JPH07111117B2 - Cast-in-place lining method using mesh line in non-segment shield method - Google Patents
Cast-in-place lining method using mesh line in non-segment shield methodInfo
- Publication number
- JPH07111117B2 JPH07111117B2 JP62011698A JP1169887A JPH07111117B2 JP H07111117 B2 JPH07111117 B2 JP H07111117B2 JP 62011698 A JP62011698 A JP 62011698A JP 1169887 A JP1169887 A JP 1169887A JP H07111117 B2 JPH07111117 B2 JP H07111117B2
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- mesh
- mold
- concrete
- lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】 「産業上の利用分野」 この発明は、シールド工事において、セグメントを用い
ることなく壁面の覆工を行うノン・セグメント・シール
ド工法におけるメッシュ筋を用いた場所打ライニング方
法に関する。TECHNICAL FIELD The present invention relates to a cast-in-place lining method using mesh reinforcement in a non-segment shield construction method for lining walls without using segments in shield construction. .
「従来の技術」 先に、本出願人はシールド機を用いてトンネルを建設す
る方法の一つとして、セグメントを用いることなくトン
ネルの壁面の覆工を行うノン・セグメント・シールド工
法(以下、「N.S.S工法」という)を提供した。"Prior art" First, as one of the methods for constructing a tunnel using a shield machine, the applicant of the present invention has a non-segment shield construction method (hereinafter referred to as " NSS method ").
この工法は、シールド機によって掘進した坑の壁面に沿
って、複数に分割された所定幅を有する内型枠と外型枠
を、一体化しつつ筒状に組み立て、次いで、この内・外
型枠が坑の掘削方向に沿って所定数だけ連設された後、
前記内型枠と外型枠との間にコンクリートを打設してコ
ンクリートライニングを施し、このコンクリートライニ
ングが固化した部分が所定の長さに達した際、このコン
クリートライニングの内側に連設された内型枠のうち後
方の内型枠を、順次外型枠から分離させて解体した後、
それを新たに掘削した壁面に組み立てる内型枠として転
用することにより地中にトンネルを構築するものであ
る。This method is to assemble a plurality of divided inner molds and outer molds with a predetermined width along the wall surface of a mine that has been dug by a shield machine into a cylindrical shape while integrating them, and then to form the inner and outer molds. After a certain number of consecutively installed along the excavation direction of the mine,
Concrete was placed between the inner mold and the outer mold to give a concrete lining, and when the solidified portion of the concrete lining reached a predetermined length, the concrete was lined inside the concrete lining. After disassembling the inner formwork behind the inner formwork from the outer formwork one after another,
By diverting it as an inner formwork to be assembled on the newly excavated wall surface, a tunnel will be built underground.
したがって、このN.S.S工法においては、一次覆工でコ
ンクリートライニングを施してトンネルを完成させ、そ
の固化したコンクリートライニングによって地山から受
ける土水圧等の長期荷重を支持するとともに、シールド
機が推進する際のジャッキ推力(短期荷重)をも受け持
つものであるので、コンクリート内に埋設される外型枠
は安価なものとなり、覆工材としての高価なセグメント
を不要とするとともに、二次覆工としてのコンクリート
ライニングをも不要とし、工期の短縮や、工費の大幅削
減を実現することができるものである。Therefore, in this NSS method, concrete lining is applied to the primary lining to complete the tunnel, and the solidified concrete lining supports long-term loads such as soil water pressure received from the ground and also when the shield machine is propelled. Since it is also responsible for jack thrust (short-term load), the outer formwork embedded in the concrete becomes inexpensive, eliminating the need for expensive segments as lining material, and as concrete for secondary lining. No lining is required, and the construction period can be shortened and the construction cost can be greatly reduced.
そのため、前記N.S.S工法においては、コンクリートラ
イニングの強度が非常に重要な問題となっており、コン
クリートライニングの内部に鉄筋を配筋する等して、そ
の強度を向上させることが望ましい。しかし、従来のシ
ールド工事の場所打ちライニング工法においては、コン
クリートライニングの内部に鉄筋を配筋するような方法
は取られていなかった。Therefore, in the NSS method, the strength of the concrete lining is a very important problem, and it is desirable to reinforce the concrete lining to improve its strength. However, in the conventional cast-in-place lining method of shield construction, a method of arranging reinforcing bars inside the concrete lining has not been taken.
そこで、本出願人は前記N.S.S工法に、従来一般に行な
われている場所打ちコンクリート工法を適用し、第8図
ないし第14図に示すようなN.S.S工法における場所打ラ
イニング方法を考えた。Therefore, the present applicant has applied a conventional cast-in-place concrete construction method to the NSS construction method and considered a cast-in-place lining method in the NSS construction method as shown in FIGS. 8 to 14.
第12図において、符号Eはトンネルを築造する周辺の地
山であり、地山E内をシールド機1によって掘削してい
る。シールド機1の後方には、これによって掘削された
坑Hの壁面に沿って周方向に複数に分割された所定幅を
有する内型枠2と外型枠3とが環状に組み立てられると
ともに、掘進方向の一定間隔毎には内型枠2と外型枠3
との間には妻枠4が取り付けられている。そして、内型
枠2と外型枠4との間には、リング筋(主筋)5と配力
筋6とが組み込まれているとともに、後方の内・外型枠
間にはコンクリートCが打設されたものとなっている。In FIG. 12, reference numeral E is a natural ground around which a tunnel is built, and the ground E is excavated by the shield machine 1. Behind the shield machine 1, an inner formwork 2 and an outer formwork 3 each having a predetermined width divided into a plurality in the circumferential direction along the wall surface of the mine H excavated thereby are assembled in an annular shape, and Inner mold 2 and outer mold 3 at regular intervals in the direction
A wife frame 4 is attached between the and. A ring reinforcement (main reinforcement) 5 and a force distribution reinforcement 6 are incorporated between the inner mold 2 and the outer mold 4, and concrete C is struck between the rear inner and outer molds. It has been set up.
そして、内・外型枠間に鉄筋5,6を組み立てるには、ま
ず、第8図に示すように、リング筋5を両端部に所定長
さの重なり部分を持つように周方向に5a,5b,5c,5dに4
分割し、これを組み立てるようにしている。なお、各鉄
筋5a,5b,5c,5dの重なり部分を結束するために、重なり
部分が位置する内型枠2には、窓(図示せず)を設ける
ようにしておく。Then, in order to assemble the reinforcing bars 5 and 6 between the inner and outer molds, first, as shown in FIG. 8, the ring reinforcing bar 5 is circumferentially 5a, so as to have an overlapping portion of a predetermined length at both ends. 4 in 5b, 5c, 5d
I'm trying to divide it and assemble it. In order to bind the overlapping portions of the reinforcing bars 5a, 5b, 5c, 5d, a window (not shown) is provided in the inner formwork 2 in which the overlapping portions are located.
つぎに、内型枠2と外型枠3とは、第13図に示すよう
に、周方向に7分割し、これを底部の方から組み立てて
行くようにしている。まず、第10図に示すように、底部
の内型枠2A,2Aと外型枠3A,3Aとを周方向に2個連結し、
その内部にリング筋5aを配設してスペーサ7(第14図参
照)に固定する。リング筋5aをスペーサ7に組み付けた
後には、リング筋5b,5cを前記型枠内部に配置してお
く。つぎに、型枠2A,3A内にリング筋5b,5cを配置した後
には、第9図に示すように、2個連設した内型枠2A,3A
の両側に、さらに、スペーサ7により連結した内・外型
枠2A,3Aと2B,3Bとをそれぞれ組み立てる。内・外型枠2
A,3A,2B,3Bを組み立てた後には、底部の内・外型枠2A,3
A内に配置しておいた、リング筋5b,5cを所定の位置に引
き出すとともに、スペーサ7に組み付ける。そして、リ
ング筋5b,5cをスペーサ7に組み付けた後には、リング
筋5dを内・外型枠2B,3B内に配置しておく。最後に、内
・外型枠2B,3Bの間に頂部の内・外型枠2K,3Kを組み立て
た後、リング筋5dをスライドさせて、リング筋5b,5cに
結束する。Next, as shown in FIG. 13, the inner mold frame 2 and the outer mold frame 3 are divided into seven in the circumferential direction, and these are assembled from the bottom. First, as shown in FIG. 10, two inner molds 2A, 2A and outer molds 3A, 3A at the bottom are connected in the circumferential direction,
The ring streak 5a is arranged inside and fixed to the spacer 7 (see FIG. 14). After the ring muscle 5a is assembled to the spacer 7, the ring muscles 5b and 5c are arranged inside the mold. Next, after arranging the ring streaks 5b and 5c in the molds 2A and 3A, as shown in FIG. 9, two inner molds 2A and 3A are arranged in series.
Further, the inner and outer molds 2A, 3A and 2B, 3B connected by the spacer 7 are assembled on both sides of each. Inner / Outer Form 2
After assembling A, 3A, 2B, 3B, the bottom inner and outer molds 2A, 3
The ring muscles 5b and 5c arranged in A are pulled out to a predetermined position and assembled to the spacer 7. Then, after the ring reinforcements 5b, 5c are assembled to the spacer 7, the ring reinforcements 5d are arranged in the inner / outer molds 2B, 3B. Finally, after assembling the inner and outer molds 2K and 3K at the top between the inner and outer molds 2B and 3B, the ring muscle 5d is slid and bound to the ring muscles 5b and 5c.
つぎに、上記のようにして、環状に組み立てた内・外型
枠2,3をトンネル掘進方向に4リング分連設する。そし
て、最後(4リング目)の型枠は、第13図,第14図に示
すように、周方向に7分割(4A,4A,4A,4A,4B,4B,4K)さ
れた妻枠4が予め内側に固定された外型枠3を用いて、
環状に組み立てる。妻枠4は、その外周部分が止水上の
問題から外型枠3の端部から少し内側にずれた位置に固
定されており、その内周部には妻枠固定板4aが固定され
ている。妻枠固定板4aは、内型枠2と外型枠3とを連結
するスペーサ7の取り付け部分であるコーン状の突起部
2aに、前記スペーサ7の端部とともに、ボルト8によっ
て固定するようにしている。また、内型枠2、2は、ボ
ルト9によってトンネル掘進方向に連結されているとと
もに、外型枠3,3はシール部材10を介して、内側から止
め金具11によって連結されている。Next, as described above, the inner and outer formwork 2 and 3 assembled in an annular shape are continuously provided for four rings in the tunnel excavation direction. And the last (4th ring) formwork, as shown in FIG. 13 and FIG. 14, is a gable frame 4 divided into 7 parts (4A, 4A, 4A, 4A, 4B, 4B, 4K) in the circumferential direction. Using the outer mold 3 which is fixed in advance in advance,
Assemble in a ring. The end portion of the gable frame 4 is fixed at a position slightly displaced inward from the end of the outer formwork 3 due to the problem of water stoppage, and the gable frame fixing plate 4a is fixed to the inner peripheral portion thereof. . The gable frame fixing plate 4a is a cone-shaped protrusion that is a mounting portion of a spacer 7 that connects the inner mold 2 and the outer mold 3.
The end portion of the spacer 7 is fixed to the 2a by a bolt 8. The inner molds 2 and 2 are connected to each other in the tunnel excavation direction by bolts 9, and the outer molds 3 and 3 are connected from inside by a stopper 11 via a seal member 10.
そして、内・外型枠2,3が4リング(1ストローク)分
連設された後には、第11図に示すように、さらに1リン
グ分の内・外型枠2,3を環状に組み立てた後、シールド
機1側から妻枠4に形成された鉄筋の貫通孔12,12,…
(第13図参照)から、配力筋6,6,…を送り込んで配筋す
る。前記妻枠4に形成された貫通孔12は内型枠2の連結
用のボルト穴9aと同じピッチで設けられており、型枠内
に配筋された配力筋6,6,…は、内型枠2に形成された窓
(図示せず)から作業員が手を入れて先に配筋された配
力筋6,6,…の端部やリング筋5,5,…に結束するようにし
ている。Then, after the inner and outer molds 2 and 3 are continuously connected for 4 rings (1 stroke), as shown in FIG. 11, the inner and outer molds 2 and 3 for 1 ring are further assembled in an annular shape. Then, from the shield machine 1 side, through holes 12, 12, ...
(Refer to Fig. 13), the force distribution muscles 6, 6, ... are fed and arranged. The through holes 12 formed in the end frame 4 are provided at the same pitch as the bolt holes 9a for connecting the inner formwork 2, and the force distribution bars 6, 6, ... Arranged in the formwork, An operator puts his hands through a window (not shown) formed in the inner formwork 2 and binds to the ends of the force distribution muscles 6,6, ... and the ring muscles 5,5 ,. I am trying.
そして、上述したように、内・外型枠2,3の内部にリン
グ筋5と配力筋6とを配筋した後には、第12図に示すよ
うに、内型枠2の内側から打設管13によってコンクリー
トCを打設することにより、内部に鉄筋が配筋されたコ
ンクリートライニングを施すようにしている。Then, as described above, after the ring muscles 5 and the force distribution muscles 6 have been arranged inside the inner and outer molds 2 and 3, as shown in FIG. By placing concrete C by the installation pipe 13, a concrete lining having reinforcing bars arranged therein is applied.
「発明が解決しようとする問題点」 しかし、前記ノン・セグメント・シールド工法にける場
所打ちライニング方法おいては、4分割したリング筋5,
5,…と配力筋6,6,…とを型枠内に1本ずつ配筋し、これ
を結束しなければならず、その作業には多大な時間と労
力を必要とし、工期の遅延や工費の増大を招来するこ
と、また、内型枠の所定の場所にはそのための鉄筋挿入
口や作業用の窓を形成しなければならず、内型枠の製作
費のコストアップの原因となること等の問題点が生じて
きた。"Problems to be solved by the invention" However, in the cast-in-place lining method in the non-segment shield construction method, the ring streak divided into 4 is used.
5, ... and distribution muscles 6,6, ... must be arranged one by one in the formwork and tied together, which requires a great deal of time and labor, and delays the construction period. And an increase in construction costs, and a rebar insertion port and a working window for that purpose must be formed at a predetermined place on the inner formwork, which causes an increase in the cost of manufacturing the inner formwork. There are problems such as becoming.
本発明は、前記問題点に鑑みてなされたもので、型枠内
への鉄筋の配筋を容易かつ迅速に行うことができるとと
もに、内型枠に鉄筋の結束等に必要な作業用の窓を不要
とすることにより、工期の短縮や工費の低減を図ること
のできるノン・セグメント・シールド工法におけるメッ
シュ筋を用いた場所打ライニング方法を提供することを
目的としている。The present invention has been made in view of the above-mentioned problems, and it is possible to easily and quickly arrange the reinforcing bars in the formwork, and the work window necessary for binding the reinforcing bars to the inner formwork. It is an object of the present invention to provide a cast-in-place lining method using a mesh streak in the non-segment shield construction method, which can shorten the construction period and the construction cost by eliminating the need for.
「問題点を解決するための手段」 本発明は、前記問題点を解決するために、内型枠と外型
枠とを一体化する際には、内型枠と外型枠との間にメッ
シュ筋を配設し、次いで、前記外型枠と内型枠とを坑の
壁面に沿って周方向、並びにトンネル掘進方向に連設し
て筒状に組み立てて行く際には、その接続部分の内型枠
と外型枠との間に、互いに隣接するメッシュ筋の双方に
重なってそれらメッシュ筋どうしを接続するための重合
接続用メッシュ筋を配設することを特徴としている。[Means for Solving Problems] In order to solve the above-mentioned problems, the present invention provides a method for integrating an inner mold and an outer mold with a space between the inner mold and the outer mold. When arranging mesh streaks, and then assembling the outer formwork and the inner formwork along the wall surface of the mine in the circumferential direction and in the tunnel excavation direction to assemble them in a tubular shape, the connecting portion thereof Between the inner form frame and the outer form frame, a mesh reinforcement for overlapping connection for arranging both adjacent mesh reinforcements to connect the mesh reinforcements is arranged.
「実施例」 以下、本発明を第1図ないし第7図を用いて説明する。
これらの図は本発明のノン・セグメント・シールド工法
におけるメッシュ筋を用いた場所打ライニング方法の一
実施例を示すものである。これらの図において、前記従
来の技術に示した構成要素と同一の要素については同一
符号を付し、その説明を省略する。[Examples] Hereinafter, the present invention will be described with reference to FIGS. 1 to 7.
These figures show an embodiment of the cast-in-place lining method using mesh streaks in the non-segment shield construction method of the present invention. In these figures, the same components as those shown in the above-mentioned prior art are designated by the same reference numerals, and the description thereof will be omitted.
まず、第3図を用いて本発明の工法の概略構成を説明す
る。地盤E中には、シールド機1によって掘削されるこ
とにより坑Hが形成されており、掘削された坑Hの壁面
に沿ってはシールド機1の後部においてエレクタ1aによ
って内型枠2と外型枠3とが筒状に組み立てられてい
る。組み立てられた内型枠2と外型枠3との間にはメッ
シュ筋20が配設されているとともに、妻枠4,4によって
区画された内型枠2と外型枠3との間には、打設管13に
よってコンクリートCが打設されるようになっている。First, the schematic structure of the construction method of the present invention will be described with reference to FIG. A mine H is formed in the ground E by being excavated by the shield machine 1, and along the wall surface of the excavated mine H, the inner mold 2 and the outer mold are formed by the erector 1a at the rear of the shield machine 1. The frame 3 and the frame 3 are assembled in a tubular shape. A mesh streak 20 is arranged between the assembled inner and outer molds 2 and 3, and between the inner and outer molds 2 and 3 divided by the end frames 4, 4. Concrete C is placed by the placing pipe 13.
つぎに、本発明のノン・セグメント・シールド工法にお
けるメッシュ筋を用いた場所打ライニング方法について
説明する。Next, a cast-in-place lining method using mesh streaks in the non-segment shield construction method of the present invention will be described.
(i)まず、第1図(a),(b)に示すように、符号
2はスキンプレート2sが円弧状に形成された内型枠であ
り、スキンプレート2sの所定の位置にはボルト8の貫通
孔(図示略)が形成されている。そして、内型枠2の外
周面には前記貫通孔と連通するボルト穴が形成されたコ
ーン状の突起部材2aが固定されている。また、符号3は
前記スキンプレート2sと同じくスキンプレート3sが円弧
状に形成された外型枠であり、外型枠3の内周面には先
端部に雌ネジが形成された連結部材7,7,…が固定されて
いる。さらに、符号20はメッシュ筋であり、予め他の場
所において、前記内型枠2や外型枠3のスキンプレート
2S,3Sの形状に合わせてリング筋(主筋)20aと配力筋20
bとを所定の本数づつ格子状に組み付けることによって
製作したものであり、リング筋20aと配力筋20bとは、十
分な強度を有した構造用の鉄筋を使用するものである。(I) First, as shown in FIGS. 1 (a) and 1 (b), reference numeral 2 is an inner frame in which the skin plate 2s is formed in an arc shape, and a bolt 8 is provided at a predetermined position of the skin plate 2s. Through holes (not shown) are formed. Further, a cone-shaped protruding member 2a having a bolt hole communicating with the through hole is fixed to the outer peripheral surface of the inner mold form 2. Further, reference numeral 3 is an outer formwork in which the skin plate 3s is formed in an arc shape similarly to the skin plate 2s, and the inner peripheral surface of the outer formwork 3 has a connecting member 7 having a female screw formed at the tip thereof. 7, ... is fixed. Further, reference numeral 20 is a mesh streak, and the skin plate of the inner mold form 2 or the outer mold form 3 has been previously formed in another place.
Ring muscle (main muscle) 20a and distribution muscle 20 according to the shape of 2S, 3S
It is manufactured by assembling a predetermined number of b and grids, and the ring reinforcement 20a and the distribution muscle 20b use structural rebars having sufficient strength.
そして、内型枠2と外型枠3とを連結して一体化する際
には、まず、前記メッシュ筋20を外型枠3のスキンプレ
ート3sと一定間隔をおいて平行となるように配置した
後、連結部材7に固定する。ついで、メッシュ筋20が取
り付けられた外型枠3の連結部材7の先端部を、内型枠
2の突起部材2aの先端部に当接させた後、内型枠2の内
周面側からボルト8を挿通し、ついで、連結部材7の先
端部に螺着させることにより連結し、それらの間に空間
Sを形成する。このようにして、内型枠2と外型枠3と
は連設されるとともに、その内部にメッシュ筋20が配設
される。なお、メッシュ筋20は、内型枠2及び外型枠3
の周方向の両端部A(連結部材7より外側)に、配力筋
20bが3本(2スパン)以上配設されるようにする。When the inner mold 2 and the outer mold 3 are connected and integrated, first, the mesh streak 20 is arranged so as to be parallel to the skin plate 3s of the outer mold 3 at a constant interval. After that, it is fixed to the connecting member 7. Then, after the tip of the connecting member 7 of the outer mold 3 to which the mesh streak 20 is attached is brought into contact with the tip of the protruding member 2a of the inner mold 2, from the inner peripheral surface side of the inner mold 2. The bolt 8 is inserted, and then the tip end of the connecting member 7 is screwed to be connected to form a space S therebetween. In this way, the inner mold form 2 and the outer mold form 3 are connected to each other, and the mesh streaks 20 are arranged therein. In addition, the mesh streak 20 includes the inner mold 2 and the outer mold 3.
At both ends A (outside of the connecting member 7) in the circumferential direction of
Make sure that at least 3 pieces (2 spans) of 20b are arranged.
(ii)つぎに、一体となった内型枠2と外型枠3をエレ
クタ1aを用いて、シールド機1の後部において環状に組
み立てる(以下、環状に組み立てた一個分の型枠を「環
状体」と略称する)。(Ii) Next, the inner formwork 2 and the outer formwork 3 which are integrated are assembled in an annular shape at the rear part of the shield machine 1 by using the erector 1a (hereinafter, one annularly assembled formwork is referred to as an “annular shape”). Abbreviated as "body").
環状に組み立てるには、まず、第5図に示すように、メ
ッシュ筋20が配設された内・外型枠2A,3Aを底部の方か
ら組み立てる。その際、重合接続用メッシュ筋21Aを、
接続部分の内型枠2Aと外型枠3Aとの間に配設して、この
重合接続用メッシュ筋21Aを互いに隣接するメッシュ筋2
0,20の双方に重ね合わせる。この場合、重合接続用メッ
シュ筋21Aは、主にリング筋(主筋)20aを接続するため
のものであり、第2図(a)に示すように、リング筋21
aと配力筋21bとを格子状に組み付けたものである。つぎ
に、第5図に示すように、内・外型枠2A,3Aの左上(紙
面に対して)に重合接続用メッシュ筋21Bを配設した
後、一体化した他の内・外型枠2A,3Aを前記内・外型枠2
A,3Aの側部にスライドさせながら組み立てて連結する。
以下同様にして、底部の内・外型枠2A,3Aの右上に重合
接続用メッシュ筋21Cを配置した後、一体化した他の内
・外型枠2A,3Aを前記内・外型枠2A,3Aに連結し、つぎ
に、前記左側に配設した内・外型枠2A,3Aの上部に重合
接続用メッシュ筋21Dを配設した後、一体化した内・外
型枠2B,3Bを前記内・外型枠2A,3Aの上部に連設し、さら
に、右側に配設した内・外型枠2A,3Aの上部に重合接続
用メッシュ筋21Eを配設した後、前記内・外型枠2A,3Aの
上部に一体化した内・外型枠2B,3Bを連設し、最後に、
前記左上の内・外型枠2B,3Bの上端部に重合接続用メッ
シュ筋21Fを配設するとともに、右上の内・外型枠2B,3B
の上部に重合接続用メッシュ筋21Gを配設した後、それ
らの間に頂部の内・外型枠3K,4Kをスライドさせながら
組み立てて連設し、環状体を形成する。In order to assemble it in a ring shape, first, as shown in FIG. 5, the inner and outer molds 2A, 3A in which the mesh muscles 20 are arranged are assembled from the bottom. At that time, the mesh muscle 21A for polymerization connection,
It is arranged between the inner formwork 2A and the outer formwork 3A of the connecting portion, and the mesh muscles 21A for superposition connection are adjacent to each other.
Overlay on both 0 and 20. In this case, the overlapping connecting mesh muscle 21A is mainly for connecting the ring muscle (main muscle) 20a, and as shown in FIG.
The a and the muscles 21b are assembled in a grid pattern. Next, as shown in FIG. 5, after the mesh line 21B for superposition connection is arranged at the upper left of the inner / outer molds 2A, 3A (to the paper surface), another inner / outer mold which is integrated 2A and 3A are the inner and outer molds 2
Assemble and connect while sliding to the side of A, 3A.
In the same manner, after placing the mesh connection mesh 21C on the upper right of the inner / outer molds 2A, 3A at the bottom, the other inner / outer molds 2A, 3A integrated with the inner / outer mold 2A , 3A, and then, the mesh wire 21D for polymerization connection is arranged on the upper part of the inner / outer molds 2A, 3A arranged on the left side, and then the integrated inner / outer molds 2B, 3B are formed. After the inner and outer molds 2A and 3A are continuously connected to each other, and further, the mesh connection 21S for polymerization connection is arranged on the upper and lower inner and outer molds 2A and 3A, and then the inner and outer molds Inner and outer molds 2B and 3B that are integrated on top of the molds 2A and 3A are installed in series, and finally,
A mesh line 21F for overlapping connection is arranged at the upper end of the upper left inner / outer molds 2B, 3B, and the upper right inner / outer molds 2B, 3B
After the superposition connecting mesh muscle 21G is arranged on the upper part of the above, the inner and outer molds 3K and 4K at the top are slid between them to assemble and connect them to form an annular body.
(iii)つぎに、環状体の内型枠2にジャッキ反力を取
ってシールド機1を一定距離だけ推進させた後、第6図
に示すように、先に組み立てた環状体の前側面(紙面に
対して左側)に連設させて、2つ目の環状体を組み立て
る。(Iii) Next, after jack reaction force is applied to the inner mold 2 of the annular body to propel the shield machine 1 for a certain distance, as shown in FIG. 6, the front side surface of the previously assembled annular body ( Assemble the second annular body by connecting it to the left side of the paper).
その際、第4図に示すように、これから接続する側の内
型枠2と外型枠3との間に重合接続用メッシュ筋22を配
置しておき、そこにエレクタ1aによって一体化した内・
外型枠2,3をスライドさせながら組み立て、連設する。
この場合に使用する重合接続用メッシュ筋22は、主に配
力筋20bを接続するためのものであり、第2図(b)に
示すように、リング筋22aと配力筋22bとを格子状に組み
付けたものである。そして、この重合接続用メッシュ筋
22には、型枠の連結部材7,7,…が位置する部分に、切欠
部22s,22s,…が形成されたものとなっている。以下、同
様にして、重合接続用メッシュ筋22を配設しながら前記
工程(ii)を繰り返すことにより、2つ目の環状体を組
み立てていく。At that time, as shown in FIG. 4, a mesh line 22 for superposition connection is arranged between the inner mold form 2 and the outer mold form 3 on the side to be connected, and the inner structure is integrated by the erector 1a.・
Assemble the outer forms 2 and 3 while sliding them, and install them in series.
The overlapping connecting mesh muscles 22 used in this case are mainly for connecting the distribution muscles 20b, and as shown in FIG. 2 (b), the ring muscles 22a and the distribution muscles 22b are latticed. It is assembled into a shape. And this mesh wire for superposition connection
The notch 22s, 22s, ... Is formed in the part of the frame where the connecting members 7, 7 ,. Thereafter, in the same manner, the second annular body is assembled by repeating the step (ii) while arranging the superposition connecting mesh muscles 22.
(iv)さらに、同様にして前記工程(iii)を繰り返す
ことにより、第7図に示すように、2つ目の環状体の前
側面に3つ目の環状体を組み立てる。そして、この3つ
目の環状体を構成する内型枠2と外型枠3の前側面に
は、妻枠4が固定されたものとなっており、これによっ
て、内型枠2と外型枠3との間にコンクリートCを打設
可能とする円筒状の密閉空間部Sが形成される。なお、
本実施例においては、3つ目の環状体に、妻枠4が固定
された内・外型枠2,3を用いたが、これに限定されるこ
となく、状況に応じて任意の環状体に用いることがで
き、密閉空間部Sの長さを自由に調節することができ
る。(Iv) Further, by repeating the step (iii) in the same manner, as shown in FIG. 7, the third annular body is assembled on the front side surface of the second annular body. The end frame 4 is fixed to the front side surfaces of the inner mold form 2 and the outer mold form 3 that form the third annular body, whereby the inner mold form 2 and the outer mold form are formed. A cylindrical closed space S in which concrete C can be placed is formed between the frame 3 and the frame 3. In addition,
In this embodiment, the inner and outer molds 2 and 3 to which the end frame 4 is fixed are used as the third annular body, but the present invention is not limited to this, and any annular body may be used depending on the situation. The length of the closed space S can be freely adjusted.
ここでコンクリート打設区間が完成する。このコンクリ
ート打設区間では、地山Eから受ける土水圧に対して
は、荷重が外型枠3からスペーサ7,7,…及び突起部材2
a,2a,…を介して内型枠2に伝達され、この内型枠2に
よって受け持つようになっている。The concrete pouring section is completed here. In this concrete placing section, the load from the outer formwork 3 to the spacers 7, 7, ...
It is transmitted to the inner formwork 2 via a, 2a, ...
(v)そして、第3図に示すように、前記の(iii)の
工程を繰り返してコンクリート打設区間の前方(トンネ
ル掘進方向)に、さらに、一個の環状体を設置した後、
コンクリート打設区間の内型枠2と外型枠3との間に打
設管13により、コンクリートCを打設してコンクリート
ライニングRを施す。なお、型枠内へのコンクリートの
充填は、内型枠2の注入孔(図示略)から行う。(V) Then, as shown in FIG. 3, after the above step (iii) is repeated and one annular body is further installed in front of the concrete placing section (tuning direction),
Between the inner formwork 2 and the outer formwork 3 in the concrete placing section, concrete C is placed by a placing pipe 13 and concrete lining R is applied. It should be noted that the filling of the concrete into the formwork is performed from an injection hole (not shown) of the inner formwork 2.
したがって、外型枠3は永久的に覆工材としてコンクリ
ートに埋設されるとともに妻枠4も埋殺しとなる。Therefore, the outer frame 3 is permanently buried in the concrete as a lining material, and the gable frame 4 is also buried.
(vi)さらに、前記(ii)〜(v)の工程を順次繰り返
すことにより、掘削した穴に覆工を行う。このようにし
て、順次覆工が行なわれるに従い、コンクリート打設区
間の後方(紙面に対して右側)にはコンクリートが硬化
していない状態の未固結コンクリート区間が、さらに、
その後方にはコンクリートが完全に硬化した状態の固結
コンクリート区間(図示略)が逐次完成していく。固結
コンクリート区間には、外型枠3と掘削した坑Hの壁面
との間に、裏込めグラウトを注入する。(Vi) Further, the excavated hole is lined by sequentially repeating the steps (ii) to (v). In this way, as the lining is carried out sequentially, the unconsolidated concrete section in the state where the concrete has not hardened further behind the concrete placing section (right side with respect to the paper surface),
After that, a solidified concrete section (not shown) in which the concrete is completely hardened is successively completed. Backfill grout is injected into the solidified concrete section between the outer form 3 and the wall of the excavated mine H.
この固結コンクリート区間においては、コンクリートラ
イニングRの強度発現により、コンクリートライニング
Rが、地山Eから受ける長期的な諸荷重を受け持つとと
もに、内型枠2との付着面に働く摩擦力により、シール
ド機1の推進時に作用する短期的なジャッキ推力を受け
持つことになる。本実施例においては、ジャッキ推力を
コンクリートCとスキンプレート2Sの付着面の摩擦力の
みで受けるだけではなく、スキンプレート2Sの外周面に
固定されたコーン2aによっても支持することができるの
で、固結コンクリート区間長を短くすることができる。In this solidified concrete section, due to the strength development of the concrete lining R, the concrete lining R bears long-term loads received from the ground E, and the friction force acting on the adhesion surface with the inner formwork 2 shields it. It will be responsible for the short-term jack thrust that acts when the aircraft 1 is propelled. In the present embodiment, the jack thrust can be received not only by the frictional force between the adhering surface of the concrete C and the skin plate 2S but also by the cone 2a fixed to the outer peripheral surface of the skin plate 2S. The length of the consolidated concrete section can be shortened.
なお、前記のようにして完成した固結コンクリート区間
が所定の長さに達したことを確認した後には、固結コン
クリート区間より後方の型枠解体区間(図示略)の内型
枠2を最後部から逐次解体していく。In addition, after confirming that the solidified concrete section completed as described above has reached a predetermined length, the inner formwork 2 of the formwork dismantling section (not shown) behind the solidified concrete section is finally removed. It will be dismantled from the department.
したがって、本発明の工法においては、一次覆工におい
て、鉄筋が配筋されたコンクリートライニングRを施す
こことによりトンネルを完成させ、そのコンクリートラ
イニングRによって土水圧等の長期荷重やジャッキ推力
等の短期荷重を受け持つものであるので、コンクリート
内に埋設される外型枠3は安価なものとなり、覆工材と
しての高価なセグメントを不要とするとともに、二次覆
工としてのコンクリートライニングをも不要とする。そ
して、前記コンクリートライニングRは鉄筋コンクリー
ト製であるため、十分に大きな強度を発現することがで
きる。さらに、本発明の工法によれば、内型枠2と外型
枠3との間にメッシュ筋20と重合接続用メッシュ筋21,2
2を配設しながら型枠を組み立てて行くようにしたもの
であり、しかも、重合接続用メッシュ筋21,22を互いに
隣接するメッシュ筋20,20の双方に重ねるのみで、その
重合接続用メッシュ筋21,22及びコンクリートを介して
双方のメッシュ筋20,20どうしが自ずと接続されるの
で、内型枠2と外型枠3との間に鉄筋を1本1本配筋し
たり、それらを結束したりする作業を省略することがで
き、多くの時間と労力とを節約することができるととも
に、内型枠2にそのために必要な鉄筋挿入口や結束作業
用の窓を形成する必要もなく、内型枠2の製作コストを
安価にすることができ、トンネル建設に要する施工期間
の短縮並びに工事費の低減等を実現することができる。Therefore, in the construction method of the present invention, in the primary lining, the concrete lining R in which the reinforcing bars are arranged is applied to complete the tunnel, and the concrete lining R completes the long-term load such as soil water pressure and the short-term load such as jack thrust. Since it bears the load, the outer formwork 3 embedded in the concrete becomes cheaper, eliminating the need for expensive segments as lining material and the need for concrete lining as secondary lining. To do. Since the concrete lining R is made of reinforced concrete, it can exhibit sufficiently large strength. Further, according to the construction method of the present invention, the mesh reinforcement 20 and the mesh reinforcements 21, 2 for superposition connection are provided between the inner mold 2 and the outer mold 3.
The formwork is assembled while arranging the two, and moreover, the mesh for superposition connection is simply overlapped with both the mesh rebars 20 and 20 adjacent to each other. Both mesh reinforcements 20 and 20 are naturally connected to each other via reinforcements 21 and 22, so that one rebar is placed between the inner formwork 2 and the outer formwork 3, Bundling work can be omitted, a lot of time and labor can be saved, and there is no need to form a reinforcing bar insertion port or a binding work window necessary for the inner formwork 2 therefor. The manufacturing cost of the inner formwork 2 can be reduced, and the construction period required for tunnel construction and the construction cost can be reduced.
なお、前記実施例においては、メッシュ筋20に鉄筋を使
用したが、これに限定されることなく、所定の強度を有
したメッシュ状のものであればなんでもよく、特に、N.
F.M(ニュー.ファイバー.メッシュ)を用いることに
より、錆びないメッシュ筋20とすることができる。In the above embodiment, the reinforcing bar is used as the mesh reinforcing bar 20, but the reinforcing bar is not limited to this and may be any mesh-shaped one having a predetermined strength, in particular, N.
By using FM (new fiber mesh), it is possible to obtain a mesh streak 20 that does not rust.
「発明の効果」 以上説明したように本発明は、内型枠と外型枠とを一体
化する際には、内型枠と外型枠との間にメッシュ筋を配
設し、次いで、前記外型枠と内型枠とを周方向、並びに
トンネル掘進方向に連設して筒状に組み立てて行く際に
は、その接続部分の内型枠と外型枠との間に重合接続用
メッシュ筋を互いに隣接するメッシュ筋の双方に重なる
ように配設し、その重合接続用メッシュ筋を介して互い
に隣接する双方のメッシュ筋どうしを接続するようにし
たものであるので、内型枠と外型枠との間に鉄筋を容易
にかつ迅速に配筋することができるとともに、内型枠に
鉄筋挿入口や鉄筋の結束等に必要な窓を設ける必要がな
くなり、内型枠の製作費のコストダウンを図り、施工期
間の短縮や、工事費の低減を実現することができる。"Effects of the Invention" As described above, the present invention, when integrating the inner mold and the outer mold, arranges a mesh streak between the inner mold and the outer mold, and then, When the outer mold and the inner mold are continuously arranged in the circumferential direction and in the tunnel excavation direction and assembled in a cylindrical shape, the inner mold and the outer mold at the connecting portion are used for polymerization connection. Since the mesh muscles are arranged so as to overlap both of the adjacent mesh muscles, and the mesh muscles for mutual connection are connected to each other through the mesh muscles for overlapping connection, the inner formwork and Reinforcing bars can be easily and quickly arranged between the outer formwork and the inner formwork does not need to be provided with a rebar insertion port or a window necessary for binding the rebars. It is possible to reduce the cost, reduce the construction period, and reduce the construction cost.
第1図ないし第7図は、本発明の一実施例を示すもの
で、第1図(a)は本発明の要部を示すものであり、メ
ッシュ筋が内型枠と外型枠との間に配設された状態を示
す正面図、第1図(b)は第1図(a)の側面図、第2
図(a)は型枠の周方向に接続部分に使用される重合接
続用メッシュ筋の平面図、第2図(b)は型枠のトンネ
ル掘進方向の接続部分に使用される重合接続用メッシュ
筋の平面図、第3図は本発明の工法の概要を説明するた
めのトンネルの側断面図、第4図はトンネル掘進方向に
型枠を連設しているところを説明するためのトンネルの
側断面図、第5図は型枠を環状に組み立てるところを説
明するためのものであり、環状体の正面図、第6図は2
つ目の環状体を組み立てた状態のトンネルの側断面図、
第7図は3つ目の環状体を組み立てた状態を示す側断面
図、第8図ないし第14図は従来の技術を示すものであ
り、第8図は型枠内に配設するために4分割されたリン
グ筋の正面図、第9図,第10図はリング筋を型枠内に配
筋する方法を説明するための型枠の正面図、第11図は配
力筋を配筋するところを説明するためのトンネルの側断
面図、第12図を組み立てた型枠内にコンクリート打設す
るところを示すトンネルの側断面図、第13図は妻枠の付
いた型枠を環状に組み立てた状態を示す環状の正面図、
第14図はトンネル掘進方向の接続部分の拡大断面図であ
る。 E……地山、C……コンクリート、R……コンクリート
ライニング、H……坑、1……シールド機、2,(2A,2B,
2K)……内型枠、3,(3A,3B,3K)……外型枠、7……連
結部材、20(20A,20B,20K)……メッシュ筋、21(21A,2
1B,21C,21D,21E,21F,21G)……重合接続用メッシュ筋
(周方向)、22……重合接続用メッシュ筋(トンネル掘
進方向)FIGS. 1 to 7 show an embodiment of the present invention, and FIG. 1 (a) shows an essential part of the present invention. A front view showing a state of being arranged between them, FIG. 1 (b) is a side view of FIG. 1 (a), and FIG.
Figure (a) is a plan view of mesh connecting mesh reinforcements used in the connecting portion in the circumferential direction of the form, and Figure 2 (b) is a connection connecting mesh used in the connecting portion in the tunneling direction of the form. Fig. 3 is a plan view of the streak, Fig. 3 is a side sectional view of the tunnel for explaining the outline of the construction method of the present invention, and Fig. 4 is a tunnel for explaining that the formwork is continuously connected in the tunnel excavation direction. FIG. 5 is a side sectional view for explaining the process of assembling the mold in a ring shape, and FIG.
A side sectional view of the tunnel in a state where the second annular body is assembled,
FIG. 7 is a side sectional view showing a state in which the third annular body is assembled, and FIGS. 8 to 14 show a conventional technique. FIG. 8 shows the arrangement in the form. Front view of four-divided ring reinforcement, Figures 9 and 10 are front views of the formwork for explaining the method of arranging the ring reinforcement in the formwork, and Fig. 11 is the reinforcement of reinforcement muscles. Fig. 12 is a side sectional view of a tunnel for explaining what to do, a side sectional view of a tunnel showing placing concrete in the assembled form of Fig. 12, and Fig. 13 is an annular form of a form with a gable frame. An annular front view showing the assembled state,
FIG. 14 is an enlarged sectional view of a connecting portion in the tunnel excavation direction. E ... Ground, C ... Concrete, R ... Concrete lining, H ... Pit, 1 ... Shielding machine, 2, (2A, 2B,
2K) …… Inner mold, 3, (3A, 3B, 3K) …… Outer mold, 7 …… Coupling member, 20 (20A, 20B, 20K) …… Mesh reinforcement, 21 (21A, 2)
1B, 21C, 21D, 21E, 21F, 21G) …… Overlap connection mesh reinforcement (circumferential direction), 22 …… Overlap connection mesh reinforcement (tunnel excavation direction)
───────────────────────────────────────────────────── フロントページの続き (72)発明者 西村 晋一 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (72)発明者 東 洋二 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (56)参考文献 特開 昭60−141997(JP,A) 特開 昭60−123700(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Shinichi Nishimura, Shinichi Nishimura, Chuo-ku, Tokyo, 2-161-1, Kyobashi, Ltd. (72) Inventor, Toyoji Tokyo, Chuo-ku, Tokyo, 2-16-1, Kyobashi, Shimizu Construction company (56) Reference JP-A-60-141997 (JP, A) JP-A-60-123700 (JP, A)
Claims (1)
の壁面に沿って、複数に分割された所定幅を有する内型
枠と外型枠を連結部材で一体化しつつ筒状に組み立てた
後、この内型枠と外型枠との間にコンクリートを打設し
てコンクリートライニングを施し、次いで、このコンク
リートライニングの固化した部分が所定の長さに達した
際、前記内型枠を外型枠から分離して解体するととも
に、新たに掘削した壁面に組み立てる内型枠として再使
用しながら地中にトンネルを構築するノン・セグメント
・シールド工法におけるメッシュ筋を用いた場所打ライ
ニング方法であって、前記内型枠と外型枠とを一体化す
る際に、内型枠と外型枠との間にメッシュ筋を配設し、
次いで、前記外型枠と内型枠とを前記坑の壁面に沿って
周方向、並びにトンネル掘進方向に連設して筒状に組み
立てて行く際には、その接続部分の内型枠と外型枠との
間に、互いに隣接するメッシュ筋の双方に重なってそれ
らメッシュ筋どうしを接続するための重合接続用メッシ
ュ筋を配設することを特徴とするノン・セグメント・シ
ールド工法におけるメッシュ筋を用いた場所打ライニン
グ方法。1. An inner formwork and an outer formwork, each having a predetermined width divided into a plurality of parts, are assembled along a wall surface of a pit formed at the rear part of a shield machine to be excavated into a tubular shape while being integrated by a connecting member. After that, concrete is placed between the inner formwork and the outer formwork to provide concrete lining, and then, when the solidified portion of the concrete lining reaches a predetermined length, the inner formwork is removed. It is a cast-in-place lining method using mesh reinforcement in the non-segment shield construction method that constructs a tunnel in the ground while separating it from the formwork and dismantling it and reusing it as an inner formwork to be assembled on the newly excavated wall. Then, when integrating the inner mold and the outer mold, a mesh streak is arranged between the inner mold and the outer mold,
Next, when the outer formwork and the inner formwork are continuously assembled along the wall surface of the mine in the circumferential direction and in the tunnel excavation direction to assemble in a tubular shape, the inner formwork and the outer form of the connecting portion are formed. Between the formwork and the mesh bar adjacent to each other, the mesh bar for non-segment shield construction method characterized by arranging the mesh bar for overlapping connection for connecting the mesh bars Cast-in-place lining method used.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62011698A JPH07111117B2 (en) | 1987-01-21 | 1987-01-21 | Cast-in-place lining method using mesh line in non-segment shield method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62011698A JPH07111117B2 (en) | 1987-01-21 | 1987-01-21 | Cast-in-place lining method using mesh line in non-segment shield method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63181892A JPS63181892A (en) | 1988-07-27 |
JPH07111117B2 true JPH07111117B2 (en) | 1995-11-29 |
Family
ID=11785257
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP62011698A Expired - Fee Related JPH07111117B2 (en) | 1987-01-21 | 1987-01-21 | Cast-in-place lining method using mesh line in non-segment shield method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH07111117B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009144425A (en) * | 2007-12-14 | 2009-07-02 | Tekken Constr Co Ltd | Shield method by direct placing concrete lining |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60123700A (en) * | 1983-09-26 | 1985-07-02 | 株式会社熊谷組 | Assembling of iron skeletal in covering concrete of site casting lining shield construction method |
JPS60141997A (en) * | 1983-12-28 | 1985-07-27 | 川崎重工業株式会社 | Assembling of iron wire cage for reinforcing tunnel wall lining material |
-
1987
- 1987-01-21 JP JP62011698A patent/JPH07111117B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPS63181892A (en) | 1988-07-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2788953B2 (en) | Structure of tunnel structure | |
JP2593284B2 (en) | Tunnel lining structure and construction method | |
JPH07111117B2 (en) | Cast-in-place lining method using mesh line in non-segment shield method | |
JPH03202599A (en) | Reinforced structure of twin tunnels | |
JP3167937B2 (en) | Construction method of shield lining segment and shield tunnel | |
KR101102435B1 (en) | Making of sheathing panel for earth retaining and this and construction technique | |
JPH11200793A (en) | Shield tunnel and lining method thereof | |
JP4760548B2 (en) | Side-by-side tunnel structure and its construction method | |
JPH08199989A (en) | Construction of large section tunnel | |
US3449916A (en) | Tunnel liner and method of making same | |
JPH05263421A (en) | Column type earth retaining wall | |
JP3584416B2 (en) | Tunnel and its construction method | |
JPH0536599B2 (en) | ||
JP3567399B2 (en) | Large section tunnel and its construction method | |
JP2725972B2 (en) | Underground structure construction method and segment piece used therefor | |
JPH0235198A (en) | Constructing method for reinforced concrete covering work in nonsegment shield method | |
JPH0562199B2 (en) | ||
JPH08284597A (en) | Lining constructing method of shield tunnel | |
JPH0772476B2 (en) | How to build a tunnel lining | |
JPH0637836B2 (en) | Tunnel lining method | |
JPS62220697A (en) | Method and structure for connecting inner mold frame and outer mold frame in non-segment shield construction method | |
JPH0560036B2 (en) | ||
JP3067552B2 (en) | Steel cage | |
JPH05140940A (en) | Sheathing method in large depth excavation | |
JPH03250195A (en) | Large sectional tunnel and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |