JPH0711649A JP15332993A JP15332993A JPH0711649A JP H0711649 A JPH0711649 A JP H0711649A JP 15332993 A JP15332993 A JP 15332993A JP 15332993 A JP15332993 A JP 15332993A JP H0711649 A JPH0711649 A JP H0711649A
Authority
JP
Japan
Prior art keywords
retaining
soil
box
earth retaining
earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15332993A
Other languages
Japanese (ja)
Other versions
JP2579584B2 (en
Inventor
Masao Nakazato
正夫 中里
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ISHII JUKI KK
Original Assignee
ISHII JUKI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ISHII JUKI KK filed Critical ISHII JUKI KK
Priority to JP5153329A priority Critical patent/JP2579584B2/en
Publication of JPH0711649A publication Critical patent/JPH0711649A/en
Application granted granted Critical
Publication of JP2579584B2 publication Critical patent/JP2579584B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To increase rapidity and safety of the work in addition to the easy work. CONSTITUTION:The ground is excavated to reach a required depth (about 1m more or less) to form a trench A and an earth-retaining box 10 assembled in advance is hung down by a construction machine like a back hoe or the like and installed therein (a). Sheet piles 14 are inserted at every required interval in every other sheet or the whole faces for instance (b). Next, the trench is excavated to make it deeper (c), and the earth-retaining box 10 and the sheet piles 14 are pushed in by a back hoe to settle gradually the whole structure in order to complete the earth-retaining work (d).

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、土留工法及び土留用ボ
ックスに関し、特に、ガス管、上・下水道管等の埋設工
事において、簡易な工法により作業の迅速性及び安全性
に優れた技術に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a soil retaining method and a soil retaining box, and more particularly to a technique which is excellent in quickness and safety of work by a simple method in burying gas pipes, water and sewer pipes and the like. .

【0002】[0002]

【従来の技術】従来、この種の土留工法は、特公昭55
−32128号公報に示されるようなものが提案されて
いる。即ち、このものは、両側端にこれと摺接する水止
部材を設けた連結具をその上端部を突出させて嵌着した
2枚の土留板を、両端にスライド用車輪を配設した伸縮
自在の適宜数のサポーターによってあらかじめ末広がり
状に所望間隔を保持して起立させた後、この土留板間の
地面を掘削して土留板を自重により沈下させ、土留板の
沈下に伴う土圧に応じ下方のサポーターを操作してその
長さを徐々に縮めて、上下のサポーターを平行に維持し
ながら土留めするように構成したものである。
2. Description of the Related Art Conventionally, this type of earth retaining method is disclosed in Japanese Examined Patent Publication Sho 55.
The one disclosed in Japanese Patent No. 32128 has been proposed. In other words, this is an expandable / contractible type that has two earth retaining plates fitted with connecting members provided with water stop members slidingly contacting the both ends with their upper ends protruding, and sliding wheels provided at both ends. After standing up with a desired number of supporters in a divergent manner at predetermined intervals in advance, excavate the ground between the earth retaining plates and let the earth retaining plates sink by their own weight, and move downward depending on the earth pressure due to the sinking of the earth retaining plates. The supporter is operated to gradually reduce its length, and the upper and lower supporters are kept parallel while retaining the soil.

【0003】[0003]

【発明が解決しようとする課題】しかし、かかる土留工
法にあっては、ガス管、上・下水道管等の埋設工事にお
いて、他の既埋設物(ガス管、上・下水道管等)が掘削
断面を横切って存在している場合には、土留板の先端部
が既埋設物に当たりそれ以上下に建込むことができず、
埋設工事の進行に支障を来すといった問題点を生じてい
た。
However, in the earth retaining method, other existing buried objects (gas pipes, water / sewer pipes, etc.) are excavated in the digging section in the burial work for gas pipes, water / sewer pipes, etc. If it exists across, the tip of the retaining plate cannot hit the existing buried object and cannot be built below it.
There was a problem that it hindered the progress of the burial work.

【0004】また、このものは、掘削溝内で連結具に土
留板を嵌合させて土留用ボックスを組立てるように構成
されるので、掘削溝内での組立て作業が捗らず作業の迅
速性に欠けることになる。更に、土留壁を形成する土留
板は1枚板で大きいために、保管するための大きなスペ
ースが必要となる欠点がある。
Further, since this structure is constructed such that the earth retaining box is assembled by fitting the earth retaining plate to the connecting tool in the excavation groove, the assembling work in the excavation groove does not progress and the work speed is increased. Will be missing. Further, since the earth retaining plate forming the earth retaining wall is large by one plate, there is a drawback that a large space for storage is required.

【0005】また、図13及び図14に示すように、所
望深さに亘って地面を掘削した後、該掘削溝A内に土留
部材を建込んで徐々に掘り進んでいく土留工法も一般に
行われている。即ち、このものは、図14(a)〜
(c)に示すように、掘削深さに応じて土留部材の深さ
方向の数を増加させて建込んでいくもので、所望深さに
亘って地面を掘削した掘削溝A内の側壁部に矢板1を建
込み該矢板1を腹起し材2で押さえながら切梁材3で固
定するものである。尚、矢板1は、掘削溝深さが深い程
木矢板よりも土圧に十分耐えうる鋼矢板が使用される。
Further, as shown in FIGS. 13 and 14, after excavating the ground to a desired depth, an earth retaining member is installed in the excavation groove A and the earth retaining method is gradually performed. It is being appreciated. That is, this is shown in FIG.
As shown in (c), the number of soil retaining members in the depth direction is increased according to the excavation depth to build up, and the sidewall portion in the excavation groove A excavating the ground over a desired depth. The sheet pile 1 is built in and the sheet pile 1 is fixed by the beam member 3 while raising the sheet pile 1 and pressing it with the material 2. As the sheet pile 1, a steel sheet pile that can withstand more earth pressure than a wooden sheet pile is used as the excavation groove depth is deeper.

【0006】しかし、このものでは、所定深さまで掘削
した後、掘削溝A内に作業員が入って土留部材(矢板
1、腹起し材2、切梁材3等)を設置することになるた
め、設置作業中に土砂が崩壊して作業員が生き埋めにな
る危険があり十分な安全性を確保することができないと
いった問題点を生じていた。本発明は、このような従来
の問題点に鑑みなされたものであり、簡易な工法であり
ながら作業の迅速性及び安全性に優れた土留工法及び土
留用ボックスを提供することを目的とする。
However, in this device, after excavating to a predetermined depth, the worker enters the excavation groove A and installs the earth retaining member (the sheet pile 1, the uprising member 2, the cutting beam member 3, etc.). Therefore, there is a problem that the earth and sand may collapse during the installation work and the workers may be buried alive, and sufficient safety cannot be ensured. The present invention has been made in view of such conventional problems, and an object of the present invention is to provide an earth retaining method and an earth retaining box which are simple construction methods and are excellent in quickness and safety of work.

【0007】[0007]

【課題を解決するための手段】このため、請求項1に記
載の発明は、所望深さに亘って掘削した掘削溝内に、予
め一対の縦部材間に横部材を橋渡して形成した一対の土
留壁枠を掘削溝幅と略同等の間隔を開けて連結部材で結
合してなる土留用ボックスを建込んだ後、前記土留用ボ
ックスの横部材に穿設された複数の貫通孔に矢板を所望
間隔を開けて差し込んで土留側壁を形成し、その後前記
掘削溝を更に堀り進んで、徐々にボックス全体を沈降さ
せて土留するようにした構成とする。
Therefore, according to the first aspect of the present invention, a pair of vertical members are previously formed by bridging a horizontal member between a pair of vertical members in a trench excavated to a desired depth. After building a box for retaining soil by connecting the retaining wall frame with a connecting member at an interval approximately equal to the excavation groove width, insert sheet piles into the through holes formed in the lateral member of the retaining box. The soil retaining side wall is formed by inserting the soil at a desired interval, and then the excavation trench is further dug to gradually settle the whole box to retain the soil.

【0008】また、掘削溝深さに応じて前記土留用ボッ
クスを複数重ねて沈降させて土留するようにすることも
できる。また、請求項3に記載の発明は、一対の縦部材
間に横部材を橋渡して土留壁枠を形成すると共に、該一
対の土留壁枠を掘削溝幅と略同等の間隔を開けて連結部
材で結合してボックスを形成し、前記横部材に複数の矢
板を所望間隔を開けて差し込むための貫通孔を穿設した
構成とする。
It is also possible to stack a plurality of the soil retaining boxes in accordance with the depth of the excavation groove and settle them to retain the soil. In the invention according to claim 3, the horizontal members are bridged between the pair of vertical members to form the earth retaining wall frame, and the pair of earth retaining wall frames are provided with a spacing substantially equal to the excavation groove width to connect the connecting members. To form a box, and through holes for inserting a plurality of sheet piles at desired intervals are formed in the lateral member.

【0009】また、掘削溝深さに応じてボックスを複数
積み重ねて接続自由に形成することもできる。また、土
留壁枠と連結部材とが組立自由に分解して形成すること
もできる。
It is also possible to stack a plurality of boxes in accordance with the depth of the excavation groove and form them freely for connection. Further, the retaining wall frame and the connecting member can be formed by freely disassembling them.

【0010】[0010]

【作用】かかる構成によれば、所望深さに亘って掘削し
た掘削溝内に、予め組み立てられた土留用ボックスを建
込むと共に、横部材に穿設された複数の貫通孔に矢板を
所望間隔を開けて差し込んで土留側壁を形成し、その
後、掘削溝を堀り進みながら徐々にボックス全体を沈降
させて土留をしつつ、例えば、ガス管、上・下水道管等
の埋設工事を行うことができる。
According to this construction, the pre-assembled earth retaining box is installed in the excavation trench excavated to the desired depth, and the sheet piles are provided at the desired intervals in the plurality of through holes formed in the lateral member. Opening and inserting to form a retaining wall, and then gradually excavating the excavation ditch to settle the entire box and retain soil, for example, burying construction of gas pipes, water and sewer pipes, etc. it can.

【0011】このように、所望深さに亘って掘削した掘
削溝内に、予め組み立てられた土留用ボックスを直接建
込み、その上から矢板を差し込んで土留側壁を形成する
ように構成されるので、掘削溝内に作業員が入って土留
部材(矢板、腹起し材、切梁材等)を設置する必要はな
く、作業の安全性を確保することができる。また、土留
用ボックスを建込み、人力により軽量な矢板を差し込む
だけで土留側壁が形成されるので、掘削溝内での組立作
業が不要となり、以て、作業の迅速性を確保することが
できる。
As described above, the pre-assembled soil retaining box is directly built in the excavation trench excavated to the desired depth, and the sheet pile is inserted from above to form the soil retaining side wall. It is not necessary for an operator to enter the excavation trench to install a clasp member (such as a sheet pile, an upholstery material, a cutting beam material), and work safety can be ensured. In addition, since the soil retaining side wall is formed simply by constructing the soil retaining box and manually inserting a lightweight sheet pile, the assembly work in the excavation trench is unnecessary, and thus the promptness of the work can be secured. .

【0012】また、複数の矢板を所望間隔を開けて独立
に差し込むように構成されるので、他の既埋設物(ガス
管、上・下水道管等)が掘削断面を横切って存在してい
る場合においても、差し込んで先端部が既埋設物に当た
る矢板はそのままにしておいて、他の矢板を差し込んで
土留側壁を形成することができ、埋設工事の進行に支障
を来すことはなく、既埋設物の上部位置の土留も確保す
ることができる。
Since a plurality of sheet piles are independently inserted at desired intervals, other existing buried objects (gas pipes, water / sewer pipes, etc.) exist across the excavated cross section. Also, even if you insert it and leave the sheet pile whose tip hits the already buried object, you can insert the other sheet pile to form the retaining wall, which will not hinder the progress of the burial work. It is also possible to secure soil retaining at the upper position of the object.

【0013】また、土留用ボックスを複数重ねて沈降さ
せて土留するようにした場合には、埋設工事の掘削溝深
さに応じて土留することができる。また、土留壁枠と連
結部材とが組立自由に分解して形成した場合には、嵩張
ることがないので、保管スペースが十分確保できると共
に、埋設現場までの搬送が容易となる。
When a plurality of earth retaining boxes are piled up and settled down to retain the soil, the soil can be retained according to the depth of the excavation groove in the burial work. Further, when the soil retaining wall frame and the connecting member are formed by disassembling and assembling freely, they do not become bulky, so that a sufficient storage space can be secured and transportation to the burying site becomes easy.

【0014】[0014]

【実施例】以下に、本発明の実施例を図に基づいて説明
する。先ず、図1〜図4において、本発明に係る土留工
法に使用される土留用ボックスの構造について説明す
る。即ち、一対の縦部材11a,11b間に2本の横部
材12,12が橋渡されて結合され土留壁枠13が形成
される。この縦部材11a,11bは、H型断面を有す
ると共に下端が鋭角に形成され掘削溝への沈降を容易と
している。また、横部材12,12の上面には、複数の
矢板14を所望間隔を開けて差し込むための貫通孔12
aが穿設されている。
Embodiments of the present invention will be described below with reference to the drawings. First, referring to FIGS. 1 to 4, the structure of the earth retaining box used in the earth retaining method according to the present invention will be described. That is, the two horizontal members 12, 12 are bridged and connected between the pair of vertical members 11a, 11b to form the earth retaining wall frame 13. The vertical members 11a and 11b have an H-shaped cross section and are formed with an acute lower end to facilitate sinking into the excavation trench. Further, through holes 12 for inserting a plurality of sheet piles 14 at desired intervals are formed on the upper surfaces of the lateral members 12, 12.
a is provided.

【0015】そして、一対の土留壁枠13,13を掘削
溝幅と略同等の間隔を開けて連結部材15で結合して土
留用ボックス10が形成される。土留用ボックス10
は、伸縮調整自在な切梁ジャッキ等で構成される連結部
材15及び土留壁枠13,13と共に分解した状態で埋
設工事現場まで搬送され、現場で組み立てられる。この
ボックス組み立てにあたっては、図5に示すようなスタ
ンド16に土留壁枠13を設置した状態で行うと、倒れ
ることがないので、安全に組立作業を行うことができ
る。
Then, the pair of soil retaining wall frames 13 and 13 are connected with a connecting member 15 at an interval substantially equal to the excavation groove width to form the soil retaining box 10. Box 10 for soil retention
Is transported to the burying construction site in a disassembled state together with the connecting member 15 and the earth retaining wall frames 13, 13 which are composed of a cut beam jack whose expansion and contraction are adjustable, and is assembled there. When assembling this box, if the soil retaining wall frame 13 is installed on the stand 16 as shown in FIG. 5, it will not fall down, so that the assembly work can be performed safely.

【0016】矢板14は、図6に示すように短冊状に形
成され、掘削溝深さに応じて木矢板又は鋼矢板が使用さ
れる。次に、図7に基づき、本発明に係る土留工法につ
いて説明する。先ず、地面を所望深さ(約1m前後)に
亘って掘削して掘削溝Aを形成し、該掘削溝A内に、予
め組み立てておいた土留用ボックス10をバックホー等
の建設機械により吊り下ろして設置する(図7(a)参
照)。
The sheet pile 14 is formed in a strip shape as shown in FIG. 6, and a wooden sheet pile or a steel sheet pile is used according to the depth of the excavation groove. Next, the earth retaining method according to the present invention will be described with reference to FIG. First, the ground is excavated to a desired depth (about 1 m) to form an excavation groove A, and the earth retaining box 10 previously assembled is hung in the excavation groove A by a construction machine such as a backhoe. (See FIG. 7A).

【0017】次に、矢板14を貫通孔12aに所望間隔
を開けて、例えば1枚とびに横部材12に穿設された貫
通孔12aに差し込んでいく(図7(b)参照)。この
場合、土質に応じて、例えば脆い砂質土であれば、矢板
14を全面に差し込んで補強を行う。尚、矢板14は、
掘削溝深さが浅い場合には木矢板が使用され、軽量であ
るために人力により設置及び撤去が行われる。また、掘
削溝深さが深い場合には鋼矢板が使用され、適宜バック
ホー等により設置及び撤去を行う。
Next, the sheet piles 14 are inserted into the through holes 12a at desired intervals, and are inserted into the through holes 12a formed in the lateral member 12 one by one (see FIG. 7B). In this case, depending on the soil quality, for example, in the case of brittle sandy soil, the sheet pile 14 is inserted over the entire surface for reinforcement. The sheet pile 14 is
When the depth of the excavation trench is shallow, wood sheet piles are used. Since it is lightweight, it is installed and removed manually. If the excavation groove is deep, steel sheet piles will be used, and they will be installed and removed by a backhoe, etc. as appropriate.

【0018】次に、バックホー等により掘削溝Aを更に
堀り進んでいく(図7(c)参照)。その後、土留用ボ
ックス10及び矢板14をバックホーで押し込み徐々に
全体を沈降させていき土留が完了する(図7(d)参
照)。尚、図8に示すように、バックホーで押し込む際
の破損を防止するためにプレッシャーフード17を縦部
材11aの上端に被せて行うと良い。
Next, the excavation groove A is further dug by a backhoe or the like (see FIG. 7C). After that, the soil retaining box 10 and the sheet pile 14 are pushed in by the backhoe to gradually settle the whole and soil retaining is completed (see FIG. 7 (d)). It should be noted that, as shown in FIG. 8, it is preferable to cover the upper end of the vertical member 11a with the pressure hood 17 in order to prevent damage when pushing it with the backhoe.

【0019】そして、最後にガス管、上・下水道管等の
埋設管を埋設し、土砂を埋戻し締固めながら土留用ボッ
クス10及び矢板14をバックホーで引抜いていく。こ
のように、土留用ボックス10を建込み、人力により軽
量な矢板14を差し込むだけで土留側壁が形成されるの
で、掘削溝A内での組立作業が不要となり、作業の迅速
性を確保することができる。
Finally, buried pipes such as a gas pipe and a water supply / sewer pipe are buried, and the earth retaining box 10 and the sheet pile 14 are pulled out by a backhoe while backfilling and compacting the earth and sand. As described above, since the soil retaining side wall is formed only by constructing the soil retaining box 10 and inserting the lightweight sheet pile 14 by human power, the assembling work in the excavation groove A becomes unnecessary, and the promptness of the work is ensured. You can

【0020】また、所望深さに亘って掘削した掘削溝A
内に、予め組み立てられた土留用ボックス10を直接建
込み矢板14を差し込んで土留側壁を形成するように構
成されるので、掘削溝A内に作業員が入って土留部材
(矢板、腹起し材、切梁材等)を設置する必要はなく、
作業の安全性を確保することができる。次に、図9及び
図10に基づき他の実施例について説明する。
Further, the excavation groove A excavated to a desired depth
Since the pre-assembled soil retaining box 10 is directly installed therein to form the soil retaining side wall by inserting the sheet pile 14, the worker enters the excavation groove A to store the soil retaining member (sheet pile, abdomen upright). Material, wood beams, etc.)
Work safety can be secured. Next, another embodiment will be described with reference to FIGS. 9 and 10.

【0021】即ち、このものは、土留用ボックスを複数
重ねて沈降させて土留するようにしたもので、土留用ボ
ックス10a,10bが接続プレート18を介してボル
トにより接続されている。これによると、埋設工事の掘
削溝深さに応じて適宜土留用ボックス10a,10bを
複数重ねて土留を行うことができる。
That is, this is one in which a plurality of soil retaining boxes are piled up and settled down to retain the soil, and the soil retaining boxes 10a and 10b are connected by bolts via the connection plate 18. According to this, soil retention can be performed by appropriately stacking a plurality of soil retention boxes 10a and 10b according to the depth of the excavation groove in the burial work.

【0022】次に、図11及び図12に基づき他の実施
例について説明する。即ち、このものは、他の既埋設物
(ガス管、上・下水道管等)が掘削断面を横切って存在
している場合の例であり、土留用ボックス10の沈降は
横部材12の下端面が既埋設物Bに当接する位置で止め
ると共に、既埋設物Bに当たる矢板14aもそのままに
しておいて、他の矢板14を差し込んで土留側壁を形成
するようにしたものであり、これによると既埋設物Bが
あっても埋設工事の進行に支障を来すことはなく、ま
た、既埋設物Bの上部位置の土留も矢板14aにより確
保することができる。
Next, another embodiment will be described with reference to FIGS. 11 and 12. That is, this is an example of the case where another existing buried object (gas pipe, water / sewer pipe, etc.) exists across the excavation cross section, and the sedimentation of the earth retaining box 10 is caused by the lower end surface of the lateral member 12. Is stopped at the position where it abuts the existing buried object B, and the sheet pile 14a that hits the existing buried article B is left as it is, and another sheet pile 14 is inserted to form the soil retaining side wall. Even if there is the buried object B, it does not hinder the progress of the burial work, and the soil retaining at the upper position of the existing buried object B can be secured by the sheet pile 14a.

【0023】[0023]

【発明の効果】以上説明したように、本発明によれば、
所望深さに亘って掘削した掘削溝内に、予め組み立てら
れた土留用ボックスを直接建込み、その上から矢板を差
し込んで土留側壁を形成するように構成されるので、掘
削溝内に作業員が入って土留部材を設置する必要はな
く、作業の安全性を確保することができる。
As described above, according to the present invention,
A pre-assembled soil retaining box is directly built in the excavation trench that has been excavated to a desired depth, and a sheet pile is inserted from above to form the soil retaining side wall. It is not necessary to install the soil retaining member after entering, and it is possible to ensure work safety.

【0024】また、土留用ボックスを建込み、人力によ
り軽量な矢板を差し込むだけで土留側壁が形成されるの
で、掘削溝内での組立作業が不要となり、以て、作業の
迅速性を確保することができる。また、複数の矢板を所
望間隔を開けて独立に差し込むように構成されるので、
他の既埋設物(ガス管、上・下水道管等)が掘削断面を
横切って存在している場合においても、差し込んで先端
部が既埋設物に当たる矢板はそのままにしておいて、他
の矢板を差し込んで土留側壁を形成することができ、埋
設工事の進行に支障を来すことはなく、既埋設物の上部
位置の土留も確保することができる。
Further, since the soil retaining side wall is formed only by constructing the soil retaining box and manually inserting the lightweight sheet pile, the assembling work in the excavation trench becomes unnecessary, thereby ensuring the promptness of the work. be able to. In addition, since it is configured to insert a plurality of sheet piles at desired intervals independently,
Even when other existing buried objects (gas pipes, water / sewer pipes, etc.) exist across the excavation cross section, leave the sheet pile whose tip is the already buried object and leave the other sheet piles open. The earth retaining wall can be formed by inserting it, so that it does not hinder the progress of the burial work, and it is possible to secure the earth retaining at the upper position of the existing buried object.

【0025】また、土留用ボックスを複数重ねて沈降さ
せて土留するようにした場合には、埋設工事の掘削溝深
さに応じて土留を行うことができる。また、土留壁枠と
連結部材とが組立自由に分解して形成した場合には、保
管スペースが十分確保できると共に、埋設現場までの搬
送が容易となる。
Further, when a plurality of earth retaining boxes are piled up and settled down for earth retaining, the earth retaining can be performed according to the depth of the excavation groove of the burial work. In addition, when the earth retaining wall frame and the connecting member are formed by being freely disassembled and formed, a sufficient storage space can be secured and transportation to the burial site becomes easy.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る土留用ボックスを示す斜視図。FIG. 1 is a perspective view showing an earth retaining box according to the present invention.

【図2】本発明に係る土留用ボックスを示す正面図。FIG. 2 is a front view showing a soil retaining box according to the present invention.

【図3】図2の側面図。FIG. 3 is a side view of FIG.

【図4】図2の平面図。FIG. 4 is a plan view of FIG.

【図5】本発明に係る土留用ボックスをスタンドを利用
して組み立てる状態を示す部分斜視図。
FIG. 5 is a partial perspective view showing a state where the soil retaining box according to the present invention is assembled using a stand.

【図6】本発明に係る土留工法に使用される矢板を示す
斜視図。
FIG. 6 is a perspective view showing a sheet pile used in the earth retaining method according to the present invention.

【図7】本発明に係る土留工法を示す工程図。FIG. 7 is a process drawing showing a soil retaining method according to the present invention.

【図8】プレッシャーフードを縦部材の上端に被せて土
留用ボックスを押し込む状態を示す部分斜視図。
FIG. 8 is a partial perspective view showing a state in which the upper end of the vertical member is covered with the pressure hood and the soil retaining box is pushed in.

【図9】本発明の他の実施例を示す断面図。FIG. 9 is a sectional view showing another embodiment of the present invention.

【図10】図9の側断面図。FIG. 10 is a side sectional view of FIG. 9.

【図11】本発明の他の実施例を示す断面図。FIG. 11 is a sectional view showing another embodiment of the present invention.

【図12】図11の側断面図。FIG. 12 is a side sectional view of FIG. 11.

【図13】従来例の土留工法を示す平面図。FIG. 13 is a plan view showing a conventional earth retaining method.

【図14】従来例の土留工法を示す側断面図。FIG. 14 is a side sectional view showing a conventional earth retaining method.

【符号の説明】[Explanation of symbols]

10 土留用ボックス 11a,b 縦部材 12 横部材 12a 貫通孔 13 土留壁枠 14 矢板 15 連結部材 16 スタンド 17 プレッシャーフード 18 接続プレート 10 Soil retaining box 11a, b Vertical member 12 Horizontal member 12a Through hole 13 Soil retaining wall frame 14 Sheet pile 15 Connecting member 16 Stand 17 Pressure hood 18 Connection plate

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】所望深さに亘って掘削した掘削溝内に、予
め一対の縦部材間に横部材を橋渡して形成した一対の土
留壁枠を掘削溝幅と略同等の間隔を開けて連結部材で結
合してなる土留用ボックスを建込んだ後、 前記土留用ボックスの横部材に穿設された複数の貫通孔
に矢板を所望間隔を開けて差し込んで土留側壁を形成
し、 その後前記掘削溝を更に堀り進んで、徐々にボックス全
体を沈降させて土留するようにしたことを特徴とする土
留工法。
1. A pair of earth retaining wall frames formed by bridging a horizontal member between a pair of vertical members in advance in a trench excavated to a desired depth with a gap substantially equal to the trench width being connected. After building the soil retaining box that is connected by members, insert sheet piles at desired intervals into a plurality of through holes formed in the transverse member of the soil retaining box to form the soil retaining side wall, and then perform the excavation. The earth retaining method is characterized in that the trench is further dug to gradually settle the whole box and retain the soil.
【請求項2】掘削溝深さに応じて土留用ボックスを複数
重ねて沈降させて土留するようにしたことを特徴とする
請求項1記載の土留工法。
2. The earth retaining method according to claim 1, wherein a plurality of earth retaining boxes are piled up in accordance with the depth of the excavation groove and settled to retain the soil.
【請求項3】一対の縦部材間に横部材を橋渡して土留壁
枠を形成すると共に、 該一対の土留壁枠を掘削溝幅と略同等の間隔を開けて連
結部材で結合してボックスを形成し、 前記横部材に複数の矢板を所望間隔を開けて差し込むた
めの貫通孔を穿設したことを特徴とする土留用ボック
ス。
3. A box is formed by bridging a lateral member between a pair of vertical members to form a retaining wall frame, and connecting the pair of retaining wall frames with a connecting member at an interval substantially equal to the excavation groove width. A box for retaining soil, characterized by being formed with through holes for inserting a plurality of sheet piles into the transverse member at desired intervals.
【請求項4】掘削溝深さに応じてボックスを複数積み重
ねて接続自由に形成されていることを特徴とする請求項
3記載の土留用ボックス。
4. The box for retaining soil according to claim 3, wherein a plurality of boxes are stacked in accordance with the depth of the excavation groove to be freely connected.
【請求項5】土留壁枠と連結部材とが組立自由に分解し
て形成されていることを特徴とする請求項3記載の土留
用ボックス。
5. The earth retaining box according to claim 3, wherein the earth retaining wall frame and the connecting member are formed by freely disassembling them.
JP5153329A 1993-06-24 1993-06-24 Earth retaining method and earth retaining box Expired - Lifetime JP2579584B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5153329A JP2579584B2 (en) 1993-06-24 1993-06-24 Earth retaining method and earth retaining box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5153329A JP2579584B2 (en) 1993-06-24 1993-06-24 Earth retaining method and earth retaining box

Publications (2)

Publication Number Publication Date
JPH0711649A true JPH0711649A (en) 1995-01-13
JP2579584B2 JP2579584B2 (en) 1997-02-05

Family

ID=15560116

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5153329A Expired - Lifetime JP2579584B2 (en) 1993-06-24 1993-06-24 Earth retaining method and earth retaining box

Country Status (1)

Country Link
JP (1) JP2579584B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7907285B2 (en) 2005-10-03 2011-03-15 Advantest Corporation Scattered light measuring device
JP6178030B1 (en) * 2017-02-28 2017-08-09 日本スピードショア株式会社 Prior construction method for earth retaining of excavation groove and supporting device used for the construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5532128A (en) * 1978-08-28 1980-03-06 Masatoshi Okada Automatic adjuster for water level
JPS5625744U (en) * 1979-08-03 1981-03-09

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5532128A (en) * 1978-08-28 1980-03-06 Masatoshi Okada Automatic adjuster for water level
JPS5625744U (en) * 1979-08-03 1981-03-09

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7907285B2 (en) 2005-10-03 2011-03-15 Advantest Corporation Scattered light measuring device
JP6178030B1 (en) * 2017-02-28 2017-08-09 日本スピードショア株式会社 Prior construction method for earth retaining of excavation groove and supporting device used for the construction method
JP2018141325A (en) * 2017-02-28 2018-09-13 日本スピードショア株式会社 Method for preliminarily constructing earth retaining wall of excavated ditch, and timbering device used in the same

Also Published As

Publication number Publication date
JP2579584B2 (en) 1997-02-05

Similar Documents

Publication Publication Date Title
KR101474515B1 (en) Earth retaining wall using support and panel, method for constructing the same
US4059964A (en) Sheeting installation system
JP5351125B2 (en) Open shield machine start method of open shield method
US3496727A (en) Apparatus for laying pipe
KR101862208B1 (en) Earth retaining wall structure and constructuon mothod thereof
JPH0711649A (en) Earth retaining method and earth retaining box
JP2021181751A (en) Reaction force structure and method for launching concrete box or open shield machine
JPS5847092Y2 (en) Earth retention shoring device for excavated trenches
JPS5847091Y2 (en) Earth retention shoring device for excavated trenches
JP5729712B1 (en) Earth retaining method and earth retaining unit
JPH0874257A (en) Earth retaining device for excavated groove
JP2018009393A (en) Earth retaining wall structure and construction method thereof
JP2876265B2 (en) Sheet pile for underground continuous wall and underground continuous wall method
KR100669530B1 (en) Construction method of a rataining well
JPH0989159A (en) Pipe line laying method, timbering method, and timbering assembling body
JPS5840609B2 (en) Earth retaining method
JPH0529248Y2 (en)
JP2876266B2 (en) Sheet pile for underground continuous wall and underground continuous wall method
JPH084009A (en) Method of supporting earth retaining sheet pile, and device therefor
KR101908690B1 (en) Soil guard installing structure
JP2584682Y2 (en) Work frame for excavation work
JPS59233028A (en) Residential land formation work on sloped ground
JP3314299B2 (en) Earth retaining device
JP2729911B2 (en) Retaining wall construction method and retaining wall block
JPS6310250B2 (en)