; на фиг. 2 - то же, в момент нагнетани  скрепл ющего раствора за опалубку и бурени  щпуров в забое ствола; на фиг. 3 -- то же, в момент уборки разрушенной породы и нагнетани  скрепл ющего раствора через тампонажные скважины; на фнг. 4 - сечение А-А на фиг. 1; на фиг. 5 - сечение Б-Б на фнг. 1. Способ осуществл етс  следующим образом . В стенках ствоЛа I через отверсти  в подвесной опалубке 2 радиально в шахматном пор дке бур т шпуры 3 дл  зар дов взрывчатого вещества, например, буровой установкой по типу БУКС или бурильной машиной , смонтированной на подвесной опалубке Одновременно со шпурами 3 перфораторами с подвесного полка 4 через прёдварительно упрочненную приконтурную зону 5 Г«Ч«-Г Wt frrr W r V ( A nnrr ttrkV4tffX бур т тампонажные скважины 6 дл  нагнетани  скрепл ющего раствора, длина которых не пpeвыщaef толщины крепи, а количество их определ етс  параметрами нагнетани  упрочн ющего раствора Шпуры 3 зар жают зар дами взрывчатого вещества и производ т взрывание так, чтобы вокруг выработки образовалась зона; 7 интенсивной тpeщинoвaтoctи, в которой породы разбиты на отдельные блоки, плотио прилегающие друг к другу по криволинейным трещинам, и разгружены от напр жений . При взрывании за счет увеличени  объема пород контур смещаетс  внутрь ствола на 0,15-0,1 м. После взрыва за подвесную опалубку 2 нагнетают скрепл ющий раствор и упрочHHiOT приконтурную зону 5 разгруженных пород. Дл  этого вначале, с целью предотвраш;ени  проникновени  скрепл ющего раствора в забой ствола, подвесную опалубку . 3 нзолируют путем установки заглушек в отверсти  дл  бурени  шпуров н подачи воздуха в эластичные герметизаторы 8. Далее к опалубке присоедин ют шланги 9 дл  подачи раствора и включают насос 10, например ИГР 250/50, установленный на подвесном полке 4 вместе6 промежуточной емкостью 11, в Которую подаетс  раствор с поверхности по трубопроводу 12. Одновременно .с нагнетанием раствора за опалубку 2 бур т щпуры 13 в забое выработки на длинузаходки, которые зар жают зар дами взрывчатого вещества и взрывают , а затем совместно с уборкой разрущеНной породы серийным оборудованием с подвесного полка 4 нагнетают скрепл ющий раствор вглубь зоны 5 разгруженных пород . Дл  этого шланги 9 присоедин ют к кондукторам, которые устанавливают в тампонажные скважины 6. Нагнетание производ т насосом Ю зажимным способом под давлением 10-25.атм, что обусловлено несущей способностью кольца упрочненной приконтурной зоны 5 разгруженных пород. Контроль режима нагнетани  производ т по расходу раствора и давлению нагнетани . После уборки породы и окончани  нагнетани  раствора в тампонажные скважнны подвесную опалубку 2 устанавливают на новую заходку, и цикл работ повтор ют. Предлагаемый способ может быть прнМенен и при других схемах сооружени  вер .....Л|«. ......, тикальных стволов. Использование изобретени  позволит снизить стоимость сооружени  ствола за счет использовани  в качестве крепи разгруженных и упрочненных горных пород, и ликвидации затрат на возведение монолитной бетонной или тюбинговой крепи, . Фррмула изобретени  . -Способ сооружени  вертикального ствола , включающий бурение шпуров и взрывание зар дов-в забое ствола, уборку разрушенной породы, бурение тампонажных скважин и подачу в них скрепл ющего раствора. отличающийс  тем, что, с целью снижени  стоимости сооружени  ствола, после взрывани  зар дов в забое ствола и уборки разрушенной породы вокруг ствола создают зону искусственной трещи нов атости путем бурени  в радиальном направлении шпуров и взрывани  в них зар дов, причем одновременно с бурением радиальных шпуров бур т тампонажные скважины в зону искусетвенной трещиноватрстн. 2. Способ по п. 1, отличающийс  тем, что радиальные шпуры и тампонажные скважины бур т в шахматном пор дке, Источники информации, прин тые во внимание при экспертизе 1. Бокий Б. В. и др. Технологи  и механизаци  .строительства подземных сооружений и щахт. М., сНедра, 1971, с. 595- 2. To.., с. 37 (прототип).FIG. I shows the barrel at the time of drilling radial boreholes on cement wells, a vertical section; in fig. 2 - the same, at the moment of injection of the fastening solution for the formwork and drilling of the shaft in the borehole bottom; in fig. 3 - the same, at the moment of harvesting the destroyed rock and forcing the fastening solution through the grouting wells; on fng. 4 is a section A-A in FIG. one; in fig. 5 - section BB on the fng. 1. The method is carried out as follows. In the walls of the wall I through the holes in the suspended formwork 2, the holes 3 are radially in a chessboard order for explosive charges, for example, a BUX drilling rig or a drilling machine mounted on the suspended formwork Simultaneously with the 3 holes in the perforators from the suspended shelf 4 through Pre-hardened marginal zone 5 G "H" -G Wt frrr W r V (A nnrr ttrkV4tffX will grout wells 6 to inject the fastening solution, the length of which is not better than the thickness of the lining, and their number is determined by injection parameters Strength mortar Boreholes 3 are charged with explosives and exploded so that a zone is formed around the mine; 7 intense cracking, in which the rocks are broken up into separate blocks adjacent to each other along curvilinear cracks and unloaded from stresses. When blasting due to an increase in the volume of rocks, the contour is displaced into the trunk by 0.15-0.1 m. After the explosion, a holding solution and reinforcement HHiOT near the boundary zone 5 of the unloaded rocks are pumped over the suspended formwork 2. To do this, first, in order to prevent penetration of the bonding solution into the bottom of the trunk, suspended formwork. 3 is nzoliruya by installing plugs in the holes for drilling holes n air supply in elastic sealers 8. Next to the formwork attach the hoses 9 for supplying the solution and turn on the pump 10, for example IGR 250/50, mounted on the suspension shelf 4 together 6 intermediate tank 11, The solution is supplied from the surface through conduit 12. Simultaneously, with injection of the solution for the formwork 2, the drill holes 13 are in the working hole for the length of the discharge, which are charged with explosive charges and blown up. Labor with serial equipment from suspended shelf 4 injects a fastening solution into the depths of zone 5 of the unloaded rocks. For this purpose, hoses 9 are attached to conductors, which are installed in plugging wells 6. The injection is carried out by a pump using a clamping method under a pressure of 10-25 atm, which is caused by the bearing capacity of the ring of reinforced marginal zone 5 of unloaded rocks. Monitoring of the injection mode is carried out according to the flow rate of the solution and the injection pressure. After the rock has been harvested and the solution has been injected into the cement wells, the suspended formwork 2 is installed on a new entry, and the cycle of work is repeated. The proposed method can also be applied in other schemes for the construction of a vertex ..... L | ". ......, tical barrels. The use of the invention will reduce the cost of building the trunk by using unloaded and strengthened rocks as lining, and eliminating the cost of erecting monolithic concrete or tubbing,. Invention Formula. - A method for constructing a vertical wellbore, including drilling holes and blasting charges — in the bottom of the hole, harvesting destroyed rock, drilling backfilling wells and feeding a holding solution into them. characterized in that, in order to reduce the cost of building the trunk, after blasting charges in the bottom of the trunk and harvesting the destroyed rock around the trunk, create an artificial cracking zone by drilling in the radial direction of boreholes and blasting charges in them, while simultaneously drilling radial boreholes drill t tamponazhny wells in the zone of artificial fracturing. 2. The method according to claim 1, characterized in that the radial bore-holes and plugging wells are drilled in chess order. Sources of information taken into account during the examination 1. Boky B.V. and others. Technologists and mechanization of the construction of underground structures and schacht. M., Nedra, 1971, p. 595- 2. To .., p. 37 (prototype).

(риг.З(rig. 3

A-AA-A

(риг. f/(rig f /

Claims (2)

Формула изобретенияClaim 1. Способ сооружения вертикального ствола, включающий бурение шпуров и взрывание зарядов-в забое ствола, уборку разрушенной породы, бурение тампонажных скважин и подачу в них скрепляющего раствора, отличающийся тем, что, с целью снижения стоимости сооружения ствола, после взрывания зарядов в забое ствола и уборки разрушенной породы вокруг ствола создают зону искусственной трещиноватости путем бурения в радиальном направлении шпуров и взрывания в них зарядов, причем одновременно с бурением радиальных шпуров бурят тампонажные скважины в зону искусственной трещиноватости.1. A method of constructing a vertical barrel, including drilling holes and blasting charges in the bottom of the barrel, cleaning the destroyed rock, drilling cement wells and supplying them with a cementing mortar, characterized in that, in order to reduce the cost of construction of the barrel, after blasting charges in the bottom of the barrel and harvesting the destroyed rock around the trunk create an artificial fracturing zone by drilling holes in the radial direction and blasting charges in them, while cement wells are drilled at the same time as the radial holes are drilled zone of artificial fracturing. 2. Способ поп. 1, отличающийся тем, что радиальные шпуры и тампонажные скважины бурят в шахматном порядке.2. The method of pop. 1, characterized in that the radial holes and cement wells are drilled in a checkerboard pattern.
SU802888259A 1980-02-27 1980-02-27 Method of constructing a vertical shaft SU877031A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802888259A SU877031A1 (en) 1980-02-27 1980-02-27 Method of constructing a vertical shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802888259A SU877031A1 (en) 1980-02-27 1980-02-27 Method of constructing a vertical shaft

Publications (1)

Publication Number Publication Date
SU877031A1 true SU877031A1 (en) 1981-10-30

Family

ID=20880218

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802888259A SU877031A1 (en) 1980-02-27 1980-02-27 Method of constructing a vertical shaft

Country Status (1)

Country Link
SU (1) SU877031A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4701073A (en) * 1984-12-05 1987-10-20 Sainsbury Garrett Michael Shaft sinking method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4701073A (en) * 1984-12-05 1987-10-20 Sainsbury Garrett Michael Shaft sinking method

Similar Documents

Publication Publication Date Title
US3690106A (en) Method of treating permeable formations
CN104613831A (en) Construction method for additionally forming periphery auxiliary holes in periphery of vertical shaft periphery hole
RU2439323C1 (en) Method to mine inclined ore deposits
RU2392434C1 (en) Method to provide for stability of high ledges
SU877031A1 (en) Method of constructing a vertical shaft
RU2059810C1 (en) Method for mining of steeply dipping mineral deposits
RU2059073C1 (en) Method for development of mineral deposits
SU1401133A1 (en) Method of preparing to mining the stores of mine fields of flooded potassium mines
RU2095574C1 (en) Method for construction of mine shafts in watered unstable rocks
RU2078209C1 (en) Method of mining mineral deposits and superstructure for its embodiment
SU977836A1 (en) Method of erecting bridge in mine working
SU1502837A1 (en) Method of sinking a mine shaft
RU2002127100A (en) METHOD FOR DRIVING MINING DRAINAGE IN DISTURBED AND WATERWATED ARRAY
SU1384793A1 (en) Method of driving workings in outburst-hazardous rock
SU1578407A1 (en) Method of restoring mine workings
SU1550174A1 (en) Method of degassing a rock body
SU1671866A1 (en) Shaft tunneling method with pre-shaft drifting
SU1535999A1 (en) Method of plugging a hole
SU1444518A1 (en) Method of sinking a technological well in mine working influence zone
SU1758232A1 (en) Method of consolidating rocks in vertical shaft sinking
RU1830417C (en) Method of hydro-isolation and consolidation of mountain-mass while tunneling
SU1550157A1 (en) Tunnel construction method
SU1180518A1 (en) Method of enhancing the stability of fissured rock when driving mine workings
SU1710763A1 (en) Method of sinking vertical shaft siding
SU973852A1 (en) Method of consolidating rock