JPH06100080B2 - Large-section tunnel construction method and ground solidification column construction device - Google Patents

Large-section tunnel construction method and ground solidification column construction device

Info

Publication number
JPH06100080B2
JPH06100080B2 JP2202438A JP20243890A JPH06100080B2 JP H06100080 B2 JPH06100080 B2 JP H06100080B2 JP 2202438 A JP2202438 A JP 2202438A JP 20243890 A JP20243890 A JP 20243890A JP H06100080 B2 JPH06100080 B2 JP H06100080B2
Authority
JP
Japan
Prior art keywords
tunnel
ground
pipe
improvement material
ground improvement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2202438A
Other languages
Japanese (ja)
Other versions
JPH0490000A (en
Inventor
敏則 豊田
Original Assignee
敏則 豊田
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 敏則 豊田 filed Critical 敏則 豊田
Priority to JP2202438A priority Critical patent/JPH06100080B2/en
Publication of JPH0490000A publication Critical patent/JPH0490000A/en
Publication of JPH06100080B2 publication Critical patent/JPH06100080B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 <産業上の利用分野> 本発明は、大断面トンネルの施工方法、特に、道路の非
常駐車帯を設ける箇所や、道路の分岐・合流部等の楕円
断面を有する大断面トンネル、又は道路をラッパ状に拡
幅する等により断面形状が変化する大断面トンネルの施
工方法、及び該工法に用いる地盤固化柱造成装置に関す
る。
DETAILED DESCRIPTION OF THE INVENTION <Industrial field of application> The present invention relates to a method of constructing a large-section tunnel, and in particular, a large section having an elliptical cross-section such as a location where an emergency parking zone on a road is provided, or a branching / merging portion of the road. The present invention relates to a method for constructing a cross-section tunnel or a large-section tunnel whose cross-sectional shape changes by widening a road into a trumpet shape, and a ground-solidifying column construction device used in the method.

<従来の技術> 既存のシールド機によって大断面トンネルを構築する場
合、その径の大きさに限界があり、また、例えば非常駐
車帯を設ける箇所や道路の分岐・合流部等その断面が楕
円形状の場合やラッパ状に変化するときは、施工が困難
であるとともに、その施工区間が短く、大型施工機械を
用いる場合施工単価が高くなりコスト面で不利益を伴
う。
<Prior art> When constructing a large-section tunnel with an existing shield machine, there is a limit to the size of the diameter, and for example, the section where the emergency parking zone is provided, the branching / merging portion of the road, etc. has an oval shape. In the case of or when it changes into a trumpet shape, the construction is difficult, and the construction section is short, and when a large construction machine is used, the construction unit price becomes high and there is a disadvantage in terms of cost.

これに代わる技術として、第6図に示すパイプルーフ工
法が上げられる。この工法は、トンネル60の外周軸方向
にパイプルーフ61を打ち込んでトンネル外郭部を形成
し、次いで外郭部の内側の土砂を掘削し、トンネル60を
構築するものである。
As an alternative technique, a pipe roof construction method shown in FIG. 6 can be mentioned. In this construction method, a pipe roof 61 is driven in the axial direction of the outer periphery of the tunnel 60 to form a tunnel outer portion, and then the earth and sand inside the outer portion are excavated to construct the tunnel 60.

<発明が解決しようとする課題> しかしながら、上記パイプルーフ工法では、大断面トン
ネルの施工区間の前後にパイプルーフ掘進のための発進
到達用の大規模な空間を構築することが必要となるの
で、その工事が大規模かつコスト高になる。また、パイ
プルーフ61はトンネルの軸方向に設けられるので、その
延長が長くなるにつれて、地盤からより大きな荷重を受
けるようになる。したがって、そのため荷重に耐えうる
ようパイプルーフ61の断面を大きくする等その構造を強
固にする必要があり、その施工が不経済かつ煩雑にな
る。さらに、隣接するパイプルーフ61を密に連結するた
めに管理に手間がかかるとともに、個々のパイプルーフ
61の断面が一定なので、トンネル断面が変化する場合
は、その変化に追随することができないという問題があ
る。
<Problems to be Solved by the Invention> However, in the above pipe roof construction method, since it is necessary to construct a large space for starting and reaching for excavating the pipe roof before and after the construction section of the large-section tunnel, The construction becomes large-scale and costly. Further, since the pipe roof 61 is provided in the axial direction of the tunnel, as the extension thereof becomes longer, the pipe roof 61 receives a larger load from the ground. Therefore, it is necessary to strengthen the structure such as enlarging the cross section of the pipe roof 61 to withstand the load, which makes the construction uneconomical and complicated. Furthermore, since the adjacent pipe roofs 61 are closely connected, it is difficult to manage and the individual pipe roofs 61
Since the cross section of 61 is constant, when the tunnel cross section changes, there is a problem that the change cannot be followed.

そこで、本発明は、上記問題点を解消すべくなされたも
ので、その目的は、通常規模の立坑の構築により容易か
つ低コストで施工可能であり、しかも大断面トンネルの
施工延長が長くなっても荷重に耐える十分な強度を有す
るトンネル外郭部を経済的に構築することができる大断
面トンネルの施工方法を提供することにある。
Therefore, the present invention has been made to solve the above-mentioned problems, and the purpose thereof is to construct a normal-scale vertical shaft easily and at low cost, and to extend the construction extension of a large-section tunnel. Another object of the present invention is to provide a method for constructing a large cross-section tunnel that can economically construct a tunnel outer portion having sufficient strength to withstand a load.

本発明の他の目的は、トンネル断面の変化に追随してト
ンネル全体を覆う外郭部を容易に構築することができ
る、大断面トンネルの施工方法を提供することにある。
Another object of the present invention is to provide a method for constructing a large-section tunnel that can easily construct an outer shell that covers the entire tunnel by following changes in the tunnel section.

<課題を解決するための手段> 本発明は、上記目的に鑑みてなされたものであり、その
要旨は、予定するトンネルに沿ってその両側に先進作業
坑を並設する工程と、該並設した作業坑のうちいずれか
一方を発信基地として他方の作業坑に向けて、複数の曲
線状鋼製部材を、予定するトンネルの上方又は下方を経
て所定の間隔で推進設置する工程と、設置した曲線状鋼
製部材に沿って、いずれか一方の作業坑から他方の作業
坑に向い地盤改良材注入管を掘進到達させる工程と、到
達した地盤改良材注入管を前記曲線状鋼製部材に沿って
後退させつつその先端部から地盤改良材を側方に噴射し
てこれを地盤の土粒子と混合し、前記曲線状鋼製受材を
芯材すなわち補強材とした所定の有効径を有する複数の
地盤固化柱を造成することによって、トンネルの上方及
び下方においてこれの全体を覆うトンネル外郭部を形成
する工程と、トンネル外郭部の内側の土砂掘削する工程
とからなる大断面トンネルの施工方法にある。
<Means for Solving the Problems> The present invention has been made in view of the above objects, and the gist thereof is a step of arranging advanced work shafts on both sides of a tunnel along a planned tunnel, and the parallel arranging. One of the working mines was used as a transmission base toward the other mining, and a plurality of curved steel members were installed at a predetermined interval through a predetermined tunnel above or below the planned tunnel. Along the curved steel member, the step of digging and reaching the ground improvement material injection pipe from one of the work wells to the other work well, and the reached ground improvement material injection pipe along the curved steel member. While retreating, the ground improvement material is jetted laterally from its tip to mix it with the soil particles of the ground, and the plurality of curved steel receiving members having a predetermined effective diameter are used as core materials or reinforcing materials. By creating solidification pillars of There is a method for constructing a large cross-section tunnel, which includes a step of forming a tunnel outer portion covering the entire area above and below the flannel and a step of excavating earth and sand inside the tunnel outer portion.

ここで、前記トンネルの両側に並設する先進作業坑は、
例えば、予定するトンネルの両横腹部に立坑を設け、こ
れを発進到達基地として推進工法やシールド工法等によ
り設置する。この場合、作業坑の大きさは、曲線状鋼製
部材の設置工や地盤改良材柱入管による地盤固化柱の造
成工の施工性を考慮して、例えば3m程度とすることが望
ましい。また、前記曲線状鋼製部材、例えば曲線鋼管の
設置工は、曲線施工が可能な既知の小口径鋼管推進工法
等により行なうことができる。曲線状鋼製部材の大きさ
は、その施工性や地盤固化柱の補強材としての強度を考
慮して、例えばその径を100mm〜150mmとすることが望ま
しい。
Here, the advanced work pits installed side by side on both sides of the tunnel are
For example, vertical shafts will be provided on both flanks of the planned tunnel, and they will be installed by the propulsion method or the shield method as a starting and reaching base. In this case, it is desirable that the size of the work pit be, for example, about 3 m in consideration of the workability of the installation work of the curved steel member and the construction work of the ground solidification column by the ground improvement material column inlet pipe. Further, the installation work of the curved steel member, for example, the curved steel pipe, can be performed by a known small-diameter steel pipe propulsion construction method or the like which enables curved construction. The size of the curved steel member is preferably, for example, 100 mm to 150 mm in diameter in consideration of its workability and strength as a reinforcing material of the ground-solidified column.

さらに、地盤改良材注入管の掘進及び地盤固化柱の造成
は、中央に貫通するガイド部材すなわち前記曲線状鋼製
部材に沿って前進後退する回転摺動部と、該回転摺動部
の前記発進立坑に連設し、かつ前記曲線状鋼製部材を内
包してこれとともに二重管を形成するサヤ管とからなる
地盤固化柱造成装置であって、前記回転摺動部は、地山
を切削するためその前面に取付けた切削手段と、回転摺
動部を前記曲線状鋼製部材を軸に回転させる回転駆動手
段と、掘進時に高圧流体を噴射するための高圧流体噴射
手段と、地盤固化柱造成時に地盤改良材を噴射するため
の地盤改良材噴射手段とを備え、一方前記サヤ管は、前
記回転摺動部へ油圧、空圧、電力等の動力を供給するた
めの動力供給設備と、前記高圧流体噴射手段へ高圧水等
の高圧流体を供給するための高圧流体供給用配管と、前
記地盤改良材噴射手段へセメントミルク等のグラウトを
供給するための地盤改良供給用配管とを備えてなる地盤
固化柱造成装置を用いて行なうことができる。また前記
回転摺動部及びサヤ管の大きさは、前記曲線状鋼製部材
の大きさ及び前記各種配管等を設けるスペースを考慮し
て、その径を例えば150mm〜200mmとすることが望まし
い。
Further, the excavation of the ground improvement material injection pipe and the formation of the ground solidification column are performed by the guide member penetrating through the center, that is, the rotary sliding part that advances and retracts along the curved steel member, and the start of the rotary sliding part. A ground solidification column building device, which is continuously connected to a vertical shaft and includes a curved pipe member and a sheath pipe that forms a double pipe together with the curved steel member, wherein the rotary sliding portion cuts the ground. In order to do so, cutting means mounted on the front surface thereof, rotation driving means for rotating the rotary sliding portion around the curved steel member as an axis, high pressure fluid ejecting means for ejecting high pressure fluid during excavation, and ground solidification column A ground improvement material injection means for injecting a ground improvement material at the time of construction, while the sheath pipe is a power supply facility for supplying power such as hydraulic pressure, pneumatic pressure, and electric power to the rotary sliding portion, Supplying high-pressure fluid such as high-pressure water to the high-pressure fluid injection means It can be performed using order and the high-pressure fluid supply pipe, a soil solidifying column reclamation device comprising a ground improvement supply pipe for supplying grout cement milk or the like into the soil improvement material ejecting means. The size of the rotary sliding portion and the sheath pipe is preferably 150 mm to 200 mm, for example, in consideration of the size of the curved steel member and the space for installing the various pipes.

<作用> 本発明では、まず、予定するトンネルの両横腹部に設け
た立坑を発進用の基地として、例えば3m程度の径を有す
る作業坑としての2本の先進トンネルを、シールド工法
や推進工法等によりトンネルの両側に沿って構築する。
次に、前記2本の先進トンネルのうちのいずれか一方か
ら他方に向けてトンネル軸方向と略直角に複数の曲線状
鋼製部材、例えば曲線鋼管を所定間隔をおいて設置し、
これをガイド部材とする。さらにこのガイド部材に沿っ
て地盤固化柱造成装置を、いずれか一方の先進トンネル
から他方の先進トンネルに到達させ、次いでこの地盤固
化柱造成装置を後退させつつ地盤改良材を側方に回転噴
射し、周囲の地盤の土粒子と混合攪拌して地盤固化柱を
造成する。ここで前記曲線鋼管は、地盤固化柱の補強材
としてこれに埋設される。このようにして設けられる地
盤固化柱は、トンネル軸方向と直角に造成されるため施
工延長が短く、かつ曲率や方向の変化によって容易にト
ンネル断面の変化に追随することができる。
<Operation> In the present invention, first, the vertical shafts provided on both flanks of the planned tunnel are used as starting bases, and two advanced tunnels as working shafts having a diameter of, for example, about 3 m are used as a shield construction method and a propulsion construction method. Build along the both sides of the tunnel.
Next, a plurality of curved steel members, for example, curved steel pipes are installed at a predetermined interval from one of the two advanced tunnels to the other at a substantially right angle to the tunnel axis direction,
This is used as a guide member. Further, along the guide member, the soil-solidifying column building device is made to reach from one of the advanced tunnels to the other advanced tunnel, and then the ground-solidifying column building device is retracted and the ground improvement material is rotated and jetted laterally. , Mix and stir with the soil particles of the surrounding ground to create a solidified ground pillar. Here, the curved steel pipe is embedded in the ground solidification column as a reinforcing material. The ground-solidifying column thus provided has a short construction extension because it is formed at right angles to the axial direction of the tunnel, and can easily follow changes in the tunnel cross section due to changes in curvature and direction.

また、本発明の大断面トンネルの施工方法に用いる地盤
固化柱造成装置は、その掘進時において、先端の回転摺
動部を回転してその前面に設けた切削手段によって地山
を切削し、かつ発進基地としての先進トンネルからの前
記サヤ管を介した推進力によって前進する。この際に、
回転摺動部の先端から噴射される高圧流体としての高圧
水は、前記切削を補助するとともに、切削土砂を流動化
してこれをガイド部材とサヤ管との間の間隙を通して排
出する。また、地盤固化柱造成時において地盤固化柱造
成装置は、サヤ管を介してガイド部材に沿って引き戻さ
れ、これと並行して前記回転摺動部を回転しつつ地盤改
良材を噴射してこれを地盤の土粒子と混合攪拌し、所定
の有効径を有する地盤固化柱を造成する。
Further, the ground solidification column building device used in the method for constructing a large cross-section tunnel of the present invention, at the time of its digging, rotates the rotary sliding portion at the tip to cut the ground by the cutting means provided on the front surface thereof, and It moves forward by propulsive force from the advanced tunnel as the starting base through the sheath pipe. At this time,
High-pressure water as high-pressure fluid injected from the tip of the rotary sliding portion assists the above-mentioned cutting, fluidizes the cutting earth and sand, and discharges it through the gap between the guide member and the sheath pipe. Further, at the time of soil solidification column construction, the soil solidification column construction device is pulled back along the guide member via the sheath pipe, and in parallel with this, the soil improvement material is injected while rotating the rotary sliding portion. Is mixed with soil particles in the ground and stirred to form a solidified ground column having a predetermined effective diameter.

<実施例> 次に、本発明の実施例を、添付図面を基に詳細に説明す
る。
<Example> Next, the example of the present invention is described in detail based on an accompanying drawing.

第1図では、本発明の大断面トンネルの施工方法が、上
下に配した往復車線を有する道路の本線トンネル11と分
岐トンネル12との合流部10を構築するために用いられて
いる。すなわち、本発明の大断面トンネルの施工方法に
より造成した多数の地盤固化柱13によってトンネル外周
を覆う外郭部14を形成し、次いで、この外郭部14の内側
の土砂を掘削除去し、所定の構造物を構築する。前記地
盤固化柱13によりトンネルの上下を覆う外郭部14は、第
2図に示すように、地盤固化柱造成のための作業坑とし
ての先進作業用トンネル15と地盤固化柱13とによって構
成され、例えば幅15m〜30m、高さ10m〜20mの大きさに形
成されている。ここで、地盤固化柱13はトンネル軸方向
と略直角に造成されるためその施工延長が短く、また各
々の地盤固化柱13は、芯材すなわち補強材として、例え
ば径が約100mm〜150mmの曲線状鋼製部材としての曲線鋼
管16をその内部を有し、さらにその形状が外側に凸とな
る曲線であるため、土圧等の外部からの荷重に対して十
分な強度を有する。また、曲線鋼管16の曲率や方向を変
えることにより容易にトンネル断面の変化に追随するこ
とができる。
In FIG. 1, the method for constructing a large-section tunnel of the present invention is used for constructing a confluence portion 10 of a main tunnel 11 and a branch tunnel 12 of a road having vertically arranged reciprocating lanes. That is, an outer shell portion 14 that covers the outer circumference of the tunnel is formed by a large number of ground-solidifying columns 13 formed by the method for constructing a large-section tunnel of the present invention, and then the earth and sand inside the outer shell portion 14 are excavated and removed to form a predetermined structure. Build things. As shown in FIG. 2, the outer shell 14 covering the top and bottom of the tunnel with the soil-solidifying column 13 is composed of an advanced work tunnel 15 and a soil-solidifying column 13 as a work pit for constructing the soil-solidifying column. For example, the width is 15 to 30 m and the height is 10 to 20 m. Here, since the ground solidification column 13 is formed at a substantially right angle to the tunnel axis direction, its construction extension is short, and each ground solidification column 13 is a core material, that is, a reinforcing material, for example, a curve with a diameter of about 100 mm to 150 mm. Since it has a curved steel pipe 16 as a member made of steel-shaped steel inside and has a curved shape that is convex outward, it has sufficient strength against an external load such as earth pressure. Further, by changing the curvature and the direction of the curved steel pipe 16, it is possible to easily follow the change of the tunnel cross section.

次に、本発明の大断面トンネルの施工方法におけるトン
ネル外郭部14の構築方法について説明する。トンネル外
郭部14の構築に先立ち、第1図に示すように、合流部10
の始点付近における本線トンネル11の両横腹部に、先進
作業用トンネル15を掘進するための発進立坑17を構築
し、さらにトンネル軸方向に沿いつつ合流部10を挾んで
その両側に、3m程度の径を有する先進作業用トンネル15
を構築する。これらの発進立坑17や先進作業用トンネル
15は、通常のシールド工法や推進工法に準じて構築す
る。
Next, a method of constructing the tunnel outer portion 14 in the method of constructing a large cross section tunnel of the present invention will be described. Prior to the construction of the tunnel outer portion 14, as shown in FIG.
At both flanks of the main line tunnel 11 near the starting point, a starting shaft 17 is constructed to excavate the advanced work tunnel 15. Advanced working tunnel with diameter 15
To build. These start shafts 17 and tunnels for advanced work
No. 15 is constructed according to the usual shield construction method and propulsion construction method.

引き続いて、第3図(イ)〜(ハ)に示す順序に従って
地盤固化柱13を造成する。すなわち、まず第3図(イ)
に示すように、曲線鋼管16を一方の先進作業用トンネル
15aから推進し、他方の先進作業用トンネル15bに到達さ
せる。次に、曲線鋼管16をガイド部材として、前記一方
の先進作業用トンネル15aから地盤固化柱造成装置20を
推進させ、第3図(ロ)に示すように、他方の先進作業
用トンネル15bに到達させる。さらに、第3図(ハ)に
示すように、他方の先進作業用トンネル15bに到達した
地盤固化柱造成装置20を前記一方の先進作業用トンネル
15aに向かって引き戻すとともに、地盤固化柱造成装置2
0の先端部からこれらの側方に向かってセメントミルク
等のグラウト40を地盤改良材として回転噴射し、これと
地盤固化柱造成装置20の周囲の地盤の土粒子とを混合攪
拌して、所定の有効径を有する地盤固化柱13を造成す
る。
Subsequently, the ground-solidifying column 13 is formed according to the order shown in FIGS. That is, first, FIG.
As shown in, the curved steel pipe 16 is connected to one of the advanced working tunnels.
Propel from 15a and reach the other advanced work tunnel 15b. Next, the curved steel pipe 16 is used as a guide member to propel the ground-solidifying column forming device 20 from the one advanced work tunnel 15a and reach the other advanced work tunnel 15b, as shown in FIG. 3B. Let Further, as shown in FIG. 3C, the ground solidification column forming device 20 reaching the other advanced work tunnel 15b is installed in the one advanced work tunnel.
It is pulled back toward 15a, and at the same time, the ground solidification column building device 2
The grout 40 such as cement milk is rotationally jetted as a ground improvement material from the tip of 0 toward the side of these, and this is mixed with the soil particles of the ground around the ground solidification column forming device 20 and stirred, A solidification column 13 having an effective diameter of is formed.

このような地盤固化柱13は、所定間隔をおいて設置した
多数の曲線鋼管16に沿って、トンネル軸方向に連続して
隙間なく密に造成され、トンネルを覆う外郭部14を構成
する。
Such a ground solidification column 13 is continuously and densely formed in the tunnel axial direction along a large number of curved steel pipes 16 installed at predetermined intervals to form an outer shell portion 14 that covers the tunnel.

本発明に用いる、地盤固化柱造成装置20は、第4図及び
第5図に示すように、回転摺動部21とこれに連設するサ
ヤ管22とによって構成される。回転摺動部21は、外郭26
と、その前面に設けた切削手段としての掘削ビット23
と、中央開口部24と、外郭26内において中央開口部24外
周に設けた油圧モーター25と、外郭26前面の4箇所に開
口する高圧水噴射装置27と、外郭26外周面4箇所に開口
する地盤改良材噴射装置28とを備えている。中央開口部
24には前記ガイド管としての曲線鋼管16がその中央に貫
通し、地盤固化柱造成装置20はこれに沿って移動すると
ともに、回転摺動部21は油圧モーター25の駆動によりこ
れを軸にして回転する。サヤ管22は回転摺動部21と略同
径、例えば150mm〜200mmの径を有するとともに、掘進方
向に対し回転摺動部21の後方に連設し、前記先進作業用
トンネル15aにおいて逐次継ぎ足される。またサヤ管22
は、曲線鋼管16を内包して二重管を形成するとともに、
これとの間に、油圧モーター25の駆動用油を供給又は排
出する動力供給設備としての油圧ホース29と、高圧水噴
射装置27に高圧水を給送する高圧流体供給用配管として
の高圧送水ホース30と、地盤改良材噴射装置28にグラウ
トを圧送する地盤改良材供給用配管としてのグラウトホ
ース31とを備える。
As shown in FIGS. 4 and 5, the ground solidification column forming device 20 used in the present invention is composed of a rotary sliding part 21 and a sheath pipe 22 connected to the rotary sliding part 21. The rotary sliding part 21 has an outer shell 26.
And a drilling bit 23 as a cutting means provided on the front surface thereof.
A central opening 24, a hydraulic motor 25 provided on the outer circumference of the central opening 24 in the outer shell 26, a high-pressure water jet device 27 opening at four locations on the front surface of the outer shell 26, and four openings on the outer circumferential surface of the outer shell 26. A ground improvement material injection device (28) is provided. Central opening
A curved steel pipe 16 as the guide pipe penetrates through the center of the guide pipe 24, and the ground solidification column forming device 20 moves along the guide pipe 24. Rotate. The sheath pipe 22 has substantially the same diameter as the rotary sliding portion 21, for example, a diameter of 150 mm to 200 mm, is continuously provided behind the rotary sliding portion 21 in the excavation direction, and is successively added in the advanced working tunnel 15a. . See also pipe 22
Includes a curved steel pipe 16 to form a double pipe,
In the meantime, a hydraulic hose 29 as a power supply facility for supplying or discharging driving oil for the hydraulic motor 25, and a high pressure water supply hose as a high pressure fluid supply pipe for supplying high pressure water to the high pressure water injection device 27. 30 and a grout hose 31 as a ground improvement material supply pipe for pumping the grout to the ground improvement material injection device 28.

上記構成を有する地盤固化柱造成装置20は、掘進時及び
地盤固化柱造成時において次のように作用する。すなわ
ち掘進時では、回転摺動部21を回転させ、前面の土砂を
切削するとともにサヤ管22を介して前記先進作業用トン
ネル15aから伝わる推進力により前進する。この際に、
高圧水噴射装置27から噴射する高圧水は、掘削ビット23
による掘削を補助し、また切削土砂を流動化して、前記
中央開口部24及び曲線鋼管16とサヤ管22との間の間隙を
経てこれらの切削土砂を排出する。一方地盤固化柱造成
時では、サヤ管22を介して回転摺動部21を引き戻しつつ
地盤改良材噴射装置28からグラウトを高圧噴射し、この
噴射力によって周囲の地盤を切削すると同時に土粒子と
グラウトとを混合攪拌して所定の有効径を有する地盤固
化柱を造成する。この際に、発生するスライムは前記切
削土砂と同様に、前記中央開口部24及び曲線鋼管11とサ
ヤ管22との間の間隙を経て排出される。
The soil-solidified column forming device 20 having the above-described structure operates as follows during excavation and formation of the soil-solidified column. That is, at the time of excavation, the rotary sliding portion 21 is rotated to cut the earth and sand on the front surface and to move forward by the propulsive force transmitted from the advanced work tunnel 15a via the sheath pipe 22. At this time,
The high-pressure water injected from the high-pressure water injection device 27 is used for the drilling bit 23.
To excavate and fluidize the cutting earth and sand, and discharge the cutting earth and sand through the central opening 24 and the gap between the curved steel pipe 16 and the sheath pipe 22. On the other hand, at the time of ground solidification column construction, high pressure jetting of grout from the ground improvement material injection device 28 while pulling back the rotary sliding part 21 via the sheath pipe 22, and the surrounding ground is cut by this injection force and at the same time soil particles and grout. And are mixed and stirred to form a solidified ground column having a predetermined effective diameter. At this time, the generated slime is discharged through the central opening 24 and the gap between the curved steel pipe 11 and the sheath pipe 22 as in the case of the cutting soil.

<発明の効果> 本発明の大断面トンネルの施工方法では、予定するトン
ネルの両側に沿って設けた先進トンネルを作業坑とし
て、トンネルの軸方向と略直角に曲線状の地盤固化柱を
複数造成し、これによってトンネル外郭部を形成するの
で、大規模な作業空間を要することなく容易かつ低コス
トで大断面トンネルを構築できるとともに、トンネルの
延長が長くなっても、荷重に耐える十分な強度を有する
トンネル外郭部を経済的に構築することができる。
<Effects of the Invention> In the method for constructing a large cross-section tunnel of the present invention, a plurality of curved ground solidification columns are formed substantially at right angles to the axial direction of the tunnel by using the advanced tunnel provided along both sides of the planned tunnel as a work pit. Since this forms the outer shell of the tunnel, a large cross-section tunnel can be constructed easily and at low cost without requiring a large working space, and even if the extension of the tunnel is long, sufficient strength to withstand the load is provided. It is possible to economically construct the tunnel outer portion having.

また、曲線状の地盤固化柱の曲率や方向を変えることに
よりトンネル外郭部を容易にトンネル断面の変化に追随
させることができる。
Further, by changing the curvature and the direction of the curved ground solidification column, it is possible to easily follow the change of the tunnel cross section in the tunnel outer portion.

さらに、本発明に用いる地盤固化柱造成装置は、曲線状
鋼製部材をガイド部材として移動する回転摺動部とこれ
に連設するサヤ管とによって構成されているので、曲線
状の地盤固化柱を容易に造成することができる。
Further, since the ground solidification column forming apparatus used in the present invention is constituted by the rotary sliding portion that moves using the curved steel member as the guide member and the sheath pipe connected to this, the curved solidification column is formed. Can be easily created.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明の大断面トンネルの施工方法の概略を示
す説明図、第2図は第1図の線II−IIに沿った断面図、
第3図(イ)〜(ハ)は本発明の地盤固化柱の造成方法
を示す説明図、第4図は本発明に用いる地盤固化柱造成
装置の構成を示す破断断面図、第5図は第4図の線V−
Vに沿った断面図、第6図は従来の大断面トンネルの施
工方法を示す断面図である。 10……合流部、13……地盤固化柱、14……外郭部、15,1
5a,15b……先進作業用トンネル、16……曲線鋼管、17…
…発進立坑、20……地盤固化柱造成装置、21……回転摺
動部、22……サヤ管、23……掘削ビット、25……油圧モ
ーター、27……高圧水噴射装置、28……地盤改良材噴射
装置、29……油圧ホース、30……高圧送水ホース、31…
…グラウトホース、40……グラウト。
FIG. 1 is an explanatory view showing an outline of a method of constructing a large-section tunnel of the present invention, FIG. 2 is a sectional view taken along line II-II of FIG. 1,
3 (a) to 3 (c) are explanatory views showing a method for forming a ground solidifying column of the present invention, FIG. 4 is a fracture cross-sectional view showing a configuration of a ground solidifying column forming device used in the present invention, and FIG. Line V- in FIG.
FIG. 6 is a sectional view taken along line V, and FIG. 6 is a sectional view showing a method of constructing a conventional large-section tunnel. 10 …… Confluence part, 13 …… Solid solidification column, 14 …… Outer part, 15,1
5a, 15b …… Advanced work tunnel, 16 …… Curved steel pipe, 17…
… Starting shaft, 20 …… Solid solidification column building device, 21 …… Rotary sliding part, 22 …… Saya pipe, 23 …… Excavation bit, 25 …… Hydraulic motor, 27 …… High pressure water injection device, 28 …… Ground improvement material injection device, 29 …… hydraulic hose, 30 …… high pressure water supply hose, 31…
... Grout horse, 40 ... Grout.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】予定するトンネルの両側に沿って先進作業
坑を並設する工程と、発進基地としてのいずれか一方の
前記作業坑から他方の作業坑に到達する複数の曲線状鋼
製部材を所定の間隔で設置する工程と、該曲線状鋼製部
材に沿っていずれか一方の作業坑から他方の作業坑に地
盤改良材注入管を到達させる工程と、該到達した地盤改
良材注入管を前記曲線状鋼製部材に沿って後退させると
ともにその先端部から地盤改良材を噴射してこれを地山
土砂と混合することにより、前記曲線状鋼製部材を芯材
とした所定の有効径を有する地盤固化柱を造成し、これ
によってトンネル外郭部を形成する工程と、その後、外
郭部の内側の土砂を掘削する工程とからなる大断面トン
ネルの施工方法。
1. A step of arranging advanced work shafts along both sides of a planned tunnel, and a plurality of curved steel members reaching from one of the work shafts as a starting base to the other work shaft. The step of installing at a predetermined interval, the step of reaching the ground improvement material injection pipe from one of the work holes to the other work hole along the curved steel member, and the reached ground improvement material injection pipe By retreating along the curved steel member and injecting a ground improvement material from its tip to mix it with natural earth and sand, a predetermined effective diameter with the curved steel member as a core material is obtained. A method for constructing a large cross-section tunnel, which comprises the steps of forming a solidified ground column and forming an outer shell of the tunnel by using it, and then excavating earth and sand inside the outer shell.
【請求項2】中央を貫通するガイド部材に沿って前進後
退する回転摺動部と、前記ガイド部材を内包して前記回
転摺動部に連設するサヤ管とからなり、前記回転摺動部
には、地山を切削する切削手段と、前記ガイド部材を軸
にこれを回転させる回転駆動手段と、掘進時に高圧流体
を掘進先方に噴射するための高圧流体噴射手段と、地盤
固化柱造成時に地盤改良材を前記ガイド部材の周囲に噴
射するための地盤改良材噴射手段とを備え、前記サヤ管
には、前記回転摺動部への動力供給設備と、前記高圧流
体噴射手段への高圧流体供給用配管と、前記地盤改良材
噴射手段への地盤改良材供給用配管とを備えた大断面ト
ンネルの覆工方法に用いる地盤固化柱造成装置。
2. A rotary sliding portion which advances and retracts along a guide member penetrating through the center thereof, and a sheath pipe which includes the guide member and is connected to the rotary sliding portion. The cutting means for cutting the ground, the rotation driving means for rotating the guide member around the guide member as an axis, the high-pressure fluid injection means for injecting high-pressure fluid to the digging destination at the time of excavation, and the ground solidification column formation time. A ground improvement material injection means for injecting a ground improvement material around the guide member, and power supply equipment for the rotary sliding portion and high pressure fluid for the high pressure fluid injection means in the sheath pipe. A solidification column forming device for use in a method of lining a large cross-section tunnel, comprising a supply pipe and a ground improvement material supply pipe to the ground improvement material injection means.
JP2202438A 1990-08-01 1990-08-01 Large-section tunnel construction method and ground solidification column construction device Expired - Fee Related JPH06100080B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2202438A JPH06100080B2 (en) 1990-08-01 1990-08-01 Large-section tunnel construction method and ground solidification column construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2202438A JPH06100080B2 (en) 1990-08-01 1990-08-01 Large-section tunnel construction method and ground solidification column construction device

Publications (2)

Publication Number Publication Date
JPH0490000A JPH0490000A (en) 1992-03-24
JPH06100080B2 true JPH06100080B2 (en) 1994-12-12

Family

ID=16457527

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2202438A Expired - Fee Related JPH06100080B2 (en) 1990-08-01 1990-08-01 Large-section tunnel construction method and ground solidification column construction device

Country Status (1)

Country Link
JP (1) JPH06100080B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002227598A (en) * 2001-01-26 2002-08-14 Tekken Constr Co Ltd Construction method for underground structure
JP4730595B2 (en) * 2005-11-04 2011-07-20 清水建設株式会社 Construction method of underground cavity
JP2017043983A (en) * 2015-08-27 2017-03-02 鹿島建設株式会社 Underground structure, and construction method of underground structure
JP2017043982A (en) * 2015-08-27 2017-03-02 鹿島建設株式会社 Underground structure, and construction method of underground structure

Also Published As

Publication number Publication date
JPH0490000A (en) 1992-03-24

Similar Documents

Publication Publication Date Title
JP7211689B2 (en) tunnel excavation method
CA3133618C (en) Method and system of constructing an underground tunnel
WO2022058885A1 (en) Tunnelling shield
CN109026035A (en) Tunnel circumferential direction variable cross-section digs method
CA2456303C (en) Continuous method of realization of underground tunnels including peripheral perforations
WO1989012729A1 (en) Method of forming underground passage and tunnel excavator
US6485234B2 (en) Apparatus and method for making cylindrical columns
JPH06100080B2 (en) Large-section tunnel construction method and ground solidification column construction device
JP3931123B2 (en) Non-open-cutting construction method for underground structures
JP2007132186A (en) Non-excavation constructing technique for underground structure
KR101237749B1 (en) Propulsion unit head that is used in shield method
JP2594864B2 (en) Widening method of underground tunnel
JP7308006B2 (en) tunnel excavation method
GB2137678A (en) Method and apparatus for pile construction
KR101075445B1 (en) Crushing type excavation apparatus for propulsion pipes
JPWO2020193960A5 (en)
JP4172706B2 (en) Ground improvement method and construction method of underground support using it
Kadkade Techniques of Excavation and New Equipment for Tunnelling
JPH06288179A (en) Expansion shield device
JPH0224486A (en) Construction of large-diameter tunnel and ring-cut type excavator
JPS6040414A (en) Improvement of horizontal ground
JPS6156388B2 (en)
JPH0860650A (en) Excavation method
JP2007092441A (en) Device for constructing tunnel
JP2005113381A5 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees