JP3362961B2 - How to build large underground structures - Google Patents
How to build large underground structuresInfo
- Publication number
- JP3362961B2 JP3362961B2 JP09627894A JP9627894A JP3362961B2 JP 3362961 B2 JP3362961 B2 JP 3362961B2 JP 09627894 A JP09627894 A JP 09627894A JP 9627894 A JP9627894 A JP 9627894A JP 3362961 B2 JP3362961 B2 JP 3362961B2
- Authority
- JP
- Japan
- Prior art keywords
- underground skeleton
- caisson
- cutting edge
- ground
- skeleton
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】
【0001】
【産業上の利用分野】本発明は、大規模な地下躯体部分
を地上で予め構築して、その後、地盤を掘削しながら地
下躯体部分のケーソンを沈設させて地下躯体を構築する
ための方法に関する。
【0002】
【従来の技術】従来、地下躯体の構築方法は、図4に示
すように、地盤1の上で躯体の外周部に刃先4を有した
ケーソン2を形成し、躯体の下部の作業空間3において
地盤の掘削作業をし、掘削土砂をグラブバケット等の搬
出手段で排土しながら、当該ケーソン2を所定の深さま
で沈設させていた。
【0003】
【発明が解決しようとする課題】しかしながら、上述の
構築方法では、ケーソン2の躯体の長さが小さいときは
沈設作業を比較的容易に施工することができるが、例え
ば、躯体の長さが25m以上の大規模なケーソンである
場合には、躯体の歪みを防止するために補強工事が必要
であって工期が長期化し、また、その補強工事に手間が
掛かってコストが嵩むと言う問題点があった。
【0004】このように、従来の大規模なケーソンを沈
設させて地下躯体を構築するには、地下躯体の補強が必
要となり、工期やコストの点において解決すべき課題を
有していた。本発明は、上記の課題に鑑みてなされたも
ので、工期の短縮と施工の容易化及びコストの軽減を図
る構築方法の提供を目的とする。
【0005】
【課題を解決するための手段】本発明の上記課題を解決
し上記目的を達成するための要旨は、大規模な地下躯体
を地上で、該地下躯体の下部に沈設用の刃先を突設させ
て予めケーソンを構築し、前記刃先によって形成される
作業空間で地盤を掘削し当該地下躯体を沈設させる構築
方法において、前記地下躯体の下部の外周部に刃先を設
けると共に、該地下躯体の下部の内側にも中間部を支持
する内部刃先を設け、前記ケーソンの各フロアーを構築
する際に壁のない部分で長スパンとなる部分において前
記内部刃先の上に着脱自在な仮設補強壁を設けて当該地
下躯体の歪みを防止し強固に維持しながら、前記地下躯
体を地盤に沈設させ、その沈設後に前記仮設補強壁を撤
去する大規模な地下躯体の構築方法としたことである。
【0006】
【0007】
【作用】本発明によれば、大規模なケーソンを構築して
地盤に沈設させる場合において、地下躯体下部の下面
に、躯体の外周部に設けた刃先と内側に設けた内部刃先
の2重構造にした刃先を設けたことで、大規模な地下躯
体の中間部が支持されて、長大なスパンの地下躯体であ
っても、特別な補強工事をすることなく沈設させること
ができる。
【0008】そして、前記内側に設けた内部刃先の近傍
に、沈設用の引張手段を配設したこと、または、前記内
部刃先の上に仮設補強壁が設けられていることとすれ
ば、大規模な地下躯体を均等に沈設させることができ、
仮設補強壁で地下躯体の歪みも防止され沈設作業能率を
良くすることができる。
【0009】
【実施例】次に、本発明に係る一実施例について図面を
参照して詳細に説明する。なお、従来例と対応する部分
には、理解容易のために同一符号を付けて説明する。
【0010】本発明に係る大規模な地下躯体の構築方法
は、図1(イ)に示すように、予め地盤1の上で地下躯
体の部分のケーソン2を構築する。
【0011】このケーソン2は、躯体の下部の外周部に
刃先4を設け、更に下部の内側にも内部刃先4aを設け
て形成する。
【0012】そして、前記ケーソン2の各フロアーを構
築する際に、図2に示すように、躯体の中央部分がエレ
ベーターや階段等のコア部分2aである場合には壁が設
けられるが、このような壁の無い部分で長スパンとなる
部分には、図3に示すように、PC版等をボルト等で着
脱自在にした仮設補強壁2cを設ける。
【0013】また、図1(ロ)に示すように、大規模な
ケーソン2を制御装置など(図示せず)でコントロール
しながら、躯体の全体を均等に沈設させ不同沈下となら
ないようにするための、地盤アンカー5を所用数配設す
る。
【0014】そして、前記地盤アンカー5は、反力によ
る梁の変形を避けるために前記内部刃先4aの近傍に設
けられるものである。また、この地盤アンカー5を引張
り、その反力で地下躯体2を沈設させるための引張手段
は、例えば、センターホール型の油圧ジャッキ6を前記
アンカー端部に設けるものである。
【0015】このようにして、地下躯体用のケーソン2
を予め地上にて構築した後に、作業空間3において掘削
作業をして地盤の土砂を排土し、前記地盤アンカー5を
油圧ジャッキ6で自動制御の下で均等に引っ張りつつ、
地下躯体2を所定の深さに沈設させる。
【0016】前記ケーソン2は、前記内部刃先4aや、
仮設補強壁2cによって、躯体の歪みを防止して該躯体
を強固に維持されながら、沈設されるものである。
【0017】なお、ケーソン2の沈設作業の終了後に、
前記仮設補強壁2cはボルトなどを外されて撤去される
ものである。
【0018】
【発明の効果】以上説明したように、本発明の大規模な
地下躯体の構築方法は、大規模な地下躯体を地上で、該
地下躯体の下部に沈設用の刃先を突設させて予めケーソ
ンを構築し、前記刃先によって形成される作業空間で地
盤を掘削し当該地下躯体を沈設させる構築方法におい
て、前記地下躯体の下部の外周部に刃先を設けると共
に、該地下躯体の下部の内側にも中間部を支持する内部
刃先を設け、前記ケーソンの各フロアーを構築する際に
壁のない部分で長スパンとなる部分において前記内部刃
先の上に着脱自在な仮設補強壁を設けて当該地下躯体の
歪みを防止し強固に維持しながら、前記地下躯体を地盤
に沈設させ、その沈設後に前記仮設補強壁を撤去する大
規模な地下躯体の構築方法としたので、外周部の刃先と
内部刃先との2重にした刃先によって、長大なスパンの
地下躯体において歪みの発生が防止され、大規模な地下
躯体を沈設させることができると共に、歪みの発生を防
ぐ補強工事等の施工が省かれてコストの低減及び工期の
短縮が図れると言う優れた効果を奏する。
【0019】また、中間部を支持する前記内部刃先の上
には、前記ケーソンの各フロアーを構築する際に壁のな
い部分で長スパンとなる部分において着脱自在な仮設補
強壁が設けられていることとしたので、大規模な地下躯
体を均一に地盤に沈設させることができるばかりでな
く、大規模な地下躯体の一部分を補強するだけで安定性
良く沈設させることができて、沈設作業の信頼性と安全
性が向上すると言う優れた効果を奏する。Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a large-scale underground skeleton in advance on the ground, and then digging the ground to set a caisson in the underground skeleton. And methods for constructing underground structures. 2. Description of the Related Art Conventionally, as shown in FIG. 4, a method of constructing an underground skeleton includes forming a caisson 2 having a cutting edge 4 on an outer peripheral portion of the skeleton on a ground 1 and working on a lower portion of the skeleton. The caisson 2 is sunk to a predetermined depth while excavating the ground in the space 3 and excavating the excavated earth and sand by carrying out means such as a grab bucket. [0003] However, in the above-described construction method, when the length of the caisson 2 is small, the laying operation can be performed relatively easily. If the caisson is a large caisson of 25m or more, reinforcement work is required to prevent distortion of the frame, the construction period is lengthened, and the reinforcement work takes time and costs increase There was a problem. As described above, in order to construct an underground skeleton by laying down a conventional large-scale caisson, reinforcement of the underground skeleton is required, and there is a problem to be solved in terms of construction period and cost. The present invention has been made in view of the above problems, and an object of the present invention is to provide a construction method for shortening a construction period, facilitating construction, and reducing costs. The gist of the present invention to solve the above-mentioned problems and achieve the above-mentioned object is to provide a large-scale underground skeleton on the ground and a cutting edge for laying under the underground skeleton. In a construction method of protruding and constructing a caisson in advance, excavating the ground in the working space formed by the cutting edge, and sinking the underground skeleton, a cutting edge is provided on an outer peripheral portion of a lower portion of the underground skeleton, and the underground skeleton is provided. Also supports the middle part inside the lower part of
The inner edge of providing, construct each floor of the caisson
When the long span in the part without the wall when the
A removable temporary reinforcing wall is provided on the internal
The underground skeleton is sunk on the ground while preventing the distortion of the skeletal structure and firmly maintained, and after the sunk, the temporary reinforcing wall is removed.
This is the construction method of the large underground skeleton to be removed. According to the present invention, when a large-scale caisson is constructed and submerged in the ground, the caisson is provided on the lower surface of the lower part of the underground skeleton and on the inside of the cutting edge provided on the outer peripheral portion of the skeleton. By providing a double-edged cutting edge, the middle part of a large underground skeleton is supported, and even a long span underground skeleton can be laid without special reinforcement work. Can be. [0008] If a pulling means for sinking is provided in the vicinity of the inner cutting edge provided on the inner side, or if a temporary reinforcing wall is provided on the inner cutting edge, a large scale is provided. Can be laid down evenly underground,
The temporary reinforcing walls also prevent distortion of the underground skeleton and improve the efficiency of the laying operation. Next, an embodiment according to the present invention will be described in detail with reference to the drawings. Parts corresponding to those in the conventional example are denoted by the same reference numerals for easy understanding. In the method for constructing a large-scale underground skeleton according to the present invention, a caisson 2 of the underground skeleton is previously constructed on the ground 1 as shown in FIG. The caisson 2 is formed by providing a cutting edge 4 at an outer peripheral portion of a lower portion of a frame, and further providing an inner cutting edge 4a inside a lower portion. When constructing each floor of the caisson 2, as shown in FIG. 2, when the central portion of the skeleton is a core portion 2 a such as an elevator or a stair, a wall is provided. As shown in FIG. 3, a temporary reinforcing wall 2c in which a PC plate or the like is detachable with bolts or the like is provided in a portion having no long wall and having a long span. Further, as shown in FIG. 1 (b), while controlling the large-scale caisson 2 by a control device or the like (not shown), the entire frame is uniformly sunk to prevent uneven settlement. The required number of ground anchors 5 will be provided. The ground anchor 5 is provided near the internal cutting edge 4a in order to avoid deformation of the beam due to a reaction force. The tension means for pulling the ground anchor 5 and submerging the underground skeleton 2 by the reaction force is, for example, a center hole type hydraulic jack 6 provided at the end of the anchor. Thus, the caisson 2 for the underground skeleton
Is constructed in advance on the ground, excavation work is performed in the work space 3 to remove earth and sand from the ground, and the ground anchor 5 is evenly pulled under automatic control by the hydraulic jack 6,
The underground skeleton 2 is laid down to a predetermined depth. The caisson 2 includes the internal cutting edge 4a,
The temporary reinforcing walls 2c prevent the body from being distorted and are sunk while maintaining the body firmly. After the caisson 2 is laid down,
The temporary reinforcing wall 2c is removed by removing bolts and the like. As described above, the method for constructing a large-scale underground skeleton according to the present invention provides a method for constructing a large-scale underground skeleton on the ground and projecting a cutting edge under the underground skeleton. Beforehand
In the construction method of constructing a substructure, excavating the ground in the working space formed by the cutting edge, and laying down the underground skeleton, a cutting edge is provided on the outer peripheral portion of the lower portion of the underground skeleton, and the inside of the lower portion of the underground skeleton is provided. Also provided an internal cutting edge to support the middle part, when building each caisson floor
In the part where there is no wall and the span becomes long, the internal blade
A removable temporary reinforcing wall is provided on the tip to
While preventing distortion and maintaining strong, the underground skeleton is sunk on the ground, and after the sunk, the temporary reinforcing wall is removed, so that a large-scale underground skeletal construction method is adopted. The double-edged cutting edge prevents the occurrence of distortion in the underground skeleton with a long span, allows the large-scale underground skeleton to be laid down, and eliminates the construction work such as reinforcement work to prevent the occurrence of the distortion, thereby reducing costs. It has an excellent effect that reduction and shortening of the construction period can be achieved. When the floor of the caisson is constructed, a wall is provided on the inner cutting edge supporting the intermediate portion.
A temporary reinforcement wall that can be attached and detached is provided at the part that has a long span, so that not only can a large-scale underground structure be laid down uniformly on the ground, It can be sunk with high stability only by reinforcing part of it, and it has an excellent effect of improving the reliability and safety of siding work.
【図面の簡単な説明】
【図1】本発明に係る大規模な地下躯体の構築方法に係
り、地上で予め地下躯体部分のケーソンを構築する様子
を示す説明図(イ)、(ロ)である。
【図2】同地下躯体の平面図である。
【図3】同大規模なケーソンを地盤に沈設させている様
子を示す縦断面図である。
【図4】従来例に係るケーソンを沈設させて地下躯体を
構築する方法を示す説明図である。
【符号の説明】
1 地盤、
2 ケーソン、
2c 仮設補強壁、
3 作業空間、
4 刃先、
4a 内部刃先、
5 地盤アンカー、
6 油圧ジャッキ。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an explanatory diagram (a) and (b) showing a method of constructing a caisson of an underground skeleton in advance on the ground according to the method of constructing a large-scale underground skeleton according to the present invention. is there. FIG. 2 is a plan view of the underground skeleton. FIG. 3 is a longitudinal sectional view showing a state in which the large-scale caisson is sunk on the ground. FIG. 4 is an explanatory view showing a method of constructing an underground skeleton by laying a caisson according to a conventional example. [Description of Signs] 1 Ground, 2 Caisson, 2c Temporary Reinforcement Wall, 3 Work Space, 4 Cutting Edge, 4a Internal Cutting Edge, 5 Ground Anchor, 6 Hydraulic Jack.
フロントページの続き (56)参考文献 特開 平3−217520(JP,A) 特公 昭39−27429(JP,B1) (58)調査した分野(Int.Cl.7,DB名) E02D 23/08 E02D 23/00 Continuation of the front page (56) References JP-A-3-217520 (JP, A) JP-B-39-27429 (JP, B1) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 23 / 08 E02D 23/00
Claims (1)
の下部に沈設用の刃先を突設させて予めケーソンを構築
し、前記刃先によって形成される作業空間で地盤を掘削
し当該地下躯体を沈設させる構築方法において、前記地
下躯体の下部の外周部に刃先を設けると共に、該地下躯
体の下部の内側にも中間部を支持する内部刃先を設け、
前記ケーソンの各フロアーを構築する際に壁のない部分
で長スパンとなる部分において前記内部刃先の上に着脱
自在な仮設補強壁を設けて当該地下躯体の歪みを防止し
強固に維持しながら、前記地下躯体を地盤に沈設させ、
その沈設後に前記仮設補強壁を撤去することを特徴とす
る大規模な地下躯体の構築方法。(57) [Claims 1] A caisson is constructed in advance by constructing a caisson by setting a large underground skeleton on the ground and projecting a cutting edge at the bottom of the underground skeleton, and forming the caisson in advance. In the construction method of excavating the ground in the working space and sinking the underground skeleton, a cutting edge is provided on an outer peripheral portion of a lower portion of the underground skeleton, and an inner cutting edge for supporting an intermediate portion is also provided inside a lower portion of the underground skeleton,
Parts without walls when building each caisson floor
On the internal cutting edge at the part where the span is long
A flexible temporary reinforcing wall is provided to prevent distortion of the underground skeleton.
While firmly maintaining , submerged the underground skeleton on the ground ,
A method for constructing a large-scale underground skeleton , comprising removing the temporary reinforcing wall after the submerged construction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09627894A JP3362961B2 (en) | 1994-05-10 | 1994-05-10 | How to build large underground structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP09627894A JP3362961B2 (en) | 1994-05-10 | 1994-05-10 | How to build large underground structures |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH07300861A JPH07300861A (en) | 1995-11-14 |
JP3362961B2 true JP3362961B2 (en) | 2003-01-07 |
Family
ID=14160668
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP09627894A Expired - Fee Related JP3362961B2 (en) | 1994-05-10 | 1994-05-10 | How to build large underground structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3362961B2 (en) |
-
1994
- 1994-05-10 JP JP09627894A patent/JP3362961B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH07300861A (en) | 1995-11-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4069509B2 (en) | Construction method of reverse struts in the outer periphery of underground excavation space | |
CN106522236A (en) | Structure for shoring of foundation trench and construction method | |
JP2006207152A (en) | Open caisson press-fitting method | |
JP3516391B2 (en) | Ground excavation method | |
JP3362961B2 (en) | How to build large underground structures | |
JP3185190B2 (en) | Construction method of PC hollow pile and underground structure | |
JP2963972B2 (en) | Construction method for underground structures | |
CN1204714A (en) | Method for forming retaining wall | |
JP2000017644A (en) | Installation method of underwater structure | |
JPH0559728A (en) | Sheathing work above underground structure | |
JPH0768707B2 (en) | Open caisson method | |
CN206233244U (en) | The supporting construction of foundation ditch | |
CN217679131U (en) | Be used for reinforced (rfd) back of deep basal pit to tear bearing structure open | |
JP3377444B2 (en) | How to build underground side walls | |
JP7461443B1 (en) | How to assemble an open shield machine | |
JP3430376B2 (en) | How to build an underground skeleton | |
JP3896003B2 (en) | Connection method and structure of shaft | |
JP2863698B2 (en) | Submersion method for submerged body and supporting mechanism used for the method | |
JP2001107361A (en) | Earth retaining work structure and ground excavation method | |
JP2007177407A (en) | Underground story extension method under the foundation of existing building | |
JPH02248521A (en) | Open shield method | |
JP2838019B2 (en) | Caisson blade framing method | |
JP2001336151A (en) | Ground excavation method using shore strut type earth retaining timbering | |
JP4589506B2 (en) | Pre-installation method of large steel columns for constructing buildings with superstructure structure by the reverse driving method | |
JP2589073Y2 (en) | Concrete cast-in-place pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |