JPS5914513Y2 - Earth retaining device for excavated trenches - Google Patents

Earth retaining device for excavated trenches

Info

Publication number
JPS5914513Y2
JPS5914513Y2 JP3987682U JP3987682U JPS5914513Y2 JP S5914513 Y2 JPS5914513 Y2 JP S5914513Y2 JP 3987682 U JP3987682 U JP 3987682U JP 3987682 U JP3987682 U JP 3987682U JP S5914513 Y2 JPS5914513 Y2 JP S5914513Y2
Authority
JP
Japan
Prior art keywords
sheet pile
guide
penetration
trench
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3987682U
Other languages
Japanese (ja)
Other versions
JPS58145348U (en
Inventor
昌美 宮島
Original Assignee
日本クリングス株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本クリングス株式会社 filed Critical 日本クリングス株式会社
Priority to JP3987682U priority Critical patent/JPS5914513Y2/en
Publication of JPS58145348U publication Critical patent/JPS58145348U/en
Application granted granted Critical
Publication of JPS5914513Y2 publication Critical patent/JPS5914513Y2/en
Expired legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【考案の詳細な説明】 本考案は、主として下水道の本管等を地中に埋設するた
めの溝の掘削に用いる土留装置に関する。
[Detailed Description of the Invention] The present invention mainly relates to an earth retaining device used for excavating a trench for burying a main sewer pipe or the like underground.

溝の掘削のために鋼矢板を打設する従来の工法の問題点
である騒音および振動を防止するために、一対の案内枠
を掘削溝の両側に配してそれらの間を切張りとしてのス
ピンドルで連結し、各案内枠の上下方向の案内空間に矢
板を上下方向に挿入し、両案内枠より下方に突出する矢
板の間の土を掘削して矢板を沈降させつつ溝を掘削する
工法およびそれに用いる土留装置を本出願人は先に提案
した(特開昭55−16172号、特願昭53−892
31号)。
In order to prevent the noise and vibration that are problems with the conventional construction method of driving steel sheet piles for trench excavation, a pair of guide frames are placed on both sides of the excavated trench, and a cut line is placed between them. A construction method in which the sheet piles are connected by a spindle and inserted vertically into the vertical guide spaces of each guide frame, and the soil between the sheet piles that protrudes downward from both guide frames is excavated to allow the sheet piles to settle while excavating a trench. The present applicant had previously proposed an earth retaining device for use therein (Japanese Patent Laid-Open No. 55-16172, Japanese Patent Application No. 53-892).
No. 31).

ところでこの種の工法および装置を用いて溝を掘削する
場合、溝を掘削すべき地盤には、軟弱な砂地盤、固い粘
土地盤等種々あるため、溝掘削の際には矢板の地中への
根入れ量を地盤に応じて適宜節する必要がある。
By the way, when excavating a trench using this type of construction method and equipment, there are various types of ground to excavate the trench from, such as soft sandy ground and hard clay ground. It is necessary to adjust the amount of penetration depending on the soil.

ところが、作業中に矢板の根入れ量を測定することは容
易でなく、地盤に応じた最適組入れ量を得ることが困難
であった。
However, it is not easy to measure the amount of penetration of the sheet piles during work, and it is difficult to obtain the optimal amount of penetration depending on the ground.

本考案はかかる現況に鑑みなされたもので、その目的と
するところは、極めて容易に矢板の地中への根入れ量を
地盤に応じて最適値にすることができる溝掘削用土留装
置を提供するにある。
The present invention was developed in view of the current situation, and its purpose is to provide an earth retaining device for trench excavation that can extremely easily set the amount of penetration of sheet piles into the ground to an optimum value according to the ground. There is something to do.

本考案は、矢板の地中への根入れ量を地盤に応じて最適
値にする手段として、矢板の下部の少なくとも内面側に
根入れ目安ゲージとなる表示を施し、根切底と目安ゲー
ジとの関係から根入れ量を適切な値に保つようにしたこ
とを特徴とする。
In this invention, as a means of optimizing the amount of penetration of the sheet pile into the ground depending on the ground, the bottom of the sheet pile is marked with a penetration gauge at least on the inner side, and the root cut and the guide gauge are displayed. A feature is that the amount of penetration is kept at an appropriate value based on the relationship.

以下、本考案を図示する一実施例に基づいて説明する。Hereinafter, the present invention will be explained based on an illustrative embodiment.

第1図ないし第3図において、1は掘削すべき溝Aの両
側に対向して配される一対の矢板案内枠であり、両案内
枠1,1は、切張りとしてのスピンドル2によって溝幅
方向に関して連結されている。
In Figures 1 to 3, reference numeral 1 denotes a pair of sheet pile guide frames disposed opposite to each other on both sides of a trench A to be excavated, and both guide frames 1, 1 are controlled by a spindle 2 as a shear tensioner. Connected in direction.

前記各案内枠1は、均等な上枠部1aおよび下枠部1b
を有し、両枠部1a、lbの両端部は、縦方向のパイプ
3,3によって一体的に連結されている。
Each guide frame 1 has an equal upper frame portion 1a and a lower frame portion 1b.
Both ends of both frame parts 1a and lb are integrally connected by vertical pipes 3, 3.

そして、スピンドル2の両端部はパイプ3に適当に連結
される。
Both ends of the spindle 2 are appropriately connected to the pipe 3.

両枠部1a、lbの各々は、主横材42幅横材5および
それらを溝幅方向に連結する連結腕6によって全体とし
て平面形状が長方形の枠をなすように形成されている。
Each of the frame portions 1a, lb is formed so as to form a rectangular frame in plan view as a whole by the main cross member 42, the cross member 5, and the connecting arm 6 that connects them in the groove width direction.

そして、上下の枠部1a、lbの主横材4と幅横材5と
の間の空間は上下に位置が合い、これらの空間によって
後に詳述する矢板Pを受けて起立状態に保持する矢板案
内空間7(第1図)が形成されている。
The spaces between the main horizontal members 4 and the width horizontal members 5 of the upper and lower frame portions 1a and lb are aligned vertically, and these spaces allow the sheet piles P, which will be described in detail later, to be received and held in an upright state. A guide space 7 (FIG. 1) is formed.

上下の枠部1a、lbは、また、縦方向パイプ3の外側
に隣接する上下方向の連結材9によって−体化されてい
る。
The upper and lower frame portions 1a and 1b are also integrated by vertical connecting members 9 adjacent to the outside of the vertical pipe 3.

連結材9は図示の例ではC形鋼(リップ付き溝形鋼)か
らなり、その底壁には前記主横材4の端部が溶接等によ
り固定されている。
In the illustrated example, the connecting member 9 is made of C-shaped steel (channel steel with a lip), and the end portion of the main cross member 4 is fixed to the bottom wall of the connecting member 9 by welding or the like.

主横材4および幅横材5は図示の例ではパイプ材で構成
され、主横材4および幅横材5の対向する側面には、そ
れらを補強するとともに矢板Pの案内作用を果たす添材
10,11が着脱可能に取付けられている。
In the illustrated example, the main cross member 4 and the width cross member 5 are made of pipe material, and on the opposing sides of the main cross member 4 and the width cross member 5, there are additives that reinforce them and serve as guides for the sheet piles P. 10 and 11 are detachably attached.

前記矢板案内空間7に上下方向に挿通される矢板群Pは
、第4図に示すように互いに長手側端の屈曲縁を係合さ
せて上下に相対的に摺動自在とした一連の矢板ニレメン
) P、、 P2. P3.・・・・・・の組合わせに
よって構成されており、この矢板Pの少なくとも内面、
すなわち溝Aの内部側に位置する面には、下端から例え
ば1m程度上方の位置に根入れ目安ゲージ線1が設けら
れている。
The sheet pile group P, which is vertically inserted into the sheet pile guide space 7, is a series of double sheet piles whose longitudinal side ends are engaged with each other so as to be relatively slidable vertically, as shown in FIG. ) P,, P2. P3. It is composed of a combination of..., and at least the inner surface of this sheet pile P,
That is, on the surface located inside the groove A, a penetration guide gauge line 1 is provided at a position, for example, about 1 m above the lower end.

この根入れ目安ゲージ線12は、第2図に示すように溝
掘削時に矢板Pの地中への根入れ量りに対応するもので
、軟弱地盤を掘削する際にはそれに対応する根入れ量り
がゲージ線12で示され、また、固い地盤を掘削する場
合には、その最適組入れ量がゲージ線12で表示されて
いる。
As shown in Fig. 2, this penetration guide gauge line 12 corresponds to the penetration depth of the sheet pile P into the ground when excavating a trench, and the corresponding penetration measurement when excavating soft ground. This is indicated by a gauge line 12, and when excavating hard ground, the optimum amount to incorporate is indicated by the gauge line 12.

また、種々の地盤に対応する複数のゲージ線を同時に表
示しておいてもよい。
Further, a plurality of gauge lines corresponding to various types of ground may be displayed simultaneously.

なお、第2図および第3図において、13は、矢板Pを
下方へ押下げる際に矢板Pの上端縁部に装着されるプロ
テクタである。
In addition, in FIG. 2 and FIG. 3, 13 is a protector mounted on the upper end edge of the sheet pile P when pushing the sheet pile P downward.

次に、以上説明した溝掘削用土留装置を用いて溝を掘削
する工法について説明する。
Next, a method of excavating a trench using the trench excavating earth retaining device described above will be described.

まず、第5図に縦断面で示すように、掘削予定位置に、
所定幅で例えば深さが案内枠1の高さにほぼ等しい溝A
′を掘削する。
First, as shown in the longitudinal section in Figure 5, at the planned excavation location,
A groove A having a predetermined width and a depth that is approximately equal to the height of the guide frame 1, for example.
′ to be excavated.

一方、地上において、案内枠1,1を上下各2本計4本
のスピンドル2で連結しておき、これを、同図に縦断面
で示す゛ように溝A′内に降ろす。
Meanwhile, on the ground, the guide frames 1, 1 are connected by a total of four spindles 2, two each on the upper and lower sides, and are lowered into the groove A' as shown in the longitudinal section in the figure.

溝A′内に降ろされるときの案内枠1.1の外面間距離
は溝A′の幅よりもやや小さくしておき、降下後スピン
ドル2をそのターンバックル2aの操作により伸長させ
、両案内枠1,1を溝壁面に圧接させる。
The distance between the outer surfaces of the guide frame 1.1 when lowered into the groove A' is made slightly smaller than the width of the groove A', and after lowering, the spindle 2 is extended by operating its turnbuckle 2a, and both guide frames 1 and 1 are brought into pressure contact with the groove wall surface.

この状態で、各案内枠1の矢板案内空間7に、連結され
た鋼矢板Pを上方から挿入し、その下端を同図に示すよ
うに土中に幾分押込む。
In this state, the connected steel sheet piles P are inserted into the sheet pile guide spaces 7 of each guide frame 1 from above, and the lower ends are pushed into the soil somewhat as shown in the figure.

また、溝掘削方向に、前記と同様に同様な溝A′を掘り
進み、すでに沈めである案内枠1,1に隣接させて新た
に組立てた案内枠1,1を沈め、互いに同じ溝壁面にそ
って並ぶ案内枠1,1の連結金具9.9の溝内にH形鋼
からなる連結材14のフランジ14a、14aを嵌込み
、両案内枠1,1を溝の長手方向に連結していく。
Further, in the trench excavation direction, a similar trench A' is dug in the same manner as above, and the newly assembled guide frames 1, 1 are sunk adjacent to the already sunk guide frames 1, 1, so that they are on the same trench wall surface. The flanges 14a, 14a of the connecting member 14 made of H-shaped steel are fitted into the grooves of the connecting fittings 9.9 of the guide frames 1, 1 arranged side by side, and both the guide frames 1, 1 are connected in the longitudinal direction of the groove. go.

溝A′内に嵌込まれた案内枠1は、相対向する案内枠1
とスピンドル2を介して連結されるが、溝壁面ぞいに隣
在する案内枠1,1は前記のようにして連結材14によ
り連結される。
The guide frame 1 fitted into the groove A' is connected to the opposing guide frame 1.
The guide frames 1, 1 adjacent to each other on the groove wall surfaces are connected by the connecting member 14 as described above.

そして、溝A′内に嵌込まれ、矢板Pが挿込まれて相対
している案内枠1,1間の掘削排土を行なうと、第6図
に縦断面図で示すように、排土の進行に伴ない、自重お
よび補助的圧下刃によって矢板Pは直立のまま沈降し、
やがて溝の深さが所定の値となり溝Aが得られたとき、
下水道本管となるヒユーム管等の埋設管を1本ずつ溝底
に降ろし、それを長手方向に順次連結していく。
Then, when the sheet pile P is inserted into the groove A' and excavation and removal is performed between the guide frames 1 and 1 facing each other, the earth is removed as shown in the vertical cross-sectional view in FIG. As the process progresses, the sheet pile P sinks while remaining upright due to its own weight and the auxiliary reduction blade.
Eventually, when the depth of the groove reaches a predetermined value and groove A is obtained,
Buried pipes such as Huyum pipes, which will become the main sewer pipes, are lowered one by one to the bottom of the trench and connected sequentially in the longitudinal direction.

設置管はこのようにして次第に延長される。The installation tube is thus gradually extended.

ところでこの溝掘削を行なう場合、矢板Pの外面側には
土庄がかかるため、第2図に示すように矢板Pの下端部
を土中に埋設して適当な根入れ量りを確保する必要があ
る。
By the way, when excavating this trench, the outer surface of the sheet pile P is covered with soil, so it is necessary to bury the lower end of the sheet pile P in the soil to ensure an appropriate depth of penetration, as shown in Figure 2. .

そして、この根入れ量りは、溝を掘削すべき地盤の状態
に応じた適宜調節する必要がある。
This amount of penetration needs to be adjusted as appropriate depending on the condition of the ground where the trench is to be excavated.

ところが、前記するように従来のものでは地盤の状態に
応じた適当な根入れ量を確保することが容易でなかった
However, as mentioned above, with the conventional type, it is not easy to secure an appropriate amount of penetration depending on the ground condition.

そこで本実施例では、矢板Pの下端がら所定の高さ位置
に根入れ目安ゲージ12を設け、この根入れ目安ゲージ
12を基準として最適な根入れ量りを確保するようにし
ている。
Therefore, in this embodiment, a penetration guide gauge 12 is provided at a predetermined height position from the lower end of the sheet pile P, and an optimum penetration measurement is ensured using this penetration guide gauge 12 as a reference.

すなわち、根入れ目安ゲージ12は、地盤の性質に対応
させて矢板P下端からの高さ位置が設定されており、溝
を掘削する場合には、根入れ目安ゲージ12の位置まで
溝掘削を行なうことにより、地盤に応じた最適な根入れ
量りが確保されるようになっている。
That is, the height position of the penetration guide gauge 12 from the lower end of the sheet pile P is set in accordance with the nature of the ground, and when excavating a trench, the trench is excavated to the position of the penetration guide gauge 12. This ensures the optimum amount of penetration depending on the soil.

例えば、固い粘土地盤に溝を掘削する場合には、矢板P
にかかる土圧が軟弱地盤に比較して小さいため、矢板P
の根入れ量りもこれに応じて少なくしてよい。
For example, when excavating a trench in hard clay ground, the sheet pile P
Since the earth pressure applied to the sheet pile P is smaller than that of soft ground,
The amount of rooting can be reduced accordingly.

このように、地盤に応じて根入れ量が異なるので、各地
盤に応じてゲージを施した矢板を用意してもよいが、同
じ矢板に種々の地盤用のゲージをすべて設けておいても
よい。
In this way, the amount of penetration differs depending on the ground, so it is possible to prepare sheet piles with gauges applied to each ground, but it is also possible to provide all the gauges for various ground on the same sheet pile. .

また、最も軟弱な地盤用のゲージのみを設け、そのゲー
ジに対応する根入れ量を最大値とし、それを目安にして
、地盤に応じた最適積大れ量を得るようにしてもよい。
Alternatively, only a gauge for the softest ground may be provided, and the penetration amount corresponding to that gauge may be set as the maximum value, and this may be used as a guideline to obtain the optimum amount of heaping depending on the ground.

溝Aの底部において接続された埋設管が隣在のものと接
続された後、矢板Pを抜取り、案内枠1,1を抜取って
から溝Aは順次埋め戻される。
After the buried pipe connected at the bottom of the groove A is connected to the adjacent one, the sheet pile P is extracted, the guide frames 1, 1 are extracted, and the groove A is sequentially backfilled.

抜取った案内枠1,1および矢板Pは、再び溝Aの掘進
に伴ない反復して使用するから、総量は多数組を必要と
しない。
The extracted guide frames 1, 1 and sheet piles P are used repeatedly as the trench A is dug again, so a large number of sets are not required.

前述のようにして案内枠1に挿入された後掘削により溝
の深さが増すことにより沈降していく矢板Pは、1つの
案内枠1内において、複数枚が互いに連結されているが
、いずれも相互に摺動変位自在に直立しているので、縦
方向には、いずれの矢板エレメントP 1 + P 2
+ P 3 +・・・・・・も単独で沈降できる状態
にある。
The sheet piles P, which are inserted into the guide frame 1 as described above and sink as the depth of the groove increases due to excavation, are connected to each other within one guide frame 1, but eventually Since both sheet pile elements P 1 + P 2 stand vertically and can be slidably displaced relative to each other, in the longitudinal direction, any of the sheet pile elements P 1 + P 2
+ P 3 +... is also in a state where it can settle independently.

一方、地表から例えば1.5mまでの深さには上水道や
ガスの引込管(いずれも図示せず)が溝Aを掘進してい
こうとする方向とほぼ水平に交差して存在することがあ
る。
On the other hand, at a depth of, for example, 1.5 m from the ground surface, there may be water supply or gas service pipes (none of which are shown) that intersect almost horizontally with the direction in which Trench A is being dug. .

これらの引込管類は必然的に矢板Pの沈降を妨げること
になる。
These lead-in pipes inevitably prevent the sheet pile P from settling.

このような取除くことのできない障害物に遭遇したとき
には、その位置にある矢板ニレメン) P、、P2.P
3゜・・・・・・が障害物より沈降を妨げられ、他の矢
板ニレメン) P 1. P 2. P 3.・・・・
・・のみが沈降させられる。
When you encounter such an obstacle that cannot be removed, move the sheet pile at that location.P., P2. P
3゜... is prevented from settling by an obstacle, and other sheet piles are falling) P 1. P2. P3.・・・・・・
Only ... is allowed to settle.

この工法では、前記特開昭55−16172号公報に記
載の工法と同様、最も深い位置に埋設される下水道本体
の施工に際し、中間の深さにある各種配管をよけて矢板
Pを沈降させることができ、安全のため設ける土留壁と
しての矢板Pを無理に打込まず、溝の深さが増すにつれ
て自然にその沈降をうながし、外力を加える必要があっ
ても、例えば掘削機パケット等によりプロテクタ13を
介して軽く押込む程度で、矢板Pによる土留壁構築を行
なうことができる。
In this construction method, similar to the construction method described in JP-A No. 55-16172, when constructing the main body of the sewer to be buried at the deepest position, the sheet pile P is lowered to avoid various pipes located at intermediate depths. For safety, the sheet pile P used as an earth retaining wall is not forced into the trench, but is allowed to settle naturally as the depth of the trench increases. An earth retaining wall can be constructed using the sheet piles P by pushing them lightly through the protector 13.

なお、この工法を実施するに際し、下側のスピンドル2
の方を多く伸長させて対をなす案内枠1,1が八字形を
なすようにしておけば、矢板Pも下方にいくにつれて拡
がり、下へいくにつれて高まる土庄によって矢板Pが内
側へ変形して溝Aの底部の幅が狭くなることを防ぐこと
ができる。
In addition, when implementing this construction method, the lower spindle 2
If the pair of guide frames 1 and 1 are made to form an eight-figure shape by elongating the guide frame 1 more, the sheet pile P will also expand as it goes downward, and the sheet pile P will be deformed inward by the tonosho that increases as it goes downward. This can prevent the width of the bottom of the groove A from becoming narrower.

しかして、矢板Pの下部内面側の矢板P下端から所定の
高さ位置に根入れ目安ゲージ12を設け、この根入れ目
安ゲージ12を基準として根入れ量りを決定するので、
地盤に応じた最適な根入れ量りが容易に得られる。
Therefore, the penetration guide gauge 12 is provided at a predetermined height position from the lower end of the sheet pile P on the lower inner surface side of the sheet pile P, and the penetration measurement is determined based on this penetration guide gauge 12.
You can easily obtain the optimum rooting depth according to the soil.

なお、根入れ目安ゲージとしては線以外の他の任意の表
示手段を用いてもよい。
Note that any other display means other than lines may be used as the penetration gauge.

以上説明したように本考案は、矢板の下部に根入れ目安
ゲージを設け、この目安ゲージを基準として矢板の根入
れ量を決定するようにしているので、溝を掘削すべき地
盤に対応する最適な根入れ量を極めて容易に得ることが
できる。
As explained above, in this invention, a penetration gauge is provided at the bottom of the sheet pile, and the depth of penetration of the sheet pile is determined based on this gauge. A large amount of penetration can be obtained very easily.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案の溝掘削用土留装置の平面図、第2図は
第1図のII −II線方向に見た図、第3図は第1図
のlll−III線断面図、第4図は矢板の斜視図、第
5図および第6図は本考案の土留装置による施工順序を
示す説明図である。 1・・・・・・矢板案内枠、2・・・・・・スピンドル
、7・・・・・・矢板案内空間、12・・・・・・根入
れ目安ゲージ、P・・・・・・矢板、PI、 P2.
P3.・・・・・・矢板エレメント、L・・・・・・根
入れ量。
Fig. 1 is a plan view of the earth retention device for trench excavation of the present invention, Fig. 2 is a view taken along line II-II in Fig. 1, Fig. 3 is a sectional view taken along line Ill-III in Fig. FIG. 4 is a perspective view of the sheet pile, and FIGS. 5 and 6 are explanatory diagrams showing the construction sequence using the earth retaining device of the present invention. 1... Sheet pile guide frame, 2... Spindle, 7... Sheet pile guide space, 12... Embedding guide gauge, P... Yaita, PI, P2.
P3. ... Sheet pile element, L ... Rooting amount.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 互いに長手側縁部を摺動自在に連結した複数枚の矢板と
、これらの矢板を受けて起立状態に保持するための矢板
案内空間を上下方向に有し溝幅方向に対向する対をなす
案内枠と、両案内枠を両端に支持するように両案内枠間
に設けた切張りとしてのスピンドルとを有する溝掘削用
土留装置において、前記矢板の下部の少なくとも内面側
に矢板の根入れの目安ゲージとなる表示を施したことを
特徴とする掘削溝用土留装置。
A plurality of sheet piles whose longitudinal side edges are slidably connected to each other, and a pair of guides that have a sheet pile guide space in the vertical direction for receiving and holding these sheet piles in an upright state and facing each other in the groove width direction. In a trench excavation earth retaining device having a frame and a spindle as a cutting tension provided between both guide frames so as to support both guide frames at both ends, there is a guideline for embedding the sheet piles at least on the inner surface side of the lower part of the sheet piles. An earth retaining device for excavation trenches characterized by being provided with a display that serves as a gauge.
JP3987682U 1982-03-20 1982-03-20 Earth retaining device for excavated trenches Expired JPS5914513Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3987682U JPS5914513Y2 (en) 1982-03-20 1982-03-20 Earth retaining device for excavated trenches

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3987682U JPS5914513Y2 (en) 1982-03-20 1982-03-20 Earth retaining device for excavated trenches

Publications (2)

Publication Number Publication Date
JPS58145348U JPS58145348U (en) 1983-09-30
JPS5914513Y2 true JPS5914513Y2 (en) 1984-04-27

Family

ID=30051148

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3987682U Expired JPS5914513Y2 (en) 1982-03-20 1982-03-20 Earth retaining device for excavated trenches

Country Status (1)

Country Link
JP (1) JPS5914513Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2584682Y2 (en) * 1991-08-14 1998-11-05 重喜 中川 Work frame for excavation work

Also Published As

Publication number Publication date
JPS58145348U (en) 1983-09-30

Similar Documents

Publication Publication Date Title
KR102195203B1 (en) Soil blocking method using horizontal Strut and slope Strut
JPS5914513Y2 (en) Earth retaining device for excavated trenches
KR200389267Y1 (en) Box type trench shoring apparatus
JPS6158640B2 (en)
JPS5847092Y2 (en) Earth retention shoring device for excavated trenches
JPS5920818B2 (en) Earth retention device for trench excavation
JPS5840607B2 (en) Trench excavation method and earth retaining device for trench excavation
JP5729712B1 (en) Earth retaining method and earth retaining unit
JPS5849250Y2 (en) Earth retention shoring device for excavated trenches
JP2005106201A (en) Pipe support
KR102571803B1 (en) Pipe laying method using the earth frame
JPS5847091Y2 (en) Earth retention shoring device for excavated trenches
JP2001207452A (en) Method for burying pipe
KR102244505B1 (en) Self-supporting Type Sheeting Structure and Method for Sheeting Construction using the same
JPS58164821A (en) Trench excavation work
JPS609179B2 (en) Large diameter pipe buried turning method
JPS5840609B2 (en) Earth retaining method
JPS5835722Y2 (en) Earth retaining device for excavated trenches
JPS5842509Y2 (en) Earth retaining wall panel for trench excavation
JPH0634423Y2 (en) Guide rail for earth retaining device for excavation trench
JP3053270U (en) Support member receiving piece used for simple earth retaining method
JPS5840122Y2 (en) Earth retention shoring device for excavated trenches
JPH0574647B2 (en)
KR20230011082A (en) Earth frame for the pipe laying
JPS5848691B2 (en) Earth retention device for trench excavation