JPH07300861A - Method for constructing large-scale underground frame - Google Patents

Method for constructing large-scale underground frame

Info

Publication number
JPH07300861A
JPH07300861A JP9627894A JP9627894A JPH07300861A JP H07300861 A JPH07300861 A JP H07300861A JP 9627894 A JP9627894 A JP 9627894A JP 9627894 A JP9627894 A JP 9627894A JP H07300861 A JPH07300861 A JP H07300861A
Authority
JP
Japan
Prior art keywords
ground
underground
underground skeleton
skeleton
scale
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9627894A
Other languages
Japanese (ja)
Other versions
JP3362961B2 (en
Inventor
Masao Narita
征夫 成田
Toru Hanawa
亨 塙
Yoshito Kanda
義人 神田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP09627894A priority Critical patent/JP3362961B2/en
Publication of JPH07300861A publication Critical patent/JPH07300861A/en
Application granted granted Critical
Publication of JP3362961B2 publication Critical patent/JP3362961B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To shorten the construction period, facilitate the construction work and reduce the cost. CONSTITUTION:In a construction method wherein a large-scale underground frame 2 is constructed on the ground beforehand in such a manner that edges of blades for settling are projected from under the frame 2, so that the ground 1 is excavated in a space 3 formed by the edges of blades to settle the frame 2, edges of the blades 4 are provided under the outer periphery of the frame 2. Furthermore inner edges of blades 4a are provided inside the underside of the frame 2 to settle the frame 2 on the ground 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、大規模な地下躯体部分
を地上で予め構築して、その後、地盤を掘削しながら地
下躯体部分のケーソンを沈設させて地下躯体を構築する
ための方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a large-scale underground skeleton part on the ground in advance, and then digging the ground to dig the caisson of the underground skeleton part to construct an underground skeleton. .

【0002】[0002]

【従来の技術】従来、地下躯体の構築方法は、図4に示
すように、地盤1の上で躯体の外周部に刃先4を有した
ケーソン2を形成し、躯体の下部の作業空間3において
地盤の掘削作業をし、掘削土砂をグラブバケット等の搬
出手段で排土しながら、当該ケーソン2を所定の深さま
で沈設させていた。
2. Description of the Related Art Conventionally, as shown in FIG. 4, a method of constructing an underground skeleton is to form a caisson 2 having a cutting edge 4 on an outer peripheral portion of the skeleton on a ground 1, and in a working space 3 under the skeleton The caisson 2 is sunk to a predetermined depth while excavating the ground and excavating the excavated earth and sand with a carrying-out means such as a grab bucket.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上述の
構築方法では、ケーソン2の躯体の長さが小さいときは
沈設作業を比較的容易に施工することができるが、例え
ば、躯体の長さが25m以上の大規模なケーソンである
場合には、躯体の歪みを防止するために補強工事が必要
であって工期が長期化し、また、その補強工事に手間が
掛かってコストが嵩むと言う問題点があった。
However, in the above-mentioned construction method, when the length of the body of the caisson 2 is small, the laying work can be performed relatively easily. For example, the length of the body is 25 m. In the case of the above large-scale caisson, there is a problem that reinforcement work is required to prevent distortion of the skeleton, the construction period is prolonged, and the reinforcement work takes time and costs are increased. there were.

【0004】このように、従来の大規模なケーソンを沈
設させて地下躯体を構築するには、地下躯体の補強が必
要となり、工期やコストの点において解決すべき課題を
有していた。本発明は、上記の課題に鑑みてなされたも
ので、工期の短縮と施工の容易化及びコストの軽減を図
る構築方法の提供を目的とする。
As described above, in order to construct an underground skeleton by sinking a conventional large-scale caisson, it is necessary to reinforce the underground skeleton, and there is a problem to be solved in terms of construction period and cost. The present invention has been made in view of the above problems, and an object thereof is to provide a construction method for shortening the construction period, facilitating construction, and reducing costs.

【0005】[0005]

【課題を解決するための手段】本発明の上記課題を解決
し上記目的を達成するための要旨は、大規模な地下躯体
を地上で、該地下躯体の下部に沈設用の刃先を突設させ
て予め構築し、前記刃先によって形成される作業空間で
地盤を掘削し当該地下躯体を沈設させる構築方法におい
て、前記地下躯体の下部の外周部に刃先を設けると共
に、地下躯体の下部の内側にも内部刃先を設け、地下躯
体を地盤に沈設させる構築方法としたことである。
Means for Solving the Problems The object of the present invention to solve the above problems and achieve the above objects is to provide a large-scale underground skeleton on the ground, and to project a blade for sinking into the lower part of the underground skeleton. In advance, built in, in the construction method of excavating the ground in the working space formed by the blade tip and submerging the underground skeleton, with the blade edge provided on the outer peripheral part of the lower part of the underground skeleton, also inside the lower part of the underground skeleton This is a construction method in which an internal cutting edge is provided and the underground structure is submerged in the ground.

【0006】前記内部刃先の近傍に、沈設用の引張手段
を配設したこと、更に、前記内部刃先の上には、仮設補
強壁が設けられていることである。
A pulling means for sinking is arranged in the vicinity of the internal cutting edge, and a temporary reinforcing wall is provided on the internal cutting edge.

【0007】[0007]

【作用】本発明によれば、大規模なケーソンを構築して
地盤に沈設させる場合において、地下躯体下部の下面
に、躯体の外周部に設けた刃先と内側に設けた内部刃先
の2重構造にした刃先を設けたことで、大規模な地下躯
体の中間部が支持されて、長大なスパンの地下躯体であ
っても、特別な補強工事をすることなく沈設させること
ができる。
According to the present invention, in the case of constructing a large-scale caisson and submerging it in the ground, a double structure of the lower cutting edge provided on the lower part of the underground building and the inner cutting edge provided on the outer peripheral portion of the building By providing the blade edge, the large-scale underground skeleton is supported at its intermediate portion, and even an underground skeleton with a long span can be sunk without special reinforcement work.

【0008】そして、前記内側に設けた内部刃先の近傍
に、沈設用の引張手段を配設したこと、または、前記内
部刃先の上に仮設補強壁が設けられていることとすれ
ば、大規模な地下躯体を均等に沈設させることができ、
仮設補強壁で地下躯体の歪みも防止され沈設作業能率を
良くすることができる。
If a pulling means for sinking is arranged in the vicinity of the inner cutting edge provided on the inner side, or if a temporary reinforcing wall is provided on the inner cutting edge, a large scale is provided. It is possible to evenly lay down underground structures,
The temporary reinforcement wall prevents distortion of the underground structure and improves the efficiency of the laying work.

【0009】[0009]

【実施例】次に、本発明に係る一実施例について図面を
参照して詳細に説明する。なお、従来例と対応する部分
には、理解容易のために同一符号を付けて説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, one embodiment according to the present invention will be described in detail with reference to the drawings. The parts corresponding to those of the conventional example will be described with the same reference numerals for easy understanding.

【0010】本発明に係る大規模な地下躯体の構築方法
は、図1(イ)に示すように、予め地盤1の上で地下躯
体の部分のケーソン2を構築する。
In the method of constructing a large-scale underground skeleton according to the present invention, as shown in FIG. 1 (a), the caisson 2 of the underground skeleton portion is previously constructed on the ground 1.

【0011】このケーソン2は、躯体の下部の外周部に
刃先4を設け、更に下部の内側にも内部刃先4aを設け
て形成する。
The caisson 2 is formed by providing a cutting edge 4 on the outer peripheral portion of the lower part of the body and further providing an internal cutting edge 4a on the inner side of the lower part.

【0012】そして、前記ケーソン2の各フロアーを構
築する際に、図2に示すように、躯体の中央部分がエレ
ベーターや階段等のコア部分2aである場合には壁が設
けられるが、このような壁の無い部分で長スパンとなる
部分には、図3に示すように、PC版等をボルト等で着
脱自在にした仮設補強壁2cを設ける。
When constructing each floor of the caisson 2, as shown in FIG. 2, a wall is provided when the central portion of the body is the core portion 2a of an elevator or stairs. As shown in FIG. 3, a temporary reinforcing wall 2c, which is a PC plate or the like that can be freely attached and detached with bolts or the like, is provided in a portion having a long span in a portion without such a wall.

【0013】また、図1(ロ)に示すように、大規模な
ケーソン2を制御装置など(図示せず)でコントロール
しながら、躯体の全体を均等に沈設させ不同沈下となら
ないようにするための、地盤アンカー5を所用数配設す
る。
Further, as shown in FIG. 1B, while controlling a large caisson 2 by a control device or the like (not shown), the whole body is uniformly sunk to prevent uneven settlement. The required number of ground anchors 5 are arranged.

【0014】そして、前記地盤アンカー5は、反力によ
る梁の変形を避けるために前記内部刃先4aの近傍に設
けられるものである。また、この地盤アンカー5を引張
り、その反力で地下躯体2を沈設させるための引張手段
は、例えば、センターホール型の油圧ジャッキ6を前記
アンカー端部に設けるものである。
The ground anchor 5 is provided in the vicinity of the internal cutting edge 4a in order to avoid deformation of the beam due to a reaction force. Further, the pulling means for pulling the ground anchor 5 and sinking the underground structure 2 by its reaction force is, for example, a center hole type hydraulic jack 6 provided at the anchor end portion.

【0015】このようにして、地下躯体用のケーソン2
を予め地上にて構築した後に、作業空間3において掘削
作業をして地盤の土砂を排土し、前記地盤アンカー5を
油圧ジャッキ6で自動制御の下で均等に引っ張りつつ、
地下躯体2を所定の深さに沈設させる。
In this way, the caisson 2 for the underground structure
After preliminarily constructed on the ground, excavating work in the work space 3 to discharge the earth and sand, and while pulling the ground anchor 5 uniformly by the hydraulic jack 6 under automatic control,
The underground structure 2 is sunk to a predetermined depth.

【0016】前記ケーソン2は、前記内部刃先4aや、
仮設補強壁2cによって、躯体の歪みを防止して該躯体
を強固に維持されながら、沈設されるものである。
The caisson 2 includes the internal cutting edge 4a,
The temporary reinforcement wall 2c prevents the distortion of the skeleton body and keeps the skeleton body firmly, and is laid down.

【0017】なお、ケーソン2の沈設作業の終了後に、
前記仮設補強壁2cはボルトなどを外されて撤去される
ものである。
After the caisson 2 is laid down,
The temporary reinforcing wall 2c is removed by removing bolts and the like.

【0018】[0018]

【発明の効果】以上説明したように、本発明の大規模な
地下躯体の構築方法は、大規模な地下躯体を地上で、該
地下躯体の下部に沈設用の刃先を突設させて予め構築
し、前記刃先によって形成される作業空間で地盤を掘削
し当該地下躯体を沈設させる構築方法において、前記地
下躯体の下部の外周部に刃先を設けると共に、地下躯体
の下部の内側にも内部刃先を設け、地下躯体を地盤に沈
設させることとしたので、外周部の刃先と内部刃先との
2重にした刃先によって、長大なスパンの地下躯体にお
いて歪みの発生が防止され、大規模な地下躯体を沈設さ
せることができると共に、歪みの発生を防ぐ補強工事等
の施工が省かれてコストの低減及び工期の短縮が図れる
と言う優れた効果を奏する。
As described above, the method for constructing a large-scale underground skeleton of the present invention is constructed in advance by placing a large-scale underground skeleton on the ground and projecting a blade edge for sinking at the bottom of the underground skeleton. Then, in the construction method of excavating the ground in the working space formed by the blade edge and submerging the underground skeleton, with the blade edge provided on the outer peripheral portion of the lower portion of the underground skeleton, an internal blade edge is also provided inside the lower portion of the underground skeleton. Since it is provided and the underground structure is submerged in the ground, the doubled cutting edge of the outer peripheral edge and the internal edge prevents the occurrence of distortion in the underground structure with a long span, thus enabling a large-scale underground structure. It has an excellent effect that it can be sunk and the construction such as reinforcement work for preventing the occurrence of distortion can be omitted to reduce the cost and the construction period.

【0019】また、前記内部刃先の近傍に、沈設用の引
張手段を配設したこと、更に、前記内部刃先の上には、
仮設補強壁が設けられていることとしたので、大規模な
地下躯体を均一に地盤に沈設させることができるばかり
でなく、大規模な地下躯体の一部分を補強するだけで安
定性良く沈設させることができて、沈設作業の信頼性と
安全性が向上すると言う優れた効果を奏する。
Further, a pulling means for sinking is provided in the vicinity of the internal cutting edge, and further, on the internal cutting edge,
Since it was decided that a temporary reinforcement wall was provided, not only can a large-scale underground structure be sunk in the ground uniformly, but also a large-scale underground structure can be reinforced by only reinforcing a part of it. It has the excellent effect of improving the reliability and safety of the digging work.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る大規模な地下躯体の構築方法に係
り、地上で予め地下躯体部分のケーソンを構築する様子
を示す説明図(イ)、(ロ)である。
FIG. 1 is explanatory diagrams (a) and (b) showing a state in which a caisson of an underground skeleton portion is preliminarily constructed on the ground according to a large-scale underground skeleton construction method according to the present invention.

【図2】同地下躯体の平面図である。FIG. 2 is a plan view of the underground structure.

【図3】同大規模なケーソンを地盤に沈設させている様
子を示す縦断面図である。
FIG. 3 is a vertical cross-sectional view showing a state in which the large-scale caisson is submerged in the ground.

【図4】従来例に係るケーソンを沈設させて地下躯体を
構築する方法を示す説明図である。
FIG. 4 is an explanatory diagram showing a method of constructing an underground skeleton by sinking a caisson according to a conventional example.

【符号の説明】[Explanation of symbols]

1 地盤、 2 ケーソン、 2c 仮設補強壁、 3 作業空間、 4 刃先、 4a 内部刃先、 5 地盤アンカー、 6 油圧ジャッキ。 1 ground, 2 caisson, 2c temporary reinforcement wall, 3 working space, 4 cutting edge, 4a internal cutting edge, 5 ground anchor, 6 hydraulic jack.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 大規模な地下躯体を地上で、該地下躯体
の下部に沈設用の刃先を突設させて予め構築し、前記刃
先によって形成される作業空間で地盤を掘削し当該地下
躯体を沈設させる構築方法において、前記地下躯体の下
部の外周部に刃先を設けると共に、地下躯体の下部の内
側にも内部刃先を設け、地下躯体を地盤に沈設させるこ
とを特徴とする大規模な地下躯体の構築方法。
1. A large-scale underground skeleton is constructed on the ground by preliminarily constructing a blade edge for sinking at a lower portion of the underground skeleton, and the ground is excavated in a working space formed by the blade edge to remove the underground skeleton. In the construction method of sinking, a large-scale underground skeleton characterized in that a blade edge is provided on the outer peripheral part of the lower part of the underground skeleton, and an internal cutting edge is also provided inside the lower part of the underground skeleton, and the underground skeleton is sunk in the ground. How to build.
【請求項2】 内部刃先の近傍に、沈設用の引張手段を
配設したことを特徴とする請求項1に記載の大規模な地
下躯体の構築方法。
2. The method for constructing a large-scale underground skeleton according to claim 1, wherein a tensioning means for sinking is arranged in the vicinity of the internal cutting edge.
【請求項3】 内部刃先の上には、仮設補強壁が設けら
れていることを特徴とする請求項1または2に記載の大
規模な地下躯体の構築方法。
3. The method for constructing a large-scale underground structure according to claim 1, wherein a temporary reinforcing wall is provided on the internal cutting edge.
JP09627894A 1994-05-10 1994-05-10 How to build large underground structures Expired - Fee Related JP3362961B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP09627894A JP3362961B2 (en) 1994-05-10 1994-05-10 How to build large underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP09627894A JP3362961B2 (en) 1994-05-10 1994-05-10 How to build large underground structures

Publications (2)

Publication Number Publication Date
JPH07300861A true JPH07300861A (en) 1995-11-14
JP3362961B2 JP3362961B2 (en) 2003-01-07

Family

ID=14160668

Family Applications (1)

Application Number Title Priority Date Filing Date
JP09627894A Expired - Fee Related JP3362961B2 (en) 1994-05-10 1994-05-10 How to build large underground structures

Country Status (1)

Country Link
JP (1) JP3362961B2 (en)

Also Published As

Publication number Publication date
JP3362961B2 (en) 2003-01-07

Similar Documents

Publication Publication Date Title
JP6010070B2 (en) Temporary closing method for existing underwater structures
JP4069509B2 (en) Construction method of reverse struts in the outer periphery of underground excavation space
JP2001262595A (en) Building construction method of underground building frame
JPH07268885A (en) Method of drive construction used for construction of subsurface structure
JP3453664B2 (en) Shaft construction method
KR0179708B1 (en) Working method for underground structure of a building
JPH07300861A (en) Method for constructing large-scale underground frame
JPH0684690B2 (en) Building basement extension method
JPH06341154A (en) Construction of underground building frame
CN110485469A (en) Round-seal reservoir and its construction method can be recycled by the integrated assembled of wall after one kind
JP3791092B2 (en) Construction method of shaft
JP4146250B2 (en) Open caisson bottom plate construction method
JP2963802B2 (en) How to build an underground parking
JP3377444B2 (en) How to build underground side walls
KR950007008B1 (en) Method for installation of truck lifter
CN214940206U (en) Foundation pit enclosure capping beam and supporting beam connecting structure
JP4031284B2 (en) Construction method for underground structures
JPS5921831A (en) Reverse placement work
JP4064837B2 (en) Housing construction method and housing
JP3430376B2 (en) How to build an underground skeleton
JPH09279609A (en) Building method of precast reinforced concrete-made underground structure
JPH02248521A (en) Open shield method
JP2570599Y2 (en) Partition structure for continuous underground wall construction
JP3889168B2 (en) Construction method of submerged structure and reinforcement piece used in the construction method
JP2001323485A (en) Method of constructing underground structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees