JP5729712B1 - Earth retaining method and earth retaining unit - Google Patents

Earth retaining method and earth retaining unit Download PDF

Info

Publication number
JP5729712B1
JP5729712B1 JP2014218314A JP2014218314A JP5729712B1 JP 5729712 B1 JP5729712 B1 JP 5729712B1 JP 2014218314 A JP2014218314 A JP 2014218314A JP 2014218314 A JP2014218314 A JP 2014218314A JP 5729712 B1 JP5729712 B1 JP 5729712B1
Authority
JP
Japan
Prior art keywords
excavation
construction
unit
work
excavation groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014218314A
Other languages
Japanese (ja)
Other versions
JP2016084623A (en
Inventor
英彦 早瀬
英彦 早瀬
Original Assignee
株式会社早瀬工業
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社早瀬工業 filed Critical 株式会社早瀬工業
Priority to JP2014218314A priority Critical patent/JP5729712B1/en
Application granted granted Critical
Publication of JP5729712B1 publication Critical patent/JP5729712B1/en
Publication of JP2016084623A publication Critical patent/JP2016084623A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

【課題】掘削溝を開削しつつ、掘削溝に隣接する施工空間に対して所定の施工作業を行う開削工事において、より確実に掘削溝の崩壊を防止し、安全な土留工法を提供する。【解決手段】地表30から作業用の掘削溝3を開削しつつ、掘削溝3に隣接する施工空間34に対して所定の施工作業を行う際の土留工法であって、掘削溝3の掘削壁面のうち、施工空間34に臨む施工面10を除く三面を覆う土留壁を有する土留ユニットを、開削の進行に伴って掘削溝3内に沈設し、土留ユニットにより施工面10以外の三面からの土圧Pを支えつつ、掘削溝3内から施工空間34に対して施工作業を行う。【選択図】図5The present invention provides a safe earth retaining method that more reliably prevents the excavation groove from collapsing in the excavation work in which a predetermined construction work is performed on a construction space adjacent to the excavation groove while excavating the excavation groove. A earth retaining method for performing a predetermined construction work on a construction space 34 adjacent to the excavation groove 3 while excavating the excavation groove 3 from the ground surface 30, wherein the excavation wall surface of the excavation groove 3 is provided. Among them, a soil retaining unit having a retaining wall covering three surfaces excluding the construction surface 10 facing the construction space 34 is set in the excavation groove 3 as the excavation progresses, and the soil from three surfaces other than the construction surface 10 is deposited by the soil retaining unit. While supporting the pressure P, construction work is performed on the construction space 34 from within the excavation groove 3. [Selection] Figure 5

Description

本発明は、例えばガス管や上下水道管との配管を地中に布設する場合など、地表から作業用の掘削溝を開削しつつ、掘削溝に隣接する施工空間に対して所定の施工作業を行う開削土木工事における土留工法、及びこれに用いられる土留ユニットに関するものである。   The present invention performs a predetermined construction work on a construction space adjacent to the excavation groove while opening the excavation groove for work from the ground surface, for example, when laying a pipe with a gas pipe or a water and sewage pipe in the ground. It is related with the earth retaining method in the open-cutting civil engineering work to be performed, and the earth retaining unit used therefor.

従来より、ガス管、石油導管、上下水道管等の配管や送電ケーブル、電話線、通信用光ファイバケーブルの保護管などを地中に布設する場合には、地上から開削により布設溝を掘削し、配管を布設、接合、検査、防食工事等を施した後、埋め戻し土により埋め戻すいわゆる開削工法が採用されることが多い。   Conventionally, when laying pipes such as gas pipes, oil pipes, water and sewage pipes, protective pipes for power transmission cables, telephone lines, and optical fiber cables for communication in the ground, excavating the laying grooves by excavation from the ground In many cases, a so-called open-cut method is employed in which pipes are laid, joined, inspected, and subjected to anticorrosion work and then backfilled with backfill soil.

この開削から埋め戻しまでの工事期間中、開削された掘削溝の側壁の崩壊を防止するために、例えば鋼製の矢板を溝の側面に沿って打設したのち、腹起しや切り梁などの支保工を所定の間隔に配置し、土圧に対する土留を行っていた。そして、一連の布設作業を行った後、掘削溝を埋戻しながら、切り梁、腹起し、矢板などを順次撤去する。これにより、掘削溝の壁面からの土圧を支持し、掘削面の崩壊を防止し、掘削溝内の作業の安全を確保することができる(例えば、特許文献1)。   In order to prevent the side walls of the excavated excavation groove from collapsing during the construction period from this excavation to backfilling, for example, a steel sheet pile is driven along the side of the excavation groove, and then the abdominal erection and cutting beam etc. The support works were placed at predetermined intervals to hold earth against earth pressure. Then, after performing a series of laying operations, the cut beams, upsets, sheet piles, and the like are sequentially removed while the excavation groove is backfilled. Thereby, the earth pressure from the wall surface of the excavation groove is supported, the collapse of the excavation surface can be prevented, and the safety of the work in the excavation groove can be ensured (for example, Patent Document 1).

特開平10−114946号公報Japanese Patent Laid-Open No. 10-114946

ところで、例えば、上述した配管の布設工事や検査等のメンテナンス作業などでは、図7に示すように、先行して埋設された本管33に対して支管35aの分岐取り出しをしたり、周囲の配管35b等による規制を回避しつつ支管35bを埋設したり等、狭隘な部分を開削する場合がある。この場合には、既存の構造物と干渉しないように開削溝3の掘削したり、施工面32aに対する施工を行う必要があり、上述したような矢板などの土留材を十分に地盤中に埋入させることができないケースもある。特に、市街地などのように既設構造物が複雑に配置されて集中している地盤では、本管33外周面の全部(360°)或いは一部(例えば90°〜180°)にコンクリート33aを打設して防護するときがあり、このようなときには、コンクリート33a部分に土留材を打込むことができない。また、これを避けて打込んだとしても、既設構造物の周囲の地盤では幾度も掘削及び埋戻しが繰り返されており、地盤が軟弱であるうえ十分な埋込深度を確保できないことから、十分な土留効果が得られないという問題がある。   By the way, for example, in the above-described piping laying work or maintenance work such as inspection, as shown in FIG. 7, the branch pipe 35a is taken out from the previously buried main pipe 33, or the surrounding piping is removed. There is a case where a narrow portion such as the branch pipe 35b is buried while the regulation by 35b or the like is avoided. In this case, it is necessary to excavate the cut groove 3 so as not to interfere with the existing structure or to perform construction on the construction surface 32a, and the earth retaining material such as the sheet pile as described above is sufficiently embedded in the ground. There are cases where it is not possible to do this. In particular, in a ground where existing structures are arranged in a complex manner such as an urban area, concrete 33a is applied to all (360 °) or a part (eg, 90 ° to 180 °) of the outer peripheral surface of the main pipe 33. There are times when it is installed and protected, and in such a case, it is not possible to drive the earth retaining material into the concrete 33a portion. Even if it is driven in avoiding this, excavation and backfilling are repeated many times on the ground around the existing structure, and the ground is soft and sufficient embedding depth cannot be secured. However, there is a problem that the soil retaining effect cannot be obtained.

そこで、本発明は、上記のような問題を解決するものであり、地表から作業用の掘削溝を開削しつつ、掘削溝に隣接する施工空間に対して所定の施工作業を行う際、より確実に掘削溝の崩壊を防止し、安全な土木作業を実現できる土留工法、及びこれに用いられる土留ユニットを提供することを目的とする。   Therefore, the present invention solves the above problems, and more reliably when performing a predetermined construction work on a construction space adjacent to the excavation groove while excavating the excavation groove for work from the ground surface. It is another object of the present invention to provide a soil retaining method capable of preventing the collapse of excavation grooves and realizing safe civil engineering work, and a soil retaining unit used therefor.

上記課題を解決するために、本発明は、地表から作業用の掘削溝を開削しつつ、掘削溝に隣接する施工空間に対して所定の施工作業を行う際の土留工法であって、
(1)掘削溝の掘削壁面のうち、施工空間に臨む施工面を除く三面を覆う土留壁を有する土留ユニットを、開削の進行に伴って掘削溝内に沈設する工程と、
(2)土留ユニットから施工面方向に向けて支持脚を突出させ、施工面側の掘削面から反力を得て、当該土留ユニットを支持する工程と、
(3)土留ユニットにより三面からの土圧を支えつつ、掘削溝内から施工空間に対して施工作業を行う工程と
を有する。
In order to solve the above problems, the present invention is a earth retaining method when performing a predetermined construction work on a construction space adjacent to the excavation groove while excavating the excavation groove for work from the ground surface,
(1) A step of sinking a soil retaining unit having a retaining wall covering three surfaces excluding the construction surface facing the construction space in the excavation groove in the excavation groove as the excavation progresses;
(2) a step of projecting the support leg from the soil retaining unit toward the construction surface direction, obtaining a reaction force from the excavation surface on the construction surface side, and supporting the soil retaining unit;
(3) A process of performing construction work on the construction space from within the excavation groove while supporting earth pressure from three sides by the earth retaining unit.

また、他の発明は、地表から作業用の掘削溝を開削しつつ、掘削溝に隣接する施工空間に対して所定の施工作業を行う際の土留工法において用いられる土留ユニットであって、
前記掘削溝の掘削壁面のうち、施工空間に臨む施工面を除く三面を覆う水平断面がコの字形の土留壁と、
前記土留壁から前記施工面方向に向けて突出され、施工面側の掘削面から反力を得て、土留壁を支持する支持脚と
を備える。
Further, another invention is a soil retaining unit used in a soil retaining method when performing a predetermined construction work on a construction space adjacent to the excavation groove while excavating the excavation groove for work from the ground surface,
Of the excavation wall of the excavation groove, a horizontal wall covering the three surfaces excluding the construction surface facing the construction space is a U-shaped retaining wall,
And a supporting leg that protrudes from the retaining wall toward the construction surface, obtains a reaction force from the excavation surface on the construction surface side, and supports the retaining wall.

これらの発明によれば、掘削溝の壁面のうち、施工面を除く三面の掘削面からの土圧を土留ユニットの土留壁で支持させるため、掘削面の崩壊を防止し、掘削溝内の作業の安全を確保することができる。このとき、土留ユニットの施工面は開放されていることから、土留ユニット内から施工面に対して、ガス管の布設工事等の作業を安全且つ容易に行うことができる。特に、土留ユニットから施工面方向に向けて支持脚を突出させ、施工面側の掘削面から反力を得て、当該土留ユニットを支持することから、周囲の土圧が偏って作用した場合であっても、土留ユニットが転倒したり、滑動したりするのを防止できる。   According to these inventions, since the earth pressure from the three excavation surfaces excluding the construction surface is supported by the earth retaining wall of the earth retaining unit among the wall surfaces of the excavation groove, the excavation surface is prevented from collapsing and the work in the excavation groove is performed. Can be secured. At this time, since the construction surface of the soil retaining unit is open, operations such as gas pipe laying work can be performed safely and easily from the interior of the soil retaining unit to the construction surface. In particular, the support legs are projected from the soil retaining unit toward the construction surface, and the reaction force is obtained from the excavation surface on the construction surface side to support the soil retaining unit. Even if it exists, it is possible to prevent the earth retaining unit from falling over or sliding.

以上述べたように、この発明によれば、ガス管や上下水道管等の配管などを地中に布設する場合など、地表から作業用の掘削溝を開削しつつ、掘削溝に隣接する施工空間に対して所定の施工作業を行う際、支持脚により、施工面側の掘削面から反力を得て、土留ユニットが転倒したり、滑動したりするのを防止でき、より確実に掘削溝の崩壊を防止し、安全な土木作業を実現できる。   As described above, according to the present invention, the construction space adjacent to the excavation groove while excavating the work excavation groove from the ground surface, such as when laying pipes such as gas pipes and water and sewage pipes in the ground, etc. When carrying out the prescribed construction work, the support legs can obtain reaction force from the excavation surface on the construction surface side, preventing the earth retaining unit from overturning or sliding, and more reliably Collapse can be prevented and safe civil engineering work can be realized.

実施形態に係る土留ユニットの外観を示す斜視図である。It is a perspective view which shows the external appearance of the earth retaining unit which concerns on embodiment. 実施形態に係る土留ユニットの分解した状態を示す斜視図である。It is a perspective view which shows the state which the earth retaining unit which concerns on embodiment decomposed | disassembled. 実施形態に係る土留ユニットの支持脚を示す側面図である。It is a side view which shows the support leg of the earth retaining unit which concerns on embodiment. 実施形態に係る土留ユニットの支持脚のみを示す斜視図である。It is a perspective view which shows only the support leg of the earth retaining unit which concerns on embodiment. 実施形態に係る開削工法の手順を模式的に示す説明図である。It is explanatory drawing which shows typically the procedure of the cutting method which concerns on embodiment. 実施形態に係る開削工法の手順を示す側断面図である。It is a sectional side view which shows the procedure of the cut-opening method concerning embodiment. 一般的な開削工事で行われる支管の分岐取り出し工事の概要を示す上面図である。It is a top view which shows the outline | summary of the branch taking-out work of the branch pipe performed by a general excavation work.

以下に添付図面を参照して、本発明に係る土留工法の実施形態を詳細に説明する。なお、本実施形態では、本発明の土留ユニットを、先行して埋設された本管から支管を分岐取り出しする工事に適用する場合を例に説明するが、本発明はこれに限定されるものではなく、例えば、ガス管、石油導管、上下水道管等の配管や送電ケーブル、電話線、通信用光ファイバケーブルの保護管など、あらゆる構造物を地中に布設する場合等、開削工事全般に適用可能である。   Hereinafter, embodiments of the earth retaining method according to the present invention will be described in detail with reference to the accompanying drawings. In the present embodiment, the earth retaining unit of the present invention is described as an example applied to a construction for branching out a branch pipe from a main pipe that has been buried in advance, but the present invention is not limited to this. Applicable to all open-cut work such as pipes such as gas pipes, oil pipes, water and sewer pipes, power cables, telephone lines, protective pipes for optical fiber cables for communication, etc. Is possible.

(土留ユニットの構成)
図1は、本実施形態に係る土留工法で用いられる土留ユニット1の外観を示す斜視図であり、図2は、土留ユニットの分解した状態を示す斜視図である。
(Composition of the soil retaining unit)
FIG. 1 is a perspective view showing an appearance of a soil retaining unit 1 used in the soil retaining method according to the present embodiment, and FIG. 2 is a perspective view showing an exploded state of the soil retaining unit.

土留ユニット1は、開削工法において開削された掘削溝内に沈設されて、掘削溝の掘削面の崩壊を防止する土留用の仮設構造物であり、単位ユニット11,12,13を積み重ねることにより、掘削溝の深さに対応させることができる。具体的に、この土留ユニット1は、上部、中部、下部の3つの単位ユニット11,12,13を垂直方向に積み重ねて組み上げるようになっている。本実施形態では、下部ユニット13の高さを、他の上部ユニット11及び中部ユニット12の高さよりも高くし、下部における安定を図っている。   The earth retaining unit 1 is a temporary structure for earth retaining which is set in the excavation groove excavated by the excavation method and prevents the excavation surface of the excavation groove from collapsing. By stacking the unit units 11, 12 and 13, It can correspond to the depth of the excavation groove. Specifically, the earth retaining unit 1 is constructed by stacking three unit units 11, 12, and 13 of an upper part, a middle part, and a lower part in a vertical direction. In the present embodiment, the height of the lower unit 13 is set higher than the heights of the other upper unit 11 and the middle unit 12 to stabilize the lower part.

各単位ユニットは、それぞれ土留壁112a,112b,122a,122b,132a,132bを有し、掘削溝3の掘削壁面のうち、施工空間34に臨む面を除く三面を覆うとともに、隣接する施工空間34に対して施工作業を行うための開放面(施工面10)を有し、水平断面がコの字形状に形成されている。この施工面10には、対向配置された土留壁112b、122b、132b間に掛け渡されるように、スペーサー116,126,136が設けられ、両側方からの土圧を支えるようになっている。   Each unit unit has a retaining wall 112a, 112b, 122a, 122b, 132a, 132b, covers three surfaces of the excavation wall surface of the excavation groove 3 except the surface facing the construction space 34, and is adjacent to the construction space 34. Has an open surface (construction surface 10) for performing construction work, and a horizontal section is formed in a U-shape. Spacers 116, 126, and 136 are provided on the construction surface 10 so as to be spanned between the retaining walls 112b, 122b, and 132b arranged to face each other, and support earth pressure from both sides.

また、各単位ユニット11〜13は、垂直方向に連結される柱部材であるポスト部113a,113b,123a,123b,133a,133bをそれぞれ有し、これらポスト部の間に上記土留壁112a,112b,122a,122b,132a,132bが配置されている。土留壁112a〜132bは鋼鉄製の板状部材であり、また、各ポスト部113a〜133bの上端部には、上方に載置される単位ユニットのポスト部に嵌め込まれる嵌合部114a,114b,124a,124b,134a,134bが取付けられている。   Each of the unit units 11 to 13 has post portions 113a, 113b, 123a, 123b, 133a, and 133b that are column members connected in the vertical direction, and the earth retaining walls 112a and 112b are interposed between these post portions. , 122a, 122b, 132a, 132b are arranged. The retaining walls 112a to 132b are plate members made of steel, and fitting portions 114a and 114b that are fitted into the post portions of the unit units placed on the upper ends of the post portions 113a to 133b, 124a, 124b, 134a, 134b are attached.

なお、これらの嵌合部のうち最上部に位置される114a,114bには、その上面部分に水平な板部材であるプレッシャーフード111が取付けられている。このプレッシャーフード111は、嵌合部114a,114bの上端に強固に固着されており、このプレッシャーフード111を重機等で下方に押圧することにより、単位ユニットを沈降させることができる。また、最下層に位置される下部ユニット13のポスト部133a及び133bの下端部には、地中内に埋入させるカッティングシュー135a及び135bが取付けられている。   In addition, the pressure hood 111 which is a horizontal board member is attached to the upper surface part in 114a, 114b located in the uppermost part among these fitting parts. The pressure hood 111 is firmly fixed to the upper ends of the fitting portions 114a and 114b, and the unit unit can be settled by pressing the pressure hood 111 downward with a heavy machine or the like. Further, cutting shoes 135a and 135b to be embedded in the ground are attached to the lower ends of the post portions 133a and 133b of the lower unit 13 positioned at the lowermost layer.

さらに、土留ユニット1の下部には、施工面10方向に向けて突出された一対の支持脚2,2を備えており、これら支持脚2,2により施工面10側の掘削面32aから反力を得て、当該土留ユニット1を支持して、転倒や滑動を抑えている。図3及び図4に、この支持脚2,2を拡大して示す。   Furthermore, a pair of support legs 2 and 2 projecting toward the construction surface 10 are provided at the lower part of the soil retaining unit 1, and the reaction force from the excavation surface 32a on the construction surface 10 side by these support legs 2 and 2 is provided. And supporting the soil retaining unit 1 to suppress the fall and sliding. 3 and 4 show the support legs 2 and 2 in an enlarged manner.

これら支持脚2,2は、下部ユニット13のポスト部133b,133bにそれぞれ取付けられる支持構造であり、ポスト部133bの下端に回動可能に取付けられる脚部22と、脚部22の固定端側とポスト部133bとを連結して突っ張ることにより土留ユニット1を支持する支持アーム21と、脚部22の先端側に保持される杭23とから概略構成される。   These support legs 2 and 2 are support structures that are respectively attached to the post portions 133b and 133b of the lower unit 13, and a leg portion 22 that is rotatably attached to the lower end of the post portion 133b, and a fixed end side of the leg portion 22 And the post part 133b are connected and stretched to roughly support the earth retaining unit 1 and a pile 23 held on the distal end side of the leg part 22.

また、ポスト部133bの下側には、挿通孔を有するフランジ136bが突設されており、脚部22の後端側には、挿通孔を有する係合部22bが形成されており、これらフランジ136bと係合部22bの挿通孔を揃えた状態で、円筒状のピン137bを挿通することで、これらフランジ136bと係合部22bとが回動可能に係合され、脚部22がポスト部133bに対して回動可能に連結される。一方、ポスト部133bの上側には、挿通孔を有するフランジ136aが突設され、支持アーム21の後端側には、挿通孔を有する係合部21aが形成されており、これらフランジ136aと係合部21aの挿通孔を揃えた状態で、円筒状のピン137aを挿通することで、これらフランジ136aと係合部21bとが回動可能に係合され、支持アーム21がポスト部133bに対して回動可能に連結される。   Further, a flange 136b having an insertion hole protrudes below the post portion 133b, and an engagement portion 22b having an insertion hole is formed on the rear end side of the leg portion 22, and these flanges are formed. With the insertion holes of 136b and the engaging portion 22b being aligned, the cylindrical pin 137b is inserted so that the flange 136b and the engaging portion 22b are pivotally engaged, and the leg portion 22 is the post portion. It is rotatably connected to 133b. On the other hand, a flange 136a having an insertion hole protrudes above the post portion 133b, and an engagement portion 21a having an insertion hole is formed on the rear end side of the support arm 21, and is engaged with the flange 136a. By inserting the cylindrical pin 137a in a state where the insertion holes of the joint portion 21a are aligned, the flange 136a and the engaging portion 21b are rotatably engaged, and the support arm 21 is attached to the post portion 133b. And are pivotally connected.

他方、脚部22には、その長手方向に沿って複数の挿通孔22cが配列され、支持アーム21の先端側には、挿通孔を有する係合部21aが形成されており、これら脚部22の挿通孔22cを選択し、それに支持アーム21側係合部21aの挿通孔を揃えた状態で、円筒状のピン21cを挿通することで、支持アーム21が脚部22に対して連結される。このとき、挿通孔22cを適宜選択することにより、脚部22の取付角度が変化されることとなる。さらに、脚部22の先端部には、筒状の円筒部22aが固着されており、この円筒部22aに杭23を挿通することにより、杭23が脚部22の先端に固定される。   On the other hand, a plurality of insertion holes 22 c are arranged along the longitudinal direction of the leg portion 22, and an engagement portion 21 a having an insertion hole is formed on the distal end side of the support arm 21. The support arm 21 is connected to the leg portion 22 by inserting the cylindrical pin 21c in a state in which the insertion hole 22c is selected and the insertion hole of the support arm 21 side engagement portion 21a is aligned therewith. . At this time, the attachment angle of the leg portion 22 is changed by appropriately selecting the insertion hole 22c. Further, a cylindrical cylindrical portion 22 a is fixed to the distal end portion of the leg portion 22, and the pile 23 is fixed to the distal end of the leg portion 22 by inserting the pile 23 into the cylindrical portion 22 a.

(土留工法の手順)
このような構成の土留ユニット1を用いた土留工法は以下の手順による。図5は、本実施形態に係る開削工法における土留工法の手順を模式的に示す説明図であり、図6は、その側断面図である。また、図7は、開削工事で行われる支管の分岐取り出し工事の概要を示す上面図である。
(Procedure of earth retaining method)
The earth retaining method using the earth retaining unit 1 having such a configuration is as follows. FIG. 5 is an explanatory view schematically showing a procedure of the earth retaining method in the open-cut method according to the present embodiment, and FIG. 6 is a side sectional view thereof. FIG. 7 is a top view showing an outline of the branch pipe branching work performed in the excavation work.

本実施形態に係る土留工法は、地表から掘削溝3を開削しつつ、掘削溝3に隣接する施工空間34に対して所定の施工作業を行う開削工法において実施される。詳述すると、ここでは、図6及び図7に示すように、先行して布設されている本管33に対して、支管35aを接続する工事を、施工空間34に対して行うべく、掘削溝3を開削する。掘削溝3は、本管33上の分岐取りだし部分周囲から、支管35aの布設範囲(施工空間34)に亘って順次掘削される。この本管33は、基礎コンクリート33b上に配設されており、本管33の外周は、場合によってその一部又は全部コンクリート33aで防護されれている(図示した例では、外周の180°部分が防護されている。)。このため、この本管33が布設されている範囲は、矢板等の土留材を打込むことができず、或いは打込んだとしても本管33周囲の地盤で十分な深さ及び反力が得られず、従来の土留工法を用いることが困難となっている。   The earth retaining method according to the present embodiment is implemented in an excavation method in which a predetermined construction work is performed on the construction space 34 adjacent to the excavation groove 3 while excavating the excavation groove 3 from the ground surface. More specifically, here, as shown in FIGS. 6 and 7, in order to perform construction for connecting the branch pipe 35 a to the main pipe 33 laid in advance, the excavation groove 34 is performed. 3 is excavated. The excavation groove 3 is sequentially excavated from the periphery of the branch extraction portion on the main pipe 33 over the installation range (construction space 34) of the branch pipe 35a. The main pipe 33 is disposed on the foundation concrete 33b, and the outer periphery of the main pipe 33 is protected by a part or all of the concrete 33a in some cases (in the illustrated example, a 180 ° portion of the outer periphery). Is protected.) For this reason, in the range where the main pipe 33 is laid, it is not possible to drive in a retaining material such as a sheet pile, or even if it is driven, sufficient depth and reaction force are obtained in the ground around the main pipe 33. Therefore, it is difficult to use the conventional earth retaining method.

本実施形態に係る土留工法では、先ず、地表30からバックホウ等の重機4により掘削溝3を開削する。この掘削溝3は、作業用の掘削溝であり、本管33上に位置される作業溝31と、作業溝31から地中の施工空間34に至る開削溝32とから形成され、本実施形態では、作業溝31内から施工空間34に臨む施工面10を通じて、開削溝32の掘削面32aに、支管35aを埋設する作業を行う。なお、図5及び図6に示した例では、既に地中に本管33が埋設されており、この本管33の上方に作業溝31を掘削するとともに、施工空間34中にも、先行して既設管35bが埋設されており、この既設管35bの下方を通過するように支管35aを埋設し、本管33に接続する。   In the earth retaining method according to the present embodiment, first, the excavation groove 3 is excavated from the ground surface 30 by a heavy machine 4 such as a backhoe. This excavation groove 3 is an excavation groove for work, and is formed by a work groove 31 located on the main pipe 33 and an excavation groove 32 extending from the work groove 31 to the underground construction space 34, and this embodiment. Then, the operation of burying the branch pipe 35a in the excavation surface 32a of the cut groove 32 through the work surface 10 facing the work space 34 from the work groove 31 is performed. In the example shown in FIGS. 5 and 6, the main pipe 33 is already buried in the ground, and the working groove 31 is excavated above the main pipe 33 and also in the construction space 34. The existing pipe 35 b is buried, and the branch pipe 35 a is buried so as to pass below the existing pipe 35 b and connected to the main pipe 33.

そして、掘削溝3の開削の進行に伴い、土留ユニット1の単位ユニット11〜13を順次沈設していく。具体的には、開削の初期段階で下部ユニット13を作業溝31部分に沈設し、開削深度が深くなるに伴い、下部ユニット13を重機4で下方に押し込んで沈降させ、その上部に次の中部ユニット12を載置し、さらに重機4で下方に押し込んで沈降させる。同様にして、上部ユニット11を載せて沈降させることにより、作業溝31の掘削壁面のうち、施工面10を除く三面を覆う土留壁を構築する。なお、構築された土留壁は、本管33の周囲のコンクリート33a上に載置されることになる。   And with progress of excavation of the excavation groove 3, the unit units 11-13 of the earth retaining unit 1 are sequentially sunk. Specifically, the lower unit 13 is set in the working groove 31 at the initial stage of excavation, and as the excavation depth becomes deeper, the lower unit 13 is pushed downward by the heavy equipment 4 to be settled, and the next middle part is placed on the upper part. The unit 12 is placed and further pushed down by the heavy machine 4 to be settled. Similarly, the earth retaining wall which covers three surfaces except the construction surface 10 among the excavation wall surfaces of the work groove 31 is constructed by placing and sinking the upper unit 11. The built retaining wall is placed on the concrete 33a around the main pipe 33.

このとき、開削の所定の段階において、土留ユニット1から施工面方向に支持脚2,2を突出させ、施工面10側の掘削面32aから反力を得て、土留ユニット1を支持させる。具体的には、施工面10の両側に位置するポスト部133b、133bからそれぞれ脚部22を張出させ、掘削面32a上に押しつけるとともに、支持アーム21によって脚部22から反力を取って、土留ユニット1を掘削面32aとは反対の方向に支持する。   At this time, in a predetermined stage of excavation, the support legs 2 and 2 are projected from the soil retaining unit 1 in the direction of the construction surface, and a reaction force is obtained from the excavation surface 32a on the construction surface 10 side to support the soil retaining unit 1. Specifically, the leg portions 22 are projected from the post portions 133b and 133b located on both sides of the construction surface 10 and pressed on the excavation surface 32a, and the reaction force is taken from the leg portion 22 by the support arm 21, The earth retaining unit 1 is supported in a direction opposite to the excavation surface 32a.

具体的には、ポスト部133bの下側において、フランジ136bと脚部側係合部22bの挿通孔を揃えた状態で、円筒状のピン137bを挿通し、脚部22をポスト部133bに対して回動可能に連結する。一方、ポスト部133bの上側において、フランジ136aと支持アーム側係合部21aの挿通孔を揃えた状態で、円筒状のピン137aを挿通することで、支持アーム21をポスト部133bに対して回動可能に連結する。これと併せて、脚部22の挿通孔22cを選択し脚部22の取付角度を決めたうえで、選択された挿通孔22に支持アーム21側係合部21aの挿通孔を揃えた状態で、円筒状のピン21cを挿通し、支持アーム21が脚部22に対して連結する。   Specifically, in a state where the insertion holes of the flange 136b and the leg-side engaging portion 22b are aligned on the lower side of the post portion 133b, the cylindrical pin 137b is inserted, and the leg portion 22 is inserted into the post portion 133b. And can be pivoted. On the other hand, on the upper side of the post portion 133b, with the insertion holes of the flange 136a and the support arm side engagement portion 21a being aligned, the cylindrical pin 137a is inserted to rotate the support arm 21 with respect to the post portion 133b. Connect movably. At the same time, after selecting the insertion hole 22c of the leg portion 22 and determining the mounting angle of the leg portion 22, the insertion hole of the engaging portion 21a on the support arm 21 side is aligned with the selected insertion hole 22. Then, the cylindrical pin 21 c is inserted, and the support arm 21 is connected to the leg portion 22.

なお、支持脚2,2を設ける上記所定の段階とは、作業溝31周囲の土圧Pや、掘削面32aの状態に応じて適宜選択することができ、例えば、すべての単位ユニット11〜13を沈設した後でもよく、下部ユニット13を沈設した直後でもよい。また、支持脚2,2を土留ユニット1に取付けるタイミングとしては、下部ユニット13を沈設する前に予め下部ユニットに取付けておいてもよく、沈設後に取付けるようにしてもよい。なお、支持脚2,2の取付角度も、開削の進行に伴い、作業溝31周囲の土圧や、掘削面32aの状態に応じて適宜変化させる。また、スペーサー116,126,136は、開削の進行度合い、作業溝31周囲の土圧に応じて適宜のタイミングで取付ける。このスペーサー116,126,136は、重機4による開削作業や、支管35aの埋設工事の障害となる場合もあることから、場合に応じて適宜省略したり、取り外したりすることができ、その取付け順序も適宜変更される。   In addition, the said predetermined stage which provides the support legs 2 and 2 can be suitably selected according to the earth pressure P around the work groove 31, and the state of the excavation surface 32a, for example, all the unit units 11-13. It may be after sunk or immediately after the lower unit 13 is sunk. Moreover, as a timing which attaches the support legs 2 and 2 to the earth retaining unit 1, it may be attached to the lower unit in advance before the lower unit 13 is set, or may be attached after being set. Note that the mounting angles of the support legs 2 and 2 are also appropriately changed according to the earth pressure around the work groove 31 and the state of the excavation surface 32a as the excavation progresses. The spacers 116, 126, and 136 are attached at an appropriate timing according to the progress of the excavation and the earth pressure around the work groove 31. The spacers 116, 126, and 136 may obstruct the excavation work by the heavy machinery 4 or the burial work of the branch pipe 35 a, and can be omitted or removed as appropriate according to circumstances. Are also changed as appropriate.

次いで、脚部22の先端部において、円筒部22aに杭23を挿通するとともに、杭23を掘削面32a内に打込むことにより、脚部22を掘削面32aに固定する。その後、土留ユニット1により、周囲三面からの土圧Pを支えつつ、掘削溝3内において施工空間34に対して支管35aを埋設する施工作業を行う。ここでは、作業溝31の底部において、コンクリート33aを斫って本管33を露出させ、支管35aを分岐接続する。   Next, at the distal end portion of the leg portion 22, the pile 23 is inserted into the cylindrical portion 22a, and the leg portion 22 is fixed to the excavation surface 32a by driving the pile 23 into the excavation surface 32a. Thereafter, the earth retaining unit 1 performs the construction work of burying the branch pipe 35a in the construction space 34 in the excavation groove 3 while supporting the earth pressure P from the three surrounding surfaces. Here, at the bottom of the working groove 31, the concrete pipe 33a is exposed over the concrete 33a, and the branch pipe 35a is branched and connected.

そして、この施工作業が終了した後には、土留ユニット1を撤去するとともに、掘削溝3の埋戻しを行う。この土留ユニット1の撤去は、現場の状況に応じて、例えば、単位ユニットにワイヤーを括り付け、上部単位ユニットから順次、重機により吊り上げるなどして行う。   And after this construction work is completed, the earth retaining unit 1 is removed and the excavation groove 3 is backfilled. The removal of the soil retaining unit 1 is performed, for example, by tying a wire to the unit unit and sequentially lifting it from the upper unit unit by a heavy machine according to the situation at the site.

(作用・効果)
このような本実施形態によれば、掘削溝3の壁面のうち、作業溝31における施工面10を除く三面の掘削面からの土圧Pを土留ユニット1で支持させるため、掘削面の崩壊を防止し、掘削溝内の作業の安全を確保することができる。このとき、土留ユニット1の施工面10側は開放されていることから、土留ユニット内から掘削面32aに対して、支管35aの埋設工事等の作業を安全且つ容易に行うことができる。特に、土留ユニット1から施工面10方向に向けて支持脚2,2を突出させ、施工面10側の掘削面32aから反力を得て、土留ユニット1を支持することから、周囲の土圧Pが作用した場合であっても、土留ユニット1が転倒したり、滑動したりするのを防止できる。
(Action / Effect)
According to the present embodiment, the earth retaining unit 1 supports the earth pressure P from the three excavation surfaces excluding the construction surface 10 in the work groove 31 among the wall surfaces of the excavation groove 3. It is possible to prevent and ensure the safety of the work in the excavation groove. At this time, since the construction surface 10 side of the soil retaining unit 1 is open, it is possible to safely and easily perform operations such as the embedding work of the branch pipe 35a from the soil retaining unit to the excavation surface 32a. In particular, since the support legs 2 and 2 protrude from the soil retaining unit 1 toward the construction surface 10 and the reaction force is obtained from the excavation surface 32a on the construction surface 10 side, the soil retaining unit 1 is supported. Even when P acts, the earth retaining unit 1 can be prevented from falling or sliding.

(変更例)
なお、上記実施形態では、土留ユニット1を上、中、下の3つの単位ユニット11〜13で構成したが、本発明はこれに限定されるものではなく、開削溝の深度に応じて、単位ユニットの数を適宜変更して、土留ユニット1の深さを貼設することができる。
(Example of change)
In addition, in the said embodiment, although the earth retaining unit 1 was comprised by three unit units 11-13 of upper, middle, and lower, this invention is not limited to this, According to the depth of a cut groove, a unit The depth of the soil retaining unit 1 can be pasted by appropriately changing the number of units.

また、上記実施形態では、脚部22を下部ユニット13の下部に設け、その支持アーム21も下部ユニット13の上部に取付けたが、開削する地盤の状態や、開削溝の深度に応じて、他の単位ユニットに取付けるようにしてもよい。さらには、支持アーム21の取付け位置を上部の単位ユニット(例えば、中部ユニット12)とし、下部ユニット13に取付けられた脚部22を、上方の単位ユニットから連結するようにしてもよい。この場合には、支持アーム21を長いものと交換し、複数の単位ユニット間に亘る高さに対応させるようにする。   Further, in the above embodiment, the leg portion 22 is provided at the lower portion of the lower unit 13 and the support arm 21 is also attached to the upper portion of the lower unit 13, but depending on the ground condition to be cut and the depth of the cut groove, It may be attached to the unit unit. Furthermore, the mounting position of the support arm 21 may be the upper unit unit (for example, the middle unit 12), and the leg portion 22 attached to the lower unit 13 may be connected from the upper unit unit. In this case, the support arm 21 is replaced with a long one so as to correspond to the height between the plurality of unit units.

P…土圧
1…土留ユニット
2,2…支持脚
3…掘削溝
4…重機
10…施工面
11…単位ユニット(上部ユニット)
12…単位ユニット(中部ユニット)
13…単位ユニット(下部ユニット)
21…支持アーム
21a,21b…支持アーム側係合部
21c,137a,137b…ピン
22…脚部
22a…円筒部
22b…脚部側係合部
22c…挿通孔
23…杭
30…地表
31…作業溝
32…開削溝
32a…掘削面
33…本管
33a…コンクリート
33b…基礎コンクリート
34…施工空間
35a…支管
35b…既設管
111…プレッシャーフード
112a,112b,122a,122b,132a,132b…土留壁
113a,113b,123a,123b,133a,133b…ポスト部
114a,114b,124a,124b,134a,134b…嵌合部
116,126,136…スペーサー
135a,135b…カッティングシュー
136a,136b…フランジ
P ... earth pressure 1 ... earth retaining unit 2, 2 ... support leg 3 ... excavation groove 4 ... heavy machinery 10 ... construction surface 11 ... unit unit (upper unit)
12 ... Unit unit (central unit)
13 ... Unit unit (lower unit)
DESCRIPTION OF SYMBOLS 21 ... Support arm 21a, 21b ... Support arm side engaging part 21c, 137a, 137b ... Pin 22 ... Leg part 22a ... Cylindrical part 22b ... Leg part side engaging part 22c ... Insertion hole 23 ... Pile 30 ... Ground surface 31 ... Work Groove 32 ... Cleaving groove 32a ... Excavation surface 33 ... Main pipe 33a ... Concrete 33b ... Concrete concrete 34 ... Construction space 35a ... Branch pipe 35b ... Existing pipe 111 ... Pressure hood 112a, 112b, 122a, 122b, 132a, 132b ... During wall 113a , 113b, 123a, 123b, 133a, 133b ... post part 114a, 114b, 124a, 124b, 134a, 134b ... fitting part 116, 126, 136 ... spacer 135a, 135b ... cutting shoe 136a, 136b ... flange

Claims (2)

地表から作業用の掘削溝を開削しつつ、前記掘削溝に隣接する施工空間に対して所定の施工作業を行う際の土留工法であって、
前記掘削溝の掘削壁面のうち、前記施工空間に臨む施工面を除く三面を覆う土留壁を有する土留ユニットを、前記開削の進行に伴って前記掘削溝内に沈設する工程と、
前記土留ユニットから前記施工面方向に向けて支持脚を突出させ、前記施工面側の掘削面から反力を得て、当該土留ユニットを支持する工程と、
前記土留ユニットにより前記三面からの土圧を支えつつ、前記掘削溝内から前記施工空間に対して前記施工作業を行う工程と
を有することを特徴とする土留工法。
While excavating a work excavation groove from the ground surface, a earth retaining method when performing a predetermined construction work on the construction space adjacent to the excavation groove,
A step of sinking a soil retaining unit having a retaining wall covering three surfaces excluding a construction surface facing the construction space in the excavation groove in the excavation groove as the excavation progresses;
A step of projecting a support leg from the soil retaining unit toward the construction surface direction, obtaining a reaction force from the excavation surface on the construction surface side, and supporting the soil retaining unit;
And a step of performing the construction work on the construction space from within the excavation groove while supporting the earth pressure from the three surfaces by the earth retaining unit.
地表から作業用の掘削溝を開削しつつ、前記掘削溝に隣接する施工空間に対して所定の施工作業を行う際の土留工法において用いられる土留ユニットであって、
前記掘削溝の掘削壁面のうち、前記施工空間に臨む施工面を除く三面を覆う水平断面がコの字形の土留壁と、
前記土留壁から前記施工面方向に向けて突出され、前記施工面側の掘削面から反力を得て、前記土留壁を支持する支持脚と
を備えることを特徴とする土留ユニット。
A earth retaining unit used in the earth retaining method when performing predetermined construction work on a construction space adjacent to the excavation groove while excavating the excavation groove for work from the ground surface,
Of the excavation wall surface of the excavation groove, a horizontal wall covering the three surfaces excluding the construction surface facing the construction space, a U-shaped retaining wall,
A soil retaining unit, comprising: a support leg that protrudes from the retaining wall toward the construction surface, obtains a reaction force from the excavation surface on the construction surface side, and supports the retaining wall.
JP2014218314A 2014-10-27 2014-10-27 Earth retaining method and earth retaining unit Active JP5729712B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014218314A JP5729712B1 (en) 2014-10-27 2014-10-27 Earth retaining method and earth retaining unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014218314A JP5729712B1 (en) 2014-10-27 2014-10-27 Earth retaining method and earth retaining unit

Publications (2)

Publication Number Publication Date
JP5729712B1 true JP5729712B1 (en) 2015-06-03
JP2016084623A JP2016084623A (en) 2016-05-19

Family

ID=53437951

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014218314A Active JP5729712B1 (en) 2014-10-27 2014-10-27 Earth retaining method and earth retaining unit

Country Status (1)

Country Link
JP (1) JP5729712B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016044487A (en) * 2014-08-25 2016-04-04 張山電氣株式会社 Excavation auxiliary device, excavation method and long size object burying method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5550105U (en) * 1978-09-22 1980-04-02
JPS62169038U (en) * 1986-04-14 1987-10-27

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5550105U (en) * 1978-09-22 1980-04-02
JPS62169038U (en) * 1986-04-14 1987-10-27

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016044487A (en) * 2014-08-25 2016-04-04 張山電氣株式会社 Excavation auxiliary device, excavation method and long size object burying method

Also Published As

Publication number Publication date
JP2016084623A (en) 2016-05-19

Similar Documents

Publication Publication Date Title
KR100884289B1 (en) Composite type steel temporary construction and construction method thereof
JP2013136921A (en) Earth retaining wall supporting method, earth retaining wall supporting structure, and underground skeleton constructing method
KR101448216B1 (en) Retaining wall with multiple pile
JP5351125B2 (en) Open shield machine start method of open shield method
JP5465086B2 (en) Construction method of underground structure
JP5729712B1 (en) Earth retaining method and earth retaining unit
KR200389267Y1 (en) Box type trench shoring apparatus
JP6710999B2 (en) Temporary receiving method for existing structures
JP6735138B2 (en) Construction method of retaining wall structure and retaining wall structure
JP2019143794A (en) Underground pipe protection method and protection structure
JP5367452B2 (en) Underground wall construction method and underground wall body
JP4581419B2 (en) Seismic isolation zone
KR101215270B1 (en) A shoring construction method using the iron board
JP7461443B1 (en) How to assemble an open shield machine
JP5021049B2 (en) Reaction device for bottom plate and method for constructing bottom plate
JP2000257069A (en) Earth retaining and earth retaining construction method
KR102575701B1 (en) A method of open cut excavation tunnel using a messer plate
JP2009209548A (en) Foundation reinforcing construction method for existing structure
JP4889993B2 (en) Construction method of widening shaft
JP4272228B2 (en) Construction method of underground structure
TW201900987A (en) Method for forming underground construction and underground construction formed thereby
JP2579584B2 (en) Earth retaining method and earth retaining box
JP2006161439A (en) Earth retaining box-shaped timbering and method of using the same
JP5817432B2 (en) Groove excavation method
JPS5914513Y2 (en) Earth retaining device for excavated trenches

Legal Events

Date Code Title Description
A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20150303

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150319

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150331

R150 Certificate of patent or registration of utility model

Ref document number: 5729712

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250