JP4170867B2 - Tunnel excavation method - Google Patents

Tunnel excavation method Download PDF

Info

Publication number
JP4170867B2
JP4170867B2 JP2003328206A JP2003328206A JP4170867B2 JP 4170867 B2 JP4170867 B2 JP 4170867B2 JP 2003328206 A JP2003328206 A JP 2003328206A JP 2003328206 A JP2003328206 A JP 2003328206A JP 4170867 B2 JP4170867 B2 JP 4170867B2
Authority
JP
Japan
Prior art keywords
excavation
tunnel
divided
section
excavator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003328206A
Other languages
Japanese (ja)
Other versions
JP2005090176A (en
Inventor
勉 木内
利彦 和田
正憲 鈴木
雅之 清水
誠介 大久保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2003328206A priority Critical patent/JP4170867B2/en
Publication of JP2005090176A publication Critical patent/JP2005090176A/en
Application granted granted Critical
Publication of JP4170867B2 publication Critical patent/JP4170867B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、自由断面掘削機を用いたトンネル掘削方法に関するものである。   The present invention relates to a tunnel excavation method using a free section excavator.

一般的なNATM(New Austrian Tunneling Method)工法は、1つの切羽に対して「掘削工程→ズリ出し工程→支保工建て込み工程→コンクリート吹き付け工程→ロックボルト工程」を1掘削サイクルとしている。掘削工程は、自由断面掘削機および油圧ブレーカなどの施工機械で切羽の方向に掘削を行う。ズリ出し工程は、ホイールローダ、油圧ショベルおよびダンプトラックなどの施工機械で掘削土砂の搬出を行う。支保工建て込み工程は、エレクターなどの施工機械で支保工の建て込みを行う。コンクリート吹き付け工程は、吹き付け機およびミキサー車などの施工機械で掘削後のトンネル地山にコンクリートの吹き付けを行う。ロックボルト工程は、ホイールジャンボなどの施工機械でトンネル地山にボーリングをしてロックボルトの埋設を行う。   A general NATM (New Austrian Tunneling Method) method has one excavation cycle of “excavation process → slipping process → support construction process → concrete spraying process → rock bolt process” for one face. In the excavation process, excavation is performed in the direction of the face using a construction machine such as a free section excavator and a hydraulic breaker. In the slipping process, excavated soil is carried out by construction machines such as wheel loaders, hydraulic excavators and dump trucks. In the support construction process, the support work is built with a construction machine such as an elector. In the concrete spraying process, concrete is sprayed onto the tunnel ground after excavation by construction machines such as a sprayer and a mixer truck. In the rock bolt process, the rock bolts are buried by boring the tunnel ground with a construction machine such as a wheel jumbo.

上記NATM工法において自由断面掘削機でのトンネル掘削は、シールド工法やTBM(Tunnel Bowling Machine)工法と比較して経済性には優るが、掘進速度が遅いことが挙げられている。   In the above-mentioned NATM method, tunnel excavation with a free-section excavator is superior to the shield method and TBM (Tunnel Bowling Machine) method, but is slow in excavation.

そこで、従来では、トンネル掘削断面を上部半断面と下部半断面とに分割して掘削するベンチカット工法あるいは全断面工法で、カッターブームの中間で屈曲自在とされるヒンジ型カッターブームとされた自由断面掘削機を採用して掘削効率に優れたものにしようとするトンネル掘削方法がある(例えば、特許文献1参照)。   Therefore, in the past, the tunnel excavation section was divided into an upper half section and a lower half section, and a bench-cut method or a full-section method was used for excavating the tunnel, and it was a hinge-type cutter boom that could be bent in the middle of the cutter boom. There is a tunnel excavation method that employs a cross-section excavator to improve excavation efficiency (see, for example, Patent Document 1).

また、別の従来では、トンネル掘削断面を上半部と下半部とに分割し、かつ下半部においてトンネル中心を境に一方側を上半部との一括施工を可能とし得るベンチ長さのミニベンチ部とするとともに、他方側を施工機械を設置可能とし得るベンチ長さのショートベンチ部とし、上半部切羽およびミニベンチ部大背切羽を切り崩した後、下半盤を走行するズリ出し機でズリ出しを行うとともに、併行してショートベンチ部の上半盤に設置した吹き付け機で吹き付けを行うことで、掘削効率を向上しようとするトンネル掘削方法がある(例えば、特許文献2参照)。   In another conventional method, the length of the bench that allows the tunnel excavation section to be divided into an upper half and a lower half, and that the lower half can be installed together with the upper half on one side of the tunnel center. The mini-bench part and the other side is a short bench part with a bench length that can be used to install a construction machine. There is a tunnel excavation method that attempts to improve excavation efficiency by performing a slippage at the same time and performing spraying with a sprayer installed in the upper half of the short bench portion (see, for example, Patent Document 2).

特開平10−115187号公報JP-A-10-115187 特開2002−21467号公報JP 2002-21467 A

しかしながら、特許文献1に参照するトンネル掘削方法では、ヒンジ型カッターブームとされた自由断面掘削機の採用によって掘削作業自体の効率が優るが、掘削作業からズリ出し作業に至る過程での効率化を図ることができない。特に、掘削箇所が明確に2箇所に分かれるロングベンチカット工法またはショートベンチカット工法では、上部半断面の底盤上でのズリ出しに際してズリ出し施工機械と自由断面掘削機とが錯綜することになるために安全性や作業効率の低下を招くことになる。また、ミニベンチカット工法またはマイクロベンチカット工法では、全断面の掘削後にズリ出しを行うので、掘削サイクルが一般的なトンネル掘削方法と変わらず、下部半断面の底盤上で掘削後のズリ出しに際してズリ出し施工機械と自由断面掘削機とが錯綜することになるために安全性や作業効率の低下を招くことになる。   However, in the tunnel excavation method referred to in Patent Document 1, the efficiency of the excavation work itself is superior due to the adoption of a free-section excavator that is a hinge-type cutter boom, but the efficiency in the process from excavation work to slipping work is improved. I can't plan. In particular, in the long bench cut method or short bench cut method in which the excavation part is clearly divided into two parts, the excavation construction machine and the free cross-section excavator are complicated when the upper half section is displaced on the bottom plate. Therefore, safety and work efficiency will be reduced. In the mini-bench cut method or the micro bench cut method, since the excavation is performed after excavation of the entire section, the excavation cycle is not different from the general tunnel excavation method, and the excavation after excavation on the bottom plate of the lower half section is performed. Since the unloading machine and the free-section excavator are complicated, the safety and work efficiency are lowered.

また、特許文献2に参照するトンネル掘削方法でも、掘削作業からズリ出し作業に至る過程での効率化を図ることができない。特に、下半盤でズリ出し作業を行っているが、上半盤のズリを下半盤に落とし込む必要があるので、上半盤にホイールローダなどの施工機械を載せる手間や、下半盤に落としたズリを再び施工機械でズリ出しする手間がかかるため一般的なズリ出し工程よりも効率が悪くなる。一方、ショートベンチ部の上半盤での吹き付けは、上半盤のズリを下半盤に落とし込むまでは行えないので結果的に上半盤のズリ出し完了を待つのと同様である。さらに、ミニベンチ部大背切羽を切り崩した部分(片側壁部および片側アーチ部)の吹き付けは、下半盤でのズリ出し完了を待つことになる。すなわち、吹き付けとズリ出しとを併行して行っているものの、結果的にズリ出し作業を待ってから吹き付け作業を行うので、上半盤側と下半盤側とで作業を行う分一般的な吹き付け工程よりも効率が悪くなる。   Further, even in the tunnel excavation method referred to Patent Document 2, it is not possible to improve the efficiency in the process from excavation work to slippage work. In particular, the lower half of the work is being done with a slip, but it is necessary to drop the upper half of the work into the lower half of the board. Since it takes time and effort to remove the dropped gap again with the construction machine, the efficiency is worse than that of a general gap removal process. On the other hand, spraying on the upper half of the short bench section cannot be performed until the upper half board is dropped into the lower half board, and as a result, it is the same as waiting for completion of the upper half board. Furthermore, the spraying of the parts (one side wall part and one side arch part) where the mini bench part large back face is cut off waits for the completion of the slippage in the lower half board. That is, although spraying and slipping are performed in parallel, as a result, the spraying work is performed after waiting for the slipping work, so the work on the upper half side and the lower half side is common. The efficiency is worse than the spraying process.

本発明は、上記実情に鑑みて、各工程間の移行の効率化を図って掘削効率を向上することができるトンネル掘削方法を提供することを目的とする。   In view of the above circumstances, an object of the present invention is to provide a tunnel excavation method capable of improving the excavation efficiency by improving the efficiency of transition between processes.

上記の目的を達成するために、本発明の請求項1に係るトンネル掘削方法は、幅方向で2つの分割区画に分割したトンネルを適用対象とし、各分割区画を常に下半部上半部に対して手前側に位置した状態で掘削機により掘削する掘削工程と、前記掘削工程で生じた掘削土砂をズリ積機によりズリ出しするズリ出し工程とを繰り返し実施するトンネル掘削方法であって、前記掘削工程は、2つの分割区画に交互に掘削機を搬入し、各分割区画において搬入した掘削機を下半部の地盤に置き、下半部を掘削した後に上半部の掘削を行うものであり、前記ズリ出し工程は、前記掘削機を搬出して空いた分割区画にズリ積機を搬入して行うものであり、かつ前記ズリ積機は、少なくとも一方の分割区画で前記掘削機が稼動している際に他方の分割区画で同時にズリ出しするタイミングを含むように稼動することを特徴とする。 To achieve the above object, a tunnel excavation method according to claim 1 of the present invention is to be subject to tunnel divided into two divided sections in the width direction, each divided section is always lower half portion upper half a drilling step of drilling by the drilling machine in a state positioned at the front side of the parts, the drilling soil caused by the excavation process a tunnel excavation method repeated for the muck step of issuing shear by shear volume machine In the excavation step , the excavator is alternately loaded into the two divided sections , the excavator loaded in each divided section is placed on the ground of the lower half, and the upper half is excavated after excavating the lower half. The slipping step is carried out by carrying out the excavator and carrying it into an empty divided section , and the slipping machine is excavated in at least one of the divided sections. When the machine is in operation, the other division Wherein the running to include the timing of issuing simultaneously shear in.

本発明の請求項2に係るトンネル掘削方法は、上記請求項1において、前記ズリ出し工程は、前方で掘削土砂を掻込みするバケットと、当該バケットで掻込みした掘削土砂を後方に搬出するコンベアとを備えたズリ積機で行うことを特徴とする。 The tunnel excavation method according to a second aspect of the present invention is the tunnel excavation method according to the first aspect, wherein the slipping- out step includes a bucket for scraping the excavated sediment in front and a conveyor for transporting the excavated sediment in the rear to the rear. It is characterized by performing with the slot machine provided with.

本発明に係るトンネル掘削方法は、トンネルの加背を幅方向で複数の分割区画にするとともに当該分割区画をさらに上半部と下半部とに分け、分割区画ごとに掘削やズリ出しを行うことで、各分割区画で掘削工程とズリ出し工程とを切り分けつつ、互いの工程作業を実質的に併行する。この結果、各工程間の移行の効率化が図られ掘削効率を向上することができる。また、掘削工程からズリ出し工程に移行するときに、自由断面掘削機とズリ積機とが錯綜することがないので安全性や作業効率を向上することができる。   In the tunnel excavation method according to the present invention, the back of the tunnel is divided into a plurality of divided sections in the width direction, and the divided sections are further divided into an upper half part and a lower half part, and excavation and slipping are performed for each divided section. Thus, the excavation process and the slipping process are separated in each divided section, and the respective process operations are substantially performed concurrently. As a result, the efficiency of the transition between each process is improved, and the excavation efficiency can be improved. Further, when shifting from the excavation process to the excavation process, the free-section excavator and the excavator are not complicated, so that safety and work efficiency can be improved.

ズリ出し工程では、前方で掘削土砂を掻込みするバケットと、バケットで掻込みした掘削土砂を後方に搬出するコンベアとを備えたズリ積機を採用しているので、自由断面掘削機に並設してズリ出しをすることができる。   In the slipping process, a slip loader equipped with a bucket that scrapes the excavated soil in the front and a conveyor that transports the excavated sediment that has been swept by the bucket to the rear is used. Then you can remove it.

以下に添付図面を参照して、本発明に係るトンネル掘削方法の好適な実施例を詳細に説明する。なお、この実施例によりこの発明が限定されるものではない。   Exemplary embodiments of a tunnel excavation method according to the present invention will be described below in detail with reference to the accompanying drawings. Note that the present invention is not limited to the embodiments.

図1は本発明に係るトンネル掘削方法のトンネル断面正面図、図2は本発明に係るトンネル掘削方法のトンネル断面平面図、図3は本発明に係るトンネル掘削方法のトンネル断面側面図、図4はトンネル掘削手順を示すトンネル断面平面図、図5はトンネル掘削手順を示すトンネル断面側面図、図6はトンネル掘削手順を示すトンネル断面平面図、図7はトンネル掘削手順を示すトンネル断面側面図、図8はトンネル掘削手順を示すトンネル断面平面図、図9はトンネル掘削手順を示すトンネル断面平面図、図10はトンネル掘削手順を示すトンネル断面平面図、図11はトンネル掘削手順を示すトンネル断面正面図である。   1 is a cross-sectional front view of a tunnel excavation method according to the present invention, FIG. 2 is a tunnel cross-sectional plan view of the tunnel excavation method according to the present invention, and FIG. Is a tunnel sectional plan view showing the tunnel excavation procedure, FIG. 5 is a tunnel sectional side view showing the tunnel excavation procedure, FIG. 6 is a tunnel sectional plan view showing the tunnel excavation procedure, and FIG. 8 is a cross-sectional plan view of the tunnel showing the tunnel excavation procedure, FIG. 9 is a plan view of the tunnel cross-section showing the tunnel excavation procedure, FIG. 10 is a plan view of the tunnel cross-section showing the tunnel excavation procedure, and FIG. FIG.

本実施例では、以下の条件のもとで高速掘進を行う。(1)建設地の地質状況がある程度把握できている。(2)切羽Kが安定している。(3)切羽Kの圧縮強度の平均が10MPa程度である。(4)切羽Kに水分が付着していない。   In this embodiment, high-speed excavation is performed under the following conditions. (1) The geological situation of the construction site can be understood to some extent. (2) The face K is stable. (3) The average compressive strength of the face K is about 10 MPa. (4) Moisture does not adhere to the face K.

図1〜図3に示すように本実施例におけるトンネル掘削方法は、トンネルの加背を幅方向で複数の切羽Kとした分割区画にする。本実施例では、トンネルの中心線Sを境に加背を左半部Aと右半部Bとの2つの分割区画にしている。   As shown in FIG. 1 to FIG. 3, the tunnel excavation method in the present embodiment is divided into a plurality of face sections K in the width direction of the tunnel. In the present embodiment, the back is divided into two divided sections of a left half A and a right half B with respect to the center line S of the tunnel.

さらに、本実施例では、前記分割区画においてトンネルの上下方向に切羽Kを下半部aと上半部bとに2分割する。すなわち、本掘削方法は、ベンチカット工法を採用しており、特にベンチ長Lを略4mにして下半部aの地盤Gに設置した施工機械によって掘削施工を行うミニベンチカット工法を採用している。   Furthermore, in the present embodiment, the face K is divided into two parts, a lower half a and an upper half b, in the vertical direction of the tunnel in the divided section. That is, this excavation method adopts a bench cut method, and in particular, adopts a mini bench cut method in which excavation is performed by a construction machine having a bench length L of about 4 m and installed on the ground G in the lower half a. .

トンネル掘削手順は、まず、図4および図5に示すように左下半部Aaの切羽Kを機械掘削する。この機械掘削に用いる施工機械は、自由断面掘削機1(掘削能力150m3/h)であって、掘削部1aとして上下左右方向に揺動可能な中折れ型のブームを備えている。また、切削ドラム部1bは、ブームの長手方向に伸縮可能に設けてある。これにより、自由断面掘削機1は、広範囲を短時間で掘削することが可能である。なお、左下半部Aaを掘削する1掘削サイクルでの掘削長L1は、略1.2mが好ましい。 In the tunnel excavation procedure, first, as shown in FIGS. 4 and 5, the face K of the lower left half Aa is mechanically excavated. The construction machine used for this machine excavation is a free-section excavator 1 (excavation capacity 150 m 3 / h), and includes a bent middle boom that can swing vertically and horizontally as an excavation part 1a. Moreover, the cutting drum part 1b is provided so that expansion-contraction is possible in the longitudinal direction of a boom. Thereby, the free section excavator 1 can excavate a wide area in a short time. The excavation length L1 in one excavation cycle for excavating the lower left half Aa is preferably approximately 1.2 m.

次いで、図5および図6に示すように左上半部Abの切羽Kを上記自由断面掘削機1によって機械掘削する。なお、左上半部Abを掘削する1掘削サイクルでの掘削長L2は、略1.2mが好ましい。   Next, as shown in FIGS. 5 and 6, the face K of the upper left half Ab is mechanically excavated by the free section excavator 1. The excavation length L2 in one excavation cycle for excavating the upper left half Ab is preferably approximately 1.2 m.

次いで、図8に示すように分割区画の左半部Aの掘削で生じた掘削土砂をズリ出しする。このズリ出しに用いる施工機械は、ズリ積機2であって、上下左右方向に揺動可能なブーム2aに対して掘削土砂を掻込みするバケット2bを有し、また当該バケット2bで掻込みした前方での掘削土砂を後方であるトンネルの長さ方向に搬出するコンベア2cを有している。さらに、図8に示すように隣接する分割区画である右半部Bでは、右下半部Baの切羽Kの機械掘削を、左半部Aでのズリ出しに併行して行う。すなわち、左半部Aでの機械掘削を完了した自由断面掘削機1を右半部Bに移動し、空いた左半部Aにズリ積機2を搬入して、左半部Aのズリ出しと右下半部Baの機械掘削を併行して行う。なお、右下半部Baを掘削する1掘削サイクルでの掘削長L3は、略1.2mが好ましい。   Next, as shown in FIG. 8, the excavated earth and sand generated by the excavation of the left half A of the divided section is removed. The construction machine used for the slippage is a slipping machine 2, which has a bucket 2b for scrambling excavated earth and sand with respect to a boom 2a that can swing in the vertical and horizontal directions. It has a conveyor 2c that carries out excavated earth and sand in the front in the length direction of the tunnel that is in the rear. Further, as shown in FIG. 8, in the right half B which is an adjacent divided section, mechanical excavation of the face K in the lower right half Ba is performed in parallel with the slippage in the left half A. That is, the free-section excavator 1 that has completed the machine excavation in the left half A is moved to the right half B, the slip loader 2 is loaded into the vacant left half A, and the left half A is slipped out. And machine excavation in the lower right half Ba. The excavation length L3 in one excavation cycle for excavating the lower right half Ba is preferably approximately 1.2 m.

次いで、図9に示すように右上半部Bbの切羽Kを上記自由断面掘削機1によって機械掘削する。この際、上記左半部Aのズリ出しが完了していない場合には、右上半部Bbの機械掘削に併行して引き続き左半部Aのズリ出しを行う。なお、右上半部Bbを掘削する1掘削サイクルでの掘削長L4は、略1.2mが好ましい。   Next, as shown in FIG. 9, the face K in the upper right half Bb is mechanically excavated by the free section excavator 1. At this time, if the left half A is not completely removed, the left half A is continuously removed in parallel with the mechanical excavation of the upper right half Bb. The excavation length L4 in one excavation cycle for excavating the upper right half Bb is preferably approximately 1.2 m.

次いで、図10に示すように右半部Bの掘削で生じた掘削土砂を上記ズリ積機2によってズリ出しする。すなわち、右半部Bでの機械掘削を完了した自由断面掘削機1を退け、空いた右半部Bにズリ積機2を搬入して、右半部Bのズリ出しを行う。   Next, as shown in FIG. 10, excavated earth and sand generated by excavation of the right half B is excavated by the excavator 2. That is, the free section excavator 1 that has completed the mechanical excavation in the right half B is withdrawn, the slip loader 2 is carried into the vacant right half B, and the right half B is slipped out.

続いて、図9あるいは図10に示すように左半部Aの掘削およびズリ出しが完了した後、当該左半部Aの切羽Kに対応する地山Mに吹き付けする。この吹き付けに用いる施工機械は、図には明示しないが、コンプレッサー搭載型吹き付け機(吹き付け能力20m3/h)であり、図11に示すように地山Mに平均10cmの内壁材として初期強度発現(10分3N)の覆工コンクリート3を施工する。すなわち、右半部Bの掘削あるいはズリ出しに併行して左半部Aで吹き付けを行うことになる。 Subsequently, as shown in FIG. 9 or FIG. 10, after excavation and slipping of the left half A are completed, the ground M corresponding to the face K of the left half A is sprayed. Although the construction machine used for this spraying is not shown in the figure, it is a compressor-mounted sprayer (spraying capacity 20 m 3 / h), and as shown in FIG. (10 minutes 3N) lining concrete 3 is constructed. That is, spraying is performed in the left half A in parallel with excavation or slipping out of the right half B.

続いて、左半部Aの吹き付けが完了した後、当該左半部Aの切羽Kに対応する地山Mにロックボルト4を埋設する。このロックボルト4の埋設に用いる施工機械は、図には明示しないが、ホイールジャンボ(150kg級)であり、図11に示すように地山Mに対してロックボルト4を埋設する。   Subsequently, after the spraying of the left half A is completed, the lock bolt 4 is embedded in the ground M corresponding to the face K of the left half A. The construction machine used for embedding the lock bolt 4 is a wheel jumbo (150 kg class), although it is not clearly shown in the figure, and the lock bolt 4 is embedded in the natural ground M as shown in FIG.

なお、左半部Aの吹き付けが完了する頃には、右半部Bの掘削およびズリ出しが完了する。そこで、右半部Bの掘削およびズリ出しが完了した後、当該右半部Bの切羽Kに対応する地山Mに上記吹き付け機によって吹き付けする。すなわち、左半部Aでのロックボルト4の埋設に併行して右半部Bで吹き付けを行うことになる。   In addition, when the spraying of the left half A is completed, excavation and slipping out of the right half B are completed. Therefore, after excavation and slipping of the right half B is completed, the ground M corresponding to the face K of the right half B is sprayed by the spraying machine. That is, spraying is performed at the right half B in parallel with the embedding of the lock bolt 4 at the left half A.

そして、右半部Bの吹き付けが完了した後、当該右半部Bの切羽Kに対応する地山Mに上記ホイールジャンボによってロックボルト4を埋設する。これにより、図11に示すように全断面の切羽Kに対応する地山Mに対して覆工コンクリート3の吹き付けおよびロックボルト4の埋設の施工が完了して1掘削サイクルが終了する。   Then, after the spraying of the right half B is completed, the lock bolt 4 is embedded in the ground M corresponding to the face K of the right half B by the wheel jumbo. Thereby, as shown in FIG. 11, the construction of spraying the lining concrete 3 and the embedding of the lock bolt 4 is completed on the ground M corresponding to the face K of the entire cross section, and one excavation cycle is completed.

さらに、1掘削サイクルを引き続き行う。この場合、左半部Aのロックボルト4の埋設の施工が完了した後、左半部A(左下半部Aa)の切羽Kの機械掘削をすることになる。すなわち、右半部Bでのロックボルト4の埋設に併行して左半部Aで機械掘削を行うことになる。   In addition, one drilling cycle continues. In this case, after the construction of burying the lock bolt 4 in the left half A is completed, the face K of the left half A (lower left half Aa) is mechanically excavated. That is, machine excavation is performed in the left half A in parallel with the embedding of the lock bolt 4 in the right half B.

したがって、上述したトンネル掘削方法では、トンネルの加背を幅方向で複数の切羽Kとした分割区画にし、この分割区画した切羽Kごとに掘削やズリ出しを行うことで、各切羽Kで掘削工程とズリ出し工程とを切り分けつつ、互いの工程作業を実質的に併行している。この結果、各工程間の移行の効率化が図られ掘削効率を向上することができる。また、掘削工程からズリ出し工程に移行するときに、自由断面掘削機とズリ積機とが錯綜することがないので安全性や作業効率を向上することができる。   Therefore, in the above-described tunnel excavation method, the tunnel back is divided into a plurality of divided faces K in the width direction, and the excavation process is performed at each face K by performing excavation and slipping for each divided face K. The process work is performed substantially in parallel with each other while separating the process and the slipping process. As a result, the efficiency of the transition between each process is improved, and the excavation efficiency can be improved. Further, when shifting from the excavation process to the excavation process, the free-section excavator and the excavator are not complicated, so that safety and work efficiency can be improved.

また、掘削およびズリ出しが完了した切羽Kに対応する地山Mに覆工コンクリート3を吹き付けし、吹き付けが完了した地山Mにロックボルト4を埋設する工程をさらに含むことで、各切羽Kで掘削工程とズリ出し工程と吹き付け工程と埋設工程とを切り分けつつ、次工程作業を実質的に併行している。この結果、各工程間の移行の効率化が図られ掘削効率を向上することができる。また、各工程に移行するときに、施工機械が錯綜することがないので安全性や作業効率を向上することができる。   In addition, the method further includes the step of spraying the lining concrete 3 onto the ground M corresponding to the face K for which excavation and slipping has been completed, and burying the lock bolt 4 in the ground M where the spraying has been completed. Therefore, the next process work is substantially performed concurrently while separating the excavation process, the slipping process, the spraying process, and the burying process. As a result, the efficiency of the transition between each process is improved, and the excavation efficiency can be improved. In addition, since the construction machine is not complicated when moving to each step, safety and work efficiency can be improved.

また、掘削工程では、切羽Kを下半部aと上半部bとに分けて、かつ、下半部aの地盤Gに設置した施工機械によって掘削を行うミニベンチカット工法を採用しているので、上記効果とともに掘削サイクルタイムの短縮化が図られるので、さらに掘削効率を向上することができる。   In the excavation process, a mini bench cutting method is employed in which the face K is divided into a lower half a and an upper half b, and excavation is performed by a construction machine installed on the ground G of the lower half a. Since the excavation cycle time is shortened with the above effects, excavation efficiency can be further improved.

また、ズリ出し工程では、前方で掘削土砂を掻込みするバケット2bと、バケット2bで掻込みした掘削土砂を後方に搬出するコンベア2cとを備えたズリ積機2を採用しているので、自由断面掘削機1に並設してズリ出しをすることができる。   Further, in the slipping process, since the slipping machine 2 including the bucket 2b for scraping the excavated sediment in the front and the conveyor 2c for transporting the excavated sediment in the rear to the rear is adopted, it is free. The cross-section excavator 1 can be juxtaposed to be displaced.

また、吹き付け工程では、地山Mに平均10cmの内壁材として初期強度発現(10分3N)の覆工コンクリート3を施工するので、吹き付けコンクリートによってトンネル構造を支えることが可能なため、鋼製支保工を省略することができる。また、吹き付けた覆工コンクリート3とロックボルト4とで鋼製支保工を要さない強度の支保を得ることができる。   In addition, in the spraying process, the concrete structure with the initial strength (10N / 3N) is applied to the natural ground M as the inner wall material with an average of 10cm, so that the tunnel structure can be supported by the sprayed concrete. Work can be omitted. Moreover, the support | cover with the intensity | strength which does not require steel support work with the sprayed lining concrete 3 and the lock bolt 4 can be obtained.

なお、上述した実施例では、トンネルの加背を幅方向に2分割した切羽Kを設けた場合の掘削手順を説明したが、トンネルの加背を幅方向に複数に分割した切羽Kを設けた場合では、例えば左側から右側に切羽Kを順次機械掘削し、掘削が完了した切羽Kの順に掘削土砂をズリ出し、掘削およびズリ出しが完了した切羽Kに対応する地山Mの順に覆工コンクリート3を吹き付け、吹き付けが完了した地山Mの順にロックボルト4を埋設すればよく、上述の効果を得ることができる。   In the above-described embodiment, the excavation procedure in the case where the face K of the tunnel is divided into two in the width direction has been described. However, the face K of the tunnel is divided into a plurality of widths in the width direction. In this case, for example, the working face K is sequentially excavated from the left side to the right side, the excavated soil is removed in the order of the finished face K, and the lining concrete is applied in the order of the ground M corresponding to the finished face K after the excavation and removal. 3 can be sprayed, and the lock bolt 4 can be buried in the order of the natural ground M where the spraying is completed, and the above-described effects can be obtained.

また、上述した実施例では、掘削が完了してからズリ出しを行っているが、機械掘削のときに自由断面掘削機1とズリ積機2とを並設して1つの切羽Kの掘削とズリ出しを同時に行うことが可能である。   In the above-described embodiment, the excavation is performed after the excavation is completed. However, the excavator 1 and the excavator 2 are juxtaposed with each other at the time of mechanical excavation. It is possible to remove the gap at the same time.

以上のように、本発明に係るトンネル掘削方法は、自由断面掘削機を用いたトンネル掘削方法に有用であり、特に、各工程間の移行の効率化を図って併行作業による掘削効率を向上することができる。   As described above, the tunnel excavation method according to the present invention is useful for the tunnel excavation method using a free-section excavator, and in particular, improves the excavation efficiency by the parallel operation by improving the efficiency of transition between the processes. be able to.

本発明に係るトンネル掘削方法のトンネル断面正面図である。It is a tunnel cross-section front view of the tunnel excavation method according to the present invention. 本発明に係るトンネル掘削方法のトンネル断面平面図である。It is a tunnel section top view of the tunnel excavation method concerning the present invention. 本発明に係るトンネル掘削方法のトンネル断面側面図である。It is a tunnel cross section side view of the tunnel excavation method concerning the present invention. トンネル掘削手順を示すトンネル断面平面図である。It is a tunnel cross-sectional top view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面側面図である。It is a tunnel cross section side view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面平面図である。It is a tunnel cross-sectional top view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面側面図である。It is a tunnel cross section side view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面平面図である。It is a tunnel cross-sectional top view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面平面図である。It is a tunnel cross-sectional top view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面平面図である。It is a tunnel cross-sectional top view which shows a tunnel excavation procedure. トンネル掘削手順を示すトンネル断面正面図である。It is a tunnel cross section front view which shows a tunnel excavation procedure.

符号の説明Explanation of symbols

1 自由断面掘削機
1a 掘削部
1b 切削ドラム部
2 ズリ積機
2a ブーム
2b バケット
2c コンベア
3 覆工コンクリート
4 ロックボルト
A 左半部
Aa 左下半部
Ab 左上半部
B 右半部
Ba 右下半部
Bb 右上半部
G 地盤
K 切羽
L ベンチ長
L1,L2,L3,L4 掘削長
M 地山
S 中心線
DESCRIPTION OF SYMBOLS 1 Free-section excavator 1a Excavation part 1b Cutting drum part 2 Sludge machine 2a Boom 2b Bucket 2c Conveyor 3 Covering concrete 4 Rock bolt A Left half part Aa Lower left half part Ab Upper left half part B Right half part Ba Right lower half part Bb Upper right half G Ground K Face face L Bench length L1, L2, L3, L4 Excavation length M Ground mountain S Center line

Claims (2)

幅方向で2つの分割区画に分割したトンネルを適用対象とし、
分割区画を常に下半部上半部に対して手前側に位置した状態で掘削機により掘削する掘削工程と、前記掘削工程で生じた掘削土砂をズリ積機によりズリ出しするズリ出し工程とを繰り返し実施するトンネル掘削方法であって、
前記掘削工程は、
2つの分割区画に交互に掘削機を搬入し、各分割区画において搬入した掘削機を下半部の地盤に置き、下半部を掘削した後に上半部の掘削を行うものであり、
前記ズリ出し工程は、
前記掘削機を搬出して空いた分割区画にズリ積機を搬入して行うものであり、かつ前記ズリ積機は、少なくとも一方の分割区画で前記掘削機が稼動している際に他方の分割区画で同時にズリ出しするタイミングを含むように稼動することを特徴とするトンネル掘削方法。
Applicable to tunnels divided into two divisions in the width direction ,
A drilling step of drilling by the drilling machine in a state where the lower half portion always the divided sections is positioned on the near side with respect to the upper half portion, muck step of issuing shear by shearing the product machine excavated earth and sand produced by the excavation process A tunnel excavation method that repeatedly carries out
The excavation process includes
The excavator is carried alternately into the two divided sections , the excavator loaded in each divided section is placed on the ground of the lower half, and the upper half is excavated after excavating the lower half,
The slipping step is
Carrying out the excavator and carrying it into a vacant divided section , and carrying out the slotting machine when the excavator is operating in at least one of the divided sections A tunnel excavation method characterized in that it operates so as to include a timing at which it is simultaneously shifted in a section .
前記ズリ出し工程は、前方で掘削土砂を掻込みするバケットと、当該バケットで掻込みした掘削土砂を後方に搬出するコンベアとを備えたズリ積機で行うことを特徴とする請求項1に記載のトンネル掘削方法。 The slipping step is performed by a slipping machine including a bucket for scraping excavated sediment in front and a conveyor for transporting excavated sediment trapped in the bucket to the rear. Tunnel excavation method.
JP2003328206A 2003-09-19 2003-09-19 Tunnel excavation method Expired - Fee Related JP4170867B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003328206A JP4170867B2 (en) 2003-09-19 2003-09-19 Tunnel excavation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003328206A JP4170867B2 (en) 2003-09-19 2003-09-19 Tunnel excavation method

Publications (2)

Publication Number Publication Date
JP2005090176A JP2005090176A (en) 2005-04-07
JP4170867B2 true JP4170867B2 (en) 2008-10-22

Family

ID=34457862

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003328206A Expired - Fee Related JP4170867B2 (en) 2003-09-19 2003-09-19 Tunnel excavation method

Country Status (1)

Country Link
JP (1) JP4170867B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102003187B (en) * 2010-10-13 2013-04-10 中国水电顾问集团华东勘测设计研究院 Construction method of under cutting excavation supporting of of deeply buried soft-rock large tunnel
CN102220868B (en) * 2011-05-23 2013-06-19 重庆中环建设有限公司 Urban shallow buried large-section tunnel five-step excavating method
CN102305091B (en) * 2011-08-25 2013-09-11 中铁十六局集团有限公司 Support structure for hard rock large-section tunnel construction, and construction method for support structure
CN102720504A (en) * 2012-06-13 2012-10-10 北京市公路桥梁建设集团有限公司 Double-side-wall-pilot-hole subsection bench cut method construction method
CN103670423B (en) * 2013-11-14 2016-04-06 中铁隧道集团有限公司 A kind of method of tunneling on stratiform phyllite rock mass
JP2015145571A (en) * 2014-02-03 2015-08-13 エフティーエス株式会社 tunnel construction equipment and construction method
JP6653493B2 (en) * 2015-05-28 2020-02-26 清水建設株式会社 Rapid tunnel construction method
CN106401591B (en) * 2016-12-07 2018-07-06 中铁四局集团有限公司 High Speed Grid method for tunnel construction is worn under low-angle
CN112282782B (en) * 2020-10-28 2022-11-18 中铁大桥局集团有限公司 Method for rapidly discharging slag from anchor hole of large-inclination-angle tunnel of suspension bridge

Also Published As

Publication number Publication date
JP2005090176A (en) 2005-04-07

Similar Documents

Publication Publication Date Title
JP4184400B2 (en) Construction method of underground structure
US5257471A (en) Excavator for forming underground continuous wall
JP4170867B2 (en) Tunnel excavation method
JP6684922B2 (en) Zero-discharging short-faced pillarless coal mining method
US5522676A (en) Undercut excavation method
JP2020504253A5 (en)
JP4181980B2 (en) Tunnel construction method
JP3322716B2 (en) Tunnel construction method
CN111411964B (en) Wheel bucket excavator mining method for strip mine slope breaking area
JP2020506309A (en) Clean and efficient coal mining
JP4543130B2 (en) Tunnel widening device
CN206942770U (en) A kind of shape of a hoof development machine promoted by crawler belt
JP4281983B2 (en) Tunnel excavation method using advanced shaft
JPH11350899A (en) Digging method for underground cavity having large cross section and rough stone digging place employing the method
JP2940402B2 (en) Rock tunnel excavation method using arch machine
SU1472673A1 (en) Method of mining a thick steep mineral bed with goaf-filling
RU2194858C2 (en) Method of combined mining of bedded mineral deposits
JP2762140B2 (en) Construction method of underground continuous wall based on underground tunnel
CN111022062B (en) Construction method for clay layer section of ramp
RU2310753C2 (en) Method for thick ore deposit development
JP2002021467A (en) Tunnel excavating method
JPH0828176A (en) Large sectional tunnel excavating machine
JPH05118189A (en) Large sectional tunnel excavating method
JP3748152B2 (en) Tunnel digging method
Młynarczyk et al. The evolution of mechanized excavating systems in LGOM mines conditions

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060210

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071126

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080304

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080502

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080805

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080807

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110815

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4170867

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120815

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130815

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130815

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130815

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees